LONG-HOLE MODULE : SUPPORT, DRILLING, BLASTING

Version: April 2, 2004 FLOOR MOBILIZATION AND

CABLES
DRILLING INSTALLATION DRILLING

DROP RAISES
REDRILLING BLASTING DRILLING

LONG-HOLE
REDRILLING BLASTING

CLEANING Hours

DEMOBILIZATION

1 2 3
Preparation ( 1 hr) (section 2.0) Preparation ( 0.3 hr/shift) (section 4.3)

Fixed activities per shift 2.13 hours/shift (section 1.0)

Preparation ( 0.3 hr/shift) (section 4.3) Fixed time ( 2.17 hr /sub-level) (section 2.0) Fixed time ( 2.48 hr/ blast) (section 2.0)

Preparation ( 0.3 hr/shift) (section 4.3) Fixed time ( 2.48 hr/ blast) (section 2.0)

5
8 m advanced /hour with 2 men (section 4.1) 3.83 hours/sub-level with 2 men (section 3.0) 3.1 m advanced /shift with 2 men (section 4.5.2)

14.9 m/hour (section 4.4) 0.13 hr/hole of 5 meters with 2 men (section 4.4)

8.9 m/hour (section 4.3)

13.9 m/hour (section 4.3) 4.7 rows/shift with 2 men (section 4.5.2)

2 blasts/ drop raise (section 4.2.1)

Productivity

18.8 meters/ms

9 manshifts/sub

76 m/ms

94.6 meters/ms

43 meters/manshift

31.6 t/ms

67.3 meters/manshift

144.7 t/ms

File: 159332107.xls.ms_office Sheet: Compilation Page 1 of 16

Experimental Mine Val-d'Or

7/22/2013 12:19 AM

UNIT COST DISTRIBUTION PER ACTIVITY MODULE: SUPPORT, DRILLING, BLASTING


FLOOR CLEANING MOBILIZATION & DEMOBILIZATION hours 75.9 $/tonne $ 0.11 Version: April 2, 2004

CABLES
DRILLING hours 719.5 $/tonne $ 1.06 INSTALLATION hours 612.6 $/tonne $ 0.90 DRILLING hours 107.1 $/tonne $ 0.16

DROP RAISES
REDRILLING hours 10.6 $/tonne 0.02 BLASTING hours 187.3 $/tonne 0.27 DRILLING hours 975.3 $/tonne $ 1.43

LONG-HOLE
REDRILLING hours 9.7 $/tonne 0.01 BLASTING hours 1552.2 $/tonne $ 2.28 TOTAL hours 4487.59 $/tonne $ 6.59

1 - Labour
Salary ($/hour) Bonus ($/hour) Fringe benefits Total ($/hour) Hours/shift $ 20.00 $ 8.19 50% $ 42.29 8
$/tonne

hours 237.4 $/tonne $ 0.35

2 - Material
Drilling (Long-Hole) including rods, steel bits, hoses, lubricants and grease Explosives and accessories Support mechanical rockbolts rebars and resin Split-Set Swellex screen cables, ciment and drilling shotcrete total support : Timber Track Pipes Ventilation Other supplies $

1.85

2.74

$ $ $ $ $ $ $ $

0.80 0.20 1.00 0.20 0.10 1.00

3 - Equipment maintenance
mechanical electrical diesel and lubricants $ $ $ $ 0.35 $ 0.11 $ $ 1.06 $ 0.90 $ $ 0.16 $ 0.02 $ 0.27 $ $ 5.22 1.43 $ 0.01 $ 2.28 -

Total/tonne

$ 13.48

4.45 $/drilled m (cables)

6.29 $/drilled m (drop raises) $

5.02 $/drilled m (Long-Hole)

$/drilled m (drop raises and Long-Hole)

Labour only

File: 159332107.xls.ms_office Sheet: Costs Page 2 of 16

Experimental Mine Val-d'Or

7/22/2013 12:19 AM

LONG-HOLE STOPE PRODUCTIVITY CALCULATION

Version: April 2, 2004

1.0 - DIRECT FIXED ACTIVITIES PER SHIFT (outside the stope)


