a)The name, location and address of the project/s being b)Development size in sq ft and land extent of the entire development in acres. c)Dimensions of the plot area on which the blocks offered to the Client will be built in sq ft. d)Built up area of the block / buildings offered to the Client in sq ft. e)Building efficiency as a __% of the super built up areas vs. the usable carpet area. Please specify what constitutes in the calculation of common area f)The list of statutory approvals for the project.

Developer Responses Built to Suit Lease Built to Suit Purchase


4,57,085 sqft (Total saleable area) - 8.96 Acres 79.35X115.96 (Basement extent) irregular plot shape 4,57,085 sqft (Total saleable area)

1.DEVELOPMENT DETAILS

overall efficiency above 80%

2. LEGAL STRUCTURE

3. SITE TOPOGRAPHY AND FLOODING RISK

4. DESIGN AND DRAWINGS

g)Current & future status of development (with timelines as applicable). h)Overall master plan & space plan of the development along with CAD drawings of the proposed space. (a)Please provide full particulars about your legal structure viz. (b)That the Developers have good title and have the right and authority to grant a lease in respect of any space being offered for Clients use. confirm that the Developers have leasehold rights (c) Please over the said Land and the Developers are entitled to construct the Buildings and lease the Spaces to the Lessee and no other person has any interest, claim or title whatsoever in the said Land and/or the Project. (d)Kindly confirm that there are no legal litigations and appeals pending related to the land and all statutory approvals and compliances for the building have been obtained as per local byelaws, life and fire safety norms (NFPA, NBC) Attach Soil Testing Report; if available Developers shall confirm the buildings ground floor and all technical spaces are above the highest known flood point for the site, or provided details of the flood water management system deployed in their development Excavation completed retainig wall & column footing in Please confirm if the building is under construction or already constructed. If not, please a)The Client would require the option to discuss, comment and make changes to the current plans to meet its desired objectives. b)Please provide a detail Microsoft Project Plan for the construction and completion of the Cold Shell + Warm Shell. Minimum 1.5 KVA / 100 sq ft (including power for comfort AC, AHUs, common area services) for the proposed area. Specify floor to floor free and clear heights and floor loading provided. Please specify the number of sewage treatment plants (STP) or if dedicated to the block/blocks offered to the Client. a)Municipal supply connection. Power @ 1 KVA / 100 sq ft (including power for comfort AC, AHUs, common area services) for the proposed area. 3.90 mts (floor to floor ht.) 1 dedicated STP offered for each builidng Yes considered, Municipal water supply connecting to individual UG sumps. Under Ground Sump Capacity : - Building -01 1. Fire water sump - 260 Cum. 2.Raw water sump - 75 Cum. 3.Treated water sump - 75 Cum. 4.Roof top water sump - 50 Cum. Building 02 :1. Fire water sump - 260 Cum. 2.Raw water sump - 145 Cum. 3.Treated water sump - 145 Cum. 4.Roof top water sump - 65 Cum. Building -03 :1. Fire water sump - 260 Cum. 2.Raw water sump - 105 Cum. 3.Treated water sump - 105 Cum. 4.Roof top water sump - 65 Cum. Over head tank Capacity : - Building -01 1. Fire water tank- 60 Cum. 2.Domestic water tank- 5 Cum. Building -02 :1. Fire water tank- 60 Cum. 2.Domestic water tank- 5 Cum. Building 03 :1. Fire water tank- 60 Cum. 2.Domestic water tank- 5 Cum.

5. SPECIFICS OF THE DEVELOPMENT 5.1 Power 5.2 Floor Height and Loading per building

b)Capacity of underground / overhead storage tanks. (Raw water tank, Filter water tank, Fire water tank, Rain water and any others). 5.3 Sewerage, drainage & water supply

c)Rain Water Harvesting. d)External Sewerage Connection. e)External Water Connection. f)Bore well (number & yield in gallon per hour). g)Please specify if there are any kinds of limitations or restrictions on the supply of water to the demised premises on a 24 hour basis. Please provide details on: a)Secure and dedicated points. b)Riser Infra structure. c)Space provision on the terrace at no extra cost for any equipment that the Client may require. a)Please provide details and locations of food court and number of counters), fine dining restaurants, super market, day care centre, ATM's , b)Other amenities. c)Transport facilities to the development. d)If there is a separate utilities block (which will contain diesel generators, chillers etc.) please specify the proximity in which it will be located from the offered building. a)Architects statement for the super built-up, built-up, carpet area b)Complete set of base building construction and specification documents. c)Status of restrooms (finished / unfinished). d)The treatment on all windows (film and laminations, blinds, roll-up shades, etc.). e)Status of interior walls. f)Status of floor slab. g)Slab to slab height for Client floors, basement, car parks, mezzanine & penthouse. h)Total number of reserved car parks and the ratio of covered to uncovered car parks for 4 wheelers & 2 wheelers along with the costs. i)Details of all external fire paths and keep clear routes. j)Detail of the staff path to and from any parking structure not directly adjacent to the building, e.g., how does staff move from the car park to the building without getting affected by extreme weather - during the monsoons. k)Occupancy Certificate details. l)Details of approval from AAI (Airport Authority of India) regarding the height of the premises.

