Académique Documents
Professionnel Documents
Culture Documents
(Ninth edition)
5 7 3 4 9 2 3 18 3 6
Node 2 3 4 5 6 7
Shortest route from Node 1 1-2 1-3 1-2-5-6-4 1-2-5 1-2-5-6 1-2-5-6-7
Distance 7 9 17 12 14 17
Problem 2:
For the Gorman Construction Company problem (see Figure 9.1), assume that Node 7 is the companys warehouse and supply center. Several daily trips are commonly made from node 7 to the other nodes or construction sites. Using node 7 as the starting node, find the shortest route from this node to each of the other nodes in the network. Node 1 2 3 4 5 6 Shortest route from Node 7 7-6-5-3-1 7-4-2 7-6-5-3 7-4 7-6-5 7-6 Distance 22 11 12 5 8 6
Node
Distance
Problem 3:
In the original Gorman Construction Company problem, we found the shortest distance from the office (node 1) to each of the other nodes or construction sites. Because some of the roads are highways and others are city streets, the shortestdistance routes between the office and the construction sites may not necessarily provide the quickest or shortest-time routes. Shown here is the Gorman road network with travel time values rather than distance values. Find the shortest route from Gormans office to each of the construction sites if the objective is to minimize travel time rather than distance.
25 12 20 6 16 5 11 18
Problem 4: Find the shortest route between nodes 1 and 8 in the following network: The shortest route between node 1 and 8: 1-4-5-6-8 3+3+2+2= distance: 10 Problem 5: Find the shortest route between nodes 1 and 10 in the following network: 1-3-5-8-10 5+6+3+5= distance: 19
A -
B -
C A
D A,B
E A,B
F C
G D,F
H E,G
C A D Start E B
Problem 2:
G Finish H
Bridge City Developer is coordinating the construction of an office complex. As part of the planning process, the company generated the following activity list. Draw a project network that can be used to assist in the scheduling of the project activities. Activity Immediate Predecessor A B C D A,B E A,B F D G E H C I C J F,G,H,I
Start
G H
Finish
Problem 3: Construct a project network for the following project. The project is completed when activities F and G are both completed. Activity Immediate Predecessor A B C A D A E C,B F C,B G D,E
C D
Start F B
Problem 4:
Finish
Assume that the project in Problem 3 has the following activity times (in months). Activity Immediate Predecessor A 4 B 6 C 2 D 6 E 3 F 3 G 5
A 4
0 4 0 4
C 2
4 6 5 7 E 3 6 9 7 10
Start
D 6
4 10 4 10
B 6
0 6 1 7
G 5 F 3 6 9 12 15
10 15 10 15
Finish
a) Find the critical path. b) The project must be completed in and year and a half. Do you anticipate difficulty in meeting the deadline? Explain. a) The critical path A-D-G b) No, I dont find a difficulty, because it will be 15 months.
Problem 5: MDS is a consulting company that specializes in the development of decision support systems. MDS has just obtained a contract to develop a computer system to assist the management of a large company in formulating its capital expenditure plan. The project leader has developed the following list of activities and immediate predecessors. Construct a project network for this problem. Activity Immediate Predecessor A B C D B E A F B G C,D H B,E I F,G J H
A Start B
E D F
H J I G Finish
b. If the decision maker knows nothing about the probabilities of the three states of nature, what is the recommended decision, using the optimistic, conservative, and minimax regret approaches? Decision Alternative D1 D2 S1 250 100 S2 100 100 State of nature S3 25 75
a. D1
s1 250 s2 100 s3 25
s1 100
s2 D2 s3
100 75
Optimistic approach (250 is the largest payoff) Select D1 Conservative approach (75 is the best of the worst possible payoffs) Select D2 Minimax regret approach D1 50; D2- 150; Select D1 Decision D1 D2 Maximum Profit S1 0 150 Minimum profit S3 50 0
Problem 2: Suppose that a decision maker faced with four decision alternatives and four states of nature develops the following profit payoff table. Decision Alternative D1 D2 D3 D4 S1 14 11 9 8 S2 9 10 10 10 State of nature S3 10 8 10 11
S4 5 7 11 13
a. If the decision maker knows nothing about the probabilities of the four states of nature, what is the recommended decision using the optimistic, conservative, and minimax regret approaches? b. Which approach do you prefer? Explain. Is establishing the most appropriate approach before analyzing the problem important for the decision maker? Explain. c. Assume that the payoff table provides cost rather than profit payoffs. What is the recommended decision using the optimistic, conservative, and minimax regret approach?