Frequency or Units Time (min)/Unit Total Time (min)

NOTES
Three-meter wide stope Two working areas per sub-level Ramp access to sub-level Three sub-levels 6 meters apart (floor/roof)

Cage (at beginning and end of shift) Travelling (shaft - refuge station - shaft) Other travelling delays Back and forth to stope Supervision Work planning Complete daily reports Lunch

2 2 4 1 1 1 1

8 5 8 15 10 15 30

16 10 0 32 15 10 15 30 0 128 minutes 2.13 hours/shift

2.0 - DIRECT FIXED ACTIVITIES PER STEP (inside the stope)


RELATED TO FLOOR CLEANING
Bring and prepare material Store material
Frequency or Units Time (min)/Unit Total Time (min) Frequency or Units Time (min)/Unit Total Time (min)

RELATED TO BLASTING
Bring and prepare material Clean the floor following blast Store equipment and explosives Check blasting line Connect the blast Close access to the stope Access verification following blast Extra scaling Repair and install ventilation

1 1

30 30

minutes/sub-level hours/sub-level

30 30 0 0 60 1.00
Total Time (min)

1 1 1 1 1 1 1 1 1

6 60 20 15 5 8 15 5 15

6 60 20 15 5 8 15 5 15 0 0 0 0 0 149 2.48

RELATED TO ANCHOR CABLE INSTALLATION


Bring and prepare material Clean pump and accessories Store material

Frequency or Units

Time (min)/Unit

1 1 1

60 40 30

minutes/sub-level hours/sub-level

60 40 30 0 0 130 2.17

minutes/blast hours/blast

File: 159332107.xls.ms_office Sheet: Long-Hole Page 3 of 16

Experimental Mine Val-d'Or

7/22/2013 12:19 AM

LONG-HOLE STOPE PRODUCTIVITY CALCULATION


3.0 - DIRECT FIXED ACTIVITIES PER STOPE
RELATED TO MOBILIZATION AND DEMOBILIZATION
Prepare the slide and working areas Bring and lower drill in the sub-level Assemble the drill Install electric services Dismantle and bring out drill from sub-level Remove electric services
Frequency or Units Time (min)/Unit Total Time (min)

Version: April 2, 2004

OTHER ACTIVITIES PER STOPE


Geologists Surveyors Mechanics and electricians Repairs in main access

Frequency or Units

Time (min)/Unit

Total Time (min)

3 3 3 3 3 3

80 60 20 60 60 180

Required number of men

240 180 60 180 180 540 0 0 0 1380 minutes 23.00 hours

1 3 4 0

15 10 20 20

minutes hours

15 30 80 20 0 0 145 2.4

Typical Long-Hole Stope


3rd drilling level or UPPER LEVEL

2nd drilling sub-level Drop raises

1st drilling sub-level

LOWER LEVEL

4.0 - DIRECT VARIABLE ACTIVITIES PER STEP (inside the stope)


4.1 - Floor cleaning
Sub-levels 1 2 3 4 5 6

Cleaning time (hours)


11.63 11.63 11.63 11.63 11.63 11.63 69.75

Productivity (linear meters/hour)

8.0

with

MEN

hours

File: 159332107.xls.ms_office Sheet: Long-Hole Page 4 of 16

Experimental Mine Val-d'Or

7/22/2013 12:19 AM

LONG-HOLE STOPE PRODUCTIVITY CALCULATION


4.2 - Stope parameters 4.2.1 - Drop raise parameters
In sub-level direction Perpendicular to sub-level direction Drilled hole diameter (mm)

Version: April 2, 2004

Include pilot holes which must be reamed. The extra holes required to open the raise to the ore width must be included (if necessary).

ore density (t/m)

