Overview
Different level of estimation Project Evaluation Introduction to Estimation Size Estimation Cost Estimation
Project Evaluation
A high level assessment of the project
to see whether it is worthwhile to proceed with the project to see whether the project will fit in the strategic planning of the whole organization
Strategic Assessment
Used to assess whether a project fits in the long-term goal of the organization Usually carried out by senior management Needs a strategic plan that clearly defines the objectives of the organization Evaluates individual projects against the strategic plan or the overall business objectives
Software Project Management 10
Portfolio management
suitable for project developed for other companies by software houses
11
SA Programme Management
Individual projects as components of a programme within the organization
Programme as a group of projects that are managed in a coordinated way to gain benefits that would not be possible were the projects to be managed independently
by D.C. Ferns
13
14
15
16
Image
How does the product affect the image of the organization?
17
SA Portfolio Management
suitable for product developed by a software company for an organization may need to assess the product for the client organization
Programme management issues apply
need to carry out strategic assessment for the providing software company
18
Technical Assessment
Functionality against hardware and software The strategic IS plan of the organization any constraints imposed by the IS plan
20
Economic Assessment
Why? Consider whether the project is the best among other options Prioritise the projects so that the resources can be allocated effectively if several projects are underway
21
22
EA Cost-benefit Analysis
A standard way to assess the economic benefits Two steps
Identify and estimate all the costs and benefits of carrying out the project Express the costs and benefits in a common unit for easy comparison (e.g. $)
23
24
25
Why?
An excess of estimated benefits over the estimated costs is not sufficient Need detailed estimation of benefits and costs versus time
26
Expenditure
27
28
Project 1
-100,000 10,000 10,000 20,000 20,000 100,000 60,000 5 12%
Project 2
-1,000,000 200,000 200,000 200,000 200,000 350,000 150,000 5 4%
Project 3
-100,000 30,000 30,000 30,000 20,000 20,000 30,000 4 10%
Project 4
-120,000 30,000 30,000 30,000 25,000 50,000 45,000 4 11%
29
Payback period
= Time taken to break even
32
value in year n PV = n (1 + r )
33
34
35
36
37
38
Useful
Dismiss a project due to its small IRR value Indicate further precise evaluation of a project
Estimation
Why? to define the project budget and to refine the product to realize the budget Who? the manager What? size and cost When? always How? techniques and models
Software Project Management 40
41
42
Estimation Approaches
Expert judgement
Ask the knowledgeable experts
Estimation by analogy
Use the data of a similar and completed project
Pricing to win
Use the price that is low enough to win the contract
Software Project Management 43
Bottom-up
The estimates of each component task are aggregated to form the overall estimate
Algorithmic model
Estimation is based on the characteristics of the product and the development environment.
Software Project Management 44
Size Estimation
Problems related to size estimation Size Estimation Model
Function Point Analysis (FPA)
45
47
52
53
Identify the productivity rate of both developer and CASE Productivity rate = average of the two PRs Calculate the effort
Effort = NOP / Productivity Rate
Software Project Management 55
Simple 1 2 N/A
Medium 2 5 N/A
Difficult 3 8 10
58
Low
Nominal
High
Very High
13
25
50
13
25
50
59
60
61
Cost Estimation
Cost Estimation Model
COCOMO II
62
63
COCOMO II (contd)
Recognizes different approaches to software development
Prototyping, Incremental development etc.
64
A history of COCOMOs
COCOMO originally proposed by Boehm in 1981, now called COCOMO 81 Later evolved to Ada COCOMO in 1989 In 1995, Boehm proposed COCOMO II
65
COCOMO II
A family of models
Uses different models in 3 different stages of the project
COCOMO II (contd)
The basic model equation Effort = Constant (Size)scale factor Effort Multiplier
Effort in terms of person-months Constant: 2.45 in 1998 Size: Estimated Size in KSLOC Scale Factor: combined process factors Effort Multiplier (EM): combined effort factors
67
68
Application precedentedness Process flexibility Architecture risk resolution Team cohesion Process maturity
Software Project Management 70
Process maturity
71
72
Assign each factor using a value between 0.5 and 1.5 (inclusive) EM is the product of all these values
74
Very Low Extra High 0.5 1.5 0.5 1.5 0.5 1.5 1.5 0.5 1.5 0.5 1.5 0.5 1.5 0.5
75
76
78
79
80
82
EAF Relations
Early Design RCPX RUSE PDIF PERS PREX FCIL SCED
Software Project Management
Post-Architecture RELY, DATA, CPLX, DOCU RUSE TIME, STOR, PVOL ACAP, PCAP, PCON AEXP, PEXP, LTEX TOOL, SITE SCED
83
84
COCOMO II (contd)
Advantages
Good improvement over COCOMO Good match for iterative development, modern technology, and management process
Disadvantages
Still immature, diverse projects in database Hard to believe that it will be any more reliable than the original COCOMO model
85
References
Hughes, B., and Cotterell, M. (1999) Software project management, 2nd ed., McGraw Hill Pfleeger, S.L. (1998) Software Engineering: Theory and Practice, Prentice Hall Royce, W. (1998) Software Project Management: A Unified Framework, Addison Wesley Center for Software Engineering, USC (1999) COCOMO II Model Definition Manual.