Académique Documents
Professionnel Documents
Culture Documents
CONTENTS
Click to go to Cover page
Fatal Nil
Root cause
Cumulative
Nil
Nil
Nil
Main Plant
No. of fire incidents 11/08/09 -Unit2 / UCB, Fire took place in Tube light fitting and false ceiling due to short circuit
Responsibility
Target date
Connection should be properly tight and insulated. Connecting wires insulation should be checked
EMD
Immediate
Main Plant
23/08/09 - Uni t-5 / At APH -5B, Fire took place in insulation near bearing housing.
Left out Insulation should be cleaned near hot surfaces area immediately
BMD
Immediate
Cumulative
16
Note *: Major pending point from previous year's action plans to be carried over to this table.
Schedule is circulated by Corporate Safety deptt . To be Lastaudit points have been complied & conducted by Audit team. closed. External Safety Audit is scheduled fom 10/09/09 to 14/09/09. Last Audit points have been complied. Audit schedule 10/09/09 to 14/09/09.
Nil
Nil
Nil
Nil
Total No. Available No. Reason for non availability Action plan Responsibility Target date
UNIT #1
Note: ORT Co-ordinator to check the following records.
Testing/ Inspection Turbine DC Lube Oil Pumps and discharge pressure DC Seal Oil Pumps and discharge pressure DC Scanner Fan APH Air Motor DG Sets DC Emergency light checking Diesel Fire Fighting Pump Diesel engine driven booster Pump Auto starting of fire fighting pumps Dewatering pumps Foam system testing in Fuel oil tank Non-Availability, if any Frequency of checking/ Inspection Last date of checking by station
5.0 ksc/40 A
Daily
Available
Daily
Available OK Available
OK OK Chlorine leak absorption system Fire fighting line water pressure at farthest & highest point Date of checking of Battery (Main Plant/UPS/Switchyard) Cable Rooms Inspection
29.04.2009 29.04.2009
05.09.09
Daily
Date of joint inspection and report of fire fighting & detection system Status of Monsoon preparation
UNIT #2
Testing/ Inspection Turbine DC Lube Oil Pumps and discharge pressure DC Seal Oil Pumps and discharge pressure DC Scanner Fan APH Air Motor DG Sets DC Emergency light checking Dewatering pumps Status of Monsoon preparation Non-Availability, if any Frequency of checking/ Inspection Last date of checking by station
Daily
05.09.2009 (as on05.09.2009) 29.08.2009 05.09.2009 (as on05.09.2009) 08.08.2009 05.09.2009 (as on05.09.2009)
UNIT #3
Testing/ Inspection Turbine DC Lube Oil Pumps and discharge pressure DC Seal Oil Pumps and discharge pressure DC Scanner Fan APH Air Motor DG Sets DC Emergency light checking Non-Availability, if any Frequency of checking/ Inspection Last date of checking by station
3.5 KSC/50 A
Daily
05.09.2009 (as on05.09.2009) Unit under O/H 29.08.2009 05.09.2009 (as on05.09.2009) 08.08.2009
Diesel engine driven booster Pump Dewatering pumps Status of Monsoon preparation
Available Available
Daily Daily
UNIT #4
Testing/ Inspection Turbine DC Lube Oil Pumps and discharge pressure DC Seal Oil Pumps and discharge pressure DC Scanner Fan APH Air Motor DG Sets DC Emergency light checking Dewatering pumps Status of Monsoon preparation Non-Availability, if any Frequency of checking/ Inspection Last date of checking by station
3.5 ksc/55 A
Daily
05.09.2009 (as on05.09.2009) 05.09.2009 (as on05.09.2009) 29.08.2009 05.09.2009 (as on05.09.2009) 08.08.2009 05.09.2009 (as on05.09.2009)
UNIT #5
Testing/ Inspection Turbine DC Lube Oil Pumps and discharge pressure DC Seal Oil Pumps and discharge pressure DC Scanner Fan APH Air Motor DG Sets DC Emergency light checking Non-Availability, if any Frequency of checking/ Inspection Last date of checking by station
3.6 ksc/48 A
Daily
05.09.2009 (as on05.09.2009) 05.09.2009 (as on05.09.2009) 29.08.2009 05.09.2009 (as on05.09.2009) 08.08.2009
Diesel Fire Fighting Pump Diesel engine driven booster Pump Dewatering pumps Status of Monsoon preparation
Available
Daily
Available Available
Daily Daily
Action plan
10 Nil Nil 49 42 0 3 34 2 13
Testing of lifting equipments are being done by competent person for 2009 as per statutory requirement..
