Vous êtes sur la page 1sur 28

g

GER-3751A

GE Power Systems

Understanding, Diagnosing,
and Repairing Leaks in
Water-Cooled Generator
Stator Windings

Joseph A. Worden
Jorge M. Mundulas
GE Power Systems
Schenectady, NY
This article is for information purposes only. The operation of individual plants involves many factors beyond GE’s con-
trol; it ultimately rests with the plant’s operator/owner. GE disclaims any responsibility for liability for damages of any
type, i.e. direct, consequential or special that may be alleged to have been incurred as result of applying this information
regardless of whether the claim is based on strict liability, breach of contract, breach of warranty, negligence, or otherwise.
Understanding, Diagnosing, and Repairing Leaks in Water-Cooled Generator
Stator Windings

Contents

Abstract . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
General Considerations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
Leaks in Stator Hydraulic Components and Connections. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
Leaks in the Stator Bar . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
Leaks in the Clip Window Braze . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
Leaks Through Porosity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
Leaks in the Clip-to-Strand Connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
Leaks Through Serrated Spacers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Leaks Initiated by Mechanical Causes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Erosion in Hollow Conductors. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Modern Winding Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
Leak Descriptions and Definitions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
Stator Winding Leak Testing Methods . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
On-Line Leak Testing Methods . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
Monitoring YTV System Vent . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
Stator Leak Monitoring System (SLMS) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
Off-Line (Maintenance) Leak Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
Stator Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
Hydraulic Integrity Test (HIT) Skid . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
Vacuum Decay Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
Pressure Decay Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
Helium Tracer Gas Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
Stator Bar Capacitance Mapping Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
Summary of Recommended Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
Industry Experience . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
Stator Winding Leak Repair Methods . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
Component Replacement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
Braze/TIG Repair . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
Epoxy Injection Repair . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
Long Term Leak Solutions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
Global Epoxy Injection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
Full Stator Rewind . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17

GE Power Systems GER-3751A (08/01)


■ ■ i
Understanding, Diagnosing, and Repairing Leaks in Water-Cooled Generator
Stator Windings

Conclusion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
Questions & Answers. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
Appendix . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
Crevice Corrosion Leak Testing Decision Tree . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
References. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
List of Figures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
List of Tables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23

GE Power Systems GER-3751A (08/01)


■ ■ ii
Understanding, Diagnosing, and Repairing Leaks in Water-Cooled Generator
Stator Windings

Abstract impact of a stator insulation failure on genera-


tor availability demonstrates the importance of
In May 1991, GE issued TIL-1098 which recom-
a thorough, routine leak testing and repair plan
mended routine maintenance testing of water-
that includes stocking of long lead-time winding
cooled stator windings for leaks. Leaks in the
components.
generator water-cooled stator winding can
affect machine availability and insulation life. The first goal should be to detect and locate
The keys to minimizing the negative impact of a leaks within the winding before they cause
leak are early detection and timely repair. irreparable damage to the stator bars.
Routine leak testing of the stator winding is the The second, and equally important goal, is to
best way to determine the existence of leaks. repair those leaks with a process that will have a
Leak tests, such as Vacuum and Pressure Decay minimal effect on outage length while at the
tests, and use of the Stator Leak Monitoring same time will provide a high level of confi-
System (SLMS), help detect larger leaks. A dence for service life.
more sensitive test, such as Helium Tracer Gas While TIL-1098, "Inspection of Generators with
Testing, is necessary to find smaller leaks. If Water-Cooled Stator Windings" provides impor-
leaks are located prior to insulation damage, tant guidance to further improve the generator
they can be repaired and the unit returned to reliability, this paper:
service.
■ Provides information about the
Stocking of stator winding and hydraulic com-
development of water leaks
ponents plays an important role in reducing
repair time for those cases where winding dam- ■ Describes the recommended testing
age has occurred as a result of water leaks. methods and maintenance practices

This paper provides information about the ■ Suggests repair options


causes of water leaks, recommended testing
methods and maintenance, and possible repair General Considerations
options. During operation, the stator winding is subject-
ed to an environment of thermal shocks, cyclic
Introduction duty, corrosion, mechanical vibration, and elec-
Stator bar insulation failures that occur in serv- tromagnetic stresses, where the potential for
ice can cause extensive collateral damage to the damage and methods of leak detection, are very
generator stator core and field. This can extend different. Water-cooled stator windings have
a forced outage several months, depending thousands of brazed joints that are potential
upon the extent of the damage. Insulation fail- sources of leaks.
ures during routine electrical testing can still Windings and components are carefully tested
have a great impact on the maintenance outage for leakage throughout the manufacturing
scope and duration. However, those repairs are process. However, leaks can develop after a peri-
typically shorter in duration than with an in- od of service. Your local GE representative can
service failure. provide a copy of related publications, supply
Wet insulation is the most common cause of fail- additional information, and provide qualified
ure for water-cooled stator bars. The severe technicians and specially designed equipment

GE Power Systems GER-3751A (08/01)


■ ■ 1
Understanding, Diagnosing, and Repairing Leaks in Water-Cooled Generator
Stator Windings

to perform the recommended tests and inspec- ■ Inlet/outlet headers, nipple


tions. In particular, GE publication GEK- connections
103566, "Creating an Effective Maintenance ■ Liquid-cooled high voltage bushings
Program," contains a listing of standard tests and connections
and other recommendations for generator
■ "P" bar liquid connections and hoses, if
maintenance.
applicable
At the start of an outage and prior to degassing
the generator, the stator cooling water system Figure 1 depicts a typical stator end winding con-
should be removed from service. This is to min- figuration. Small leaks in these locations typi-
imize the potential for water ingress from water cally will not result in winding damage so long
leaks into the stator. as hydrogen gas pressure is maintained above
the stator cooling water pressure. However, cap-
Leaks in Stator Hydraulic Components illary action can cause water to leak from a bar
and Connections even though gas pressure is maintained higher
Leaks in the generator stator hydraulic system than the cooling water pressure. Larger leaks
may originate at any of the following hydraulic can be detected by on-line testing methods and
components: Vacuum and Pressure Decay Tests, which are
■ Copper tubing, pipes, piping discussed in more detail later.
connections, elbows, fittings, sleeve Even extremely small water leaks can be detri-
joints, tube extensions, connection mental if allowed to persist. This is particularly
sleeves the case if the stator water system is left in opera-
■ TeflonTM hoses and hose fittings tion during outages when the generator is
degassed. Under these circumstances, the pres-
■ Liquid cooled series loop brazes sure differential provides the greatest drive for
■ Connection rings water to be forced into the groundwall insulation.

