Vous êtes sur la page 1sur 64

Tiltable Pole Mast DKP206 and DKP210

USER'S GUIDE
M210315en-B March 2003

PUBLISHED BY Vaisala Oyj P.O. Box 26 FIN-00421 Helsinki Finland Phone (int.): +358 9 8949 1 Fax: +358 9 8949 2227

Visit our Internet pages at http://www.vaisala.com/ Vaisala 2003 No part of this manual may be reproduced in any form or by any means, electronic or mechanical (including photocopying), nor may its contents be communicated to a third party without prior written permission of the copyright holder. The contents are subject to change without prior notice.

Please observe that this manual does not create any legally binding obligations for Vaisala towards the customer or end user. All legally binding commitments and agreements are included exclusively in the applicable supply contract or Conditions of Sale.

_________________________________________________________________________________

Table of Contents
CHAPTER 1

GENERAL INFORMATION............................................................................ 5 About This Manual ................................................................... 5 Contents of This Manual ....................................................... 5 Version Information ............................................................... 6 Related Manuals ................................................................... 6 Feedback............................................................................... 6 Safety......................................................................................... 6 General Safety Considerations ............................................. 6 Product Related Safety Precautions ..................................... 7 ESD Protection...................................................................... 8 Warranty .................................................................................... 9 Technical Support .................................................................... 9
CHAPTER 2

PRODUCT OVERVIEW................................................................................ 11 Introduction to DKP206 and DKP210 ................................... 11 Foundation Set .................................................................... 14 Guy Wires............................................................................ 15 Lightning Rod ...................................................................... 16 Winch (Optional).................................................................. 16 Product Nomenclature ........................................................ 17
CHAPTER 3

INSTALLATION............................................................................................ 19 Siting Criteria .......................................................................... 19 Ambient Measurements ...................................................... 19 Tilting Direction.................................................................... 21 Soil Evaluation..................................................................... 21 Site Preparation...................................................................... 21 Power Supply and Communication Lines ........................... 21 Tools Required for Installation ............................................. 22 Unpacking Instructions ......................................................... 22 Inspecting the Delivery........................................................ 22 Contents of the Delivery...................................................... 22 Foundation.............................................................................. 25 Soil and Frost Conditions .................................................... 25 Orientation of the Mast........................................................ 25 Concrete Foundations ......................................................... 28 Making a New Concrete Block....................................... 29 Using an Existing Concrete Block.................................. 32 Assembling the Mast ............................................................. 33 Work Order.......................................................................... 33

VAISALA_________________________________________________________________________ 1

User's Guide _______________________________________________________________________

Installing the Pedestal Tube ................................................34 Connecting the Lowest Mast Tube to the Pedestal Tube .....................................................................36 Connecting the Lifting Rod to the Mast ...............................37 Connecting the Guy Wire Set to the Mast ...........................38 Assembling the Mast Tubes ................................................39 Assembling the Lightning Rod.............................................39 Connecting the Grounding Cable to the Insulated Guy Wire..............................................................................41 Routing the Device Cables ..................................................42 Erecting the Mast....................................................................43 Installing and Using the Winch ............................................43 Securing the Hinge ..............................................................46 Connecting the Guy Wires to the Concrete Blocks .............46 Equipment Grounding and Lightning Protection................50 Equipment Grounding..........................................................53 Grounding of the Lightning Rod ..........................................55
CHAPTER 4

MAINTENANCE............................................................................................57 Regular Maintenance..............................................................57 Tilting the Mast .......................................................................57 Disconnecting and Securing the Guy Wire .........................57 Using the Winch ..................................................................58 Tilting the Mast Manually.....................................................58 Erecting the Mast....................................................................59
CHAPTER 5

TECHNICAL DATA.......................................................................................61 Specifications .........................................................................61

2 _____________________________________________________________________M210315en-B

_________________________________________________________________________________

List of Figures
Figure 1 Figure 2 Figure 3 Figure 4 Figure 5 Figure 6 Figure 7 Figure 8 Figure 9 Figure 10 Figure 11 Figure 12 Figure 13 Figure 14 Figure 15 Figure 16 Figure 17 Figure 18 Figure 19 Figure 20 Figure 21 Figure 22 Figure 23 Figure 24 Figure 25 Figure 26 Figure 27 Figure 28 Figure 29 Figure 30 Figure 31 Figure 32 Figure 33 Figure 34 Figure 35 Figure 36 Figure 37 Figure 38 Figure 39 Figure 40 Figure 41 Figure 42 Figure 43 Figure 44 Figure 45 Figure 46 Figure 47 Figure 48 DKP210 Mast Dimensions (in mm) .......................................... 12 DKP206 Mast Dimensions (in mm) .......................................... 13 Foundation Set for DKP210 and DKP206 Masts ..................... 14 Guy Wires Set .......................................................................... 15 Passive Lightning Rod with the Cable and the Holders ........... 16 Winch (Optional)....................................................................... 16 Recommended Mast Location in Open Area ........................... 20 Recommended Mast Length on Top of a Building ................... 20 Contents of the Mast Delivery (Part 1) ..................................... 23 Contents of the Mast Delivery (Part 2) ..................................... 24 DKP210 Mast Orientation......................................................... 26 DKP206 Mast Orientation......................................................... 27 Main Mast Block and Orientation Plate (Dimensions in mm) ................................................................. 28 Concrete Block for Guy Wire (Dimensions in mm) .................. 29 Reinforcement for the Concrete Blocks ................................... 30 Foundation Assembly for the Mast Base ................................. 31 Foundation Assemblies for a New Concrete Block .................. 31 Accessories for Existing Concrete Block Installation ............... 32 Pedestal Tube Alignment to North-South Direction ................. 34 Pedestal Tube Attachment ....................................................... 34 Pedestal Tube Adjustment with Water Level ........................... 35 Axle for Hinge ........................................................................... 36 Hinge Bolt Installation............................................................... 36 Lifting Rod Installation Accessories ......................................... 37 Lifting Rod Clamp Attachment ................................................. 38 Guy Wire Attachment ............................................................... 38 Alignment of the Mast Tubes.................................................... 39 Lightning Rod Installation to the Mast ...................................... 40 Dimensions (in mm) for Lightning Rod Assembly on the Mast............................................................................... 40 Alignment of the Insulated Guy Wire and the Lightning Rod Holders ..................................................................................... 41 Lightning Rod Cable Attachment ............................................. 42 Winch Installation ..................................................................... 43 Securing Clamp of the Winch................................................... 44 Lower Cable Lead .................................................................... 44 Attaching the Hook ................................................................... 45 Bolts and Washers for Securing the Hinge .............................. 46 Guy Wires................................................................................. 47 Connecting the U-bolt to the Eye Bolt ...................................... 48 Guy Wire 1 Attachment ............................................................ 48 Securing the Guy Wires ........................................................... 49 Installing Cable Shrouds .......................................................... 49 Location of the Grounding Rods and an Optional Grid, the Arrow Points to the Mast Tilt Direction ..................................... 51 Ground Rod Installation............................................................ 52 Installing the Grounding Bar..................................................... 53 Connecting the Grounding Cables to the Bar .......................... 54 Grounding Cable Protection ..................................................... 55 Grounding of the Lightning Rod ............................................... 56 Tilted Mast with Tilting Support ................................................ 58

