Vous êtes sur la page 1sur 8

Weekly Updated by 28-Mar-2013

MCB Schedule

2013-04-01 07:15
Activity ID

Activity Name

riginal Start

MCB Milestone

Finish

Total
Float

ration
223 2013-01-10 A

2013-11-20

-5

223 2013-01-10 A

2013-11-20

-5

223 2013-01-10 A

2013-11-20

Milestones
Milestones

Activity
%
Complete

2013
Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Interior doors - Luardi, Delivery at Site

2013-03-28*

143

0%

SAHCKMCB11490

Stretch ceiling - Savi, Delivery at Site

2013-03-28*

100

0%

SAHCKMCB11510

Fine porcelain stoneware - Marrazi, Delivery at Site

2013-01-10 A

SAHCKMCB11530

Landscape - TBD, Delivery at Site

2013-03-28*

SAHCKMCB15210

Telecom./IPCS Cabinet Delivery at Site

2013-03-06 A

100%

Telecom./IPCS Cabinet Delivery at Site

SAHCKMCB17350

Marshalling cabinet (15ea) Delivery at Site

2013-03-07 A

100%

Marshalling cabinet (15ea) Delivery at Site

SAHCKMCB17410

FGS Remote IO cabinet & marshalling cabinet Delivery at ...

2013-03-07 A

100%

FGS Remote IO cabinet & marshalling cabinet Delivery at Site

SAHCKMCB17420

Server System Network etc (85ea) delivery

2013-03-26 A

100%

SAHCKMCB17450

Workstation (20ea) Delivery at Site

2013-03-28*

16

0%

Workstation (20ea) Delivery at Site

SAHCKMCB17510

Console for all EPCs (59ea) Delivery at Site

2013-03-28*

15

0%

Console for all EPCs (59ea) Delivery at Site

SAHCKMCB17650

Operator Training Consoles Delivery at Site

2013-03-28*

16

0%

Operator Training Consoles Delivery at Site

SAHCKMCB19310

Power Receiving at 700-SS-100 & 200

2013-03-28*

15

0%

Power Receiving at 700-SS-100 & 200

SAHCKMCB19550

Energizing for MCB

2013-08-03*

17

0%

SAHCKMCB19930

Mechanical Completion

2013-11-20*

-5

0%

100%
100

222 2012-09-27 A

2013-07-30

103

BUILDING

176 2012-09-27 A

2013-05-18

162

Wall finish

31 2012-09-27 A

2013-02-20 A

Cement plaster with painting

26 2012-09-27 A

2013-01-22 A

100%

SHFCKMCB10610

Acid resistant painting

12 2012-12-25 A

2013-02-20 A

100%

17 2012-12-12 A

2013-03-28

204

17 2012-12-12 A

2013-03-28

204

104 2012-11-19 A

2013-03-28

205

SHFCKMCB20650

Water Proofing

Floor finish

Stretch ceiling - Savi, Delivery at Site


Fine porcelain stoneware - Marrazi, Delivery at Site
Landscape - TBD, Delivery at Site

Server System Network etc (85ea) delivery

Energizing for MCB


Me

Cement plaster with painting


Acid resistant painting

95%

Water Proofing

SHFCKMCB30550

Raised access floor system

32 2012-11-19 A

2013-03-14 A

100%

Raised access floor system

SHFCKMCB30710

Static conductive linoleum

25 2013-02-05 A

2013-03-14 A

100%

Static conductive linoleum

SHFCKMCB30850

Chemical resistant tile

13 2013-02-27 A

2013-03-28

205

98%

171 2012-11-17 A

2013-05-18

162

SHFCKMCB51010

Double leaf steel door

62 2013-03-16 A

2013-05-18

162

30%

SHFCKMCB51210

Blast resistant door

35 2013-03-16 A

2013-04-21

184

40%

SHFCKMCB51250

Hardware & Accessories

48 2013-03-25 A

2013-05-12

39

20%

SHFCKMCB51310

Scaffold Removal

25 2012-11-17 A

2013-01-08 A

Door & Windows

ELECTRICAL

215 2012-11-03 A

2013-07-18

100%

Chemical resistant tile


Double leaf steel door
Blast resistant door
Hardware & Accessories
Scaffold Removal

-17

143 2012-11-03 A

2013-03-28 A

SQFCKMCB20110

Elec. Room & Bottom of access floor

68 2013-01-11 A

2013-01-17 A

100%

SQFCKMCB20150

Between of GL and Ceiling

18 2013-01-12 A

2013-03-28 A

100%

Between of GL and Ceiling

SQFCKMCB20210

Ceiling

42 2012-11-03 A

2013-03-28 A

100%

Ceiling

Cable Tray & Race way Installation

Elec. Room & Bottom of access floor

119 2013-02-25 A

2013-07-18

-17

SQNCKMCB30110 MCC & UPS / Battery

58 2013-02-25 A

2013-04-20

23

66%

MCC & UPS / Battery

SQNCKMCB30150 Telecom & FA & IPCS Cabinet

34 2013-03-16 A

2013-04-20

31

50%

Telecom & FA & IPCS Cabinet

SQNCKMCB30210 TSI & FA Device

55 2013-03-06 A

2013-05-18

20%

SQNCKMCB30250 Lighting & Receptacle

47 2013-02-25 A

2013-04-02

46

90%

SQNCKMCB30350 Elect. Equipment Test for Pre-comm.

56 2013-05-12

2013-07-18

-17

0%

76 2013-02-23 A

2013-06-26

-17

SQHCKMCB40110 For Power(MCC, UPS, Battery rack)

65 2013-03-28

2013-06-11

-17

0%

SQHCKMCB40210 For TSI & FA & IPCS

65 2013-02-23 A

2013-06-26

-17

50%

SQHCKMCB40310 For Lighting & Receptacle

70 2013-02-25 A

2013-06-09

-2

10%

Equipment Installation
Installa

Cable Pulling & wiring


wir

Remaining Level of Effort

Actual Work

Critical Remaining ...

