Académique Documents
Professionnel Documents
Culture Documents
15-May-2013
Floor
32 31 30 29 28 27 26 25 23 22 21 20 19 18 17 16 15 14 13 12 11 10 8 7 6 5 4 2 1 G B1 B2 B3 B5& B4
Basement Podium offices Residential
24
N/A
N/A
Pre Week This Week Cumulat ive
N/A
Pre Week This Week Cumulat ive
N/A
Pre Week This Week Cumulat ive
N/A
Pre Week This Week Cumulat ive
Work type
CMU Block
Plaster
Water proofing
Marble Floor
Pre Week
This Week
Cumulat ive
Marble Wall
Pre Week
This Week
Cumulat ive
Porcelain
Parcel No.3.04 OT
IN PROGRESS Above 90% Percent complete - N/A DATA DATE EXCEEDED PLANNED START DATE DATA DATE EXCEEDED PLANNED FINISH DATE NOTE: THE ACTUAL CUMULATIIVE PERCENTAGE OF ACTIVITIES AS EXECUTED ON SITE REPORTED BY DAR ENGINEER.
KAFD KAFD Package ZoneFinishing 3 Finishing Progress Progress Track Track Sheet Sheet
Floor
32 31 30 29 28 27 26 25 23 22 21 20 19 18 17 16 15 14 13 12 11 10 8 7 6 5 4 2 1 G B1 B2 B3 B5& B4
Basement Podium offices Residential
24
N/A
N/A
Pre Week This Week Cumulat ive
N/A
Pre Week This Week Cumulat ive
N/A
Pre Week This Week Cumulat ive
N/A
Pre Week This Week Cumulat ive
N/A
Pre Week This Week Cumulat ive
Work type
False Ceiling
Wall/Partitions Wall G B
Epoxy paint
Wall Paint
Ceiling paint
Pre Week
This Week
Cumulat ive
Steel Door
Floor
32 31 30 29 28 27 26 25 23 22 21 20 19 18 17 16 15 14 13 12 11 10 8 7 6 5 4 2 1 G B1 B2 B3 B5& B4
Basement Podium offices
0%
Residential
24
Work type
Pre Week
This Week
Cumulat ive
WoodenDoors
Pre Week
This Week
Cumulat ive
Handrail
Pre Week
This Week
Cumulat ive
Kitchen Cabinet
Parcel No.3.04 OT
Floor
ROOF 17 16 15 14 13 12 11 10 8 7 6 5 4 2 1 G B2 B3 B5& B4
Planned START Dates (RCS R6.0) Basement Podium offices
B1
Residential
N/A
N/A
Pre Week This Week Cumulat ive
N/A
Pre Week This Week Cumulat ive
N/A
Pre Week This Week Cumulat ive
N/A
Pre Week This Week Cumulat ive
Work type
CMU Block
Plaster
Water proofing
Marble Floor
Pre Week
This Week
Cumulat ive
Marble Wall
Pre Week
This Week
Cumulat ive
Porcelain
Parcel No.3.05 OT
IN PROGRESS Above 90% Percent complete - N/A DATA DATE EXCEEDED PLANNED START DATE DATA DATE EXCEEDED PLANNED FINISH DATE NOTE: THE ACTUAL CUMULATIIVE PERCENTAGE OF ACTIVITIES AS EXECUTED ON SITE REPORTED BY DAR ENGINEER.
