Vous êtes sur la page 1sur 38

Closing Date: Our Reference:

06/06/2011 T10/2011

11:00am

Subject:

Tender for the Procurement of the Main Ventilation Plant serving Hexagon House in Marsa

Tender Document:

This is available for download free of charge from: www.mepa.org.mt

Terms of Reference

1.0

SCOPE OF WORKS The scope of works is to supply, install, connect, test and commission the main ventilation plant serving Hexagon House in Blata l-Bajda, Malta.

MAIN VENTILATION PLANTS SERVING THE EAST AND SOUTH BLOCKS Works shall include the supply installation, testing and commissioning of: Two new air-handling units complete with supply and extract fans, heat recuperators, filters, specialized activated carbon filters, cooling coils and heating coils, inclusive of new ductwork in polyurethane sandwich panel to connect to ductwork provided by third parties, Office zone air differential pressure control equipment, each zone comprising of a differential pressure sensor and two variable air volume controllers capable of controlling and measuring the total supply and extract air flow rates to / from each office zone.

AUTOMATIC CONTROL SYSTEM Works shall include the supply installation, testing and commissioning of: A motor control panel inclusive of connecting up of the main power supply cabling (provided by others) to the panels incoming isolator, All outgoing power cabling and isolators inclusive of containment in enclosed cable trays for the air handling units supply fans, extract fans, actuators (provided as part in this package and the 4No motorized diverting valves provided by others), AHU internal lighting and safety devices, duct mounted accessories such as VAV boxes etc., All sensors and actuators forming part of this control system, All outgoing control cabling to sensors and actuators inclusive of containment in enclosed cable basket, Provision of human machine interfaces on the control panel and another on a remote control panel located inside the facility managers office that allow control of the main ventilation plant, monitoring of the air-flows through each VAV box and the differential pressure in each office zone, controlling and monitoring leaving air temperatures, monitoring activated carbon filter temperature and relative humidities, A control system capable of controlling the plant to achieve individual office zone differential pressure control, supply air temperature controls, free cooling controls, AHU fan speed regulation etc.

ASSIGNMENT OF WARRANTED PROJECT ENGINEERS Works shall include the provision of contractors project engineers (mechanical and electrical) to ensure and certify that all the plant and equipment selected, installed and commissioned is capable of achieving the design intents.

ADDITIONAL OPTIONAL WORKS Optional works are works in which the client may be interested to order at any time during the execution of the scope of works until formal handing over acceptance by the client. Such additional works may include the supply installation, testing and commissioning of: An indoor air quality monitoring system with the scope of limiting the amount of outdoor air delivered to each office zone when the AHU is not operating in free cooling or free heating modes, in order to reduce energy consumption by the main ventilation fans, chiller and heatpumps, whilst at the same time maintaining the office zone differential pressure.

2.0

PRELIMINARIES 2.1 Prior to the tendering procedure, the tenderers are to visit the site and agree with the client on the location of the main plant in order to enable them to quantify the length of pipework, cabling, cable baskets, cable trays, cabling etc. required. The tender submittal shall include in the offer a drawing indicating the pre-agreed location of main equipment and routing of pipework, cabling, cable trays and cable baskets. Quoted prices are to include for coordination with all other contractors on site. To include for craneage of all equipment as necessary. To allow for the presence of a technical quality assurance manager throughout the execution of the project with respect to procurement, installation, commissioning and handing over. All openings in walls and ceilings shall be marked, opened and made good by the contractor after receipt of a confirmation to proceed by the client or their representative structural engineers. All electrical works in this tender document shall be carried out by Licence B electricians. The Contractor shall ensure that all the work is carried out in the most diligent, competent and professional manner to ensure a high standard of workmanship. He shall ensure compliance with all the relevant local legislation in particular Health and Safety and the current Electrical Supply Regulations. All prices quoted in the attached bills of quantities are to exclude VAT, but are to include any other taxes and levies as might apply. VAT shall only be entered in the tender summary page. Design temperatures The internal design conditions are indicated in the enclosed VRF schedule. The capacities of all equipment have been calculated around these conditions and tenderers are to ensure that all equipment offered is like wise suitably sized. Peak outdoor air conditions are to be taken as 35 C, 43% r.h. Noise levels All systems shall be selected, designed and installed to produce sound pressure levels within the occupied space that do not exceed the Noise Criteria (NC) or Noise Ratings (NR) listed in the enclosed schedule. Any noise attenuators or acoustic treatment required shall be deemed to have been included as necessary, even if such attenuators are not shown on the drawings.

2.2 2.3 2.4

2.5

2.6

2.7

2.8

2.9

2.10

2.11

Vibration transmission Vibration transmission from the equipment to the building must be eliminated by means of appropriate anti vibration mountings. These mountings shall be supplied with the equipment and included in the tendered price. Compatibility with the marine environment Air cooling coils should be treated against potential corrosion by manufacturer approved methods to provide a warranty of 10 years. Neatness of installation The installation is therefore required to be neat, linear, level, orderly and having a good visible surface finish. Pipe sizes Pipe sizes referred to in these documents refer all to the internal clear bore diameter. Design and re-design as part of the scope of works Part of the scope of this work is to carry out re-designs that may be necessary in order to achieve proper co-ordination with building structure, finishes and other M&E services. Such designs and re-designs shall be limited in nature to maintaining the overall performance concept of the installation as per the annexed drawings. It shall include any pipe sizing, duct sizing, indoor unit selection, air terminal selection, re-routing of ductwork, pipework, calculation of head losses from fans and equipment, acoustic calculations and selection of noise attenuating devices, vibration calculations and selection of vibration attenuating devices, that may arise during the project due to either the need for co-ordination of services or any site instructions that may be issued by the client and / or consulting engineers.

2.12

2.13

2.14

2.15

2.16

Electrical equipotential bonding All earthing requirements shall comply with the 16th Edition of the I.E.E. regulations, and current Enemalta requirements. All copper earthing material shall be BS approved and intended for use in earthing installations. In particular all mechanical equipment and fluid conveying systems such as AHUs, fans, chillers, VRFs, metal ductwork, aluminium grilles etc. shall be earthed by means of earth wiring in order to ensure continuity between sections such as between flanges of ductwork, between motor anti-vibration mountings and supporting frames, between supporting structures with rubberised footings and earth itself.

2.17

Fire stopping Wherever services pass from one fire compartment to another, approved fire stopping material is to be applied by the Contractor to all service penetrations including cable trunking, cable trays, etc., and between sleeves and the service passing through them.

3.0

TECHNICAL SPECIFICATIONS 3.1 AIR-HANDLING UNITS The air-handling units for the offices shall be modular air-handling units constructed for internal or external installation depending on the final installation location. The construction shall be from extruded aluminium profiles and sandwich type panels with a minimum thickness of 40 mm, galvanized sheet steel inner and outer leaves. Insulation shall be of the injected polyurethane type with a possibility of an additional mineral wool acoustic blanket for improvement of acoustic insulation.

Access doors with fasteners for quick opening shall be available for all functional and maintainable elements of the air-handling unit such as heat recovery unit, filters, fans, dampers, actuators, cooling coils, heating coils, droplet eliminators, fans and motors. Fan and filter sections shall be equipped with a viewing window and a luminaire with externally mounted weatherproof isolator and interconnecting power supply cabling.

