Date: 26/02/2013 Observation of Status of Escalator and Lift Works: 12 nos escalator not yet commence installation at sector

r 2 4 nos lift not yet commence work at sector 2 Item Location Observation Note Glass Lifts S2-PL4 & S2-PL5 Assembly of lifts yet to commence awaiting erection of steel structure. Civil Works Construction of Level 3b floor which is above the lift locations is yet to complete i.e. installation of lifts is not possible. Escalator S2-ESC6 Escalator assembled and ready for installation. The possibility of the intermediate beam obstructing the erection of the escalator is yet to be confirmed. Service Lift S2-SL-5 Assembly of lifts yet to commence. Civil Works Construction of the lift core is yet to commence.

1.

S2 L3 GL: 23/G2

2.

S2 L3 GL: 21-22/F Escalator S2-ESC1 Escalator length is about 800mm longer than the length between the landings. JV yet to resolve the discrepancy.

3.

S2 L3 GL: 19a/F-G1

Item

Location

Observation Note Escalator S2-ESC8 Escalator assembled and ready for installation. Civil Work- Insufficient width at upper landing. No action yet to rectify the problem.

4.

S2 L3 GL: 22-23/F Escalator S2-ESC9 Escalator assembled and ready for installation. Civil Work Insufficient width at lower pit and insufficient width at upper landing. No action yet to rectify the problem.

5.

S2 L3 GL: 23-24/F Escalator S2-ESC3 & S2-ESC4 Escalator assembled and ready for installation. Civil Work Size of pits are not adequate. No action yet to rectify the problem.

6.

S2 L2 GL: 21-22/B

Item

Location

Observation Note Vehicle Lift S2-VL1 No access from Level 3 to Lift Motor Room.

7.

S2 L3 GL: 24-25/B-C Passenger Lift S2-PL6 Assembly of lifts yet to commence. Civil Works Construction of the lift core is to be expedited.

8.

S2 L3 GL: 25/F 9. Escalators S2-ESC10, S2-ESC11, S2ESC13 & S2-ESC14 Escalator assembled and ready for installation. Civil Work Mismatched of lengths between landings and lengths of escalators.

S2 L2 GL: 26-27/G2-H

Item

Location

Observation Note Escalators S2-ESC12 Escalator assembled and ready for installation. Civil Work Corridor wall obstructing the installation of the escalator. Pit yet to be constructed. No action yet to rectify the problem.

10.

S2 L2 GL: 25-26/G-G1 Escalators S2-ESC7 Escalator assembled and ready for installation. Civil Work Intermediate beam obstructing the erection of the escalator. No action yet to rectify the problem.

11.

S2 L3 GL: 25-26/G1-G2 Passenger Lift S2-PL7 & S2-PL7 Water tightness problem interrupt installation of lift equipments inside the lift cores.

12.

Item

Location

Observation Note Escalators S2-ESC7 Installation work commence today.

13.

S2 L2 G/L: 27a/G-F

Date: 26/02/2013 Observation of Status of Escalator and Lift Works: 4 nos escalator installation is in progress at sector 6 2 nos glass lift steel structure works are in progress at sector 6
Item Location Observation Note

Escalators S6-ESC1 (cover with plastic sheet) Installation - work in progress Power Supply outstanding cabling work Glass Lift S6-PL1 Steel Structure work in progress Installation of lift in progress

1.

S6 L2 G/L: 22a/J1a Escalators S6-ESC2 (cover with plastic sheet) Steel Structure work in progress Power Supply outstanding cabling work

2.

Glass Lift S6-PL2 Steel Structure work in progress Installation of lift in progress

S6 L2 G/L: 22a/J1a Escalators S6-ESC3 & S6-ESC4 Work in progress

3.

S6 L2 G/L: 22b-23b/H4-H6