Yes considered Yes considered, Sewerage lines connecting to individual STPs. Yes considered, external water supply connecting to individual UG sumps. As per the site condition & Client requirements Check with lassoing team

5.4 Telecommunication

5.5 Support / project amenities and facilities in the development

Please refer the attached sale area statement.

6. PREMISES DETAILS

745 car parks covered (75 regular , 670 stack) 35 surface external parking

54 mts

a)Floor plate sizes in sq ft and number of levels. b)Column pacing/grid. c)Floor to ceiling height (clear height) offered on all floors (Near Slab & Capital Area in mm).

Please refer the attached sale area statement. 11 mts c/c 3900 finish to finish/75mm screed/500 mm capital/260mm slab thickness (clear ht. 3565mm below slab & 3325 below capital)

d)Structural floor loading capacity of the leased premises expressed in Kgs/ m. 400 kgs/m2 e)Finishing in the common areas main staircase, fire staircases, main lobby on ground floor, lift lobbies on all floors, washrooms and pantries. f)Whether the premises has been designed for adequate earth quake Yes the premises is designed for adequate earth quake resistance as per the NBC Zonal norms. resistance as per the NBC Zonal norms. g)Lightening protection for the premises. Provisioned h)The list of Clients that currently occupy or have committed space in the premises (i.e. Client Profile). i)Any deviations in the construction of the premises from the specifications, and the sanctioned plans, that have not been regularized by the applicable authorities. Please confirm if the building has been built as per sanctioned plan. j)Please confirm the locations of DG sets, Chillers, run of chilled water, transformers, electrical panels etc. D.G'S, Electrical Panels are provisioned in the basement, Chillers on the Partial terrace on 12th floor with dedicated Chilled water shafts & tge Transformers are planned in the the external.

7. BUILDING REQUIREMENTS

8. BASEMENT

a)Please specify usage for parking, elevator lobbies and UPS utilities b)Please specify the number of basement levels as topography allows and if ventilated as per code requirements. 2 Basement levels are planned . Building Plinth is raised by 150mm from the external podium levels d)Please provide a defined route for service vehicles into and out of a)Please specify provision/seating capacity and area in sq ft and b)Please confirm location defined for Caf. c)The Client would prefer a dedicated service lift provision for cafeteria space in terrace for the movement of vendor and its materials if incase terrace is an option for caf. Please confirm if the Caf/ staff facilities can be located on the terrace level, if so, please confirm, which passenger and service lifts service that level and also what is the occupancy load allow by fire regulations. All necessary set up should be provided for setting up of open flame live kitchen in the caf, and all necessary statutory approvals should be obtained. Service lift provision done with the Present planning d)Other amenities, if any. c)Elaborate on building plinth and height of formation level Specification of internal and external finishes. External finished with Structural glaxing & clay tile cladding. 2 Nos. of 2500 kVA transformer with space provision for 1 No. 2500kVA in future. Total MD 4571 kVA. Yes distribution panels provided in each floor.

9. STAFF AMENITIES

10. FINISHES SPECIFICATION

a)The transformer capacity of the premises in Amps and if distribution panels are provided on each floor. 11. MAIN CABLING & ELECTRICAL WORKS

b)In case Client requires extra power apart from the assigned load by the Developer what are the additional power/ back up power costs per Prestige to Comment. KVA and the percentage of the deposit which would be refundable at the end of the Lease tenure. a)Wet Riser Mains, Hydrants and Fire Water Storage Tanks (Specify if Provided Wet riser & down comer system from b)Fire Pumps/Wet Riser Pumps c)Hose Reel/Hose Reel Cabinets (Specify if on each floor) d)Common Area and Internal Fire Alarm systems (Smoke Detectors, Break Glass Detectors etc.) e)Common Area and Internal Sprinkler System Works f)PA System/Hooter System g)Statutory requirements that the equipment complies with Fire Fighting standards h)Pre action systems to be provided in the areas which would be earmarked for server and lab areas (if any) i)External fire fighting infrastructure and systems. a)Number, brand, capacity in kgs and speed in mtrs/ sec of b)Service Certification Details. c)Service Lift. a)Please confirm that you will be able to meet all the requirements for b)Type & capacity of air-conditioning provided - water-cooled or aircooled. (Please specify if in line with LEED requirements). c)Space provision (additional) if the Client would like to place their chiller unit. a)Total back-up capacity in KVA being provided 15. DG SET / UPS b)Numbers and brand of the DG sets / UPS to be provided. Provided one set of fire pumps with 3 nos of wet risers. Yes considered on each floor Yes considered on each floor & entire building Yes considered on each floor & entire building Yes considered on each floor common area only Yes considered NO Yes considered 5 nos. of 20 Passenger lifts & 1 service lift provisioned 1 NO. Provisioned

