Declaration

I hereby declared that this report submission is my own work and to the best of my knowledge. It does not contain any material previously published or written by any other person or any material which substantial extent has been accepted for the award of any degree or diploma of a university or other institution of higher education, except where referenced are mentioned.

Rathnayake R.M.R.S.B Department of Building Economics, Faculty of Architecture, University of Moratuwa, Sri Lanka, April 2009

Acknowledgement
This research study embraces much dedication and ready assistance received from many people, who contributed in ample ways to complete this study. Consequently, I take this opportunity to convey my sincere gratefulness to every one of them. It is my foremost duty to pay my gratitude to the Department of Building Economics, University of Moratuwa, and all the academic as well as non academic staff of the department for the tremendous service rendered. I extend my gratitude to Mr. Indunil Senevirathna, Head of the Department of Building Economics, for his keen interest, encouragement and the guidance to the achievement of producing this dissertation. Furthermore, I am grateful to my supervisor, Mrs. Kanchana Perera, Senior lecturer, Department of Building Economics, for her outstanding supervision, her guidance, encouragement, and constructive criticisms significantly contributed towards the successful completion of this research. I extend my gratefulness to Dr. Sepani Senarathna, the dissertation coordinator, for her interest and dedication throughout the year. I should express my appreciation to senior lectures of the Department of Building Economics Prof. R. Rameezdeen, Mr. Suranga Jayasena, Mrs. Yasangika Sandanayaka and Mr. Sandun Fernando for their valuable guidance throughout the research process. I convey my special thanks to Mr. Lalith Rathnayaka (VForm consultants), Mr Thilak kolonne (VForm consultant),Mr. Elmo Fernando (Havelock city project) Mr. Pieris (Department of Mathematics, University of Moratuwa) for their special guidance, assistance and encouragement provided to clarify the problems of this research. I would like to convey my utmost gratitude to all the professionals of organizations who gave me a great support in many ways for the success of this research. Finally I express my heartfelt thanks for my family members, relations, colleagues and my seniors and juniors for giving me an outstanding company to make this dissertation possible.

Rathnayake R.M.R.S.B. 24th April 2009

Table of Content

Table of Contents
Acknowledgement ...................................................................................ii Table of Contents......................................................................................I List of Figures.........................................................................................II List of Tables.........................................................................................III List of Appendix.....................................................................................IV Abbreviations ..........................................................................................V Abstract...................................................................................................VI Chapter 01................................................................................................1 Chapter 02................................................................................................7 Chapter 03..............................................................................................36 Chapter 04..............................................................................................47 Chapter 05..............................................................................................76 References .............................................................................................82 Appendix ................................................................................................89

Construction Risk: Further Consideration of Technical Risk

List of Figures

List of Figures

Figure 3.1: Research Process................................................................37 Figure 3.2: Nested reseach methodology..............................................38 Figure3.3: Research methodology illustration.....................................39

Construction Risk: Further Consideration of Technical Risk

II

List of Tables

List of Tables

Table.2. 1: Risk identification process..................................................19 Table.2. 2: Risk identification................................................................19

Construction Risk: Further Consideration of Technical Risk

III

List of Appendix

List of Appendix
Appendix 01 Preliminary Survey Appendix 02 Questionnaire Survey Appendix 03-A Interview Guideline Appendix 03-B Interview Transcript Appendix 04 Calculating Reliability Using SPSS Appendix 05 Summary of Calculated Cronbachs Alpha Appendix 06 Calculation of RII

Construction Risk: Further Consideration of Technical Risk

IV

Abbreviations

Abbreviations
BOQ CQS FIDIC ICTAD QS RII SBD - Bills of Quantities - Chief Quantity Surveyor - Federation International Des Ingenieurs- Counseils - Institute for Construction Training and Development - Quantity Surveyor - Relative Important Index - Standard Bidding Document

