Vous êtes sur la page 1sur 92

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Contents

Contents
3 BTS Data Configuration ...........................................................................................................3-1
3.1 Adding a Site .................................................................................................................................................3-3 3.1.1 Task Description ..................................................................................................................................3-3 3.1.2 Procedure .............................................................................................................................................3-3 3.1.3 Verification.........................................................................................................................................3-18 3.1.4 Data Table ..........................................................................................................................................3-19 3.2 Deleting a Site .............................................................................................................................................3-21 3.2.1 Task Description ................................................................................................................................3-21 3.2.2 Procedure ...........................................................................................................................................3-21 3.2.3 Verification.........................................................................................................................................3-25 3.2.4 Data Table ..........................................................................................................................................3-25 3.3 Adding a TRX .............................................................................................................................................3-26 3.3.1 Task Description ................................................................................................................................3-26 3.3.2 Procedure ...........................................................................................................................................3-26 3.3.3 Verification.........................................................................................................................................3-30 3.3.4 Data Table ..........................................................................................................................................3-30 3.4 Deleting a TRX ...........................................................................................................................................3-31 3.4.1 Task Description ................................................................................................................................3-31 3.4.2 Procedure ...........................................................................................................................................3-31 3.4.3 Verification.........................................................................................................................................3-35 3.4.4 Data Table ..........................................................................................................................................3-35 3.5 Adding or Deleting a Board ........................................................................................................................3-37 3.5.1 Task Description ................................................................................................................................3-37 3.5.2 Procedure ...........................................................................................................................................3-37 3.5.3 Verification.........................................................................................................................................3-40 3.5.4 Data Table ..........................................................................................................................................3-40

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

Contents

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3.6 Modifying Board Type ................................................................................................................................3-41 3.6.1 Task Description ................................................................................................................................3-41 3.6.2 Procedure ...........................................................................................................................................3-41 3.6.3 Verification.........................................................................................................................................3-47 3.6.4 Data Table ..........................................................................................................................................3-47 3.7 Configuring Site Tower-Top Amplifier .......................................................................................................3-47 3.7.1 Task Description ................................................................................................................................3-47 3.7.2 Procedure ...........................................................................................................................................3-47 3.7.3 Verification.........................................................................................................................................3-50 3.7.4 Data Table ..........................................................................................................................................3-50 3.8 Modifying Site Data ....................................................................................................................................3-51 3.8.1 Task Description ................................................................................................................................3-51 3.8.2 Procedure ...........................................................................................................................................3-51 3.8.3 Verification.........................................................................................................................................3-53 3.8.4 Data Table ..........................................................................................................................................3-53 3.9 Modifying the Site Output Property............................................................................................................3-54 3.9.1 Task Description ................................................................................................................................3-54 3.9.2 Procedure ...........................................................................................................................................3-54 3.9.3 Verification.........................................................................................................................................3-55 3.9.4 Data Table ..........................................................................................................................................3-55 3.10 Starting Up Traffic Stat. Task Re-Register ................................................................................................3-56 3.10.1 Task Description ..............................................................................................................................3-56 3.10.2 Procedure .........................................................................................................................................3-56 3.11 Renaming a Site or Cell.............................................................................................................................3-58 3.11.1 Task Description...............................................................................................................................3-58 3.11.2 Procedure .........................................................................................................................................3-58 3.11.3 Verification.......................................................................................................................................3-61 3.11.4 Data Table ........................................................................................................................................3-61 3.12 Modifying a Ring Topology Mark ............................................................................................................3-63 3.12.1 Task Description ..............................................................................................................................3-63 3.12.2 Procedure .........................................................................................................................................3-63 3.12.3 Verification.......................................................................................................................................3-66 3.12.4 Data Table ........................................................................................................................................3-66

ii

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Contents

3.13 Adding a Slave Chain to a Site..................................................................................................................3-67 3.13.1 Task Description ..............................................................................................................................3-67 3.13.2 Procedure .........................................................................................................................................3-67 3.13.3 Verification.......................................................................................................................................3-70 3.13.4 Data Table ........................................................................................................................................3-70 3.14 Deleting a Slave Chain of a Site................................................................................................................3-71 3.14.1 Task Description ..............................................................................................................................3-71 3.14.2 Procedure .........................................................................................................................................3-71 3.14.3 Verification.......................................................................................................................................3-74 3.14.4 Data Table ........................................................................................................................................3-74 3.15 Configuring Site Idle Timeslots ................................................................................................................3-74 3.15.1 Task Description ..............................................................................................................................3-74 3.15.2 Procedure .........................................................................................................................................3-74 3.15.3 Verification.......................................................................................................................................3-78 3.15.4 Data Table ........................................................................................................................................3-78 3.16 Modifying Site Properties in Batches........................................................................................................3-79 3.16.1 Task Description ..............................................................................................................................3-79 3.16.2 Procedure .........................................................................................................................................3-79 3.16.3 Verification.......................................................................................................................................3-83 3.16.4 Data Table ........................................................................................................................................3-83

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

iii

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Figures

Figures
Figure 3-1 Selecting a module and BIE board....................................................................................................3-4 Figure 3-2 Selecting a BIE port and upper site...................................................................................................3-4 Figure 3-3 Site configuration..............................................................................................................................3-5 Figure 3-4 Selecting the mode of BIE port adjustment ......................................................................................3-5 Figure 3-5 Site BIE Port Cascade List dialog box..............................................................................................3-6 Figure 3-6 Adding TRXs ....................................................................................................................................3-6 Figure 3-7 Adding a cell.....................................................................................................................................3-7 Figure 3-8 Configuring the property of site device ............................................................................................3-8 Figure 3-9 Modifying site internal connections..................................................................................................3-8 Figure 3-10 Adding cells ....................................................................................................................................3-9 Figure 3-11 Added cells....................................................................................................................................3-10 Figure 3-12 Setting cell properties ................................................................................................................... 3-11 Figure 3-13 Modifying reserved parameters ....................................................................................................3-12 Figure 3-14 Command list for dynamic configuration .....................................................................................3-12 Figure 3-15 Selecting the Manual Mode option ...............................................................................................3-13 Figure 3-16 Manual timeslot adjustment..........................................................................................................3-14 Figure 3-17 TRX property................................................................................................................................3-15 Figure 3-18 RSL property configuration ..........................................................................................................3-16 Figure 3-19 Site trunk mode configuration ......................................................................................................3-17 Figure 3-20 BSC BIE description data .............................................................................................................3-18

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

Figures

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Figure 3-21 Selecting a site ..............................................................................................................................3-22 Figure 3-22 Deleting a site ...............................................................................................................................3-22 Figure 3-23 Site trunk mode.............................................................................................................................3-23 Figure 3-24 Site TRX property.........................................................................................................................3-24 Figure 3-25 Command list for dynamic configuration .....................................................................................3-25 Figure 3-26 Selecting a site ..............................................................................................................................3-26 Figure 3-27 Adding TRXs ................................................................................................................................3-27 Figure 3-28 Configuring the cell ......................................................................................................................3-28 Figure 3-29 Assigning TRXs to the cell ...........................................................................................................3-28 Figure 3-30 Configuring the related properties ................................................................................................3-29 Figure 3-31 Selecting a cell..............................................................................................................................3-32 Figure 3-32 Selecting TRXs.............................................................................................................................3-33 Figure 3-33 Prompt to modify the reserved channel number ...........................................................................3-33 Figure 3-34 Information prompt.......................................................................................................................3-34 Figure 3-35 Changing the reserved channel number ........................................................................................3-34 Figure 3-36 Command list for dynamic configuration .....................................................................................3-35 Figure 3-37 Selecting a site ..............................................................................................................................3-37 Figure 3-38 Adding or deleting a board............................................................................................................3-38 Figure 3-39 Configuring the property of site device ........................................................................................3-39 Figure 3-40 Command list for dynamic configuration .....................................................................................3-40 Figure 3-41 Selecting a site ..............................................................................................................................3-41 Figure 3-42 Changing the board type ...............................................................................................................3-42 Figure 3-43 Site device property ......................................................................................................................3-42 Figure 3-44 Changing the PBU card type ........................................................................................................3-43 Figure 3-45 Changing the CDU type................................................................................................................3-44 Figure 3-46 Selecting the EDU type.................................................................................................................3-44

