Goals and Organization for Tonights Meeting Presentation Recap Evolution of LAUS in stages Next Steps
Presentation Outline
June 2012: Master Plan Team approved by Board August 2012: Notice to Proceed 24 month process Work organized into 3 tasks 4 briefings Task 1: 1 Community Meeting Task 2: 2 Community Workshops Task 3: 1 Community Workshop
Project Overview
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
2012
A S O N D
2013
J F M A M J J A S O N D
2014
J F M A M J J
Task 1
Today
Task 2
Task 3
Board Meeting
Project Timeline
Project Scope
Concurrent transport projects: SCRIP (Southern California Regional Interconnector Project) Silver Line Bus Rapid Transit Station
Separate but related and coordinated planning projects: Union Station Master Plan Union Station Wayfinding Union Station Community Linkages
Size of Circle = Relative number of users Total for Cesar Chavez / Vignes is almost equal to total for Patsaouras Plaza
Transport Optimization
Destination
Connectivity
Program Distribution
Neighborhood Connections
Bus
N. ALAMEDA ST.
Reinforce Connections to Chinatown Add Parking or Passenger Drop-off Reinforce Link to El Pueblo
Mozaic Apartments
MWD
El Pueblo
Alameda Streetscape
Union Station
Streetscape Improvements
New Median
Terminal Annex
Metro Headquarters
Sidewalk + Parkway
Enhanced Lighting
Tunnel Precedents
Pedestrian and Streetscape Improvements New Continental Crosswalks New Landscaped Medians
VIGNES ST.
Dennys
Graphic Novel
Next Steps
Evaluation Criteria
Evaluation Criteria
For Tonight:
Visit the stations Fill out a comment form; return tonight, or via mail or email
Next Steps
What programming or activities would you like to see at Union Station? Which elements of the passenger concourse and bus terminal address your transport needs? Which do not? How will any of these plans improve your transit experience? How do the transit and development concepts enhance Union Station as a destination? Other Comments?