Vahan Gevorgian, NREL Clinton T. Hedrington, VIWAPA June 15-16, 2010 St. Thomas, USVI
60% by 2025
History of Submarine Power Transmission Submarine power transmission has been around for more than a century.
Early usesisolated offshore facilities, lighthouses, etc. Mid 20th centurypower supply of near-shore islands Since 1960sconnection of autonomous grids for better stability and resource utilization, LCC HVDC Modern daysoffshore wind, longer-distance power transmission, network interconnections, increased number of islands connected to mainland grid, HVDC light, etc.
Mercury Arc Valves (Source: Wikipedia)
2025
Europe
Rest of the world Japaninterisland (50 km HVDC) Philippinesinterisland (21 km HVDC) New Zealandinterisland (40 km, HVDC) AustraliaTasmania (290 km, HVDC) S. KoreaCheju Island (100 km, HVDC)
2025
2025
Disadvantages
High cost of power converters Complexity of control, communications, etc. Maintenance cost higher than for AC; spare parts needed HVDC circuit breakers reliability issue
Leading the Caribbean to a sustainable energy future. 60% by Innovation for Our Energy Future 2025
Source: Prysmian
Source: ABB
Extruded cables for DC VSC technology (HVDC light) - 300 kV, 1000MW Mass impregnated paper cables for DC - 600kV, 2000MW bi-pole HVDC ultra deep technology 1600 m (2000m possible)
Source: ABB
2025
Others 18%
Anchors 18%
7000 circuit km of submarine power cables 49 faults reported during 1990-2005 Only 4 faults identified as internal
Source: Submarine Power Cables by Thomas Worzyk, Springer, 2009 (page 212)
2025
2025
Oahu Wind Integration and Transmission Study Hawaii Clean Energy Initiative (HCEI)October 2008
Multiyear initiative 70% clean energy by 2030 (40% by renewables) Agreement between state of Hawaii and HECO
400 MW wind from Lanai and/or Molokai to Oahu (Stage 1) 100 MW of Oahu on-island wind (Stage 2)
AWS Truewind and NREL wind and solar data HECO study of generator flexibility
Leading the Caribbean to a sustainable energy future.
9
2025
10
2025
Costs (HVAC)
AC cables AC substations Sea/land cable transition Fixed compensation reactors Other components
Costs (HVDC)
DC cables DC converter stations Sea/land cable transition Other components DC losses (20 years)
Only 6 selected for detailed simulation (AC and DC) and RFQ
Molokai 200 MW
Stage 1 200 MW Pole Lanai Maui 200 MW Iwilei 200 MW Pole - Stage 2
11
2025
HVAC Simulations
138 kV bus
Operation due Spontaneous breaker-open 70 mile AC to overvoltage operation undersea cable protection
34.5 kV bus
600 V bus
230 kV Bus
Receiving end
Fiberoptic link
12
2025
HVDC Simulations
LVRT/HVRT limits Voltage (pu)
Detailed models of VSC in PSCAD Traditional control strategy Sending endfrequency and AC voltage control Receiving endAC reactive power DC bus voltage control Contingency and protection scenarios simulations
Time (sec)
13
2025
Final report goes public in July 2010. Contains conclusions, detailed cost and technical analysis for all preferred options.
Leading the Caribbean to a sustainable energy future.
14
2025
15
2025
16
2025
2025
18
2025
Questions?
Source: www.nexans.com
19