vi

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Figures

Figure 3-47 Changing the TRX type ................................................................................................................3-45 Figure 3-48 Command list for dynamic configuration .....................................................................................3-46 Figure 3-49 Selecting a site ..............................................................................................................................3-48 Figure 3-50 Configuring the tower-top amplifier .............................................................................................3-48 Figure 3-51 Modifying the property of site device...........................................................................................3-49 Figure 3-52 Site tower-top amplifier configuration..........................................................................................3-49 Figure 3-53 Command list for dynamic configuration .....................................................................................3-50 Figure 3-54 Selecting a site ..............................................................................................................................3-51 Figure 3-55 Modifying site data .......................................................................................................................3-52 Figure 3-56 Changing the site device property.................................................................................................3-52 Figure 3-57 Command list for dynamic configuration .....................................................................................3-53 Figure 3-58 Selecting a site ..............................................................................................................................3-54 Figure 3-59 Modifying site output parameters .................................................................................................3-55 Figure 3-60 Selecting a startup mode ...............................................................................................................3-57 Figure 3-61 Command list for dynamic configuration .....................................................................................3-57 Figure 3-62 Renaming a site or cell..................................................................................................................3-58 Figure 3-63 Renaming the site .........................................................................................................................3-59 Figure 3-64 Renaming a cell ............................................................................................................................3-60 Figure 3-65 Renaming an external cell.............................................................................................................3-60 Figure 3-66 Renaming a 3G external cell.........................................................................................................3-61 Figure 3-67 Selecting a BIE .............................................................................................................................3-64 Figure 3-68 Selecting a BIE port......................................................................................................................3-64 Figure 3-69 Configuring the closed loop BIE port...........................................................................................3-65 Figure 3-70 Command list for dynamic configuration .....................................................................................3-66 Figure 3-71 Selecting a BIE .............................................................................................................................3-68 Figure 3-72 Selecting a BIE port......................................................................................................................3-68

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

vii

Figures

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Figure 3-73 Selecting a site ..............................................................................................................................3-69 Figure 3-74 Selecting a port number ................................................................................................................3-69 Figure 3-75 Site BIE Port Cascade List dialog box..........................................................................................3-70 Figure 3-76 Selecting a BIE .............................................................................................................................3-72 Figure 3-77 Selecting a port .............................................................................................................................3-72 Figure 3-78 Deleting the slave chain................................................................................................................3-73 Figure 3-79 Site BIE Port Cascade List dialog box..........................................................................................3-73 Figure 3-80 Selecting a BIE .............................................................................................................................3-75 Figure 3-81 Selecting a port .............................................................................................................................3-75 Figure 3-82 Port Idle Timeslot Assignment dialog box....................................................................................3-76 Figure 3-83 Failed idle timeslot assignment.....................................................................................................3-76 Figure 3-84 Detailed information about assigned timeslots .............................................................................3-77 Figure 3-85 Command list for dynamic configuration .....................................................................................3-78 Figure 3-86 Selecting a site type and sites .......................................................................................................3-80 Figure 3-87 Selecting site properties ................................................................................................................3-80 Figure 3-88 Modifying site properties..............................................................................................................3-81 Figure 3-89 Site Device Property dialog box ...................................................................................................3-82 Figure 3-90 Command list for dynamic configuration .....................................................................................3-83

viii

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Tables

Tables
Table 3-1 Mapping between port number and TRX number ..............................................................................3-9 Table 3-2 Modified data tables during the addition or deletion of a site ..........................................................3-19 Table 3-3 Modified data tables during the addition of a TRX ..........................................................................3-30 Table 3-4 Modified data tables during the deletion of a TRX ..........................................................................3-35 Table 3-5 Modified data tables during the addition or deletion of a board .......................................................3-40 Table 3-6 Modified data tables during the modification of the board type.......................................................3-47 Table 3-7 Modified data table during the configuration of site tower-top amplifier.........................................3-51 Table 3-8 Modified data tables during the modification of site data ................................................................3-53 Table 3-9 Modified data table during the modification of site output property ................................................3-56 Table 3-10 Modified data tables during the renaming of a site or cell.............................................................3-61 Table 3-11 Modified data tables during the modification of a ring topology mark ..........................................3-66 Table 3-12 Modified data tables during the addition of a slave chain to a site .................................................3-70 Table 3-13 Modified data tables during the deletion of a slave chain of a site .................................................3-74 Table 3-14 Modified data tables during the configuration of site idle timeslots...............................................3-78 Table 3-15 Modified data tables during the modification of a batch of site properties.....................................3-83

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

ix

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

3
About This Chapter
Title 3.1 Adding a Site 3.2 Deleting a Site 3.3 Adding a TRX 3.4 Deleting a TRX 3.5 Adding or Deleting a Board 3.6 Modifying Board Type 3.7 Configuring Site TowerTop Amplifier 3.8 Modifying Site Data 3.9 Modifying the Site Output Property 3.11 Renaming a Site or Cell 3.12 Modifying a Ring Topology Mark 3.13 Adding a Slave Chain to a Site 3.14 Deleting a Slave Chain of a Site

BTS Data Configuration

The following table lists the contents of this chapter. Description Describes how to add a site. Describes how to delete a site. Describes how to add a TRX. Describes how to delete a TRX. Describes how to add or delete a board. Describes how to modify the board type. Describes how to configure the site tower top amplifier. Describes how to modify site data. Describes how to modify the site output property. Describes how to rename a site or cell. Describes how to modify a ring topology mark. Describes how to add a slave chain to a site. Describes how to delete a slave chain of a site.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-1

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Title 3.15 Configuring Site Idle Timeslots 3.16 Modifying Site Properties in Batches

Description Describes how to configure site idle timeslots. Describes how to modify site properties in batches.

3-2

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

3.1 Adding a Site


3.1.1 Task Description
Purpose Prerequisite To add a site without resetting the BSC
z z z

The BSC is configured with idle E1 ports. The data to be configured is consistent and correct. You can add only one site to one BIE port in one operation. If the new TRXs are distributed on multiple chains, add TRXs or cells after adding the site. Adding a site also involves adding a cell. Perform Modify Cell Handover Parameter to configure the neighbor cell after adding the site.

Note

3.1.2 Procedure
Adding a Site Without Timeslot Manual Adjustment
Using an example, this part shows how to add a site without timeslot manual adjustment. Assume that you have to add Site2, and TRX 0, TRX 3, TRX 5, TRX 8, TRX 18, TRX 21 and TRX 24 in BM1 for two cells. The conditions of the example are as follows:
z

Cell1 includes TRX 0, TRX 5, TRX 18 and TRX 24; Cell2 includes TRX 3, TRX 8 and TRX 21. Cell1 and Cell2 are bi-directionally adjacent. No timeslot manual adjustment is required for the new site. The new site is connected to port0 of BIE0. The trunk mode is 2E1 port*15:1multiplexing/port.

z z z z

The procedure is as follows: Step 1 On the BSC Data Auto Configuration System, choose BTS > Add a Site. The Add a Site dialog box as shown in Figure 3-1 is displayed.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-3

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Figure 3-1 Selecting a module and BIE board

Step 2 Select a module and BIE board. Step 3 Click Next. The Add a Site dialog box is refreshed, as shown in Figure 3-2.

Figure 3-2 Selecting a BIE port and upper site

The trunk mode can be changed only when no site is connected to the BIE.

Step 4 Select the BIE port 0 and upper site Site0. Then click Add Site. The Add Site dialog box as shown in Figure 3-3 is displayed.

3-4

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

Figure 3-3 Site configuration

Step 5 Enter Site2 in the Site Name text box. Select BTS312 from the Site Type drop-down list and Port[0] from the Port to This Site drop-down list. Step 6 Click OK. The Confirm dialog box as shown in Figure 3-4 is displayed.

Figure 3-4 Selecting the mode of BIE port adjustment

Step 7 Click No.

After a site is added, Add Site, Trunk Mode, and all the BIE ports in the Add a Site dialog box as shown in Figure 3-2 are unavailable.

Step 8 Click Site Ports Table. The Site BIE Port Cascade List dialog box as shown in Figure 3-5 is displayed. Ensure that the connection between the upper site and lower site is correct.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-5

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Figure 3-5 Site BIE Port Cascade List dialog box

Step 9 Click OK to return to the Add a Site dialog box as shown in Figure 3-2.

In the Site BIE Port Cascade List dialog box, Modify BIE Port and Site Connection is available only when the selected BIE port is the sub-chain port. For the Next Site whose Inlet Port No. is 0, the inter-site port cascade relationship cannot be removed. The inlet port 0 of the next site cannot be modified.