Header

Electric and Hydraulic


Connection

Bar Clip
Teflon
Hose
GER3751-1

Hydraulic
Connection Stator Bar

Figure 1. Typical stator end winding configuration

GE Power Systems GER-3751A (08/01)


■ ■ 2
Understanding, Diagnosing, and Repairing Leaks in Water-Cooled Generator
Stator Windings

Leaks in the Stator Bar dence discovered here revealed a leak process
that initiates in the braze alloy at the inner sur-
Leaks in the Clip Window Braze face (a crevice corrosion mechanism). Under
During the manufacturing process, a window in the right conditions the leak can change to cor-
the clip provides access for the mechanical rosive penetration of adjacent copper (phos-
assembly of the clip to the strand package. A phoric acid attack), with a limited depth and
cover is brazed to the clip and strand package cross section.
during the clip assembly. Though unlikely, GE's analysis of the crevice corrosion phenome-
braze joints for this cover could potentially be a non in clip-to-strand braze joints shows it to be
source of leaks. a two stage process:
Leaks Through Porosity ■ Phase 1. The first stage of the corro-
sion process consists of corrosion of
One of two types of clips (leaf or bottle type) is
the braze alloy inside the clip at the
brazed to the ends of water-cooled stator bars.
strand ends. Water works its way into
Modern leaf or bottle clips are machined from
existing small voids at the braze surface
solid copper blocks, assuring excellent quality
(due to the "spongy" nature of the
and mechanical integrity of the copper clip.
braze) and stagnates. If conditions are
However, older machines were built with cast
right (i.e. void size), crevice corrosion
clips. Some of the hydraulic plumbing compo-
of the braze takes place attacking the
nents used on older units with bottle clips were
phosphorus rich phase of the braze
also cast. These cast components may develop
alloy. Initial void sizes increase as
leaks in localized areas of high porosity.
material corrodes. The water chemistry
Leaks in the Clip-to-Strand Connection changes to phosphoric acid as a result
A clip-to-strand braze connection is made of crevice corrosion of the braze alloy.
between the stator strands and the bar clip. This The Phase I process is limited by the
braze connection is made and leak-tested dur- crevice reaching critical volume, solution
ing stator bar manufacturing. chemistry and precipitating out phos-
A number of leaking clips have been analyzed phate salt along the surface of the braze,
from different generators. The leak paths in which slows/stops further corrosion.
each of the clips analyzed were similar. In each ■ Phase 2. The second stage of corrosion
case, the cross-sectional size of the leak path begins if the copper strand is contacted
stayed relatively constant over its entire length. by the void as it grows. This causes a
This indicates that the depth of the penetration corrosive attack of the copper strands
into the copper and adjacent braze was indeed by the phosphoric acid solution
limited. However, the corrosion mechanism was created by corrosion of the braze alloy.
able to continue by driving down the length of The corrosion of the copper strands
the copper strand. This, coupled with the selec- takes place preferential to the braze
tive attack of the phosphorous-rich braze alloy, alloy and at a higher rate. The depth
indicates that the corrosion reaction needs into the copper is limited and roughly
phosphorous to "fuel" the process. The evi- constant (approximately 0.015 inches),

GE Power Systems GER-3751A (08/01)


■ ■ 3
Understanding, Diagnosing, and Repairing Leaks in Water-Cooled Generator
Stator Windings

partly by the precipitation of are starting to experience leaks from crevice


phosphate salt on the copper, and corrosion along the spacer clip braze joint after
partly by the volume of the liquid thirty years of operation.
becoming too large to maintain the
Leaks Initiated by Mechanical Causes
critical acid concentration.
The end winding support system is designed to
The corrosion mechanism changes (due
move as one assembly. When signs of greasing
to a change in water chemistry) and the
or dusting are detected it is an indication that
phosphorus-rich phase of braze is again
there is relative motion between components.
attacked. Then, as the solution chemistry
Depending upon the location and severity of
changes due to phosphorus being added
observed movement, corrective action may
to the solution, preferential attack of the
need to be taken immediately in order to
copper occurs. The mechanism switches
reduce the risk of a high cycle fatigue failure of
back and forth from crevice corrosion of
the copper plumbing. These types of leaks will
the braze alloy to acid attack of the cop-
result in a noticeable change in the amount of
per as the leak path makes its way down
hydrogen detected in the YTV vent (the typical
the strand. Figure 2 illustrates the crevice
name for the vent line to the atmosphere) from
corrosion process.
the stator cooling water storage tank. (See Figure
3.) When this type of failure occurs on the inlet
Leaks Through Serrated Spacers
side of the cooling system, cooling water can be
Stator bar clips in the 1960s used a "serrated displaced by hydrogen in the stator bar.
spacer clip" design. This design did not use Excessive bar temperatures may result leading
foam metal alloy filler and did not have high to insulation failure.
levels of porosity in the clip to strand braze
joint. The initiation and development of crevice Erosion in Hollow Conductors
corrosion in the "serrated spacer clip" design Water flow through the stator bar hollow con-
has been a much slower process. These units ductors may result in some erosion of the cop-

Voids in "Spongy" Selective Attack


Area of Braze of Cu3 P
WATER BOX

Copper Strand
GER3751-2

Cooling Water

Copper Strand Brazing Metal


1) Solution at braze surface (inlet water)
2) Water works its way into voids in braze and stagnates
3) Crevice corrosion of braze (primarily Cu3P)
4) Critical solution or surface area conditions met, and Cu corrodes
5) Solution/surface area conditions change favoring braze corrosion
6) Solution/surface area conditions change favoring Cu corrosion
7) Leak drives down the bar to outer surface

Figure 2. Crevice corrosion mechanism

GE Power Systems GER-3751A (08/01)


■ ■ 4
Understanding, Diagnosing, and Repairing Leaks in Water-Cooled Generator
Stator Windings

GENERATOR
YCD YCF FRAME

COLL
END

TURB.
END
OUTLET INLET
HEADER HEADER

YTV
VENT
YCFD YCFD

LIQUID
DETECTOR

YST-1
WATER
STORAGE
TANK

GER3751-3
PUMPS

COOLERS

Figure 3. Stator cooling water system


per. However, for GE generators operating MicapalTM II exhibit excellent
under normal conditions, the rate of erosion is toughness, durability, and resistant to
quite small, and will not impact operation over externally applied chemicals,
the life of the winding. GE water-cooled gener- moisture, oil, and other contaminants
ators have not experienced a forced outage or ■ Operation with gas pressure higher
required a stator rewind as a result of erosion. than water pressure, which, in case of
a leak, results in hydrogen flowing into
Modern Winding Design
the stator bar, and, from there, to the
Modern winding design provides resistance to YTV vent.
water damage. Four design features minimize
■ Use of machined copper fittings.
water-leak related damage to the generator
winding insulation during operation and ■ Improvement in brazing processes.
between maintenance tests:
■ Inherent resistance of modern stator Leak Descriptions and Definitions
bar insulation systems to water There are a number of unknowns, variables,
damage. Stator bars insulated with and assumptions that are made when discussing

GE Power Systems GER-3751A (08/01)


