Académique Documents
Professionnel Documents
Culture Documents
|
|
.
|
\
|
=
1
o
|
Setting time delay on overcurrent relays
IDMT Curve Description
Standard o
|
L
Moderately Inverse
IEEE
0.02
0.0515
0.114
Very Inverse
IEEE
2
19.61
0.491
Extremely Inverse
IEEE
2
28.2
0.1217
Inverse
US-CO8
2
5.95
0.18
Short Time Inverse
US-CO2
0.02
0.02394
0.01694
Standard Inverse
IEC
0.02
0.14
Very inverse
IEC
1.0
13.5
Extremely inverse
IEC
2.0
80.0
Long Time Inverse
IEC
1
120
IEEE and IEC constants for standards, overcurrent relays
Standards of Time/Current characteristics
General in Overcurrent Protection
Protection coordination principles
Criteria for setting instantaneous units
Coordination of OC time delay units
Example of Overcurrent Protection Setting
Fault Location, Isolation and Service Restoration
(FLISR)
System to illustrate automatic change of group setting
Content
Example - Single Line
BUSBAR 7 115kV
BUSBAR 4
BUSBAR 6
BUSBAR 3
BUSBAR 2
BUSBAR 5
BUSBAR 1
34.5 kV 34.5 kV
34.5 kV
13.2 kV
1 2 3
4
5
6 7
8
9
34.5 kV
TR2
TR1
0
.
4
5
3
k
A
L3
0
.
6
5
1
k
A
2
.
1
7
0
k
A
0
.
4
5
3
k
A
34.5/13.2 kV
3 MVA
Z%=7.3
Dy1
115/34.5 kV
15 MVA
Z%=10
Yy0
34.5 kV
182.87 MVA
3.060 kA
250/5
1 MVA
L4
L
2
1 MVA 1 MVA 1 MVA
0
.
0
0
0
k
A
0
.
0
0
0
k
A
Z
L
1
=
1
.
0
8
6
p
u
Calculate the following:
1. The three phase short circuit levels on busbars 1 and 2
2. The transformation ratios of the CTs associated with breakers 1 to 8,
given that the number of primary turns is a multiple of 100
The CT for breaker number 9 is 250/5
3. The settings of the instantaneous elements, and the TAP and DIAL
settings of the relays to guarantee a coordinated protection
arrangement, allowing a discrimination margin of 0.4 seconds
4. The percentage of the 34.5 kV line protected by the instantaneous
element of the overcurrent relay associated with breaker 6
The p.u. impedances are calculated on the following bases:
V = 34.5 kV, P = 100 MVA
Example - Data
All the relays to be set are Beckwith M-7651, numerical type,
with the characteristics indicated in the following slide.
Relay 7 is a Westinghouse CO 11. The settings are:
TAP = 4 A
DIAL = 5
Instantaneous = 1100 A
Example - Data
Now, consider all the relays to be set are Beckwith M-7651, numerical
type with the characteristics indicated in the following slide. The relays
have an extremely inverse time current characteristic with the following
constants:
o = 2.0,
| = 80
L = 0
The TCC is defined by
Where MULT = Fault current (in secondary amps)/TAP
The following considerations have to be taken into account:
For setting of the instantaneous element a value of ten (10) times the
maximum load current is used.
The margin time for this relay can be 0.2 s since it is of numerical type.