Construction Risk: Further Consideration of Technical Risk

Abstract

Abstract
Construction is a highly risk-prone industry without a very good track record of coping with risks. The participants in the industry, as a result, have been enduring the agonizing outcomes of failure in the form of unusual delays in project completion, with cost overruns and sometimes failure to meet quality standards and operational requirements. Thus, an effective analysis and management of construction associated risks remain a big challenge to the industry practitioners. Moreover, it is crucial to correctly classify important technical risks. Consequently, this research was mainly focused on identification of the critical risks both significant in occurrence and impact, the performance in construction lifecycle, and allocation of technical risk among contracting parties in building construction projects in Sri Lanka. This paper presents a comprehensive methodology that addressed all above mentioned objectives. To understand the perceptions of construction practitioners on technical risks in Sri Lankan building construction projects is an important step in this process, a questionnaire survey and structured interviews were conducted and 24 technical risks were identified and evaluated by using relative importance index. According to the collected data and the results of the statistical analysis procedures employed, the most severe technical risks encountered by the contracting parties in the Sri Lankan building construction industry are: 1) Shortage in skillful workers; 2) Design changes / Design variations by client; 3) Inadequate program scheduling and tight program scheduling; 4) Materials shortage; 5) Estimation errors; 6) Unusual weather and force majeure; and 7) Unknown site physical conditions. Mainly significance of technical risk factors, considering time, cost, and quality were figured out. Moreover the performance of technical risk factors in construction lifecycle and perception about the allocation of technical risk factors among construction parties were figured out. It is important to consider those factors when considering a building construction project and depending on the project perspectives type technical risk factors to be considered also change. Keywords: Technical Risk, Construction Project Lifecycle, Building Construction Project, Risk Allocation, Critical Risk.

Construction Risk: Further Consideration of Technical Risk

VI

Introduction

Chapter 01
1 INTRODUCTION
1.1 BACKGROUND

The concept of risk can be applied to nearly every human decision making action of where, the consequences are uncertain (Flanagan and Norman 1993). The word of risk has entered in to the English language in the mid 17 th century, coming from the French word risqu (Covello and Mumpower 1985 cited Thilakarathne 2007). Cooper and Chapman (1987 cited Dent 1997, p. 1) define risk as exposure to the possibility of economic or financial loss or gain physical damage or injury or delay as a consequence of the uncertainty associated with pursuing a particular course of action. Construction industry is one of the most dynamic and challenging industries (Woodward 1997) and it is subjected to more risk and uncertainty than many other industries (Flanagan and Norman 1993). Furthermore, according to Patrick et al. (2007), Kangari (1995), Uher and Toakley (1999), and Thevendran and Mawdesley (2004), risk relates to construction industry and obviously it is related to construction projects. Hence, construction projects consistently expose to various sources of risks (Poh and Tah 2006). Those risks can effect to productivity, performance, quality, and budget of a construction project (Kangari 1995). However, risks cannot be eliminated (Patrick et al. 2007), but it can be minimized or transferred from one stakeholder to other stakeholder in the construction process (Kangari 1995). Thus, formal and efficient risk management process is needed to manage all types of risks in construction projects (El-Sayegh 2008). Consequently, management of risks has turned into a main part of the organizational activities (Flanagan and Norman 1993). The risk management is a tool which control risks in construction projects (Hamshayini 2007, p. 1). The main aim of risk management is to assist all construction project aims (Mills 2001) by mitigating the risk, transferring the risk to other parties, or sharing the risk among the parties
Construction Risk: Further Consideration of Technical Risk 1

Introduction

(Rahman and Kumarasami 2005). Similarly Kangari (1995) figured out, risk management is an important part of the decision making process in construction projects. Therefore, it is evident that, risk management has been commonly applied across the construction sector in project level (Thevendran and Mawdesley 2004, p. 131). Risk management is a process which, aims to identify and assess risks in order to enable them to be understood clearly and managed effectively (Hilson 2003, p. 85). Furthermore, Shen (1997) suggested that a systematic process of risk management should include: risk identification; risk analysis; and risk responses, where as risk responses has been further divided into the four actions: risk retention; risk reduction; risk transfer; and risk avoidance for managing risk in construction projects. Risk identification is the first stage of risk management. It develops the basis for the next step: analysis and control of risk management. Therefore, the correct identification of risks ensures the effectiveness of risk management (Tchankova 2002). Uher and Toakley (1999) further substantiated the same argument indicating that the concept of risk identification appears to be the most known and practiced out of the three phases involved in risk management. In addition, there has been an increase in research on risk management practices in the construction industry (Rahman and Kumaraswamy 2005), (Archbold 2006), (Akintoye and Macleod 1997). However, Rahman and Kumaraswamy (2005) argued that, little research has been conducted in foreign countries to investigate the overall consequences and uncertainties systematically in construction risk management for various project participants. Construction risks are allocated to different parties through contract conditions, but each and every risk item is difficult to foresee at the outset, due to the natural complexity and uncertainty that exists in construction projects (Akintoye and Macleod 1997). Moreover, Kunishima and Shoji (1996) argued that, the objectives of construction projects could defer from country to country or nation to nation, and all nations and regions of the world may have their own characteristics (cited Andi 2006). Because there are differences in way of living, way of thinking, and way of value systems, and similarly, it could differ their ideas of managing risks. Therefore,
Construction Risk: Further Consideration of Technical Risk 2