■ ■ 5
Understanding, Diagnosing, and Repairing Leaks in Water-Cooled Generator
Stator Windings

leaks and their effects. Development of leaks, detected "leak" is the result of one "large" leak,
rate of growth, and effects, are dependent upon or several "smaller" ones.
variables in operation, manufacture, and mate- Maintenance testing, on the other hand, has the
rials. These variables make it difficult to deter- capability of locating individual leaks as small as
mine a "critical" leak size, water migration rates, 10-5 std. cc/sec. Under the same conditions as
and other parameters. When making these cal- the "large" leak, this size leak would pass about
culations, it is assumed that the ideal gas and 10 std. cc/year. The size of a leak necessary to
fluid equations apply. An in-depth analysis of cause stator bar insulation failure is believed to
the crack propagation or fluid flow is beyond be on this order. Continued operation will only
the scope of this paper. increase the magnitude of the leak. The rate of
Leaks encountered in braze and weld joints typ- this growth is a function of many variables
ically fall between 10-5 and 10-2 std. cc/sec. including location, material properties, and
Leaks below 10-7 std. cc/sec will usually be thermal and mechanical stresses.
plugged by the water itself. Bubble Testing and Uncertainties over critical leak size and growth
Vacuum/Pressure Decay Testing are useful for rates has prompted GE’s "early detection and
leaks greater than 10-4 std. cc/sec; more sensi- repair" philosophy.
tive detection tests (such as the Helium Tracer On-Line Leak Testing Methods
Gas Test) are needed for leaks smaller than
On-line testing allows for monitoring of the
that. These values apply for exposed leaks.
winding condition over the period between
Since the majority of leaks occur in the series maintenance tests, but is not capable of isolat-
loop connections, which are covered with many ing individual leaks. However, on-line testing is
layers of tape and epoxy, leak detection still an important part of proper stator mainte-
becomes more difficult as the sensitivities of all nance. Early detection and repair are crucial to
tests are reduced. minimizing the damage that can result from
water within the generator. Periodic monitoring
Stator Winding Leak Testing Methods of these indicators should be a fundamental
part of operating all generators with water-
Stator leak testing can be broken into two dis- cooled stator windings.
tinct categories: on-line testing and off-line (or
Even after the winding has passed routine main-
maintenance) testing.
tenance tests, large leaks caused by component
On-line tests are defined as those tests that do failure or rapid propagation may occur during
not require removal of the generator from serv- operation. Detecting and repairing these leaks
ice. Off-line (Maintenance) tests define the quickly is important to minimizing generator
bulk of the leak tests. These tests require damage. Two fundamental on-line indicators
removal of the generator from service and, in are used to detect stator winding leaks:
some cases, removal of the generator field.
■ The liquid detector alarm. Water found
On-line testing looks at the winding as a whole in the alarm’s drain indicates the
and is not capable of isolating individual leaks. presence of water within the generator.
It is generally impossible to determine if the There may be several sources of this

GE Power Systems GER-3751A (08/01)


■ ■ 6
Understanding, Diagnosing, and Repairing Leaks in Water-Cooled Generator
Stator Windings

water including the hydrogen seal oil checking the YTV vent on weekly basis. For a
system, the hydrogen coolers, stator hydrogen flow rate of 10 ft3 to 200 ft3 per day,
winding leaks, and even wet hydrogen a full set of HIT Skid tests is recommended at
gas due to poor-quality of the gas the next outage. If the flow rate is greater than
supply. 200 ft3 per day, it is recommended that the unit
■ The presence of hydrogen at the YTV be removed from service and source of the leak
vent. (See Figure 3.) If water is found in repaired.
the liquid detector, the YTV vent
Stator Leak Monitoring System (SLMS)
should be checked for hydrogen. The
water is likely to be coming from a GE has developed a Stator Leak Monitoring
stator winding leak if the vent flow test System (SLMS) which is highly recommended
results indicate a problem. If the vent for:
hydrogen flow is "normal", an alternate ■ Oxygenating stator cooling water to
source of water should be explored. the recommended level
■ Monitoring the level of hydrogen
Monitoring YTV System Vent
escaping out of the YTV vent
Excessive hydrogen gas flowing out of the stator
The system consists of a flow meter, gas analyz-
water cooling system vent indicates that a large
er, data acquisition and control system and a sys-
leak within the stator winding is likely. The sta-
tem piping modification package. The SLMS
tor water cooling system is a hydraulically closed
module is mounted at the hydrogen detraining
system except for the YTV vent, which is
tank and connects to a gas analyzer and a flow
designed to allow for water expansion and con-
meter which are added to the existing piping.
traction caused by temperature changes during
The system brings fresh filtered air into the
operation. The deionized water remains aerat-
cooling water to provide a measurable gas flow
ed by virtue of the YTV vent. Since hydrogen
and to maintain the proper water oxygen con-
pressure is normally higher than water pres-
tent (2 to 8 ppm). Figure 4 shows the typical
sure, a leak in the winding may show up as
configuration of the SLMS system.
excessive hydrogen flow through the vent.
Hydrogen pressure inside the generator is the Measurement of the hydrogen content and gas
only possible source of hydrogen to this system. flow provides an accurate measurement of
Accurate measurements of hydrogen flow are hydrogen leakage through the stator winding.
quite difficult and subject to error. Also, some The level of hydrogen leakage is directly related
uncertainty is present when attempting to dif- to a leak in the water-cooled stator winding.
ferentiate between hydrogen flow due to a leak Additionally, SLMS aids in minimizing stator
and that due to TeflonTM hose permeation. bar copper erosion, resin bed damage, rectifier
During operation, the hydraulic hoses can be grounds, and stator winding strand blockage.
the source of up to 2 ft3 of hydrogen flow per
day. Through routine monitoring of the vent Off-Line (Maintenance) Leak Testing
flow, winding leaks can be detected by noting a A periodic off-line stator leak maintenance test
steady upward trend or step increases in hydro- program will indicate the presence of problems
gen flow through the vent. GE recommends and possibly avert failures altogether.

GE Power Systems GER-3751A (08/01)


■ ■ 7
Understanding, Diagnosing, and Repairing Leaks in Water-Cooled Generator
Stator Windings

VENT GAS

PLANT COMPUTER

6 CFD WATER
RETURN

WATER COOLED
STATOR
YTV
SCWS ALARM

WATER
STORAGE TANK
POWER
IN 6 CFD
(110VAC)

SLMS

GER3751-4
System COOLING
Plant Air Supply WATER
6.5 CFM @ 100 psi DRAIN PUMP

AIR INJECTION

Figure 4. Typical Stator Leak Monitoring System (SLMS)