12. FIRE FIGHTING EQUIPMENTS: DETAILS OF THE PROVISIONS MADE

13. SERVICE LIFTS, LIFTS & ESCALATORS

14. AIR-CONDITIONING PROVISIONS

4500 kVA 3 Nos. of 1500 kVA DG sets with space provision for 1 No. 1500 kVA in future. Make:- Powerica. No UPS considered.

a)Security control system in the premises. New age and b)Centralized smoke detection and fire suppression system available in the premises. c)In case of premises maintenance by the Developer or an appointed maintenance agency of the Developer, provide the following details: a)Basis of calculation of maintenance b)Inclusions to the maintenance c)Exclusions to the maintenance 16. PREMISES MANAGEMENT & MAINTENANCE d)Regular premises working hours. e)In case of requirement of services beyond the regular working hours, i.e. airconditioning, power back-up, elevators, all essential services, charges for the same. f) Kindly note that the maintenance charges should calculated for a 24/7 operations schedule and the Developer should have no objection for 24/7 (The scope of services for thea above quoted maintenance charges can be enclosed if available). 17. FACILITIES FOR DIFFERENTLY-ABLED AS PER NATIONAL Confirm the availability of Facilities like handicap access ramps, grab rails, handicap toilets AND / OR INTERNATIONAL NORMS etc in each building / block. Yes the facility is Physically challenged friendly. 18. STORAGE FACILTIES Confirm on any provisions centrally or exclusively for the Client for stores & Debris. Please confirm that the Client will have terrace rights to install telecom related equipment 19. TERRACE RIGHTS for smooth running of its operations at no additional rent. Please confirm that the Client will have the right to use its standard graphics at the various 20. SIGNAGE RIGHTS/ GRAPHICS Signage rights on premises facade or monument directory common to occupants if building offered is a part of a larger park. a)Provide an estimate of the timeframe. b)Procuring of Occupancy Permit and any other relevant authorization to enable the Client to commence operations from the premises. c)Handover of the premises to the Client for commencing IT d)Handover of the premises for occupation with fit outs, with commissioning certificate for DG / Chillers and all the services. 21. SCHEDULE OF HANDOVER e)Premises completion in all respects and all Developer led teams exiting the site. f)Completion & commission confirmation of all Services facilitated by Client by the Clients architects & consultants before the fitCompletion out start. & commission confirmation of all Restroom's g) facilitated by Client by the Clients architects & consultants before the fit out start. a) Hard option area that can be kept on hold for the Client in b)Holding cost attached, if any. 22. EXPANSION OPTIONS c)First Right of Refusal to the Client for all vacancies as & when they arise, in the premises. Feasibility of provision and associated terms and conditions with timelines as per Client 23. INCUBATION SPACE specs Lease Option a)Lease tenure and renewal options (in years). b)Notice periods for termination and for renewal. c)Warm shell rental (along with fit out rental should the Client want the Developer to fit out). d)Definition of Warm Shell being provided. e)Rent Effective Date (Rent Free Period). 24. FINANCIAL PROPOSAL f)Interest free refundable security deposit (in months). g)Lock-in period if applicable. h)Rent Reviews. i)Any car parking charges. j)Maintenance charges. k)Review or escalation on maintenance charges. l)Please specify if maintenance is outsourced or if internal. 25. FINANCE FOR PROJECT Please outline how the project is being financed. Please confirm that the firms in competition to the Client shall not lease any space in the Symantec, Microsoft, Trend Micro, Fire Eye, Cisco, Bluecoat etc. 26. NON COMPETE Please also confirm that no space shall be leased in the premises to an entity which has a joint venture/ partnership or tie-up of any nature with any company/ companies identified. 27. DEVELOPER TRACK RECORD AND REFERENCES Please provide names and references of Clients for whom you have undertaken a similar venture. Please confirm that during negotiations for the premises under question, Client shall be Also please confirm that no other real estate agents would be involved in this process from your side. All statutory taxes with respect to the development to be borne by the Developer The Validity of the offer shall be for 3 months from the date of submission of the RFP response.

28. TRANSPARENCY 29. TAXES 30. VALIDITY