PMP Exam SelfAssessment Test

75 Free Sample Questions

Sponsors:

"If money is your hope for independence you will never have it. The only real security that a man will have in this world is a reserve of knowledge, experience, and ability. Henry Ford, Entrepreneur Explanations (skip) The free preparation test below covers the current PMP exam version (per 31 August 2011).
Feedback (since 2003)
Mailed May 11, 2013 by Vijay K.R. (India):

FREE Download for learning and instruction. Insight tree supports project selection and helps you become a decision tree expert.

"Dear Oliver, [...] I have passed my PMP Each question in this self exam yesterday (10assessment test has one best May). I would like to answer. thank you for your advice and those Time to finish the test: 90 valuable contents on Minutes. your website - it has There is a timer in the title bar been a great help during my preparation. (top of most browsers). You are great in this PM community and Click the dark blue button have been doing a (below) to reset the timer to wonderful job. Wish 00:00:00. you more success in coming days. Click here for links to 3,000+ more PMP prep questions from Best Regards." Mailed May 3, 2013 by Stuart B. various providers (4,000+ for (Australia, via LinkedIn): PMI members). "Oliver, I passed the PMP Life training classes: Exam in Sydney today www.oliverlehmann.com/semin and I used the practice ar-dates.html exams from your website (the CAPM PMI has not participated in one included) as part of the development of this self my preparation. assessment test and has not I just wanted to say reviewed the content. that I thought the material was very well written and realistic of how the actual exam was structured and I

certainly believe it helped me cross the line. Many thanks."


Mailed April 9, 2013 by Adhik K. (USA, via LinkedIn):

"Hello Oliver, Yesterday I achieved my target of getting my PMP in first attempt. Just wanted thank you for all your free questions that helped me preparing better for my goal. Thanks & Regards."
Mailed January 23, 2013 by Ramesh Ch. (India):

"Respected Oliver Sir, I'm glad to announce that I achieved the most coveted PMP credential on 21st Jan 2013. I'm even more glad and thankful to your free resources in www.oliverlehmann.co m which had enriched my PM knowledge and bridged the gaps in infinite number of ways."
Mailed July 24, 2012 by Christina W. (Canada):

"Hello Oliver; Thanks for your links to the many practice tests. I took the PMP exam on July 19th and did well. Best Regards, Christina"
Mailed July 09, 2012 by ChandraShekhar B. (India):

"This test is very helpful in evaluating weak areas."


Mailed January 26 2012 by Sandie Q. (USA):

"Hi there Oliver - your PMP sample exam is

really great; it's given me a good sense of the remaining work I need to do. Vielen Dank und Grusse aus Washington DC."
Mailed November 04 2011 by Satish S. C. (India, via Google+):

"Hi Oliver I've cleared the PMP in first attempt Thanks for all your valuable guidance and help. Really much appreciated. "
Mailed October 27 2011 by Daniel C. (Australia, via LinkedIn):

"Oliver, on a side note I wish to say thank you for all the work you have put into to PMP training. I think it is safe to say that without your 175 free questions and the iPAD app that is also based on your questions I would not have passed the PMP exam as easily as I did. You really made a difference for me and I appreciate it. The most difficult part for me was getting into the PMP mindset and looking at everything from their way of thinking, not the actual contents of the exam. The way you phrased the questions and explained the answers helped me achieve the appropriate mindset. "
Mailed October 27 2011 by Harald G. (Switzerland, via LinkedIn):

"I just wanted to briefly let you know that I found your

website with the sample PMP exam to be excellent and it was a crucial part in my preparation. Thanks very much for putting it together and for having made it available to everybody!"
Mailed September 07 2011 by David W. (UAE):

"I tried your questions a couple of times, particularly to get my head round the style of Qs & As. I found them extremely useful. [...] Many thanks once again. I passed the PMP exam 2 weeks ago."
Mailed July 05 2011 by Leland R. (USA):

"I have taken your battery of test as part of PMP Exam Prep. It gave me the confidence I needed."
Mailed June 21 2011 by Sandeep T. (India):

"Thank you for your excellent question. It really gave me clear understanding about my sweet spot and weak areas."
Mailed April 02 2011 by Claudia S. (Switzerland):

"What helped me to prepare myself was to take a couple of test exams to get a feeling for the questions and specially for the time needed. The test exam provided by Oliver was the one that was nearest to the real test specially regarding timing."

Mailed May 03 2010 by Sandra J. (USA):

"I recently passed the PMP and found your site the single most helpful tool, after the PMBOK itself."
Mailed April 08 2010 by Sandy C. (USA):

"I'm proud to say that I passed the exam this week, thanks very much to your help."
Mailed September 15 2009 by Stephen H. (Canada):

"The test was very helpful, and highlighted areas where I needed further studies thank you."
Mailed June 27 2009 by Bill C. (USA):

"I passed the PMP exam yesterday."


Mailed April 08 2009 by Mary K. Y. (USA):

This was great practice. It highlighted some areas on which I need to focus."
" Mailed August 25 2008 by Aarti S. (USA):

"Your tips and practice exams were really helpful and I was able to focus on areas that I was weak at and pass the exam."
Mailed October 10 2007 by Naji C. (Canada):

"I am glad that I did your tests online, the free 75q and the 175 one. The questions helped me pass the exam and really find gaps in my knowledge. By the way, you are the only one who covered the PTA questions. I had on my exam 3 PTA related questions."
Mailed October 10 2007 by Stefano B.