Relay 7 is the same W CO 11 with TAP = 4 A, DIAL = 5 and Inst =
1100 A
Example - Settings with a numerical relay
( ) 1
80 *
2
=
MULT
Dial Time
t
Characteristics of relay M-7651
The PICK UP or TAP
settings are available in
Steps of 0.001
The TIME DIAL
settings are available in
Steps of 0.01
Example Short circuit printout
Fault location Distance
from fault
Element
name
Type Un [kV]
UL-E (RST)
[kV]
AU L-E
(RST) []
Ik" (RST)
[kA] From Node To Node
BUSBAR6 Faulted 0 34,5 19,919 180 3,06
BUSBAR6 BUSBAR2 L1 Line 0
BUSBAR6 BUSBAR3 L2 Line 0
BUSBAR6 BUSBAR5 L4 Line 0,453
BUSBAR6 BUSBAR4 L3 Line 0,453
BUSBAR6 BUSBAR7 TR1 2W Transformer 2,17
BUSBAR2 1 34,5 19,919 180
BUSBAR2 BUSBAR6 L1 Line 0
BUSBAR2 BUSBAR1 TR2 2W Transformer 0
BUSBAR3 1 34,5 19,919 180
BUSBAR3 BUSBAR6 L2 Line 0
BUSBAR5 1 34,5 8,281 179,94
BUSBAR5 BUSBAR6 L4 Line 0,453
BUSBAR5 BUSBAR5
G8
Synchronous
Machine
0,453
BUSBAR4 1 34,5 8,281 179,94
BUSBAR4 BUSBAR6 L3 Line 0,453
BUSBAR4 BUSBAR4
G15
Synchronous
Machine
0,453
BUSBAR7 1 115 8,988 180
BUSBAR7 BUSBAR6 TR1 2W Transformer 0,651
BUSBAR7 BUSBAR7 EQUIVALENT Network Feeder 0,651
BUSBAR1 2 13,2 7,621 180
BUSBAR1 BUSBAR2 TR2 2W Transformer 0
Tap setting - Example
I
load1,2,3
= 43.74 A Pickup
1,2,3
= (1.5)(43.74)(5/100) = 3.28 A Pickup
1,2,3
= 3.28 A
I
load4
= 131,22 A Pickup
4
= (1.5)(131.22)(5/200) = 4.92 A Pickup
4
= 4.92 A
I
load5
= 50.20 A Pickup
5
= (1.5)(50.20)(5/100) = 3.76 A Pickup
5
= 3.76 A
I
load6
= 50.20 A Pickup
6
= (1.5)(50.20)(5/200) = 1.88 A Pickup
6
= 1.88 A
I
load8
= 251.02 A Pickup
8
= (1.5)(251.02)(5/300) = 6.28 A Pickup
8
= 6.28 A
I
load9
= 75.31 A Pickup
9
= (1.5)(75.31)(5/250) = 2.26 A Pickup
9
= 2.26 A
Summary of currents and CT ratios Example
Breaker
No.
Pnom
(MVA)
Inom
(A)
Isc
(A)
5/100
Isc
(A)
CT
Ratio
9
8
7
6
5
4
1,2,3
15
15
1
3
3
3
1
75.31
251.02
16.73
50.20
50.20
131.22
43.74
4797.35
2170.40
3060.34
3060.34
1025.67
1076.06
1076.06
233.12
108.51
153.01
153.01
51.28
53.80
53.80
250/5
300/5
200/5
200/5
100/5
200/5
100/5
Settings with a numerical relay
Relays 1, 2 and 3
Iinst. trip = 10 Inom (1/CTR)
= 10 43.74 (5/100) = 21.87 A
Iprim. trip = 21.87(100/5) = 437.4 A.
MULT = 21.87/3.28 = 6.668 times
with Time Dial = 0.05,
Relay 4
To coordinate with relays 1, 2 and 3 at 437.4 A ,
relay 4 requires that t
4a
= 0.092 + 0.2 = 0.292 s.
( )
s t 092 . 0
1 668 . 6
80 05 . 0
2
=
=
Settings with a numerical relay
MULT
4a
= (437.4)(5/200)(1/4.92) = 2.223 times.
At 2.223 times, and t
4a
= 0.292 s,
However, the dial 0.05 is the minimum that the relay has.
This relay has no setting for the instantaneous
( ) ( ) 01 . 0 1 223 . 2
80
292 . 0
2
=
|
.
|
\
|
= Dial Time
Summary of numerical relay settings Example 2
Relay
No.