Actual Level of Effort

Remaining Work

Milestone

Nov

Interior doors - Luardi, Delivery at Site

0%

SHFCKMCB10350

Ceiling finish

Oct

-5

SAHCKMCB11450

UPS/EQUIPMENT/INSTRUMENT/TELECOM ROOM
UPS/EQUIPMENT

Sep

Page 1 of 8

TSI & FA Device


Lighting & Receptacle
Elect. Equipment Test for Pre-comm.
For Power(MCC, UPS, Battery rack)
For TSI & FA & IPCS
For Lighting & Receptacle
Date
2013-04-01

Revision
Weekly Updated Cut-off by 28-Mar-2013

Checked

Approved

Weekly Updated by 28-Mar-2013

MCB Schedule

2013-04-01 07:15
Activity ID

Activity Name

riginal Start

Finish

Total
Float

HVAC

ration
134 2012-10-26 A

2013-04-18

Work

134 2012-10-26 A

2013-04-18

Activity
%
Complete

2013
Jan

Feb

Mar

Apr

SHHCKMCB10010 Temp. Aircon Delivery

26 2012-12-10 A

2013-02-28 A

100%

Temp. Aircon Delivery

SHHCKMCB10050 Temp. Aircon Install

13 2012-12-29 A

2013-02-28 A

100%

Temp. Aircon Install

SHHCKMCB10110 Duct installation & Insulation

38 2012-10-26 A

2013-03-28 A

100%

SHHCKMCB10150 Duct fixture installation

31 2012-12-25 A

2013-04-04

80%

SHHCKMCB10210 Auto control tray & pulling work

31 2012-12-10 A

2013-04-08

70%

SHHCKMCB10250 Duct test (only leak & balancing)

9 2013-04-08

2013-04-18

0%

8 2013-03-28

2013-04-06

142

8 2013-03-28

2013-04-06

142

8 2013-03-28

2013-04-06

142

209 2012-11-17 A

2013-07-30

103

209 2012-11-17 A

2013-07-30

103

FIRE FIGHTING
Work
SSDCKMCB10150

Pipe pneumatic test

INSTRUMENT
Work

May

Jun

Jul

Aug

Sep

Oct

Nov

Duct installation & Insulation


Duct fixture installation
Auto control tray & pulling work
Duct test (only leak & balancing)

0%

Pipe pneumatic test

SRBCKMCB10110

Marshalling cabinet (15ea) Delivery at Site

16 2013-03-07 A

2013-03-31

42

85%

SRBCKMCB10150

FGS Remote IO cabinet & marshalling cabinet Delivery at ...

18 2013-03-07 A

2013-03-28

204

95%

SRBCKMCB10170

Server System Network etc (85ea) delivery

18 2013-03-26 A

2013-03-30

43

SRBCKMCB10250

Tray & Frame Installation

57 2012-11-17 A

2013-01-16 A

SRBCKMCB10310

Equipment Installation

46 2013-03-16 A

2013-05-15

10%

SRBCKMCB10350

Internal Cable Termination

37 2013-04-11

2013-05-25

0%

SRBCKMCB10410

Power Cable Termination

38 2013-04-25

2013-06-09

0%

SRBCKMCB10450

Ground Cable Termination

23 2013-06-09

2013-07-04

0%

SRBCKMCB10510

Optical Cable pulling (Only for Common & MCB except ot...

84 2013-04-18

2013-07-30

0%

Optical Cable pulling (Only for Common & MCB excep

SRBCKMCB10550

Optical Cable Termination by Vendor

81 2013-04-22

2013-07-30

0%

Optical Cable Termination by Vendor

SRBCKMCB10650

Instrument Equipment Test/Pre-comm

17 2013-07-06

2013-07-30

0%

Instrument Equipment Test/Pre-comm

244 2012-11-09 A

2013-08-31

81

217 2012-11-10 A

2013-07-08

117

SYSTEM ENG. ROOM


RO
BUILDING

Marshalling cabinet (15ea) Delivery at Site


FGS Remote IO cabinet & marshalling cabinet Delivery at Site

90%

Server System Network etc (85ea) delivery

100%

Tray & Frame Installation


Equipment Installation
Internal Cable Termination
Power Cable Termination
Ground Cable Termination

74 2012-11-10 A

2013-02-20 A

SHFCKMCB10150

Hollow concrete block

18 2012-11-10 A

2013-01-02 A

100%

Hollow concrete block

SHFCKMCB10410

Cement plaster with painting

18 2012-11-17 A

2013-01-02 A

100%

Cement plaster with painting

SHFCKMCB10650

Drywall finish

14 2013-01-20 A

2013-02-20 A

100%

Wall finish

Ceiling finish

104 2013-01-14 A

2013-05-27

Drywall finish

101

SHFCKMCB20450

Water Proofing

20 2013-01-14 A

2013-03-28

-13

95%

SHFCKMCB20710

Suspended plaster board ceiling

25 2013-04-29

2013-05-27

101

0%

Suspended plaster board ceiling

SHFCKMCB20910

Suspended metal ceiling

25 2013-04-29

2013-05-27

101

0%

Suspended metal ceiling

45 2013-05-18

2013-07-08

101

Floor finish
SHFCKMCB30610

Raised access floor system

27 2013-05-18

2013-06-17

101

0%

SHFCKMCB30750

Recomposed Quartz stone tiles

28 2013-06-06

2013-07-08

101

0%

97 2013-03-12 A

2013-07-08

117

Partitions
SHFCKMCB70650

SE Glass partition system

27 2013-03-12 A

2013-07-08

101

60%

SHFCKMCB70750

Acoustic wood panels

27 2013-06-08

2013-07-08

117

0%

SHFCKMCB70850

Fixed glass panels

27 2013-06-08

2013-07-08

117

0%

SHFCKMCB70910

Scaffold Removal

26 2013-03-28

2013-04-27

-3

0%

226 2012-12-01 A

2013-08-31

ELECTRICAL
Conduit piping & s
sleeve work
SQFCKMCB10350

Internal wall(hollow concrete block)

Cable Tray & Race way Installation


SQFCKMCB20250

Ceiling (for HVAC damper)

Equipment Installation
Installa
Remaining Level of Effort

Actual Work

Critical Remaining ...