VAISALA_________________________________________________________________________ 3

User's Guide _______________________________________________________________________

List of Tables
Table 1 Table 2 Table 3 Table 4 Table 5 Table 6 Manual Revisions .......................................................................6 Product Nomenclature for DKP206 Masts ...............................17 Product Nomenclature for DKP210 Masts ...............................17 Examples of Soil Resistivities, Ohm-Meters.............................52 DKP210 Specifications .............................................................61 DKP206 Specifications .............................................................62

4 _____________________________________________________________________M210315en-B

Chapter 1 _________________________________________________________ General Information

CHAPTER 1

GENERAL INFORMATION

This chapter provides general notes for the product.

About This Manual


The purpose of this manual is to describe and give guidelines how to construct the foundations for the DKP206 and DKP210 masts and how to install the masts.

Contents of This Manual


This manual consists of the following chapters: - Chapter 1, General Information, provides general notes for the product. - Chapter 2, Product Overview, introduces the DKP206 and DKP210 mast features, options, and the product nomenclature. - Chapter 3, Installation, provides instructions for installing the DKP206 and DKP210 masts. - Chapter 4, Maintenance, provides information that is needed for the basic maintenance of the DKP206 and DKP210 masts. - Chapter 5, Technical Data, provides the technical data of the DKP206 and DKP210 masts.

VAISALA_________________________________________________________________________ 5

User's Guide _______________________________________________________________________

Version Information
Table 1
Manual Code M210315en-A M210315en-B

Manual Revisions
Description The first version of the DKP206 and DKP210 Tiltable Pole Mast User's Guide. This manual, the second version of the DKP206 and DKP210 Tiltable Pole Mast User's Guide.

Related Manuals
For sensor and other equipment specific foundation and installation information, refer to the separate instruction manuals that are supplied with the equipment.

Feedback
Vaisala Customer Documentation Team welcomes your comments and suggestions on the quality and usefulness of this publication. If you find errors or have other suggestions for improvement, please indicate the chapter, section, and page number. You can send comments to us by e-mail: manuals@vaisala.com

Safety General Safety Considerations


Throughout the manual, important safety considerations are highlighted as follows:

WARNING

Warning alerts you to a serious hazard. If you do not read and follow instructions very carefully at this point, there is a risk of injury or even death.

CAUTION

Caution warns you of a potential hazard. If you do not read and follow instructions carefully at this point, the product could be damaged or important data could be lost.

6 _____________________________________________________________________M210315en-B

Chapter 1 _________________________________________________________ General Information

NOTE

Note highlights important information on using the product.

Product Related Safety Precautions


This section lists general precautions related to the mast installation. To ensure your safety, you must also read the device specific safety precautions that are listed in the corresponding field device manuals.

WARNING

For safety reasons, do not install the mast alone.

WARNING

For safety reasons, do not install the mast when the wind speed is over 7 m/s.

WARNING

Always wear a safety helmet during mast installation.

WARNING

Be careful when erecting the mast. See that there are no power lines or other obstacles above the mast.

WARNING

Secure the mast properly to prevent it from falling. Tighten all the adjustment screws securely.

WARNING

Be sure that there are no persons under the mast during erecting the mast.

WARNING

When erecting the mast with the winch, avoid touching the wire with bare hands. Do not try to guide the wire.

VAISALA_________________________________________________________________________ 7

User's Guide _______________________________________________________________________

WARNING

To minimize shock hazard, the instrument chassis and cabinet must be connected to an electrical ground. The power cable must either be plugged into an approved electrical outlet or the instrument must be carefully grounded to a low-resistance safety ground.

WARNING

Do not operate the equipment in an explosive environment, for example, in the presence of flammable gases or fumes.

WARNING

Do not attempt internal service or adjustment unless another person, capable of rendering first aid and resuscitation, is present.

WARNING

Operating personnel must not remove instrument covers. Component replacement or internal adjustments must be made by qualified maintenance personnel. Do not replace components with the power cable connected. Under certain conditions, dangerous voltages may exist for some time even with the power cable disconnected. To avoid injuries, disconnect power and discharge circuits before touching them.

CAUTION

Do not install substitute parts or modify the unit. Improper modification can damage the product or lead to malfunction. Contact Vaisala for repairs to ensure that safety features are maintained.

ESD Protection
Electrostatic Discharge (ESD) can cause immediate or latent damage to electronic circuits. Vaisala products are adequately protected against ESD for their intended use. However, it is possible to damage the product by delivering electrostatic discharges when touching, removing, or inserting any objects inside the equipment housing.

8 _____________________________________________________________________M210315en-B

Chapter 1 _________________________________________________________ General Information

To make sure you are not delivering high static voltages yourself: - Handle ESD sensitive components on a properly grounded and protected ESD workbench. When this is not possible, ground yourself to the equipment chassis before touching the boards. Ground yourself with a wrist strap and a resistive connection cord. When neither of the above is possible, touch a conductive part of the equipment chassis with your other hand before touching the boards. - Always hold the boards by the edges and avoid touching the component contacts.

Warranty
For certain products Vaisala normally gives a limited one year warranty. Please observe that any such warranty may not be valid in case of damage due to normal wear and tear, exceptional operating conditions, negligent handling or installation, or unauthorized modifications. Please see the applicable supply contract or conditions of sale for details of the warranty for each product.

Technical Support
For technical questions, contact the Vaisala technical support: E-mail Telephone Fax helpdesk@vaisala.com +358 9 8949 2789 +358 9 8949 2790

VAISALA_________________________________________________________________________ 9

User's Guide _______________________________________________________________________

This page intentionally left blank.

10 ____________________________________________________________________M210315en-B

Chapter 2 ___________________________________________________________ Product Overview

CHAPTER 2

PRODUCT OVERVIEW

This chapter introduces the DKP206 and DKP210 mast features, options, and the product nomenclature.