CT ratio
Tap
DIAL
Instantaneous
1,2,3
4
5
6
7
8
9
100/5
200/5
100/5
200/5
200/5
300/5
250/5
3.28
4.92
3.76
1.88
4
6.28
2.26
0.05
0.05
0.14
0.25
5
0.05
0.13
21.87 A
25.73 A
32.05 A
27.5 A
16.27 A
Example 2- Coordination Curves with NR
0,010 kA 0,100 kA 1,0 kA 10,0 kA 100 kA 1000 kA
1000 s
100 s
10,0 s
1,0 s
0,100 s
0,010 s
0,010 kA 0,100 kA 1,0 kA 10,0 kA 100 kA
13,2 kV:
35 kV:
R-1
R-2
R-3
R-4
R-5
R-6
R-7
R-8
R-9
L-1
T-2
T-1
Using Beckwith Software for Relay M-7651
Using Beckwith Software for Relay M-7651
Using Beckwith Software for Relay M-7651
Using Beckwith Software for Relay M-7651
For the Relay 5
Using Beckwith Software for Relay M-7651
For the Relay 5
Using Beckwith Software for Relay M-7651
For the Relay 5
Using Beckwith Software for Relay M-7651
For the Relay 5
Using Beckwith Software for Relay M-7651
For the Relay 5
Using Beckwith Software for Relay M-7651
For the Relay 5
Using Beckwith Software for Relay M-7651
Thermal limits of copper conductors
Thermal Plastic
Insulation 75C
Thermal capacity of transformers
T
I
M
E
(
s
e
c
o
n
d
s
)
TIMES NORMAL BASE CURRENT
1
0.9
0.8
0.7
0.6
0.5
0.4
0.3
0.2
0.1
1 2 3 4 5 6 7 8 9 10 20 30 40 50 2 3 4 5 6 7 8 9 10 20 30 40 50
10
9
8
7
6
5
4
3
2
100
90
80
70
60
50
40
30
20
1000
900
800
700
600
500
400
300
200
10000
9000
8000
7000
6000
5000
4000
3000
2000
CATEGORY TRANSFORMERS
Above 10000 kVA Single-Phase
Above 30000 kVA Three-Phase
IV
THROUGH-FAULT PROTECTION CURVE
FOR FAULTS WHICH WILL OCCUR
FREQUENTLY OR INFREQUENTLY
K TRANSFORMER IMPEDANCE
12 10 8 7 6 5 4
Category IV
Checking of energizing conditions
It is important to check that the relay settings are not going to
present problems when system elements are energized.
In the case of transformers, the initial magnetization inrush current
can be expressed as:
I
Inrush
= K I
nom
where
I
nom
= nominal transformer current
K = 8, from 500 to 2,500 kVA transformer capacity
K = 10 above 2,500 kVA transformer capacity
The inrush point remains during 0.1 seconds.
General in Overcurrent Protection
Protection coordination principles
Criteria for setting instantaneous units
Coordination of OC time delay units
Example of Overcurrent Protection Setting
Fault Location, Isolation and Service Restoration
(FLISR)
System to illustrate automatic change of group setting
Content
Power System Restoration
One of the most important functions in Distribution Automation
(DA) is the service restoration in case of a fault in the primary
feeder.
The main goal of automatic service restoration is the execution of
series of operations of the tie (NO) and section (NC) switches,
directed to restore the energy supply to the maximum number of
possible areas that have been affected after a fault in a primary
feeder or substation.
The above normally implies to reconfigure the network by
transferring loads from the healthy portions of faulty feeders to
neighbor feeders that are operating normally.
Illustration of Normal Condition
Illustration of Upstream Restoration
Illustration of Downstream Restoration
System reconfiguration changes topologies and therefore line
flows and short circuit values also change.
Different scenarios may be feasible for the same fault condition as
illustrated in the figure.
In these circumstances equipment duties have to be checked,
voltage profiles and equipment loading.
Relay values of pick up and time dials have to be rechecked to
assure that nuisance tripping do not occur or unwished pick ups.
This requires necessarily the use of different group settings.
Power System Restoration
The steps to restore service when a fault happens can be
summarized as follows:
1. The corresponding relay operates and trips the breaker. If
reclosing units operate and the fault remains, the feeder is
open.
2. The fault is located and the associated section switches open to
isolate it.
3. The feeder is re-energized up to the location of the first section
switch that was open Upstream Restoration.
4. The healthy sections are transferred to one or more neighbor
feeders by operating NO switches Downstream Restoration.
5. The faulty section is repaired by the crew.
The first four steps ideally should be completed within a minute to
avoid affecting SAIFI and SAIDI values.
Fault Location, Isolation and Service Restoration
(FLISR)
I II III
F
3
2
F
1
F
6
5
7
10
8
9
1
11
T1
T2
T3
2
3
4
12
14
13
Location of NC and NO Switches in a DS
Manual Restoration vs FLISR
When a permanent fault occurs, customers on healthy
sections of the feeder may experience a lengthy outage.
FLISR provides the means to restore service to some
customers before field crews arrive on the scene.
When carrying out the reestablishment, the operations that are
executed should allow that the system satisfies some restrictions,
such as:
The capacity of current of the transformers and lines should be
within specified limits
The voltage drop should stay inside an established margin.