3.1.1

General construction specifications

Air handling units designed as modular section units consisting of selfsupporting frame, airtight panels, base frame and internal components for airconditioning. Manufacturing and quality assurance according ISO 9002. AHUs shall have their EN1886 construction claims Eurovent certified. The AHU construction in accordance to EN1886 and all standards referred to in EN1886. Examples of such referenced standards are EN292-2 for mechanical safety of fans, EN61310-1 with respect to signage. The construction of the AHUs shall conform to the following minimum specifications as classified in EN1886 3.1.2 Casing strength class Casing air leakage Filter Bypass leakage Thermal performance of casing Thermal bridging factor D1 L1 F9 T3 TB3

Construction

The self-supporting frame is to be made of extruded aluminium profiles giving a great rigidity, quality Al Mg Si 0.5 F22 according to DIN 17.162, with special grooves for a perfect joint sealing with rubber resistant to ageing where the airtight panels are attached to the frame. Inside the self-supporting frame corners a special aluminium piece is placed to provide rigidity to the unit and to avoid the structure to get out of shape. Every module of the unit shall consist of an individual frame, all assembled by screws with a sealed joint, to result in a perfect airtight unit. The wall, ceiling and bottom airtight panels of the unit are to be all sandwich type with at inner side of least 1.0 mm thick galvanised sheet steel, quality St02Z/200 according to DIN 17.162, and an outer 1.0 mm thick galvanised sheet steel, outside surface coated in to a color as approved by the client or project manager according to ASTM-525-A, and internal insulation with polyurethane rubber, to achieve a thermal insulation U-Value of at least 0.43 W/mK. The panel thickness shall be at least 40 mm. The panels are to be screwed to the frame to provide smooth external and internal surfaces to allow an easy cleaning of the units. Access doors for maintenance and airtight panels are to be of the same construction and are to be provided with a quick release device for an easy opening and closing, hinges to enable the opening from inside to avoid accidents and also special aluminium hinges.

The access doors for fan sections are to be provided with a double-glass inspection round window. Thermal insulation with polyurethane rubber: 0.43 W/(mK) The panels shall achieve a minimum reduction of the radiated noise levels in each octave band according to the following table: (Hz) (dB) 63 27 125 26 250 29 500 42 1k 41 2k 39 4k 41 8k 37

Additional acoustic cladding may however be required to be installed on-site if the unit does not achieve acceptable external noise levels. The aluminium frame of each module is to be attached to a base frame providing stability and through several points of linkage to facilitate cranage lift of the whole assembled air-handling unit or to facilitate its transportation on a fork-lift truck. The base frame shall consists of carbon steel cold shaped profiles, quality St37.2 according to DIN 17.100, coated in URKI-NATO RAL3000, assembled as a rectangle to match the perimeter of the module, with enough crossing steps depending on the module dimensions. The base frame and the self-supporting frame are screwed. In the same way the base frame is to be equipped with drilled holes to enable the joining of the modules with screws which are to be supplied by the AHU manufacturer. The panels shall include 20 mm diameter sealable rubber bushes upstream and downstream of each equipment (fan, filter, coils, droplet eliminators, sound attenuators etc.) to permit the insertion of monitoring equipment such as micro-manometers, temperature and relative humidity meters. The construction shall be suitable for an external installation. It shall therefore include a cleanable weather and acid-rain resistant surface and protection for all structural joints of the AHUs external surfaces.

3.1.3

Fans and motors

Supply and return fans shall be with backward inclined curved blades to present a non-loading power characteristic when the fan operates at low external static pressures. Alternative plug fan type for a very compact construction design however may also be considered. All single or three phase motors shall be equipped with a PTC for a fail safe operation. Impeller shall be made from sheet steel with a powder coating for surface protection. The fan shall be equipped with a rotating diffuser to provide high efficiency and good acoustic performance. The fan section shall include the following accessories: Viewing window with double skinned glass, Safety wire mesh behind inspection door sized for a maximum deflection of 5 mm with fan operating with open door, Externally mounted variable speed drive (with enclosure suitably rated for indoor or outdoor application depending on the installation location of the air-handling unit) (variable speed drive shall be provided from AHU supplier) Factory fitted power cable entry point with sealable rubber grommets. Factory fitted isolator Factory fitted emergency switch Differential pressure sensor for fan operation indication

Pressure tappings on fan for air flow measurement on data provided by the fan manufacturer Notes: 1. The fans are to be selected with an allowance for the internal ESP of the fans based on the filters in a Dirty condition as recommended by the filter manufacturer or similar to those in the technical schedules (Data sheets of separate filter manufacturer are to be annexed)

3.1.4

Filters

The filter media shall be fire resistant synthetic material with a filtering efficiency as shown in the drawings and schedules. Panel filters are to be mounted on guide rails to facilitate side withdrawal. Bag filters and mini-pleat filters are to be mounted with fixing spring clips on special galvanized sheet steel frames suitable for the type of filter used. Particulate filters are to be mounted on special frames completely welded with an air tightness device of the filtering cells to guarantee air tightness between the clean and dirty filter sides. Each filter section shall be provided with an externally mounted magnehelic gauge and a differential pressure sensor for remote filter condition monitoring. A spare set of filters shall be provided for each one installed as per Bill of Quantities Specific notes: 1. The activated carbon filters specified are intended to remove as much as possible odours from adjacent facilities including oil bunkering, ports, dock yards etc. To this effect they shall be specially impregnated grade selected for an enhanced take-up of mercaptans, organo-sulphurs and acid gas odours with a dwell time of at least 1 second and an adsorption efficiency of approximately 99.5%. The carbon cells in the first pass shall have a 25,000 hours operating time based on inlet concentrations of 0.1 ppm hydrogen sulphide (0.14 mg/m), 0.01 ppm each of methyl mercaptans (0.02 mg/m), ethyl mercaptans (0.026 mg/m) and skatole (0.055 mg/m). Different options can be provided for evaluation purposes. 2. The activated carbon filters to be supplied for this project are to be capable of operating in an optimum range in Malta at the heat recovery units supply air conditions specified in the project schedules. 3. The activated carbon filters offered with the units must be submitted for clients approval before the offer is submitted for approval, alternatively the tenderers can submit the cost of the AHU with different types of activated carbon filters, the tendered price shall be the more expensive option with possible cost savings included as options in the offers covering letter. 4. All AHU filter banks are to be site tested and certified by the contractors warranted mechanical engineer for filter bypass leakage using the methods indicated in EN1886

3.1.5

Ventilation Heat exchangers

recovery

Equipment:

Cross

flow

heat

The plate heat exchanger shall be designed for optimum heat transfers between the supply and extract air streams. Specifically for this project the heat recovery equipment shall be sealed to ensure that there is no cross contamination between the supply and return air streams. It shall be equipped with a by-pass damper and factory fitted on-off actuator to allow free-cooling and free-heating by the control system / BMS. The minimum heat exchange efficiency of the selected heat recovery equipment shall be 51% at design flow rates; the maximum pressure drop of the heat exchangers shall not exceed that mentioned in the AHU schedules.

3.1.6

Cooling and heating coils

Cooling and heating coils are to be manufactured of copper tube and aluminium bonded fins. The AHU section is to be provided such that the air velocity at the cooling coils does not exceed 2.5 m/s The coil shall be equipped with an automatic air-vent, site installed drain valve with hose connector. Cooling coils shall have polypropylene droplet eliminator, condensate drain tray, drain pipe to outside, primable p-trap capable of maintaining a water seal even in the when the fan operates at its maximum static pressure.

3.1.7

Sound attenuators

The units shall include any attenuators required to ensure that the system noise breakout is in accordance with the noise levels specified for each space. The sound attenuators shall be steam washable and manufactured from high quality anti-molding material. The sound attenuators shall be provided from the AHUs supplier.

