orkover objective:
To abandon the well in a safe manner permitting the removal and restoration of the location.
Account code :
Well history:
The well was drilled in xxx and was completed as an oil well. An Outside Liner repair was carried out in xxx. The well was closed in due to high water-cut in xxx. In xxx, the well was suspended with gravel, cement and a killstring.
1/7
-- Total time 50
Milieu restrictions :
Neighbouring wells: none
2/7
Concession:
Coordinates : X Y
Wellhead description:
3/7
Casing scheme:
|Size |Weight|Grade|Coupling|From |To |TOC |
Kickoff depth : -
4/7
General Notes
1. This is a H2S locations. Full H2S precautions to be taken including; H2S caravan to be on site, continuous pH monitoring and gas detection in the flow line, no body to stand on the tanks whilst circulating.
5/7
Programme :
1. Check tubing and production casing pressures, and pressure of all casing/casing annuli. Bleed off pressures. Report pressures in WOR even if zero.
4. Remove wellhead.
5. Pull H-plug
12. Cut 7" casing 50m below the 9 5/8" shoe at +/-151m. Assembly for cutting 7" casing as per Red Baron instructions. Circulate 7" x 9 5/8" annulus. Dump returns into separate pit. Check if 7" casing is free by lifting wellhead.
13. Lift flange. Cut casing below flange. N/U adapter spool. Fish 7" casing stub.
14. Retrieve 7" casing. Red Baron casing cutting tool to be used instead of breaking
6/7
connections.
15. RIH 2 3/8" Cmt stinger to 154m and set cement plug to surface. Pump (50m open hole) water spacer ahead. Pump cement until good cement returns seen at surface.
16. POOH and clean out wellhead. If necessary perform top fill cementation to 3m below TBF.
7/7