FIDIC Conditions Selection Criteria

Straight Forward Contract

Yes

Short Form of Contract


(Green Book)

Yes

Conditions of contract for


Construction
(Red Book)

No

Designing is in the scope of


Employer
No

Contractor's Design
Plant and/or High Unforeseen
Risks

Maintenance in
Contractor's Scope

Yes

No
No

Fixed Price Lump sum


Little Employer Involvement &
low Unforeseen risks
No

Yes

Yes

Conditions of contract for


Design Build & Operate
Projects
(Gold Book)

Conditions of Contract for


Plant and Design Build
(Yellow Book)
Conditions of Contract for
EPC/ Turnkey Projects
(Silver Book)
Employer's Requirements Modified FIDIC/ Other
Conditions