Introduction to DKP206 and DKP210


DKP206 and DKP210 are designed for different kinds of weather station application areas, such as, airfields as well as synoptical and climatological networks. The height of DKP206 is 6 m and that of DKP210 is 10 m. DKP206 and DKP210 are tiltable masts, that is, they can easily be tilted up and down by one person when installing and maintaining the various devices on the mast. Also special attention has been paid to easiness and quickness of the mast installation. The mast is designed to withstand high wind conditions, up to 50 m/s of maximum wind speed with one standard set of guy wires. With an additional set of guy wires, the maximum wind speed can be up to 75 m/s. The plate of the pedestal tube is made of stainless steel with a powder coating resistant to corrosion. The material of the lifting rod and mast tubes is anodized aluminum. Other mast constructions and mounting accessories are made of stainless steel. The mast can be either painted white or aviation-painted white/orange.

VAISALA________________________________________________________________________ 11

User's Guide _______________________________________________________________________

0303-019

Figure 1

DKP210 Mast Dimensions (in mm)

12 ____________________________________________________________________M210315en-B

Chapter 2 ___________________________________________________________ Product Overview

NOTE

50 mm 1.97 in. 60 mm 2.36 in. 75 mm 2.95 in. 101.6 mm 4 in. 1 890 mm 74.4 in 2 353 mm 92.6 in. 4 900 mm 192.9 in. 5 475 mm 215.5 in. 6 000 mm 236.2 in. 7 000 mm 275.6 in. 7 450 mm 293.3 in. 9 000 mm 354.3 in. 10 000 mm 393.7 in. 11 065 mm 435.6 in.

0303-020

Figure 2

DKP206 Mast Dimensions (in mm)

VAISALA________________________________________________________________________ 13

User's Guide _______________________________________________________________________

Foundation Set
The foundation set includes all the necessary installation accessories both for a new and an existing concrete block.

0303-021

Figure 3

Foundation Set for DKP210 and DKP206 Masts

The following numbers refer to Figure 3 above: 1 2 3 4 5 6 7 8 9 = = = = = = = = = Nuts and washers for the foundation bolts Orientation plate for the mast base Eye nuts for the guy wires Wedge bolts for an existing concrete block Plates with the nut for the guy wire blocks Square plate for the mast base Foundation bolts Bar for installing the wedge bolts Key piece for the wedge bolts

14 ____________________________________________________________________M210315en-B

Chapter 2 ___________________________________________________________ Product Overview

Guy Wires
One set of guy wires is delivered in the basic set. The top fastener of the guy wires is mounted at the uppermost tube of the mast during the installation. The basic delivery contains one set of guy wires and the accessories as shown in Figure 4 below.

0207-090

Figure 4

Guy Wires Set

The following numbers refer to Figure 4 above. 1 2 3 4 5 = = = = = Top fastener Upper mast tube Guy wires Installation accessories Cable shrouds

VAISALA________________________________________________________________________ 15

User's Guide _______________________________________________________________________

Lightning Rod
The mast is delivered with a passive lightning rod made from copper. The lightning rod holders are made of non-conductive material to protect the mast devices from overvoltage when lightning occurs. Refer to Figure 5 below. An active type of lightning rod is available as an option for areas where heavy lightning activity occurs frequently.

0303-022

Figure 5

Passive Lightning Rod with the Cable and the Holders

Winch (Optional)
The optional winch is equipped with the friction break, thus stopping automatically when the user releases the handle. The winch is easily installed to the pedestal tube. After erecting the mast, the winch should be removed from the pedestal tube and stored in a dry and warm place.

0303-023

Figure 6

Winch (Optional)

16 ____________________________________________________________________M210315en-B

Chapter 2 ___________________________________________________________ Product Overview

Product Nomenclature
Table 2
Standard Nomenclature DKP206W DKP206AV DKF200 DKL200 DKP206GW DKP200SW DKP200LR DKW200 DKP200TS DKH200ACCESS DKP200IS

Product Nomenclature for DKP206 Masts


Description 6 m high pole mast, color white 6 m high pole mast, color orange/white Foundation Set Passive Lightning Rod Guy Wire Set Support Guy Wire for DKL200 Lifting Rod Winch Tilting Support Assembly Set for Active Lightning Rod Installation/Tilting Set Note The package contains either of these product alternatives.

The package contains either of these product alternatives. Optional with DKP206AV Optional Optional Optional with Active Lightning Rod Optional with DKP206AV

Table 3
Standard Nomenclature DKP210W DKP210AV

Product Nomenclature for DKP210 Masts


Description 10 m high pole mast, color white 10 m high pole mast, color orange/white Foundation Set Passive Lightning Rod Lifting Rod Additional Guy Wire Set Winch Tilting Support Assembly Set for Active Lightning Rod Installation/Tilting Set Note The package contains either of these product alternatives. Includes always Guy Wire Set.

DKF200 DKL200 DKP200LR DKP210GW DKW200 DKP200TS DKH200ACCESS DKP200IS

Optional with DKP210AV Optional Optional Optional Optional with Active Lightning Rod Optional with DKP206AV

VAISALA________________________________________________________________________ 17

User's Guide _______________________________________________________________________

This page intentionally left blank.

18 ____________________________________________________________________M210315en-B

Chapter 3 ________________________________________________________________ Installation

CHAPTER 3

INSTALLATION

This chapter provides instructions for installing the DKP206 and DKP210 masts.

Siting Criteria Ambient Measurements


Finding a suitable site for the mast is important for getting representative ambient measurements with the mounted sensors. For further information refer to the local and WMO recommendations. Allow sufficient clearance especially for the wind sensors. The mast should not be located next to a building or any other object that might affect the airflow. The following two figures provide general guidelines for the mast location. In general, there should be at least 150 m of open area to all directions from the mast. The minimum distance between the mast and obstacles is ten times the height of an obstacle. Refer to Figure 7 on page 20. The recommended minimum length (h in Figure 8 on page 20) for the mast installed on top of a building is 1.5 times the height of the building (H). When the diagonal (W) is less than the height (H), the minimum length of the mast is 1.5 times W.

VAISALA________________________________________________________________________ 19

User's Guide _______________________________________________________________________

0204-040

Figure 7

Recommended Mast Location in Open Area

NOTE

150 m 500 ft.

0204-041

Figure 8

Recommended Mast Length on Top of a Building

20 ____________________________________________________________________M210315en-B

Chapter 3 ________________________________________________________________ Installation

Tilting Direction
Also note the tilting direction of the mast. When installed in the northern hemisphere, the mast tilts to west. There should be a clear area up to 9 m on the west side of the mast. The area should be free of obstacles preventing the mast from being erected and tilted.