2.85

Drilling
Number of drilled meters Production 54 mm 4 4 4 4 4 4 96 96 96 96 96 96 576 Reaming 102 mm 24 24 24 24 24 24 144 Number of blasts /drop raise 2 2 2 2 2 2 12 Production Reaming 102 16 16 16 16 16 16

Blasting
Blasted holes /blast 16 16 16 16 16 16 123 123 123 123 123 123 739 Tonnes

Drop raises
Drilling sub-levels 1 2 3 4 5 6 Actual length 6 6 6 6 6 6 Width 2.4 2.4 2.4 2.4 2.4 2.4 Height 3.0 3.0 3.0 3.0 3.0 3.0 # of drop raises 1 1 1 1 1 1 6

54

4.2.2 - Drilling and blasting parameters of production rows


Length of Drilling sub-levels 1 2 3 4 5 6 sub-levels 93 93 93 93 93 93 Spacing between rows 1.2 1.2 1.2 1.2 1.2 1.2 Number of rows 76 76 76 76 76 76 Average area /row (m2) 18 18 18 18 18 18

The average area must include the planned dilution Number of tonnes /row 62 62 62 62 62 62 369 Number of drilled meters/row 18 18 18 18 18 18 Total number of drilled meters 1368 1368 1368 1368 1368 1368 8208

Adjust the number of rows per blast to obtain a round blast number

Average number of holes/row 3 3 3 3 3 3

Total number of holes 228 228 228 228 228 228 1368

Number of rows/blast 4 4 4 4 4 4

Number of blasts 19 19 19 19 19 19 114

Number of tonnes/blast 246 246 246 246 246 246 1477

Total length to be blasted, including drop raises. However, raises already open must be removed.

Total tonnage from production rows Average tonnage per drilled meter

28071.36 tonnes 3.42 tonnes/meter


Includes drilling of reamed holes See worksheets: Prod_Drilling: production drilling Drop Raise_Drilling: drop raise drilling The time included in this section reduces the available drilling time per shift

4.3 - Drilling
Drilling time (hours)
Sub-levels 1 2 3 4 5 6 # shifts (incl maintenance) drilling hours (incl maintenance) Drop raises 10.79 10.79 10.79 10.79 10.79 10.79 64.72 12 68.32 Long-Hole 98.42 98.42 98.42 98.42 98.42 98.42 590.50 106 622.30

Redrilling time following blast damages (hours)


Drop raises % Hours 10% 1.1 10% 1.1 10% 1.1 10% 1.1 10% 1.1 10% 1.1 10% 6.47 # shifts (incl maintenance) 1 drilling hours (incl maintenance) 6.77 Long-Hole % 1% 1% 1% 1% 1% 1% 1% Hours 1.0 1.0 1.0 1.0 1.0 1.0 5.91 1 6.21

Productivity (meters/hour)
Drop raises 8.9 Long-Hole 13.9

Mechanical maintenance of drill (for each shift)


Grease and lubricants Check bolts of table, slide, etc. Check hydraulic oil level Drill cleaning Other verifications Average maintenance time per shift 8.0 4.0 2.0 2.0 2.0

18.0 min/shift

Includes drilling of reamed holes

Drop raises ->

Average productivity (m/shift) 43.0 67.3

NOTE: The average productivity includes: drilling, daily maintenance, fixed time per shift and contingencies. <- Long-Hole

File: 159332107.xls.ms_office Sheet: Long-Hole Page 5 of 16

Experimental Mine Val-d'Or

7/22/2013 12:19 AM

LONG-HOLE STOPE PRODUCTIVITY CALCULATION


4.4 - Support by anchor cables
Drilling sub-levels Long-Hole 1 2 3 4 5 6 Length of sub-levels 93 93 93 93 93 93 Spacing between rows 2.4 2.4 2.4 2.4 2.4 2.4 Number of rows 38 38 38 38 38 38 0 0 0 0 Number of holes/row 6 6 6 6 6 6 Number of cables Number of drilled /hole meters/row 1 30 1 30 1 30 1 30 1 30 1 30 Total number of drilled meters 1140 1140 1140 1140 1140 1140 0 0 0 0 6840 Total cable length (m) 1140 1140 1140 1140 1140 1140 0 0 0 0 6840 Drilling time (hours) 76.5 76.5 76.5 76.5 76.5 76.5 0.0 0.0 0.0 0.0 459.1

