From To EXCERSISE BATH/MUSIC PMP STUDY OFFICE FAMILY TV

06.30AM 07.30AM 0.25 0.75 0.00 0.00 0.00 0.00


07.30AM 08.30AM 0.00 0.00 1.00 0.00 0.00 0.00
08.30AM 09.00AM 0.00 0.00 0.00 0.00 0.50 0.00
09.00AM 07.00PM 0.00 0.00 2.00 6.50 0.00 0.00
07.00PM 08.00PM 0.00 0.00 0.00 0.00 0.00 1.00
08.00PM 09.00PM 0.25 0.25 0.00 0.00 0.50 0.00
09.00PM 10.00PM 0.00 0.00 1.00 0.00 0.00 0.00
10.00PM 10.30PM 0.00 0.00 0.00 0.00 0.50 0.00
10.30PM 06.30AM 0.00 0.00 0.00 0.00 0.00 0.00
TOTAL 0.50 1.00 4.00 6.50 1.50 1.00

PMP STUDY PLAN


Day Morning Afternoon Evening Morning Afternoon Evening
21.09.2004 Overview Overview Overview 26.09.2004 Rita 7&8 Rita
22.09.2004 Rita 1 Rita 27.09.2004 Rita 9 & 10 Rita
23.09.2004 Rita 2 Rita 28.09.2004 Rita 11 Rita
24.09.2004 Rita 3&4 Rita 29.09.2004 Rita 12 Rita
25.09.2004 Rita 5&6 Rita 30.09.2004 Rita 1 TO 12 Rita

04.10.2004 Overview Overview Overview 09.10.2004 Andy 7&8 Andy


05.10.2004 Andy 1 Andy 10.10.2004 Andy 9 & 10 Andy
06.10.2004 Andy 2 Andy 11.10.2004 Andy 11 Andy
07.10.2004 Andy 3&4 Andy 12.10.2004 Andy 12 Andy
08.10.2004 Andy 5&6 Andy 13.10.2004 Andy 1 TO 12 Andy
DOS/DONTS EMAILS SLEEP TRAVEL TOTAL
0.00 0.00 0.00 0.00 1.00
0.00 0.00 0.00 0.00 1.00
0.00 0.00 0.00 0.00 0.50
0.25 0.75 0.00 0.50 10.00
0.00 0.00 0.00 0.00 1.00
0.00 0.00 0.00 0.00 1.00
0.00 0.00 0.00 0.00 1.00
0.00 0.00 0.00 0.00 0.50
0.00 0.00 8.00 0.00 8.00
0.25 0.75 8.00 0.50 24.00
No Knowledge Area No Process Purpose No Input No Tools and Techniques No Output
1 Integration 1 Project Charter the document that 1 Contract 1 Project Selection Methods 1 Project Charter
officially starts the 2 SOW 2 Expert Judgment
project 3 Organizational Policies 3 PMIS (Prj.Mngt.Inf.Sys)
Project Management
4 Environmental Factors 4 Methodology

2 Preliminary defining the initial view Preliminary Project Scope


Project Scope of the scope 1 Charter 1 Project Planning Methodology 1 Statement
Statement 2 SOW 2 Expert Judgment
3 Organizational Policies 3 PMIS (Prj.Mngt.Inf.Sys)
4 Environmental Factors

3 Project Plan Integrating and Preliminary Project


Development coordinating all project 1 Scope Statement 1 Project Planning Methodology 1 Project Plan
plans to create a 2 Environmental Factors 2 Expert Judgment 2 Supporting Detail
consistent, coherent 3 Organizational Policies 3 PMIS (Prj.Mngt.Inf.Sys)
document
Project Management
4 Processes