Soil Evaluation
Always, evaluate the soil to determine the appropriate type of the foundation required. When designing the foundation, the local construction companies must be consulted to find out about the soil and frost conditions in your area. When the soil is frost-susceptible, make sure to always use the proper insulation.

CAUTION

For the mast base installation, the soil bearing capacity has to exceed 45 kPa (940 pounds-force/sq. foot).

Site Preparation Power Supply and Communication Lines


Before assembling the mast the power supply and communication lines must be available. The primary AC power service must comply with the National Electrical Code (NEC) or equivalent specifications for grounding the primary power service entrance. The mains must be continuous and without spikes and blackouts. If the AC (mains) voltage is fluctuating more than the given tolerance allows, the AC (mains) voltage stabilizers are recommended. The following applies to all field cabling: - Use armored field cables. - Cables must be suitable for underground use. - Check the cable core diameter according to maximum allowable drop. - Route the cables through conduits to the equipment.

VAISALA________________________________________________________________________ 21

User's Guide _______________________________________________________________________

- Check cable conduit diameters or use additional termination boxes. - Ground the cable shield at both ends. - Use spike and overvoltage protection devices at both ends of field cables. Always make a detailed cabling and wiring plan. Data transmission lines from the outdoor sites to indoor devices have to be prepared carefully. Also the power supply for the equipment used needs to be planned carefully. It is recommended to use a conduit to protect the cables that connect the indoor components to the outdoor components from damage and moisture. Also traffic, standing water, and the twist and stress caused by the connectors will damage the cables.

Tools Required for Installation


You need a set of Allen keys, two adjustable wrenches, a water level, a compass, and a big hammer.

Unpacking Instructions Inspecting the Delivery


Check the shipping boxes for possible damage. Check that there are no loose parts or connectors before installing the mechanics of the equipment and cabling them. If there has been any damage, contact Vaisala without delay.

Contents of the Delivery


The mast and the accessories are packed into cartons. The contents of the cartons may vary depending on the selected options. Check the delivery contents against the packing list provided in a plastic folder on the carton. Refer to Figure 9 on page 23 and Figure 10 on page 24 to identify the items.

22 ____________________________________________________________________M210315en-B

Chapter 3 ________________________________________________________________ Installation

0303-024

Figure 9

Contents of the Mast Delivery (Part 1)

The following numbers refer to Figure 9 above. 1 2 3 4 5 6 7 = = = = = = = Holders of the lightning rod (2 pcs) Upper mast tube, 60 mm Lightning rod with the cable Guy wires Cable shrouds for the guy wires (yel/blk, 3 sets) Winch Lifting rod, 60 mm

NOTE

Figure 9 above and Figure 10 on page 24 provide only examples of the contents. The contents may vary depending on the model of the mast and on the selected options.

VAISALA________________________________________________________________________ 23

User's Guide _______________________________________________________________________

0303-025

Figure 10

Contents of the Mast Delivery (Part 2)

The following numbers refer to Figure 10 above: 1 2 3 4 = = = = Tilting support Pedestal tube, 100 mm Lower mast tube, 75 mm Assembly set: Guy wire fasteners (3 pcs) Guy assembly set (1 set) Hinge set (1 set) Lifting rod assembly set (1 set) Lightning rod assembly set (1 set) Foundation set: Foundation bolts, M20 (7pcs) Wedge bolts, M20 (7 pcs) Tool for wedge bolts (1 pc) Eye nuts for guy wires (3 pcs) Spring washers, M20 (10 pcs) Washers, M20 (10 pcs) Nuts, M20 (14 pcs) Nuts with plate, M20 (3 pcsc) Square plate with 4 nuts (1 pc) Orientation plate (1 pc)

24 ____________________________________________________________________M210315en-B

Chapter 3 ________________________________________________________________ Installation

Foundation Soil and Frost Conditions


When designing the foundation, the local construction companies must be consulted to find out about the soil and frost conditions in your area. When the soil is frost-susceptible, make sure to always use the proper insulation.

Orientation of the Mast


Refer to Figure 11 on page 26 for the orientation of the mast. The concrete blocks for guy wires have to be placed so that the pole mast can be tilted west (east in the southern hemisphere) by releasing only the guy wire 1, see Figure 11 on page 26. To ease the orientation of the mast, the two-headed arrow is cut on the orientation plate. "N" should face north and "S" should face south to ensure the aiming of the weather station devices to the correct position.

VAISALA________________________________________________________________________ 25

User's Guide _______________________________________________________________________

0207-064

Figure 11

DKP210 Mast Orientation

NOTE

5 - 6 m 16.4 - 19.7 ft.

26 ____________________________________________________________________M210315en-B

Chapter 3 ________________________________________________________________ Installation

0207-065

Figure 12

DKP206 Mast Orientation

NOTE

4 m 13.1 ft.

VAISALA________________________________________________________________________ 27

User's Guide _______________________________________________________________________

Concrete Foundations
The DKP206 and DKP210 pole masts can be mounted on a new or an existing concrete block. The pole mast is fixed to the concrete block with foundation bolts.

NOTE

The minimum weight of the main mast block is 400 kg (882 lb.).

When constructing a new concrete block, fasten the foundation bolt assembly simultaneously with the concrete pour. If there is an existing concrete foundation, you have to drill the holes for the foundation bolts. In both cases, use the delivered orientation plate for correct placing of the foundation bolts. For the protection of the cables, it is recommended to install a cable conduit, which has a minimum diameter of 70 mm (2.76 in.). See Figure 13 below.

0303-026

Figure 13

Main Mast Block and Orientation Plate (Dimensions in mm)

NOTE

70 mm 2.76 in. 80 mm 3.15 in. 200 mm 7.87 in. 250 mm 9.84 in. 600 mm 23.62 in. 800 mm 31.50 in.

28 ____________________________________________________________________M210315en-B

Chapter 3 ________________________________________________________________ Installation

Concrete block dimensions for the guy wires are presented in Figure 14 below.

0303-027

Figure 14

Concrete Block for Guy Wire (Dimensions in mm)

NOTE

40 mm 1.57 in. 50 mm 1.97 in. 240 mm 9.45 in. 400 mm 15.75 in. 600 mm 23.62 in. 800 mm 31.50 in.