3.2

HVAC CONTROL SYSTEMS 3.2.1 Motor control centres

Control Panel Design For the purpose of operation and safety, the panel shall be considered as one assembly and shall have a common appearance, layout, etc. Details of all panels must be approved by the client prior to ordering. These shall include the panel fascia drawings showing the intended monitoring and control stations or alternatively screenshots if the contractor opts to provide an HMI in the form of a touchscreen pc. The contractor shall also submit wiring diagrams of the proposed panels together with a written sequence of operation. The layout of control panel shall reflect the layout of the plant being served. Indicators and controls for associated plant shall be grouped together.

All doors in any panel containing exposed dangerous voltages shall be provided with interlocked isolators such that the door cannot be opened except with the isolator in the 'Off' position. Isolation shall comply with BS 7671. Equipment which requires on-line adjustment and testing by non-electrically qualified personnel must be accessible and usable without interrupting the supply or overriding safety interlocks. The cubicle shall be fitted with a hinged, lockable door. The control panel shall be designed to maintain all components within their environmental temperature tolerance limits, having regard to the likely conditions in the area of installation. When the temperature cannot be maintained by means of natural air convention the contractor shall provide mechanical ventilation. Incoming air shall be filtered, the filters being of the replaceable disposable type. The control panel, complete with its electrical components, wiring, etc. shall conform to BS 7671, including all latest amendments.

Control Panel Labelling All panels and individual panel sections shall be provided with exterior labels to BS 5378, Part I indicating the voltage within the panel section, clear warnings of risk and instructions for isolation. All switches, controls and indicators on control panels and cubicles shall be clearly labelled as to function and associated plant. If the panel does not totally control the supply of electricity to associated plant then a notice affixed to the front of the panel shall warn of the need for isolation elsewhere. All cables shall be identified with permanently fixed numbered ferrules. The numbering shall correspond to the numbers affixed to the terminals. Identification and coding should be that used on the design drawings, schematics and schedules.

Control Panel Construction Control panel shall be constructed to IP54 when sited internally. Externally located panels shall be constructed to a minimum of NEMA 4 or IP65. The doors and casing shall be galvanised sheet steel, minimum thickness 14 gauge, folded and seam welded to form a rigid self-supporting structure. Bracing and stiffening shall be used as necessary to take the weight of internal components and control assemblies. No sharp edges or corners shall be accepted. The panel doors shall be front hinged and the complete casing shall be stove enamel finished. The panel shall be manufactured by a reputable supplier who is ISO 9001:2000 certified and has experience in panel building of at least 5 years. Control panel shall be of the wall or floor mounted type. Panel shall have eyebolts fitted to facilitate delivery and installation. The panel shall have approximately 20% free space to facilitate the addition of future equipment over and above the optional systems described in the specifications and bill of quantities.

It shall be provided with adequate undrilled and / or detachable gland plates of sufficient size and strength to accept glands for all types of cable conduits and cable trunking/ trays or ladders intended for termination with the panel. All wiring within the panel shall be arranged in looms and / or perforated trunking. All cables shall run continually from terminal to terminal without intervening joints. Panels shall be internally partitioned to provide separation as a means of safety, wherever necessary. All termination shall be fully shrouded, recessed or otherwise protected against accidental contact. Where live equipment cannot be isolated then it shall be covered with a perspex shield carrying appropriate warning labels in addition to specified shrouding. Wiring looms, cable ways and trunking should be sized to allow for 25% expansion or addition. Flexible looms shall connect door mounted to interior mounted components such that wires shall not weaken or break with repeated door opening. The loom shall be arranged to avoid pinching or looping as the door is closed and be fully supported at each end. Indicator lamps shall be LED type. The panels shall incorporate all the necessary equipment, including motor rated MCCBs or MCBs, contactors / starters with overloads, start / stop buttons, run / trip indication, speed indication, hand / off / auto switches, auxiliary contacts, relays, insulated transformer, means of isolation, wiring etc. to provide the facilities listed hereunder and in the MCC schedule. Phase indicating lights 1. Lamp test facility 2. Lockable isolating handle 3. Main flasher/audible unit located on the top part of the panel to indicate an alarm condition on any equipment. Trip alarm indication inside the panel via adequate 24 volt relays with remote audio/visual alarm inside the Engineering Workshop. 4. Phase failure unit 5. Emergency stop push button allowing manual shutdown of the complete panel 6. Complete shutdown of the panel upon receiving a signal from the Fire Alarm Panel interface. 7. Control circuit with MCB, On lamp, insulated transformer, relays, etc. for the control circuits necessary. 8. Interlocks as detailed in the specifications and schedules and as may be necessary for the safe operation of the equipment. A local means of isolation shall be provided adjacent to each item of equipment The contractor shall provide a fully enclosed shed type room for all control panels that are intended to be located outdoors. The room shall be equipped with lockable 1.2 m wide doors, lighting installation capable of achieving a minimum of 800 lux, ventilation system (natural or mechanical) capable of maintaining the control panel at an acceptable temperature throughout the year and for all loads required by motors.

10

3.2.2

Control System Functional Description

General Requirements (applicable to all AHUs) Filter condition monitoring Cleanliness of filters shall be monitored via a differential pressure switch (provided by the AHU supplier), when the differential pressure as sensed by the switch exceeds the filter manufacturers recommended value, the control system shall give rise to a flag in order to alert that the filters need to be replaced. AHU Fan condition monitoring Supply fans shall be monitored for their status via either a fan differential pressure switch (provided by the AHU supplier) or through the overload switch located in the MCC. Fire detection monitoring Should a fire occur inside any part of the building served by the AHUs, as signalled by a fire alarm interface (provided by other) located adjacent to the MCC, the MCC shall provide the following signals to the respective AHU: - Disable supply fan - Disable extract fan, - Close outdoor air intake damper, - Close return air damper, This feature shall be a hard-wired feature in the MCC (i.e. not through a controller), its operational status shall be however monitored via a controller in order to know that the fans and cooling systems are disabled. Free cooling and heating In those instances when cooling is required (T actual > T setpoint) and the outdoor air temperature is cooler than the return temperature, the heat exchanger is to be bypassed (provide a signal to the AHU supplier provided on/off by-pass actuators), open the fresh air damper to their maximum position to admit the maximum possible amount of outdoor air to cool the served zone naturally, open the zones VAV boxes in a manner that maintains the same proportional air volume flow rates between the various VAV boxes. (This is applicable even for units without heat exchangers). The converse shall apply on free heating.

Particular Requirements for AHU-East, and AHU-South) General (for AHU-East and AHU-South) The Office block areas shall have their ventilation served through AHU-East and AHU-South. These shall comprise of a supply and extract fan, heat recovery ventilation element with free cooling bypass damper, filters capable of delivering air filtered to at least F7 quality, activated carbon filters, cooling coils heating coils and if necessary sound attenuators. AHU Fan operation The AHU fans shall be started on receipt of a signal to start the ventilation system. The signal shall be received via either a room mounted switch located near the reception or through the MCC fascia or through a remote location through an internet connection. Once the signal is received, the AHU intake and exhaust dampers shall fully open and once a confirmation is received from the damper limit switches that both dampers are fully open, the fans shall ramp up (via the AHU supplier provided speed drives) to a desired speed (full speed as commissioned, or to a manually selected speed). The AHU fan speed shall also be user

