Académique Documents
Professionnel Documents
Culture Documents
Week No : Date :
TW-018 13-May-13
NEXT WEEK 20 -May - 2013 To 26 -May - 2013 Q'TY Description Unit Plan
Procurement
Procurement
10,000.00 1 1 1 2 6 1 1 1 3 B B1 B2 B3 B4 B5 B6 C QA/QC Daily fabrication inspection Steel Structure Inspection Fabrication piping 800HT , 304H Insulation Inspection 03D030 Rediographic test for Piping 800HT after PWHT Inspection Fabrication piping 800HT , 304H Final Inspection Check List and Release on field steel str Construction Installation Scaffolding for 03R003 Installation Steel Sturcture Stair Tower for 03R003 Installation Pipe 66" for Reactor 03R003 Installation pipe 24",28" for 304H and 800HT Fit-Up and welding Skirt 800HT for Support pipe Fit-Up and welding Skirt 800HT for pipe Installation Insulation Equipment 03E006A M3 KG DB Joint Joint Joint Ea 200 5,000.0 5,000.0 66.0 4.0 2.0 2.0 1.0 KG Joint Ea Joint Joint set 10,000.00 6 1 3 3 1
B10 Inspection Leveling and Centering Equipment 05X007 C C1 C2 C3 Construction Total piping quantity Shop fabrication & welding Field fabrication & welding -Field fabrication & welding -Tie-ins C4 C5 C6 Field installation work Pressure test & flushing Steel structure Shop fabrication Package KG DB DB DB 2,688.0 752.0 2,107.0 449.0 449.0 2,859.0 17 334,162.7 30,000.00 12,000.00 -18000.00 330,000.0 331,560.7 1,560.70 2,601.96 94.0 94.0 0.00 752.0 752.0 0.00 C C1 C2 C3 C4 C5 C6 C7 C8 C9 Construction Fabrication Steel Structure Installation Scaffolding for 03R003 Installation Insulation Equipment 03E014 Installation Insulation Equipment 02E003A Installation Insulation Equipment 03E006A Installation Steel Sturcture 03R003 Leveling and Centering Equipment 05X007 Modify Bracing Steel Structure Equipment 04E014 Installation Line 66" for Reactor 03R003
KG M
3
4,000.0 300 1.0 1.0 1.0 3,000.0 3.0 3.0 2.0 1.0 2.0 6.0
C1 C2 C3 C4 C5 C6 C7 C8
C10 Installaton Temporary for Line 66" C11 Fit-Up and welding Skirt 800HT for Support pipe C12 Fit-Up and welding pipe 304H ,800HT
2. Progress S-curve
TECHNIP ENGINEERING (THAILAND) CO., LTD. (EPCm Contractor) Checked By :
...... ( ........) Date : ... / .... / ..
Page 1 of 1