Académique Documents
Professionnel Documents
Culture Documents
Introductions
Biography Mr. Livengood is a registered architect with more than 35 years of experience in architectural design, project management, design analysis, and document preparation. He is also an attorney experienced in construction litigation, government contracts, international contracts and arbitration, as well as schedule delay and claims on a variety of large and small projects. He has served as an expert witness and testified on scheduling, damages, and causation issues numerous times. Mr. Livengood has written numerous articles on schedule delay and claims issues.
Introductions
Biography Mr. Kelly has more than 15 years of construction management, government contracts and consulting experience in the private and public sectors. He has been engaged by both the owner and contractor on Federal, State and Municipal levels and specializes in transportation, government facilities and critical structures assignments. He has provided forensic schedule analysis and litigation support on construction methodology, cost analysis, and delay/disruption issues, and has written several articles on scheduling and delay analysis .
Introduction
This is the Critical Path, and a slippage or delay in completion of any activity along that path will extend final completion correspondingly.
Definition of QRA
Quantitative Risk Analysis:
Risk analysis is used to estimate a numerical value (usually probabilistic) on risk outcomes wherein risk probabilities of occurrence and impact values are used directly rather than expressing the severity narratively or by ranking as in qualitative methods.
Purpose of QRA
Assessing the potential variability in project duration (in individual activities, various subnetworks, or the overall completion milestone) resulting from identified project risks. Assessing how risks, including threats and opportunities, in the project schedule may influence project economics. Understanding which paths in the schedule have the highest probability of influencing the schedule completion or key milestones. Understanding which risks have the most influence on overall schedule variability.
Risks are identified by the project management team and tracked in a Risk Register. Register shows risks, likely impacts, responsible party for the risk, and party responsible for mitigating the risk.
Risks listed in register are then associated with specific activities within the schedule, and relate to duration estimates. Risk Register could be used after the fact to determine responsibility and efficacy of actions taken to mitigate risk.
10
The establishment of these points of the triangular distribution curve is a matter of judgment for the scheduler and the risk analyst, but these points have a major effect on the Monte Carlo simulation.
11
13
14
17
18
Contemporaneous Period Analysis (Windows) Bifurcated CPA Recreated CPA Impacted As-Planned
Dynamic Logic
Modeled
Additive Model
Retrospective TIA
Subtractive Model
19
Methodology Selection
Facts of the Case
1st
Technical Considerations
2nd
Quality of source data Complexity of the dispute Timing of analysis Expertise of analyst
Choosing a methodology is a process that must consider and balance a variety of selection factors, based on these priorities.
Commercial Considerations
3rd
20
10
Methodology Selection
An analysts selection of a methodology is based (at least in part) on the quality of the existing schedules, and how they were used on the project. If the project schedules were used to plan and execute the project, it is advisable to use those schedules in the analysis.
The schedules would have influenced the contemporaneous understanding of criticality.
21
Contemporaneous Understanding of Criticality and Variability of the Critical Path in Risk Adjusted Schedules
11
QRA is a process that attempts to quantify, using the initial schedule (and possibly updates), what events are most likely to have their cushions of float consumed. The analyst must understand how this process influenced the contemporaneous understanding of criticality.
24
12
Task Y Path 2
Non-Critical Activity Critical Activity Float Bar
Path 1 drives the Critical Path in the initial schedule, and Path 2 (through Task Y) shows 12 days of Total Float (roughly 7% of project duration).
26
13
Based on duration estimates, clearly there is some likelihood that Path 2 will drive the Critical Path. Software helps quantify that likelihood.
27
Distribution
Projects duration is a range rather than a definite number. How should that be handled in the Firm Fixed Price Contract?
28
14
Distribution
Did this influence the contemporaneous understanding of criticality? Did the project management team act on this information?
29
15
Whether or not the QRA process was relevant to the project management teams actions is likely to be revealed during document research. If it did (as it should have why else do a QRA?) then the analyst must account for this fact in the delay analysis.
31
Risk-Adjusted Schedules: Questions for the Forensic Analyst How was the schedule risk-adjusted? What was the Quality of the Risk Adjustment? Did the Risk Adjusted Schedule Influence the Contemporaneous Understanding of Criticality?
32
16
First Question
How was the schedule risk adjusted?
Summary Schedule QRA
More common. Often performed by the owner during planning, and not used by contractor. Summary schedule doesnt rise to the level of detail necessary to show means and methods. Some argue more useful overall, but likely to result in a time (or cost) contingency rather than influencing thoughts on criticality.
Summary Schedule QRA may still provide insight into the project; however, it is not particularly relevant to FSA methodology selection.
33
First Question
How was the schedule risk adjusted?
Detailed Schedule QRA
Often criticized as overly difficult or infeasible. Means and methods are represented by the level of detail. More likely to influence thoughts on criticality.
Assuming Detail Schedule, adjusted through QRA, was then used to plan and implement the project, how well was the QRA performed?
34
17
Second Question
What was the Quality of the Risk Adjustment?
Quality of QRA is its own Source Validation Protocol. RP 64R-11s Minimum Conditions of Satisfaction are relevant.
35
18
Second Question
What was the Quality of the Risk Adjustment?
Potential questions to ask:
What was the basis of estimation for the three-point estimates? Did they come from some identifiable source or quantifiable means? Were the line-by-line estimates performed in light of accurate estimates of quantity/resource levels/production rates? What was the basis of choice of a distribution curve, if not a triangular distribution? Were issues related to merge bias taken into account? Were risks properly correlated?
37
Third Question
Did the Risk Adjusted Schedule Influence the Contemporaneous Understanding of Criticality?
Again, the answer to this question is in the project documents. If the QRA was performed and ignored, its value to the analyst is diminished. Was QRA used in update schedules? Recovery schedules?
38
19
Methodology Selection
Facts of the Case
1st
Technical Considerations
2nd
Quality of source data Complexity of the dispute Timing of analysis Expertise of analyst
As a supplement to the first and second level factors for consideration in methodology selection, the analyst must also account for the QRA and the riskadjusted schedules.
Commercial Considerations
3rd
40
20
critical path.
Dynamic Logic
Windows. Use information to track CPs and show how means & methods were altered to react to QRA. Not useful in performance, but could help justify use of IAP. No effect on this method.
Modeled
Additive Model
Retrospective TIA
Subtractive Model
No effect on these methods, because they do not rely on contemporaneous Collapsed As-Built (Multiple) understanding of criticality.
41
Conclusion
Contemporaneous Period Analyses (observational/ dynamic logic) uses the existing schedule series which strongly rely on contemporaneous understanding of criticality.
Existence of a QRA should recommend a CPA (or BCPA) analysis as a method, assuming other requirements are met. Factoring in the QRA is essential.
42
21
Conclusion
The As-Planned vs. As-Built family (observational/static logic) relies in part on contemporaneous understanding of criticality for definition of the as-planned critical path. Regardless of selected methodology, the performance of the QRA will likely have generated important documentation (intentions, means and methods, etc.) that should be nonetheless considered by analysts.
43
Questions?
John C. Livengood Esq., AIA, CFCC, PSP Construction Claims Services ARCADIS U.S., Inc.
John.Livengood@arcadis-us.com (O) 410-381-1990 x31 (M) 202-669-1360
Patrick M. Kelly, PE, PSP Construction Claims Services ARCADIS U.S., Inc.
Patrick.Kelly@arcadis-us.com (O) 410-381-1990 x12 (M) 757-217-6820
22