11

adjustable from the MCCs HMI (Human Machine Interface, which may be a touch screen based controller The fan speed shall normally be controlled to maintain a constant duct static pressure as sensed by static pressure sensors installed on the supply duct and on the return duct. Location of installation of the duct static pressure sensor shall generally be circa 2 metres (upstream for supply and downstream for return) away from the farthest VAV box or closable air terminal from the AHUs fan Both AHUs shall have the total air volume flow monitored by means of a summation of the signal from the VAV boxes, which shall be averageable every 0.5 seconds. Alternatively the units may be equipped with flow grids c/w volume air-flow display in m/h (not shown on the drawings and BOQs) on the following ducts: (main supply duct, main return air duct) Cooling or heating control When air-flow is proven across the AHUs supply fans via their differential pressure switches, the cooling or heating mode is enabled (cooling or heating mode is selectable from the user interface and will effect the mode of operation of the AHUs respective heatpump chiller by providing a signal to the LON gateway provided with the chiller CH-01 and heat pump HP-01, provided by others). The system shall control the supply duct temperature. Modulating control shall be done in the following sequence (described in cooling mode but the reverse shall also apply to heating mode): When the unit is not in free-cooling or free-heating modes: Modulate the chillers leaving water temperature, up to an adjustable maximum value as recommended by the chiller and heat pump manufacturers (by providing a signal through the chiller and heat pump LON gateway provided by others), Modulate the AHUs three way valve (cooling or heating depending on mode of operation) (three way valve and actuator provided by others) When the unit is in free cooling or free-heating mode: Start the disabling sequence of the chiller or heat pumps, their associated pumps and place the three way valve in diverting mode. The temperature set-point shall be user adjustable via the MCCs HMI (Human-Machine Interface), or through a remote panel. The controller shall modulate the position of the chilled water control valve in response to the demand for cooling or heating. In addition the system shall also provide a monitor of the actual supply duct temperature and relative humidity. The system shall have in addition a control loop pre-programmed to facilitate control of supply duct temperature and humidity in the summer months by having the cooling coil and chilled water temperature controlling the supply duct moisture content to the moisture content calculated from the desired supply duct temperature and relative humidity, while the heating coil will re-heat the supply air to the desired supply air temperature as necessary. This total control function will have the possibility of being disabled in favour of the supply duct temperature only control function. Heat exchange control When air-flow is proven across the AHUs supply fan via the differential pressure switch, the heat exchange cooling mode is enabled.

12

The system shall operate the heat exchanger in recovery mode as long as: - In cooling mode: Tsupply air > Tsupply air set-point AND Treturn air < Toutdoor air, and - In heating mode: vice versa. The supply duct, return duct and outdoor air duct temperature sensors are to be provided by the controls contractor. The supply duct temperature set-point shall be adjustable via a space provided HMI and / or through a remote panel. Activated carbon filter air condition monitor The temperature and relative humidity of the activated carbon filter bank shall be monitored via AHU mounted sensors. If the temperature or relative humidity on the activated carbon filters drops below the minimum values or rises above the maximum values recommended by the activated carbon filter manufacturer, an alarm is raised and the user shall be requested to confirm whether they require the fan to be disabled or override the alarm. Office zone air differential pressure control This function shall take precedence over all other temperature control or energy control functions but not safety functions such as disabling of the ventilation systems in case of fire. Each office zone shall have their differential pressure monitored and controlled via a sensitive air differential pressure sensor, to ensure that each office zone is maintained at a positive pressure with filtered air with respect to the external unfiltered environment. In normal operation the supply air volume shall be maintained constant by the VAV box to a client agreed air volume flow rate, to ensure adequate ventilation of the building. The room pressure control shall monitor the office zone air differential pressure and modulate the position of the office zone return air VAV box to maintain a constant user-adjustable differential pressure Other monitoring only functions The control system shall also enable the monitoring only of the following parameters that have not been listed in the preceding sections: Office zone supply air flow rate, Office zone return air flow rate, Office zone differential pressure, AHU entering water temperature, AHU leaving water temperature, Chiller entering water temperature, Chiller leaving water temperature, AHU supply duct temperature, AHU return duct temperature Alarms Raised The control system shall provide the following alarms that may not be mentioned in the preceding sections: Activated carbon filter temperature outside the recommended range Activated carbon filter relative humidity outside the recommended range Office zone differential pressure low (adjustable for example to 3 Pa and critically low for example less than 1 Pa) AHU total return air flow rate low (user adjustable setpoint monitored through summation of all associated VAV boxes or via the inclusion of a flow grid on the supply and return ducts that are not shown on

13

3.3

the drawings and BOQs) warning of Potential loss of heat recovery performance and overloading of chillers and heat pump. AHU supply fan tripped AHU return fan tripped Chiller tripped Chiller circulating pump tripped Heat-pump tripped Heat-pump circulating pump tripped

AIR CONTROL EQUIPMENT 3.3.1 VAV Boxes

Materials: Casing in galvanised sheet steel, aluminium sensor tubes and blades, gear wheels made of antistatic plastic (ABS), heat resistant up to 50 C. Selection based on duct dimensions. Simple setting by the customers of the volume flow with Vmin and Vmax adjustment potentiometers with percentage scales. During the installation or commissioning of controller, adjustment is possible without supply voltage. The controlled is to have a transparent protection cover that prevents inadvertent resetting and provides general security. The control damper blade shall be delivered in a 45 position in order to allow ventilation air flow without additional control functions. Required characteristics: Flow rate adjustment without adjustment tool Functional testing with service button Functional check by indicator light Factory functional testing of each unit using a dedicated test rig High visibility external indicator light for signalling the functions: (Set, not set and power failure). Functional testing of actuator CLOSED, OPEN and control operation shall be possible with service button. Electrical connections with screw terminals, terminal for looping the supply voltage (24 V shall be acceptable), i.e. for the connection of simple voltage transmission to the next controller. Wire clamping bracket fixed to the casing. Voltage range for control and actual value signal 0 to 10 VDC. Possible override controls with external switches using potential free contacts: CLOSED, OPEN, Vmin or Vmax. The price quoted for all the VAV boxes shall include allowance for the electrical power supply system to the VAV boxes which shall be taken from an adjacent suitable essential powered isolator (as provided in the electrical volume of this project). The electrical power supply system to all VAV boxes is to be designed and installed as part of the scope of works of the scope of works of this work package. General requirements for this project: 1. All VAV boxes shall be insulated with factory fitted acoustic and thermal insulation which shall be 40 mm thick mineral wool. 2. It will also be acceptable if the contractor alternatively provides a LON gateway on the VAV boxes and connect the gateways to a high level interface in the control panel.

14

3.3.2

Volume flow rate measuring units

These shall be used in conjunction with the VAV boxes (if not integrated with the VAV boxes themselves) and also on the main supply and extract air ducts of the ventilation AHUs. Volume flow rate measuring unit for continuous monitoring of the actual flow rate in ventilation ducts. Consists of circular or rectangular housing with averaging differential pressure sensor grid and factory fitted, pre-wired static pressure transducer. Same connection diameter on both ends with groove for lip seal, to fit ducts DIN 24 145 or DIN 24 146. Measurement accuracy 5 % even with unfavourable supply and extract ducting arrangements. Pressure drop 10 % to 26 % of measured pressure differential depending on size. Materials: Galvanised steel casing and attachments Aluminium sensor tubes Included with insulation for tempered air carrying ducts

3.3.3

Fire / Smoke dampers

Shall be compliant with applicable EN standards. They shall be complete with position microswitch, and ceiling mounted position indicator.