4 Direct and Carrying out the Project Management


Manage Project project plan by 1 Project Plan 1 Methodology 1 Deliverables
Execution performing the 2 Ap'd Corrective Actions 2 PMIS (Pr. Mngt.Inf.Sys) 2 Reg'd Changes
activities included 3 Ap'd Preventive Actions 3 Imp'd Corrective Actions
therein
4 Ap'd Change Requests 4 Imp'd Preventative Actions
Ap'd and Validated Work Performance
5 Defect Repair 5 Information
Administrative Closure
6 Procedure
5 Monitor and Compare work results Project Management Project Management
Control Work to the plan and make 1 Plan 1 Methodology 1 Rec'd Corrective Action
adjustments
2 Work Performance Info 2 PMIS (PrjMngt.Inf.Sys) 2 Rec'd Preventative Action
3 Rejected Change Reqs 3 Earned Value Technique 3 Req'd Changes
4 Expert Judgment 4 Forecasts
5 Rec'd Defect Repair
5 Integrated Coordinating changes Project Management
Change Control across the entire 1 Project Plan 1 Methodology 1 App'd Change Requests
project 2 Req'd Changes 2 PMIS 2 Rejected Change Requests
3 Work Performance Info 3 Expert Judgment 3 Project Plan Updates
Project Scope Statement
4 Rec'd Preventive Action 4 Change Control Board 4 updates
5 Rec'd Corrective Act 5 App'd Corrective Actions
6 Rec'd Defect Repair 6 App'd Defect Repair
7 Deliverables
7 Deliverables 8 Validated Defect Repair
6 Close Project Closing the project Project Management
down correctly 1 Project Plan 1 Methodology 1 Admin Closure Procedure

2 Contract Documentation 2 Expert Judgment 2 Contract Closure Procedure


Final Product
3 Environmental Factors 3 PMIS (PrjMngt.Inf.Sys) 3 Service/Result
Organizational Process
4 Organizational Policies 4 Assets Updates
5 Deliverables
6 Work Performance Info
Scope 2 Scope Planning Plan for how scope 1 Environmental Factors 1 Expert Judgment 1 Scope Management Plan
Management and changes to the Organizational Process
scope will be 2 Assets 2 Templates, Forms, Standards
managed 3 Project Charter
4 Project Plan
Preliminary Scope
5 Statement
2 Scope Definition defining and Organizational Process
documenting the 1 Assets 1 Product Analysis 1 Scope Statement
deliverables that are Preliminary Scope
part of the scope 2 Statement 2 Alternatives Identification Req'd Changes
3 App'd Change Reqs 3 Expert Judgment Project Scope Plan Updates

4 Scope Management plan 4 Stakeholder Analysis


3 Create WBS Subdividing the major 1 Organizational Process 1 Work Breakdown Structure 1 Work Breakdown Structure
deliverables into Assets Templates
smaller, more
manageable 2 Project Scope Statement 2 Decomposition 2 WBS Dictionary
components Project Scope
3 Management Plan 3 Scope Statement Updates
Scope Management Plan
4 App'd Change Reqs 4 Updates
Scope Baseline (Scope
5 Statement, WBS/Dictionary)
6 Req'd Changes
4 Scope Verifying the product
Verification matches the 1 Scope Management plan 1 Inspection 1 Accepted Deliverables
documented scope 2 WBS Dictionary 2 Req'd Changes
3 Scope Statement 3 Rec'd Corrective Actions
4 Deliverables

5 Scope Control Controlling changes to 1 WBS 1 Change Control System 1 Scope Changes
the project scope--
ensuring all of what is 2 Project Scope Statement 2 Variance Analysis 2 WBS Updates
"in scope" and only 3 WBS Dictionary 3 Replanning 3 Scope Baseline Updates
that is completed
Configuration Management
4 Scope Management plan System 4 Req'd Changes
5 Performance Reports Rec'd Corrective Actions
Organizational Process
6 App'd Change Reqs Assets Updates

7 Work Performance Info 4 Project Plan Updates


3 Time 1 Activity list the project 1 WBS 1 Decomposition 1 Activity List
Management Definition activities 2 Scope Statement 2 Templates 2 Activity Attributes
3 Environmental Factors 3 Rolling Wave Planning 3 Milestone List
4 WBS dictionary 4 Expert Judgment 4 Req'd Changes
5 Project Plan 5 Planning Component