Step 10 Click Next. The Add a Site dialog box is refreshed, as shown in Figure 3-6.

Figure 3-6 Adding TRXs

3-6

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

Step 11 Select 0 TRX from the Available TRX list box, and then click Add TRX to add it to the Installed TRX list box. Repeat the same steps to add 3 TRX, 5 TRX, 8 TRX, 18 TRX, 21 TRX and 24 TRX to the Installed TRX list box. Step 12 Click Next. The Add a Site dialog box is refreshed, as shown in Figure 3-7.

Figure 3-7 Adding a cell

Step 13 Click Modify Site Device's Property. The Site Device's Property dialog box as shown in Figure 3-8 is displayed.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-7

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Figure 3-8 Configuring the property of site device

Step 14 Select the rack from the Current Rack drop-down list. Delete the excessive boards, and double-click the CDU to configure the CDU board property. Step 15 Click BTS Property to configure site property. Then click OK to return to the Site Device's Property dialog box. Step 16 Click Inter-site Link. The Modify Site Internal Connections dialog box as shown in Figure 3-9 is displayed.

Figure 3-9 Modifying site internal connections

3-8

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

Step 17 Configure the site internal connections. Table 3-1 lists the mapping between port number and TRX number.

Table 3-1 Mapping between port number and TRX number Cabinet Group No. 0 1 2 Port No. 07 811 1619 TRX No. Corresponding to BTS30 017 1835 3653 TRX No. Corresponding to BTS312 023 2447 4871

Step 18 Click OK to return to the Site Device's Property dialog box as shown in Figure 3-8. Step 19 Click Complete to return to the Add a Site dialog box as shown in Figure 3-7. Step 20 Click Add Cell. Select 2 from the Cell Number box, as shown in Figure 3-10. Figure 3-10 Adding cells

In the Add Cell dialog box as shown in Figure 3-10, note the following conditons:
z

Cell Name cannot be changed if Cell Number exceeds 1 or Name Cell by Site's Name is selected. If Name Cell by Site's Name is selected, the naming convention of the cell is site nameserial number. The two cells added in this example are named Site2-1 and Site2-2. If Cell Number exceeds 1 and Name Cell by Site's Name is not selected, Cell-Cell No. is used as the Cell Name.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-9

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

The default cell template is used for the added cell. The system also supports customized cell template. For details, see section 4.1 "Adding Cell."

Step 21 Click OK. The Add a Site dialog box is refreshed, as shown in Figure 3-11. The two cells are displayed in the Cell List box.

Figure 3-11 Added cells

Step 22 Select Site2-1. Then Click Modify Cell Property. The Set Cell's Property dialog box as shown in Figure 3-12 is displayed.

3-10

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

Figure 3-12 Setting cell properties

Step 23 Assign 0 TRX, 5 TRX, 18 TRX and 24 TRX as well as properties such as available frequency and network parameters to Site2-1. To set the advanced property, see section 4.1 "Adding a Cell."

In the Add a Site dialog box shown in Figure 3-11, you can select the added cell and click Delete Cell to delete it.

Step 24 Click Complete&Exit to return to the Add a Site dialog box as shown in Figure 3-11. Step 25 Add TRX 3, TRX 8, and TRX 21 to Site2-2 in the same way as adding the TRXs to Site2-1 by following step 22 through step 24. Step 26 Click Modify Reserved Parameters in the Add a Site dialog box as shown in Figure 3-11. The Modify Reserved Parameters dialog box as shown in Figure 3-13 is displayed. You can change the reserved parameters of the added site, cell or TRX, or retain the default value 65535.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-11

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Figure 3-13 Modifying reserved parameters

Step 27 Click OK to return to the Add a Site dialog box as shown in Figure 3-11. Step 28 Click Next. The Add a Site dialog box is refreshed, as shown in Figure 3-14.

Figure 3-14 Command list for dynamic configuration

Step 29 Click Start Dynamic Configuration.

3-12

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

You can only change the physical link No. and the signaling connection No. of the LAPD of the selected site under the selected BIE port.

Step 30 Choose Cell > Modify Cell Handover Parameter to configure the adjacent relationship for the two cells after adding the site. ----End

Adding a Site with Timeslot Manual Adjustment


To add a site with timeslot manual adjustment, perform the following steps: Step 1 Perform step 1 through step 6 of "Adding a Site Without Timeslot Manual Adjustment." Step 2 In the Confirm dialog box as shown in Figure 3-4, click Yes. The Manual Mode check box appears in the Add a Site dialog box as shown in Figure 3-15.

To manually adjust timeslots, see the M900/M1800 BSC Data Configuration Manual Initial Configuration.

Figure 3-15 Selecting the Manual Mode option

Step 3 Select Manual Mode. Step 4 Click Next. The following procedure for adding a cell is the same as that for adding a cell without the timeslot manual adjustment.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-13

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

After the cell is added, the Add a Site dialog box is refreshed, as shown in Figure 3-16.

Figure 3-16 Manual timeslot adjustment

The Add a Site dialog box shown in Figure 3-16 lists all the sites on the chain where the added site resides. If the TRXs of the level 1 site on the chain where the added site resides are distributed on multiple chains, the Add a Site dialog box lists all the sites on the main chain. To manually adjust the timeslots, you need to enter all the TRX properties such as Abis TS No., Abis Sub-TS No. and Trunk Circuit No., and the RSL and OML properties. If site cascading is involved, you also need to configure the site trunk mode and BIE port property. You can check the Idle Timeslot if the selected site has idle timeslots. Step 5 Select the new site. Click TRX Property in the Add a Site dialog box. The TRX Property dialog box is displayed as shown in Figure 3-17.

3-14

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

Figure 3-17 TRX property

The TRX Property dialog box lists the default values of the properties. The Abis TS No. and Abis Sub-TS No. are 0; the Trunk Circuit No. is 65535; the BSC BIE E1 TimeSlot No. is 255. Rev. OML Trunk Circuit No., Rev. OML ABIS TS No., Rev. OML BSC BIE E1 TS No. and Rev. OML Physical Link No. are available if the relay mode of BIE board is full rate ring topology or half rate ring topology. In timeslot manual adjustment mode, the physical links of RSL and OML are calculated automatically.

The dynamic configuration can modify only the TRX properties of the new site, and view but not modify the TRX properties of other sites. RSLs are multiplexed according to Abis TS No. entered. You must ensure that the data is correct.

Step 6 In the TRX Property dialog box as shown in Figure 3-17, double-click the row of the TRX whose RSL properties are to be modified. The RSL Property dialog box as shown in Figure 3-18 is displayed.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-15

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Figure 3-18 RSL property configuration

Step 7 Enter the related information, and then click OK to return to TRX Property dialog box as shown in Figure 3-17. Step 8 Click OK to return to the Add a Site dialog box as shown in Figure 3-16. If the new site is a cascaded site, click Site Trunk Mode Description in the Add a Site dialog box to display the Site Trunk Mode dialog box as shown in Figure 3-19. Configure the BIE trunk mode. For detailed information about the parameters in the Site Trunk Mode dialog box, see the M900/M1800 BSC Data Configuration Reference Engineering Parameters.

3-16

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

Figure 3-19 Site trunk mode configuration

Trunk Mode No. in the Site Trunk Mode dialog box as shown in Figure 3-19 should be twice the upper site number. If the networking mode is full rate ring topology or half rate ring topology, the reverse trunk mode number should be twice the upper site number plus one.

Step 9 Click OK to return to the Add a Site dialog box as shown in Figure 3-16. Step 10 Click BIE Port Property. The BSC BIE Description Data dialog box as shown in Figure 3-20 is displayed. For detailed information about the BIE description data, see the M900/M1800 BSC Data Configuration Reference Engineering Parameters.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-17

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Figure 3-20 BSC BIE description data

Step 11 Adjust the properties of the Abis interface and BS interface. Step 12 Click OK to return to the Add a Site dialog box as shown in Figure 3-16. Step 13 Click Next. The Add a Site dialog box is refreshed. Step 14 Click Start Dynamic Configuration to activate the data. ----End

In the chain topology or tree topology, reset the sites from the one at the top level of the chain or reset the BIE if the new site is not functional. After adding a site, re-register the traffic statistics tasks of this site. If the added site is the level 1 site of the BIE port, reset the BIE after adding the site.

z z

3.1.3 Verification
After adding a site, check that:
z

The channels of all the cells are in idle state. After the node icons of the newly added site are displayed on the OMC SHELL, start the Site Maintenance System of the newly added site. If all the TRXs are powered on and are functional, the channels of all the cells are in idle state.