3.4

DUCTWORK The scope of work Is to supply, install, test and commission the following ductwork on both AHU-East and AHU-South: Outdoor air intake duct with rain water ingress protection located at least 5 metres away from exhaust air points, Exhaust air ductwork with rain water ingress protection, Connect to the AHU supply duct to the supply air ducts provided by others Connect to the AHU exhaust duct to the exhaust air ducts provided by others The contractor shall be responsible to check the actual building dimensions, shape and other relevant details before starting the fabrication of ductwork. Any duct off sets that may be required to fit in the space available shall be deemed to have been included in the tendered price and no additional payments shall be made in this respect. All seams, joints and connections between the ducting sections and the connections to the plant shall be made in a manner which shall reduce air leakage to a minimum. Internal roughness and obstructions to the air flow (other than dampers, vanes etc.) shall not be accepted. Connections to the equipment shall be made with angle flanged joints and flexible canvas connections. Bends and offset shall have a minimum throat radius equal to the width of the duct at that section. Mitred 90 bends will be considered acceptable in the event of space constraints and subject to the inclusion of turning vanes as per SMACNA and CIBSE standards that lower the loss coefficient to values less than 0.13 All supports, hangers bolts nuts, drop rods etc., shall either be galvanised or else, shall be cleaned and coated with two coats of galvanic paint to avoid rusting.

15

3.4.1

Pre-Insulated sandwich panel ductwork

All duct work used for conditioned air systems shall be manufactured from rigid expanded polyurethane foam. The duct panels shall have embossed aluminium foil on the external surface of the panel and smooth aluminium foil on the internal surface. Sections cut from panels to construct the duct shall have edges cut at 45 and bonded together using recommended adhesives. Internal corners of ductwork shall have a silicon type sealer applied and aluminium foil tape shall be applied on all the external edges. Edges of all the panels at all joints, transition pieces or connection to the air devices etc., shall be reinforced using suitable and proprietary metal profiles. Joints between panels shall have a gasket between the metal profiles and another interlocking profile to ensure the panels are held securely together. Panels held together with adhesive and or tape only will not be accepted. Duct stiffeners and supports shall be included as recommended by the panel manufacturers. The manufacturer's recommended spacing of the supports required shall be submitted before duct work is fabricated. The following material specifications shall apply: General ventilation systems: Internal ductwork: 20 mm polyurethane thickness with 80 micron thick aluminium foils face on the internal and external side. External ductwork: 32 mm polyurethane thickness with 200 micron thick aluminium foils face on the internal and external side. The external duct side shall in addition be painted with two coats of rubberized paint to the colour approved by the client.

3.4.2

Air tightness

Ducts shall be constructed to achieve an air-tight construction having a maximum leakage of 1.0% of the design system. Ducts are to be pressure tested as per HVCA DW/143 standards.

3.4.3

Air balancing

Accuracy level to be achieved is 7.5% of the design flow rates.

3.4.4

Installation workmanship management procedures

and

testing

standards

and

All installation and testing procedures shall comply and be carried out in accordance to the following standards specifically the sections relevant to this project: HVCA Guide DW/145: Guide to Good Practice for the Installation of Fire and Smoke Dampers HVCA Guide DW/143: A Practical guide to ductwork leakage testing HVCA Guide DW/144: Specification for Sheet metal ductwork HVCA Guide DW/TM2: Guide to good practice: Internal Cleanliness of New Ductwork Installations

16

HVCA Guide DW/TM3: Guide to good practice for the Design for the Installation of Fire and Smoke Damper HVCA Guide TR/17: Guide to good practice: Cleanliness of Ventilation Systems A copy of the above guidelines is to be made available on-site for quick reference by the foreman and quality assurance manager in charge. Adequate records and proof of carrying out the procedures described in the above shall be provided, and these are to be certified by the contractors quality assurance warranted mechanical engineer. The quality assurance mechanical engineer shall be required to be present on site throughout the execution of all these tests in order to ascertain fulfillment of these requirements.

4.0

DOCUMENTATION The contractor shall supply full documentation for all works carried out. The documentation shall be in the English language, and shall comprise the following: Detail and installation drawings As-built drawings Details of all items as far as they deviate from the design given to the contractor Spare parts lists, if any List of all replacement parts subject to wear Manufacturer documents, technical specifications, sorted per item Owners manuals, Operation instructions Maintenance Instructions, if any Testing documents required by local authorities All test certificates All documents must be supplied in A4 folders, drawings folded to A4 format. All documents shall be supplied in electronic format on a CD as well, drawings in DWG AutoCAD 14 Format.

5.0

TIMELINE The supply and delivery of the system must be in 8 weeks from the date of signing the contract and the commissioning in the next 3 weeks.

6.0

REPORTING The Contractor shall report to the MEPAs Director Corporate Services or his delegated representative..

7.0

PAYMENT Payment will be made 45 days from the date of invoice after final successful commissioning is completed. A 10% retainer will be kept for 6 months.

8.0

WARRANTIES 8.1 Definitions

The following words and expressions shall have the meanings hereby assigned to

17

them, except where the context otherwise requires: (i) (ii) "Employer" means The Malta Environment and Planning Authority "Contractor" means the person whose Tender has been accepted by the Employer and the legal successors in title to such person, but not (except with the consent of the Employer) any assignee of such person. The Engineer means the person, engineer, firm, company, or corporation authorised in writing by the Employer in respect of the exercise of certain rights and powers of the Employer under the Contract. Taking-Over Certificate

(iii)

8.2

When the whole of the Works have been substantially completed and have satisfactorily passed any Tests on Completion prescribed by the Contract, the Contractor may give a notice to that effect to the Engineer, with a copy to the Employer, accompanied by a written undertaking to finish with due expedition any outstanding work during the Defects Liability Period. Such notice and undertaking shall be deemed to be a request by the Contractor for the Engineer to issue a TakingOver Certificate in respect of the Works. The Engineer shall, within 21 days of the date of delivery of such notice, either issue to the Contractor with a copy to the Employer, a Taking-Over Certificate, stating the date on which, in his opinion, the Works were substantially completed in accordance with the Contract, or give instructions in writing to the Contractor specifying all the work which, in the Engineer's opinion, is required to be done by the Contractor before the issue of such Certificate. The Engineer shall also notify the Contractor of any defects in the Works affecting substantial completion that may appear after such instructions and before completion of the Works specified therein. The Contractor shall be entitled to receive such Taking-Over Certificate within 21 days of completion, to the satisfaction of the Architect, of the Works so specified and remedying any defects so notified.

8.3

Taking Over of Sections or Parts

Similarly, in accordance with the procedure set out in Sub-Clause 8.1, the Contractor may request and the Engineer shall issue a Taking-Over Certificate in respect of: (a) any substantial part of the Permanent Works which has been both completed to the satisfaction of the Engineer and, otherwise than as provided for in the Contract, occupied or used by the Employer, or (b) any part of the Permanent Works which the Employer has elected to occupy or use prior to completion (where such prior occupation or use is not provided for in the Contract or has not been agreed by the Contractor as a temporary measure).

8.4

Substantial Completion of Parts

If any part of the Permanent Works has been substantially completed and has satisfactorily passed any Tests on Completion prescribed by the Contract, the Engineer may issue a Taking-Over Certificate in respect of that part of the Permanent Works before completion of the whole of the Works and, upon the issue of such Certificate, the Contractor shall be deemed to have undertaken to complete with due expedition any outstanding work in that part of the Permanent Works during the Defects Liability Period.

8.5

Surfaces Requiring Reinstatement

18

Provided that a Taking-Over Certificate given in respect of any Section or part of the Permanent Works before completion of the whole of the Works shall not be deemed to certify completion of any ground, roof or surfaces requiring reinstatement unless such Taking-Over Certificate shall expressly so state.