Actual Level of Effort

Remaining Work

Milestone

18 2012-12-01 A

2013-01-03 A

18 2012-12-01 A

2013-01-03 A

52 2013-01-27 A

2013-04-09

52 2013-01-27 A

2013-04-09

99 2013-02-05 A

2013-07-24

100%

Water Proofing

Raised access floor system


Recomposed Quartz stone tiles
SE Glass partition system
Acoustic wood panels
Fixed glass panels
Scaffold Removal

Internal wall(hollow concrete block)

80%

Page 2 of 8

Ceiling (for HVAC damper)

Date
2013-04-01

Revision
Weekly Updated Cut-off by 28-Mar-2013

Checked

Approved

Weekly Updated by 28-Mar-2013

MCB Schedule

2013-04-01 07:15
Activity ID

Activity Name

riginal Start

SQNCKMCB30310 TSI & FA Device

Finish

ration
87 2013-02-05 A

2013-06-24

78 2013-04-22

2013-07-24

SQNCKMCB30410 Lighting & Receptacle

Total
Float

Activity
%
Complete
24
20%
1

136 2013-02-05 A

2013-08-31

71 2013-04-09

2013-07-01

18

0%

SQHCKMCB40510 For TSI & FA

95 2013-02-05 A

2013-06-24

24

20%

SQHCKMCB40550 For Lighting & Receptacle

74 2013-03-28

2013-06-22

0%
0%

SQHCKMCB40650 Elect.Equipment Test for Pre-comm.

74 2013-05-26

2013-08-31

HVAC

170 2012-11-09 A

2013-05-25

91

Work

170 2012-11-09 A

2013-05-25

91

SHHCKMCB30010 Temp. Aircon Delivery

14 2013-04-18

2013-05-04

-2

0%

SHHCKMCB30050 Temp. Aircon Install

18 2013-05-05

2013-05-25

-2

0%

SHHCKMCB30110 Duct installation & Insulation

44 2012-11-09 A

2013-01-22 A

100%

SHHCKMCB30150 Duct fixture installation

33 2012-12-02 A

2013-02-28 A

100%

SHHCKMCB30210 Auto control tray& pulling work

33 2013-03-28

2013-05-05

101

0%

SHHCKMCB30250 Duct test (only leak & balancing)

6 2013-05-07

2013-05-13

101

0%

91 2013-03-28

2013-07-13

-13
-13

INSTRUMENT

Feb

Mar

Apr

May

Jun

Jul

Aug

For Power(HVAC)
For Lighting & Receptacle
Elect.Equipment Test for Pre-comm.

Temp. Aircon Delivery


Temp. Aircon Install
Duct installation & Insulation
Duct fixture installation
Auto control tray& pulling work
Duct test (only leak & balancing)

91 2013-03-28

2013-07-13

18 2013-03-28

2013-04-17

-2

0%

SRBCKMCB20150

Tray & Frame Work (Instrument)

31 2013-03-30

2013-05-04

-13

0%

SRBCKMCB20210

Equipment Installation

24 2013-05-21

2013-06-17

-13

0%

Equipment Installation

SRBCKMCB20250

The Other Cable pulling

34 2013-05-05

2013-06-12

-9

0%

The Other Cable pulling

SRBCKMCB20310

The Other Cable termination and test

21 2013-06-06

2013-06-30

-3

0%

SRBCKMCB20350

Instrument Equipment Test/Pre-comm

21 2013-06-18

2013-07-13

-13

0%

248 2012-11-03 A

2013-09-05

77

241 2012-11-17 A

2013-09-05

-3

167 2012-11-17 A

2013-05-13

85

BUILDING
Wall finish
SHFCKMCB10450

Cement plaster with painting

26 2012-11-17 A

2013-03-27 A

SHFCKMCB10710

Acoustic wooden Cladding

66 2013-03-16 A

2013-05-13

85

102 2013-01-12 A

2013-06-17

55

Ceiling finish

100%

Workstation (20ea) Delivery at Site


Tray & Frame Work (Instrument)

The Other Cable termination and test


Instrument Equipment Test/Pre-comm

Cement plaster with painting

40%

Acoustic wooden Cladding

SHFCKMCB20140

Water Proofing

26 2013-01-12 A

2013-03-21 A

100%

SHFCKMCB20150

Upper steel substructure partitions - Area A

34 2013-03-12 A

2013-03-28 A

100%

SHFCKMCB20170

Upper steel substructure partitions - Area B

39 2013-03-18 A

2013-04-01

40

90%

SHFCKMCB20510

Acoustic solid wood suspended ceiling-white - Only Area A

34 2013-02-25 A

2013-04-16

101

50%

Acoustic solid wood suspended ceiling-white - Only Area A

SHFCKMCB20750

Acoustic solid wood suspended ceiling-Natural - Only Area A

35 2013-02-23 A

2013-04-13

35

60%

Acoustic solid wood suspended ceiling-Natural - Only Area A

SHFCKMCB20950

Acoustic solid wood suspended ceilng with custom light co...

42 2013-03-23 A

2013-04-07

44

80%

SHFCKMCB21110

Stretch ceiling custom made wooden enclosure - Only Are...

26 2013-01-12 A

2013-03-31

122

90%

SHFCKMCB21250

Suspended plaster board ceiling - Only Area B

50 2013-03-28

2013-05-25

20

0%

SHFCKMCB21310

Mold & moisture resistant gypsumboard ceiling - Only Are...

43 2013-04-20

2013-06-08

20

0%

SHFCKMCB21410

Suspended radial metal ceiling - Only Area B

42 2013-04-11

2013-05-29

24

0%

SHFCKMCB21550

Suspended metal ceiling - Only Area B

46 2013-04-25

2013-06-17

24

0%

78 2013-04-28

2013-08-03

20

Floor finish
SHFCKMCB30910

Raised access floor system - Area A

33 2013-04-30

2013-06-08

20

0%

SHFCKMCB30930

Raised access floor system - Area B

27 2013-05-27

2013-06-27

20

0%

SHFCKMCB30950

Recomposed Quartz stone tiles - Area A

35 2013-05-29

2013-07-09

25

0%

SHFCKMCB30970

Recomposed Quartz stone tiles - Area B

26 2013-06-27

2013-08-03

20

0%

SHFCKMCB31010

Scaffold Removal

26 2013-04-28

2013-05-27

-3

0%

102 2013-04-28

2013-09-05

-3

63 2013-04-28

2013-07-10

-3

Door & Windows


SHFCKMCB50150

Double leaf steel door

Remaining Level of Effort

Actual Work

Critical Remaining ...

