Luthra Institute of Manag Sub: Production and Operations Management Date: 28th March, 2013 Assignment II

Draw the network for the following activities and find the critical path an
EX- 21 Activity 1-2 1-3 1-5 2-3 2-6 3-4 4-7 5-6 6-7 Ex-26 Activity Duration(days) 1-2 9 1-4 4 1-3 7 2-5 7 3-4(dummy) 0 3-6 5 4-6 8 5-6 8 5-7 9 5-8 10 6-7 6 7-9 10 8-9 2 Duration(days) 3 4 14 10 5 4 6 1 1 Activity 1-2 1-3 1-4 2-3 2-5 3-5 4-5 EX-22 Duration(days) 4 2 5 7 7 2 5

Ex-27 Activity 1-2 1-3 2-4(dummy) 2-7 3-4(dummy) 3-8 4-5 5-6 6-7(dummy) 6-8(dummy) 7-9 8-9 9-10 10-11 Duration(days) 3 8 0 1 0 2 4 7 0 0 5 6 8 9

Ex-30 Activity Duration(days) 1-2 1-3 1-4 2-3(dummy) 3-4 3-5

Ex-31 Activity A B C D E F Immediate Predecessors Duration(days) ____ 10 ____ 9 A 9 A 8 B 7 B 11

4 7 6 0 5 7

4-5(dummy) 5-6 5-7 6-7

0 5 6 0

D,E

Activity A B C D E F G H I

Ex-34 Immediate Predecessors Duration(days) ____ 8 ___ 6 A 14 A 5 C 11 D 7 B 11 E,F 4 G 18

Activity A B C D E F G

Ex-35 Immediate Predecessors Duration(days) ___ 6 ___ 5 A 4 B 4 B 4 C,D 6 E 6

Activity A B C D E F G H I J K L

Ex-38 Immediate Predecessors Duration(days) __ 3 A 2 A 4 A 6 B 3 E 2 C 6 D 4 G 4 D 2 J 2 F,H,I 4

Activity A B C D E F G H

Ex-39 Immediate Predecessors Duration(days) ___ 4 ____ 7 A 3 A 3 B 2 B 2 D,E 2 F,G 3

S.R.Luthra Institute of Management Production and Operations Management Shift II, Sem II Class A2 ch, 2013 Assignment II Submission Date: 12th April'2013

owing activities and find the critical path and the duration of the project

Activity 1-2 1-3 1-4 2-4 3-4 4-5

Ex-23 Duration(days) 9 8 15 5 10 2

Activity 1-2 1-3 2-4 3-4 3-5 4-6 5-6

Ex-24 Duration(days) 2 8 4 1 2 5 6

Activity 1-2 1-3 1-4 2-5(dummy) 3-5 4-5(dummy) 5-6 5-7 5-8 6-7(dummy) 7-9 8-11 9-10 9-11 10-11 11-12 Ex-32 Duration(days) Activity A B C D E F

Ex-28 Duration(days) 4 3 3 0 2 0 1 2 3 0 3 5 2 4 0 2

Ex-29 Activity Duration(days) 1-2 4 1-3 3 1-5 2 2-3(dummy) 0 2-4 1 2-5 3 2-6 4 3-7 5 4-6(dummy) 0 5-7(dummy) 0 5-9 6 6-7 2 6-9 4 7-8 1 8-9 5

Immediate Predecessors Duration(days) ____ 12 ___ 10 A 5 A 6 B,C 16 D 16

Activity A B C D E F

Ex-33 Immediate Predecessors Duration(days) ___ 13 A 8 B 10 C 9 B 11 E 10

G H I J K

D,F E H G,I J

8 6 7 14 18

Duration(days)

Activity A B C D E F G H

Ex-36 Immediate Predecessors Duration(days) ___ 2 ___ 4 ___ 3 A 1 B 6 C 5 D,E 7 F,G 2

Activity A B C D E F G H I

Ex-37 Immediate Predecessors Duration(days) ___ 7.8 ___ 20 ___ 33 A 18 A 20 B 9 C 9.8 D 8 E,F 4

Duration(days)

Activity A B C D E F G H

Ex-40 Immediate Predecessors Duration(days) ___ 1 ___ 2 ___ 2 A,B 2 B,C 4 C 1 D 4 G,E,F 8

Ex-25 Activity Duration(days) Activity Duration(days) 1-2 30 6-7 7 1-3 7 7-8(dummy) 0 2-4 10 7-9 7 3-4(dummy) 0 8-9 12 3-10 30 8-10(dummy) 0 4-5 14 9-11 15 4-8 21 10-11 15 5-6 10