ANCHOR WINCH COOLING PUMP MISSION 2500, SUPREME 6x5x14, 13.7 IMP.

, 75 HP, 1750 RPM - SUCTION LINE VELOCITY 205 m3/hr - DISCHARGE CAPACITY/FLOWRATE 400 GPM or 100 m3/hr @ 213 ft. Pump Capacity Analysis: Given: Height of RIG Floor = 115 ft. Discharge Flow rate = 400 GPM Discharge/Pressure Head = 213 ft. For RIG Floor Drill Water Transfer Pump Head Calculation = H = hd hs 1. Solving for hs = hss + hps - hfs Where; hs=total suction head, hss=suction static head, hps=suction surface head, hfs=suction friction head Minimum Static Head; suction tank is below the pump centerline hss = -10.83ft hps = 0 ft, since theres no pressure For the friction loss, 6 pipe at 900 gpm, from table pipe friction manual, is 1.09 ft per hundred ft of pipe Therefore; (10.83/100)(5.05) = 0.55 ft Solving for friction coefficient (K), From the table, Fittings K 6 900 elbow 0.29x4 = 1.16 6 sq. edge 0.5 6 gate valve 0.11x2 = 0.22 Total coefficient, K=1.88 From Table, V2/2g=1.55 Friction loss on fittings= K(V2/2g) = 1.88x1.55 = 2.91ft Total friction loss on suction= 0.55+2.91 = 3.46ft hs=-10.83+0-3.46 = -14.29 2. Solving for hd = hsd + hpd + hfd Where; hd=total discharge head, hsd=static discharge head, hdp = discharge pressure head, hfd=discharge friction head Static discharge head, total elevation from pump centerline hsd=122ft hpd=0 ft For friction loss, 4 at 400gpm, from table pipe friction manual, is 8.47ft per hundred ft of pipe. Friction loss = (length of pipe/100)x8.47 = (52.33/100)x8.47 = 4.43 ft Friction loss on fittings Fittings K 4 900 elbow 0.22x7 =1.54 4 gate valve 0.16 4 tee 0.14 Total coefficient, K=1.84 From Table, V2/2g=1.58 Friction loss on fittings=K(V2/2g) = 1.84x1.58 = 2.91 ft Total friction loss on discharge = 4.43+2.91 = 7.34 hd=122+0+7.34 = 129.34 ft H = hd hs = 129.34 (-14.29) = 143.63 ft

Suction pipe dia. = 6 Discharge pipe dia= 5

ANCHOR WINCH COOLING PUMP MISSION 2500, SUPREME 6x5x14, 13.7 IMP., 75 HP, 1750 RPM - SUCTION LINE VELOCITY 205 m3/hr - DISCHARGE CAPACITY/FLOWRATE 400 GPM or 100 m3/hr @ 213 ft. Pump Capacity Analysis: Given: Height of RIG Floor = 115 ft. Discharge Flow rate = 400 GPM Discharge/Pressure Head = 213 ft.

Suction pipe dia. = 6 Discharge pipe dia= 5

For Anchor Winch Drill Water Transfer Pump Head Calculation = H = hd hs 1. Solving for hs = hss + hps - hfs Where; hs=total suction head, hss=suction static head, hps=suction surface head, hfs=suction friction head Minimum Static Head; suction tank is below the pump centerline hss = -10.83ft hps = 0 ft, since theres no pressure For the friction loss, 6 pipe at 900 gpm, from table pipe friction manual, is 1.09 ft per hundred ft of pipe Therefore; (10.83/100)(5.05) = 0.55 ft Solving for friction coefficient (K), From the table, Fittings K 6 900 elbow 0.29x4 = 1.16 6 sq. edge 0.5 6 gate valve 0.11x2 = 0.22 Total coefficient, K=1.88 From Table, V2/2g=1.55 Friction loss on fittings= K(V2/2g) = 1.88x1.55 = 2.91ft Total friction loss on suction= 0.55+2.91 = 3.46ft hs=-10.83+0-3.46 = -14.29 2. Solving for hd = hsd + hpd + hfd Where; hd=total discharge head, hsd=static discharge head, hdp = discharge pressure head, hfd=discharge friction head Static discharge head, total elevation from pump centerline hsd=35ft hpd=0 ft For friction loss, 4 at 400gpm, from table pipe friction manual, is 8.47ft per hundred ft of pipe. Friction loss = (length of pipe/100)x8.47 = (515/100)x8.47 = 43.62 ft Friction loss on fittings Fittings K 4 900 elbow 0.22x9 =1.98 4 gate valve 0.16x2 =0.32 4 tee 0.14x3 =0.42 Total coefficient, K=2.66 From Table, V2/2g=1.58 Friction loss on fittings=K(V2/2g) = 2.66x1.58 = 4.2 ft Total friction loss on discharge = 43.62+4.2 = 47.82 ft hd=35+0+47.82 = 82.82 ft H = hd hs = 82.82 (-14.29) = 97.11 ft

Vous aimerez peut-être aussi