2 Activity Order the activities PDM (Precedence diagramming Project Schedule network
Sequencing and create the project 1 Scope Statement 1 method--AON) 1 diagrams
network diagrams ADM (Arrow diagramming
2 Activity List 2 method--AOA) 2 Activity List Updates
3 Activity Attributes 3 Dependency Determination 3 Activity Attributes Updates
4 Milestone List 4 Apply Leads and Lags 4 Req'd Changes
5 App'd Change Requests

3 Activity Resource Estimating the size of 1 Environmental Factors 1 Expert Judgment 1 Activity Resources Reqs
Estimating the activity, the
number of resources, 2 Activity List/Attributes 2 Alternatives Analysis 2 Activity Attributes Updates
and the availability Resource Breakdown
3 Resource Availability 3 Published Estimating Data 3 Structure
Project Plan (schedule
4 plan) 4 Project Management Software 4 Resource Calendar
6 Bottom-up Estimating 5 Req'd Changes

3 Activity Duration Estimating the number


Estimating of work periods that 1 Environmental Factors 1 Expert Judgment 1 Activity Duration Estimates
will be needed to Organizational Process Analogous Estimating (Top-
complete individual 2 Assets 2 down) 2 Activity Attributes Updates
activities
3 Scope Statement 3 Parametric Estimating (linear) 3

4 Activity List/Attributes 4 PERT Three-Point Estimating

5 Activity Resource Reqs 5 Reserve Analysis


6 Resource Calendar
Project Plan (risk
register, activity cost
7 estimates)
5 Schedule Create the schedule Organizational Process
Development 1 Assets 1 Schedule Network Analysis 1 Project Schedule
2 Scope Statement 2 Critical Path Method 2 Schedule Model Data
Schedule Compression
3 Activity List/Attributes 3 (crashing, fast tracking) 3 Schedule Baseline
Project Schedule What-if Schedule Analysis
4 Network Diagrams 4 (Monte Carlo) 4 Resource Reqs updates

5 Activity Resource Reqs 5 Resource Leveling 5 Activity List Updates


6 Resource Calendar 6 Critical Chain Method 6 Project Calendar Updates
Activity Duration
7 Estimates 7 Project Management Software 7 Req'd Changes
Project Plan (Schedule
8 plan and risk register) 8 Applying Calendars 8 Project Plan Updates
9 Adjusting Leads and Lags
10 Schedule Model

5 Schedule Control Influencing the factors Schedule Management


that create schedule 1 Plan 1 Progress Reporting 1 Schedule Model Data
changes to ensure 2 Schedule Baseline 2 Schedule Change Control Sys 2 Baseline updates
that the changes are Performance Measurements
agreed upon, 3 Performance Reports 3 Performance Measurement 3 (SPI, SV, EV)
Determining that the
Schedule Comparison Bar
schedule has
4 Change Requests 4 Charts 4 Req'd Changes
changed, Manage the
actual changes when Rec'd Corrective Action,
and as they occur Activity list/Attributes
Updates, Project Plan
5 Variance Analysis 5 Updates
4 Cost 1 Cost Estimating Developing an 1 Environmental Factors 1 Analogous Estimating 1 Activity Cost Estimates
Management approximation Organizational Process
(estimate) of the costs 2 Assets 2 Determine Resource Cost Rates Supporting Details
of the resources 3 Scope Statement 3 Bottom-up Estimating Req'd Changes
needed to complete
Cost Management Plan
the project activities
4 WBS / Dictionary 4 Parametric Modeling Updates
5 Project Plan 5 Project Management Software
6 Reserve Analysis

