Task Name IGW Project Contract Effective Date/LC Open date Survey , Design & Site ready confirma Survey & Design Network Planning As build Drawing Manufacturing Shipment Delivery of Goods in Warehouse Equipments up to site Hardware Installation MSOFTX3000 UMG8900 R8 SG7000 NE40E-X3 iManager U2000(V100R003) Quidway S9300 Terabit Routing Switch S3300 Series Ethernet Switches Eudemon 1000E Firewall OptiX OSN 3500(V100R008) iManager M2000 SANEX DDF ODF Power for Central Room( 220V 50Hz -4 Software Comissioning MSOFTX3000 UMG8900 R8 SG7000 NE40E-X3 Quidway S9300 Terabit Routing Switch S3300 Series Ethernet Switches Eudemon 1000E Firewall iManager U2000(V100R003) OptiX OSN 3500(V100R008) iManager M2000 SANEX System Integration Task

Duration 100 days 1 day 8 days 8 days 6 days 2 days 25 days 25 days 2 days 2 days 28 days 6 days 6 days 6 days 6 days 5 days 5 days 3 days 3 days 3 days 5 days 5 days 4 days 5 days 10 days 5 days 5 days 5 days 5 days 3 days 3 days 3 days 3 days 2 days 3 days 2 days 3 days

Start Mon 1/2/12 Mon 1/2/12 Tue 1/3/12 Tue 1/3/12 Tue 1/3/12 Thu 1/5/12 Tue 1/3/12 Tue 2/7/12 Tue 3/13/12 Thu 3/15/12 Mon 3/19/12 Mon 3/19/12 Mon 3/19/12 Mon 3/19/12 Tue 3/27/12 Tue 3/27/12 Tue 3/27/12 Tue 3/27/12 Tue 3/27/12 Tue 3/27/12 Sun 4/1/12 Sun 4/8/12 Sun 4/15/12 Thu 4/19/12 Thu 4/26/12 Thu 4/26/12 Thu 4/26/12 Thu 4/26/12 Thu 5/3/12 Thu 5/3/12 Thu 5/3/12 Thu 5/3/12 Thu 5/3/12 Thu 5/3/12 Mon 5/7/12 Mon 5/7/12 Wed 5/9/12 Milestone Summary Project Summary

Finish Sun 5/20/12 Mon 1/2/12 Thu 1/12/12 Thu 1/12/12 Tue 1/10/12 Sun 1/8/12 Mon 2/6/12 Mon 3/12/12 Wed 3/14/12 Sun 3/18/12 Wed 4/25/12 Mon 3/26/12 Mon 3/26/12 Mon 3/26/12 Tue 4/3/12 Mon 4/2/12 Mon 4/2/12 Thu 3/29/12 Thu 3/29/12 Thu 3/29/12 Thu 4/5/12 Thu 4/12/12 Wed 4/18/12 Wed 4/25/12 Wed 5/9/12 Wed 5/2/12 Wed 5/2/12 Wed 5/2/12 Wed 5/9/12 Mon 5/7/12 Mon 5/7/12 Mon 5/7/12 Mon 5/7/12 Sun 5/6/12 Wed 5/9/12 Tue 5/8/12 Sun 5/13/12

1st Half Jan

Feb

Mar

Apr

May

Jun

2nd Half Jul

External Tasks External Milestone Deadline


Page 1

IGW Project Implementation Schedule

Split Progress

** Project implementation will based on Government rules & Regulation

ID 38 39

Task Name Provisional Acceptance Test Cutover

Duration 3 days 2 days

Start Mon 5/14/12 Thu 5/17/12

Finish Wed 5/16/12 Sun 5/20/12

1st Half Jan

Feb

Mar

Apr

May

Jun

2nd Half Jul

Task
IGW Project Implementation Schedule

Milestone Summary Project Summary


Page 2

External Tasks External Milestone Deadline

Split Progress

** Project implementation will based on Government rules & Regulation