Actual Level of Effort

Remaining Work

Milestone

Water Proofing
Upper steel substructure partitions - Area A
Upper steel substructure partitions - Area B

Acoustic solid wood suspended ceilng with custom light cover - Only Area B
Stretch ceiling custom made wooden enclosure - Only Area A
Suspended plaster board ceiling - Only Area B
Mold & moisture resistant gypsumboard ceiling - Only Area B
Suspended radial metal ceiling - Only Area B
Suspended metal ceiling - Only Area B
Raised access floor system - Area A
Raised access floor system - Area B
Recomposed Quartz stone tiles - Area A
Recomposed Quartz stone tiles - Area B
Scaffold Removal

0%
Page 3 of 8

Nov

For TSI & FA

Workstation (20ea) Delivery at Site

MAIN CONTROL R
ROOM

Oct

Lighting & Receptacle

SRBCKMCB20110

Work

Sep

TSI & FA Device

0%

SQHCKMCB40450 For Power(HVAC)

Cable Pulling & wiring


wir

2013
Jan

Double leaf steel door


Date
2013-04-01

Revision
Weekly Updated Cut-off by 28-Mar-2013

Checked

Approved

Weekly Updated by 28-Mar-2013

MCB Schedule

2013-04-01 07:15
Activity ID

Activity Name

riginal Start

SHFCKMCB50310

Double leaf wood steel door - MCR

SHFCKMCB50410

Single leaf wood door

SHFCKMCB50510

Hardware & Accessories

ration
63 2013-05-05

2013-07-18

Activity
%
Complete
-3
0%

63 2013-05-12

2013-07-28

-3

0%
0%

Partitions

Finish

Total
Float

54 2013-06-23

2013-09-05

-3

137 2013-02-10 A

2013-09-05

-3

2013
Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Double leaf wood steel door - MCR


Single leaf wood door
Hardware & Accessories

SHFCKMCB70450

SE Glass partition system

35 2013-02-10 A

2013-04-04

16

80%

SHFCKMCB70550

Acoustic wood panels

40 2013-03-28

2013-05-13

43

0%

SHFCKMCB70610

Fixed glass panels

40 2013-04-18

2013-06-03

43

0%

SHFCKMCB70710

SE glass partition system - Corridor

34 2013-03-05 A

2013-07-01

43

60%

SHFCKMCB70810

Sloped glass partition system - Corridor

40 2013-03-05 A

2013-09-05

-3

60%

Sloped glass partition system - Corrid

52 2013-06-25

2013-09-05

-3

52 2013-06-25

2013-09-05

-3

0%

Emergency control center console tab

248 2012-11-03 A

2013-09-05

-3

Furniture
SHFCKMCB80210

Emergency control center console table

ELECTRICAL
Conduit piping & s
sleeve work
SQFCKMCB10550

Internal wall(hollow concrete block)

Cable Tray & Race way Installation

18 2012-11-08 A

2013-01-30 A

18 2012-11-08 A

2013-01-30 A

100%

169 2012-11-03 A

2013-05-23

76
76

SE Glass partition system


Acoustic wood panels
Fixed glass panels
SE glass partition system - Corridor

Internal wall(hollow concrete block)

SQFCKMCB20310

Elec. Room & Bottom of access floor

49 2013-03-28

2013-05-23

SQFCKMCB20410

Ceiling

77 2012-11-03 A

2013-02-20 A

85 2013-02-05 A

2013-04-21

104

68 2013-02-05 A

2013-04-21

23

70%

TSI & FA Device

70%

Lighting & Receptacle

Equipment Installation
Installa
SQNCKMCB30450 TSI & FA Device
SQNCKMCB30510 Lighting & Receptacle

68 2013-02-23 A

2013-04-21

104

157 2013-01-30 A

2013-09-05

-3

SQHCKMCB40610 For Power(HVAC)

63 2013-03-28

2013-06-09

62

SQHCKMCB40710 For TSI & FA & IPCS

87 2013-01-30 A

2013-03-06 A

SQHCKMCB40750 For Lighting & Receptacle

72 2013-02-23 A

2013-03-21 A

SQHCKMCB40810 Elect.Equipment Test for Pre-comm.

70 2013-06-03

2013-09-05

-3

HVAC

213 2012-12-10 A

2013-08-19

90

Work

213 2012-12-10 A

2013-08-19

90

Cable Pulling & wiring


wir

0%
100%

0%
100%
100%

12 2013-03-23 A

2013-03-28 A

SHHCKMCB50030 Temp. Aircon Install

18 2013-03-28

2013-04-17

SHHCKMCB50150 Duct fixture installation

39 2012-12-10 A

2013-03-07 A

SHHCKMCB50210 Auto control tray& pulling work

30 2013-03-23 A

2013-04-24

61

20%

SHHCKMCB50250 Duct test (only leak & balancing)

12 2013-04-25

2013-05-08

169

0%

SHHCKMCB50350 Drainage piping work

100%

2013-03-07 A

SHHCKMCB50410 Portable water piping work

53 2013-02-02 A

2013-03-07 A

SHHCKMCB50450 Sanitary fixture work

91 2013-04-25

2013-08-19

37 2013-03-23 A

2013-03-28 A

37 2013-03-23 A

2013-03-28 A

37 2013-03-23 A

2013-03-28 A

99 2012-12-05 A

2013-07-20

-3
-3

FIRE FIGHTING
Work
SSDCKMCB30110

Installation inergen pipe work (access floor)

INSTRUMENT

0%
100%

108 2013-02-02 A

61

100%

2013-04-17

-3

0%

SRBCKMCB30150

Tray & Frame work (Instrument)

22 2012-12-05 A

2013-04-04

15

70%

SRBCKMCB30210

Equipment installation

27 2013-04-18

2013-05-19

-3

0%

SRBCKMCB30250

Internal cable termination

15 2013-05-04

2013-05-21

-3

0%

SRBCKMCB30310

Power cable termination

18 2013-05-14

2013-06-04

-3

0%

SRBCKMCB30350

Ground cable termination

19 2013-05-21

2013-06-12

0%

SRBCKMCB30410

LAN cable termination

22 2013-06-04

2013-06-30

-3

0%

SRBCKMCB30450

Instrument Equipment Test/Pre-comm

18 2013-06-26

2013-07-20

-3

0%

Remaining Work

Milestone

Duct fixture installation


Auto control tray& pulling work
Duct test (only leak & balancing)
Portable water piping work

2013-07-20

Actual Level of Effort

Temp. Aircon Install

0%

18 2013-03-28

Critical Remaining ...