Version: April 2, 2004

Total cable installation time (hours) 30.4 30.4 30.4 30.4 30.4 30.4 0.0 0.0 0.0 0.0 182.4

Anchor cables per drift outside the mineralized zone Total time per hole

Total tonnage from drilling rows (Long-Hole) Meter of cable/Long-Hole tonne

28071 tonnes 0.244 meter of cable/tonne


See worksheet: Cable_Drilling: productivity calculation of anchor cable drilling

Average installation time of anchor cables


a - Insert cables and hoses per hole b - Cement the collar per hole c - Grouting per hole d - Install plate and tensioning per hole Installation time of anchor cables per hole Number of men (installation)

Time (minutes) 3 0 5 0 8 2

Productivity (meters/hour)

14.9

meters/hour

Number of men (drilling) 1 Average productivity (meters/shift) * 76.0 meters/shift * The average productivity includes: drilling, daily maintenance, fixed time per shift and contingencies.

4.5 - Blasting
Long-Hole rows only

4.5.1 - Loading parameters


Sub-levels 1 2 3 4 5 6 Number of holes to be loaded Drop raises Long-Hole 32 228 32 228 32 228 32 228 32 228 32 228 192 1368 Drop raises 96 96 96 96 96 96 576 Number of meters to be loaded Length not loaded/row Long-Hole 3 1140 3 1140 3 1140 3 1140 3 1140 3 1140 6840 Kg of explosives Drop raises Long-Hole 222 2637 222 2637 222 2637 222 2637 222 2637 222 2637 1332 15822 Kg of explosives/blast Drop raises Long-Hole 111 139 111 139 111 139 111 139 111 139 111 139

Loading
Explosive density (g/cc) Hole diameter (mm) Kg of explosives/meter Drop raises 1.01 54 2.31 Long-Hole 1.01 54 2.31

Powder factor (kg/tonne) Number of primers/hole

1.80 1

0.56 1

File: 159332107.xls.ms_office Sheet: Long-Hole Page 6 of 16

Experimental Mine Val-d'Or

7/22/2013 12:19 AM

LONG-HOLE STOPE PRODUCTIVITY CALCULATION


4.5.2 - Loading time
Drop raises (hours)
Sub-levels 1 2 3 4 5 6 Fixed 3.39 3.39 3.39 3.39 3.39 3.39 20.36 Variable 1.60 1.60 1.60 1.60 1.60 1.60 TOTAL 5.00 5.00 5.00 5.00 5.00 5.00 29.98 Fixed 19.00 19.00 19.00 19.00 19.00 19.00

Version: April 2, 2004

Long-Hole (hours)
Variable 16.41 16.41 16.41 16.41 16.41 16.41 TOTAL 35.41 35.41 35.41 35.41 35.41 35.41 212.45

Average fixed time for loading


a - Cleaning/hole b - Bottom hole blocking/hole c - Single priming/hole d - Collar verification/hole e - Connecting time/row

Time (minutes) Drop Raises 4 2 3 2 4 Long-Hole 3 2 2 1 3

Enter the reference number of men for the transportation and loading of explosives
Drop raises Loading productivity (kg/hour) 200 Long-Hole 250 # of men 2 2

NOTE: - fixed time:

includes a,b,c,d,e

- varable time: includes transportation and loading of explosives

LONG-HOLE DROP RAISES

NUMBER OF ROWS/SHIFT TONNES/SHIFT NUMBER OF BLASTS/SHIFT METERS ADVANCED/SHIFT

4.7 289 1.03 3.1

rows/shift tonnes/shift blasts/shift meters/shift

Transportation of explosives to the loading area (kg/hour)