Boiler License
Aux. Boiler NA
U-1 8/17/2010
U-2 7/1/2010
U-3 4/24/2010
U-4 5/24/2010
U-5 11/16/2009
U-6
U-7
Description
Aux. Boiler
Compressed Chlorine
Diesel Storage at
Hydrogen Generation
N/A
12/31/2010
12/31/2010
9/30/2013
AREA TG Hall Last date of checking structures as 8/18/2008 per Guidelines Compliance of observations completed Y (Y/N) Action Plan for the NA Pending Observations Freq. of 01 year checking Next date Aug-09 of checking
Boiler Dec.-08
ESP Jul-09
CHP Jun-08
AHP Jul-09
Bunkers Dec.-08
Y NA 01 year Dec.-09
Y NA 01 year Jul-10
Y NA 01 year Jun-09
Y NA 01 year Jul-10
Y NA 01 year Dec.-09
Y NA 01 year Mar-10
Y NA 01 year Mar-10
Note: ORT Co-ordinator is to affix the relevant Reports along with Action Plan
Area
TG
CHP
AHP
Oil Tanks
Last date of checking as per guidelines including spring loaded foundations Compliance of observations completed (Y/N) Action Plan for the Pending Observations Freq. Of checking Next date of checking
Aug-09
Apr-09
Jun-09
Jun-09
Mar-09
Y NA 06 Months Feb-10
Y NA 06 Months Sept.-09
Y NA 06 Months Dec.-09
Y NA 06 Months Dec.-09
Y NA 06 Months Sep-09
Note: ORT Co-ordinator is to affix the relevant Reports along with Action Plan
Unit No. 1 2 3 4 5 6 7 8 9 10 11 12
Major Observations
Proposed Action
Note: ORT Co-ordinator is to affix the relevant Reports along with Action Plan
5 yrs rolling 5 yrs rolling 5 yrs rolling 5 yrs rolling plan as plan as under plan as under Balance in 08plan as under under covering all covering all the covering all the 09 covering all the structures. structures. structures. the structures.
Balance in 08-09
5 yrs rolling 5 yrs rolling plan as under plan as under covering all covering all the the structures. structures.
2005-06
2007-08
2008-09
2009-10
Remarks
OFS OFS
OFS TMD
6.
Bal CHP-I
CHP
7.
CHP-II
Contract Re-sch Aug'09 amendment ( Paint Recd under approval in Mar'09) - Civil.
8.
Boiler I
Sept.'2008
Boiler II TG Hall I TG Hall II ESP + AHP + Compressor house (TAC)-(II) Balance of plant (CW, CT, Balance of plant (CW, CT, Ch. Partially Completed Partially Completed
Contract & Re-sch Oct'09 Material ( Paint Reced Availablein Mar'09) Civil Contract to be Re-sch Mar'10 initiated Civil. to be Contract Re-sch Mar'10 initiated Civil. to be Contract Re-sch Mar'10 initiated Civil. Re-sch Jun'09 Contract & ( Paint del Material Mar'09) Available-Civil Mar'10 Mar'10
o to Cover page
Respons ibility
Target date
Responsibility
Target date
Nil
NA
NA
NA
Medium Velocity Availability of Fire Water Spray Tenders Main Water Foam Jeep Plant Tender Tender tender CHP provided provided 1 1 nil available available 1 1 nil
Action plan
Action plan
Action plan
Action plan
Action plan
Action plan
Responsibility
Target Date
se
U-8
U-9
U-10
U-11
U-12
Y NA 01 year Oct'09
Frequency of checking Stage S/D Opportunity Stage S/D Opportunity Stage S/D Opportunity Stage S/D Opportunity
Compressor House Dec'07 As per requirement 5 yrs rolling plan as under covering all the structures.
