Académique Documents
Professionnel Documents
Culture Documents
GER-3954B
GE Power Systems
ii
Major Outage
X X X
X X X X X X X X
X X X
GT25553
condition. On-line monitoring and diagnostic techniques are limited in detecting potential problems, such as bar movement and vibration, component damage, copper dusting, coil distortion and foreign object damage (FOD). Many of these conditions could lead to a major failure of the equipment if left unresolved for a period of time. It is in these areas that in-situ
inspection supplements the capabilities of on line monitoring and diagnostics to reduce the risk of a failure. In-situ inspection should be used during minor outages as a tool for assessing the generator condition. The inspection results can be used to help plan the generator maintenance at future
Remote Access Camera Field Coil End Turns Stator Bars End Winding Support System Flux Shield Lower Frame Extension
GT25678
Common Problems
MAGIC RAC Wedge EL-CID RR Capac- Clearance Visual Visual Tapping NDE itance Meas.
tion insulation. Damaged insulation can result in circulating currents that can lead to core overheating and stator damage or even failure (Figure 6). EL-CID uses a low core excitation level (about 4% rated flux) to establish a magnetic field within the core. A highly sensitive, miniaturized sensing coil, or chattock, is used along the core surface to detect fault currents which will result from core insulation damage. A signal processor located in the control system computer is used to measure, record and report these faults. EL-CID has been proven to be especially valuable on machines where core loosening has been more prevalent.
although wedge tightess is a good indicator of clearance between the top stator bar and wedge, it can be misleading when the radial clearance exists elsewhere in the slot. As a result, GE recommends measuring the actual clearance between the stator bars and the bottom of the core slot through a stator clearance test. Clearance testing involves applying a force on each stator bar where it exits the core slot, and accurately measuring its radial movement. GE has developed specialized tooling to perform this test which protects against stator damage during the test. Measurements are made on both ends of the stator core (Figure 7). A map of the stator winding and each bars radial clearance is analyzed to determine the existence of, or potential for bar movement.
Circulating Current
Field Body
Retaining Ring
GT25775
Figure 8. Stator end winding viewed using GEs remote access camera
Test Area
Test Electrode
GT25552
locating the probe. GEs remote access camera is also used for positioning the probe and identifying its location. This system is being used successfully and provides results similar to those obtained during field out inspections.
access to the ID surface where eddy current testing is used to detect very small surface indications. Testing of the rings while installed on the field can also be performed, however, with less sensitivity to crack detection on the ID surface. Testing, similar to that performed with the field removed from the stator, can be completed on many units without removing the field. The NDE test equipment has been modified by miniaturizing the scanner assembly using the same signal processing system as that used with the field out. The system provides an ultrasonic test (0.050/1.27 mm crack detection threshold) on the ring ID and an eddy current test (0.005/0.127 mm crack detection threshold) on the ring OD.
Other Testing
There are several other tests and inspections recommended during minor and major outages in addition to those discussed. They include electrical testing of the stator and field windings and RTDs as well as hydraulic testing of water-cooled stator windings. A complete
Qualification Testing
Qualification testing involved performing an insitu inspection on an actual generator and comparing these results with those obtained through traditionally accepted inspection methods. MAGICs visual inspection system was the first to be qualified. The MAGIC inspection was performed on a GE generator at Georgia Powers Plant Vogtle, during a scheduled major inspection outage. An inspection report was written which documented the condition of the generator gas gap region as well as the collector endwinding region which was inspected using the remote access camera. A thorough visual inspection was then performed with the field out and the results were compared. GE found the in-situ inspection results were completely satisfactory with good image resolution, thoroughness and perspective. The field out inspection found no defects which had not been detected with the MAGIC visual inspection. MAGICs wedge tapping capability was developed by miniaturizing and remotely delivering an industry accepted wedge tapping device. This direction was taken so that wedge tightness data, whether taken with the field in or out, could be easily correlated. Data correlation is important to the long term trending and condition assessment. MAGICs wedge tap system was qualified on a large GE generator through comparison of in-situ test results with field out wedge tapping and hammer testing techniques. As a result of its wedge tapping development, GE added the ability to listen to the tap test while in progress. This information is very useful in assuring the test is being performed
Qualification Efforts
Changing an Industry Mindset