9.0

DEFECTS LIABILITY 9.1 Defects Liability Period

In these Conditions the expression "Defects Liability Period" shall mean the defects liability period calculated from: (a) the date of completion of the Works certified by the Engineer in accordance with Clause 8, or (b) in the event of more than one certificate having been issued by the Engineer under Clause 8, the respective dates so certified, and in relation to the Defects Liability Period the expression "the Works" shall be construed accordingly. The defects liability period for this contract shall however be not less than 24 calendar months from the date of certification by the Engineer

9.2

Completion of Outstanding Work and Remedying Defects

During the Defects liability period, the Contractor shall: (a) complete any minor works, if any, outstanding on the date stated in the Taking-Over Certificate as soon as practicable after such date, and (b) execute all such work of amendment, reconstruction, and Remedying defects, shrinkages or other faults as the Engineer may, during the Defects Liability Period or within 14 days after its expiration, as a result of an inspection made by or on behalf of the Engineer prior to its expiration, instruct the Contractor to execute. The expiration of the Defects Liability Period shall not exonerate the Contractor from any further liabilities arising at Law.

9.3

Cost of Remedying Defects

All work referred to in Sub-Clause 9.2 (b) shall be executed by the Contractor at his own cost if the necessity thereof is, in the opinion of the Architect, due to: (a) the use of materials, Plant or workmanship not in accordance with the Contract, (b) where the Contractor is responsible for the design of part of the Permanent Works, any fault in such design, or (c) the neglect or failure on the part of the Contractor to comply with any obligation, expressed or implied, on the Contractor's part under the Contract, If, in the opinion of the Engineer, such necessity is due to any other cause, he shall determine an addition to the Contract Price and shall notify the Contractor accordingly, with a copy to the Employer.

9.4

Contractor's Failure to Carry Out Instructions

19

In case of default on the part of the Contractor in carrying out such instruction within a reasonable time, the Employer shall be entitled to employ and pay other persons to carry out the same and if such work is work which, in the opinion of the Engineer, the Contractor was liable to do at his own cost under the Contract, then all costs consequent thereon or incidental thereto shall, after due consultation with the Employer and the Contractor, be determined by the Engineer and shall be recoverable from the Contractor by the Employer, and may be deducted by the Employer from any monies due or to become due to the Contractor and the Engineer shall notify the Contractor accordingly, with a copy to the Employer.

10.0

SUBMISSION REQUIREMENTS Tenderers will be requested to either clarify/rectify any incorrect and/or incomplete documentation and/or submit any missing documents within five working days from notification. The offer should be deposited in sealed envelopes entitled Tender for the Procurement of the Main Ventilation Plant serving Hexagon House in Marsa and referenced T10/2011 to the tender box at the MEPA premises in Floriana, by th Monday 06 June 2011 before 11.00a.m. A soft copy of the tender offer should be provided within the sealed envelope. Any questions concerning this call for tenders should be addressed to the Director of Corporate Services, Ing Ray Piscopo on email ray.piscopo@mepa.org.mt by not later than Tuesday 31st May 2011. Questions and answers, and alterations to the tender document will be published as a clarification note on the website of the Contracting Authority (http://www.mepa.org.mt/info-tender). Clarification notes will constitute an integral part of the tender documentation, and it is the responsibility of tenderers to visit this website and be aware of the latest information published online prior to submitting their Tender. Late or incomplete submissions will not be considered. Diversion from the specification will render the offer null and void.

11.0

CRITERIA FOR THE EVALUATION OF OFFERS The offers will be evaluated on the basis of the most economically advantageous tender approach. The following criteria will be used in the evaluation of submissions:
Adherence to specified technical requirements and delivery After sales services and availability of spare parts and technical expertise 80% 20%

The total attainable score is 100 points. To be considered for this contract, bidders must score at least 65 points. The contracting authority shall have the right to seek clarifications on points of a technical nature to enable a proper evaluation of any tender, which, however, would at that stage have already been declared to be basically compliant. The Most Economically Advantageous Tender (MEAT) is established by weighing technical quality against price on a [80/20] basis respectively. This is done by multiplying: the technical scores awarded to the offers by 0.80 the financial scores awarded to the offers by 0.20 MEPA reserves the right to refuse any offer, even the most advantageous.

20

Noise Schedules Area Noise Rating (NR) 30


1

Executive offices General office cubicles (two or more continuous occupants) Open plan offices Training room and auditoria Circulation spaces (corridors, stairwells, lifts) Entrance hall, lobbies Computer Rooms External Areas (tested diurnally on a weekday, Saturday and Sunday) External Areas (tested nocturnally on a weekday, Saturday and Sunday)

35 35 32 40 40 45 < 3db LAeq,T over background noise level < 3db LAeq,T over background noise level

Notes 1. The NR levels indicated in this schedule are the maximum permissible noise level generated from M&E equipment. Should any areas not be listed in the above schedules, reference should be made to CIBSE guide A. 2. The contractor is expected to carry out all necessary acoustic calculations based on construction and the equipment offered by himself and include in the tendered prices all the necessary acoustic damping measures in order to achieve a lower noise level than that specified in this schedule. Such measures may be included in the relevant section of the Bill of Quantities

21

AHU SCHEDULE
Job title: Hexagon House Ventilation system Date: Apr-11

General Reference Area served Type AHU-South North Office zone Double decker, cross flow HX w/ bypass, Height (mm) Length (mm) Width (mm) 3550 9600 (excl. silencers) 2100

Configuration Supply side: Intake air-tight shut off damper with actuator and limit switch, G4 pleated filters, F7 bag filters, heat recovery, fan expansion section, fan, flow expansion section, specialised activated carbon filters, compact F7 dust filters, cooling coil, droplet eliminator, heating coil

Return side:

G4 pleated filters, F7 bag filters, fan, fan expansion section, heat recovery with bypass damper and actuator, exhaust section, exhaust air-tight shut-off damper with on/off actuator and limit switch.

Side view of unit

Construction specification according to EN1886 Casing Strength: Casing air leakage: Filter bypass leakage: Thermal performance of casing: Thermal bridging factor: D1 L1 F9 T3 or better TB3

Connecting dimensions Intake damper size: Exhaust damper size: Return air frame size: Supply air frame size: 1600 x 1350 1600 x 1350 1800 x 1350 1800 x 1350

Fans Type Deliverable flow rate (m3/hr) Min motor & fan efficiency (%) Motor size (kW) Motor Service factor

Supply Backward inclined 21,060 80 11.0 with VF Drive 1.2

Return Backward inclined 17,118 78 7.5 with VF Drive 1.3

22

Coils Cooling Air flow rate (m3/hr) Max air pressure drop (Pa) Air on-coil conditions Air off-coil conditions Thermal power (kW) Water flow rate (m/h) Entering water temperature ( C) Max water pressure drop (kPa) Control method Electrical Power (kW) Number of steps Power Supply (V / ph / Hz) Humidification capacity (kg/h) 21,060 130 (when wet) 30.9 C d.b., 50.5% r.h. 16.5 C d.b., 95.9% r.h. 158.0 27.17 10 27.5 Control Valve Heating 21,060 48 14.5 C d.b., 62.5% r.h. 21.0 C d.b. 46.5 8.00 40 30 Control Valve -

Cross flow heat exchanger

(sensible type only with no cross leakage. With bypass dampers with on/off actuators) Summer Outdoor air side Return air side 17,118 110 24.0 C d.b., 45.0% r.h. Winter Outdoor air side 14,130 160 9.0 C d.b., 60.0% r.h. 14.5 C d.b., 62.5% r.h. Return air side 11,938 110 20.0 C d.b., 60.0% r.h.

Air flow rate (m/hr) Max air pressure drop at specified flow rate (Pa) Air on conditions Required air off conditions

21,060 160 35.0 C d.b., 40.0% r.h. 29.5 C d.b., 54.6% r.h.

