E-690 OBJECTIVES

 Who should attend?


To provide participants with a broader understanding of project management, its objectives,
roles and techniques.

Anyone requiring a The course will present the constraints, challenges and industry practices in connection
comprehensive with the hydrocarbon field development from Discovery to First Oil/Gas. It will be illustrated
understanding of Oil & Gas by the presentation of major development projects and the projection of several projects
upstream project movies and/or pictures. Practical case studies are illustrating the magisterial course.
management techniques.
COURSE CONTENT
PETROLEUM ECONOMICS AND FIELD EVALUATION PROCESS 0.5 day
Introduction to the main elements used in connection with the economics in the petroleum industry: reserves,
associations, economic analysis, petroleum contracts
Field evaluation process from discovery to decision to develop: Field evaluation, Preliminary studies (feasibility and
conceptual study – Example of Dunbar project), Front End Engineering, Pre-project activities and project execution
plan, key documents, specifications, HSE fundamentals (HAZOP, Technical review), decision to develop
Fundamentals of cost estimating

 Duration
PROJECT ORGANIZATION 0.5 day
Project key issues, characteristics, and objectives
Different Oil & Gas project organizations - Relationship between the project content, and it’s technical challenges, the
contractor’s market conditions, on one hand, and the sponsors, contractor’s organization etc on the other hand
5 days Client’s organization for Basic Engineering, Detail Engineering, Procurement, Yard Fabrication, Onshore Works,
Offshore Works, Commissioning
Role of project leader and communication within the project team

 Dates & Location


Exercise: Case simulation for project organization
CONTRACTUAL STRATEGY AND CONTRACTS 1 day
Different contract types in view of the target, service types, and degree of responsibility of the different involved parties
November 23-27, 2009 Advantages and disadvantages of the different types
Rueil-Malmaison (Paris) Contractual strategy: Contractual Plan Option (reimbursable, at cost + fee, lump sum), Options comparison, and
how to prepare a contractual strategy?
Four main types of contractual strategy: Separate Contracts, EPSC, EPSCC, Turn Key Contracts
Contracts General: Contract Definition, Contract Documents (Agreements, Annexes, Exhibits), Call for Tender
procedure, Operator and Contractor objectives, Risks in contract performances, HSE
Contracts Particular Conditions: Review of very key but specific conditions such as contract law, Independent
Contractor, Correctness and Sufficiency of contract documents, Subcontractors, Insurances
Case study and exercise
PROGRESS AND SCHEDULE CONTROL - REPORTING 0.5 day
Preparation of Work Breakdown Structure (WBS)
Definition of terms and coherence between the Project Schedule, the Budget and the Cost Control
Initial Schedule: from the General Bar Chart to the Critical Path Schedule (PERT)

 Registration
Monitoring of the Project: Progress method, man-hours, various methods of payment
Practical exercise: Scheduling of an offshore project
TECHNICAL CONTROL OF A PROJECT 0.5 day
Fees: € 2,060
Quality aspects of a project: Quality assurance, Quality control characteristics and principles, Quality assurance
organization
Contact: Operation and maintenance philosophies
Quality control to be implemented during each phase of a project: Basic Engineering, Detail Engineering,
exp.rueil@ifptraining.com Procurement, Construction, Transportation, Pre-commissioning, Commissioning
Fax: (+33) 1 47 52 74 27 Constraints to be considered: Reference documents, Project specifications, Specific requirements, Methods, tools and
organization
Constraints to be specifically highlighted while dealing with engineering: monitoring of safety requirements, weight
control…
Functional acceptance tests and transfer of installation to production organization
Exercise
SAFETY ORGANIZATION FOR A PROJECT 0.5 day
This point is detailed through various examples and exercises
Safety engineering fundamentals, Safety aspects to be considered for operation, Safety organization

 Course Coordinator
at contractor’s sites
SCHEDULE AND COST CONTROL 0.5 day
From the Preliminary Estimate to the Initial Budget
Franck BEIJER Improvement of the cost estimate up to Basic Engineering
Preparation of the Cost Control – Cost Control Methodology: change orders, budget transfer, budget forecast
Project Financing, key aspects – Financing by shareholders - The owner’s stand point
Practical exercise: estimation of an offshore project

Ref. CONS / PROJGB DEVELOPMENT PHASES OF A PROJECT -


EXAMPLES: Dunbar, Girassol, Dalia, Canyon Express… 0.5 day
Project setting, Project organization, Contractual strategy, Technical description, Project management techniques
developed, Safety aspects - Quiz
PROJECT MANAGEMENT ISSUES 0.5 day
Project Management issues such as Project Risk Management, Project Reporting, Authorities and Partners
relationship…
Examples of critical phases for various projects such as: site stabilization, change of basic data during the project,
Contractor default…
Brief presentation of various projects and open discussions about Project Management