17.0
SYSTEM COMPLIANCE
CONTENTS
Contents:
17.1 STATUS OF TECHNICAL AUDIT ACTION PLAN: 17.2 STATUS OF PEER AUDIT ACTION PLAN: 17.3 STATUS OF ROPR ACTION PLAN 17.4 STATUS OF ACTION PLAN OF OTHER COMMITTEES / REVIEWS 17.5 STATUS OF AUDITS CONDUCTED BY ORT COORDINATOR: 17.6 IMPLEMENTATION OF RECOMMENDATIONS OF KNOWLEDGE TEAM 17.7 STATUS OF TECHNICAL COMPLIANCE AUDIT ACTION PLAN: 17.8 TECHNICAL COMPLIANCE: 17.9 DEPARTMENT-WISE LMI STATUS 17.10 STATUS OF PENDING LMIS 17.11 LIST OF TC DOCUMENTS NOT APPLICABLE TO STATION
11-14/12/07
104
12
* Attach details of pending points along w ith action plan as separate file in ORT folder
* Attach details of pending points along w ith action plan as separate file in ORT folder
6/02-04-07
File enclosed
* Attach details of pending points along w ith action plan as separate file in ORT folder
Issues
Action plan
Responsibility
Target Date
Present Status
April Hot air dampers of stage-I are passing. Mill area Gas inert system not availble in stage-II Mill area May Mill area Maintenance hoist of stage-II: 1 no out off 4(25T) is not in service due to motor got burnt. Mill area Mill area June July Aug Sept Oct Nov Dec Jan Feb March Balls taken out from Ball mill of 4CD, 4EF during overhuling found to be very small less than 10mm. New ball replacement frequency DGM(BMD) Maintenance hoist of stage-I: 1 no out off 3 is not in service due to cable DGM(BMD) DGM(BMD) DGM(BMD)
Area
Unit
Action Plan
Responsi bility
Target Date
Present Status
Scaffolding : Scaffolding has been erected inside the furnace providing access to all heat transfer surfaces Capping of tubes Unit-4 08-12 Jul.-06 Reheater : Some of the exit coils are either touching the refractory on slant portion of goose-neck or Air Preheater : As per the latest wear-debris analysis of oil sample by R&D, the wear condition of Steam / air blowing of new bends / tubes Radiography of old weld joints Burner Transition tubes: i) High erosion noticed in WW burner transition tubes along Aux. air compartment at LTSH: i) 14 nos. stubs at LTSH inlet are being replaced for erosion. Platen SH : Mechanical rubbing noticed at some locations in spacer tube. Scaffolding : Sufficient scafold material to be procured for complete scafold, Cleaning : Using high pressure jetting in furnace. Penthouse Cleaning : Cleaning & Burnt skin casing to be repaired using design quality of refractory. Economiser Coil Erosion : Thickness Survey & Replacement of eroded coils of Economiser Zone should be done. LTSH : Eroded tubes Replacement & proper clamping. Unit-2 13-16 Jun.07 Platen SH : Inspection of Platen SH replacement of misaligned/blowed..
Use of wooden planks as scaffolding for inspection of panelletes to be discontinued, as it is unsafe. All vertical cut tubes to be capped immediately after cutting. Wherever additional refractory is provided, it is to be removed.
-------
Site has agreed to ensure the same in future overhauls. More emphasis is being given to capping Refractory removed to increase gap.