Maintenance testing of water-cooled generator Stator Preparation


stators has been divided into two categories:
Having a dry stator hydraulic system (bars,
■ Tests performed during minor outages headers, fittings, etc.) is essential to performing
(typically every 30 months) Stator Leak Testing. The presence of moisture
■ Tests performed during major outages within the winding can conceal a small leak,
(typically every 60 months) making it undetectable to some leak tests. The
most efficient method of removing water is to
The standard minor outage test program con-
perform a "Stator Blowdown" using very dry air.
sists of a Vacuum Decay Test and a Pressure
There are situations where the last remaining
Decay Test, in addition to visual inspection.
moisture trace within the winding must be
These tests do not require access to the stator
removed by pulling a vacuum on the system,
bore and can be performed with the rotor in
which will "boil off" the water. This is a time-
place, whenever the generator is removed from
consuming process and can be minimized by
service.
performing a thorough blowdown prior to vac-
The standard major outage test program con- uum drying. This process is slow in relation to
sists of Pressure Decay Test, Vacuum Decay Test, blowdown, but is necessary. Typically, if a wind-
Helium Tracer Gas Test and Stator Bar ing has been dried well by blowdown, vacuum
Capacitance Mapping Testing, as well as electri- must be pulled on the winding until it is dry,
cal testing. During a major outage the field is which can take approximately 24 to 36 hours.
removed and this facilitates the performance of
a Helium Tracer Gas Testing and Stator Bar Hydraulic Integrity Test (HIT) Skid
Capacitance Mapping Testing. An outline for To facilitate and expedite the dryout of the
major outage leak testing procedures is given in water-cooled stator windings, as well as the
Figure 5. Vacuum and Pressure Decay Tests, GE has

GE Power Systems GER-3751A (08/01)


■ ■ 8
Understanding, Diagnosing, and Repairing Leaks in Water-Cooled Generator
Stator Windings

Stator Preparation Capacitance Mapping Test

PASS FAIL
Vac & Press Decay
Tests (or HITS)
No Risk of In-
Visually
PASS FAIL Service or
Tracer Gas Test Tracer Gas Test Inspect Series
Electrical Test
Loops and
Failure Due
Winding for
to Wet Stator
Moisture
Perform Winding
Capacitance PASS FAIL FAIL PASS
Mapping
Failed Passed Carefully
Cap Cap Inspect Suspect
Locate Leaks w/Tracer Test Test Series Loop
Sniff or Snoop and Winding
Using
Tracer Gas
Visually Check for
Repair Leaks Moist HydraulicCircuit,
Series Loops,
or Leaks in Locations ELECTRICAL

GER3751-5
Retest with
Tracer Gas
Not Checked w/Tracer TESTING

Retest Vac & Press


Decay (or HITS)

Figure 5. Major outage leak test plan

developed a self-contained, skid-mounted sure, and accurate results can be obtained


equipment, called a "HIT Skid" (Hydraulic in one hour of decay testing. This is much
Integrity Test Skid). Hoses from the skid are less than the typical twenty-four hours required
connected to the generator at specified flanges for a Pressure Decay Test. Ironically the test’s
of the stator. The only external requirement for sensitivity can also be an obstacle to accurate
the skid is a 480 VAC power source at 30 amp. test results. Because the test is so sensitive,
Figure 6 shows a typical Hydraulic Integrity Test extremely small leaks at flanges and other non-
Skid set. welded connections, and the effects of out-
gassing, can result in poor test results. For this
Vacuum Decay Testing reason, it is very important for all connections
Vacuum Decay Testing is a useful tool for deter- to be tight and all components (hoses, connec-
mining the integrity of the entire water-cooled tions, flanges, gaskets, etc.) to be in good con-
stator hydraulic system. The primary advantage dition.
to vacuum decay testing is its sensitivity. Decay Moisture diffused into the copper oxide surface
measurements are made in units of microns. on the stator bars and the walls of the TeflonTM
(See Figure 7.) As a reference, one micron is hoses will outgas at a slow rate. This rate can be
equivalent to 0.00002 psi, which is undetectable high enough to cause the winding to fail the
on a typical pressure gage, yet easily measured vacuum decay test. By analyzing the vacuum
with common vacuum gages. The test also meas- decay data, it is possible to detect the pressure
ures the leak rate of the entire winding without rise due to water outgassing. (See Figure 8.)
requiring access to the stator winding. Windings that fail Vacuum Decay Testing and
Vacuum Decay Testing is relatively insensitive to show indications of outgassing must be further
changes in temperature and atmospheric pres- vacuum-dried and retested.

GE Power Systems GER-3751A (08/01)


■ ■ 9
Understanding, Diagnosing, and Repairing Leaks in Water-Cooled Generator
Stator Windings

GER3751-6
Figure 6. HIT Skid

3
1
10 Pressure Decay Testing
5
10 2
5
5 10 The Pressure Decay Test has two advantages in
2
2
10 2 2
5 comparison to the Vacuum Decay Test. It pro-
0.1 vides a greater pressure differential (at least five
5 1 2
5
2
5 1 times that of the vacuum test) and applies pres-
2 5
10 2 sure in the normal direction of the leak flow.
10–2
5 0.1 2
These factors may make it easier to find leaks
5
5 0.1
2
2 undetectable to vacuum. During the Pressure
5
1 2
Decay Test, exposed potential leak sites can be
10–3 5 10 –2
2
5
10–2 tested with a "bubble" solution.
5
2
INCHES OF MERCURY

2
0.1 2
5 Drawbacks to pressure testing are its insensitivi-
ATMOSPHERE

10–4 –3 ty to small leaks, sensitivity to changes in the


10 2
TORR

5
PSIA

5
2
5 10–3 environment (temperature and barometric
2 5
10–2 2 pressure), and the time required to test. In a
10–5 –4

5
5 10 2
typical test at 80 psi, a volume of 1.0 ft3 must
2
5 10–4
2 5
leak out of the generator to register a change of
–3
10 2
1 psi. For this reason, extremely accurate gages
10–6
5 10–5 2
5
5 10–5 are needed, preferably with 0.1 psi indications.
2
2
–4 5 Also, to detect small leaks, the test must be done
10 2
10–7 over many hours so that the leak volume
5 10–6 2
5 –6
5 10 becomes significant relative to the test’s sensi-
2
2 5
10–5 2 tivity.
10–8 –7
5 10 2
5 –7 Prior to exposure to high pressures, the stator
5 10
2
2
winding must be completely dry internally.
10–6 2
10–9 Subjecting a winding with water in it to high
10–8 GER3751-7

pressure may force moisture into insulation,


Figure 7. Units of pressure conversion nomograph through yet undetected leak paths, and cause

GE Power Systems GER-3751A (08/01) ■ ■ 10


Understanding, Diagnosing, and Repairing Leaks in Water-Cooled Generator
Stator Windings

GER3751-8

PRESSURE

Outgassing/Virtual Leak
Source is Depleted; Real
Leak Takes Over

TIME
Figure 8. Rate of rise curve (outgassing and leak)

insulation damage. Small leaks can also be con- ers of glass, mica, and resin within the winding.
cealed by moisture within the leak path. This can make detection difficult. A process of
Therefore, the winding should be initially vacu- bagging the series loop connections (the source
um-decay tested in order to assure dryness. The of most leaks) has greatly improved the ability
pressure test should be conducted with very dry to locate very small leaks. Helium pressure is
air or nitrogen to assure that moisture is not maintained on the winding for a period of time
reintroduced to the system. to allow helium from a buried leak to migrate
through the insulation and become concentrat-
Helium Tracer Gas Testing ed in the bag. In about 85% of the cases, after
Helium Tracer Gas Testing is a method of leak removing the insulation, leaks on the order of
detection where the generator is pressurized at least 10-4 std. cc/sec have been found. The
with a helium gas so that possible leak points other 15% generally showed traces of helium in
can be detected using a helium gas detector. various locations not concentrated enough to
There is a wide range of tracer gases and tracer pinpoint for repair.
gas detectors on the market. In many cases, leaks that were found with the
The Mass Spectrometry technology used by GE tracer gas would have been missed if the stator
employs helium as the tracer gas because it is winding only had been Vacuum Decay Tested
the lightest inert gas, nontoxic, and non-haz- and Pressure Decay Tested. Early detection pro-
ardous. Other gases do not provide the level of vides the opportunity to make repairs before
sensitivity of helium, and some of them can more extensive damage can occur to the stator
combine with any residual water in the winding winding insulation.
to form acidic solutions. Tracer gas testing does have its own shortfalls,
Tracer gas detector sensitivity is very important however, which highlight the importance of a
in finding leaks in the generator stator winding. program inclusive of Vacuum Decay Testing
Leak sources can be buried beneath several lay- and Pressure Decay Testing. The two most