Sound attenuation Comment Type Recommended min length (mm) Induct sound pressure loss (dB) Noise breakout loss (dB) Required on both supply and return air streams 900 As required to achieve noise criteria As required to achieve noise criteria

Filtration (each filter bank below to be equipped with pressure switch and magnehelic gauge) Location Type Grade Min / Max P at section's flow (Pa) DP to be allowed for internal AHU static pressure loss (Pa)

Outdoor air intake Outdoor air intake Return fan suction side Return fan suction side

Pleated Bag pocket insert Pleated Bag pocket insert

G4 F7 G4 F7

Included in below 172 / 350 Included in below 137 / 350

Included below 300 Included below 300

23

After HRV's supply side

Activated Carbon

(Impregnated type. See specification document)

115

120

Pre-coils

Compact rigid bag

F7

62 / 200

150

Notes: 1. Minimum ESP's for this project shall be 350 Pa. (The AHU is to be engineered with low pressure drop components in order to maintain the motor service factor specified above, when taking into account the filter p specified for the calculation of the internal AHU pressure drop) 2. Reference is to be made to the technical specifications for further details and the control schematic to illustrate the various AHU mounted sensors required 3. All dampers to come with factory fitted actuators.

Notes Project parameters highlighted in Blue: Not to be altered Other parameters may be altered depending on the performance of the thermal wheel offered

24

AHU SCHEDULE
Job title: Hexagon House Ventilation system Date: Apr-11

General Reference Area served Type AHU-East East Office zone Double decker, cross flow HX w/ bypass, Height (mm) Length (mm) Width (mm) 3150 8800 (excl. silencers) 1900

Configuration Supply side: Intake air-tight shut off damper with actuator and limit switch, G4 pleated filters, F7 bag filters, heat recovery, fan expansion section, fan, flow expansion section, specialised activated carbon filters, compact F7 dust filters, cooling coil, droplet eliminator, heating coil

Return side:

G4 pleated filters, F7 bag filters, fan, fan expansion section, heat recovery with bypass damper and actuator, exhaust section, exhaust air-tight shut-off damper with on/off actuator and limit switch.

Side view of unit

Construction specification according to EN1886 Casing Strength: Casing air leakage: Filter bypass leakage: Thermal performance of casing: Thermal bridging factor: D1 L1 F9 T3 or better TB3

Connecting dimensions Intake damper size: Exhaust damper size: Return air frame size: Supply air frame size: 1400 x 1200 1400 x 1200 1600 x 1250 1600 x 1250

Fans Type Deliverable flow rate (m3/hr) Min motor & fan efficiency (%) Motor size (kW) Motor Service factor

Supply Backward inclined 15,408 79 9.0 with VF Drive 1.3

Return Backward inclined 12,996 79 5.5 with VF Drive 1.3

25

Coils Cooling Air flow rate (m3/hr) Max air pressure drop (Pa) Air on-coil conditions Air off-coil conditions Thermal power (kW) Water flow rate (m/h) Entering water temperature ( C) Max water pressure drop (kPa) Control method Electrical Power (kW) Number of steps Power Supply (V / ph / Hz) Humidification capacity (kg/h) 15,408 120 31.0 C d.b., 50.3% r.h. 16.8 C d.b., 96.2% r.h. 111.2 19.12 10 27 Control Valve Heating 15,408 48 14.5 C d.b., 62.5% r.h. 21.0 C d.b. 34.2 5.88 40 26 Control Valve -

Cross flow heat exchanger

(sensible type only with no cross leakage. With bypass dampers with on/off actuators) Summer Outdoor air side Return air side 12,996 81 24.0 C d.b., 45.0% r.h. Winter Outdoor air side 15,408 109 9.0 C d.b., 60.0% r.h. 14.5 C d.b., 62.5% r.h. Return air side 12,996 81 20.0 C d.b., 60.0% r.h.

Air flow rate (m/hr) Max air pressure drop at specified flow rate (Pa) Air on conditions Required air off conditions

15,408 109 35.0 C d.b., 40.0% r.h. 29.5 C d.b., 54.6% r.h.

Sound attenuation Comment Type Recommended min length (mm) Induct sound pressure loss (dB) Noise breakout loss (dB) Required on both supply and return air streams 900 As required to achieve noise criteria As required to achieve noise criteria

Filtration (each filter bank below to be equipped with pressure switch and magnehelic gauge) Location Type Grade Min / Max P at section's flow (Pa) DP to be allowed for internal AHU static pressure loss (Pa)

Outdoor air intake Outdoor air intake Return fan suction side Return fan suction side

Pleated Bag pocket insert Pleated Bag pocket insert

G4 F7 G4 F7

Included in below 149 / 350 Included in below 123 / 350

Included below 275 Included below 350

26

After HRV's supply side

Activated Carbon

(Impregnated type. See specification document)

140

150

Pre-coils

Compact rigid bag

F7

51 / 200

150

Notes: 1. Minimum ESP for this project shall be 350 Pa. (The AHU is to be engineered with low pressure drop components in order to maintain the motor service factor specified above, when taking into account the filter Dp specified for the calculation of the internal AHU pressure drop) 2. Reference is to be made to the technical specifications for further details and the control schematic to illustrate the various AHU mounted sensors required 3. All dampers to come with factory fitted actuators.

Notes Project parameters highlighted in Blue: Not to be altered Other parameters may be altered depending on the performance of the thermal wheel offered

27

Item

Description

Unit

Qty

Rate (excl. VAT)

Total

Provide, supply, deliver to site, hoist, install, test and commission the following according to approved engineering standards and workmanship. PRELIMINARIES 1 Visit site, co-ordinate with existing services, building structure, fabric, furnishings and equipment, liaise with electrical contractor re: optimum location and size of isolators / fused connection units, chasing required for drains pipework etc., liaise with project manager on optimum base for outdoor units. LS 1

Co-ordinate all services building structure and proposed furniture and dcor layouts, re-design routing and fine tune sizing as necessary and produce construction drawings.

LS

Provide construction drawings for client's approval inclusive of roof layouts, plinth and waterproofing requirements for chillers, heat pump, MCC, AHU's, pipework and cable trays

LS

Allow for the provision of a warranted mechanical engineer and a warranted electrical engineer to ensure and certify that the system is capable of achieving it's intents. The engineers must be involved in the selection of all plant and equipment (including controllers, sensors, cabling etc), the installation phase, the connecting up phase, and the commissioning phase.

LS

PAGE TOTAL

28

VENTILATION SYSTEM (AIR SIDE) - East Block 5 Air-Handling Unit complete with factory supplied variable frequency drives, damper actuators, magnehelic gauges, differential pressure sensors, temperature and relative humidity sensors, static pressure sensors etc. as per drawings, complete with condensate drain pipework in PVC-u pipework complete with p-trap piped to nearest gulley, unit mounted isolator, flexible duct connection, supports, spring anti-vibration mountings reference:

a.

AHU-East

No

Connecting up of unit to existing ductwork using sandwich panel type ducting 30 mm thick with 200 micron thick aluminium foil face, manufacturer approved for external installation c/w two coats of rubberised paint in a colour as approved by the client:

a. b. c.

Supply ducting: 900 x 600 Return ducting: 800 x 600

LS LS LS

1 1 1

Outdoor air ducting: 1500 x 1000 (6 metres with elbow)

VAV boxes with thermal and acoustic insulation, flow grids, damper actuators, controllers as specified, to be retrofitted to existing ductwork. a. b. c. d. e. 450x250mm 450x200mm 400x250mm 400x200mm 350x250mm No No No No No 4 1 7 1 3

Room mounted Differential Pressure Sensors(0 - 50 Pa, 4-20mA)

No

Duct mounted static pressure sensors (0 to 500 Pa, 4-20mA)

No

PAGE TOTAL

29

VENTILATION SYSTEM (AIR SIDE) - South Block 10 Air-Handling Unit complete with factory supplied variable frequency drives, damper actuators, magnehelic gauges, differential pressure sensors, temperature and relative humidity sensors, static pressure sensors etc. as per drawings, complete with condensate drain pipework in PVC-u pipework complete with p-trap piped to nearest gulley, unit mounted isolator, flexible duct connection, supports, spring anti-vibration mountings reference:

a.