(Italy):

"I would like to thank you again for the free and precious support provided by your tests. They were really close to the exam and helped much me and my other 2 colleagues to pass the PMP exam with a good score." Mailed July 14 2007 by Belinda C. (USA): "I did take the exam and passed it back in May. I believe that your questions were the closest to prep for the exam." Mailed March 8 2007 by Pam H. (USA): "I only whish I could have found you earlier. I missed this exam 3 times. I even went through #######'s Boot Camp... a good course but something went amiss for me when I really saw the questions on the test ... I have not been studying these type of questions given to me from the Boot Camp." Mailed January 8 2007 by Joseph K. (UK): "I did the test and had 54 correct answers. I then passed the exam. Your questions were a good preparation for the real thing. " Mailed September 12 2006 by Claudia D. (USA): "I just took (and passed) the PMP exam yesterday. Your test is

the closest I have found to the real thing. I was getting fairly high scores from other practice tests and was quite shocked yesterday by how difficult the real exam was." Mailed May 9 2006 by Rick M. (USA): "I teach an 8 day PMP Prep Course. I have had over 120 of my students pass the PMP exam over the past 2 years. I have always encouraged my students to take your exam to test their knowledge."
Mailed April 20 2006 by Walid T. (Canada):

"I found some of the questions quite challenging and requiring more than the allocated 72 seconds to answer ... the sample test provided a good learning experience." Mailed January 25 2006 by John C. (USA): "Your test questions are very useful and helped me assessing where I need to do more." Mailed August 1 2005 by Stephen L. (New Zealand): "Good questions."
Mailed June 14 2005 by Saurabh V. (India):

"The test is the most comprehensive one that I have seen so far." Mailed August 26 2004

by David S. (UK): "I can start breathing again, score for the exam 158/200, thanks for the confidence boost from your test questions!" Mailed June 29 2004 by Nadja V. (Finland): "I took several practice exams. Your exam provided the best reality check both in terms of level of difficulty of the actual PMP exam and my score on the final exam. Thanks." Mailed Jan 12 2004 by Andrea I. (Italy): "I did the test two days before the exam and found it useful and also a good approximation of the real exam question, compared with other sample tests taken before. Moreover, the result reached was exactly the same as in the exam (84%)."
Mailed May 05 2003 by Dana P.B. (USA): "I did find the questions helpful. To the extent that I passed the exam on my first attempt."

inShare See references

Marked for review

1. ________ is typically not referred to as a buffer type in critical chain project management. Resource buffer Free buffer Feeding buffer Project buffer

See references

Marked for review

2. A company has to make a choice between two projects, because the available resources in money and kind are not sufficient to run both at the same time. Each project would take 9 months and would cost $250,000. 1. The first project is a process optimization which would result in a cost reduction of $120,000 per year. This benefit would be achieved immediately after the end of the project. 2. The second project would be the development of a new product which could produce the following net profits after the end of the project: 1. year: 2. year: 3. year: $ 15,000 $ 125,000 $ 220,000

Assumed is a discount rate of 5% per year. Looking at the present values of the benefits of these projects in the first 3 years, what is true? Both projects are equally attractive. The first project is more attractive by app. 7%. The second project is more attractive by app. 5%. The first project is more attractive by app. 3%. See references

Marked for review

3. A production process has been defined as part of an industrial equipment manufacturing project. The process is intended to produce steel bolts with a length of 20 cm. The control limits are 19.955cm and 20.045cm. The measurements made at the end of the process yielded the following results: 20.033cm, 19.982cm, 19,995cm, 20.006cm, 19.970cm, 19.968cm, 19.963cm, 19.958cm, 19.962cm, 19.979cm, 19.959cm. What should be done? The process is under control. It should not be adjusted. A special cause should be investigated, the process should be adjusted. The control limits should be adjusted. The measuring equipment should be recalibrated.

See references

Marked for review

4. Your project management team includes two external consultants each from a different company. You found that repeated conflicts between the two consultants already slow down project progress and jeopardize achievement of objectives.Which stage of team development can be difficult to overcome in such a situation? Storming from Forming, Storming, Norming, Performing Panic from Enthusiasm, Panic, Hope, Solution Kickoff from Assignment, Kickoff, Training, Communicating Frustration from Direction, Frustration, Cooperation, Collaboration See references

Marked for review

5. During a project, earned value analysis is performed, resulting in the following numbers: EV: 523,000; PV: 623,000; AC: 643,000. Which results are correct? CV: +120,000; SV: +100,000 CV: +100,000; SV: +120,000 CV: -100,000; SV: -120,000 CV: -120,000; SV: -100,000 See references

Marked for review

6. A project manager spent some days to create a multi-page document, which he called project charter. The document should have been issued by the project sponsor. The sponsor found the document outsized and asked for a condensed document. Which of the following is usually not an element of the project charter? The authority level of the project manager Detailed control account and work package descriptions The business need that the project was undertaken to address High-level risks See references

Marked for review

7. A document called ____________ is created by decomposing the project scope into smaller, more manageable elements. Scope Statement Network Logic Diagram Work Breakdown Structure Requested Change See references 8. Which of the following tools is used to create a risk management plan? Risk planning meetings Documentation reviews Data precision rankings Diagramming techniques See references

