NAME Nationality Year of Birth Profession Specialisation Total Year of Experience

NAGESH GANESH HEGDE INDIA 23-JUNE-1968 B.E. MECHANICAL ENGINEERING POWER PLANT, DESALINATION, WATER & WASTE WATER TREATMENT. 19 Years

Highly accomplished design and engineering manager with expertise in application of cutting edge technology in Desalination Projects, Power Projects, Water and Waste water Treatment Projects and water distribution projects in world class Organisations with global presence. SUMMARY A competent professional with an expertise of more than 19 years in designing and engineering of Desalination plants, Power Plants, Water and Waste water Treatment Plants and water distribution projects, with more than seven years of exposure to international environment. Highly competent in Project Feasibility study; Detailed project report, Project Financial models, evaluation of different technological solutions, equipment specifications, Tendering assistances, detailed engineering, procurement services, construction and commissioning of the plant. Adept in detailed designing and engineering, optimisation and application of Cutting Edge Technology in RO Plants, Water and Waste water treatment plant, Diesel Power Plant, Gas turbine Power Plant, Hydro Power Plant, HVAC, Fire protection and Building Management systems. Proven ability to manage medium to large scale projects with a good understanding of Indian and international design and engineering standards and practices. Highly competent in developing green field projects from concept to commissioning that including, feasibility study, financial models, lender engineering, environmental issues, EPC contracting, testing commissioning and operation and maintenance of the plant. Fue supply agreement, Power Purchase agreement, Water purchase agreement, site usufruct agreement etc. Demonstrated expertise for RO Plants, Water and Waste water treatment plant, Diesel Power Plant, Gas turbine Power Plant, Hydro Power Plant, HVAC, Fire protection and Building Management systems. Adept at pipe stress analysis, pressure vessel and storage tanks design, rotating and static equipment designs, water hammer / surge analysis, structural design analysis. Possess good knowledge of technical & commercial aspects of contracts, Project Planning, budgeting, scheduling, cost estimation, Purchase of equipments, project control & monitoring, QA/QC plan and project closing. Possess a good knowledge of ASME, AWWA, API, TEEMA, BIS, IS, ISO, ASHRAE, NFPA, NACE & UPC codes and standards. A motivated professional with excellent communicational and interpersonal skills and very conversant in software packages like: Primavera-P3, M.S.Project, MS Office-2007. CAESSERII, PV Elite, STAAD Pro & CADWORKS.

AWARDS:
British Expertise International Business Award for Innovation 2008-2009 Project Manager of the Year -2008 from Mott MacDonald UK - 2008 Highly Commended Award for Design, Engineering, Installation and Commissioning of World Largest Desalination Plant on the Barge- year 2008. Special Technological Innovation (STI) award from CH2MHill Denver USA 2007.

Your initials/page number 09/02/Staff No (note use of obliques, month and year only in date)

EXPERIENCE RECORD 2007 - 2009 MOTT MACDONALD LTS, Abu Dhabi 2007 2009 Projects Manager Power Generation Group.
Responsibilities: Feasibility study, preparation of detailed project reports for Power and Desalination Plants. Develop detailed technical specification and financial model for Power and Desalination Plants. Shoulder the responsibility for developing a Master Specification for Power and Desalination plant and Equipments. Detailed Design and Engineering of Plant and Equipment. Developed many different foot print Design of Desalination plant. Conduct the Training of Design Engineers. Customer satisfaction.

Achievements: Won British Expertise International Business Award for Innovation 2008/09 for my work in Desalination. Won Project Manager of Year 2008 Award from - Mott MacDonald, Energy Division. Won Highly commended Award for the year 2008 from Mott MacDonald for the Successful design and commissioning of World Largest SWRO Plant on Barge Designed the World Largest Barge Mounted SWRO Plant for Saudi Arabia. Received an Appreciation letter and Special Bonus reward from Mott MacDonald, UK for the same. Successfully completed the 50MLD SWRO project entire design and Maximise the profit margin by 35% Developed an innovative design approach to submerged Ultra filtration Tanks. Developed an IWP model for SWRO plants.

Key Projects: FUJAIRAH PE-2 Expansion 30MIGD SWRO and New 1000MW Combined cycle power plant and 40MIGD SWRO Plant:

Project Feasibility study for new 70MIGD (Total) SWRO Plant and 1000MW Duel fuel Combined Cycle Power plant. Study of various options, technologies, optimising the foot print of the project, detailed cost estimation for different process technologies, interface issues with existing plant, environmental issues, tariff study, fuel availability study, water and power evacuation study preparation of Tender Document, Evaluation of bids Project Engineering and Management.