450

File: 159332107.xls.ms_office Sheet: Long-Hole Page 7 of 16

Experimental Mine Val-d'Or

7/22/2013 12:19 AM

LONG-HOLE STOPE PRODUCTIVITY CALCULATION


5.0 - STOPE COMPILATION
5.1 - TABLE OF REQUIRED HOURS PER ACTIVITY
5.1.1 - DIRECT FIXED ACTIVITIES
(inside the stope)

Version: April 2, 2004

FLOOR CLEANING ref. section 2.0

MOBILIZATION AND DEMOBILIZATION ref. section 3.0 DRILLING

DROP RAISES
REDRILLING BLASTING ref. section 2.0 DRILLING

LONG-HOLE
REDRILLING BLASTING ref. section 2.0 CABLES ref. section 2.0 OTHERS ref. section 3.0

DIRECT FIXED Number of times

(hours)

1.00 6 6.00

23.00 1 23.00

2.48 12 29.76

2.48 114 282.72

2.17 6 13.02

2.42 1 2.42
TOTAL Scheduled hours

356.92

5.1.2 - DIRECT VARIABLE ACTIVITIES


(inside the stope)

FLOOR CLEANING ref. section 4.1

MOBILIZATION AND DEMOBILIZATION ref. section 3.0 DRILLING ref. section 4.3

DROP RAISES
REDRILLING ref. section 4.3 BLASTING ref. section 4.5.2 DRILLING ref. section 4.3

LONG-HOLE
REDRILLING ref. section 4.3 BLASTING ref. section 4.5.2 CABLES ref. section 4.4 OTHERS

DIRECT VARIABLE

(hours)

REFERENCE NUMBER OF MEN

69.75 2

68.32 2

6.77

One man by default One man per drill

29.98 2 men (loading) 2 men (transp.)

622.30

6.21

One man by default One man per drill

212.45 2 men (loading) 2 men (transp.)

641.5 1 man (drilling) 2 men (install.)

One man
TOTAL Scheduled hours

1657.27
Loading Loading Drilling

PLANNED NUMBER OF MEN

1
One man per drill

2
Transportation

1
One man per drill

2
Transportation

1
Installation

ONLY DIRECT VARIABLE ACTIVITIES ARE INFLUENCED BY THE NUMBER OF MEN. THEREFORE, ACCORDING TO THE NUMBER OF MEN ENTERED, WE OBTAIN:

Loading 27.02 Transportation 2.96

Loading 177.29 Transportation 35.16

Drilling 459.10 Installation 182.40

DIRECT VARIABLE

(hours) *

69.75

68.32

6.77

29.98

622.30

6.2

212.45

641.50

TOTAL Scheduled hours

* The planned number of men can be different from the one entered in each section. If the number is different, the time required for variable activities will be corrected in proportion to the number of men.

1657.28

File: 159332107.xls.ms_office Sheet: Long-Hole Page 8 of 16

Experimental Mine Val-d'Or

7/22/2013 12:19 AM

LONG-HOLE STOPE PRODUCTIVITY CALCULATION

Version: April 2, 2004

5.2 - STOPE PRODUCTIVITY CALCULATION

FLOOR

MOBILIZATION AND DEMOBILIZATION 23.00 + DRILLING + 68.32

DROP RAISES
REDRILLING + 6.77 BLASTING 29.76 hr (2 men) + Loading 27.02hr (2 men) Transportation 2.96 hr (2 men) DRILLING + 622.30

LONG-HOLE
REDRILLING + 6.21 BLASTING CABLES 282.72 hr (2 men) 13.02 hr (2 men) + + Loading Drilling 177.29 hr (2 men) 459.1 hr (1 man) Transportation Installation 35.16 hr (2 men) 182.4 hr (2 men) OTHERS 2.42 +