Marked for review

Marked for review

9. In order to speed up a project, you made a decision to fast-track a phase currently performed with five team members, and another one which was planned to begin in four weeks time with another five team members. Which of the following activities should you do first? Make sure that all exit criteria of the consecutive phase have been met to ensure the flow of communications in a team situation which is more complex by a factor of 2. Make sure that all entry criteria of the previous phase have been met by planning and performing a phase gate meeting to assess technical aptness. Make sure that all exit criteria of the previous phase have been met by planning and performing a phase gate meeting to assess technical performance. Restructure your team and delegate tasks in order to ensure the flow of communications in a team with the number of communication channels increased by a factor of 4.5. See references

Marked for review

10. A project manager has been asked to support an internal project request by developing a business case. What kind of information is the person expected to provide in the document? The detailed information from a business standpoint to determine whether bidding for the customer project will be successful.

The detailed information from a project management standpoint to determine whether the project will be successful. The detailed information from a technical standpoint to determine whether the project will be successful. The necessary information from a business standpoint to determine whether the project is worth the investment. See references

Marked for review

11. You found the following earned value analysis information for a project that was recently closed-out:SPI = 0.7, CPI = 1.0 The project has been cancelled while it was executed. At that time the project was behind schedule and on budget. The project's deliverables have all been finished. The project came in behind schedule but on budget. The project's deliverables have all been finished. The project came in ahead of schedule but on budget. The project's deliverables have all been finished. The project came in on schedule but over budget. See references 12. Which should be included in a requirements management plan? The document should trace requirements to project scope / WBS deliverables. It should describe how requirements activities will be planned, tracked, and reported. It should trace high-level requirements to more detailed requirements. It should trace requirements to business needs, opportunities, goals, and objectives. See references 13. In a traditionally drawn decision tree, a circle represents ___________. a chance to which no expected monetary value can be assigned so that a likely pay-off can not be shown. a decision to which no expected monetary value can be assigned so that a likely pay-off can not be shown. a chance to which an expected monetary value may be assigned to calculate the most likely pay-off. a decision to which an expected monetary value may be assigned to calculate the most likely pay-off.

Marked for review

Marked for review

See references

Marked for review

14. A project management team has subcontracted work to a service company. Which of the following tools is the best choice to assure that this company will be able to meet the quality requirements of the project? Quality audit Deliverable inspection Fixed price contract Service level agreement See references

Marked for review

15. With your team you are using judgment from subject matter experts to identify and analyze project risks. There is a small number of experts available, but some of them have long been in a teacher-student or manager-assistant relationship. Which of the following techniques can ensure best that there is no dominating opinion during an expert review? Peer review SWOT analysis Delphi technique Monetary value calculation See references

Marked for review

16. You are running a project for a customer based on a cost-reimbursable contract with the following terms: Target costs: $ 1,000,000 Fixed fee: $ 100,000 Benefit/cost sharing: 80% / 20% Price ceiling: $ 1,200,000 Which is the PTA (= point of total assumption, break point) of the project? $1,300,000 $1,500,000 $80,000 $1,125,000

See references

Marked for review

17. During execution of a project which is performed for a customer on a T&M (time and material) contract base, a new project manager is taking over the assignment. He discovers that two members assigned to the project have charged time without performing any work for the project customer. Upon further investigation, he determines that this occurred because there have been no other project assignments open for these employees. The customer is unaware of these facts. What should the project manager do? Try to find some productive work for these staff members in the project and leave them on the team. The best thing is to do nothing. The customer will not realize the problem anyway. Try to find a responsible person for the over-assignment who can be made accountable. Take the two people off the team immediately and arrange for the refund of the excess charges to the customer. See references

Marked for review

18. Start dates in the following network logic diagram are defined as early morning, finish dates are evening. If tasks are scheduled to begin at early start date, what is true?

Activity B has a free float of 10 d. Activity B has a total float of 10 d. Activity A has a free float of 10 d. Activity A has a total float of 10 d.

See

Marked for review

references 19. Your project is executed with a globally spread virtual team. The project progress has been found to be too slow. Which measure is most likely to immediately speed up the project? Technical training for all team members Daily phone conferences and detailed reporting A team meeting at a location convenient to all team members Collocation of team members at a suitable place See references

Marked for review

20. A project management team wants to procure some customized products which are available in identical grade and quality from many vendors. What should be included in the procurement package to ensure that their offers will be comparable? A statement of work describing the needs of the project in sufficient detail to enable vendors to make suitable proposals A statement of work specifying attributes and metrics of the requested deliverables in detail to allow vendors submission of bids The approved project scope statement, the WBS which should be broken down to work package level and the WBS dictionary The risk management plan and the reports from those risk management reviews which have been made so far See references

Marked for review

21. Which of the following becomes increasingly important in a virtual team environment? Requirements engineering Communication planning Formal procurements closure Network diagramming See references

Marked for review

22. You are assigned as the project manager to a project which is executed for a customer under FP contract. Your customer informed you this morning that they insist on certain "refinements" of the project scope. You agree that the requested actions make really sense to the project, but believe that they constitute a major change increasing the project scope. What should you do next?