Vendor Bid Analysis, Cost of


7 Quality
2 Cost Budgeting Cost Baseline - takes 1 Scope Statement 1 Funding Limit Reconciliation 1 Cost Baseline (Budget)
the estimated project 2 WBS / Dictionary 2 Parametric Modeling 2 Project Funding Reqs
expenditures and Cost Management Plan
maps them back to 3 Activity Cost Estimates 4 Reserve Analysis 3 Updates
dates on the calendar
4 Supporting Details 5 Cost Aggregation 4 Req'd Changes
5 Project Schedule
6 Resource Calendar
7 Contract
8 Cost Management Plan

3 Cost Control Influencing the factors 1 Cost Baseline 1 Cost Change Control Sys 1 Cost Estimating Updates
that create changes to Performance Measurement
the cost baseline 2 Project Funding Reqs 2 Analysis (EV…) 2 Cost Baseline Updates
(PROACTIVE!!) Performance
measure what's 3 Performance Reports 3 Forecasting (EAC, ETC) 3 Measurements
executed against what
was planned
4 Project Plan 4 Project Performance Reviews 4 Forecasted Competition
5 Work Performance Info 5 Project Management Software 5 Req'd Changes
6 App'd Change Reqs 6 Variance Management 6 Rec'd Corrective Actions
7 Organizational Updates
8 Project Plan Updates
5 Quality 1 Quality Planning Identifying which 1 Environmental Factors 1 Benefit/Cost Analysis 1 Quality Management Plan
Management Quality specifications 2 Organizational Process 2 Benchmarking 2 Quality Checklists
are for this project & Process Improvement Plan
determining how to 3 Scope Statement 3 Cost of Quality 3 (Project Plan)
satisfy them
4 Project Plan 4 Design of experiments 4 Quality Baseline

5 Project Plan Updates


2 Quality Execution of planned
Assurance systematic quality Quality Planning Tools and Req'd Changes/Corrective
control measures to 1 Quality Mngt Plan 1 Techniques 1 Actions
ensure the project will Quality Audits (review the
take advantage of all product to see which
processes --Process processes should be Organizational Process As
improvement 2 Quality Metrics 2 improved) Updates

3 Work Performance Info Process Analysis Plan Updates


4 Apr'd Change Reqs
Implemented
Change/Corrective/defec
5 t/preventive

6 Quality Control Measures

Process Improvement
7 Plan
3 Quality Control Monitoring each Cause and Effect Diagrams Quality Control
deliverable to 1 Quality Metrics 1 (Ishikawa, fishbone) 1 Measurements
determine if they Control Charts (Statistical
comply with relevant 2 Quality Mngt Plan 2 Process Control) 2 Validated Defect Repair
Quality standards & 3 Work Performance Info 3 Inspection 3 Baseline Updates
identifying ways to
4 Checklists 4 Defect Repair Review 4 Validated Deliverables
eliminate causes of
unsatisfactory Req'd Changes/Corrective
performance 5 Apr'd Change Reqs 5 Pareto Chart 5 Actions
Run Chart/Scatter
Diagram/Statistical
Sampling/Flow-
6 Deliverables 6 Charting/Histogram Plan Updates
6 Human 1 Organizational identifying, Organizational Charts and Role & Responsibility
Resource Planning documenting & 1 Environmental Factors 1 Position Descriptions 1 Assignments
Management assigning project Matrix (Responsibility
roles, responsibilities, 2 Organizational Assets 2 Assignment Matrix) 2 Staffing Management Plan
and reporting 3 Project Plan 3 Networking 3 Organization Chart
relationships
Organizational Theory
2 Staff Acquisition Getting the human 1 Staffing Mngt.Plan 1 Reassignment 1 Project Staff Assigned
resources needed 2 Environmental Factors 2 Negotiation 2 Resource Availability
assigned to & working Staffing Management Plan
on the project. 3 Project Org Charts 3 Acquisition (external to org) 3 Updates
Roles and
4 Responsibilities 4 Virtual Teams

5 Organizational Assets
3 Team Executing process Project Staff
Development that focuses on 1 Assignments 1 Forms of Power 1 Performance Assessments
building a sense of
team and improving its 2 Resource Availability 2 General Management Skills
performance
Reward & Recognition
3 Staffing Mngt Plan 3 Systems