Calls in the newly added sites can be established.

3-18

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

3.1.4 Data Table


Table 3-2 lists the modified data tables in the BSC Data Management System.

Table 3-2 Modified data tables during the addition or deletion of a site No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 Table Name HWII Power Control Table BSC Cell Table TRX Configuration Table Radio Channel Configuration Table LAPD Semi-perm. Connection Table LAPD Signaling Connection Table BSC BIE Active/Stby. Group Table BSC BIE Description Table Site BIE Trunk Mode Description Table Site BIE Configuration Table Signaling Channel Link Table System Information Table Cell Configuration Table Normal Handover Table Cell Allocation Table BA1(BCCH) Table BA2(SACCH) Table Cell Attribute Table Cell Alarm Threshold Table Cell Call Control Table Cell Call Control Parameter Table Cell Module Information Table Handover Control Table GSM0508 Handover Table Load Handover Table Intra-cell Continuous HO Control Table

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-19

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

No. 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56

Table Name Penalty Table Filter Table Emergency Handover Table Adjacent Cell Relation table Power Control Selection Table Ordinary Cell Power Control Table BTS Power Control Table MS Power Control Table Radio Channel Management Control Table Site Description Table Site Slot Description Table Carrier Configuration Table External Cell Description Table Fast-Moving Handover Table Cell Module Information Table Frequency Hopping Table Site Frame Description Table HW II Channel Allocation Table Antenna and Feeder Configuration Table Concentric Cell Handover Table Site Software Configuration Table Site Reserved Parameter Table Cell Reserved Parameter Table TRX Reserved Parameter Table 3G BA1Table 3G System Information Table Inter-RAT Handover Table (UTRAN FDD) UTRAN FDD Adjacent Relation Table 3G Filter Table 3G BA2 Table

3-20

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

3.2 Deleting a Site


3.2.1 Task Description
Purpose Prerequisite To delete sites that are no longer required
z

Block all the cells of the site to be deleted on the Site Maintenance System. This avoids call processing in the site during deletion. If the site has sub cascading sites, delete these sub sites. If the site to be deleted is not the level 1 site connected to the BIE port and the BIE port is in timeslot manual adjustment mode, change the BIE trunk mode of the site by implementing timeslot manual adjustment. After deleting a site, you need to delete the site icon on the OMC SHELL. When a site is deleted, all the cells connected to it will also be deleted.

Note

3.2.2 Procedure
Using an example, this part shows how to delete a site. Assume you have to delete Site2 in BM1. The conditions of the example are as follows:
z z

The BIE port of Site2 is in the timeslot manual adjustment mode. Site2 is the sub-site of Site0.

The procedure is as follows: Step 1 On the BSC Data Auto Configuration System, choose BTS > Delete a Site. The Delete a Site dialog box as shown in Figure 3-21 is displayed.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-21

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Figure 3-21 Selecting a site

Step 2 Select Site2.

If no site is selected or the site selected is not the last level site, the Next button in the Delete a Site dialog box is unavailable.

Step 3 Click Next. The Delete a Site dialog box is refreshed, as shown in Figure 3-22.

Figure 3-22 Deleting a site

All the sites connected to the BIE port of the site to be deleted (Site2 in BM1) are listed in the Delete a Site dialog box as shown in Figure 3-22. If the connection is in multi-chain mode, all the sites of the main chain BIE port are listed. The site to be deleted is not listed.

3-22

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

If the BIE port connected to the selected site is not in timeslot manual adjustment mode, the dynamic configuration dialog box instead of the timeslot manual adjustment dialog box will be displayed. The Idle Timeslot button is available if the selected site has idle timeslots.

Step 4 Select the last site in the list box, and then click Site trunk mode description in the Delete a Site dialog box. The Site Trunk Mode dialog box as shown in Figure 3-23 is displayed. You can manually change the site BIE trunk mode. For detailed information about the BIE trunk mode, see the M900/M1800 BSC Data Configuration Reference Engineering Parameters.

Figure 3-23 Site trunk mode

Step 5 Delete all the records of the site with Trunk Mode No. as 0 by pressing Delete. The site BIE trunk mode description of Site2 is deleted.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-23

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Step 6 Click OK to return to the Delete a Site dialog box as shown in Figure 3-22. Step 7 Click TRX Property to view the site TRX property, as shown in Figure 3-24. The TRX Property dialog box lists the TRX property of Site0.

Figure 3-24 Site TRX property

Do not change the value of any parameter in the TRX Property dialog box as shown in Figure 3-24.

Step 8 Click OK to return to the Delete a Site dialog box as shown in Figure 3-22. Step 9 Click Next. The Delete a Site dialog box is refreshed, as shown in Figure 3-25.

3-24

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

Figure 3-25 Command list for dynamic configuration

Step 10 Click Start Dynamic Configuration to activate the data. ----End

After a site is deleted, the adjacent relationship between cells under this site is also deleted. Therefore, the Configure handover data command must be sent to the adjacent cells for automatic update of the adjacent relationship.

3.2.3 Verification
After deleting the site, check that:
z z z

The maintenance of the deleted site is not available on the OMC SHELL. The system prompts the error site number. The OMLs and RSLs corresponding to the sites are released in the switching network boards.

3.2.4 Data Table


Table 3-2 lists the modified data tables in the BSC Data Management System.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-25

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3.3 Adding a TRX


3.3.1 Task Description
Purpose Prerequisite Note To add TRXs to a site for cell capacity expansion Block the cells of the site on the Site Maintenance System.
z

You can add TRXs to only one site of one BIE port in one operation. If you have to add TRXs to multiple sites of one BIE port or to multiple BIE ports of one site, add TRXs to one site of one BIE port first, and then repeat the steps to add the TRXs to more sites or ports. If the BIE port of the site is in timeslot manual adjustment mode, you also need to adjust the timeslot manually.

3.3.2 Procedure
Using an example, this part shows how to add TRXs to a site. Assume that you have to add TRXs 0 and 7 to Site0-1 and Site0-2 under Site0 in BM1. The BIE port of Site0 is in timeslot manual adjustment mode. The procedure is as follows: Step 1 On the BSC Data Auto Configuration System, choose BTS > Add TRX. The Add TRX dialog box as shown in Figure 3-26 is displayed.

Figure 3-26 Selecting a site

Step 2 Select Site0 in BM1.

3-26

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

If no site is selected, the Next button in the Add TRX dialog box as shown in Figure 3-26 is unavailable.

Step 3 Click Next. The Add TRX dialog box as shown in Figure 3-27 is displayed.

Figure 3-27 Adding TRXs

Step 4 Select 1 TRX, and then click Add TRX to add it to the Installed TRX list box. Repeat the same steps to add 7 TRX to the Installed TRX list box.

The BIE the Site Belongs to drop-down list box and the Select Port option buttons are unavailable if the Installed TRX list already has TRXs.

Step 5 Click Next. The Add TRX dialog box is refreshed, as shown in Figure 3-28.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-27

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Figure 3-28 Configuring the cell

If the new TRXs change the intra-site transparent transmission relationship, for example, TRX 18 is added to site30 that earlier had only TRX 1 and TRX 4, you need to click Modify Site Property to configure the intra-site link. For details of intra-site link configuration, see section 3.1 "Adding a Site."

You cannot add or delete cells in the Add TRX dialog box as shown in Figure 3-28.

Step 6 Select Site0-1. Then click Modify Cell Property. The Assign TRX to Cell dialog box as shown in Figure 3-29 is displayed. You can click Modify CA to add frequencies to the cell.

Figure 3-29 Assigning TRXs to the cell

3-28

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

Step 7 Assign 1 TRX to Site0-1, and then double-click 1 TRX listed in the Assigned TRX box to assign frequencies to Site0-1. Repeat the same steps to assign 7 TRX and frequencies to Site0-2. Step 8 In the Assign TRX to Cell dialog box, click Complete & Exit to return to the Add TRX dialog box as shown in Figure 3-28.

You can click Modify Reserved Parameters to change the reserved parameters or retain the default value 65535. If no TRX is assigned to the cell, the Next button in the Add TRX dialog box is unavailable.

Step 9 Click Next in the Add TRX dialog box as shown in Figure 3-28. The Add TRX dialog box is refreshed, as shown in Figure 3-30.