GHUBRAH IWPP 500MW Combined cycle plant and 110,000M3/Day SWRO Plant.:

Project Feasibility study for new 500mw Combined Cycle Gas Turbine Plant and 110MLD SWRO plant. Preparation of detailed cost estimation, area availability, interface issues with existing plant, environmental issues, tariff study, fuel availability study and review of fuel supply agreement, water and power evacuation study etc complete.

2 x 55,500M3.day SWRO plant Palm Jebel Ali

Preparation of detailed project specification, detailed purchase specifications for the entire plant and equipment.

Salalah IWPP 430MW Combined cycle plant and 70,000M3/Day SWRO Plant.
Preparation of detailed project specification, system configuration and providing the functional specification for all the equipment. Advising the client on financial models. Review of Power purchase agreement, water purchase agreement and Fuel purchase agreement.
Your initials/page number 09/02/Staff No (note use of obliques, month and year only in date)

2x25000M3/Day capacity, Barge Mounted Sea water RO Plants in Saudi Arabia.


Detailed Design and Engineering of SW Intake, Brine/waste disposal, Product water transfer, Fire Protection, HVAC, Fuel Oil system etc. Review of Detailed Design of RO, UF, Pumps, pipe works and layout, Chemical dosing system, Electrical Switchgear room and dwelling area, Barge mooring details, Diesel power plant etc.

Shoaibah IWPP Saudi Arabia.


Detailed design Review of Mechanical Works. Seawater Intake, DMF, RO, Plant Layout, Chemical system, chemical storage tanks, CO2 Generation plant, Potabalization system, HVAC etc.

IMDAD Potable water Transmission and Distribution Project Phase-1 (17.5MIGD).


Preparation of Detailed Specification for Water Transmission and Distribution pumps, surge vessels, Pipes, valves, compressors, cranes etc complete.

Hassiyan Desalination and Power Plant Dubai, DEWA..


Preparation of Tender Specification for D-min plant and Waste water Plant.

2005 2007 2005 2007

CH2M HILL INTERNATIONAL, DUBAI Engineering Manager.

Responsibilities: Responsible for complete designing of the Project including Process, Civil engineering, Mechanical engineering, Electrical engineering , Instrumentation and controls. Shoulder the responsibility for integrating the design and engineering aspects of the projects. Perform the analysis of designs to optimise the design and cost. Develop a design team through proper induction and training, lead them to complete the Design and Engineering deliverables for the project as per time schedules. Establish specification for the procurement, evaluation of vendor quotes and procurement assistance. Responsible for the installation of the equipment and providing support for commissioning. Provide design and engineering support for preparing proposal and in marketing. Achievements: Received STI Award for the Design of SWRO plant during the year 2007 Suceessfully developed the standard design and specification template for the Sea water RO plants. Instrumental in streamlining the engineering work resulting in a reduction of the design work by 40%. Efficiently standardised the project modules, resulting in easy cost estimation. Successfully standardised the RO foot print therby giving a big leverage in market position.

Key Projects : 2x5MIGD SWRO Plant at Layyah, Sharjah.


Detailed Design and Engineering of Plant Process, Layout, Mechanical, Piping, Instrumentation, Electrical and Civil works, Procurement Assistance, site co-ordination and Inspection of various Equipment at Manufacturers shop. Project configuration was: Sea Water Intake, DAF, DMF, CF, RO, ERI, RO CIP&flushing, Brine reject system, chemical dosing and Neutralization system, Product storage and Transfer system. An EPC project.

2x5MIGD SWRO Plant at Khorfakhan, Sharjah.


Detailed Design and Engineering of Plant Process, Layout, Mechanical, Piping, Instrumentation, Electrical and Civil works, Procurement Assistance, site co-ordination and Inspection of various
Your initials/page number 09/02/Staff No (note use of obliques, month and year only in date)

Equipment at Manufacturers shop. Project configuration was: Sea Water Intake, DMF, CF, RO, ERI, RO CIP&flushing, Brine reject system, chemical dosing and Neutralization system, Product storage and Transfer system. An EPC project.

2x3.5MIGD SWRO Plant at Kalba, Sharjah.

Detailed Design and Engineering of Plant Process, Layout, Mechanical, Piping, Instrumentation, Electrical and Civil works, Procurement Assistance, site co-ordination and Inspection of various Equipment at Manufacturers shop. Project configuration was: Sea Water Intake, UF, UF cleaning, CF, RO, ERI, RO CIP & flushing, Brine reject system, chemical dosing and Neutralization system, Product storage and Transfer system. An EPC project.