Hours of fixed activities Hours of variable activities

CLEANING 6.00 + 69.75

= TOTAL * PLANNED NUMBER OF MEN = 2 75.75

= 23.00 * 2 =

= 68.32 * 1 =

= 6.77 * 1 =

= 622.30 * 1 =

= 6.21 * 1 =

= 2.42 * 1 =

TOTAL MANHOURS REQUIRED

151.5

46.0

68.3

6.8

119.5

622.3

6.2

990.3

849.9
Total manhours

2.4 2863.28
+

Number of hours per shift (schedule)

8 hours with a contingency of


15.0% ============>

manshift contingency
=

429.49 3292.77
+

required manhours inside the stope required manhours from direct fixed activities (outside the stope) MANHOURS
INSIDE THE STOPE PRODUCTIVE CONTINGENCY TOTAL (STOPE) OUTSIDE STOPE TOTAL FIXED

1194.82
=

total (manhours)

4487.59

TOTAL (manshifts)
4487.6
100%

560.95

2863.3
64%

429.5
10%

3292.8
73%

1194.8
27%

TONNES PRODUCTIVITY

28810

51.4

tonnes/manshift

File: 159332107.xls.ms_office Sheet: Long-Hole Page 9 of 16

Experimental Mine Val-d'Or

7/22/2013 12:19 AM

LONG-HOLE STOPE PRODUCTIVITY CALCULATION


6.0 - STOPE STATISTICS
Drilled meters
54 mm 102 mm 144 Powder Factor

Version: April 2, 2004

Tonnes
739 28,071

T/drilled m
1.026 3.42

Explosives (kg)
1,332 15,822

(kg/tonne) 1.80 0.56

DROP RAISES LONG-HOLE CABLES

576 8208 6840

Meters
6840

# of holes
1368

TOTAL

15624

144

28,810

1.83

17,154

0.60

6.1 - STOPE PLANNING FACTORS


Required number of shifts (including contingencies and fixed time per shift)
Mobilization and Demobilization 4.5 DROP RAISES DRILLING 13.4 REDRILLING 1.3 BLASTING 11.7 DRILLING 121.9 LONG-HOLE REDRILLING 1.2 BLASTING 97.0 CABLES DRILLING 89.9 INSTALL. 36.2 OTHERS 0.5 392.5 shifts

Floor cleaning 14.8 with 2 men

with 2 men

with 1 man

with 1 man

with 2 men

with 1 man

with 1 man

with 2 men

with 1 man

with 2 men

with 1 man

Productivity
Floor cleaning 18.8 meters/ms Mobilization & Demobilization 9 manshifts/sub Installation of cables 94.6 meters/ms

Drilling (m/shift) DROP RAISES LONG-HOLE CABLES 43.0 67.3 76.0


per drill

Loading 63.1 tonnes/shift 289.4 tonnes/shift


3.1 meters/shift 4.7 rows/shift

File: 159332107.xls.ms_office Sheet: Long-Hole Page 10 of 16

Experimental Mine Val-d'Or

7/22/2013 12:19 AM

LONG-HOLE

PRODUCTIVITY CALCULATION OF PRODUCTION DRILLING


1.0 - Calculation of the average drilling time per rod
minutes
Insert the rod Drilling time/rod Change of rod Hole cleaning/rod Loosen the rod Store the rod 0.4 1.5 0.4 0.5 1.4 0.7

Version: April 2, 2004

3.0 - Hole breakthrough


Adjust the time in relation to the penetration rate and the length of the rod min
Drill through screen Fractured ground 0.5 0.4

0.9 min/ breakthrough

4.0 - Pivoting the drill on the same rotation point


average drilling time per rod
4.9 min/rod Loosen the slide and adjust the dip Tighten the slide and check the dip

min
0.7 0.8

length of the rod (m) average time per drilled meter

1.2 4.1 min/drilled m

pivoting average time

1.5 min

5.0 - Moving the drill on the same row without changing the position of the drill rig (setup) min 2.0 - Casing
min
Insert the rod with steel bit for casing Drilling Insert casing Remove the rod with steel bit for casing 0.4 1.5 2.0 0.8 Moving the drill to the other rotation point Check position of the drill 1.0 0.5

average time to move drill on the same row (not the rig)