Introduction

the management of risk is significantly influenced by the uniqueness of the construction industry of that particular country. As such as, it emphasizes a need of in depth investigation to the overall consequences and uncertainties in construction risk management for a variety of project participants in Sri Lankan context. Besides, according to the empirical study by Kangari (1995) revealed that management practices are mainly focused on construction risk allocation towards perception of the typical large contractors and owners. Further, the same study emphasized the identification of strategies or usage of risk management techniques to add value to project delivery and improve the effectiveness of the construction industry throughout of the process of construction. To handle risks in construction projects appropriately, it is required to assign them scientifically among parties (El-Sayegh 2007). Thus, scientific assignment of risk among project parties can be achieved by only if it analytically investigates the overall consequences and uncertainties in construction risks and risk supervision (Andi 2006). More importantly, this can only be achieved if all parties do understand their risk responsibilities properly (Perera 2006). Identification of sources of risk is vital aspect in risk management process (Tchankova 2002). Edward and Browen (1998) supported the same argument stating that for a proper risk management process, it has to first identify source of risks. Further, the same study classified the sources of risks in to nine categories: financial; legal; management; market; policy; health; cultural; social and political risks. However, among all these risks sources/ factors, the technical risk sources/ factors are not well-represented or not evident in risk management literature (Edwards and Broun 1998). According to above mentioned findings and facts, to trounce them and fill the gap, which had already figured out. Thus, this emphasized a need of research in risk management area with orientation to identify and analyze possible risk factors associated with building construction process and consequences and uncertainties towards contractors and owners. further to assess their towards project parties/stakeholders; specially

Construction Risk: Further Consideration of Technical Risk

Introduction

1.2 RESEARCH PROBLEM


Even though there were researches which were conducted by the researchers (Danasinghe 2007), (Hamshyani 2007), (Thilakarathne 2007), (Pushpakumara 1997) in Sri Lanka related to several aspects of risk in construction they have not considered the technical risks in building construction. Further, above discussed facts also revealed that, the consideration of the technical risk in construction projects is enormously significant. Therefore this research was done on Construction Risks: Further Consideration of Technical Risks for the Sri Lankan Building Construction industry.

1.3 AIM OF THE RESEARCH


The aim of this research was to identify, and analyze technical risk factors in the building construction.

1.4 OBJECTIVES
Identify the technical risk factors associated with building construction Analyze the allocation of risk factors among construction parties. Figure out consequences of above risks on project goals Identify the performance of technical risk in construction lifecycle.

1.5 METHODOLOGY
1.5.1 LITERATURE SURVEY AND REVIEW
Comprehensive preliminary literature survey was carried out based on journals, books, articles, conference proceeding, census reports, government publications, dissertations, previous research investigations and internet. Further review carried out to acquire the theoretical knowledge regarding the research area and required analysis.
Construction Risk: Further Consideration of Technical Risk 4

Introduction

1.5.2 PRELIMINARY SURVEY


Preliminary survey carried out to identify most critical technical risk factors in Sri Lankan building construction industry and to identify some building projects for further study.

1.5.3 QUESTIONNAIRE SURVEY


A detail questionnaire survey carried out to determine significant technical risk factors and response to those risk factors from practitioners in construction industry. Moreover, structured interviews were conducted, in order to gain practical experience and opinion on risk allocation to construction parties and occurrence of risk factors in construction lifecycle simultaneously with questionnaire survey.

1.6 SCOPE AND LIMITATIONS


This research was limited to technical risk factors, which are affecting to building construction in Sri Lanka.

1.7 GUIDES TO DISSERTATION


This dissertation was structured into five chapters namely as introduction, literature synthesis, method of study, analysis and findings and conclusions, recommendations and further research. Chapter 01:- Introduction Chapter one presents the background to the study, aims and objectives, scope of the study with the organization of the report.