Temp. Aircon Delivery

100%

99 2012-12-05 A

Actual Work

Elect.Equipment Test for Pre-comm.

Drainage piping work

Console for all EPCs (59ea) Delivery at Site

Remaining Level of Effort

For Lighting & Receptacle

100%

SRBCKMCB30110

Work

For Power(HVAC)
For TSI & FA & IPCS

0%

SHHCKMCB50010 Temp. Aircon Delivery

10

Elec. Room & Bottom of access floor


Ceiling

Page 4 of 8

Sanitary fixture work

Installation inergen pipe work (access floor)

Console for all EPCs (59ea) Delivery at Site


Tray & Frame work (Instrument)
Equipment installation
Internal cable termination
Power cable termination
Ground cable termination
LAN cable termination
Instrument Equipment Test/Pre-comm
Date
2013-04-01

Revision
Weekly Updated Cut-off by 28-Mar-2013

Checked

Approved

Weekly Updated by 28-Mar-2013

MCB Schedule

2013-04-01 07:15
Activity ID

Activity Name

riginal Start
ration
204 2012-11-08 A

HVAC Room
BUILDING

Finish
2013-06-06

79 2012-11-08 A

2013-02-21 A

Total
Float

Activity
%
Complete

2013
Jan

Feb

Mar

79 2012-11-08 A

2013-02-21 A

Hollow Concrete Block

39 2012-11-08 A

2013-01-03 A

100%

Hollow Concrete Block

SHFCKMCB13570

Cement Plaster

37 2012-12-01 A

2013-01-09 A

100%

Cement Plaster

SHFCKMCB33870

Emulsion Painting

25 2012-12-26 A

2013-02-21 A

100%

18 2012-11-17 A

2013-01-14 A

18 2012-11-17 A

2013-01-14 A

98 2013-01-30 A

2013-05-28

18 2013-01-30 A

2013-03-21 A

18 2013-01-30 A

2013-03-21 A

17 2013-03-18 A

2013-04-13

72

17 2013-03-18 A

2013-04-13

72

72 2013-02-23 A

2013-05-28

53

Ceiling finish
SHFCKMCB23870

Exposed ceiling works

ELECTRICAL
Conduit piping & s
sleeve work
SQFCKMCB13370

Conduit Pipe work

Cable Tray & Race way Installation


SQFCKMCB13570

Cable Tray & Race way work

Equipment Installation
Installa

May

Jun

Jul

Aug

100%

Exposed ceiling works

100%

Conduit Pipe work

20%
100%

Cable Tray & Race way work

MCC Installation

14 2013-02-23 A

2013-02-28 A

TSI, FA Device Installation

25 2013-03-28

2013-04-27

53

0%

SQFCKMCB43570

LTG & Receptacle Installation

24 2013-04-08

2013-05-05

53

0%

SQFCKMCB43870

Elect. Equipment Test for Precomm.

19 2013-05-05

2013-05-28

53

0%

Elect. Equipment Test for Precomm.

Cable Pulling & wiring


wir

19 2013-05-05

2013-05-27

53

SQFCKMCB33170

Cable pulling & Wiring for TSI, FA Device

11 2013-05-09

2013-05-22

53

0%

Cable pulling & Wiring for TSI, FA Device

SQFCKMCB33370

Cable pulling & Wiring for LTG & Receptacle

15 2013-05-09

2013-05-27

53

0%

SQFCKMCB33570

Cable pulling & Wiring for HVAC Power

14 2013-05-05

2013-05-21

53

0%

112 2013-01-29 A

2013-06-06

144

112 2013-01-29 A

2013-06-06

144

SHHCKMCB13170 Duct installation& insulation

53 2013-02-17 A

2013-05-20

160

SHHCKMCB53170 Duct fixture installation

32 2013-04-13

2013-05-20

160

0%

SHHCKMCB73270 Auto control panel , tray & wiring

45 2013-03-23 A

2013-04-23

54

50%

SHHCKMCB93170 Equipment installation _AHU/ACCU

39 2013-01-29 A

2013-04-01

73

90%

SHHCKMCB93370 Refrigerent pipe Work

41 2013-03-25 A

2013-05-05

44

20%
0%

SHHCKMCB93870 Pre-comissioning

Operator Training Room, Permit Room, Emergency Con...


BUILDING
Wall finish

28 2013-05-05

2013-06-06

44

325 2012-11-08 A

2013-12-04

276 2012-11-12 A

2013-09-22

63

158 2012-11-15 A

2013-05-12

167

MCC Installation
TSI, FA Device Installation
LTG & Receptacle Installation

Cable pulling & Wiring for LTG & Receptacle


Cable pulling & Wiring for HVAC Power

15%

100%

Duct installation& insulation


Duct fixture installation
Auto control panel , tray & wiring
Equipment installation _AHU/ACCU
Refrigerent pipe Work
Pre-comissioning

SHFCKMCB10250

Hollow concrete block

38 2012-11-15 A

2013-02-21 A

SHFCKMCB10510

Cement plaster with painting

36 2013-01-19 A

2013-04-01

19

90%

Cement plaster with painting

SHFCKMCB10750

Drywall finish

32 2013-01-22 A

2013-04-01

15

90%

Drywall finish

SHFCKMCB10850

Fine porcelain stoneware

35 2013-04-01

2013-05-12

15

0%

SHFCKMCB11010

Natural stone cladding

38 2013-02-26 A

2013-04-28

178

30%

Natural stone cladding

SHFCKMCB11050

Skim coat & Painting

38 2013-03-16 A

2013-04-28

178

30%

Skim coat & Painting

83 2013-01-30 A

2013-06-12

140

Ceiling finish

Hollow concrete block

Fine porcelain stoneware

SHFCKMCB20200

Water Proofing

26 2013-01-30 A

2013-04-01

202

95%

SHFCKMCB20210

Upper steel substructure partitions

75 2013-03-05 A

2013-04-14

-9

80%

SHFCKMCB20350

Acoustic wood veneer ceiling

49 2013-03-28

2013-05-23

18

0%

SHFCKMCB20550

Glue bonded glass and panel suspended ceilings

35 2013-04-01

2013-05-12

15

0%

SHFCKMCB20810

Suspended microperforated gypsum board ceiling

62 2013-03-28

2013-06-08

-9

0%

Suspended microperforated gypsum board ceiling

SHFCKMCB21010

Suspended plaster board ceiling

62 2013-03-28

2013-06-08

-9

0%

Suspended plaster board ceiling

SHFCKMCB21150

Water resistant gypsum board ceiling

62 2013-04-01

2013-06-12

37

0%

SHFCKMCB21450

Suspended metal ceiling

49 2013-04-13

2013-06-08

-9

0%

Remaining Level of Effort

Actual Work

Critical Remaining ...