AHU01-South

No

11

Connecting up of unit to existing ductwork using sandwich panel type ducting 30 mm thick with 200 micron thick aluminium foil face, manufacturer approved for external installation c/w two coats of rubberised paint in a colour as approved by the client:

a. b. c.

Supply ducting: 900 x 750 Return ducting: 900 x 650

LS LS LS

1 1 1

Outdoor air ducting: 1500 x 1400 (6 metres with elbow)

12

VAV boxes with thermal and acoustic insulation, flow grids, damper actuators, controllers as specified, to be retrofitted to existing ductwork. a. b. c. d. e. f. g. h. i. j. 800x250mm 700x250mm 650x250mm 550x250mm 550x200mm 450x200mm 400x250mm 400x200mm 350x250mm 300x200mm No No No No No No No No No No 2 2 2 3 1 1 1 1 1 1

PAGE TOTAL

30

k.

250x200mm

No

13

Room mounted Differential Pressure Sensors(0 - 50 Pa, 4-20mA)

No

14

Duct mounted static pressure sensors (0 to 500 Pa, 4-20mA)

No

PAGE TOTAL

31

BMS / MCC / Controls 15 MCC as specified, including all controllers, RCB's, MCB's, isolators, control gateways, I/O cards, controllers, gateways etc. for a complete system as specified LS 1

16

All sensor and actuators forming required to achieve the functional control requirements but not mentioned in other parts of these bill of quantities

LS

17

All outgoing control cabling to sensors inclusive of containment in enclosed cable basket, sized to achieve 40% free space even with the uptake of the optional systems, supports and labelling

LS

18

All outgoing power cabling from MCC to AHU's and VAV's, isolators on chiller, heat pump and AHU fan inverters and internal lighting for a complete and working system inclusive of containment in enclosed cable trays sized to maintain 40% free space, supports and labelling

LS

19

Human machine interfaces on the control panels

LS

20

All necessary software programming

LS

21

Repeater panel in facility manager's office complete with all necessary interconnecting power and control cabling between MCC and repeater panel, containment as necessary

LS

22

Testing and documenting the performance of each sensor and actuator by means of a comparison between the reading at the controller and that of a calibrated instrument. Alternatively utilise a signal generator to measure and confirm the signals at the sensor end and at the actuator end.

LS

23

Carry out functional performance testing and verify that all control function, monitors and alarms are operational

LS

PAGE TOTAL

32

TESTING, ADJUSTING, BALANCING, COMMISSIONING AND HANDINGOVER

24

Pre-commissioning cleaning of pipework as per BSRIA guidelines and regulations

LS

25

Test all control points (sensors and actuators), verifying their reading at the controller's end against that of a calibrated instrument located instead of the sensors

LS

26

Commission, adjust and balance as necessary all VAV boxes to ensure that an adequate office zone pressurisation of 7Pa is achieved as sensed by the office zone mounted differential pressure sensors. Provide all documentation noting down supply air flow, return air-flow and differential pressure achieved in each office zone

LS

27

Test and commission in accordance to all relevant CIBSE and BSRIA guidelines

LS

28

Test and certify the external noise level caused by the plant as follows:

a.

That the noise levels near the plant are as per noise schedules

LS

29

Test, commission and certify all installation as per manufacturer's recommendations, specific regulations etc. Provide all certification.

LS

30

Provided as-fitted drawings, O&M manuals, sensor calibration certificates, commissioning documentation in hard-copy format.

Sets

31

Provided as-fitted drawings, O&M manuals, sensor calibration certificates, commissioning documentation in electronic format.

Sets

PAGE TOTAL

33

OPTIONAL SYSTEM: ROOM AIR QUALITY CONTROL SYSTEM 32 Supply, Install, test and connect indoor air quality sensors comprising of carbon dioxide and volatile organic compound sensors, complete with field interconnecting cabling and containment in heavy gauge plastic conduit / UV protected cable basket between sensors and controllers as follows: No 16

a. b.

Return duct mounted sensors (0 - 2000 ppm of CO2) AHU supply duct mounted sensors (0-2000 ppm of CO2)

No No

16 2

33

Upgrade controllers I/O cards to take the additional sensors

LS

34

Upgrade control software to include for the possibility of enabling the indoor air quality supply air flow rate control in such a manner that the total supply air flow to each room is modulated through the supply VAV box, whilst the AHU supply fan speed drive is regulated by the duct mounted static pressure sensors. At all times the room differential pressure control loop is to maintain precedence over the Indoor air quality control loop.

LS

35

Upgrade HMI's on MCC and repeater panel to allow for each office zone's setting of the desrired indoor air quality levels

LS

36

Test and commission the system and verify that the zone differential pressure control system continues to operate satisfactorily even with the indoor air quality control system in function

LS

37

Test, commission and certify all installation as per manufacturer's recommendations, specific regulations etc. Provide all certification.

LS

38

Provided as-fitted drawings, O&M manuals, sensor calibration certificates, commissioning documentation in hard-copy format.

Sets

39

Provided as-fitted drawings, O&M manuals, sensor calibration certificates, commissioning documentation in electronic format.

Sets

PAGE TOTAL

34

OPTIONAL SYSTEM: ANCILLARY SET OF FILTERS FOR AHU'S

40 a. b. c. d. e. f.

Supply and hand over only a spare set of filters for the AHU-East: Pre-filters - G4 grade outdoor air side Pre-filters - G4 grade return air side F7 filters outdoor air side F7 filters, return air side F7 filters, downstream of activated carbon filters Activated carbon filters Set Set Set Set Set Set 1 1 1 1 1 1

41 a. b. c. d. e. f.

Supply and hand over only a spare set of filters for the AHU-South: Pre-filters - G4 grade outdoor air side Pre-filters - G4 grade return air side F7 filters outdoor air side F7 filters, return air side F7 filters, downstream of activated carbon filters Activated carbon filters Set Set Set Set Set Set 1 1 1 1 1 1

PAGE TOTAL

35

SUMMARY OF BILL OF QUANTITIES


PRELIMINARIES Total of Page 28

VENTILATION SYSTEM (AIR SIDE) - East Block Total of Page 29

VENTILATION SYSTEM (AIR SIDE) - South Block Total of Page 30 Total of Page 31

BMS / MCC / Controls Total of Page 32

TESTING, ADJUSTING, BALANCING, COMMISSIONING AND HANDINGOVER Total of Page 33

Total Price:

Add / Omit (to specify): Total: V.A.T. @ 18% Overall Total without optional items:

36

OPTIONAL SYSTEMS OPTIONAL SYSTEM: ROOM AIR QUALITY CONTROL SYSTEM Total of Page 34 V.A.T. @ 18% Total for this optional system

OPTIONAL SYSTEM: ANCILLARY SET OF FILTERS FOR AHU'S Total of Page 35 V.A.T. @ 18% Total for this optional system

Signature: Name in Block: Occupation: I.D. Card No.: VAT Reg. No.: For and on behalf of: Company Reg. No.: Address:

Telephone No.: Date:

37

Drawing List

Drawing No 1106-HVACS-001 1106-HVACS-002

Description AHU duct and control schematic East Zone AHU duct and control schematic South Zone

Latest date Apr 2011 Apr 2011

38

Vous aimerez peut-être aussi