GE Power Systems GER-3751A (08/01)


■ ■ 11
Understanding, Diagnosing, and Repairing Leaks in Water-Cooled Generator
Stator Windings

notable shortfalls are the inability to inspect the All insulating materials (i.e., air, MicapalTM,
entire winding, and the need for access to the water) have a property known as the dielectric
whole winding. To detect small leaks, the sniffer constant. The Capacitance Mapping Test is
detector must be brought within 2 to 3 inches of based on the difference between the dielectric
the leak. Since it is nearly impossible to cover constant of water and that of the groundwall
every square inch of the winding, tracer test insulation system. Where there is a mixture of
techniques such as bagging the series loops, test air, water, and insulation, the measured capaci-
only the most probable leak sites. This cannot tance will be a different composite number. The
provide confidence that the entire winding is Capacitance Mapping Test uses this principle to
leak-tight. Under normal circumstances it is identify insulation that has been penetrated by
preferable to remove the field to perform water. The capacitance probe is attached to the
Helium Tracer Gas Testing. Limited testing can bars within three inches of the bar armor.
be done with the field in place with the upper Capacitance is measured between ground and
end shields removed. the test area. Before the test, the bars must be
cleaned with a solvent to assure proper contact.
Stator Bar Capacitance Mapping Testing Although Capacitance Mapping Testing only
Stator Bar Capacitance Mapping Testing in investigates the condition of the bar insulation
water-cooled generators is recommended to immediately under the probe, if a bar is leaking,
determine the extent of water penetration of it is anticipated that the water will migrate along
the groundwall insulation. The stator winding the bar to where the electrode is located.
does not have to be dry to perform the Capacitance readings are taken for each of the
Capacitance Mapping Test. This test is non- bars in the winding, and at both ends of the
destructive to the stator bar. If a bar fails the generator. Good capacitance data will provide
Capacitance Mapping Test, it should be consid- a normal curve when plotted with nearly all of
ered unsuitable for long-term service. The the data falling between –2 and +2 standard
intent of this test is to locate bars that are at deviations from the average. Wet bars that have
high risk of in-service and/or hipot failure. failed electrical testing have generally had
Capacitance Mapping Test results are sensitive capacitance values falling outside +5 standard
to the number of layers of bar insulation. This deviations from the average. Industry feedback
sensitivity makes it necessary to test the bars in suggests that bars found with a capacitance level
a location where the groundwall insulation is greater than +3 standard deviations are to be
consistent from bar to bar, typically at the "first considered suspect.
bend." The series loop joints may not be ade- Bars that are found with damaged groundwall
quately tested with a capacitance probe because insulation are not repairable and require
of the possible inconsistencies in the taped insu- replacement within one year because long-term
lation thickness. This is because series loops exposure to moisture weakens the insulation,
may be unevenly hand-taped while the stator making it more susceptible to mechanical dam-
bars are evenly machine-taped. Design of the age and failure from normal and transient volt-
stator end winding makes access to the stator age stresses. Also, moisture within a strand pack-
bar insulation difficult except at the first bend age deteriorates the bonding resin between
region, which is near the stator core. strands and may lead to separation of packages.

GE Power Systems GER-3751A (08/01)


■ ■ 12
Understanding, Diagnosing, and Repairing Leaks in Water-Cooled Generator
Stator Windings

Relative motion between strands could now fied stator winding leaks as one important fac-
cause strand shorts and ultimately bar failure. tor affecting generator reliability and availabili-
There is no effective way to dry a wet bar. ty. Through May, 2001, there were approxi-
Damage is irreversible. mately 600 GE water-cooled generators in serv-
ice, with an average stator winding age of over
Summary of Recommended Tests 26 years. The expected design life of a liquid-
cooled winding is 30 years.
Table 1 summarizes the recommended leak tests
for water-cooled generator stator windings, as Through May, 2001, of the number of water-
cooled stator windings that failed, 15% failed in
well as their frequency of performance. The
service, and 55% failed electrical tests. The in-
recommended outage intervals have proven
service failure rate has shown a marked increase
themselves over many years of use.
over the past several years. This appears to be
due to changes in maintenance practices.
Industry Experience Figure 9 shows a breakdown by cause of failure
A review of historical data compiled on water- for water-cooled stator winding failures through
cooled generators through May, 2001, identi- May, 2001.

Recommended Testing Frequency


On-Line During Outages
Test Minor Outage Major Outage
Weekly (End Shields (with Rotor
Removed) Removed)

Liquid
Detector X

YTV Flow X(2)

Vacuum
Decay Test X(1) X

Pressure
Decay Test X(1) X

Helium Test

Helium Test with


Rotor Removed X

Capacitance
Test X

NOTES:

(1) For generators not equipped with SLMS. Vacuum and Pressure Decay
tests are recommended during minor outages to assess the integrity of
the stator hydraulic system.
(2) For units equipped with SLMS, the YTV vent is monitored
automatically.

Table 1. Recommended leakage tests for water-cooled generator windings

GE Power Systems GER-3751A (08/01)


■ ■ 13
Understanding, Diagnosing, and Repairing Leaks in Water-Cooled Generator
Stator Windings

75% of Failures Due to Wet Insulation

Water-Cooled Stator Bar Failures


7
Comments for In-Service
Failures:
6 Electrical Test 1989 One failure probably due to
In Service water leak. Cause
Number of Events

5 unknown.
1995 Two failures due to
4 abrasion.
1999 One failure due to crevice
3 corrosion. One failure due
to abrasion.
2 2000 One failure due to leaking
copper tube and/or water
1 conductivity.
2001 One failure due to cracked
tube.
0
1985 1986 1987 1988 1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001

Figure 9. Updated leak test data

A review of the leak-testing history provides evi- Gas Testing and Capacitance Mapping Testing.
dence that passing both the Vacuum Decay Test (See Figure 10.) The combination of all these
and the Pressure Decay Test—though vital in tests provides the best possible assurance that
the Maintenance and Inspection Program of the stator windings are free of destructive water
Water-Cooled Generators—does not necessarily leaks. Our experience indicates that of those
guarantee a leak-free stator winding. The results generators with windings that failed electrical
demonstrate the importance of Helium Tracer tests due to wet insulation through May, 2001:

PASSED
FAILED
100%
90%
33%
80%
70%
63% 70%
60%
82%
50%
40%
67%
30%
GER3751-10

20% 37% 30%


10% 18%
0%
re

e
m

nc
ce
su
uu

ita
a
es
c

Tr
Va

ac
Pr

ap
C

Figure 10. Maintenance test data through May, 2001

GE Power Systems GER-3751A (08/01) ■ ■ 14


Understanding, Diagnosing, and Repairing Leaks in Water-Cooled Generator
Stator Windings

■ Most passed the Vacuum Decay Test clip-to-strand braze, water can migrate along
■ Approximately 50% passed the Pressure the bar at the interface between the bar copper
Decay Test and insulation. This can result in water accu-
■ All failed the Helium Tracer Gas Test mulation in the insulation, particularly at the
and Capacitance Mapping Test core line, and result in an electrical failure to
ground during operation or failure during
Stator Winding Leak Repair Methods maintenance testing. Insulation degraded by
water permeation cannot be restored to origi-
Stator winding leak repair methods can be bro-
nal condition, and replacement of the bar is
ken down into three categories:
recommended if the "wet" insulation is detect-
■ Component Replacement
ed in the first bend near the core line in the bar
■ Braze/TIG Repair slot or grading section.
■ Epoxy Injection Repair As demonstrated by industry experience, a stock-
The type of repair method depends upon a ing program of stator bars and long-self life mate-
number of factors including type of leak, its rials reduces outage time extension in cases
location, leak size, the desired longevity and where major repairs need to be performed due
confidence of the repair, and the condition of to failed bars and water leaks. Table 2 shows the
the bar insulation.
recommended stocking quantities for spare sta-
Component Replacement tor bars.

Components that have required replacement in Braze/TIG Repair


the past include TeflonTM hoses, hydraulic fit- Leaking hydraulic braze joints are usually fixed
tings and piping, and stator bars. by rebrazing, and additional braze alloy is
Leaks in hoses, fittings and piping connections, added, as required. Tungsten Inert Gas (TIG)
are usually the result of fatigue failure, parts repairs are used on porosity leaks and repairing
abrasion, or casting porosity. These compo- window leaks. TIG repairs are done on window
nents can frequently be replaced with the gen- leaks because the stator bar insulation may be
erator field in place. However, there are some damaged if heated too much.
winding arrangements that limit access and do The TIG repair causes only localized heating
require field removal from the stator to remove and should not damage bar insulation.
and install new parts. However, TIG repairs are largely surface
Stator bar replacement is a more complex task, repairs, making them mostly suitable for loca-
and does require the field to be out of the sta- tions where strength is not a requirement.
tor. For that reason bars are replaced only when Epoxy Injection Repair
the fundamental integrity of the groundwall
Clip to strand leaks can be repaired by GE’s
insulation has been compromised.
patented Epoxy Injection Repair process. This
Most water leaks have been found and repaired process uses a specialized borescope with video
prior to damaging the electrical insulation display in conjunction with specialized epoxy
properties. However, when a leak occurs at the injection equipment.

GE Power Systems GER-3751A (08/01)


■ ■ 15
Understanding, Diagnosing, and Repairing Leaks in Water-Cooled Generator
Stator Windings

Recommended Number of
Spare Generator Stator Bars
Stator
Bar Four-Pole Two-Pole
Number of Slots Number of Slots

54 60 66 72 30 36 42 48 54 60

Top 14 15 17 18 15 18 21 23 25 27
Bottom 4 4 4 4 4 4 4 4 4 4
P-Bar* 1 1 1 1 2 2 2 2 2 2

*Machines with Generrex Excitation Only


Table 2. Recommended number of spare stator bars

Figure 11 shows a typical epoxy-injected clip. the stator bar need to be injected to ensure that
The epoxy itself is a specifically formulated the leak source is sealed. The epoxy is heat-
compound designed to bond to the oxide layer cured and then the clip is inspected and leak-
on the surface of the copper. The stator wind- tested. Once the epoxy is cured and the unit has
ing must be dry prior to starting the epoxy passed the required testing, the procedure is
injection process. Access is gained by removing considered to be a permanent repair. This
the TeflonTM hose and the hydraulic pumping repair is performed by a qualified GE specialist.
components. The technician directs a syringe’s Prior to performing the epoxy injection repair,
pinpoint nozzle to the target area aided by a the stator bar-to-bar insulation or bar-to-con-
borescope video display. The epoxy is injected nection ring insulation is removed to verify that
into the crevices between the strands. Each dia- the leak is a clip-to-strand leak and not a clip
mond shape area formed by the strand corners, porosity or window leak, which are repaired
as well as between strand columns and rows, is using other methods. If a clip-to-strand leak is
injected to fill any voids. Clips on both ends of verified, it should be determined that the stator

Figure 11. Epoxy-injected clip

GE Power Systems GER-3751A (08/01)


■ ■ 16
Understanding, Diagnosing, and Repairing Leaks in Water-Cooled Generator
Stator Windings

bar insulation is not wet. The Capacitance Global Epoxy Injection


Mapping Test is a reliable indicator of wet
Global epoxy injection consists of the applica-
insulation. Insulation is electrically and
tion of epoxy to all stator bar clips. This can be
mechanically weakened by water penetration.
performed on a planned basis, at one time, or
Replacement of stator bars having wet insula-
over a series of outages. This proactive applica-
tion is recommended due to the potential for
tion to all the stator bar clips eliminates future
an in-service failure and significant damage to
risks of stator bar leakage due to crevice corro-
the generator.
sion, reduces the potential for outage extension
In addition to the Capacitance Mapping Test, and the likelihood of in-service failure due to
GE recommends that the suitability for service water leaks.
of the stator bars be confirmed with a high GE’s research indicates that—if unabated—
potential test prior to performing this repair. crevice corrosion in the stator cooling system
The repair should only be performed on bars will continue to progress through the remain-
that are considered suitable for service. ing life of the machine. On machines built
GE’s proprietary Epoxy Injection Repair is the before 1986, the risk associated with the poten-
simplest, most non-invasive and highest tech- tial development of leaks as the generators age
nology repair available. The procedure can be is considerable. The Global Epoxy Injection
process eliminates this risk and the need for
performed during either a planned or emer-
contingencies for leak repair and possible bar
gency outage. To minimize the impact on out-
replacement. The cost of replacing a wet bar
age duration, the epoxy injection repair is time
can be significant, considering replacement
efficient, flexible to respond to sudden changes
parts, labor, and extension of outages. For cus-
in scope, low risk, and provides a high quality, tomers that do not wish to rewind the stator due
reliable, and permanent solution. to crevice corrosion problems, we strongly rec-
GE will work with customers to develop a sched- ommend global application of epoxy to all clips
ule that fits the specific outage window. To as soon as possible.
obtain a summary of experience with this
Full Stator Rewind
repair, contact your local GE office.
While Global Epoxy Injection can eliminate
Long Term Leak Solutions future risk of stator bar leakage due to crevice
corrosion for a generator stator winding that
In the competitive environment that utilities has not yet experienced a bar leak, a complete
face today, reduction in generator availability generator stator rewind provides the best long-
from unplanned outages and added mainte- term solution to leaks in a water-cooled genera-
nance (due to water leaks) may pose an unac- tor. Thanks to the introduction of modern
ceptable penalty. GE offers two options for a materials and to refinements and optimization
long-term solution to address these leaks and in design practices and technology, the reliabil-
provide improved generator availability: ity of a water-cooled generator stator winding
can be greatly increased. A full stator rewind
■ Global Epoxy Injection also provides the opportunity for an electrical
■ Full Stator Rewind power uprate of the water-cooled generator.