Accept the request of the customer. Diligently document the additional costs and working hours spent by yourself and the team on the implementation of the change and invoice these to the customer at appropriate rates. Perform earned value analysis to assess the current status of the project and get all the numbers you need to communicate the case to the change control board which then will have to make the best decision regarding the customer request. Check the contract, the project charter, the scope statement and other documents related to the project and the contract. Implement ADR (alternative dispute resolution) procedures if the conflict cannot be resolved otherwise. Talk to the project sales department and find a joint solution with them how to best reject the request considering the commercial and strategic value of the customer to the organization you are working for. See references

Marked for review

23. A prime contractor in a customer project under CPFF contract has run into unexpected technical problems. Fixing them will require a lot of additional work to be done. The company made a decision to book more staff and equipment from their subcontractors in order to adhere to the agreed timeline. The customer agreed to this decision. What will most likely happen? The contractors indirect costs will increase and the customers payment for them will increase, too. The contractors indirect costs will increase, but the customers payment for them will not increase. The contractors indirect costs will not increase, but the customers payment for them will. Both the contractor's indirect costs and the customers payment for them will not increase. See references

Marked for review

24. A project management team is evaluating the causes that might contribute to unsatisfactory performance and quality. Which of the following statements is not true? Normal process variation is attributable to random causes and sometimes also called "white noise". Special causes are easier to predict and handle than random causes (also called common causes). Special causes are unusual events which are difficult to foresee and often produce outliers. A process can be optimized to limit the bandwidth of variations due to random causes. See references

Marked for review

25. You are performing a project management audit in your company and find that most of the project plans are neither consistent nor up-to-date. Which of the following statements is not true? Projects should never be executed without a valid, updated and working project management plan. The consistency of the project management plan is secondary because it is only the results that matter. A great deal of effort is required to develop and update a project plan, but the benefits include less pressure on all stakeholders and a resulting product that will satisfy the requirements. Poor planning and insufficient updating of project management plans are common reasons for cost and time overruns. See references 26. You want to perform active risk acceptance. What should you do? Create contingency reserves in resources, money and time. Develop a plan to minimize impact in case that an identified risk occurs. Develop a plan to minimize the probability of occurrence for identified risks. Make additional resources available to speed up the project. See references

Marked for review

Marked for review

27. A project manager made 3-point estimates on a critical path and found the following results:

Assuming 3 sigma precision level for each estimate, what is the standard deviation of the allover path? App. 4.2 days App. 5.2 days App. 6.2 days

You can not derive the path standard deviation from the information given. See references 28. When do bidder conferences normally take place? After the contract has been awarded to keep alternatives open. After submission of bid or proposal, but before contract award. Prior to the submission of a bid or proposal by the bidder. After technical meetings with bidders to discuss contract requirements. See references 29. What is defined by control limits? A measuring instrument solely used to describe process capability. The process is found capable if the 3 sigma range is exceeded by not more than 0.3% of a tested sample lot. The limits of the six sigma area on either side of a control chart to plot measured values; data found outside the area are out of specification and can lead to rejection of an entire batch. The area consisting of typically three standard deviations on either side of a mean value of a control chart to plot measured values found in statistical quality control The area consisting of typically three standard deviations on either side of a mean value of a control chart to plot measured values found in quality assurance See references 30. The scope baseline consists of what? Scope statement, WBS, and WBS dictionary Cost baseline, quality baseline and schedule baseline Configuration management plan and configuration identification document Procurement statement of work and project scope statement See references

Marked for review

Marked for review

Marked for review

Marked for review

31. Activity 1 has a duration of 20 days, activity 2 of 10 days, activity 3 of 5 days and activity 4 of 6 days.

What is the minimum total duration between the milestones A and B? 36 days 37 days 39 days 42 days See references

Marked for review

32. Which tool and technique is used in the processes Create WBS and Define activities? Nominal group technique Human resource assignment Brainstorming Decomposition See references 33. Which of the following statement(s) on whistleblowing is/are not true? a. It is a term used to define an employees decision to disclose information on unethical, immoral or illegal actions at work to an authority figure. b. An employee should always discuss the matter with people external to the company before following the "chain of command" and discuss it with the immediate superior. c. The consequences of whistleblowing are often extreme and might include being branded as an owner of bad judgment, layoff, civil action and imprisonment. d. Carefully performed whistleblowing can lead to the end of unethical business practices. a b

Marked for review

b, c c, d See references 34. Which of the following statements is not true? Attribute sampling is the process of assessing whether results conform to specifications or not. Prevention means keeping errors out of the process by applying actions before the process starts changing its input. Variables sampling means that the result is classified into one of the 3 categories:"acceptable" - "acceptable after rework" - "rejected". Inspection is often mainly done to keep errors out of the hands of the customer instead of as a means of process control. See references

Marked for review

Marked for review

35. Which statement describes best why you should document assumptions? Assumptions might prove to be wrong. Knowing which assumptions were incorrect allows baseline adjustments in case of project crisis. Assumption analysis is a valuable tool and technique to explore the validity of assumptions during risk identification. Assumptions limit the project management team's options for decision making because they can not be controlled by the team. In case of schedule or budget overruns, the documentation of assumptions supports a clear assignment of responsibility. See references 36. Which is normally not regarded as an element of cost of quality? Prevention costs Maintenance cost Appraisal costs Failure costs See references

Marked for review

Marked for review

37. You have recently been assigned as a project manager to a new B-O-T (build, operate,

transfer) capital project. Reviewing the initial documentation you found out that it has been calculated with a very small margin during operations of its product for the shareholders. What should you do? As you are not responsible for lifecycle costing, you don't have to worry about operation profits. Focus on project costs from initiation through handover. Ensure maximum profits by buying the best and cheapest items, components and modulespotentially from a big number of different suppliersand integrating them. Create a realistic plan broken down to a sufficient level of detail. Perform all risk management processes. Ensure real-time communications with all stakeholders. Try to get a second project manager assigned to share decision making and accountability to shareholders with the person. See references

Marked for review

38. A project is handled by departments of an organization and expedited by a project coordinator. Which of the following statements is most likely to be true? The performing organization is a weak matrix. The performing organization is doing "management by projects". The performing organization is a strong matrix. The performing organization is projectized. See references

Marked for review

39. You are project manager in a global project with a team consisting of people from various countries. What can you try to prevent misunderstandings due to cross-cultural differences? Use all communication methods available that are suitable for the team and follow up in writing when communicating verbally. Remember that cultural and individual diversity may help project teams solving unforeseen problems during the course of the project. When you are about to form a team for your project, keep in mind that some cultures are developed, others are more primitive. Some have values, some not. You should consequently avoid choosing members from countries with cultures that are not similar to your own. Cultural dilemmas can prevent any project from being successful. They should therefore be smoothed or suppressed so as to make sure that they cannot disrupt project work. Your effort should concentrate on communication that can help reach that goal. As norms regarding communication habits differ significantly across various cultures, communicating between people from different countries should only be done using language. The nonverbal dimension simply bears too many risks. See references

Marked for review

40. Which statement on conflicts is true? Conflict resolution should focus on people, not issues. Conflict is natural and forces a search for alternatives. Conflict should always be handled in private and not in the team. Too much openness is a common cause of conflict. See references

Marked for review

41. A change request in a project has been rejected some weeks ago. Yesterday, the project manager found out that it nevertheless has been implemented by the team members, who knew of the change request, but not of the rejection. In order to avoid such a situation, rejected change requests should be consistently communicated to stakeholders through which process? Report performance Verify scope Perform integrated change control Monitor and control risks See references 42. What is a trigger in project risk management? An expected situation causing an unidentified risk to occur A warning sign that a previously identified risk might be occurring or has occurred An unexpected situation causing an identified risk to occur An unexpected situation causing an unidentified risk to occur See references

Marked for review

Marked for review

43. According to the project plan, a contractor is scheduled to deliver some software components today afternoon. A regular payment is due to be made to this contractor tomorrow. You and your project team received a note this morning informing you that the software delivery will be delayed by 2 weeks. What should you do right now? You should delay the payment also for 2 weeks.

You must immediately find a different contractor. You should conduct a meeting with the contractor to resolve the delivery issues before making the payment. You should make the payment and reschedule the project plan. See references

Marked for review

44. In a software company a large number of simultaneously performed projects utilize the same groups of human and other resources.

What is the term commonly used for this situation? Concurrent engineering Resource over-allocation Resource pooling Program management See references

Marked for review

45. What does the acronym RACI commonly stand for in project management? Responsible, Accountable, to be Consulted, to be Informed Remote, Attached, Connected, Integrated Risk Analysis and Caution Initiative Randomly Accessible Cashflow Information See references

Marked for review

46. You have used estimates made by your team members and applied the critical path method to compute a network logic diagram for your project. Then you found out that it cannot be sufficiently optimized for scarce resources and fast progress towards a given deadline. What should you do next?

Apply resource leveling heuristics to uncritical activities only. Reduce estimates on duration and work efforts by an adequate percentage. Apply Three-point estimation and critical chain project management. Remove physical constraints and replace hard logic with soft logic. See references

Marked for review

47. Liquidated damages (LDs) are contractually agreed payments in order to... ...give the contractor an incentive to meet an aggressive schedule or challenging quality objectives. ...penalize the contractor for late completion of a project or failure to meet specifications. ...cover the customer's costs caused by late completion or failure to meet specifications by the contractor. ...make a bid or proposal binding for the offerer while the customer has time to select among various bidders. See references 48. What should not be covered by a risk management plan? Roles and responsibilities for handling project risks Timing of project risk management activities The methodological approach used for risk management Individual risks and potential responses to them See references

Marked for review

Marked for review

49. You are assigned as the project manager to a project which had a one-time cost variance in the past caused by unexpected rework which has meanwhile been finished. You perform earned value analysis and get the following results: EV: 250,000; PV: 200,000; AC 275,000 BAC is 500,000. What is right? EAC = 550,000 EAC = 525,000

EAC = 500,000 EAC = 425,000 See references

Marked for review

50. An estimation has been made that the construction of a residential home will cost a certain amount per square foot of living area. This is an example of what type of estimating? Analogous estimating Bottom-up estimating Top-down estimating Parametric estimating See references 51. What is true for prototypes? Prototyping causes significant costs and should be avoided wherever possible. They are tangible and allow for early feedback on requirements by stakeholders. Prototypes are mostly developed toward the end of a design or build phase. Prototypes increase the risk of misunderstandings between developers and users. See references 52. What is a constructive change? A change request that helps improving the project and its product, service or result and is discussed generally in a friendly style. A direction by the buyer or an action taken by the seller that the other party considers an undocumented change to the contract. A field change or ad-hoc change mandated by the project customer in a public construction project. A change request which will lead to the re-construction of an older version of the project performance baseline by the contractor. See references

Marked for review

Marked for review

Marked for review

53. Which of the following is generally not regarded to be a motivator according to Frederick Herzberg?

Working conditions and interpersonal relations Responsibility for enlarged task Interest in the task Recognition for achievement See references 54. What is true for modern project management? Project managers need... ... to have a strict standing in negotiating ... to show experience in tricking business partners ... to be team players and facilitators instead of "bosses" ... to be strongly linked to local traditions See references

Marked for review

Marked for review

55. You are the project manager in an engineering project and have recently signed a contract with a software vendor for the development of a complicated control solution. The software will be used to control machinery equipment which your project team is currently developing. The contract is a lump-sum contract. The contractor has target cost estimated which seem rather low to you. Which of the following statements is not true for this situation? It is the contractor's risk in this type of contract that their profit may vanish if costs have been underestimated. This form of contract should only be chosen when all the requirements for the building of the product are well-known by all parties involved. In a fixed-price contract, change requests can cause issues regarding additional time and extra costs for the changes to be applied. It is likely that your organization may have to assume any unexpected additional costs for the software development. See references

Marked for review

56. A review to determine whether of project activities comply with organizational and project policies, processes, and procedures is commonly called Quality auditing Inspection Quality testing

Reject screening See references 57. Which of the following is true regarding the code of accounts? It allows one to easily identify the breakdown level of the item in the resource structure. It describes the coding structure used by the performing organization to report financial information in its general ledger. It is the collection of unique identifiers generally assigned to WBS items. It defines ethical behavior in the project and the responsibilities to the customer and the profession. See references

Marked for review

Marked for review

58. You are the manager of your company's project management office. The company is running many concurrent projects; most of them share a resource pool of technical staff. Understanding how resources are utilized across projects has been found essential to overall project performance, including cost effectiveness and profitability. This morning you received a message that the resource pool members will be unable to perform as planned for the next months because the overall work load has grown too high and while delays are adding up, the morale of the staff is going down. What should you do next? Ensure that quantitative information for all projects is being made available in a uniform and reliable fashion and verify that the project management methodology is adhered to. Then consolidate the information to get an understanding of the problems related with the use of shared resources. Implement an enterprise project management software solution which is able to level the human resources across the various projects and which has the capability to model resource assignment on a percentage level thus optimizing resource utilization for the overall organization. Do nothing related to the described problem unless you are explicitly requested by the organizations upper management. Supporting decision making on the level on which project portfolio management is done, is not the project management office's business. Evaluate project management software which supports planning and scheduling across enterprise-wide project portfolios. Avoid managing the availability of shared enterprise resources for the projects run by an organization because this is not the business of a project management office. See references

Marked for review

59. You have been criticized that certain specifications in your scope statement do not pass the test for SMART objectives. What are SMART objectives? Objectives specified in far more detail than necessary for a execution of a successful project. Easily achievable objectives which help you reducing the pressure on yourself and the team. Objectives that should be achieved in order to attain formal recognition by both the customer and the project sponsor. Objectives that are described using specific, measurable, assignable, realistic and timerelated specifications. See references

Marked for review

60. You have been assigned as a project manager to a software project. While you and your team are working on a WBS (work breakdown structure), estimations for activity durations based on the activity list vary significantly. Which additional documents may help you clarify this situation? Milestone list and scope baseline. Project schedule network diagrams and human resource plan. Activity cost estimates and scope baseline. Activity attributes and project scope statement. See references 61. You are performing earned value technique on your project. After budget approval, an additional and unexpected cost item has been identified, which made the project more expensive some weeks ago. The item has meanwhile been paid by the project team, and it is expected that for the remaining duration of the project, costs will be as budgeted. In this case, which is the best formula to calculate EaC (Estimate at Completion)? EaC = BaC - CV EaC = BaC / CPI EaC = AC + BtC / CV You can not compute the EaC. See references

Marked for review

Marked for review

62. During a company event, you had the opportunity to talk to a colleague project manager. He told you that in his current project actual costs are 15% under cumulated costs budgeted for today. What do you think? The information given to you by the colleague is not sufficient to assess project performance. The project will probably be completed with total costs remaining under budget until the end. A significant cost increase during the further course of the project will probably bring the costs back to baseline level. Original cost forecasting and budgeting for the project must have been poor to allow this variance. See references 63. What is the meaning of a concept called the "Journey to Abilene"? Project managers should visit their customers far more often than what is usual in order to avoid misunderstandings and bad emotions. International projects may have an increased need for traveling which can lead to additional costs and troubles with time zones. Committee decisions can have the paradox outcome, that a jointly made or approved decision is not desired by any individual group member. A project is a temporary endeavor undertaken to create a unique product, service or result. Repeating it would be similar to making the same journey twice. See references

Marked for review

Marked for review

64. Which of the following statements describes best the relationship between project phases and the project life cycle? The project life cycle includes the time when the project is performed and the expected product lifespan after that. In project management, the sequence of project phases and phase gates is often referred to as project life cycle. The project life cycle is regarded as a sequence of project activities while phases are defined to control overlapping activities. The project life cycle describes how iterations of project management processes are used when a project schedule is developed. See references

Marked for review

65. Which is an appropriate order in most project situations for the development of scope-related documents? 1. Project SOW (statement of work), 2. Project charter, 3. Project scope management plan, 4. Project scope statement, 5. WBS (work breakdown structure) and WBS dictionary. 1. Work breakdown structure, 2. Scope statement, 3. Project charter, 4. CSOW (contractual statement of work), 5. Contractual work breakdown structure 1. Feasibility study3. Contract, 4. CWBS (contractual work breakdown structure), 5. Scope of work descriptions, 6. PID (project initiation document). 1. BOM (Bill of materials), 2. CAP (control account plan), 3. Project charter4. Change management plan,5. Scope baseline. See references 66. What is the S-curve in project management?