Figure 3-30 Configuring the related properties

Step 10 Select the added site from the list box. Click TRX Property, Site Trunk Mode Description, and BIE Port Property to configure the related properties. In the TRX Property dialog box, you can only change the TRX properties of the selected BIE port and site. Do not change the TRX properties of other BIE ports and sites. This principle is applicable to all dynamic configuration operations.

If the BIE port of the BIE where the TRXs reside is not in the timeslot manual adjustment mode, choose the dynamic configuration mode as described in section 3.1 "Adding a Site." For details of timeslot manual adjustment, see section 3.1 "Adding a Site."

Step 11 Click Next. The Add TRX dialog box is refreshed.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-29

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Step 12 Click Start Dynamic Configuration to activate the data. ----End

In the star or tree topology, if the new TRX or other equipment fails to operate, reset the sites on the link where the site resides one by one starting from the top level site. You can also reset the BIE. After adding a TRX, you need to re-register the traffic statistics tasks of the site.

3.3.3 Verification
After adding the TRXs, check that:
z z z

The new TRXs are functional on the Site Maintenance System. The conversations over the new TRXs are normal. The related data in the data tables and in the host are correct.

3.3.4 Data Table


Table 3-3 lists the modified data tables in the BSC Data Management System.

Table 3-3 Modified data tables during the addition of a TRX No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Table Name Site BIE Configuration Table Site Slot Description Table Site Description Table Antenna and Feeder Configuration Table Site Frame Description Table TRX Configuration Table Carrier Configuration Table Radio Channel Configuration Table LAPD Semi-perm. Connection Table LAPD Signaling Connection Table Signaling Channel Link Table Frequency Hopping Table Cell Attribute Table BA1(BCCH) Table

3-30

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

No. 15 16 17 18

Table Name BA2(SACCH) Table Site BIE Trunk Mode Description Table BSC BIE Description Table TRX Reserved Parameter Table

3.4 Deleting a TRX


3.4.1 Task Description
Purpose Prerequisite To delete a faulty TRX, or to adjust the capacity of the cells within one site
z z

Block the TRX on the Site Maintenance System. To delete main BCCH TRX, choose Cell > Modify TRX Channel Type first to change the TRX into non-main BCCH TRX and assign a new BCCH to the cell. If the cell has only one main BCCH TRX left, choose Cell > Delete Cell to delete the cell. If the number of full rate channels the cell can provide is smaller than that reserved after the TRXs are deleted, change the reserved channel number first. You can delete the TRXs (except main BCCH TRXs) of only one cell in one site at a time. For the BTS20, the associated FPU is also deleted when the TRX is deleted. For the BTS3001C, the associated MFU is also deleted when the TRX is deleted. After the TRX is deleted, the rack will be deleted (except for rack0) if there is no TRX on it. If the BIE port is in timeslot manual adjustment mode, adjust the timeslot manually when deleting the TRX. For details, see section 3.1 "Adding a Site" or section 3.3 "Adding a TRX."

Note

3.4.2 Procedure
Using an example, this part shows how to delete TRXs. Assume that you have to delete TRX 18 and TRX 21 of Site2 in BM1. These two TRXs reside in Site2-1 that contains TRX 0, TRX 18 and TRX 20.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-31

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

The procedure is as follows: Step 1 On the BSC Data Auto Configuration System, choose BTS > Delete TRX. The Delete TRX dialog box as shown in Figure 3-31 is displayed.

Figure 3-31 Selecting a cell

Step 2 Select Site2-1.

The Next button is unavailable if no cell is selected.

Step 3 Click Next. The Delete TRX dialog box is refreshed, as shown in Figure 3-32.

3-32

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

Figure 3-32 Selecting TRXs

Step 4 Select 18 TRX in the Assigned TRX list box, and then add it to the Deleted TRX list box. Repeat the same steps to add 21 TRX to the Deleted TRX list box. Step 5 Click Next. The Delete TRX dialog box is refreshed, as shown in Figure 3-33.

Figure 3-33 Prompt to modify the reserved channel number

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-33

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

If you delete the main BCCH TRX, the Information prompt as shown in Figure 3-34 appears.

Figure 3-34 Information prompt

If the number of full rate channels the cell can provide is less than that reserved after the TRX is deleted, you need to change the reserved channel number first. Step 6 Click OK. The Delete TRX dialog box is refreshed, as shown in Figure 3-35.

Figure 3-35 Changing the reserved channel number

Step 7 Change the number in the Correct the Reserved Channel Number text box. Step 8 Click Next. The Delete TRX dialog box is refreshed, as shown Step 9.

3-34

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

Figure 3-36 Command list for dynamic configuration

Step 9 Click Start Dynamic Configuration to activate the data. ----End

In the star or tree topology, if the new TRX or other equipment fails to operate, reset the sites on the link where the site resides one by one starting from top level site. You can also reset the BIE. After deleting a TRX, you need to re-register the traffic statistics tasks of the site.

3.4.3 Verification
Check that the TRXs are deleted on the Site Maintenance System.

3.4.4 Data Table


Table 3-4 lists the modified data tables in the BSC Data Management System.

Table 3-4 Modified data tables during the deletion of a TRX No. 1 2 3 Table Name Site BIE Configuration Table Site Slot Description Table Site Description Table

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-35

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

No. 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Table Name Antenna and Feeder Configuration Table Site Frame Description Table TRX Configuration Table Carrier Configuration Table Radio Channel Configuration Table LAPD Semi-perm. Connection table LAPD Signaling Connection Table Signaling Channel Link Table Frequency Hopping Table Cell Attribute Table BA1(BCCH) Table BA2(SACCH) Table Site BIE Trunk Mode Description Table BSC BIE Description Table TRX Reserved Parameter Table Radio Channel Management and Control Table HW Channel Allocation Table

3-36

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

3.5 Adding or Deleting a Board


3.5.1 Task Description
Purpose To delete:
z z

The standby TMU and standby OMU The PSU, PMU, EAC, PBU, CDU, EDU, TES, TEU, MCK, and HPA

Prerequisite Note

None
z z

You cannot delete the active TMU, OMU, TRX, FPU, MFU, or MMU. The FPU in the BTS20 and the MFU in the BTS3001C can be deleted only when the TRXs have been deleted. The site output property and extended parameter will be adjusted as the default value when the EAC is deleted. For details, see section 3.8 "Modifying Site Data" and section 3.9 "Modifying the Site Output Property."

3.5.2 Procedure
To add or delete a board, perform the following steps: Step 1 On the BSC Data Auto Configuration System, choose BTS > Add or Delete Board. The Add or Delete Board dialog box as shown in Figure 3-37 is displayed.

Figure 3-37 Selecting a site

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-37

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Step 2 Select the site in which the board is to be added or deleted. Step 3 Click Next. The Add or Delete Board dialog box is refreshed, as shown in Figure 3-38.

Figure 3-38 Adding or deleting a board

Step 4 Click Add/Delete BTS Board. The Site Device's Property dialog box as shown in Figure 3-39 is displayed.

3-38

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

Figure 3-39 Configuring the property of site device

Step 5 Select the board and press Delete to delete it. Right-click in the blank of the panel and choose Add Board to add a board. You can also select and right-click the board, and then choose Add Board or Delete Board in the floating menu to add or delete the board.

TRXs cannot be deleted in this operation.

Step 6 Click Complete to return to the Add or Delete Board dialog box as shown in Figure 3-38. Step 7 Click Next. The Add or Delete Board dialog box is refreshed, as shown in Figure 3-40.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-39

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Figure 3-40 Command list for dynamic configuration

This operation leads to fourth level reset of the site. Step 8 Click Yes in the Confirm dialog box, and then click Start Dynamic Configuration to activate the data. ----End

3.5.3 Verification
After adding or deleting a board, check that:
z z

The board status is normal on the Site Maintenance System. The related data in the data tables and in the host are correctly modified.

3.5.4 Data Table


Table 3-5 lists the modified data tables in the BSC Data Management System.

Table 3-5 Modified data tables during the addition or deletion of a board No. 1 2 3 Table Name Site Frame Description Table Site Slot Description Table Antenna and Feeder Configuration Table

3-40

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

No. 4

Table Name Site Description Table

3.6 Modifying Board Type


3.6.1 Task Description
Purpose Prerequisite Note To change the types of the CDU, EDU, TRX or PBU None None

3.6.2 Procedure
To change the type of a board, perform the following steps: Step 1 On the BSC Data Auto Configuration System, choose BTS > Modify Board Type. The Modify Site Board Type dialog box as shown in Figure 3-41 is displayed.