Making a New Concrete Block


1. Make a cast mould with steel reinforcements according to the design shown in Figure 15 on page 30. Use the 12-mm deformed steel. In addition to the reinforcement presented in Figure 15 on page 30, you need to add two additional horizontal bar layers. The distance between the layers should be approximately 200 mm. Note that you can make the guy wire blocks similarly, but the reinforcement horizontal bar length should be 300 mm instead of 400 mm presented in Figure 15 on page 30.

VAISALA________________________________________________________________________ 29

User's Guide _______________________________________________________________________

NOTE

10 mm 0.39 in. 12 mm 0.47 in. 40 mm 1.57 in. 50 mm 1.97 in. 70 mm 2.76 in. 150 mm 5.91 in. 300 mm 11.81 in. 400 mm 15.75 in. 600 mm 23.62 in.

600
0207-068

400

Figure 15 2.

Reinforcement for the Concrete Blocks

If necessary, place the cable duct tubes into the casting mould prior to casting. The recommended inner diameter of the duct tube is 70 mm (2.76 inches). Place the steel reinforcement into the casting mould. Screw the foundation bolts (number 1 in Figure 16 on page 31) to the nuts (6) which are fixed to the square metal plate (3).

3. 4.

30 ____________________________________________________________________M210315en-B

Chapter 3 ________________________________________________________________ Installation

0207-069

Figure 16 5.

Foundation Assembly for the Mast Base

Fix the orientation plate (2) to the upper ends of the foundation bolts (1) with eight nuts (4 and 5), see Figure 16 above. The top of the bolt should be approximately 80 mm above the orientation plate, refer to Figure 13 on page 28.

0207-062

Figure 17 6.

Foundation Assemblies for a New Concrete Block

Install the foundation assembly into the mould so that the foundation bolt threads stand above the surface, see Figure 13 on page 28. The orientation plate (number 4 in Figure 17 above) should be at the same height as the top of the finalized concrete block. Protect the threads of the bolts above the orientation plate, for example, by taping them. Also check the correct alignment of the foundation assembly with the orientation plate

VAISALA________________________________________________________________________ 31

User's Guide _______________________________________________________________________

(number 4 in Figure 17 on page 31). "N" should face north and "S" should face south. 7. For the guy wires, fix the foundation bolt (number 2 in Figure 17 on page 31) to the plate with a nut (3). Fix the eye nut (1) to the other end of the foundation bolt. Level the assembly so that the top of the bolt will be 40 mm above the concrete in the finalized block. The eye nut will then be one centimeter above the finalized concrete block. Pour in the concrete. Finish the concrete block.

8.

Using an Existing Concrete Block


1. Drill holes with a diameter of 25 mm into the concrete block using the orientation plate as a guide. Make sure that the depth of the holes is 240 mm (5 mm).

NOTE

5 mm 0.20 in. 25 mm 0.98 in. 240 mm 9.45 in.

0207-070

Figure 18 2.

Accessories for Existing Concrete Block Installation

First, install the key piece (number 3 in Figure 18 above) correctly inside the wedge bolt (4). The narrow end should point to the direction of the lower arrow in Figure 18 above. Assemble the wedge bolts into the holes. There are four bolts for the mast base and one bolt for each of the guy wire blocks.

32 ____________________________________________________________________M210315en-B

Chapter 3 ________________________________________________________________ Installation

3. 4. 5. 6.

Hammer the wedge bolts (4) down using the provided bar (2). Screw the foundation bolts (1) to the wedge bolts and tighten the screws properly. Fill the remaining space of the holes with a suitable compound. Start erecting the mast after the compound is dry.

Assembling the Mast Work Order


To assemble the mast, follow the work order below: 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. Attach the 2-meter-high pedestal tube to the concrete foundation. Lift the lower base of the mast to the upper end of the pedestal tube and assemble the hinge axle. Attach the lifting rod to the clamp that is preinstalled to the lowest mast tube. Attach the guy wires to the uppermost mast tube. Connect the mast tubes together. Lift the upper end of the mast on the tilting support. Assemble the holders to the lightning rod and attach the assembly to the mast. Attach the winch and route the winch wire to the appropriate guides. Install any other devices that will be installed to the tiltable part of the mast and attach the cables to the mast with cable ties. Attach the jacketed copper grounding wire to the insulated guy wire with the cable ties. Erect the mast with the winch and secure the hinge with the bolts. Connect the guy wires with fasteners to their foundations and mark them with the cable shrouds. Remove the winch and assemble the devices to the pedestal tube.

For detailed instructions, refer to the following sections.

VAISALA________________________________________________________________________ 33

User's Guide _______________________________________________________________________

Installing the Pedestal Tube


1. Turn the pedestal tube so that the plate lug faces south in the northern hemisphere and north in the southern hemisphere, see Figure 19 below. The plate lug is for attaching the guide for the winch wire.

0303-028

Figure 19 2.

Pedestal Tube Alignment to North-South Direction

First place the washers and then the spring washers onto the previously installed nuts and lift the pedestal tube through the bolts onto the washers. Install the nuts with the washers and spring washers to the foundation bolts. Refer to Figure 20 below.

3.

0303-029

Figure 20

Pedestal Tube Attachment

34 ____________________________________________________________________M210315en-B

Chapter 3 ________________________________________________________________ Installation

The following numbers refer to Figure 20 on page 34: 1 2 3 4 4. = = = = Foundation bolt Spring washers, under and above the plate Washers, under and above the plate Nuts, under and above the plate

Level the pedestal tube to vertical with the nuts that are under the plate. For adjusting the level, use the appropriate wrench and the water level to check that the pedestal tube is vertical. Refer to Figure 21 below. Finally, tighten the bolts with the appropriate wrenches.

5.

0303-030

Figure 21

Pedestal Tube Adjustment with Water Level

VAISALA________________________________________________________________________ 35

User's Guide _______________________________________________________________________

Connecting the Lowest Mast Tube to the Pedestal Tube


To connect the lowest mast tube to the pedestal tube, install the axle for the hinge. For installing the axle, follow the procedure below: 1. Take the axle (number 1 in Figure 22 below) for the hinge from the plastic bag labeled Hinge Set.

0303-031

Figure 22 2. 3.

Axle for Hinge

Thread the Allen bolt (4) with the washers (2 and 3) to either end of the axle. Lift the mast end (3) on the hinge (1) and install the axle (2), see Figure 23 below.

0303-032

Figure 23

Hinge Bolt Installation

36 ____________________________________________________________________M210315en-B

Chapter 3 ________________________________________________________________ Installation

4.

Thread the other Allen bolt to the axle and tighten both ends with the Allen key.