Actual Level of Effort

Remaining Work

Milestone

Nov

53

SQFCKMCB43370

HVAC Room

Oct

Emulsion Painting

SQFCKMCB43270

HVAC

Sep

144

SHFCKMCB13270

Wall finish

Apr

Page 5 of 8

Water Proofing
Upper steel substructure partitions
Acoustic wood veneer ceiling
Glue bonded glass and panel suspended ceilings

Water resistant gypsum board ceiling


Suspended metal ceiling
Date
2013-04-01

Revision
Weekly Updated Cut-off by 28-Mar-2013

Checked

Approved

Weekly Updated by 28-Mar-2013

MCB Schedule

2013-04-01 07:15
Activity ID

Activity Name

riginal Start

Floor finish

Finish

Total
Float

ration
111 2013-04-01

2013-08-19

58

Activity
%
Complete

2013
Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

SHFCKMCB30150

Raised access floor system

27 2013-04-13

2013-05-13

-9

0%

SHFCKMCB30310

Natural stone tile

52 2013-06-10

2013-08-19

-4

0%

SHFCKMCB30410

Hardwood floor

38 2013-06-26

2013-08-19

-4

0%

Hardwood floor

SHFCKMCB30450

Fine porcelain stoneware

38 2013-06-10

2013-07-28

49

0%

Fine porcelain stoneware

SHFCKMCB30510

Chemical resistant tiles

24 2013-04-01

2013-04-29

19

0%

SHFCKMCB30650

Carpet tiles

26 2013-06-24

2013-07-28

49

0%

SHFCKMCB30810

Scaffold Removal

26 2013-05-28

2013-06-26

95

0%

Scaffold Removal
Single leaf wood door

68 2013-05-16

2013-08-12

95

SHFCKMCB50210

Single leaf wood door

36 2013-05-16

2013-06-26

95

0%

SHFCKMCB50350

Single leaf toilet door

35 2013-05-23

2013-07-02

95

0%

SHFCKMCB50450

Single leaf Steel door(Fire rated)

53 2013-06-03

2013-08-12

95

0%

SHFCKMCB50550

Blast resistant door and window

35 2013-05-23

2013-07-02

122

0%

107 2013-01-30 A

2013-08-19

35

Door & Windows

Partitions

Nov

Raised access floor system


Natural stone tile

Chemical resistant tiles


Carpet tiles

Single leaf toilet door


Single leaf Steel door(Fire rated)
Blast resistant door and window

SHFCKMCB70210

SE Glass partition system

50 2013-03-05 A

2013-08-19

-4

75%

SHFCKMCB70250

Acoustic wood panels

50 2013-06-12

2013-08-19

34

0%

Acoustic wood panels

SHFCKMCB70310

Fixed glass panels

50 2013-06-12

2013-08-19

34

0%

Fixed glass panels

SHFCKMCB70410

SE glass partition system - Corridor

50 2013-01-30 A

2013-08-19

34

75%

SE glass partition system - Corridor

SHFCKMCB70510

Glue bonded glass and aluminum wall panels

58 2013-03-16 A

2013-08-19

35

25%

Glue bonded glass and aluminum wall panels

26 2013-05-14

2013-06-12

139

Furniture

SE Glass partition system

SHFCKMCB80110

Conference meeting table

26 2013-05-14

2013-06-12

139

0%

Conference meeting table

SHFCKMCB80150

Pantry cabinets

26 2013-05-14

2013-06-12

139

0%

Pantry cabinets

129 2012-11-12 A

2013-04-22

78

External AL claddin
cladding system
SHFCKMCB10550

Frame structure & Insulation

79 2012-11-12 A

2013-03-20 A

SHFCKMCB10810

AL cladding works

78 2013-01-13 A

2013-04-01

78

95%

SHFCKMCB10910

Illuminated wall shadow box

78 2013-02-16 A

2013-04-22

78

95%

60 2013-01-30 A

2013-06-01

95

26 2013-01-30 A

2013-03-30

63

95%

9 2013-03-30

2013-04-09

63

0%
0%

Roofing

100%

SHFCKMCB21050

Water proof work

SHFCKMCB21210

Roof paver

SHFCKMCB21350

Fixed skylights blast resistant

27 2013-03-30

2013-04-30

95

SHFCKMCB21510

Roof access hatch

27 2013-04-30

2013-06-01

95

SHFCKMCB21650

Down spot & Drain

52 2013-02-28 A

2013-03-07 A

AL cladding works
Illuminated wall shadow box
Water proof work
Roof paver
Fixed skylights blast resistant

0%

Roof access hatch

100%

223 2012-11-17 A

2013-08-19

SHFCKMCB30210

Wood entry canopy

50 2013-06-12

2013-08-19

35

0%

SHFCKMCB30350

Inergen shelter

78 2012-11-17 A

2013-04-24

182

70%

Exterior works

Frame structure & Insulation

Down spot & Drain

90
Wood entry canopy
Inergen shelter

27 2013-08-19

2013-09-22

34

SHFCKMCB40250

Fire & Safety signs

27 2013-08-19

2013-09-22

34

0%

Fire & Safety signs

SHFCKMCB40350

Room & Facilities signage

27 2013-08-19

2013-09-22

34

0%

Room & Facilities signage

76 2013-06-13

2013-09-22

34

76 2013-06-13

2013-09-22

34

0%

Landscaping

248 2012-11-08 A

2013-09-05

23

Sign & Way fiding

Land scaping
SHFCKMCB90150

Landscaping

ELECTRICAL
Conduit piping & s
sleeve work
SQFCKMCB10610

Internal wall

Cable Tray & Race way Installation

39 2012-11-08 A

2013-02-07 A

39 2012-11-08 A

2013-02-07 A

77 2013-02-16 A

2013-05-13

103
103

SQFCKMCB20450

Bottom of access floor

26 2013-04-14

2013-05-13

SQFCKMCB20510

Ceiling

77 2013-02-16 A

2013-03-07 A

100%
0%
100%

102 2013-02-05 A

2013-06-27

72

SQNCKMCB30610 TSI & FA Device

79 2013-02-05 A

2013-06-19

72

10%

SQNCKMCB30650 Lighting & Receptacle

79 2013-03-28

2013-06-27

72

0%

Equipment Installation
Installa

Remaining Level of Effort

Actual Work

Critical Remaining ...