Construction Risk: Further Consideration of Technical Risk

Introduction

Chapter 02:- Literature synthesis This chapter explains briefly about risk management with the use of literature and figure out possible risk factors according to past researches. It also illustrates the classification of risk sources and critical risk source. Chapter 03:- Method of study In this chapter, research methodology is described in detail. Furthermore, details about background study, research design, method of data collection, and method of data analysis or the data analysis technique are included. Chapter 04:- Analysis and finding This chapter consists with the finding of the preliminary survey, questionnaire survey, structured interviews, and comprehensive analysis of those findings. Chapter 05:- Conclusions, recommendations and further research This chapter concludes the research findings, emprise recommendations, and areas to be considered when doing further researches

Construction Risk: Further Consideration of Technical Risk

Literature Review on Risk Management

Chapter 02

2. LITERATURE REVIEW ON RISK MANAGEMENT


2. 1 INTRODUCTION
This is an overview of risk management practice in construction industry. Mainly, it focuses on different risk factors influencing in decision-making process. Further, how it is going to handle in building construction industry in Sri Lanka. Initially, in this review it discuses about the risk, its behavior, and relation to construction industry, which exposes to unpredictable environmental circumstances and how these risky circumstances encountered in different behaviors undertaken by parties in construction. Secondly, it describe the approaches and the management strategies, which can be adopted in achieving project goals and reviewed risk management process in detail manner, giving more emphasis to risk identification and risk response. Further, it is concerned on construction project, its relationship to risk, and need of risk management to construction project. Moreover, it illustrate about classifications of the construction risk, and technical risk and its relationship to contraction projects, construction parties intervene to the risk management in construction project, and behavior of the technical risk with the construction life cycle. Furthermore, this literature chapter illustrated about the need of risk management to Sri Lankan construction industry. Finally, the literature survey has wound up by reaching to the research topic, Construction Risks: Further Consideration of Technical Risks , which would support to identify prevailing technical construction risk factors, analyze the allocation of all risk factors among construction parties and figure out consequences of risk factors to project goals and figure out the magnitude of technical risk in stages of building construction project lifecycle.
Construction Risk: Further Consideration of Technical Risk 7

Literature Review on Risk Management

2.2 CERTAINTY, UNCERTAINTY, AND RISK


The construction industry is enormous or complex and construction projects involve hundred or even thousands of interacting activities, each with a cost, time, quality, and it is burdening with more risk and uncertainties than many other industries (Flanagan and Norman 1993). In addition according to Burchett (1999), risk and uncertainty can spoil the construction activities (cited Mills 2001). Therefore, it is important to define these concepts separately. Further, should understand to making decisions in construction industry (Flanagan and Norman 1993). According to Storner et al. (1995), decision-making is using during planning process to identify and selecting course of action to deal with specific problem or to take advantage of an opportunity. Due to that, decision-making implements under deferent circumstances and mainly these situations can categorize into three such as decision making in certainty, decision making in risk, and decision making in uncertainty (Thilakarathne 2007).

2.2.1 CERTAINTY
Certainty is the situation where the outcomes are consistent, measurable, and accurate from all available alternatives that can be occurred (Storner et al. 1995). Further, more according to Kerzner (2001); there is a hundred percent accuracy for all alternatives, which can be occurred in a particular situation, when there is a certainty to make decisions.

2.2.2 UNCERTAINTY
Flanagan and Norman (1993, p. 22) define the uncertainty as the situation in which there are no historic data or previous historic relating to the situation being considered by the decision-maker. Besides, Stoner et al. (1995) defines as unpredictable external conditions or lack of information needed to establish the probability of events. According above both definitions and Thilakarathne (2007) s argument it is revealed that the uncertainty is the situation where, there is no any

Construction Risk: Further Consideration of Technical Risk

Literature Review on Risk Management

information to predict future events based on probability and it is the worst condition in decision making.

2.2.3 RISK
The word risk is quite modern and it is coming from the French word risqu in mid 17th century to the English vocabulary (Flanagan and Norman 1993). Risk is primarily related to rewards, some risk should be accepted as long as they are in line with the rewards (El-Sayegh 2007, p. 441). Risk is an unavoidable component of all activities (Wang 2002). The word risk is defined as the possibility of something bad happening in sometime in the future; a situation that could be dangerous or have a bad result in the Oxford Advance Learners dictionary (2000, p.1105) Furthermore, Cooper and Chapman (1987 cited Dent 1997, p. 1) defined risk by considering the practical behavior of risk as Exposure to the possibility of economic or financial loss or gain, physical damage or injury, or delay, as a consequence of the uncertainty associated with pursuing a particular course of action. Besides, Flanagan and Norman (1993) define the risk considering the assessable of risk as measurable uncertainty, while uncertainty is as immeasurable risk. However, when consider the project risk; it is defined by El-Sayegh (2007, p.1) as an uncertain event or condition that, if it occurs, has a positive or negative effect on at least one project objective such as time, cost, scope, or quality. According to the definitions of risk given by the Cooper and Chapman (1987 cited Dent 1997), Flanagan and Norman (1993), El-Sayegh (2007) it can be convinced that risk is generally referred to economical or physical loss rather than gain due to measurable uncertainty, while uncertainty is as immeasurable risk. Even, there are many definitions for the risk given by several researchers, for this research considers the Cooper and Chapman (1987 cited Dent 1997) definition as the definition for the risk.