Figure 3-41 Selecting a site

Step 2 Select a site.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-41

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Step 3 Click Next. The Modify Site Board Type dialog box is refreshed, as shown in Figure 3-42.

Figure 3-42 Changing the board type

Step 4 Click Modify BTS Board Type. The Site Device's Property dialog box as shown in Figure 3-43 is displayed.

Figure 3-43 Site device property

Step 5 through step 7 show how to change the type of the PBU board.

3-42

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

Step 5 Double-click the PBU board. The Set PBU Board Property dialog box as shown in Figure 3-44 is displayed.

Figure 3-44 Changing the PBU card type

Step 6 Select the PBU board type from the PBU Card Type drop-down list. Step 7 Click OK to return to the Site Device's Property dialog box as shown in Figure 3-43. Step 8 through step 10 show how to change the type of the CDU board. Step 8 Double-click the CDU board. The Set CDU Board Property dialog box as shown in Figure 3-45 is displayed.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-43

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Figure 3-45 Changing the CDU type

Step 9 Select the CDU type from the CDU Type drop-down list. Step 10 Click OK to return to the Site Device's Property dialog box as shown in Figure 3-43. Step 11 through step 13 show how to change the EDU type. Step 11 Double-click the EDU board. The Set CDU Board Property as shown in Figure 3-46 is displayed.

Figure 3-46 Selecting the EDU type

3-44

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

Step 12 Select the EDU type from the CDU Type drop-down list. Step 13 Click OK to return to the Site Device's Property dialog box as shown in Figure 3-43. Step 14 through step 16 show how to change the TRX type. Step 14 Double-click the TRX board. The TRX Property dialog box as shown in Figure 3-47 is displayed.

Figure 3-47 Changing the TRX type

Step 15 Select the TRX type from the TRX Type drop-down list. Step 16 Click OK to return to the Site Device's Property dialog box as shown in Figure 3-43.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-45

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

The value range of the TRX frequency is as follows:


z z z z

PTRX: 1124 ETRX: 0124 or 9751023 RTRX: 0124 or 9551023 DTRX: 512885

The value range of the ETR frequency is as follows:


z z z z

PETR: 512810 DETR: 512885 RETR: 0124 or 9551023 EETR: 128251

Step 17 Click Complete to return to the Modify Site Board Type dialog box as shown in Figure 3-42. Step 18 Click Next. The Modify Site Board Type dialog box is refreshed, as shown in Figure 3-48.

Figure 3-48 Command list for dynamic configuration

This operation leads to third level reset of the site. Step 19 Click Yes in the Confirm dialog box, and then click Start Dynamic Configuration to activate the data. ----End

3-46

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

3.6.3 Verification
Check that the related data in the data tables are correctly modified.

3.6.4 Data Table


Table 3-6 lists the modified data tables in the BSC Data Management System.

Table 3-6 Modified data tables during the modification of the board type No. 1 Table Name Site Slot Description Table

3.7 Configuring Site Tower-Top Amplifier


3.7.1 Task Description
Purpose Prerequisite Note To configure the site tower-top amplifier None The BSC Data Auto Configuration System will send a third level reset command after the site tower-top amplifier is modified.

3.7.2 Procedure
To configure the site tower-top amplifier, perform the following steps: Step 1 On the BSC Data Auto Configuration System, choose BTS > Configure Site Tower-top Amplifier. The Configure Site Tower-top Amplifier dialog box is displayed, as shown in Figure 3-49.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-47

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Figure 3-49 Selecting a site

Step 2 Select a site. Step 3 Click Next. The Configure Site Tower-top Amplifier dialog box is refreshed, as shown in Figure 3-50.

Figure 3-50 Configuring the tower-top amplifier

Step 4 Click Configure Site Tower-top Amplifier. The Site Device's Property dialog box as shown in Figure 3-51 is displayed.

3-48

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

Figure 3-51 Modifying the property of site device

Step 5 Double-click the CDU (or EDU). The Set CDU Board Property dialog box as shown in Figure 3-52 is displayed.

Figure 3-52 Site tower-top amplifier configuration

Step 6 Configure the site tower-top amplifier.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-49

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

For detailed information about the parameters, refer to the M900/M1800 BSC Data Configuration Reference Engineering Parameters. Step 7 Click OK to return to the Site Device's Property dialog box as shown in Figure 3-51. Step 8 Click Complete to return to the Configure Site Tower-top Amplifier dialog box as shown in Figure 3-50. Step 9 Click Next. The Configure Site Tower-top Amplifier dialog box is refreshed, as shown in Figure 3-53.

Figure 3-53 Command list for dynamic configuration

This operation leads to third level reset of the site. Step 10 Click Yes, and then click Start Dynamic Configuration to activate the data. ----End

3.7.3 Verification
Check that the tower-top amplifier is correctly modified on the Site Maintenance System.

3.7.4 Data Table


Table 3-7 lists the modified data tables in the BSC Data Management System.

3-50

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

Table 3-7 Modified data table during the configuration of site tower-top amplifier No. 1 Table Name Antenna and Feeder Configuration Table

3.8 Modifying Site Data


3.8.1 Task Description
Purpose Prerequisite Note To modify the clock mode, clock parameter, and transmission mode of the site None If the transmission mode is modified, the BSC Data Auto Configuration System will send the fourth level reset command.

3.8.2 Procedure
To modify the site data, perform the following steps: Step 1 On the BSC Data Auto Configuration System, choose BTS > Modify Site Data. The Modify Site Data dialog box as shown in Figure 3-54 is displayed.

Figure 3-54 Selecting a site

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-51

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Step 2 Select a site. Step 3 Click Next. The Modify Site Data dialog box is refreshed, as shown in Figure 3-55.

Figure 3-55 Modifying site data

Step 4 Click Modify Site Data. The Site Device Property dialog box as shown in Figure 3-56 is displayed.

Figure 3-56 Changing the site device property

3-52

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

Step 5 Change the site device property. For detailed information about the site description, refer to the M900/M1800 BSC Data Configuration Reference Engineering Parameters. Step 6 Click OK to return to the Modify Site Data dialog box as shown in Figure 3-55. Step 7 Click Next. The Modify Site Data dialog box is refreshed, as shown in Figure 3-57.

Figure 3-57 Command list for dynamic configuration

Step 8 Click Start Dynamic Configuration to activate the data. ----End

3.8.3 Verification
Check that the related data in the data tables and in the host are correctly modified.

3.8.4 Data Table


Table 3-8 lists the modified data tables in the BSC Data Management System.

Table 3-8 Modified data tables during the modification of site data No. 1 Table Name Site Description Table

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-53

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

No. 2 3 4

Table Name BSC BIE Description Table BSC BIE Active/Stby. Group Table Cell Call Control Table

3.9 Modifying the Site Output Property


3.9.1 Task Description
Purpose Prerequisite Note To change the relay status of the environment alarm box The site is configured with EAC. If no EAC is configured, see section 3.5 "Adding or Deleting a Board" to add it. The function is available only when the site is configured with EAC.

3.9.2 Procedure
To modify the site output property, perform the following steps: Step 1 On the BSC Data Auto Configuration System, choose BTS > Modify Site Output Property. The Modify Site Output Property dialog box as shown in Figure 3-58 is displayed.

Figure 3-58 Selecting a site

3-54

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

Step 2 Select a site. Step 3 Click Next. The Modify Site Output Property dialog box is refreshed, as shown in Figure 3-59.

Figure 3-59 Modifying site output parameters

Step 4 Click Modify Site Output Property to modify the EAC relay status. Step 5 Click Next in the Modify Site Output Property dialog box as shown in Figure 3-59. Step 6 Click Start Dynamic Configuration in the displayed dialog box to activate the data. ----End

3.9.3 Verification
Check that the related data in the data tables and in the host are correctly modified.

3.9.4 Data Table


Table 3-9 lists the modified data tables in the BSC Data Management System.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-55

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Table 3-9 Modified data table during the modification of site output property No. 1 Table Name Site Description Table

3.10 Starting Up Traffic Stat. Task Re-Register


3.10.1 Task Description
Purpose Prerequisite Note To start up traffic statistics task re-registration None The function is usually used when the operations that affect cell handover relationship are performed. These operations include dynamically adding/deleting a site, adding/deleting TRX, adding/deleting a cell, modifying cell adjacency relationship and modifying CGI.