GE Power Systems GER-3751A (08/01)


■ ■ 17
Understanding, Diagnosing, and Repairing Leaks in Water-Cooled Generator
Stator Windings

Conclusion A. Implementing Global Epoxy Injection


will eliminate any future risk associated
As the typical water-cooled generator in the
with crevice corrosion/clip to stand
industry approaches 30 years of service, there is
leaks. However, during normal opera-
an increasing likelihood of winding failures
tion the stator winding is subjected to
associated with water leaks. The cost can be sig-
thermal shocks, cyclic operation, corro-
nificant in terms of added downtime for repair
sion, and mechanical/electrical vibra-
of generator stator cooling water leaks. Early
tion. These normal operational stresses
detection and repair of water-cooled stator
can lead to the development of other
winding leaks can significantly reduce the risk
kinds of leaks. Therefore, the testing in
of winding insulation failure, as well as the cost
TIL-1098 is still recommended.
of downtime and winding repair. A proactive
approach to on-line monitoring and off-line 3) Q. What improvements have been made
leak testing is necessary for early detection of by GE to reduce the likelihood of devel-
leaks in order to maximize the service life of the oping leaks in water-cooled generator
stator windings. stator windings?
A. GE has made continuous improve-
Questions & Answers ments that resulted in liquid-cooled sta-
tor windings of high quality that are far
The following are typical questions and answers
more reliable and more efficient than
regarding generator stator cooling water leaks,
ever before. By applying our state-of-
testing, and repair. They are included to sup-
the-art processes, and by using superior
plement the information provided in the main
machined stator bar clips, advanced
body of this paper.
brazing techniques, and enhanced
1) Q. What are the causes of leaks in a water- cleaning methods, we are confident of
cooled stator winding? having a product that, when operated
A. There are a number of possible / prob- and maintained as recommended, will
able causes for the development of provide our customers with generator
leaks in a liquid-cooled stator winding. water-cooled windings with the highest
During normal operation the stator reliability in the industry.
winding is subjected to thermal shocks, 4) Q. We have just completed implementing
cyclic operation, corrosion, and a Global Epoxy Injection on one of our
mechanical/electrical vibration. These 1970s vintage generators. What is the
normal operational stresses can lead to probability of developing leaks on
the development of leaks in a liquid- other sister units?
cooled stator winding. A. Liquid-cooled generators that were
2) Q. If we implement Global Epoxy manufactured between 1970 and 1986
Injection on a winding that has not yet are most susceptible to developing clip-
seen crevice corrosion, will we be to-strand leaks as a result of crevice cor-
exempted from the periodic testing rosion. Clip-to-strand braze connec-
required by TIL-1098? tions on liquid-cooled stator bars that

GE Power Systems GER-3751A (08/01)


■ ■ 18
Understanding, Diagnosing, and Repairing Leaks in Water-Cooled Generator
Stator Windings

were made prior to 1970 contained ser- be required prior to testing. The other
rated spacers and were much more option is to continue with the testing
resistant to developing these clip-to- recommended in the instruction book.
strand leaks. Now, however, after more This has proven successful to date.
than 30 years of service, we have docu- 8) Q. Why does GE recommend removing
mented cases of clip-to-strand leaks, the water pressure when the machine gas
result of crevice corrosion, in a few of pressure is removed?
these machines. The Crevice
A. The winding water pressure should
Corrosion Leak Testing Decision Tree
always be maintained lower than the
may be used as an aid to planning gen-
machine gas pressure to minimize
erator maintenance activities. (See
water penetration through leak paths
Appendix.)
in the stator winding. This practice is
5) Q. Why is Helium Tracer Gas Testing rec- precautionary and makes sense, even
ommended following acceptable for windings that have been successful-
Vacuum Decay Test and Pressure Decay ly leak tested.
Test results?
9) Q. Is it possible for a winding to pass some
A. The Helium Tracer Gas Test is the most
leak tests and to fail others?
sensitive leak test that GE offers to date.
It is capable of detecting leaks nearly A. Yes. Each of the recommended leak
five orders of magnitude smaller than tests has its unique advantages and lim-
that which can be detected with either itations. It is recommended that all tests
the Vacuum Decay Test or Pressure be conducted at the suggested interval
Decay Test. because of the complementary nature
of these tests. Some leak types and/or
6) Q. What size leak does GE consider accept-
locations are more likely to fail certain
able?
leak tests. Therefore, it is recommend-
A. Any leak that is detected using methods ed that all tests be performed at the
described in this paper are considered suggested interval.
unacceptable.
10) Q. Does the winding need to be dry to
7) Q. Do the leak test criteria in TIL-1098
perform the Capacitance Mapping
apply to oil-cooled stator windings?
Test?
A. Our experience shows that oil-cooled
A. No. The Capacitance Mapping Test
stator windings have not been suscepti-
detects the presence of water within the
ble to stator bar insulation failure
ground wall insulation. This test is
caused by stator winding leaks. For this
effective because of the large differ-
reason, oil-cooled machines were not
ence in the dielectric constant of water
included in TIL-1098. However, the
and the normal ground wall insulation.
leak testing methods recommended for
water-cooled machines could be 11) Q. Why is the acceptable leak criterion dif-
applied to oil-cooled machines, but a ferent for the Vacuum Decay Test and
thorough flush of the windings would the Pressure Decay Test?