Construction Risk: Further Consideration of Technical Risk

Literature Review on Risk Management

Risk is the potential for unnecessary or negative consequences of an event or activity (Rowe 1997), a combination of hazard and exposure (Chicken and Posner 1998). Achrol (1988 cited Kolltveit 2004) has distinguished uncertainty and risk as following way: situations where having a known probability of occurrence of outcome due to particular activity are called risk, while uncertainty arises with the unknown outcome of event. Moreover, Stoner et al. (1995) illustrate risk as a situation where the decisions made by decision makers mainly by considering probabilities calculated using historical information in that particular incident.

Certainty

Risk

Uncertainty

HIGH

MANAGERIAL CONTROL

LOW

(Source- Stoner et al. 1995)


Figure 2. 1: Decision Making Spectrum

2.3 IMPORTANCE OF UNDERSTANDING THE RISK


Particularly, the industries, organizations, and projects that are having complex structure and technical complexity are heavily exposed to the risk (Zou et al. 2007). Furthermore construction projects are one off endeavors with many unique futures such as long period, complicated process, abominable environment, financial intensity and dynamic organization structure (Flanagan and Norman 1993), (Smith 1999, cited Zou et al. 2007). Risk cannot eliminate but they can transfer from one party to another or share among parties through contract clauses (Andi 2006). Therefore, understanding the concept of risk and understanding the behavior of risk is very much important to manage the risk successfully to achieve targets in every aspect where risk is related (Flanagan and Norman 1993).

Construction Risk: Further Consideration of Technical Risk

10

Literature Review on Risk Management

2.3.1 IMPACT OF RISK


Following figure gives a simplified view of the risk hierarchy,

The Environment The Market/ Industry The Company The Project/ Individual

(Source- Flanagan and Norman 1993)


Figure 2. 2: The Risk Hierarchy

Impact of Risk to the General Environment The general environment is that which affect all organizations in given society. Therefore according to Flanagan and Norman (1993) the impact of risk to the general environment will be issue to every society aspects and it can be divided in to two parts, firstly the physical and secondly the political, social and economic. They further argued that the risk arising from physical environment can be identified and steps can be taken to mitigate them. However, for the political, social, and economic only government can control the environment risk (Jamil et al. 2008).

Impact of Risk to the Market / Industry and company The risk which is occurs countrywide or worldwide and it will cause to the market and ultimately to the industry (Flanagan and Norman 1993). Typically, industry and the market contain large number of small and companies or organizations then such kind of risk will cause to the organizations Dent (1997).

Construction Risk: Further Consideration of Technical Risk

11

Literature Review on Risk Management

Impact of Risk to the Project Risk can affect productivity, performance, quality, and budget of construction project (Kangari 1995). Moreover, Andi (2006) emphasize that, failure to adequately dealing with risk will be cause cost and time overruns in construction projects. However, Ahamad and Azar (2004) have given most serious effects precisely that can be occurring due to risk in construction projects from project management point of view and it can be summarized as follows: Failure to keep within the cost estimate Failure to achieve the required completion date Failure to achieve the required quality and operational requirements This research is mainly limited the study to the project level.

2.4 CONSTRUCTION RISK AND RISK MANAGEMENT


Construction risk is usually perceived as events that influence project objectives of cost, time, and quality (Ahamad and Azar 2004, p.1). According to Wong et al. (2004), Andi (2006), Zou et al. (2007), Flanagan, and Norman (1993), elimination of all risks in construction projects is impossible. Further, it emphasizes on significance of construction risk and risk management approaches in construction to offload the risk consequence under following topics.

2.4.1 WHY RISK IN CONSTRUCTION


Usually construction industry continually faces with a variety of situations involving many unknown, unexpected, frequently undesirable, and often unpredictable situations and factors (Fong 1987). According to Kangari et al. (1989 cited Akintoye and Macleod 1997), these situations are not limited to the construction industry. Therefore, construction industry naturally exposes to risk more than other industries and risk inherent in every construction project (Kangari 1995). Moreover, the size and complexity of construction projects are increasing which adds to the risks (El-

Construction Risk: Further Consideration of Technical Risk

12

Literature Review on Risk Management

Sayegh 2007). Further, according to El-Sayegh (2007, p. 431) construction projects are perceived to have more inherent risk due to the investment of many contracting parties such as designers, contractors, subcontractors, suppliers, etc.. Besides, Stoner et al. (1995) and Hastak and Shaked (2000 cited Wang 2002) illustrate the construction project risk as, it has to be operated in an environment where there are many uncertainties so that the aim will be operate on risk. Therefore, risk relation to construction as a variable in the process of a construction project whose variation results in uncertainty as to the final cost, duration, and quality of the project (Bufaied 1987, cited Akintoye and Macleod 1997). Due to these reasons, use of specific risk management will ensure the full control to mitigate the risk in construction.

