Area Replacement Calculations

per ASME B31.3, paragraph 304.3.3


Project:
Area:
Header No.
Branch No.
Temperature:
Materal:
Header:

Freeport LNG
CC1
E-1A LNG Vaproizer
NPS 10 S/10S
230

By: G. Woods
Check:

Pressure:

200

corrosion:

S:

18800

Eh:

A312-TP304
S:
OD
Nom. Wall
Header:
60.000
0.4375
Branch:
10.75
0.365
th
tb
Min. wall:
0.318
0.057

18800

Eb:

A240-304

Branch:

Dim. d1:

10.111

A1:

3.213

Dim. d2:

10.111

A2:

0.657

L4a:

0.957

L4:

0.957

L4b:

1.298

A3:

0.502

A4:

1.928

A2+A3+A4:
% Replaced:

3.088
96.104

Pad OD:
Pad, Tr:

14.750
0.500

d2a:

5.758

% mill tol.:

12.5
Angle B:

y:

90

0.4

Tb
tb

mill tol.
c
UFT

A3

Pad reinforced intersection


Tr
Th

Pad OD
A2

A1
L4

mill tol.

Date: 4-25-06
Date:

A4

d1

c
d2

d2
B

C Header

th