4 Team building activities

5 Ground Rules

6 Co-location

7 Training
4 Manage Project Manage the staffing Project Staff
Team management plan and 1 Assignments 1 Observation and Conversation 1 Req'd changes (to staff)
change were needed Roles and Project Performance
2 Responsibilities 2 Appraisals 2 Rec'd Corrective Actions
3 Staffing Mngt Plan 3 Conflict Management 3 Rec'd Preventive Actions
Input to Performance
4 Project Org Charts 4 Sources of Conflict 4 Appraisals
Lesson Learned
5 Organizational Assets 5 Issue Log 5 Documentation (variance)
Team Performance
6 Assessments 6 Project Plan Updates
7 Performance Reports
8 Work Performance Info
7 Communication 1 Communications Determining the info. Communication Reqs Analysis Communications Mngt.
Management Planning & communication 1 Environmental Factors 1 (communication channels) 1 Plan
needs of the 2 Organizational Assets 2 Communication Technology
stakeholders: who 3 Project Plan
needs what
information, when 4 Scope Statement
2 Information they willneeded
Making need it info
and Organizational Process
Distribution available to project 1 Communication Skills 1 Updates
stakeholders in a Communications Mngt. Information Gathering and
timely manner 1 Plan 2 Retrieval System 2 Requested Changes
Lessons Learned Process
3 (meetings)

4 Information distribution methods


3 Performance Reporting against the Information Presentation Tools
Reporting performance 1 Work Performance Info 1 (graphical info) 1 Performance Reports
baseline--how the Performance
project is doing Measurements Information Gathering and
against the plan 2 (CV,SV,CPI,etc.) 2 Compilation 2 Forecasts
Forecasted Completion
3 (EAC, ETC) 3 Status Review Meetings 3 Requested Changes
Quality Control
4 Measurements 4 Time Reporting Systems 4 Recommended Corrections
Organizational Process
5 Approved Change Reqs 5 Cost Reporting Systems 5 Updates
6 Deliverables

7 Project Plan
4 Manage ensuring the Communications Mngt. Communications Methods
Stakeholders stakeholders are 1 Plan 1 (effective meetings) 1 Resolved Issues
heard and their needs Organizational Process
are meet 2 Organizational Assets 2 Issue Logs 2 Updates
App'd
Changes/Corrective/Plan
3 Updates
8 Risk 1 Risk Defining what level of 1 Environmental Factors 1 Planning Meetings and Analysis 1 Risk Management Plan
Management Management tolerable level of risk, 2 Organizational Process
Planning how risk will be
managed, who's 3 Scope Management Plan
responsible for risk
4 Scope Statement
activities, time and
cost associated with Project Management
risk, findings will be 5 Plan
communicated
2 Risk Determining which 1 Risk management plan 1 Documentation reviews 1 Risk Register
Identification risks might affect the Information Gathering
project and 2 Environmental Factors 2 Techniques (SWOT)
documenting their
characteristics 3 Project Scope Statement 3 Checklist Analysis
4 Project Plan 4 Assumptions Analysis
Diagramming Techniques
5 Organizational Process 5 (Ishikawa)
3 Qualitative Risk Performing a 1 Risk management plan 1 Risk probability & impact 1 Risk Registry Updates
Analysis qualitative analysis of Probability / impact risk rating
risks and conditions to 2 Risk Register 2 matrix 2 List of prioritized risks
prioritize their effects 3 Organizational Process 3 Risk Data Quality Assessment
on project objectives
4 Scope Statement 4 Risk Categorization
5 Risk Urgency Assessment

4 Quantitative Risk Measuring the Data Gathering and


Analysis probability and Representation Techniques
consequences of risks 1 Risk management plan 1 (Interviewing, Expert Judgment) 1 Risk Register Updates
and estimating their Quantitative Risk Analysis and
implications for project Modeling Techniques
objectives (Sensitivity, Tornado diagrams,
Expected Monetary Value Prioritized list of Quantified
2 Risk Register 2 analysis, Decision Trees) 2 Risk
3 List of prioritized risks 3 Modeling and Simulation
4 Organizational Process