2.4.2 RISK MANAGEMENT


Risk management was introduced as a separate new field to the construction industry to respond to the increasing uncertainties and its importance has been realized with the increasing of practical usages or practical applications (Thomas and Bone 2002, cited Thevendran and Mawdesley 2004) Risk management is an important consideration for all aspects of decision making in constructions and construction projects and there is a considerable body of literature dealing with the topic of risk management (Ahamad and Azar 2004), (Uher and Toakley 1999), (Akintoye and Macleod 1997). Risk management is defined as a procedure to control the level of risk and to mitigate its effects (Toakley 1989 cited Uher and Toakley 1999, p. 161), the generally recognized steps entailed are risk identification, risk analysis and risk response (Uher and Toakley 1999, p. 161). Further, according to Flanagan and Norman (1993), risk management is a structure, which aims to recognize and enumerate all risks to which the business or project expose so that a conscious decision can be taken on how to manage the risks. Moreover Zou et al. (2007), define the risk management as a process, which is build to understand risks caused towards the achieving of goals and what should be done to ensure success.

Construction Risk: Further Consideration of Technical Risk

13

Literature Review on Risk Management

However, when consider above-mentioned definitions with compare to Nummedal et al. (1996 cited Ahamad and Azar 2004) definition of risk management such as a process to control the level of risk and to mitigate its effects and it is a systematic approach for identifying, evaluating, and responding to risks encountered in a project. It is convinced that that the risk management is a systematic process to identify, evaluate and responding to risks encountered in a project. Nummedal et al. (1996 cited Ahamad and Azar 2004) definition takes for this research as the definition for the risk management. The application of systematic risk management in construction projects has long been recognized as an effective approach to minimizing risk impacts (Flanagan and Norman 1993) and it will aims to identify and assess risk in order to enable them to be understood clearly and managed effectively (Hillson 2003).

2.4.2.1 SYSTEMATIC RISK MANAGEMENT PROCEDURE Systematic approach of risk management will be given assurance to the risk management process by minimizing the missing of risk factors and there affect. Basically, a systematic risk management process consist with three steps

(Source- Dent 1997)


Figure 2.3: Risk Management Umbrella

Construction Risk: Further Consideration of Technical Risk

14

Literature Review on Risk Management

Further, it is illustrate by using following figure by Dent (1997), simply understand the risk management procedure and to do risk management in systematic way. (Source- Dent 1997)

Figure 2.4: Risk Management Process Diagram

Risk management process is cyclical one (Poh and Tah 2006), and according to Dallas (2006) risk management should be viewed as a continuous activity throughout the development of a project, resulting in a steady reduction of the level of risk across the project as it proceeds. As a project evolves, some risks will allocate to deferent parties in the project team, some will pass and no longer represent a threat, and new risks will emerge. Some management actions will prove effective, others

Construction Risk: Further Consideration of Technical Risk

15

Literature Review on Risk Management

less so, figure outlines the key activities in this iterative process. Cyclical nature of risk management is shown in following figure more detail by considering the above three steps of risk management, which is defined by Dent (1997).

Risk identification

Risk monitoring

Risk estimation

Controlled risk environment

Risk evaluation

Risk response

(Source- Dallas 2006)


Figure 2. 5: Risk Management Cycle

By considering risk management procedure diagram with the risk management cycle can demonstrate as following,

Risk identification Risk estimation Risk evaluation

Risk identification and classifying Analysis the risk Respond to risk

Risk response Risk monitoring

Risk Identification and classification

Construction Risk: Further Consideration of Technical Risk

16

Literature Review on Risk Management

Risk identification is the first phase of risk management and it is extremely important for all construction projects (Jamil et al. 2008). Because, it develops the foundation for next steps; analysis and control of risk management (Flanagan and Norman 1993). Accurate risk identification ensures all losses or gain that challenge the

organization or the project, then these non-identified risks will become nonmanageable (Greene and Trieschmann 1984 cited Tchankova 2007) Besides Al-Bahar (1988 cited Al-Bahar 1990, p. 534), risk identification is defined as the process of systematically and continuously identifying, classifying, and assessing the preliminary significance of risks associated with a construction project. According to Flanagan and Norman (1993), risk identification done considering the Sources of risk, events that are arising from that particular source of risk and effects caused by those events it is shown in following figure 2.6. Source Events Effects

(Source- Flanagan and Norman 1993)


Figure 2. 6 : Risk Identification

Further, Tchankova (2007) argue that the attention of risk manager should not be concentrated only on what can be insured or mitigated and it should start with the basic questions: How can the organizational resources be threatened? What adverse effect can prevent the organization from achieving its goals/ What favourable possibility can be revealed?