Connecting the Lifting Rod to the Mast


The delivery may contain the lifting rod that is used with the winch to erect and tilt the upper mast assembly. The clamps are preinstalled at the factory to the pedestal tube and to the lowest mast tube. The clamp on the lifting rod has hooks (number 1 in Figure 24 below) and taps (2) to ease the installation. The stainless steel bolts (3) are included in the Lifting Rod Assembly Set (4).

0303-033

Figure 24

Lifting Rod Installation Accessories

To attach the lifting rod to the previously installed lower mast tube, follow the procedure below: 1. 2. Place the lifting rod (number 1 in Figure 25 on page 38) on the mast assembly as shown in Figure 25 on page 38. Make sure that both taps on the clamp go into the railing and the hooks (number 3 in Figure 25 on page 38) at the end of the clamp go firmly around the opposite clamp. Install the bolts (number 2 in Figure 25 on page 38) with the washers and tighten them with an Allen key.

3.

VAISALA________________________________________________________________________ 37

User's Guide _______________________________________________________________________

0303-034

Figure 25

Lifting Rod Clamp Attachment

Connecting the Guy Wire Set to the Mast


1. Install the clamps (1) around the mast with the bolts (2) to assemble the top fastener. The top fastener should be assembled next to the tapered edge (3). See Figure 26 below. After installing the lightning rod, you should aim the insulated guy wire so that it points northwest when the mast is erected. The lightning rod holders are aligned to the same direction as the insulated guy wire, refer to Figure 30 on page 41.

2.

0303-035

Figure 26

Guy Wire Attachment

38 ____________________________________________________________________M210315en-B

Chapter 3 ________________________________________________________________ Installation

Assembling the Mast Tubes


The upper mast tube(s) has the O-ring (number 1 in Figure 27 below) installed on the tube. For connecting the mast tubes, just slide the mast tubes together. You need to rotate either of the tubes to align the groove (2) on the upper tube and the ridge (3) inside the lower mast tube, see Figure 27 below.

0303-036

Figure 27

Alignment of the Mast Tubes

Assembling the Lightning Rod


Lightning protection is provided with a well-grounded lightning rod placed to the highest point of the mast. The lightning rod is completely insulated from other mast construction and separately connected to its own lightning ground rod(s) several meters away from other equipment ground rod(s). A 25 mm grounding cable is routed down from the top of the mast via an insulated guy wire. See Figure 31 on page 42. To install the lightning rod, follow the procedure below: 1. 2. 3. Slide the lightning rod to the holes in the holders. The arrow in Figure 28 on page 40 shows the recommended direction. Attach the lightning rod to the holders with the bolts (number 1 in Figure 28 on page 40). Slide the optional obstruction light holder (2) to the mast between the lightning rod holders and tighten the nuts (3).

VAISALA________________________________________________________________________ 39

User's Guide _______________________________________________________________________

0303-037

Figure 28 4. 5.

Lightning Rod Installation to the Mast

Secure the holders to the mast with the bolts in the clamps (4). Check that the dimensions for the installed lightning rod are as illustrated in Figure 29 below.

0303-038

Figure 29

Dimensions (in mm) for Lightning Rod Assembly on the Mast

NOTE

20 mm 0.79 in. 150 mm 5.91 in. 350 mm 13.8 in. 440 mm 17.3 in. 1065 mm 41.9 in

40 ____________________________________________________________________M210315en-B

Chapter 3 ________________________________________________________________ Installation

Connecting the Grounding Cable to the Insulated Guy Wire


Before erecting the mast, connect the grounding cable to the insulated guy wire as follows: 1. Aim the insulated guy wire so that it points northwest (in the northern hemisphere) when the mast is erected. The lightning rod holders are aligned to the same direction as the insulated guy wire, see Figure 30 below.

0303-039

Figure 30 2.

Alignment of the Insulated Guy Wire and the Lightning Rod Holders

Attach the grounding cable (number 3 in Figure 31 on page 42) with a wire rope clip (5) below the insulator (4).

NOTE

Leave some extra cable between the lightning rod and the wire rope clip on the guy wire to ensure that the guy wire does not pull the lightning rod downwards.

VAISALA________________________________________________________________________ 41

User's Guide _______________________________________________________________________

0303-040

Figure 31

Lightning Rod Cable Attachment

The following numbers refer to Figure 31 above. 1 2 3 4 5 = = = = = Lightning rod Lightning rod holders Grounding cable Insulator Wire rope clip

Routing the Device Cables


Route the device cables from the top of the mast down the hinge side to avoid possible damage to the cables when tilting the mast. It is also important to attach the cables to the mast with the cable ties. The recommended distance between the cable ties is from 30 to 40 cm (11 ... 16 in.).

42 ____________________________________________________________________M210315en-B

Chapter 3 ________________________________________________________________ Installation

Erecting the Mast


NOTE
Before erecting the mast, refer to the installation instructions of the additional sensors and devices. It is important to aim the sensors correctly before erecting the mast.

Before erecting the mast, check that the bolts of the top fastener are tight. The top fastener (number 1 in Figure 26 on page 38) is mounted on the upper mast tube.

Installing and Using the Winch


It is recommended to use the winch for erecting the mast. The winch is easy to install and should be removed after use. 1. Attach the handle (number 5 in Figure 32 below) to the shaft of the winch.

0303-041

Figure 32

Winch Installation

VAISALA________________________________________________________________________ 43

User's Guide _______________________________________________________________________

2.

Install the winch towards the pedestal tube so that the tap (3) on the tube goes to the hole (2) on the winch. Make sure that the plastic cover on the winch faces up. Wrap the clamps (1) around the tube to the clamp assemblies (4) and attach them. Finally, secure the clamps with the provided pin clips as shown in Figure 33 below.

3. 4.

0303-042

Figure 33 5.

Securing Clamp of the Winch

Attach the cable bearer (number 2 in Figure 34 below) with the quick link (3) to the plate lug (4) of the pedestal plate. Make sure that the wire (1) with the hook points east (when installing in the northern hemisphere).

0303-043

Figure 34 6.

Lower Cable Lead

Clip the hook (number 2 in Figure 35 on page 45) to the plate lug (1) of the lifting rod.

44 ____________________________________________________________________M210315en-B

Chapter 3 ________________________________________________________________ Installation

0303-044

Figure 35 7.

Attaching the Hook

Take a good grasp on the handle and turn it clockwise to erect the mast. The winch is equipped with a friction break and thus, it stops automatically when you release the handle.

WARNING

Make sure that there are no people under the mast when the mast is being erected.

WARNING

When erecting the mast with the winch, avoid touching the wire with bare hands. Do not try to guide the wire.