Actual Level of Effort

Remaining Work

Milestone

Internal wall

Page 6 of 8

Bottom of access floor


Ceiling
TSI & FA Device
Lighting & Receptacle
Date
2013-04-01

Revision
Weekly Updated Cut-off by 28-Mar-2013

Checked

Approved

Weekly Updated by 28-Mar-2013

MCB Schedule

2013-04-01 07:15
Activity ID

Activity Name

riginal Start
ration
135 2013-02-05 A

Cable Pulling & wiring


wir

Finish
2013-09-05

Total
Float

Activity
%
Complete

Feb

Mar

Apr

May

Jun

Jul

Aug

112 2013-02-05 A

2013-03-07 A

SQHCKMCB40350 For Lighting & Receptacle

112 2013-03-28

2013-08-14

39

0%

SQHCKMCB40410 Elect.Equipment Test for Pre-comm.

112 2013-04-16

2013-09-05

23

0%

242 2012-12-10 A

2013-09-26

59

100%

Elect.Equipment Test for Pre-comm.

2013-09-26

59

62 2012-12-10 A

2013-04-15

146

75%

SHHCKMCB70150 Duct fixture installation

52 2013-02-16 A

2013-05-06

146

60%

SHHCKMCB70210 Auto control tray & pulling work

34 2013-04-25

2013-06-03

134

0%

SHHCKMCB70250 Duct test (only leak)

13 2013-06-03

2013-06-18

134

0%

SHHCKMCB90110 Equipment installation & Refrigerant pipe work

33 2013-03-24 A

2013-04-30

50

15%

Equipment installation & Refrigerant pipe work

SHHCKMCB90150 Auto control panel & wiring

32 2013-03-24 A

2013-04-30

50

50%

Auto control panel & wiring

SHHCKMCB90210 Pre-com, T.A.B

20 2013-04-30

2013-05-23

50

0%

SHHCKMCB90310 Drainage piping work

69 2013-02-16 A

2013-03-14 A

SHHCKMCB90350 Portable water piping work

36 2013-02-17 A

2013-04-01

SHHCKMCB90410 Sanitary fixture work

69 2013-06-26
82 2013-01-29 A

100%
103

90%

2013-09-26

30

0%

2013-05-27

124
124

82 2013-01-29 A

2013-05-27

SSDCKMCB40110

Installation of Manifolds (Cylinder Shelter)

47 2013-01-29 A

2013-02-20 A

100%

SSDCKMCB40150

Installation of Trench Piping (MCB-Cylinder Shelter)

46 2013-02-16 A

2013-03-07 A

100%

SSDCKMCB40210

Test (Room Integrity) & commissioning

26 2013-03-28

2013-04-27

124

0%

SSDCKMCB40250

Installation Portable Fire Extinguisher

26 2013-04-28

2013-05-27

124

0%

205 2013-03-28

2013-12-04

-17

Work

INSTRUMENT

Nov

For Lighting & Receptacle

242 2012-12-10 A

FIRE FIGHTING

Oct

For TSI & FA & IPCS

SHHCKMCB70110 Duct installation & Insulation

HVAC Room

Sep

23

SQHCKMCB40250 For TSI & FA & IPCS

HVAC

2013
Jan

Duct installation & Insulation


Duct fixture installation
Auto control tray & pulling work
Duct test (only leak)

Pre-com, T.A.B
Drainage piping work
Portable water piping work
Sanitary fixture work

Installation of Manifolds (Cylinder Shelter)


Installation of Trench Piping (MCB-Cylinder Shelter)
Test (Room Integrity) & commissioning
Installation Portable Fire Extinguisher

205 2013-03-28

2013-12-04

-17

SRBCKMCB40110

Operator Training Consoles Delivery at Site

24 2013-03-28

2013-04-24

-8

0%

SRBCKMCB40150

Tray & Frame work

24 2013-04-13

2013-05-09

-9

0%

SRBCKMCB40210

Equipment installation

24 2013-04-25

2013-05-22

0%

SRBCKMCB40250

The Other Cable pulling

26 2013-05-11

2013-06-09

-9

0%

SRBCKMCB40310

The Other Cable termination and test

24 2013-06-10

2013-07-07

-9

0%

SRBCKMCB40350

SIT test, IO test & Function test

27 2013-07-13

2013-08-24

-13

0%

SRBCKMCB40410

SAT test (common)

20 2013-08-28

2013-09-22

-17

0%

SRBCKMCB40450

ISIT test (common)

31 2013-09-17

2013-10-22

-17

0%

ISIT test (comm

SRBCKMCB40510

ISAT test (package 4)

40 2013-10-05

2013-11-20

-17

0%

ISA

SRBCKMCB40770

ISAT test with Other EPC Contractor

52 2013-10-05

2013-12-04

-17

0%

201 2013-04-01

2013-12-04

-17

201 2013-04-01

2013-12-04

-17

Work

COMMON
ELECTRICAL

59 2013-04-01

2013-06-09

63

SQNCKMCB60210 Electrical Equip.(MCC, Cabinet, UPS, Battery) earth

49 2013-04-01

2013-05-28

19

0%

SQNCKMCB60310 Lightning equip. install

52 2013-04-09

2013-06-09

63

0%

Ground & Lighting work

Operator Training Consoles Delivery at Site


Tray & Frame work
Equipment installation
The Other Cable pulling
The Other Cable termination and test
SIT test, IO test & Function test
SAT test (common)