According to Dent (1997) and Flanagan and Norman (1993) Identification can be further illustrated by considering the followings factors of risk, Likelihood
17

Construction Risk: Further Consideration of Technical Risk

Literature Review on Risk Management

Controllable Uncontrollable Types Severity

The objective of risk identification is to identify all possible risks (Highways agency 2001), categorize risks that could affect the project (Kangari 1995), and document these risks (Flanagan and Norman 1993), not to eliminate risks from consideration or to develop solutions for mitigating risks and those functions are carried out during the risk assessment and risk mitigation steps. Some of the documentation and materials should use in risk identification as they become available include these. Risk identification process Moreover, the degree, to which the identification process will influence the effectiveness of risk management and its contribution to the overall project management of any particular project, is dependent on the way the steps of the process are implemented (Chapman 2001, p. 147). Furthermore, proper implementation of these steps will ensure better effectiveness of identification process and it will guide to better understanding of risk. Moreover, the key factors involved in each step of the risk identification process demonstrate in following figure and table. There are six steps involved in the risk identification process. The following sections will discuss each step separately (Al-Bahar 1988 cited Al-Bahar 1990). Risk RiskIdentification IdentificationProcess Process
Existence Uncertainty Preliminary Checklist Risk Events/ Consequence Scenarios Logical Risk Classification Scheme Risk Category Summary Sheet Construction Risk: Further Consideration of Technical Risk Risk Mapping

18

Literature Review on Risk Management

(Source- Al-Bahar 1988 cited Al-Bahar1990)


Figure 2. 7 : Risk identification process

Table.2. 1: Risk identification process

Step Existence of Uncertainty Preliminary Checklist Risk Events/ Consequences Scenarios Risk Mapping

Key Issues Recognize the existence of uncertainty about particular risks associated with the project List all potential risks that can possibly occur in the project Identify different risk events and consequent scenarios associated with each potential risk Assess the significance of identified risk by constructing the risk curve

Logical Classify the identified potential risks according to Classification their nature and potential impact Scheme Risk Category Integrate the participation of all personnel involved Summary Sheet in the project management team (Source- Al-Bahar 1988 cited Al-Bahar1990)

According to Highways Agency (2001), risk identification process begins with the team compiling the project's risk events and identification process will vary, depending on the nature of the project and the risk management skills of the team members, but most identification processes begin with an inspection of issues and concerns created by the project development team. Further, these issues and concerns are able to derive from an examination of the project description, work breakdown structure, cost estimate, design and construction schedule, procurement plan, or general risk checklists. A number of documents and tools are available to support the risk identification process. Following table provides an example of project-specific documents, programmatic documents, and techniques available for risk identification.
Table.2. 2: Risk identification

Construction Risk: Further Consideration of Technical Risk

19

Literature Review on Risk Management

Project Specific documents Project description Work breakdown structure Cost estimate Design and construction schedule Procurement plan Listing of team's issues and concerns

Programmatic Documents Historic data Checklists Final project reports Risk response plans Organized lessons learned Published commercial databases Academic studies

Techniques Brainstorming Scenario planning Expert interviews Nominal group methods Delphi methods Crawford slip methods Influence or risk diagramming

(Source- Highways Agency 2001)

There is significant evidence in literature that checklists (Jamil et al. 2008), Delphi method, expert interviews, and document, which are specific to the project, are most popular methods of risk identification Akintoye and MacLeod (1997).