WARNING

Always wear gloves when using the winch. Do not touch the gears of the winch.

VAISALA________________________________________________________________________ 45

User's Guide _______________________________________________________________________

Securing the Hinge


After erecting the mast, secure the hinge with the provided accessories as illustrated in Figure 36 below.

NOTE

Always assemble the washers (number 3 in Figure 36 below) under the spring washers (2) to prevent the paint from being damaged.

0303-045

Figure 36

Bolts and Washers for Securing the Hinge

The following numbers refer to Figure 36 above: 1 2 3 = = = Allen bolt Spring washer Washer

Connecting the Guy Wires to the Concrete Blocks


WARNING
Always wear gloves when handling the guy wires.

46 ____________________________________________________________________M210315en-B

Chapter 3 ________________________________________________________________ Installation

Follow the procedure below to connect the guy wires to the concrete blocks: 1. Connect the guy wires 2 and 3 as instructed in step a. below and connect the guy wire 1 as instructed in step b. below. The guy wire 1 is installed differently from the others, because it is released when the mast is tilted. For the location of the guy wires, refer to Figure 37 below.

0303-046

Figure 37 a.

Guy Wires

For the guy wires 2 and 3, connect the U-bolt (number 2 in Figure 38 on page 48) to the eye bolt (1) installed on the concrete block. Slide the strap (3) onto the U-bolt and thread the nuts.

VAISALA________________________________________________________________________ 47

User's Guide _______________________________________________________________________

0207-091

Figure 38 b.

Connecting the U-bolt to the Eye Bolt

For the guy wire 1, connect the U-bolt (number 3 in Figure 39 below) to the eye nut (1) with an additional bow shackle (2) to enable easy releasing of the wire. The strap (4) is used as with the guy wires 2 and 3.

0303-047

Figure 39

Guy Wire 1 Attachment

NOTE

The additional bow shackle (number 2 in Figure 39 above) may differ from the one shown in the figure.

2.

Secure the guy wires with the provided wire rope clips (number 3 in Figure 40 on page 49). Place the wire rope clips on the wire so that the forged, grooved part clamps the wire coming from the mast (the tension side) and the U-bolt clamps down on the end-most section of the wire. Check also that the wire is properly in the key groove (1). After assembling the wire rope clips properly, tension the guy wire by tightening the nuts (number 2 in Figure 40 on page 49) to slide the strap, until the initial tension of the guy wires is

3.

48 ____________________________________________________________________M210315en-B

Chapter 3 ________________________________________________________________ Installation

sufficient. When tensioning the guy wires, make sure that the mast remains straight and that all the guy wires are equally tensioned.

0207-092

Figure 40 4. 5.

Securing the Guy Wires

Cut the extra guy wire. Finally, place the black and yellow cable shrouds around the guy wires, see Figure 41 below. There is one package of shrouds for each wire.

0207-093

Figure 41

Installing Cable Shrouds

The following numbers refer to Figure 41 above. 1 2 = = Guy wire Cable shrouds

VAISALA________________________________________________________________________ 49

User's Guide _______________________________________________________________________

Equipment Grounding and Lightning Protection


With mast installations equipment grounding and lightning protection must be done separately. The main principles are described below: - Proper equipment grounding is required for personnel safety and for equipment protection. A piece of equipment is grounded by connecting its metal structures and electrical equipment to an external buried ground rod. Individual site requirements may dictate changes in the procedures described in this manual. Changes are permissible as long as protection equivalent to the original requirements is provided for the system.

WARNING

Failure to provide proper grounding may result in personnel injury or death from electrical shock and may severely damage equipment.

WARNING

Lightning protection is required to prevent personnel injury and equipment damage due to direct lightning strikes and lightninginduced current surges.

- The materials used in the manufacture of the grounding systems must be chosen to prevent them from forming an electrolytic couple. It is recommended to use copper (Cu). - The equipment grounding system and lightning protection grounding system should be located as far as possible from each other. The minimum recommended distance is 5 m (16 ft.). Due to this the lightning rod grounding cable is routed down from the top of the mast via the guy wire which is insulated from the mast construction, refer to number 2 in Figure 42 on page 51. The equipment grounding should be done near the mast block as illustrated in Figure 42 on page 51.

50 ____________________________________________________________________M210315en-B

Chapter 3 ________________________________________________________________ Installation

0303-048

Figure 42

Location of the Grounding Rods and an Optional Grid, the Arrow Points to the Mast Tilt Direction

The following numbers refer to Figure 42 above. 1 2 3 4 5 6 = = = = = = The grounding rod The guy wire block of the insulated guy wire The mast block An optional grounding rod An optional connecting cable The 5-meter minimum distance between the rods

- The recommended grounding resistance is 10 or less for both the grounding of lighting protection rod and for the equipment grounding. Soil conditions (sand, rocks, etc.) and the ground resistance measurement determines the design and construction of the grounding system. Buried ground rods and / or buried wire can be used for the ground network. The type and combination used depend on soil conditions (ease of installation) and on the value of measured ground resistance (the most effective way of reducing

VAISALA________________________________________________________________________ 51

User's Guide _______________________________________________________________________

resistance to the required value of 10 or less). Measurements of the earth resistance must be made at least 48 hours after rainfall. - The connection between ground rods and the equipment frames and copper cables should be made with appropriate compression lugs, bolts, nuts, and lock washers. - Optionally, the top of the earth electrode can be housed inside covered pit as illustrated in Figure 43 below. Table 4 Examples of Soil Resistivities, Ohm-Meters
Median 26 33 55 190 300 800 Variation 1 ... 50 10 ... 55 30 ... 80 80 ... 300 100 ... 500 600 ... 1 000

Soil Type Topsoil, loam Inorganic clays of high plasticity Silty or clayey fine sands with slight plasticity Fine sandy or silty clays, silty clays, clean clays Silty sands, poorly graded sand-silt mixtures Well graded gravel, gravel sand mixtures

Due to the above reasons and soil variations, the grounding accessories presented in this manual (rods, connectors, etc.) are only examples of the proper ones, thus recommended to be supplied locally.

0303-049

Figure 43

Ground Rod Installation

52 ____________________________________________________________________M210315en-B

Chapter 3 ________________________________________________________________ Installation

The following numbers refer to Figure 43 on page 52: 1 2 3 4 = = = = Access well Grounding rod Compression lug Grounding cable

Equipment Grounding
The equipment grounding cable is connected to the equipment ground system (rod or other) from the one main grounding point, which is normally a grounding bar located underneath the main system enclosure.