1.5 min

6.0 - Moving the drill rig from one row to another or on the same row min
Put drill rig in moving mode Moving the drill rig Align drill rig on reference points Put drill rig in drilling mode Check alignment of drill rig Adjust table inclination (dip of the row) 0.6 1.5 1.5 1.0 1.0 0.5

minutes/casing

4.7

average time to move drill rig

6.1 min

File: 159332107.xls.ms_office Sheet: Prod_Drilling Page 11 of 16

Experimental Mine Val-d'Or

7/22/2013 12:19 AM

LONG-HOLE

PRODUCTIVITY CALCULATION OF PRODUCTION DRILLING


7.0 - Typical row
Length of rods (m) Hole diameter (mm) Breakthrough yes=1, no=0
15 15 15 1 1 1

Version: April 2, 2004

1.2 54 mm Drilling time (min) Displacements (min) Breakthrough Casing Positioning


0.9 0.9 0.9 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.5 1.5 1.5 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Hole #
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

Length

Setup
1 1 1

Casing

Number of rods
12.7 12.7 12.7 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

Drilling

62.1 62.1 62.1 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

45

186.2

2.7

0.0

4.5

Setup 1.5

Row 6.1

Number of drill rig displacements on the same row 0 Enter the required number of displacements of the drill rig on the same row. The displacement time between rows is already included in the calculations. Average productivity

Total drilling time per row 201.0 minutes 3.35 hours 13.5 meters/hour 44.3 feet/hour

File: 159332107.xls.ms_office Sheet: Prod_Drilling Page 12 of 16

Experimental Mine Val-d'Or

7/22/2013 12:19 AM

LONG-HOLE

PRODUCTIVITY CALCULATION OF DROP RAISE DRILLING


1.0 - Calculation of the average drilling time per rod
Insert the rod Drilling time/rod Change of rod Hole cleaning/rod Loosen the rod Store the rod DIAMETER (mm) Production Reaming 54 102 0.4 0.4 1.5 2.4 0.4 0.8 0.5 0.5 1.4 2.0 0.7 0.8

Version: April 2, 2004 3.0 - Hole breakthrough


min Adjust the time in relation to the penetration rate and the length of the rod
Drill through screen Fractured ground 0.5 0.4

0.9 min/ breakthrough

4.0 - Pivoting the drill on the same rotation point


min average drilling time per rod length of the rod (m) average time per drilled meter 54 mm 102 mm 1.2 pivoting average time 4.1 minutes/drilled meter 5.8 minutes/drilled meter 1.5 min 4.9 6.9 min/rod
Loosen the slide and adjust the dip Tighten the slide and check the dip 0.7 0.8

5.0 - Moving the drill on the same row without changing the position of the drill rig (setup) min 2.0 - Casing
min
Insert the rod with steel bit for casing Drilling Insert casing Remove the rod with steel bit for casing 0.4 1.5 2.0 0.8 Moving the drill to the other rotation point Check position of the drill 1.0 1.5

average time to move drill on the same row (not the rig)

2.5 min

6.0 - Moving the drill rig from one row to another or on the same row
Put drill rig in moving mode Moving the drill rig Align drill rig on reference points Put drill rig in drilling mode Check alignment of drill rig Adjust table inclination (dip of the row)

min
1.0 2.0 2.0 1.0 1.0 2.0

minutes/casing

4.7

average time to move drill rig

9.0 min

7.0 - Typical drop raise drilling


Length of rods (m) Length of holes (m) Breakthrough yes=1, no=0
1 1

1.2 6 # setups /row Number of rows


5 2 7

# holes
16 4

Diam (mm)
54 102

Length
96 24 120

Casing yes=1, no=0


0 0

Number of rods
82.7 20.7

Drilling

Drilling time (min) Breakthrough Casing


14.4 3.6 0.0 0.0

Displacements (min) Positioning


4.5 3.0 Setups

3 2 5

405.1 142.6

547.7

18.0

0.0

7.5

12.5

Rows 90.0

Only big diameter hole drilling. If pilot holes are required before drilling the big diameter, these will have to be added to the first line.