System should continue being radial
The Number of operations of the equipment has limits
Important customers have priority
System must be balanced in the best possible way
The coordination of the protection must be maintained
Restrictions for Restoration
Case Example Initial Configuration
Feeder in studio
B1 Z1
Z3
Z4
Z5
Z2
Z6
Z7
B3
B4
B2
Z8
Z9
Z10
Z11
Z12 Z13 Z14 S1
S2
S3
S4
S5
S6
S7
S8
S9
S10
S11 S12 S13
Circuit Breaker
Section switch normally closed
Tie switch normally open
Zi Feeder section
Case Example Fault Clearing
B1 Z1
Z3
Z4
Z5
Z2
Z6
Z7
B3
B4
B2
Z8
Z9
Z10
Z11
Z12 Z13 Z14 S1
S2
S3
S4
S5
S6
S7
S8
S9
S10
S11 S12 S13
Circuit Breaker
Section switch normally closed
Tie switch normally open
Zi Feeder section
Case Example Fault Location and Isolation
B1 Z1
Z3
Z4
Z5
Z2
Z6
Z7
B3
B4
B2
Z8
Z9
Z10
Z11
Z12 Z13 Z14 S1
S2
S3
S4
S5
S6
S7
S8
S9
S10
S11 S12 S13
Circuit Breaker
Section switch normally closed
Tie switch normally open
Zi Feeder section
Case Example Feeder Reenergization
B1 Z1
Z3
Z4
Z5
Z2
Z6
Z7
B3
B4
B2
Z8
Z9
Z10
Z11
Z12 Z13 Z14 S1
S2
S3
S4
S5
S6
S7
S8
S9
S10
S11 S12 S13
Circuit Breaker
Section switch normally closed
Tie switch normally open
Zi Feeder section
Case Example System Restoration
B1 Z1
Z3
Z4
Z5
Z2
Z6
Z7
B3
B4
B2
Z8
Z9
Z10
Z11
Z12 Z13 Z14 S1
S2
S3
S4
S5
S6
S7
S8
S9
S10
S11 S12 S13
Circuit Breaker
Section switch normally closed
Tie switch normally open
Zi Feeder section
Case Example Return to Original Configuration
B1 Z1
Z3
Z4
Z5
Z2
Z6
Z7
B3
B4
B2
Z8
Z9
Z10
Z11
Z12 Z13 Z14 S1
S2
S3
S4
S5
S6
S7
S8
S9
S10
S11 S12 S13
Circuit Breaker
Section switch normally closed
Tie switch normally open
Zi Feeder section
Case Example Initial Configuration
F2 Load =3p.u.
F1 Load =7p.u.
F3 Load =2p.u.
F4 Load =2p.u.
Total Load =14p.u.
B1 Z1
Z3
Z4
Z5
Z2
Z6
Z7
B3
B4
B2
Z8
Z9
Z10
Z11
Z12 Z13 Z14 S1
S2
S3
S4
S5
S6
S7
S8
S9
S10
S11 S12 S13
Circuit Breaker
Section switch normally closed
Tie switch normally open
Zi Feeder section
Case Example System Reconfigured
F2 Load =5p.u.
F1 Load =1p.u.
F3 Load =4p.u.
F4 Load =3p.u.
Total Load =13p.u.
B1 Z1
Z3
Z4
Z5
Z2
Z6
Z7
B3
B4
B2
Z8
Z9
Z10
Z11
Z12 Z13 Z14 S1
S2
S3
S4
S5
S6
S7
S8
S9
S10
S11 S12 S13
Circuit Breaker
Section switch normally closed
Tie switch normally open
Zi Feeder section
A fault will occur
in the magenta feeder
Initial Situation
FLISR Central Intelligence
Magenta Feeder
has tripped
FLISR Central Intelligence
restore
is called to
isolate the fault
and restore the
network
FLISR Central Intelligence
restore has
1- isolated the fault
2- restored the part
upstream to the fault,
using the fault
detectors
FLISR Central Intelligence
All possible
Restoration plans
are then proposed
to the operator
FLISR Central Intelligence
One Restoration plan
is selected
FLISR Central Intelligence
Breaker that open to
avoid two-end supply
of feeders
only a small zone is
still out of supply
and need repair
Restoration plan
has been executed
Breakers that close
to
restore the system
FLISR Central Intelligence
Distributed Intelligence automatically isolates faulted distribution
segments using a team of peer devices.