Al Hamriya SWRO Plant at Sharjah 20MIGD capacity.

Preparation of detailed Technical Offer for the Tender, Cost Estimation, Bid evaluation, Performance guarantee and warranty studies. Co-ordination and supervision of all discipline design & Engineering activity.

2005 2005 2005 2005

HYFLUX MIDDLE EAST, DUBAI Project Manager.

Responsibilities: Shouldered the responsibility of designing the Mechanical, Electrical and Instrumentation Engineering and the Process of Project. Involved in developing specification for procurement, evaluation of vendor quotes and provided procurement assistance. Managed the co-ordination between vendors. Handled the planning, scheduling, monitoring and control of Projects. Worked on the Cost estimation of Project and management of Project claims and related financial matters. Liason with client, consultant for techno-commercial issues. Responsible for invoicing and collection of payment. Achievement: Completed the Design and Engineering of 32MLD SWRO plant within three months.

Key Project Title : 2x7MIGD SWRO Plant at Palm Jumeriah, Dubai.

Detailed Design and Engineering for the Project Process, Layout, Mechanical and Piping details. Procurement Assistance, site co-ordination and Inspection of various Equipment at Manufacturers shop. Project configuration was: Sea Water Intake, UF, CF, RO, ERI, RO CIP&flushing, Brine reject system, chemical dosing and Neutralization system, Product storage and Transfer system. An EPC project.

Waster Water Treatment plant at CLRI Coimbatore - India.

Preparation of detailed Technical Offer for the Tender, Cost Estimation, Bid evaluation Coordination and supervision of all discipline design & Engineering activity.

Pilot study - Leather and Dye Industrial waste treatment using submerged membrane and RO Technology.

Detailed Design of the Pilot plant, preparation of pilot testing protocol, result analysis and applying the out come of the results in Detailed design.

100MIGD SWRO Plant at Tuas - Singapore.

Design co-ordination, Procurement assistance, Preparation of commissioning protocols, Testing and commissioning of the Plant.

Your initials/page number 09/02/Staff No (note use of obliques, month and year only in date)

2002 2005 2002 2005

VA TECH WABAG LIMITED, CHENNAI, INDIA Project Manager.

Key Projects: 100MIGD Drinking water Treatment plant at Panjrapur, Mumbai.

Detailed Design and Engineering of Process, Layout, Mechanical, Piping, Instrumentation, Electrical and Civil works, procurement, shop inspection, installation, testing and commissioning of the plant. Project configuration was: Water Intake, water conveying system, Flash mixer, Lamella Clarifier, Gravity sand filters, chlorination system, product storage and transfer system. An EPC project.

10MLD De-Mineralised Water Plant for Chennai Petroleum.


Detailed Design and Engineering of Process, Layout, Mechanical, Piping, Instrumentation, Electrical and Civil works, procurement, shop inspection, installation, testing and commissioning of the plant, procurement, shop inspection, installation, testing and commissioning of the plant. Preparing the O&M Protocol and Maintaining the plant for 18 months. Project configuration was: Water Intake, Pressure Sand Filters. Carbon Filters, SAC, SWAC, SBA, WBA, MB, De-gasser, Acid and Caustic re-generation system, Neutralization system, Product storage and Transfer system, etc complete. An EPC project.

15MIGD De-Mineralised Water Plant for IOCL, Panipat.

Detailed Design and Engineering of Process, Layout, Mechanical, Piping, Instrumentation, Electrical and Civil works, procurement, shop inspection, installation, testing and commissioning of the plant. Project configuration was: Water Intake, Pressure Sand Filters. Carbon Filters, SAC, SWAC, SBA, WBA, MB, De-gasser, Acid and Caustic re-generation system, Neutralization system, Product storage and Transfer system, etc complete. An EPC project.

1999 2002 1999 2000 2000 2002

DAR ENGINEERING CONSULTANT, RIYADH, SAUDI ARABIA Sr.Engineer. Manager

Project Title : 65MW Dual Fuel Power Plant at Tabouk, KSA.

Feasibility study, Detailed Project Cost estimation and Financing models, Detailed Project specification for Turbine, fuel oil system, Cooling system, Power Distribution and grid arrangement etc.

25MW Gas Turbine Power Plant at Riyadh, KSA.


Detailed Plant design and Engineering of GE frame 6 Turbine, Governing system, Fuel Oil system, Oil coolers, Inlet Air system, Start up and Emergency Diesel Engines, Plant layout, piping, Fire Protection system, HVAC system, material handling arrangement etc complete. An EPC Project

3 Nos of 66/33KV GIS substation at Riyadh, KSA..

Detailed Plant design and Engineering of Substation, Transformers, GIS, Fire Protection system, HVAC system, material handling arrangement etc complete. An EPC Project

450KV Substation at Jeddah, KSA.

