MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION (A Government of Maharashtra Undertaking)

SECTION-I STANDARD CEMENT CONSUMPTION Item No. Name of Work Rate of Cement consumption in bags. 3.10 / Cum 4.10 / cum. 5.20 / cum. 6.20 / cum. 7.00 / cum. 8.20 / cum. 9.90 / cum 1.40 / cum. 1.09/cum 1.70 / cum. 2.10 / cum. 1.15 / cum. 1.40 / cum. 1.70 / cum. 0.28 / m2. 1.70 / cum. 2.00 / cum. 2.50 / cum. 1.90 cum. 2.30 / cum. 2.80 / cum. 2.15 / cum. 2.60/ cum. 3.20 / cum. Remarks Lower limit Remarks Upper Limit 3.40 4.40 5.50 6.50 7.30 8.50 10.20 ------------------------------------

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

C.C. M-75 C.C.M-100 C.C. M-125 C.C. M-150 C.C. M-175 C.C.M-200 C.C. M-225 Brick masonry 2nd class in CM 1:6 without pointing a) Brick masonry 2nd class in CM 1:8 without pointing b) Brick masonry 2nd class in CM 1:5 without pointing c) Brick masonary 2nd class in CM 1:4 without pointing Brick masonary 1st class in CM 1:6 without pointing Brick masonary 1st class in CM 1:5 without pointing. Brick masonary 1st class in CM 1:4 without pointing 115 mm thick Brick masonary CM 1:3 UCR masonry in CM 1:6 UCR masonary in CM 1:5 UCR Masonary in CM 1:4 (35% mortar to be used) UCR masonary CM 1:6 without pointing ( 40 % mortar to be used ) UCR masonary CM 1:5 without pointing (40 % mortar to be used) UCR masonary CM 1:4 without pointing ( 40 % mortar to be used ) UCR masonary CM 1:6 without pointing (45 % mortar to be used). UCR masonary CM 1:5 without pointing ( 45 % mortar to be used) UCR masonary CM 1:4 without pointing ( 45 % mortar to be used).

2.80 3.80 4.90 5.90 6.70 7.90 9.60 -----------------------------------

44
Contractor Executive Engineer

MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION (A Government of Maharashtra Undertaking)


25 Laterite stone masonary with 18% mortar in CM 1:6 Laterite stone masonry with 18 % mortar in CM 1:5 Laterite stone masonry with 18 % mortar in CM 1:4 Laterite stone masonry with 18 % mortar in CM 1:3. Coursed rubble masonry second sort in CM 1:6 without pointing mortar 30 % Coursed rubble masonry second sort in CM 1:5 without pointing. Coursed rubble masonry second sort in CM 1:4 without pointing. Random rubble masonry second sort in CM 1:6 without pointing Random rubble masonry second sort in CM 1:5 without pointing Random rubble masonry second sort in CM 1:4 without pointing. Pointing to stone masonry CM 1:3. Pointing to brick masonry in CM 1:3 Cement Plaster in CM 1:3 6mm thick 12 mm thick. 20 mm thick 25 mm thick 40 mm thick 35 36 37 38 39 40 41 42 43 44 45 46 Shahabad stone paving on 25mm thick cement mortar 1:4 Shahabad stone paving on 25mm thick cement mortar 1:6. IPS flooring 40mm thick M-150. Cement or marble mosaic tiles or glazed tiles flooring on 20mm thick bed in CM 1:4. Barbed wire fencing. Hollow Concrete Block 200mm Block masonary CM 1:6. Hollow Concrete Block 100mm Block masonary CM 1:3 Kaddappa Sill Tandoor and Marble mosaic treads and risers. RCC Grill fixing Vitram tile and dados Providing water proofing with BB. Coba average 100mm thick with IPS finish. 0.85 / cum. 1.00 / cum. 1.30 / cum. 1.70 / cum. 1.40 / cum. 1.70 / cum. 2.10 / cum 1.55 / cum. 1.85 / cum. 2.30 / cum. 0.05 / sq..m 0.03 / sq.m. 0.07 / sq.m. 0.13 / sq.m 0.20 / sq.m 0.28 /sq.m. 0.40 / sq.m. 0.35 / sq.m. 0.30 / sq.m. 0.30 / sq.m. 0.30 / sq.m. 0.10 / RM. 1.20 / Cum. 1.20 / cum. 0.05 / RM. 0.80 / sq.m. 0.10 / sq.m. 0.45 / sq.m. 0.50 / sq.m. ----------------------------------------------------------------------------------------------------------------------------

26 27 28 29 30 31 32 33 34

45
Contractor Executive Engineer