Generator inspection for years consisted of a minor outage every 2 1/ 2 years and a major outage with the field removed every five years. This practice proved to be quite successful in maintaining a high level of reliability of the generator fleet. Deregulation is causing the power generation industry as a whole to rethink its philosophy on equipment maintenance and OEMs, and utilities and insurers alike need to evolve to meet the needs of this new marketplace. In-situ inspection of generators is one way GE has evolved to meet these demands, and GE needs to work with customers and their insurers to properly apply this technology. In-situ inspection will not be considered a complete success unless it can provide an inspection with the similar accuracy, sensitivity and thoroughness of a field removed inspection. In-situ inspection must not bring with it a significant increase in the risk of failure over traditional inspection techniques. Many GE customers with generators at nuclearpowered plants are required by their insurers to remove the generator field at a specified interval to complete a major inspection. GE is currently working with several major insurers to reconsider this policy as a result of in-situ inspection technology. The first step toward replacing traditional inspections with those performed in-situ is qualification of the inspection techniques. GE has completed several qualification tests and is in the process of documenting
10
Qualification Report
A detailed qualification report will be prepared to document the results and provide the data needed to demonstrate the validity of in-situ
11
Table 2. Inspection time savings comparison Performing an in-situ inspection during a minor outage prior to a planned major outage can help determine the necessity and scope of the major outage. The outage may be postponed altogether if the generator is found in good condition. If problems are found, the information gathered during the inspection can be used to make preparations for repair at the next outage. These preparations include planning the repair, identifying labor and material needs and developing contingency plans. When it comes to generator maintenance, experience has shown that preparation and planning are critical to effieicntly executing an outage. Inspection cycle through use of in-situ techniques is achieved by greatly reducing the level of generator disassembly required to complete the inspection. Reducing the level of disassembly has a number of benefits beyond reduced cycle time. Cost savings result from reduced disassembly and reassembly labor, repair and planning. Not removing the field from the generator also frees up overhead crane availability for use on other parts of the outage. The total cost of field removal and reassembly is reported at $100,000 to $250,000 for fossil plants and $250,000 to $500,000 for nuclear plants. The cost associated with partial disassembly to allow in-situ inspection varies with the scope of the inspection but, generally, runs about 1/3 the cost of complete disassembly. Table 3 compares the cost of a traditional vs. in-situ inspection. Another economic benefit of in-situ inspection is the reduction of consequential generator damage as a result of the outage. Rotor removal requires uncoupling the turbine-generator shafts; careful disassembly of stator endshields on both ends of the generator; removal of the bearings, hydrogen seals, oil deflectors and exciter assemblies; and the skillful reassembly and realignment of these same components. Improper endshield reassembly may result in oil ingestion problems, expensive and time consuming oil cleanup procedures, undesirable lubrication of the armature slot and endwinding restraining systems, increased armature motion, and accelerated armature insulation wear. (Refer to TIL 1098-3R2 for additional information on the adverse effects of oil ingestion). Rotor removal incurs risk of damage to the precision components of the hydrogen seal oil assemblies, and requires the heavy lifting and temporary warm, dry storage of the rotor. The problems or damage resulting from disassembly can lead to very costly repairs. For this reason, the best policy is to minimize disassembly.
12
6 4 6 1000/1500 2 5 2 200/300 Traditional Inspection ($K) In-Situ Inspection ($K) SAVINGS ($K)
$125 $20 $175 $160 $480 $40 $50 $60 $100 $250 Total Cost $480 $250 $230
Traditional
Savings of $230,000
In-Situ In Situ
Generator Inspection Type Footnotes: 1. Generator Inspection Scope Included Visual and Wedge Tightness Inspection. Electrical and Leak Testing Cost Not Included. 2. Disassembly and Test Costs Used for a Large Steam Turbine Generator at a Nuclear Site.
13
Conclusions
The power generation industry is undergoing major changes requiring power producers, OEMs and insurers to adapt. One way GE has responded to these market changes is through the development of tools that enable in-situ inspection of generators. In-situ inspection offers an acceptable, low cost alternative to the traditional field out generator inspection in many cases. GE has been and will continue to work within the industry to gain acceptance of in-situ inspection techniques. GE is presently working on enhancing the capabilities of its insitu inspection service and expanding the application to smaller generators. In-situ inspection will play an increasing role in reducing power producers cost of generation.
2.5
MINOR Visual
5
MAJOR Visual Wedge ELCID IN-SITU Wedge
10
Traditional
MAGIC In-Situ
IN-SITU Visual
NOTES: Electrical and Hydraulic testing continue at recommended intervals NDE testing and TILs may require rotor removal for completion
GT25551
14
15
16