GE Power Systems GER-3751A (08/01)


■ ■ 19
Understanding, Diagnosing, and Repairing Leaks in Water-Cooled Generator
Stator Windings

A. The sensitivity of the Vacuum Decay which is generally available only at


Test, and the effects of winding mois- major outages. Vacuum Decay and
ture and test equipment condition on Pressure Decay Testing do not require
test results have made it necessary to access and can be performed at any
establish a higher acceptable decay time with the generator off-line, pro-
rate. viding the ability to test the winding
12) Q. Can water escape through a leak path between major outages. (b) Tracer gas
with the machine under gas pressure? testing is used to inspect easily accessi-
A. Yes. Through capillary action water can ble locations (such as the series loop
escape through some leaks. Leaks that and header connections) which
are buried beneath layers of insulation account for the majority of winding
and resin are believed to be more sus- leaks. Vacuum Decay and Pressure
ceptible to this phenomenon. The Decay procedures test the entire wind-
hydrogen pressure drop across these ing, and are needed to test locations
layers of tape is also believed to be a fac-
not covered by tracer testing. (c) Little
tor.
additional effort is needed to perform
13) Q. Why is bar replacement recommended Vacuum Decay and Pressure Decay tests
for wet bars that pass hipot?
when preparing to tracer gas test a
A. Damage to wet insulation is irre- winding. Since the winding must be
versible, and there is no known way to vacuum dried prior to tracer gas test-
dry a bar once it has become wet. Long ing, Vacuum Decay Testing does not
term exposure to water weakens the
require additional equipment. Pressure
insulation, making it more susceptible
Decay Testing can be performed while
to mechanical damage and failure from
the winding is pressurized with tracer
voltage stress. In addition, the water
gas, thereby adding little time to the
can cause the bonding resin that holds
the copper strand package together to overall inspection. (d) The combina-
deteriorate allowing the strands to sep- tion of these three test methods with
arate and relative motion between the the Capacitance Mapping Test, pro-
strands to occur. This relative motion vides the best possible assurance that
can lead to strand shorts, causing over- the stator windings are free of destruc-
heating and ultimately bar failure. tive water leaks.

14) Q. If Tracer Gas testing is the most sensi- 15) Q. Does the stator winding have to be
tive test available, why are Vacuum completely dry prior to leak testing?
Decay and Pressure Decay Testing nec- A. Yes. Research and experience has
essary?
shown that smaller leaks can be
A. There are several reasons why Vacuum blocked by moisture at typical test pres-
Decay and Pressure Decay tests are nec- sures. Vacuum drying is necessary to
essary: (a) First, tracer gas testing completely remove all moisture within
requires access to the stator winding, the winding prior to testing.

GE Power Systems GER-3751A (08/01)


■ ■ 20
Understanding, Diagnosing, and Repairing Leaks in Water-Cooled Generator
Stator Windings

16) Q. If we install SLMS will we be exempted of those tests. Some leak types and/or
from performing the periodic testing locations are more likely to fail certain
required by TIL-1098? leak tests. In order to test for all leak
A. No. The Stator Leak Monitoring types and locations, all the leak tests
System (SLMS) provides continuous referenced in this paper are recom-
on-line monitoring for leaks, but it mended.
doesn’t have the same level of sensitivi- 18) Q. I have heard that low level oxygen sta-
ty that can be achieved by the tests rec- tor cooling water systems do not have
ommended in TIL-1098. Because of the crevice corrosion. Does GE recom-
complementary nature of these tests, it mend converting its high oxygen level
is recommended that these tests be per- system to a low oxygen level system?
formed at the suggested intervals. A. Some studies indicate that low-level
17) Q. If we rewind our generator stator using oxygen systems are less susceptible to
modern materials and techniques, or developing corrosion. However, those
install a whole new generator, will we be systems have problems. Low-level oxy-
exempted from performing the period- gen systems are more susceptible to
ic testing required by TIL-1098? developing cuprous oxide. This is an
unstable oxide that tends to plug hol-
A. Even though windings and compo-
low conductors in stator bar, blocking
nents are carefully tested for leakage
the cooling water flow. These plugged
throughout the manufacturing process,
strands can lead to overheating of the
those tests cannot assure that water
bar, separation and delamination of the
leaks will not develop after a period of
strand package, which may lead to a
service. During operation, the stator
breakdown of the groundwall insula-
winding is subjected to an environment
tion, resulting in a stator ground fail-
of thermal shocks, cyclic duty, corro-
ure. GE does not recommend convert-
sion, mechanical vibration, and electro-
ing from its high-level oxygen system to
magnetic stresses. Slight variations in
a low-level oxygen system.
component and braze qualities can also
result in water leaks after exposure to 19) Q. What is the recommended concentra-
an operating environment. It is recom- tion of dissolved oxygen in the stator
mended that all of the tests recom- cooling water?
mended in TIL-1098 be performed, at A. The recommended concentration for
intervals suggested by experience, dissolved oxygen in the stator cooling
because of the complementary nature water is 2 to 8 ppm.

GE Power Systems GER-3751A (08/01)


■ ■ 21
Understanding, Diagnosing, and Repairing Leaks in Water-Cooled Generator
Stator Windings

Appendix

CREVICE CORROSION LEAK TESTING DECISION TREE

Action Risk Next Step Outcome/Future Action

Nothing Ultimately, Bar Failures


High
Nothing Next
Risk
Outage Test See Below
for Results of
Rewind Test or Rewind
PRE-OUTAGE MAINTENANCE PLANNING

Epoxy Injection
Leak Repair Med Risk Next Outage,
Leak Repeat Review
– High – of All Four Options
Wet Bar Med Risk
Risk Replacement

No Risk See Below for


Full Rewind Results/Benefits
Test
Test
Global Epoxy Reduced Testing
Low Risk
Injection with SLMS

Nothing

No Leak Repeat Every Outage.


Next Ultimately, Rewind
– Med – Outage Test
Risk or Repair

Rewind

Lowest Results/Benefits:
Rewind Possible • Fixes leak issues
Risk • Potential output/efficiency improvement
• Incorporates state-of-the-art technology
• Reduces risk of outage extension
• Reduces followup testing w/SLMS

Global Epoxy Low


Risk Permanent Leak Repair If No Wet Bars
Injection

GE Power Systems GER-3751A (08/01) ■ ■ 22


Understanding, Diagnosing, and Repairing Leaks in Water-Cooled Generator
Stator Windings

References
1. Anderson, J. Armature Bar Insulation Capacitance Measurement Procedure. General Electric
Co., July 1990, p.2.
2. Lembke, B. Liquid Leak Test and Repair. General Electric Co., July 1990, pp. 12-18.
3. Varian Associates, Incorporated. Introduction to Helium Mass Spectrometer Leak Detection.
Palo Alto, CA: Varian Associates, 1980.
4. Zawoysky, R. Stator Water Cooling System Issues. General Electric Co., January 2001.
5. Worden, J. Updated Leak Test Data. General Electric Co., May, 2001.
6. TIL-1098, Inspection of Generators With Water-Cooled Stator Windings.
7. GEK-103566, Creating An Effective Maintenance Program.

List of Figures
Figure 1. Typical stator end winding configuration
Figure 2. Crevice corrosion mechanism
Figure 3. Stator cooling water system
Figure 4. Typical Stator Leak Monitoring System (SLMS)
Figure 5. Major outage leak test plan
Figure 6. HIT Skid
Figure 7. Units of pressure conversion nomograph
Figure 8. Rate of rise curve (outgassing and leak)
Figure 9. Updated leak test data
Figure 10. Maintenance test data through May, 2001
Figure 11. Epoxy-injected clip

List of Tables
Table 1. Recommended leakage tests for water-cooled generator windings
Table 2. Recommended number of spare stator bars

GE Power Systems GER-3751A (08/01)


■ ■ 23
Understanding, Diagnosing, and Repairing Leaks in Water-Cooled Generator
Stator Windings

GE Power Systems GER-3751A (08/01)


■ ■ 24

Vous aimerez peut-être aussi