Detailed Plant design and Engineering of Substation, Transformers, GIS, online insulator washing system, Fire Protection system, HVAC system, material handling arrangement etc complete. An EPC Project.

3 Nos of 380/66KV GIS substation at AL-Khobar, KSA..


Detailed Plant design and Engineering of Substation, Transformers, GIS, Fire Protection system, HVAC system, chilled water system, material handling arrangement etc complete. An EPC Project.

1997 1999

SULZER FLOVEL HYDRO LIMITED, INDIA

Your initials/page number 09/02/Staff No (note use of obliques, month and year only in date)

1997 1999

Sr.Dy Manager Projects.

Key Projects: 2 x 15MW Bhavani Sagar Hydro Electric Project TNEB, India .
Detailed design, Engineering, Manufacturing of Vertical Kaplan Hydro Turbine, Governors, and Auxiliaries, Procurement of Generators, panels, substation equipments, supply, installation, testing, Trial running, commissioning and Performance testing of Power plant.. Project also involves, Dam intake system with roller gates, Trash rakes, Penstock of 3.5M dia, over velocity protection devices, Tail race etc An EPC Project.

2 x 4.5MW Harangi Hydro Electric Project Energy Development Co. India .

Detailed design, Engineering, Manufacturing of Horizontal Double regulated Hydro Turbine, Governors, and Auxiliaries, Procurement of Generators, panels, substation equipments, supply, installation, testing, Trial running, commissioning and Performance testing of Power plant.. Project also involves, Dam intake system with roller gates, Trash rakes, Horse shoe Tunnel of 5M dia 1KM long, Penstock Tail race etc. Project also includes the 5KM of Transmission line. An EPC Project.

4 x 4.5MW Hemavathy Hydro Electric Project Sandoor Power Corpn,. India .

Detailed design, Engineering, Manufacturing of Horizontal Double regulated Hydro Turbine, Governors, and Auxiliaries, Procurement of Generators, panels, substation equipments, supply, installation, testing, Trial running, commissioning and Performance testing of Power plant.. Project also involves, Dam intake system with roller gates, Trash rakes, Horse shoe Tunnel of 5M dia 1KM long, Penstock Tail race etc. Project also includes the 5KM of Transmission line. An EPC Project.

1995 1997 1995 1996 1996 1997

BHORUKA POWER CORPORATION LTD, INDIA Asst. Manager. Dy.Manager

Key Projects: 5 x1.5MW Shahapur Hydro Electric Project India .

This is an Non-conventional Energy Development scheme. Project was on Irrigation canals. Detailed feasibility study, Detailed project report, liason with the financial institution for arranging the funds for the projects, Developing detailed project financial model, cost estimation, project life cost estimation, NAV analysis. Power purchase agreement, statutory approval from the Government authorities. Preparation of detailed Tender document, invitation of bids, Techno-commercial evaluation of bids, purchase recommendation, Contracting, Review of detailed design, site co-ordination, equipment inspection, testing, installation and commissioning. Detailed O&M Protocol, trouble shooting plans. This was an BOOT basis Project.

2 x9MW Shiva Hydro Electric Project India .

Detailed feasibility study, Detailed project report, liason with the financial institution for arranging the funds for the projects, Developing detailed project financial model, cost estimation, project life cost estimation, NAV analysis. Power purchase agreement, statutory approval from the Government authorities. Preparation of detailed Tender document, invitation of bids, Techno-commercial evaluation of bids, purchase recommendation, Contracting, Review of detailed design, site co-ordination, equipment inspection, testing, installation and commissioning. Detailed O&M Protocol, trouble shooting plans. This was an BOOT basis Project.

60MW WADI Combined cycle Plantm KEB, India .

Detailed feasibility study, Detailed project report, liason with the financial institution for arranging the funds for the projects, Developing detailed project financial model, cost estimation, project life cost estimation, NAV analysis. Power purchase agreement, statutory approval from the
Your initials/page number 09/02/Staff No (note use of obliques, month and year only in date)

Government authorities.Preparation of detailed Tender document, invitation of bids, Technocommercial evaluation of bids, purchase recommendation, Contracting, Review of detailed design, site co-ordination, equipment inspection, testing, installation and commissioning.

100MW Dual Fuel Power Plant at Nellur India .