a. Optimistic approach select D1, 14 Conservative approach select D3, 9 Minimax regret approach select D3, 5 Decision Alternative D1 D2 D3 D4 S1 0 3 5 6 S2 1 0 0 0 State of nature S3 1 2 1 0
S4 8 6 2 0
b. Yes, it is important to establish the most appropriate approach before analyzing, because in that way you can minimize the loses and maximize the profits. I prefer the minimax regret approach because like this the possibility to lose more is the smallest.
Problem 3: Southland Corporations decision to produce a new line of recreational products has resulted in the need to construct either a small plant or a large plant. The selection of plant size depends on how the marketplace reacts to the new product line. To conduct an analysis, marketing management has decided to view the possible long-run demand as either low, medium, or high. The following payoff table shows the projected profit in millions of dollars: Decision Alternative Small plant Large plant Low 150 50 Long-run demand Medium 200 200
a. Construct a decision tree for this problem b. Recommend a decision based on the use of the optimistic, conservative, and minimax regret approaches.
Low 150 a. Medium 200 Small plant High 200 Low 50 Large plant
Medium 200
High 500
b. Optimistic Approach Choose High long-run demand and Large plant 500 Conservative approach Choose Low long-run demand and Small plant 150 Minimax regret approach Choose Low long-run demand and Large plant 100 Decision Alternative Small plant Large plant Low 0 100 Long-run demand Medium 0 0
High 300 0
Problem 4: Investment Advisors, Inc. , has three investment strategies under consideration. Profits from the strategies will depend on what happens to the prime interest rate over the next three months. Payoffs (in thousands of dollars) are shown.
Rate Increase S3 40 80 70
What investment strategy would you recommend based on the use of optimistic, conservative and minimax regret approaches? Optimistic Strategy D2, 80 Conservative Strategy D1, 40 Minimax regret Strategy D2, 35
Rate Increase S3 40 0 10
Problem 5: The following profit payoff table was presented in Problem 1. Suppose that the decision maker has obtained the probability estimates: P(s1) = 0.65, P(s2) = 0.15, and P(s3) = 0.20. Use the expected value approach to determine the optimal decision.
State of nature S3 25 75
EV (d1) = 0.65(250) +0.15(100) +0.20(25) = = 162.5 +15 +5 = = 182.5 EV (d2) = 0.65(100) +0.15(100) +0.20(75) = = 65+15+15 = = 95 The optimal decision is D1 with an expected value of 182.5!
Problem 1: In the market share analysis of section 17.1, suppose that we are considering the Markov process associated with the shopping trips of one customer, but we dont know where the customer shopped during the last week. Thus, we might assume a 0.5 probability that the customer shopped at Murphys and 0.5 probability that the customer shopped at Ashleys at period 0; that is 1(0) = 0.5 and 2(0) = 0.5. Given these initial state probabilities, develop a table similar to table 17.2 showing the probability of each state in future periods. What do you observe about the long-run probabilities of each state? Current weekly shopping period Next weekly shopping period Murphys Food liner Ashleys Supermarket
0.9 0.2
0.1 0.8
2(1)]
[ ]
[ 1(3)
2(3)]
[ 1(4)
2(4)]
[ 1(5)
2(5)]
[ 1(6)
2(6)]
[ 1(7)
2(7)]
1 0.55 0.45
2 0.585 0.415
6 0.646 0.353
7 0.652 0.347
Problem 2:
Management of the New Fangled Softdrink Company believes that the probability of a customer purchasing Red Pop or the companys major competition, Super Cola, is based on the customers most recent purchase. Suppose that the following transition probabilities are appropriate: From Red Pop Super Cola Red Pop 0.9 0.1 To Super Cola 0.1 0.9
a. Show the two-period tree diagram for a customer who last purchased Red Pop. What is the probability that this customer purchases Red Pop on the second purchase? b. What is the long-run market share for each of these two products? c. A RP advertising campaign is being planned to increase the probability of attracting SC customers. Management believes that the new campaign will increase to 0.15 the probability of a customer switching from SC to RP. Whats the projected effect of the advertising campaign on the market shares?
