Internal Problems and Question List Pre-Function Area Panel Fold company needs to come for the last

few minor adjustments so that the gypsum can be closed around it o Called today 2/8 they said they would come at 9AM 2/9 Fabric o Can be measured now but has not been o I propose it can be installed too if properly protected o Need clarification on who is responsible and when they will come Sprinkler heads o Have called Maged and he states this is a financial issue o Need adjustments in Dishwasher and Kitchen and sprinkler heads too Speakers o Have they been ordered? o Is there a down payment? o Lead time? Switches for lights o Are they available? o Why cant we install? Fire Alarms o Are they on site? o If not who will order? From where? Emergency panels o Do these need to be ordered? o Who will install? Shaimaa says this is not our scope of work Grills o Essam has measurements o Has order been made? Money paid? Marble o What is the final status of who will supply rest of marble/finish installation? o Bianco sample to be supplied today Not found and first location, checking second location and answer/status by day end o Solution for damaged marble in PF floor and marble for Lobby area? Wood Ceiling o Wood supplied except for essential element needed to begin installation o FINANCIAL ISSUE how to proceed? Bar in PF o What is the status of the bar? o When will it be delivered? Lights for Ceiling o Why are they not ordered? o When will they arrive? o Can we handle the shipping to speed it up?

Connection of Marble floor to Carpet o Rising the carpet selected as design? o Does it require us to place orders? o Does it require approvals? Mirrors? o Who is going to do the mirrors in PF o Emilio refused and Gresh as well Shelves behind the bar o Who will do this? Skirting/Socket Interaction o What can we do ie plastering etc to prep the sockets etc? o Is socket prep dependent on marble skirting finishing or can we work independently? Wall paper o Who is to provide and when? Wood in Bathroom o If we are not going to use Emilio then who are we going to use and when will they come?

MAIN BALLROOM Sockets o AV can be installed Does this require any prep work by our crews? o Other sockets CAN NOT be installed due to: Hazam states specs on color etc not known Kamel states that area has to be prepped by our crews Emergency Panels o Same questions as above Whose scope of work? Who to install and when? Switches o Why can these not be installed now? LIGHTS o MAJOR ISSUE preventing most other work in this area Will we go with track? If so then we have closed 1st layer gypsum and will have to open again Decision has to be taken and lights ordered Marble o Same issue as above Who will finish? Where to supply from? How long etc? AS BUILT o Rejected for HVAC

Dimming Control approved with SIGNIFICANT changes requested status? Action? Spot Lights Near Windows o Not lined up correctly? Action?

KITCHEN DISHWASH - CORRIDOR Fire fighting pipes moved slightly o Moustafa states not in scope and needs approval from Maged, ie FINANCIAL ISSUE Sprinklers to be installed o FINANCIAL ISSUE TIED TO MAGED Gas o When to finish? o Payment? Who to install the panel behind the hood? o Need to order? o How long to install? o When to be installed? o Who will open the hood? Lights o Ayman to give verdict tomorrow 2/9/10 o Need installation by Electric Crew Holes for lights need to be opened o In progress but NEGLECTED TILL TODAY Testing o When is the earliest we can test?

AHU/MECH ROOM Lights will NOT FIT due to air duct/pipes o Adjustment? Solution? None so far Light switches o Need prep by our crew to finish installation Testing o When can we test at earliest date? o Needs electric cable too?

OTHER NO ACTION TAKEN SO FAR o WHY? o Is Emilio to provide the railing?

o o o o

If so what is the status? Where to we order the paneling from below the rails? Area near stairs in PF has plumbing issue before ceiling to close Action to be taken? Ceiling installation in multiple small areas NO ACTION TAKEN Paint/Plaster of walls NO ACTION TAKEN

TESTING AND COMMISIONING What is the status of the Electrical Board When will it arrive? Can we test and commission before using existing panel?

CONCLUSION: Main areas will problems that prevent the majority of work are: 1. Marble 2. Electrical Board for testing and commissioning 3. Wood in Ceiling

Most if not all are financial issues, so the financial strategy should be made clear to the responsible parties and followed up day to day. Without solutions to these issues ability to request additional workers squashed. Without solutions to these issues coordination of all other work becomes intensely more difficult. Proposed solutions need to be made clear as this renders all scheduling obsolete. Additionally, work in minor areas which has no connection to main issues is NOT being worked on. This is a good opportunity to complete work but not being leveraged. Work crews state that they "dont have any work", this is sometimes true and when it is, it is because the main issues listed above. However this is also not true because we are not leveraging them against the areas that we do have open work such as the minor areas near the kitchen, stairs, elevator etc. Workers are also not splitting their crews effectively, ie they use ALL there workers on the closing of the ceiling and neglect the work on the opening of the ceiling in the dishwasher area etc, as one example. There is no reason not to be working in multiple areas and advancing areas in parallel.