Académique Documents
Professionnel Documents
Culture Documents
A. This specification is intended as a generic guideline for use in defining the requirements of Epoxy Adhesive Injection utilizing the pressure injection process and concrete spall repair.
1.02 Pre-Qualification:
A. All concrete repairs shall be performed by an trained applicator and experienced workmen. They shall have satisfactorily completed a program of instruction in the methods of restoring concrete structures utilizing the specific epoxy injection process indicated. The curriculum shall include theory on the nature and causes of cracking in concrete structures, the technical aspects of correct material selection and use, and the operation, maintenance and trouble shooting of equipment. B. The applicator shall submit for review by the Engineer, at least seven days prior to proceeding, a written description of the proposed epoxy materials, their acceptable approvals and the injection procedure. The list shall include the repair work proposed for each item. C. The work shall utilize an epoxy injection system approved in writing by the Engineer of Record. This approval shall be kept with the approved set of plans for the project. D. All preparation work shall be monitored by a Special/Deputy Inspector, approved by the Engineer and in the employ of the Owner or the Engineer as the Owners representative, but not the Contractor or any other persons or parties responsible for the work. All phases and stages must be approved by the Engineer and the Special/Deputy Inspector of Record before work may proceed.
B. Documented proof that the proposed product has a five year proven record of performance of pressure injection grouting of cracks, confirmed by actual field tests and five successful installation that the Engineer can investigate.
ports shall be spaced on the far side at half the spacing for members up to 10" in thickness. Members over 10" in thickness shall have ports at equal spacing on each face. D. Surface seal material shall be applied to the face of the crack between the entry ports. For through cracks, surface seal shall be applied to both faces if accessable. E. Enough time for the surface seal material to gain adequate strength shall pass before proceeding with the injection. Avoid unnecessary delays to maintain the competance of the cap seal.
A. Enough time for the surface seal material to cure for adequate bond shall pass before proceeding with the injection..
B. So that an adequate number of Special/Deputy Inspectors be present, the Contractor shall notify the Engineer, 24 hours in advance, the number of injection crews scheduled for repair work. C. No pressure injection work shall proceed if the temperature of the existing concrete being repaired is less than 40 degree Fahrenheit.
psi and watch for any resin flow back through the supply lines for 10 minutes. If any flow is present, do not dispense. On continuing projects, it is adequate to conduct the above tests once a week unless the equipment has been adjusted or any repairs affected, in which case the three stage testing shall be performed before work is re-started whenever mechanical adjustments or repairs have been completed. Nozzle or hose replacements shall not be considered criteria for requiring a three stage test.
D. The Special/Deputy Inspector of Record shall be present for continuous inspection of all epoxy injection. The Special/Deputy Inspector shall monitor the work and shall record the work procedure and materials to achieve the maximum results.
3.06 Testing (Core testing shall only be with the approval of the Engineer of Record.
Note that coring may not be advisable under certain conditions and the requirement may be waived.) A. Cores shall be taken at locations designated by the Engineer or the Special/Deputy Inspector but not the Contractor or any other person responsible for the work. A core shall be defined as a 2 x member thickness core for samples in members 12 or less. Members greater than 12 in thickness shall be 12 or as required by the Engineer of Record in length. B. Three cores shall be taken for the first 100 linear ft. of crack repaired. These cores shall be reviewed by the Special/Deputy Inspector and the results submitted to the Engineer and the Owner for approval before continuing injection. C. During the course of the epoxy repair there shall be taken a minimum of one 2 core per 100 linear feet of repaired crack with a minimum of 1 per day. These cores shall be reviewed by the Special/Deputy Inspector and the results submitted to the Engineer and the Owner for approval before continuing injection. D. It is imperative that no reinforcing steel or tendons are cut when drilling cores. If rebar is encountered, abort the drilling procedure, remove the short core and relocate the coring procedure. E. The cores shall be handled carefully to avoid breakage and stored and transported in suitable containers. F. These cores shall be examined by the Special/Deputy Inspector for epoxy penetration of the cracks. If visual inspection shows that the minimum penetration requirements have been met and the results approved by the Engineer of Record and the Owner the core is considered to be satisfactory. If the penetration is considered inadequate, the core is considered a failure.
G. Satisfactory cores shall be demolished for further inspection. If no fracture occurs on a glue line, the core is acceptable. If a break occurs on a glue line, the core fragments shall be further inspected and/or tested to determine if the failure is attributable to improper metering or mixing of the resin. If so, the core shall be considered unsatisfactory and injection work shall be halted. H. The Engineer shall consider the failed cores and is required to develop a remedial injection procedure, the results of which shall be re-cored for re-examination. I. The core holes shall also be examined by the Special/Deputy Inspector and the core holes repacked with the continuous inspection of the Special/Deputy Inspector. The interior of the core hole shall be roughened by appropriate means to obtain a minimum surface profile of +/- 1/16 of exposed aggregate and packed with an approved non-shrink grout per manufacturers instructions and appropriate Research Report.