Period 1 a.
Period 2
0.1
0.1
Red Pop
(0.1)(0.1) = 0.01
0.9
Super Cola
(0.1)(0.9) = 0.09
Super Cola = 0.18 Red Pop = 0.81 + 0.01 = 0.82 is the probability the customer purchases Red Pop on the second Purchase!
= [ 1(0)
2(0)]
[ ]
c.
1=
0.9 2 = 0.1
1
0.15 1 + 0.9 2= 1
1+
2 2
1=
1 1 2 = 1 - 0.6 2 = 0.4
Problem 3:
a. [ 1(0) [ 1(1)
2(0)]
= [1 0]
2(0)]
2(1)]
= [ 1(0) = [1 0] [
[ ]
= [0.9 0.10] The probability of the system being down in the next our of operation: b.
1= 2= 1 2(1)
= 0.10
0.9
1+
0.3
0.10 1 + 0.70 2= 1
1=
1 1
2=
1 - 0.75 2 = 0.25
Problem 4:
a.
1=
2 2
1=
0.95 1 + 0.60 1 = 0.95 1 + 0.60 0.601 1 = 0.351 +0.60 1 = 0.60 1 = 0.92 is the steady-state probability of the system being in the running state.
2=
1 1 2 = 1 - 0.92 2 = 0.08 is the steady-state probability the system being in the down state.
Problem 5:
a. From No traffic delay Traffic delay No traffic delay 0.85 0.25 To Traffic delay 0.15 0.75
[ 1(0) [ 1(1)
2(0)]
2(1)]
[ ]
[ 1(2)
2(2)]
= 0.42 The probability for the next 60 minutes the system will be in the delay state is 0.42!
2(2)
b.
1=
2 2
1=
0.85 1 + 0.25 1 = 0.85 1 + 0.25 0.251 1 = 0.61 +0.25 1 = 0.25 1 = 0.625 That is the probability that in the long run the traffic will not be in the delay state!
2=
1 1 2 = 1 0.625 2 = 0.375
Route 1-4-5-8-10 1-4-5-9-10 1-4-6-8-10 1-4-6-9-10 1-3-5-8-10 1-3-5-9-10 1-3-6-8-10 1-3-6-9-10 1-3-7-8-10 1-3-7-9-10 1-2-5-8-10 1-2-5-9-10 1-2-6-8-10 1-2-6-9-10 1-2-7-8-10
Value 22 25 27 23 19 22 26 22 22 21 22 25 24 20 25
1-2-7-9-10
24
The dynamic programming reduces the number of computation by decomposing the large problem into a number of interrelated smaller problems, which are easier to solve.
Problem 2:
a. Stage 1: Input Node 7 8 9 Arc (decision) 7-10 8-10 9-10 Shortest distance to Node 10 8 10 6
Stage 2: Input Node 5 6 Arc (decision) 5-9 6-9 Shortest distance to Node 10 11 17
Stage 3: Input Node 2 3 4 Arc (decision) 2-5 3-5 4-6 Shortest distance to Node 10 18 19 21
Stage 4: 1-2 10 1-3 8 1-4 5 So the shortest route from node 1 to node 10 is 1-4-6-9-10 with a distance of (5+4+11+6) = 26. b. In the same way it is: 4-6-9-10 with a distance of (4+11+6) = 21. c. Route 1-2-5-7-10 1-2-5-8-10 1-2-5-9-10 1-3-5-7-10 1-3-5-8-10 1-3-5-9-10 1-3-6-8-10 1-3-6-9-10 1-4-6-8-10 1-4-6-9-10 Value 32 36 28 31 35 27 34 31 29 26
Dynamic programming reduces the number of computation by decomposing the large problem into a number of interrelated smaller problems, which are easier to solve.
Problem 3:
Problem 4:
Problem 5: