Vous êtes sur la page 1sur 2

SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)

SAUDI ARAMCO INSPECTION CHECKLIST


Installation of Fire Water Isolation Valves
PROJECT TITLE

SAIC NUMBER

DATE APPROVED

QR NUMBER

SAIC-L-2056
WBS / BI / JO NUMBER

25-May-05

MECH-

CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) LAYOUT DRAWING NUMBER SCHEDULED INSPECTION DATE & TIME SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO INSPECTION LEVEL

EQUIPMENT DESCRIPTION REV. NO. PURCHASE ORDER NUMBER

EQPT CODE

SYSTEM ID.

PLANT NO.

EC / PMCC / MCC NO. QUANTITY INSP. MH's SPENT TRAVEL TIME

ACTUAL INSPECTION DATE & TIME SAUDI ARAMCO ACTIVITY NUMBER CONTRACTOR INSPECTION LEVEL

SAUDI ARAMCO USE ONLY


WORK PERMIT REQUIRED?

ITEM No. A

ACCEPTANCE CRITERIA General Requirements: Steel body valves shall be used for above ground firewater system block valves to avoid failure due to fire, and AG to be equipped with position indicator or showing full open and close positions. Isolation valves between the hydrant and fire water main, if provided, shall be buried in accordance with SAES-S-040. Each utility line shall be provided with an isolation valve just upstream of the specified hose connector at the termination. A branch piping of a raw/firewater combined distribution system, serving firewater systems of a building or a facility is connected upstream of the isolation valve of the raw water supply piping. Each pressure control valve shall be provided with an upstream and downstream manual isolation valves, designated "locked open". Installation of isolation valves serving mains or branch piping to fire fighting equipment or any firewater system shall meet the requirements of SAES-B-017. Isolation valves between the hydrant and fire water main, if provided, shall be buried Underground piping, valves, and fittings shall be externally protected against corrosion per SAES-X-600. The spray system shall be considered to start at the inlet flange of the isolation valve connecting to the distribution piping. The spray system shall consist of an isolation valve, a strainer, actuation valve, and spray system piping. Isolation and actuation valves shall be accessible from grade and shall otherwise meet the access requirements of SAES-B-054 The entire spray system downstream of the isolation valve shall be capable of being drained by low point drains The deluge system shall be considered to start at the inlet flange of the isolation valve connecting to the distribution piping The system shall consist of an isolation valve, deluge valve, piping, and deluge heads.

REFERENCE

PASS

FAIL

N/A

RE-INSP DATE

A1

SAES-L-008 Para 8.2 SAES-B-017, Para. 7.2.2 g SAES-L-310, Para. 19.8 SAES-S-040, Para. 5.5.17 SAES-B-017, Para. 14.4.2 SAES-S-040, Para. 5.7.3 SAES-B-017, Para 7.2.2 SAES-B-017, Para 7.3.4 SAES-B-017, Para 10.5.1

A2

A3

A4

A5

A6

A7 A8

A9

A10

SAES-B-017, Para 10.5.2 SAES-B-017, Para 10.5.4 SAES-B-017, Para 11.6.1 SAES-B-017, Para 11.6.2 SAES-B-017, Para 11.7.1 SAES-B-009, Para 4.8.6.7

A11

A12

A13

A14 Deluge valves may be manually operable except as specified in Section. Sectionalizing valve handwheels shall be accessible from deck level and A15 located at a convenient operating height, hand wheels or other extension shall not obstruct walk ways or equipment access ways.

Page 1 of 2

SAUDI ARAMCO ID/PID - 2/19/05 - REV 0 (Standards Cutoff - August 2004)

SAUDI ARAMCO INSPECTION CHECKLIST


0
PROJECT TITLE

SAIC NUMBER

DATE APPROVED

QR NUMBER

0
WBS / BI / JO NUMBER

25-May-05

MECH-

CONTRACTOR / SUBCONTRACTOR

ITEM No.

ACCEPTANCE CRITERIA

REFERENCE

PASS

FAIL

N/A

RE-INSP DATE

A16

Flanged valves shall be provided at the ends of Fire Water loops to sectionalizing/Flushing upon completion of construction and at intervals. Buried sectionalizing valves in FW system shall be provided with indicator posts. Chain wheel operation shall not be installed on emergency isolation valves. Gate valves are used above ground, they shall be installed so that the stems are horizontal. Block valves shall be provided in piping to isolate line failures for repair,and assure flow of FW to all risk areas in case of failure in fire.

SAES-B-009, Para 4.8.6.8 SAES-L-008 Para 7.7 SAES-B-009, Para 4.8.6.2 SAES-B-017, Para 12.4c SAES-B-017, Para 9.2

A17

A18

A19

A20

REMARKS:

REFERENCE DOCUMENTS:y g ( y ) 2. SAES-B-009, Fire Protection and Safety Requirements for Offshore Production Facilities, (30 January, 2002)

4. SAES-S-040, Saudi Aramco Water Systems, 31 December 2003

Contractor / Third-Party
Construction Representative*
Work is Complete and Ready for Inspection: Name, Initials and Date: Name, Initials and Date:

Saudi Aramco
PMT Representative
T&I Witnessed QC Record Reviewed Work Verified

QC Inspector
Performed Inspection Name, Initials and Date: Work / Rework May Proceed

PID Representative
T&I Witnessed Name, Initials and Date: QC Record Reviewed Work Verified

QC Supervisor
Quality Record Approved: Name, Sign and Date: *Person Responsible for Completion of Quality Work / Test

Proponent and Others


Name, Organization, Initials and Date: T&I Witnessed QC Record Reviewed Work Verified

Y = YES

N = NO F = FAILED

Page 2 of 2

Vous aimerez peut-être aussi