3.10.2 Procedure
To start up traffic statistics task re-registration, perform the following steps: Step 1 On the BSC Data Auto Configuration System, choose BTS > Startup Traffic Stat. Task Reregister. The Startup Traffic Stat. Task Re-register dialog box as shown in Figure 3-60 is displayed.

3-56

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

Figure 3-60 Selecting a startup mode

Step 2 Select the startup mode. Step 3 Click Next. The Startup Traffic Stat. Task Re-register dialog box is refreshed, as shown in Figure 3-61.

Figure 3-61 Command list for dynamic configuration

Step 4 Click Start Dynamic Configuration to activate the data. ----End

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-57

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

This operation does not change any data table.

3.11 Renaming a Site or Cell


3.11.1 Task Description
Purpose Prerequisite Note To rename a site or cell None You can rename all the sites and cells in one operation.

3.11.2 Procedure
Renaming a Site
To rename a site, perform the following steps: Step 1 On the BSC Data Auto Configuration System, choose BTS > Rename Site or Cell. The Rename Site or Cell dialog box as shown in Figure 3-62 is displayed.

Figure 3-62 Renaming a site or cell

Step 2 Select a site, and then click Rename Selected Object.

3-58

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

The Rename Site dialog box as shown in Figure 3-63 is displayed.

Figure 3-63 Renaming the site

Step 3 Change the site name. Step 4 Click OK to return to the Rename Site or Cell dialog box as shown in Figure 3-62. Step 5 Click Next. Step 6 Click Start Dynamic Configuration to activate the data. ----End

Renaming a Cell
The procedure for renaming a cell, external cell, or 3G external cell is the same as that for renaming a site. The procedure is as follows: Step 1 Choose BTS > Rename Site or Cell. The Rename Site or Cell dialog box as shown in Figure 3-62 is displayed. Step 2 Select a cell, and then click Rename Selected Object. The Rename Cell dialog box, External Cell Property dialog box, or 3G External Cell Property dialog box is displayed as shown in Figure 3-64, Figure 3-65, or Figure 3-66 respectively according to the type of the selected cell.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-59

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Figure 3-64 Renaming a cell

Figure 3-65 Renaming an external cell

3-60

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

Figure 3-66 Renaming a 3G external cell

Step 3 Change the cell name. Step 4 Click OK to return to the Rename Site or Cell dialog box as shown in Figure 3-62. Step 5 Click Next. Step 6 Click Start Dynamic Configuration to activate the data. ----End

3.11.3 Verification
Check that the related data in the data tables are correctly modified.

3.11.4 Data Table


Table 3-10 lists the modified data tables in the BSC Data Management System.

Table 3-10 Modified data tables during the renaming of a site or cell No. 1 2 3 Table Name BSC Cell Table TRX Configuration Table Radio Channel Configuration Table

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-61

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

No. 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

Table Name Site BIE Configuration Table Signaling Channel Link Table System Information Table Cell Configuration Table Normal Handover Table Cell Allocation Table BA1 (BCCH) Table BA2 (SACCH) Table Cell Attribute Table Cell Alarm Threshold Table Cell Call Control Table Cell Call Control Parameter Table Cell Description Table Handover Control Table GSM0508 Handover Table Load Handover Table Intra-cell Continuous HO Control Table Penalty Table Filter Table Emergency Handover Table Adjacent Cell Relation Table Power Control Selection Table Ordinary Cell Power Control Table BTS Power Control Table MS Power Control Table Radio Channel Management Control Table Site Description Table Site Slot Description Table Carrier Configuration Table Fast-moving Handover Table Site Frame Description Table

3-62

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

No. 35 36 37 38 39 40 41 42 43 44 45 46 47 48

Table Name HW II Channel Allocation Table Site Reserved Parameter Table Cell Reserved Parameter Table TRX Reserved Parameter Table External Cell Description Table Adjacent Cell Relation Table 3G BA1 Table 3G BA2 Table 3G System Information Data Table Inter-RAT Handover Table (UTRAN FDD) UTRAN FDD Adjacent Relation Table 3G Filter Table UTRAN FDD Cell Description Table Semi-permanent Connection Table

3.12 Modifying a Ring Topology Mark


3.12.1 Task Description
Purpose Prerequisite Note To modify a ring topology mark, for example, to add or delete reverse ring port in the ring topology None None

3.12.2 Procedure
To modify a ring topology mark, perform the following steps: Step 1 On the BSC Data Auto Configuration System, choose BTS > Modify Ring Topology Mark. The Modify Ring Topology Mark dialog box as shown in Figure 3-67 is displayed.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-63

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Figure 3-67 Selecting a BIE

Step 2 Select a BIE board.

Only the BIE board whose relay mode is full rate ring topology or half rate ring topology can be selected in the Modify Ring Topology Mark dialog box as shown in Figure 3-67.

Step 3 Click Next. The Modify Ring Topology Mark dialog box is refreshed, as shown in Figure 3-68.

Figure 3-68 Selecting a BIE port

Step 4 Select the BIE port and the site.

3-64

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

If the selected BIE port is a ring network port, the Delete Topology Mark button is available and the Add Topology Mark button is unavailable. If the selected BIE port is not a ring network port, the Add Topology Mark button is available and the Delete Topology Mark button is unavailable.

You can modify the ring topology mark of only one BIE port in one operation

Step 5 Click Add Topology Mark. The Configure Closed Loop BIE Port dialog box as shown in Figure 3-69 is displayed.

Figure 3-69 Configuring the closed loop BIE port

Step 6 Select the closed loop BIE port. Step 7 Click OK to return to the Modify Ring Topology Mark dialog box as shown in Figure 3-68. To delete a topology mark, select the BIE port, and then click Delete Topology Mark to delete the reverse BIE port. Step 8 Click Next. The Modify Ring Topology Mark dialog box is refreshed, as shown in Figure 3-70.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-65

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Figure 3-70 Command list for dynamic configuration

Step 9 Click Start Dynamic Configuration to activate the data. ----End

3.12.3 Verification
Check that the related data in the data tables are correctly modified.

3.12.4 Data Table


Table 3-11 lists the modified data tables in the BSC Data Management System.

Table 3-11 Modified data tables during the modification of a ring topology mark No. 1 2 3 4 5 6 7 8 9 Table Name Radio Channel Configuration Table LAPD Semi-perm. Connection Table LAPD Signaling Connection Table BSC BIE Description Table Site BIE Trunk Mode Description Table Site BIE Configuration Table Signaling Channel Link Table Site Description Table Trunk Circuit Table

3-66

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

No. 10 11

Table Name BSC BIE Semi-permanent Connection Table BSC BIE Active/Stby. Group Table

3.13 Adding a Slave Chain to a Site


3.13.1 Task Description
Purpose Prerequisite Note To add a slave chain to a site None None

3.13.2 Procedure
To add a slave chain to a site, perform the following steps: Step 1 On the BSC Data Auto Configuration System, choose BTS > Add Slave Chain to Site. The Dynamic Add Slave Chain to Site dialog box as shown in Figure 3-71 is displayed.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-67

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Figure 3-71 Selecting a BIE

Step 2 Select a BIE board.

Only the BIE board that has at least one port not configured can be selected in the Dynamic Add Slave Chain to Site dialog box as shown in Figure 3-71.

Step 3 Click Next. The Dynamic Add Slave Chain to Site dialog box is refreshed, as shown in Figure 3-72.

Figure 3-72 Selecting a BIE port

3-68

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

Step 4 Select a BIE port. Step 5 Click Add Slave Chain. The Select Target Site for Setup Multi-Link dialog box as shown in Figure 3-73 is displayed.

Figure 3-73 Selecting a site

Step 6 Select a site. Click OK. The Select Port No. for Multi-link Site as shown in Figure 3-74 is displayed.

Figure 3-74 Selecting a port number

Step 7 Select a port number from the Access Port No. in Target Site drop-down list. Step 8 Click OK to return to the Dynamic Add Slave Chain to Site dialog box as shown in Figure 3-72. Step 9 Click Site Ports Table.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-69

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

The Site BIE Port Cascade List dialog box as shown in Figure 3-75 is displayed.

Figure 3-75 Site BIE Port Cascade List dialog box

Step 10 Modify the Inter-site port cascade relationship. Step 11 Click OK to return to the Dynamic Add Slave Chain to Site dialog box as shown in Figure 3-72. Step 12 Click Next. Step 13 Click Start Dynamic Configuration to activate the data. ----End

3.13.3 Verification
Check that the related data in the data tables are correctly modified.

3.13.4 Data Table


Table 3-12 lists the modified data tables in the BSC Data Management System.