It requires proper communication and protective relay coordination.
Reconfigures adjacent feeders to restore power to customers
beyond fault.
Minimizes outage size and duration.
FLISR Distributed Intelligence
FLISR Distributed Intelligence
FLISR Local Intelligent
Substation A
Substation B
R014
R013
R015
R017
R016
R016
Group1
R013
Group1
R015
Group1
Substation A
R016
Group1
UV
OC
AR-Reclosers
2s, 3s
R013
Group1
OC
UV-4s
AR-Reclosers
2s, 3s
R015
Group1
ABR-5s
OC
AR
Substation B
R014
R017
FLISR Local Intelligent
R016
Group1
R013
Group1
R015
Group1
Substation A
R016
Group1
UV
OC
AR-Reclosers
2s, 3s
R013
Group1
OC
UV-4s
AR-Reclosers
2s, 3s
R015
Group1
ABR-5s
OC
AR
Substation B
R014
R017
FLISR Local Intelligent
R016
Group1
R013
Group1
R015
Group1
Substation A
R016
Group1
UV
OC
AR-Reclosers
2s, 3s
R013
Group1
OC
UV-4s
AR-Reclosers
2s, 3s
R015
Group1
ABR-5s
OC
AR
Substation B
R014
R017
FLISR Local Intelligent
R016
Group1
R013
Group1
R015
Group1
Substation A
R016
Group1
UV
OC
AR-Reclosers
2s, 3s
R013
Group1
OC
UV-4s
AR-Reclosers
2s, 3s
R015
Group1
ABR-5s
OC
AR
Substation B
R014
R017
Count 2 s
FLISR Local Intelligent
R016
Group1
R013
Group1
R015
Group1
Substation A
R016
Group1
UV
OC
AR-Reclosers
2s, 3s
R013
Group1
OC
UV-4s
AR-Reclosers
2s, 3s
R015
Group1
ABR-5s
OC
AR
Substation B
R014
R017
FLISR Local Intelligent
R016
Group1
R013
Group1
R015
Group1
Substation A
R016
Group1
UV
OC
AR-Reclosers
2s, 3s
R013
Group1
OC
UV-4s
AR-Reclosers
2s, 3s
R015
Group1
ABR-5s
OC
AR
Substation B
R014
R017
FLISR Local Intelligent
R016
Group1
R013
Group1
R015
Group1
Substation A
R016
Group1
UV
OC
AR-Reclosers
2s, 3s
R013
Group1
OC
UV-4s
AR-Reclosers
2s, 3s
R015
Group1
ABR-5s
OC
AR
Substation B
R014
R017
FLISR Local Intelligent
R016
Group1
R013
Group1
R015
Group1
Substation A
R016
Group1
UV
OC
AR-Reclosers
2s, 3s
R013
Group1
OC
UV-4s
AR-Reclosers
2s, 3s
R015
Group1
ABR-5s
OC
AR
Substation B
R014
R017
FLISR Local Intelligent
R016
Group1
R013
Group1
R015
Group1
Substation A
R016
Group1
UV
OC
AR-Reclosers
2s, 3s
R013
Group1
OC
UV-4s
AR-Reclosers
2s, 3s
R015
Group1
ABR-5s
OC
AR
Substation B
R014
R017
FLISR Local Intelligent
General in Overcurrent Protection
Protection coordination principles
Criteria for setting instantaneous units
Coordination of OC time delay units
Example of Overcurrent Protection Setting
Fault Location, Isolation and Service Restoration
(FLISR)
System to illustrate automatic change of group setting
Content
System to illustrate automatic change of group setting
G1
T1 T2
1
2
3
4
Grid
G2
Coordination curves considering adaptive relaying
T1 T2
1
2
3
4
Grid
G1
G2
Loss of a Parallel Transformer
t2
0.5If
t2a
R1
If
t1
R2a
If
t1
R2
t2
Outage of G2
Ir1 =It1+It2 Ir2 =It1
T1 T2
1
2
3
4
Grid
G1
G2
Loss of a DG Source
t2
Ir2
t2a
R
1
Ir1
t1
Ir1
t1
R2
Normal Condition
Ir1 =It1+It2+Ig2 Ir2 =It1
R2a
Coordination is lost in the
yellow area unless a setting
group change is enabled
Coordination curves considering adaptive relaying
Questions ?
jmgers@gersusa.com
Tel: 954-384 8925