Total drilling time per drop raise minutes 675.7 hours 11.26

Total number of additional displacements of the drill rig 3

Enter the total number of additional displacements of the drill rig on all the rows. The displacement time between rows is already included in the calculations.

Average productivity

10.7 meters/hour

35.1 feet/hour

File: 159332107.xls.ms_office Sheet: Drop Raise_Drilling Page 13 of 16

Experimental Mine Val-d'Or

7/22/2013 12:19 AM

LONG-HOLE

PRODUCTIVITY CALCULATION OF ANCHOR CABLE DRILLING


1.0 - Calculation of the average drilling time per rod
min
Insert the rod Drilling time/rod Change of rod Hole cleaning/rod Loosen the rod Store the rod

Version: April 2, 2004

3.0 - Hole breakthrough


Adjust the time in relation to the 0.4 1.5 penetration rate and the length 0.4 of the rod
0.5 1.4 0.7

min
Drill through screen Fractured ground 0.4

0.4 min/ breakthrough

4.0 - Pivoting the drill on the same rotation point


average drilling time per rod
4.9 min/rod Loosen the slide and adjust the dip Tighten the slide and check the dip

min
0.7 0.5

length of the rod (m) average time per drilled meter

1.2 4.1 min/drilled m

pivoting average time

1.2 min

5.0 - Moving the drill on the same row without changing the position of the drill rig (setup) 2.0 - Casing
min
Insert the rod with steel bit for casing Drilling Insert casing Remove the rod with steel bit for casing 0.4 1.5 2.0 0.8 Moving the drill to the other rotation point Check position of the drill

min
0.0 0.0

average time to move drill on the same row (not the rig)

0.0 min

6.0 - Moving the drill rig from one row to another or on the same row
Put drill rig in moving mode Moving the drill rig Align drill rig on reference points Put drill rig in drilling mode Check alignment of drill rig Adjust table inclination (dip of the row)

min
1.0 2.0 2.0 1.0 1.0 1.0

minutes/casing

4.7

average time to move drill rig

8.0 min

File: 159332107.xls.ms_office Sheet: Cable_Drilling Page 14 of 16

Experimental Mine Val-d'Or

7/22/2013 12:19 AM

LONG-HOLE

PRODUCTIVITY CALCULATION OF ANCHOR CABLE DRILLING


7.0 - Typical row
Length of rods (m) Hole diameter (mm) Breakthrough yes=1, no=0
5 5 5 5 5 5 0 0 0 0 0 0

Version: April 2, 2004

1.2 54 mm Drilling time (min) Displacements (min) Breakthrough Casing Positioning


0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.2 1.2 1.2 1.2 1.2 1.2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Hole #
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

Length

Setup
1 1 1 2 2 2

Casing

Number of rods
4.3 4.3 4.3 4.3 4.3 4.3 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

Drilling

21.2 21.2 21.2 21.2 21.2 21.2 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

Setup 0

30

127.4

0.0

0.0

7.2

Row 8.0

Number of drill rig displacements on the same row 0 Average productivity Enter the required number of displacements of the drill rig on the same row. The displacement time between rows is already included in the calculations.

Total drilling time per row 142.6 minutes 2.38 hours 12.7 meters/hour 41.7 feet/hour

File: 159332107.xls.ms_office Sheet: Cable_Drilling Page 15 of 16

Experimental Mine Val-d'Or

7/22/2013 12:19 AM

Typical Long-Hole Stope


3rd drilling level or UPPER LEVEL

2nd drilling sub-level Drop raises 1st drilling sub-level

LOWER LEVEL

File: 159332107.xls.ms_office Sheet: Drawing Page 16 of 16