5 Project Scope Statement


6 Project Plan

5 Risk Response Developing Negative Strategies (Avoid,


Planning procedures and 1 Risk management plan 1 Transfer, Mitigate) 1 Risk Register Updates
techniques to Positive Strategies (Exploit,
enhance opportunities 2 Risk Register Share, Enhance) 2 Project Plan Updates
and reduce threats to
the project's Compromise (Acceptance, Risk-Related Contractual
objectives Contingent Response Strategy) 3 Agreements

6 Risk Monitoring Monitoring residual 1 Risk management plan 1 Risk Assessment 1 Risk Register Updates
and Control risks, identifying new 2 Risk Register 2 Risk Audits 2 Req'd Changes
risks, executing risk 3 App'd Change Requests 3 Variance and Trend Analysis 3 Rec'd Corrective Actions
reduction plans, and
Technical Performance
evaluating their
4 Work Performance Info 4 Measurement 4 Rec'd Preventative Actions
effectiveness
throughout the project Organizational Process
life cycle. 5 Performance Reports 5 Reserve Analysis 5 Access
6 Status Meetings 6 Project Management Plan
9 Procurement 1 Plan Purchase Determining which Procurement Management
Management and Acquisition components or 1 Organizational policies 1 Make-or-buy analysis 1 Plan
services of the project 2 Project Plan 2 Expert Judgment 2 Procurement SOW
will be procured from Contract type (Fixed Price, Cost
external sources Reimbursable, Time and
3 Environmental Factors 3 Material) 3 Contract SOW
4 Scope Statement Point of Total Assumption 4 Make-or-buy decisions
5 WBS / Dictionary 5 Requested Changes

2 Plan Contracting Detailed documents Procurement


(RFPs) that will allow 1 Management Plan 1 Standard forms 1 Procurement documents
bid 2 Contract SOW 2 Expert Judgment 2 Evaluation criteria
3 Project Plan
Contract Statement of work
4 Make-or-buy Decisions 3 updates
3 Request Seller Distributing Docs then
Responses Obtaining quotations, 1 Procurement documents 1 Bidder conferences 1 Proposals
bids offers, or 2 Organizational policies 2 Develop Qualified Sellers List 2 Qualified Sellers List
proposals as
appropriate Procurement Procurement documents
3 Management Plan Advertising 3 Package
4 Select Sellers Choosing from among 1 Organizational policies 1 Contract negotiation 1 Selected Sellers
potential sellers who Procurement
will be awarded a 2 Management Plan 2 Weighting system 2 Contract
contract
3 Evaluation Criteria 3 Screening system 3 Contract Management Plan
4 Proposals 4 Independent estimates 4 Resource Availability
5 Qualified Sellers List 5 Seller Rating Systems 5 Procurement Plan Updates
6 Project Plan 6 Expert Judgment 6 Requested Changes
Procurement Document
7 Package 7 Proposal Evaluation Techniques
8 Independent estimates
5 Contract Managing the
Administration relationship with the 1 Contract 1 Contract change control system 1 Contract Documentation
seller Contract Management Buyer-Conducted Performance Organizational Process
2 Plan 2 review 2 Assets Updates
3 Selected Sellers 3 Inspections and Audits 3 Requested Changes
4 Work Performance Info 4 Performance Reporting 4 Recom'd Corrective Actions
Approved Change
5 Requests 5 Records Management System 5 Project Plan updates
6 Performance Reports 6 Payment System
7 Information Technology
8 Claims Administration
6 Contract Closure Completion and Procurement
settlement of contract, 1 Management Plan 1 Procurement audits 1 Closed Contracts
including resolution of Contract Management Organizational Process
any open items 2 Plan 2 Records Management System 2 Assets Updates
3 Contract Documentation

Contract Closure
4 Procedure

Legend:
Initiating Executing Closing
Monitoring and
Planning Controlling