Detailed feasibility study, Detailed project report, liason with the financial institution for arranging the funds for the projects, Developing detailed project financial model, cost estimation, project life cost estimation, NAV analysis. Power purchase agreement, statutory approval from the Government authorities. Preparation of detailed Tender document, invitation of bids, Technocommercial evaluation of bids, purchase recommendation, Contracting, Review of detailed design, site co-ordination, equipment inspection, testing, installation and commissioning.

1994 1995 1994 1995

TATA CONSULTING ENGINEERING LTD, INDIA Mechanical Engineer.

Key Projects : 125MW Bhivpuri Hydro Electric Project India .

Preparation of detailed Tender document, invitation of bids, Techno-commercial evaluation of bids, purchase recommendation, Contracting, Review of detailed design, site co-ordination, equipment inspection, testing, installation and commissioning. Project includes Reservoir Intake, Penstocks-3.5M Each, Penstock valves, Impulse turbines, Generator, Governors, control panels, switchgears, material handling equipments, substation, tail race system etc complete.

2x9MW Chunchunakate Hydro Electric Project India .


Preparation of detailed Tender document, invitation of bids, Techno-commercial evaluation of bids, purchase recommendation, Contracting, Review of detailed design, site co-ordination, equipment inspection, testing, installation and commissioning. Project includes river diversion, Penstock, Kaplan turbines, Generator, Governors, control panels, switchgears, material handling equipments, substation, tail race system etc complete.

Assessment of 90year old Gokak Hydro Electric Project and Up-gradation India

Study of the power plant existing system, (turbine, generators, controls etc) conducting the capacity testing of generator, up gradation of the turbine and auxiliaries and Governor and controls. Plant out put is increased by 25% using the same generators.

1991 1994 1991 1992 1992 1994

BOVING FOURESS LTD, INDIA Asst.Engineer. Engineer

Detailed design and engineering of Hydro turbines, Penstock valves, Gates, Trash rakes, Hydraulic control units, Governors, Compressed air system, C.W.System, Drainage and Dewatering system, Emergency Diesel Engines, Substations, surge vessels, Penstocks etc. Involved in design of various projects. Some them are listed below:

Your initials/page number 09/02/Staff No (note use of obliques, month and year only in date)

Key Project: 4x4MW Mallapur Hydro Power Plant India

Complete automatic plant having Horizontal Kaplan turbine Generator and auxiliaries.

15MW Dhansiri Hydro Electric power Plant India


Horizontal Kaplan turbine Generator and auxiliaries.

2.2MW Gokak Hydro Power Plant India

Complete automatic plant having Francis turbine Generator and auxiliaries.

6MW Moyangchu Hydro Electric power Plant India


Impulse (pelton wheel) turbine and generator unit.

EDUCATION AND PROFESSIONAL STATUS


B.E., Mechanical Engineering, from B.D.T College of Engineering, Davangere, University of Mysore, 1990, 1st Class with Distinction PG Diploma in Foreign Trade Management, From Institute of Export Management, Calcutta, 1993, Grade -B Project Management, from Indian Institute Of Science, Bangalore, 1996, Grade -B+

LANGUAGE SKILL
Kannada English Hindi Urdu : : : :

Mother tongue Spoken Fluent, written good, reading good. Spoken fluent; written good; reading good. Spoken Fluent,

PUBLICATIONS

New era in SWRO Projects : This brings out many issues related to Barge Mounted Sea water RO Plant.

Computer skills : Microsoft Project, Primavera P3,Expedition, MS Office -2007 and VB6

Engineering Software Tools: CAESAR-II, PV Elite, PDS, PDMS, AutoPlant, Bejack, Auto Pipe, Pipe Net, STAAD Pro, Auto CAD2007, CAD WORKS, MATHCAD, CHVAC etc.

TRAINING:
Responsible Leader Ship In house programme -IIM-Calcutta. Contract Management in House programme - IIM Bangalore. Effective Management of Export contracts Conducted by Indian Overseas Bank. Letter of credit, Law of Contract and claims handling Project Management Professional by PMCC Bangalore. SAFE Way to Work and HSE Training by Mott MacDonald Ltd HAZOP studies in process Industries Safety in Design

Address for Communication:


e-mail : hegdenagesh@rediffmail.com IN INDIA F-11, NANDARESIDENCY 1ST MAIN, PRASHANTI NAGAR EXTN, OFF-ISRO LAYOUT BANGALORE 560 078
Your initials/page number 09/02/Staff No (note use of obliques, month and year only in date)

IN UAE

ABU DHABI

INDIA PHONE: +91-80-26665295 +91-9945436777

+971-50-2207885

Your initials/page number 09/02/Staff No (note use of obliques, month and year only in date)