KAFD KAFD Package Zone Finishing 3 Finishing Progress Progress Track Track Sheet Sheet
Floor
ROOF 17 16 15 14 13 12 11 10 8 7 6 5 4 2 1 G B2 B3 B5& B4
Planned START Dates (RCS R6.0) Basement Podium offices
B1
Residential
N/A
N/A
Pre Week This Week Cumulat ive
N/A
Pre Week This Week Cumulat ive
N/A
Pre Week This Week Cumulat ive
N/A
Pre Week This Week Cumulat ive
N/A
Pre Week This Week Cumulat ive
Work type
False Ceiling
Wall/Partitions Wall G B
Epoxy paint
Wall Paint
Ceiling paint
Pre Week
This Week
Cumulat ive
Steel Door
Floor
ROOF 17 16 15 14 13 12 11 10 8 7 6 5 4 2 1 G B2 B3 B5& B4
Planned START Dates (RCS R6.0) Planned FINISH Dates (RCS R6.0)
Pre Week This Week Cumulat ive 0%
Basement
B1
Podium
offices
Residential
Work type
WoodenDoors
Pre Week
This Week
Cumulat ive
Handrail
Pre Week
This Week
Cumulat ive
Kitchen Cabinet
Parcel No.3.05 OT
Floor
ROOF 25 23 22 21 20 19 18 17 16 15 14 13 12 11 10 8 7 6 5 4 2 1 G B2 B3 B5& B4
Planned START Dates (RCS R6.0) Basement Podium offices Residential
24
B1
N/A
N/A
Pre Week This Week Cumulat ive
N/A
Pre Week This Week Cumulat ive
N/A
Pre Week This Week Cumulat ive
N/A
Pre Week This Week Cumulat ive
Work type
CMU Block
Plaster
Water proofing
Marble Floor
Pre Week
This Week
Cumulat ive
Marble Wall
Pre Week
This Week
Cumulat ive
Porcelain
KAFD KAFD Package Zone Finishing 3 Finishing Progress Progress Track Track Sheet Sheet
Floor
ROOF 25 23 22 21 20 19 18 17 16 15 14 13 12 11 10 8 7 6 5 4 2 1 G B2 B3 B5& B4
Planned START Dates (RCS R6.0) Basement Podium offices Residential
24
B1
N/A
N/A
Pre Week This Week Cumulat ive
N/A
Pre Week This Week Cumulat ive
N/A
Pre Week This Week Cumulat ive
N/A
Pre Week This Week Cumulat ive
N/A
Pre Week This Week Cumulat ive
Work type
False Ceiling
Wall/Partitions Wall G B
Epoxy paint
Wall Paint
Ceiling paint
Pre Week
This Week
Cumulat ive
Steel Door
Floor
ROOF 25 23 22 21 20 19 18 17 16 15 14 13 12 11 10 8 7 6 5 4 2 1 G B2 B3 B5& B4
Planned START Dates (RCS R6.0) Planned FINISH Dates (RCS R6.0)
Pre Week This Week Cumulat ive 0%
Basement
B1
Podium
offices
Residential
24
Work type
WoodenDoors
Pre Week
This Week
Cumulat ive
Handrail
Pre Week
This Week
Cumulat ive
Kitchen Cabinet
Floor
ROOF 15 14 13 12 11 10 8 7 6 5 4 2 1 G B2 B3 B5& B4
Planned START Dates (RCS R5.1) Basement Podium offices
B1
Residential
N/A
N/A
Pre Week This Week Cumulat ive
N/A
Pre Week This Week Cumulat ive
N/A
Pre Week This Week Cumulat ive
N/A
Pre Week This Week Cumulat ive
Work type
CMU Block
Plaster
Water proofing
Marble Floor
Pre Week
This Week
Cumulat ive
Marble Wall
Pre Week
This Week
Cumulat ive
Porcelain
KAFD KAFD Package Zone Finishing 3 Finishing Progress Progress Track Track Sheet Sheet
Floor
ROOF 15 14 13 12 11 10 8 7 6 5 4 2 1 G B2 B3 B5& B4
Planned START Dates (RCS R6.0) Basement Podium offices
B1
Residential
N/A
N/A
Pre Week This Week Cumulat ive
N/A
Pre Week This Week Cumulat ive
N/A
Pre Week This Week Cumulat ive
N/A
Pre Week This Week Cumulat ive
N/A
Pre Week This Week Cumulat ive
Work type
False Ceiling
Wall/Partitions Wall G B
Epoxy paint
Wall Paint
Ceiling paint
Pre Week
This Week
Cumulat ive
Steel Door
Floor
ROOF 15 14 13 12 11 10 8 7 6 5 4 2 1 G B2 B3 B5& B4
Planned START Dates (RCS R6.0) Planned FINISH Dates (RCS R6.0)
Pre Week This Week Cumulat ive 0%
Basement
B1
Podium
offices
Residential
Work type
WoodenDoors
Pre Week
This Week
Cumulat ive
Handrail
Pre Week
This Week
Cumulat ive
Kitchen Cabinet