---------------------------Burnt skin casing is replaced. ---Completed ---Eroded tubes replaced & proper clamping done. ---Completed ---Completed ---Completed ---Completed ---Completed ---Completed ---------------------------------------------All replaced All replaced Done Checking Done Done Done Done Done Done Done Done Done Done With fluorcent die. Till date 189 old joints have been X-rayed. Radiography of critical erection joints planned in i) All eroded tubes replaced ii) Installed guide vanes in AA elevation of Pre heating with coil will be ensured from next O/H Spacer tube replaced and in next overhauls also this will be ensured. Station has initiated indent for procurement of additional scafolding mat. Done Inspection done Bearing replaced Being done.
Inspection of both the guide bearings to be done. Inspection of Support brg of RAPH-4A to be done after withdrawing the All new tubes / bends to be steam / air blown to check for through ness and internal cleaning. Radiography of old joints to be done in a phased manner. i) ii) i) Replacement of eroded tubes based on thickness survey Misaligned tube to be corrected All such stubs to be replaced using correct pre-heating process.
BMD BMD
Spacer tube to be replaced in full BMD Approach for platen SH and Roof were made. BMD Will done after Replacement of RH/SH Coils. BMD BMD BMD BMD BMD
RH : Replacement of RH Tubes based on RLA study. BMD Hangers : Tightening of front wall Hanger fitted to drum, HRH Support hangers & Platen pannel hangers. . APH : APH Basket replacement. Ducts & Dampers : Repair to bring its original condition. BMD ESP : Replacement of GD screen emitting and collection electrodes. BMD Unit-3 09-13 Oct.-06 All Jacking oil hoses to be replaced . Its clamp tightning to be ensured DPT of metallic jacking oil supply pipe to individual bearing. Unit-4 14-15 July-06 Thickness checking of Bends in HPT balance chamber leak off to CRH pipe. MS & CRH piping hanger and Support checking in cold and hot condition correction to required values. Checking of jacking oil line welding joints Condenser bracing checking Turbine & Aux. RLA Study of LP & IP Turbine including inlet zone MS, HRH & CRH Thickness survey Unit-2 & Unit-4 Jun & May-07 Material Mix-up Notch cutting at pedestal 2 Bellow Inspection MOT Cleaning Opening of MS Strainer & HRH Condenser flood test 1 2 3 4 5 Electrical 6 7 8 9 10 11 12 1 2 3 4 5 C&I 6 7 8 9 10 11 12 1 2 3 4 5 Off Site 6 7 8 9 10 11 TMD TMD TMD TMD TMD TMD TMD TMD TMD TMD TMD TMD TMD TMD BMD BMD
3
1
0
1
1
3
LMIs Approved
199
141
117
117
117
Jan'09
Mar.'09
Remarks
--
Total
114
114
114
Nil
Sl. No 1 2
Subj ect Power Station Drainage Code of Practice for Power Plant Chemistry
Cycle Chemistry Guidelines for Startup, Shutdown and Layup Practices Guidelines for Inspection & Maintenance of Structures/Buildings in the Vicinity of Corrosive Chemicals, Insulator Protection in Polluted Atmospheres Operating Guidelines for Valve Regulated Lead Acid Batteries
Mar-05
Oct-99
5 6
Jan-97 Oct-00
8 9 10
The Examination, Maintenance, Safety & Handlimg Aspects of Phosphate Ester Fire Resistant Hydraulic Fluids Control of PFA Agglomerate Emissions from Coal Fired Power Fire Resistant Fluids for Control Systems-Avoidance of Mixing Guidelines for Operation Review Team (ORT) Meeting
Jan-00
18.0
SYSTEM HEALTHINESS
CONTENTS
Contents:
18.1 STATUS OF PROTECTION & AUTO LOOPS: 18.2 STATUS OF PROTECTIONS CHECKING & AVAILABILITY: 18.3 DETAILS OF AUTO LOOPS NOT IN SERVICE: 18.4 CONVEYOR PROTECTIONS AVAILABILITY: 18.5 DETAILS OF TESTING OF TURBINE: 18.6 TURBINE GOVERNING SYSTEM: 18.7 DETAILS OF ELECTRICAL TESTING (During the month): 18.8 STATION BATTERY SYSTEM 18.9 ACTION PLAN FOR ANY ABNORMALITY IN THE BATTERY SYSTEM: 18.10 TRANSFORMERS DGA TEST STATUS
(Continuation)
SYSTEM Protection (Total-Nos) Protection (In service -Nos) Auto Loops (Total- Nos) Auto Loops (In service- Nos) UPS Total- No.s UPS in service-No.s CMC/Runback System (in service) Y/N U-7 U-8
UNIT 1
Protection
20.08.2009
20.08.2009
31.08.2008
2 3 4 5 6 7 8 9 10 11 12
UNIT
05.09.2009
03.06.2007
19.06.2009
05.09.2009
05.09.2009
1.65/2.1 ------> (31.08.2009) Bolt 1&2 respectively. 2.3/2.35------> (05.09.2009) Bolt 1&2 respectively. 2.2/2.35------> (05.09.2009) Bolt 2&1 respectively.