Electrical Equip.(MCC, Cabinet, UPS, Battery) earth


Lightning equip. install

132 2013-04-08

2013-09-22

-17

SXNCKMCB10110

MCC & UPS/Battery

28 2013-07-10

2013-08-22

-17

0%

SXNCKMCB10150

IPCS without Other Contractors

53 2013-07-10

2013-09-22

-17

0%

IPCS without Other Contracto

SXNCKMCB10210

Telecommunication system without Other Contractors

53 2013-07-10

2013-09-22

-17

0%

Telecommunication system w

SXNCKMCB10250

Fire alarm system without Other Contractors

27 2013-08-19

2013-09-22

-17

0%

SXNCKMCB10310

Lighting & Receptacle

28 2013-07-10

2013-08-22

-17

0%

SXNCKMCB10350

HVAC

51 2013-04-08

2013-06-06

44

0%

193 2013-04-11

2013-12-04

-17

2013-10-21*

21

Test & Commissioning


Commission

Other Contractor - EPC 2 & 3


SXNCKMCB88110

EPC 2, Contract Milestone E34 for Complete SAT of ICS

Remaining Level of Effort

Actual Work

Critical Remaining ...

Actual Level of Effort

Remaining Work

Milestone

MCC & UPS/Battery

Fire alarm system without Oth


Lighting & Receptacle
HVAC

0%
Page 7 of 8

EPC 2, Contract
Date
2013-04-01

Revision
Weekly Updated Cut-off by 28-Mar-2013

Checked

Approved

Weekly Updated by 28-Mar-2013

MCB Schedule

2013-04-01 07:15
Activity ID

Activity Name

riginal Start
ration
0

2013-06-03*

Activity
%
Complete
131
0%

EPC 3, Contract Milestone E34 for Complete SAT of ICS

2013-12-04*

-17

0%

SXNCKMCB88170

EPC 3, Forecast Date of Milestone E34 for Complete SAT...

2013-05-23*

140

0%

SXNCKMCB88310

Instal. Finish Date of 720 Marshalling Cabinets, EPC 2

2013-04-27*

163

0%

SXNCKMCB88330

Instal. Finish Date of 721 Marshalling Cabinets, EPC 2

2013-05-11*

151

0%

SXNCKMCB88350

Instal. Finish Date of 722 Marshalling Cabinets, EPC 2

2013-05-02*

158

0%

SXNCKMCB88370

Instal. Finish Date of 730 Marshalling Cabinets, EPC 2

2013-04-11*

176

0%

SXNCKMCB88390

Instal. Finish Date of 731 Marshalling Cabinets, EPC 2

2013-04-22*

167

0%

SXNCKMCB88410

Instal. Finish Date of 732 Marshalling Cabinets, EPC 2

2013-05-15*

147

0%

SXNCKMCB88430

Instal. Finish Date of 733 Marshalling Cabinets, EPC 2

2013-04-29*

161

0%

SXNCKMCB88450

Instal. Finish Date of 734 Marshalling Cabinets, EPC 2

2013-06-03*

131

0%

SXNCKMCB88470

Instal. Finish Date of 740 Cabinets in Field, EPC 2

2013-06-22*

115

0%

SXNCKMCB88490

Instal. Finish Date of 741 Marshalling Cabinets, EPC 2

2013-06-02*

132

0%

SXNCKMCB88510

Instal. Finish Date of 742 Cabinets in Field, EPC 2

2013-06-22*

115

0%

Instal. Finish Date of 742 Cabinets in Field, EPC 2

SXNCKMCB88530

Instal. Finish Date of 726 Cabinets in Field, EPC 2

2013-06-22*

115

0%

Instal. Finish Date of 726 Cabinets in Field, EPC 2

SXNCKMCB88550

Instal. Finish Date of 727 Cabinets in Field, EPC 2

2013-06-22*

115

0%

SXNCKMCB88570

Instal. Finish Date of 751 Marshalling Cabinets, EPC 3

2013-06-03*

131

0%

Instal. Finish Date of 751 Marshalling Cabinets, EPC 3

SXNCKMCB88590

Instal. Finish Date of 752 Marshalling Cabinets, EPC 3

2013-06-04*

130

0%

Instal. Finish Date of 752 Marshalling Cabinets, EPC 3

SXNCKMCB88610

Instal. Finish Date of 753 Marshalling Cabinets, EPC 3

2013-05-23*

140

0%

SXNCKMCB88630

Instal. Finish Date of 754 Marshalling Cabinets, EPC 3

2013-05-02*

158

0%

SXNCKMCB88650

Instal. Finish Date of 780 Marshalling Cabinets, EPC 3

2013-05-07*

154

0%

SXNCKMCB88130

EPC 2, Forecast Date of Milestone E34 for Complete SAT...

SXNCKMCB88150

Remaining Level of Effort

Actual Work

Critical Remaining ...

Actual Level of Effort

Remaining Work

Milestone

Finish

Total
Float

2013
Jan

Page 8 of 8

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

EPC 2, Forecast Date of Milestone E34 for Complete SAT of ICS


EPC 3, Forecast Date of Milestone E34 for Complete SAT of ICS
Instal. Finish Date of 720 Marshalling Cabinets, EPC 2
Instal. Finish Date of 721 Marshalling Cabinets, EPC 2
Instal. Finish Date of 722 Marshalling Cabinets, EPC 2
Instal. Finish Date of 730 Marshalling Cabinets, EPC 2
Instal. Finish Date of 731 Marshalling Cabinets, EPC 2
Instal. Finish Date of 732 Marshalling Cabinets, EPC 2
Instal. Finish Date of 733 Marshalling Cabinets, EPC 2
Instal. Finish Date of 734 Marshalling Cabinets, EPC 2
Instal. Finish Date of 740 Cabinets in Field, EPC 2
Instal. Finish Date of 741 Marshalling Cabinets, EPC 2

Instal. Finish Date of 727 Cabinets in Field, EPC 2

Instal. Finish Date of 753 Marshalling Cabinets, EPC 3


Instal. Finish Date of 754 Marshalling Cabinets, EPC 3
Instal. Finish Date of 780 Marshalling Cabinets, EPC 3

Date
2013-04-01

Revision
Weekly Updated Cut-off by 28-Mar-2013

Checked

Approved

Vous aimerez peut-être aussi