BALDEV INFRA PROJECTS (P) LTD

Construction of 168 Units Type III T/S Quarters at NMDC Bacheli DAILY SITE REPORT FOR SITE NO. I & II Dated- 20-Jan-12
WORK MEN DETAILS
REJA 25 0 18 27 0 7 COOLIE 12 0 2 3 0 5 MASON 0 4 0 0 CENTRING MISTRI CENTRING HELPER 0 16 12 7 1 16 7 9 SUPERVISOR As per attendance 1 1 0 OTHERS 0 1 0 0 TOTAL 38 0 58 50 16 12 REMARKS
Co's side, de watering, cleaning of slurry, raft rcc, road cleaning, boulder loading & breaking, sand boulder filling.

TODAYS ATTENDANCE OF STAFF (Enter: A = Absent, L = Leave, E = Excused, or P = Present)

20-Jan-12

Sr No. 1 2 3 4 5 6 7 8 REMARK 4 hrs Plinth filling at bl-14, loading of soil for shifting, metal loading & misc works local shifting of soil, cement, boulders etc idle metal & soil shifting local at bl-07 at bl-06 Other details No. of trips 1 2 2 1 2 REMARK For co's mixure machine 3 4 5 6 7 8 9 9 10 11 12 13 14 15 16 A 0 Sr. No

Name of Staff & Designation Sunil Kulkarni (Proj. Mgr) Kailash Wakode (Engr) Pranav Patel (Engr) Prahlad Sharma (Works Mgr) P. L. Khande (Supervisor) N. Kumar (Supervisor) Raju Chapadi (Supervisor) Mukesh Bhaskar (Supervisor) (on leave since 24th Dec) Gautam Srivastav (Tract. Driv) Bhola Nag (Dumper Driv) Moti Ram More (Office Boy) Damyanti Bai (Cook) Night Watchmen, Idea Sec (1st Site) Night Watchmen, Idea Sec (2nd Site) Sushant (RM800 Operator) J. P. Wahane (Engr.) P 15 TODAYS Expences with balance Particulars NMDC BACHELI SITE B/f Photocopy & courior mess expences Data card recharge 29448 E 0 DR

Attendance P P P P L P P P P P P P P P P P L 1 20-Jan-12 CR

0 bricks made (half size)

66 bricks made (full size)

Electrical shutdown

Dept. (Brick making team) SSM Engineers (Murty/Madhav Rao) Shashikant Kanwar Tulsi Dass (Shuttering/centering team) Ramesh Agrawal (Brick making team)

MACHINERY DETAILS
TYPE OF MACHINE EX-110 Tractor Mixure RM-800 Dumper 2207 5 HP Diesel pump 2 HP elect pump Sleep No issued by us 8680 8681, 83 8679, 82 START READING 35.5 1447.7 75427 END READING 45.7 1447.7 75433 TOTAL RUNNING 10.2 0 6 5 hrs 5 hrs QTY (Cft) 300 2x308 2x308 Time of Unloading 11.2 12.30, 18 10.50, 17.15 VEHICLE DIMENSION 14.6x8x2.7 14.6x7.6x2.10 14.6x7.6x2.10 HSD ISSUED READING AT TIME OF ISSUE 26.9 Hr Mtr not working

INWARDS METAL, SAND & BOULDERS ONLY


ITEM SUPPLIER VEHICLE NO. CG-18-H-1069 CG-18-H-1091 Pit pass No. 5672704 5671796, 2913 5671791, 2911 Remarks

Metal 20 mm (G) Durga st. cru. Sand Sand P.D. Sing P.D. Sing

50 191 98

LOCAL PURCHASE/machine/other materials received


S.NO 1 2 3 4 DETAILS Backfilling Excavation Sand & boulder filling RCC 1:2:4 PCC ITEM
Engine oil

SUPPLIER
*petrolium

QTY 1ltr

SIZE

VEHICLE DIMENSION

VEHICLE NO.

WORK DETAILS
NO'S QUANTITY 100 0 15 13.94 5 TARGETED 100 0 20 15 5 Required for the project 88288 834.48 48410
ACTUAL ACHIEVED

100 0 15 13.94 5

NEXT DAY TARGET 100 0 20 15 5

REMARKS At bl- 14 for 6 rafts at bl-07 5th fl at bl-01, 4 rafts at bl-06, 12 col at bl-09, 6 col & 11 caps at bl-11 for 6 rafts at bl-07

Total Balance (+ for Dr, - for Cr)

29448 29109

339

REQUIREMENT
ITEM
Curing pipe 1/2 inch Sprinkler with stand

STOCK POSITION
Details of material CEMENT Bag STEEL (MT) METAL 40 MM (Cft) METAL 20 MM Granite (Cft) METAL 20 MM Regular (Cft) METAL 12 MM (Cft) SAND (Cft) CC BRICKS NOS Boulders(cft) Upto date Qty 16200 273.34 17850 22110 197951 59318 53640 157700 340000 70000 24075 115018 17432 6650 9008 15015 36614 17796 1750 0.00 0.00 1232 66 0 9008 15015 37846 17862 1750 443 16 1137 0 378 8565 14999 36709 17862 1372.44 5 Total OPENING 377 50.53 1561 6005 RECEIVED 0 0.00 0.00 300.00 TOTAL 377 50.53 1561 6305.30 CONSUMPTION 99 0.60 159 BALANCE 278 49.93 1402 6305.30 Sr No. 1 2 3 4

HSD DETAILS Particulars Purchased Ex-110 diesel pump+mixure machine+vibrator 0+3+0 Tractor 4 Balance 0 4 4 Opening balance 4 Issued qty

QTY
4 bundle 3 nos

concrete breaker

Bl-01 : SF slab shuttering in prog. Bl-02 : Yet to start. Bl-03 :plinth complete, backfilling in prog. Bl-04 : Gf slab casting done on 8th Jan 12.

overall position of project

Special Remarks and happenings during the day

Pl arrange for the steel shuttering of slab as discussed

Bl-05 : GF slab complete, ff columns complete. Bl-06 : pb compl for 2 unit, col started, sand/boulder filling/PCC/ rafts started for remaining 2 units. Bl-07 : Excavn done for 2 units, sand/boulder filling / PCC started. Bl-08 : Filling upto pl bot in prog. Bl-09 : Plinth Beam complete, columns started.

Field Er Mr. J.P. Wahane joined today

Bl-10 : Ff slab casting done on 19th Jan. Bl-11 : Ff col in progress. Bl-12 : Shuttering for GF slab in progress. Bl-13 :col for gf complete. Bl-14 :Plinth beams complete, plinth filling in prog.

Mr. Patel,Khande & P. Sharma REPORT PREPARED BY

Out of 42 slabs, 7 slabs complete, 2 are sure in this month, backlog will be of 1 slab as per planning.

SUNIL KULKARNI CHECKED BY