2nd question They were asking if bend tests were acceptable On the PQR, all of the results were below 3 mm
Choices were abcdYes No No need for bend test Yes. But specimen # 1 and are rejected.
Third question Thickness range was mentioned in the WPS abcdYes No Yes, but not the right range Dont remember
If RBI is not being used, the interval between piping inspections shall reviewed when changing service from: abcdAnhydrous to Hydrofluoric acid Natural gas to hydrogen Natural gas to Hydrofluoric acid
Light letter B on the radiography film indicates: Sufficient back scatter and film is acceptable Insufficient backscatter and film is rejected Insufficient backscatter and film is acceptable Sufficient backscatter and film is rejected
During radiography, when source side film is not possible, a film side source is used with the following letter/s on the film abcdF.S F B S.S
Which of the following electrodes are suitable for GMAW GTAW? abcdE 7018 ER707-E Dont remember Dont remember-
Which of the following valves has will never encounter pigging problems abcdGate Ball Slide Dont remember the forth one
When calibrating UT equipment, the difference in temperature between the probe and part being examined shall not be more than _____ abcdDont remember Dont remember Dont remember Dont remember
You can start coating activities prior to the following tests except: Flexibility test Initial service test Leak test Hydrotest
Service conditions have been changed for one the piping. Rate of corrosion has to determined no longer than a- One year from the time of installation b- Three months c- Rate of corrosion need not to be revised d- 6 months
abcd-
When you notice a corroded support that is attached to one of the piping, and it is required to lift the pipe to verify the corrosion, what is your correct action a- Take the line out of service b- Ask for a detailed lifting procedure c- Lift pipe immediately to check the corrosion d- Dont remember
During a hydrotest, the relief valve has opened when the pressure reached the set point of the relief valve, what is your correct action abcdReduce the pressure Do nothing Review the procedure Replace the relief valve
The acceptable frequency to check the magnetizing power of a yoke is abcdEvery year Before and after use Every two years Every six months
Mandatory Optional
Same requirements as primary process piping
Every 10 years
Threaded connections associated with machinery and subject to fatigue damage should be inspected
Every six month Every one year Periodically Treated as other normal piping circuits
Things that normally found on flanges: abcdTemperature range Manufacturer name and marking Flange classification size
During inspection, you found CUI with a damaged insulation; the piping was class II, the allowed percentage of insulation remove is abcd100% 50% 33% Up to the inspector
Service conditions have been changed for one the piping. Determining the probable rate of corrosion from which the remaining wall thickness at the time of the next inspection can be a- Left as is b- Estimated from similar material in comparable service and comparable operating
Computation for MWAP is as follows: abcdActual thickness minus twice the estimated corrosion loss Actual thickness minus the estimated corrosion loss Actual thickness minus corrosion rate times RL Actual thickness minus twice corrosion rate times RL
During a routine inspection, you notice a bulge in a pressure vessel that is attached to a piping. Your immediate action is Evaluate the case as per API 579 Evaluate the case as per ASME B31.3 Report the case to operation Take both the vessel and the piping out of service for evaluation
There was no question about thermal expansions All short term, long term, and remaining life questions were closed book
I also remember many questions, but they need to be organized in my brain. So when ready, I will forward them to you.