Marked for review

A graph that is generated if a normal curve is integrated. A graph that is to be integrated to generate a normal curve. A metaphoric description of the short term uncertainties that are present in every project. The graph that describes the typical growth of earned value during the course of the project. See references

Marked for review

67. An output of the process Estimate activity resources is a document called "activity resource requirements". It identifies the types and quantities of resources... ...while the term resources is limited to equipment and materials. ...required for each activity in a work package.

...while the term resources is limited to human resources. ...to be obtained solely from the performing organization. See references

Marked for review

68. What is not the purpose of configuration control when configuration management is applied in a project? Verification that the configuration identification for a configuration item is accurate, complete, and will meet specified program needs. Ensuring that proposed and approved changes to configuration items are fully analyzed. Ensuring that proposed and approved changes to configuration items are fully documented. Managing and controlling the frequently requested changes to a project by applying agreed rules. See references 69. Which statement describes best the meaning of the term cost baseline? A cost baseline is always created by translating time-phased cost information into cost data on activity or work-package level. A cost baseline is an approved time-phased budget that will be used to measure and monitor cost performance on the project. Data to draw a cost baseline can be easily generated and updated as necessary from information related to actual project cost. A cost baseline is usually displayed in the form of an inverse S-curve drawn from the beginning of the project until data date. See references 70. Which is not true in regard of RoI (return on investment) for a project? It defines the cumulated net income from an investment at a given point in time or during a defined period. It includes investment, direct and indirect costs and may include allowances for capital cost, depreciation, risk of loss, and/or inflation. It is most commonly stated as a percentage of the investment or as a dimensionless index figure. It is the time when cumulated net income is equal to the investment.

Marked for review

Marked for review

See

Marked for review

references 71. A project sponsor requested earned value data on two concurrent projects from the project managers. Both projects are regarded as equally important and strategically beneficial and have been finished by over 80%. He received the following information:Project A: PV: $1,800,000 EV: $2,300,000 AC: $2,100,000Project B: PV: $2,000,000 EV: $1,500,000 AC: $1,600,000The sponsor considers to shift some resources from project A to project B to speed up the second project which is currently behind schedule. What is the most likely outcome of such a measure? Changing team assignments during late course of a project typically increases cost efficiency. Changing team assignments during late course of a project typically increases time efficiency. According to the law of diminishing returns, the consolidated cost variance of the two projects will decrease. According to the law of diminishing returns, the consolidated cost variance of the two projects will increase. See references

Marked for review

72. Which of the following statements describes best the relationship of quality and grade? Low grade is always a problem; low quality may be overcome by a good rework and repair process. Grade is a category or rank given to entities having different functional requirements but the same need for quality. Both quality and grade can often be improved through intelligent measuring, testing and examining. Low quality is always a problem as it bears on the ability of an item to meet requirements; low grade may sometimes be acceptable. See references

Marked for review

73. Network templates which contain only portions of a network are often referred to as Sub-networks or fragment networks Subprojects Programs WBS items See references

Marked for review

74. You have been asked to calculate the internal rate of return (IRR) of a project? What will you assess? The time period needed to pay back the investment from a project when future income is discounted. The inherent discount rate or investment yield rate produced by the project's deliverables over a pre-defined period of time. The rate of negative risk that can be accepted for a project without turning the expected net present value negative. The expected benefit from a projects deliverable calculated as a percentage of the original investment over a specified time period. See references

Marked for review

75. You just created the following network logic diagram to describe the planned flow of activities for your project which will start tomorrow:

Which potential inconsistency in the diagram should you solve right now? Activity E is open ended ( a "dangle") in relation to the finish milestone path convergence. Activity F is open ended in relation to the path divergence after the start milestone. You cannot calculate a critical path when lags and/or leads are calculated in percent. Activities E to F need another task drawn as a hammock to calculate level of effort.

Result:
Notes:

of 75,

- After clicking the Solve Sample Test button, the correct answers will be highlighted in blue color above in the questions & answers section. made a decision in 2006 to not publish passing scores for the exams any more. The actual score is estimated to be between 70% and 75%. I recommend to target 75% results or better in this and all - PMI other difficult prep tests you are taking, 82% in simple tests. I am... ...generally interested in the PMP certification. ...on my way to pass the PMP exam. ...already certified as a PMP.

Finished? Click here to send your feedback to me. Help your friends find this free service easier by clicking: inShare

More Providers of Free PMP (+CAPM) Preparation Questions


Christelle P. from Canada mailed Oct 11 2003: "I passed the test! Thanks for the 75 prep questions. The only way to succeed is to write tons of practice exams!" So true! In 2002, I was the only provider of free PMP exam prep questions on the web. Today, you can find thousands of them on the web. Below are links to many providers with more than 3,000 free prep items (questions and answering options); more than 4,000 for PMI members:
# of free test items Level of difficulty

Provider Ajith Namboothiri

URL

Comment Requires registration. Number of questions may grow, as visitors are invited to add further questions. Many questions of CAPM exam style.