UNIT 1 2 3 4 5 6 7 8 9 10 11 12
GT#1,2,3,4,5 UAT# 1A/B, UAT#2A/B, UAT#3A/B, UAT#4A/B, UAT#5A/B, ST#1,2,3,4 GEN#1,2,3,4,5 GT#1,2,3,4,5, KV Switchyard, 1,2,3,4,5 220 15.75 Kv bus duct-
Nil.
Nil
238
238
237
*Note: ORT Cordinator to check the above aspects personally (at random)
Action plan PR Raised. PR No.100019576,Dt.21/04/0 4000027146 placed to M/S Exide PO No. 4000005984,Dt.08/08/08
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
GT-5 GT-6 GT-7 GT-8 GT-9 GT-10 GT-11 GT-12 UAT-1A UAT-1B UAT-2A UAT-2B UAT-3A UAT-3B UAT-4A UAT-4B UAT-5A UAT-5B UAT-6A UAT-6B UAT-7A UAT-7B UAT-8A UAT-8B UAT-9A UAT-9B UAT-10A UAT-10B UAT-11A UAT-11B UAT-12A UAT-12B TIE TIE STATION STATION
Done
Done
Done Done Done Done Done Done Done Done Done Done
Done Done Done Done Done Done Done Done Done Done
U-4 33 33 21 21 2 2 Y/Y
U-5 33 33 35 35 2 2 Y/Y
U-6
U-9
U-10
U-11
U-12
Action plan
Responsibility
Target Date
Reason
Action plan
Responsibility
Target Date
20.0 CHP
in service
Action Plan
Responsibility
Target Date
ACTUAL OVER SPEED TEST TDBFP-A TDBFP-B Speed, rpm Date Speed, rpm
3245
18.08.2009
NA
NA
NA
3339
06.03.2008
NA
NA
NA
3331
19.06.2009
NA
NA
NA
3284
28.04.2009
NA
NA
NA
3269
28.11.2008
NA
NA
NA
Responsibility
Target Date
Corrective Actions
Responsibility
Target Date
Nil.
Nil
Nil
Nil
Unit 3
BANK2
Unit 4
BANK1
Unit 4
BANK2
Unit 5
BANK1
Unit 5
BANK2
237
238
238
237
238
ERY SYSTEM:
Responsibility DGM(EMD DGM(EMD) Present Status in last O/H in May'09 these banks Dec'09 shown 100% capacity due to Next unit2 O/H , Aug- Material Awaited Sept'09 Target Date
000005984,Dt.08/08/08
SEP
OCT
Done
Done
Done
Done Done Done Done Done Done Done Done Done Done
Done Done Done Done Done Done Done Done Done Done
Done Done Done Done Done Done Done Done Done Done
TDBFP-B Date
Responsibilit y
Target Date
NA
NA
NA
NA
NA
UPS UNIT3
UPS UNIT4
UPS UNIT5
SWYD 1
SWYD 2
418
423
419
421
420
420
419
237
237.5
NOV
DEC
JAN
FEB
MAR