Table 3-12 Modified data tables during the addition of a slave chain to a site No. 1 2 Table Name Radio Channel Configuration Table BSC BIE Description Table

3-70

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

No. 3 4 5 6 7 8

Table Name Site BIE Trunk Mode Description Table Site BIE Configuration Table Signaling Channel Link Table BSC BIE Active/Stby. Group Table Trunk Circuit Table BIE Port Connection Table

3.14 Deleting a Slave Chain of a Site


3.14.1 Task Description
Purpose Prerequisite Note To delete a slave chain of a site None None

3.14.2 Procedure
To delete a slave chain of a site, perform the following steps: Step 1 On the BSC Data Auto Configuration System, choose BTS > Delete Slave Chain of Site. The Dynamic Delete Slave Chain of Site dialog box as shown in Figure 3-76 is displayed.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-71

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Figure 3-76 Selecting a BIE

Step 2 Select a BIE board.

Only the BIE board that is configured with slave chains can be selected in the Dynamic Delete Slave Chain of Site dialog box as shown in Figure 3-76.

Step 3 Click Next. The Dynamic Delete Slave Chain of Site dialog box is refreshed, as shown in Figure 3-77.

Figure 3-77 Selecting a port

Step 4 Select a BIE port. Click Del. Slave Chain. The Dynamic Delete Slave Chain of Site dialog box is refreshed, as shown in Figure 3-78.

3-72

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

Figure 3-78 Deleting the slave chain

Step 5 Click Site Ports Table. The Site BIE Port Cascade List dialog box as shown in Figure 3-79 is displayed.

Figure 3-79 Site BIE Port Cascade List dialog box

Step 6 Modify the inter-site port cascade relationship. Step 7 Click OK to return to the Dynamic Delete Slave Chain of Site dialog box as shown in Figure 3-78. Step 8 Click Next. Step 9 Click Start Dynamic Configuration to activate the data.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-73

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

----End

3.14.3 Verification
Check that the related data in the data tables are correctly modified.

3.14.4 Data Table


Table 3-13 lists the modified data tables in the BSC Data Management System.

Table 3-13 Modified data tables during the deletion of a slave chain of a site No. 1 2 3 4 5 6 7 8 Table Name Radio Channel Configuration Table BSC BIE Description Table Site BIE Trunk Mode Description Table Site BIE Configuration Table Signaling Channel Link Table BSC BIE Active/Stby. Group Table Trunk Circuit Table BIE Port Connection Table

3.15 Configuring Site Idle Timeslots


3.15.1 Task Description
Purpose Prerequisite Note To configure the idle timeslots of a site None None

3.15.2 Procedure
To configure the idle timeslots of a site, perform the following steps:

3-74

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

Step 1 On the BSC Data Auto Configuration System, choose BTS > Configure Site Idle TimeSlot. The Configure Site Idle TimeSlot dialog box as shown in Figure 3-80 is displayed.

Figure 3-80 Selecting a BIE

Step 2 Select a BIE board. Step 3 Click Next. The Configure Site Idle TimeSlot dialog box is refreshed, as shown in Figure 3-81.

Figure 3-81 Selecting a port

Step 4 Select a BIE port.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-75

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Step 5 Click Configure Idle Timeslot. The Port Idle Timeslot Assignment dialog box as shown in Figure 3-82 is displayed.

Figure 3-82 Port Idle Timeslot Assignment dialog box

Step 6 Modify the site idle timeslot number. Click Apply. If the port has no idle timeslot for assignment, the Information prompt as shown in Figure 383 is displayed.

Figure 3-83 Failed idle timeslot assignment

Step 7 In the Port Idle Timeslot Assignment dialog box as shown in Figure 3-82, click Detail. The Port Idle Timeslot Assignment dialog box is refreshed, as shown in Figure 3-84.

3-76

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

Figure 3-84 Detailed information about assigned timeslots

The meaning of each parameter in the Port Idle Timeslot Assignment dialog box as shown in Figure 3-84 is as follows:
z z z z

TS No. refers to the timeslot number of E1. Site No. refers to the number of BTS to which the TRX belongs. TRX No. refers to the number of the TRX to which the channel and idle timeslot belong. Type refers to the timeslot type, such as the traffic channel (T), idle channel (I), and unused channel (U).

Step 8 Click Restore to return to the Port Idle Timeslot Assignment dialog box as shown in Figure 3-82. Step 9 Click OK to return to the Configure Site Idle TimeSlot dialog box as shown in Figure 3-81. Step 10 Click Next.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-77

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

The Configure Site Idle TimeSlot dialog box is refreshed, as shown in Figure 3-85.

Figure 3-85 Command list for dynamic configuration

Step 11 Click Start Dynamic Configuration to activate the data. ----End

3.15.3 Verification
Check that the related data in the data tables and in the host are correctly modified.

3.15.4 Data Table


Table 3-14 lists the modified data tables in the BSC Data Management System.

Table 3-14 Modified data tables during the configuration of site idle timeslots No. 1 2 3 4 Table Name Radio Channel Configuration Table Site BIE Trunk Mode Description Table Site BIE Configuration Table BSC BIE Description Table

3-78

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

No. 5

Table Name BSC BIE Semi-permanent Connection Table

3.16 Modifying Site Properties in Batches


3.16.1 Task Description
Purpose To modify a batch of site properties. These properties include Site Description, TMU Auto Activation Info, Extend Property, Output Property, and Ring Topology Property None. You can select a site type and modify all the properties of the sites that belong to this site type. You can also select all the BTS types to modify their common properties. The site properties are of three types:
z z

Prerequisite Note

General property: It includes most of the properties. TMU activation property: It includes Auto-Activation Function Switch, Main Version No. of TMU, Sub-Version No. of TMU, Version Time, Patch Number, Month, and Day. BTS output property: It includes Refrigeration Facilities, Calefaction Facilities, Dehumidification Facilities, Humidification Facilities, Fire Extinguishing Facilities, and Burglarproof Facilities.

Only one type of properties can be modified in one operation.

3.16.2 Procedure
To modify a batch of properties of sites, perform the following steps: Step 1 On the BSC Data Auto Configuration System, choose BTS > Batch Modify Site Property. The Batch Modify Site Property dialog box as shown in Figure 3-86 is displayed.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-79

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Figure 3-86 Selecting a site type and sites

Step 2 Select a site type and sites. You can also select All Site Type. Step 3 Click Next. The Batch Modify Site Property dialog box is refreshed, as shown in Figure 3-87.

Figure 3-87 Selecting site properties

Step 4 Select the properties.

3-80

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

Step 5 Click Next. The Batch Modify Site Property dialog box is refreshed, as shown in Figure 3-88.

Figure 3-88 Modifying site properties

Step 6 Click Modify Site Property. The Site Device Property dialog box as shown in Figure 3-89 is displayed.

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-81

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

Figure 3-89 Site Device Property dialog box

Step 7 Modify the site properties. Step 8 Click OK to return to the Batch Modify Site Property dialog box as shown in Figure 3-88. Step 9 Click Next. The Batch Modify Site Property dialog box is refreshed, as shown in Figure 3-90.

3-82

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

3 BTS Data Configuration

Figure 3-90 Command list for dynamic configuration

Step 10 Click Start Dynamic Configuration to activate the data. ----End

The configuration of some site parameters requires the configuration of relevant boards. For example, if the BTS is not configured with the EAC, the Upper Humidity Threshold and Lower Humidity Threshold cannot be configured. If any of the selected sites is not configured with the EAC, none of the properties related to the EAC can be configured.

3.16.3 Verification
Check that the related data in the data tables are correctly modified.

3.16.4 Data Table


Table 3-15 lists the modified data tables in the BSC Data Management System.

Table 3-15 Modified data tables during the modification of a batch of site properties No. 1 2 3 Table Name Site Description Table LAPD Signaling Connection Table Site Slot Description Table

Issue 08 (2006-08-20)

Huawei Technologies Proprietary

3-83

3 BTS Data Configuration

M900/M1800 Base Station Controller Data Configuration Manual - Dynamic Configuration

No. 4

Table Name Cell Call Control Table

3-84

Huawei Technologies Proprietary

Issue 08 (2006-08-20)

Vous aimerez peut-être aussi