CAUTION

Always use clamps for connecting a cable to the grounding rod or two cables together, do not solder.

Consult the local authority for local grounding requirements. A copper grounding cable and conductive grounding rod(s) are recommended. Usually, the customer is responsible for supplying grounding cables, rods, clamps, power cables, long distance signal cables, and conduits for cables.

0207-094

Figure 44

Installing the Grounding Bar

VAISALA________________________________________________________________________ 53

User's Guide _______________________________________________________________________

The following numbers refer to Figure 44 on page 53. 1 2 3 = = = Hammer Protective cap Grounding bar

NOTE

The grounding accessories shown in Figure 44 on page 53 are examples of the grounding accessories. It is recommended to supply them locally.

Silver epoxy material or equivalent should be used to bond the interconnecting wire to the ground rods. The cross section of the interconnection copper wire is recommended to be 25 mm2. The length should be about 2 meters. The 2-meter cable can be obtained by first cutting the connection cable of the lightning rod to the correct length. The rest of the cable can be used for grounding the equipment. The original length of the cable is 15 m.

0207-095

Figure 45

Connecting the Grounding Cables to the Bar

The following numbers refer to Figure 45 above. 1 2 3 = = = Grounding cable Clamp Grounding bar

Always protect the grounding cable on the surface of the concrete block as illustrated in Figure 46 on page 55. This applies only when

54 ____________________________________________________________________M210315en-B

Chapter 3 ________________________________________________________________ Installation

the mast is installed on an existing concrete block. It is recommended to use a conduit when you cast the block for the mast.

0303-050

Figure 46

Grounding Cable Protection

The following numbers refer to Figure 46 above. 1 2 3 4 = = = = Clamp Grounding cables, for the lightning detector and power supply unit Plate to protect the grounding cables and the AC power cable Mast base

Grounding of the Lightning Rod


Do this in a similar way to the equipment grounding. The lightning rod is grounded near the guy wire block, see Figure 47 on page 56.

VAISALA________________________________________________________________________ 55

User's Guide _______________________________________________________________________

0303-051

Figure 47

Grounding of the Lightning Rod

The following numbers refer to Figure 47 above. 1 2 3 4 = = = = Clamp Rod Cable from the lightning rod Guy wire attachment

56 ____________________________________________________________________M210315en-B

Chapter 4 _______________________________________________________________ Maintenance

CHAPTER 4

MAINTENANCE

This chapter provides information that is needed for the basic maintenance of the DKP206 and DKP210 masts.

Regular Maintenance
The mast tubes are anodized and painted for durability in demanding harsh environments. Normally there is no need for maintenance. Only the mast should be checked yearly for any damage to the coating. Check also yearly the guy wires for correct tightness. Inspect the guy wires for damage as well.

Tilting the Mast


You need to tilt the mast, for example, when devices installed on the upper assembly need maintenance. The following sections provide instructions on tilting the mast.

Disconnecting and Securing the Guy Wire


1. 2. Disconnect the guy wire 1 that is on the opposite side of the mast to the hinge. For the location, see Figure 37 on page 47. Connect the spring clip that is mounted to the released guy wire to the hole in the hinge.

VAISALA________________________________________________________________________ 57

User's Guide _______________________________________________________________________

Using the Winch


1. 2. Install the winch to the mast as instructed in section Installing and Using the Winch on page 43. Open the securing Allen bolts in the hinge.

CAUTION

Do not open the Allen bolts in the horizontal hinge axle.

3.

Lower the mast slowly with the winch by turning the handle.

CAUTION

Make sure to have a good control of the handle.

4. 5.

Install the tilting support to the end of the mast, see Figure 48 below. Lower the mast slowly with the winch so that finally the mast rests on the tilting support.

0303-052

Figure 48

Tilted Mast with Tilting Support

Tilting the Mast Manually


Manual tilting is recommended only if the maximum height of the mast is 6 meters.

58 ____________________________________________________________________M210315en-B

Chapter 4 _______________________________________________________________ Maintenance

Erecting the Mast


To erect the mast after maintenance operations, refer to the section Installing and Using the Winch on page 43.

VAISALA________________________________________________________________________ 59

User's Guide _______________________________________________________________________

This page intentionally left blank.

60 ____________________________________________________________________M210315en-B

Chapter 5 _____________________________________________________________ Technical Data

CHAPTER 5

TECHNICAL DATA

This chapter provides the technical data of the DKP206 and DKP210 masts.

Specifications
Table 5 DKP210 Specifications
Description/Value 10 m (32.8 feet) 100 mm (3.94 in) 60 mm (2.36 in) 50 m/s (100 knots) 75 m/s (145 knots) 125 kg Stainless steel Aluminum alloy Stainless steel 28 kN (6 295 lbf) Black and yellow colored cable shrouds to the height of 2 meters from the ground Galvanized steel, thread M20, length 300 mm (11.8 in), with M20 wedge bolts (cast or drilled into concrete using the provided orientation plate) Stainless steel Corrosion-resistant powder coating Anodized and painted Galvanized Uncoated -40 +60 C (-40 ... 140 F) Property Height Diameter Lowest section Highest section Maximum wind speed With one set of guy wires With two sets of guy wires Weight (DKP210W with winch) Pedestal tube and hinge Mast tubes and lifting rod Guy wires Material Breaking strength Marking Threaded anchor bolts

Other parts, e.g., bolts Coating/Painting Pedestal tube Aluminum parts Steel parts Stainless steel parts Temperature

VAISALA________________________________________________________________________ 61

User's Guide _______________________________________________________________________

Table 6

DKP206 Specifications
Description/Value 6 m (19.7 feet) 100 mm (3.94 in) 60 mm (2.36 in) 50 m/s (100 knots) 105 kg Stainless steel Aluminum alloy Stainless steel 28 kN (6 295 lbf) Black and yellow colored warning pieces to the height of 2 meters from the ground Galvanized steel, thread M20, length 300 mm (11.8 in), with M20 wedge bolts (cast or drilled into concrete using the provided orientation plate) Stainless steel Corrosion-resistant powder coating Anodized and painted Galvanized Uncoated -40 +60 C (-40 ... 140 F)

Property Height Diameter Lowest section Highest section Maximum wind speed With one set of guy wires Weight (DKP206W with winch) Pedestal tube and hinge Mast tubes and lifting rod Guy wires Material Breaking strength Marking Threaded anchor bolts

Other parts, e.g., bolts Coating/Painting Pedestal tube Aluminum parts Steel parts Stainless steel parts Temperature

62 ____________________________________________________________________M210315en-B

Vous aimerez peut-être aussi