Vous êtes sur la page 1sur 2

Project No.

DAILY REPORT
by Resident Lead Consultant
P O Box 1378 RUWI, Post Code 112 Telephone: 2460 1503 / 1509 / 1259 Fax: 24696066 e-mail: handp@omantel.net.om

11K5
Issue Date

AIRPORT TERMINAL BUILDINGS OXY Mukhaizna

03 April 2013

2 pages Ref.: attached photographs taken today Comments/Replies Arrivals bitumen painting of ground crossbeams - backfill/compacting for longitudinal g/beams Departure grids A-J - Formwork for columns starters - backfill/compaction in areas without u/g services Departure grids D-J de-shutter ground beams - application of bitumen paint - blinding slabs for column footings of covered walkway ERT rebar/formwork of remaining 7 column bases GSE shaded bays rebar/formwork for stub columns Arrivals bitumen painting of ground crossbeams - backfill/compacting for longitudinal g/beams Departure grids A-J concrete pour of column starters - backfill/compaction in areas without u/g services Departure grids D-J application of bitumen paint - blinding slabs for column footings of covered walkway ERT rebar/formwork of remaining 7 column bases GSE shaded bays concrete pour of stub columns Not yet issued, pending approval of Galfars offer for the Sheel&Core Contract Prior to formal issue of W.I. 371 -Shell&Core-, Galfar is to complete all ground beams and backfill/compaction by 10/04/2013, then revised Construction Programme in accordance with W.I. 371 will be in place. To be clarified with OXY-HO at site on 09/04/2013 Galfar to accept site instructions from authorized personnel only, to be nominated shortly.

Status on Site General Issues 1) Scheduled work 02/04/2013

2) Scheduled work today

3) New Work Instruction No. 371 4) Site Meeting 02/04/2013

Action Galfar not started complete commenced complete ongoing commenced commenced completed Galfar not started done ongoing ongoing completed ongoing completed OXY-HO Galfar

5) MEP first-fix 6) Chain of command

OXY, Huckle OXY, Huckle

Architectural 7) Sewage tank 8) Water tank Structural 9) Revisions MEP 10) X-ray scanning cable duct Prepared by:

Drawing with setting-out dimensions issued to OXY-HO for approval. Drawing with setting-out dimensions issued to OXY-HO for approval. Issued to OXY-HO for approval To be coordinated by MEP-first fix Contractor to be appointed by OXY-HO Herbert Krause HK Resident Lead Consultant Huckle and Partners LLC

OXY-HO OXY-HO

OXY-HO OXY-HO Date: 03 April 2013

Distribution: OXY-HO various, OXY-Muk various, Huckle-HO, Oman Designers, Hoehler-Partner, Galfar E&C various,

Site form

Project No.

DAILY REPORT
by Resident Lead Consultant
P O Box 1378 RUWI, Post Code 112 Telephone: 2460 1503 / 1509 / 1259 Fax: 24696066 e-mail: handp@omantel.net.om

11K5
Issue Date

AIRPORT TERMINAL BUILDINGS OXY Mukhaizna

03 April 2013

2 pages

Site form