(explain)

www.ajithn.com

208

La Tha CertChamp CertGear

206-free-pmp-exam-questions.blogspot.com www.certchamp.com www.certgear.com certification.about.com

206 200 6 Free trial of CertGear's exam simulator. Questions based on Whizlabs' Exam Simulator software trial. Requires registration Online practice exam from the authors of Head First PMP book. A PDF file with 2MB for download.

Certification. about.com

20

EdWel Programs Head First Labs

www.edwel.com www.headfirstlabs.com

200 200

MeasureUp

www.measureup.com

Simulates a test environment online similar to the original environment. Simulates a H test environment online similar to the original environment. PDF file (app. H 1MB) for download. Just like the real thing: Questions are written against the PMP Examination Content Outline and reference to a current project management source. German language aid for the 175 questions. H

My PMP

www.mypmp.ie

90

Oliver F. Lehmann, PMP

www.oliverlehmann.com

175

www.oliverlehmann-training.de www.oliverlehmann.com

175

75

The 75 H questions above, with a timer in the title bar. 30 free questions for Apple iPhone and iPad. 30 free questions for Android smartphones and tablets. 30 free questions for Windows 8 smartphones and tablets. H

itunes.apple.com/de/app/xzams-pmpsample/id399303897?mt=8 market.android.com/details?id=com.digit.pmpexamfree

30

30

www.windowsphone.com/en-gb/store/app/pmp-examfree PMP Preparation in Google+

30

New PMP prep H question posted and discussed from time to time. Visitors H submit new PMP prep questions and discuss them. 164 CAPM Prep Questions: Not quite the PMP exam (CAPM)

Project Management, PMI, PMP Certification in Google+

www.oliverlehmann.com

style, but also helpful for your preparation.

CAPM Virtual Study Group

50

For CAPM (CAPM) preparation: Attendees are invited to post own questions. Also helpful for PMP preparation. Registration required. My friend Cornelius Fichtner and his company are happy to help project managers pass the PMP exam. Registration required. Simulators help get familiar with MC exam environments. Simple simulator

OSP International LLC

www.free-pm-exam-questions.com

110

free.pm-exam-simulator.com

90

PassTheProjectExam PMConnection PMExam.com

passtheprojectexam.com www.pmconnection.com www.pmexam.com

431 10 ?

Order their H free Daily Digest as an e-mail service. A great resource with intelligent questions. Nice little simulator for the real test. Good questions. H

PMPerfect.com

www.pmperfect.com

10

PMPQuest.com PMP Question Bank PM Study

www.pmpquest.com pmpbank.googlepages.com www.pmstudy.com www.pmstudy.com

12 200 50 Good, difficult H questions. 200 free questions after optional registration. Registration needed Registration required. Registration required. Come as an Excel file. CAPM Prep (CAPM)

15 15 155 30 25

PMTI Pmzilla Practical PM Pty. Ltd.

www.4pmti.com www.pmzilla.com www.mosaicprojects.com.au www.mosaicprojects.com.au

Questions. Not quite the PMP exam style, but also helpful for your preparation. PreparePM

www.preparepm.com

165

High quality H questions, which simulate the real test very well. H Registration required.

Project PMP ProXalt SSI Logic, Christopher Scordo, PMP, ITIL

sites.google.com/site/pgmpguide/ www.proxalt.com pmi.books24x7.com

480 20

+1000 Free (for PMI H members) online version of the book through PMI's eReads and Reference. Commercial version available in stores. 200 Registration required. Tough stuff. Good. H

Simplilearn

www.simplilearn.com www.testprepreview.com www.threon.com www.trial-exams.com/ www.tutorialspoint.com www.slideshare.net www.voightps.com

Test Prep Review Threon Trial Exams Tutorials Point University High School Fresno Voight Project Solutions

15 13 30 200 150 500 (CAPM) My friend and H colleague Dr. Roger Voight has a large body of free questions. Many of them are also helpful for CAPM candidates. You need MS Internet Explorer to open them. Registration required

H
H

Whizlabs

www.whizlabs.com

52

Digest for exam simulator. H Registration required.

* Level of difficulty marked with H: If you achieve 75% in these tests, you should be well prepared for the real exam.

Raise the number to 82% for the other tests. Preparation seminars with Oliver F. Lehmann, PMP Vorbereitungsseminare mit Oliver F. Lehmann, PMP

Help your friends find this free service easier by clicking: inShare

Sponsors: FREE Download for learning and instruction. Insight tree supports project selection and helps you become a decision tree expert.

"PMI", "PMP", PgMP", "CAPM", "PMBOK" are marks of the Project Management Institute (PMI) which are registered in the United States of America and in other nations PMI has not participated in the creation of this self assessment test and has not reviewed it for correctness. This test is for self assessment only and no guaranty is given for pass ing the PMP exam. Some of the names of companies and their products listed and linked to on this page are marks which are registered in various countries. 2004-2007, all rights reserved. The owner of this website is not responsible for contents of external pages to which he placed hyperlinks. Contact: oliver@oliverlehmann.com Advertisment