Importance of risk identification According to Hayes et al. (1987cited Hassanein and Afify 2005), many managers believe that the principle benefits of risk management come from the identification rather than analysis stage. Moreover, Hayes et al. (1987 cited Afify and Hassanein 2005) argued that, for them great benefits comes from the discipline of thinking through the project, understanding the potential risks, and considering possible responses. Besides, Bajaj et al. (1997) also supported to that argument and further they printout following causes, might occur unless otherwise use a proper risk identification process,

Failure to keep within the cost estimate Failure to achieve the required completion date Failure to achieve the required quality and operational requirements
Construction Risk: Further Consideration of Technical Risk 20

Literature Review on Risk Management

Risk Estimation and analysis Risk analysis is the process of quantifying the various risk elements identified in previous sections (Kangari 1988, p. 117). The essence of risk analysis is that it attempts to capture all feasible options and analyze the various outcomes of any decisions (Flanagan and Norman 1993). Moreover, Risk analysis and evaluation defined by Al-Bahar (1988, p. 118) as A process which incorporates uncertainty in a quantitative manner, using probability theory, to evaluate the potential impact of risk. Risk estimation and analysis process Al-Bahar (1988) has developed a schematic process to risk estimation and analysis as shown in following figure 2.8,

Risk RiskAnalysis Analysisand andEvaluation EvaluationProcess Process


Data Collection

Objective Statistical Data Modeling Uncertainty

Subjective Judgmental Data

Assessment of
Potential Consequences Evaluation of Potential Impact of Risk

Assessment of Probability Distribution

(Source- Highways Agency 2001)


Figure 2. 8 : Risk analysis process

Further, Flanagan and Norman (1993) has been introduced six steps to follow when estimating and analyzing to achieve it very successfully and six steps can be illustrated as follows,

Construction Risk: Further Consideration of Technical Risk

21

Literature Review on Risk Management

Step 1: All the various option should be considered Step 2: Consider the risk attitude of decision maker Step 3: Consider what risk have been identified, which are controllable and what the impact is likely to be

Step 4: Interpretation of the results of the analysis and development of a strategy to deal with the risk

Step 6: Decide what risks to retain and what risks to allocate to other parties

Risk Estimating or Risk Analysis Methods According to Ward and Chapman (1997 cited Ahamad and Azahar 2004), there are two decision criterias has developed to facilitate the decision making process in qualitatively or quantitatively. Quantitative risk analysis is a way of numerically estimating the probability that a project will meet its cost and time objectives and it give accurate results than the qualitative method if the available data is strong and reliable (Osama and Almishari 2003). Therefore, to define the fundamental decisions, the practical approach should be made by each participant in the project and to model the project in terms of categories of sources of risk (Kerzner 2001). Such kinds of approaches are as follows, Delphi techniques Monte Carlo simulation Sensitive analysis Decision analysis

Response to Risk Risk response is the process of mitigation risk (Tah and Carr 2000) and that can be done by using proper allocation, which should consider the ability to absorb the risk

Construction Risk: Further Consideration of Technical Risk

22

Literature Review on Risk Management

and the incentives being offered to carry it (Flanagan and Norman 1993). Further response to risk can take any of four basic forms as shown in figure2.9, Risk Response

Risk Retention

Risk Reduction

Risk Transfer

Risk Avoidance

(Source- Flanagan and Norman 1993)


Figure 2. 9 : Risk Response

Risk Retention Risk, which produces individually small, repetitive losses are those most suited to retention (Flanagan and Norman 1993, p. 62), the level of retention decided by the financial circumstance, and it is based on probability of a claim for damages and what parties can afford to pay if the claim is successful (Carter and Doherty 1974).

Risk Reduction According to Flanagan and Norman (1993) one approach of reducing the risk exposure is distribute risk among parties and risk reduction falls into four basic categories, Education and training to alert the staff to potential risks Physical protection to reduce the likelihood of loss System are needed to ensure consistency and to make people ask the what if questions Physical protection can be taken to protect people and property

Risk Transfer Risk transferring is the process of assigning uncertainty factors to the various parties involved (Thompson and Perry 1992). Risk allocation defines the proportion of risks be shared by owner, designer, contractor, and perhaps other parties (Baker et al.

Construction Risk: Further Consideration of Technical Risk

23

Literature Review on Risk Management

1999). The contract documents allocate risks and establish the relationship of parties in a construction contract (Kangari 1988). Risk transferring does not reduce the risk it just transfer the effect of risk to another party. It means, anyhow one party has to bare or absorb the risk (Flanagan and Norman 1993). Common method of transferring risk is the insurance and further it can be transferred by pricing considerably high, by using sub contracting and claims (Hertz 1964 cited Baker et al. 1999).

Risk Avoidance Risk avoidance means refuse to accept risks. Risk avoidance is normally associated with pre-contact negotiations (Flanagan and Norman 1993). Further, risk avoidance refers as risk elimination and there are number of ways through the risk can be avoided. Such as by tendering a very high bid (Carter and Doherty 1974 cited Baker et al. 1999), either avoid certain risk or avoid certain consequences following from risks and most pertinent example of risk avoidance is the use of exception clause (Flanagan and Norman 1993).

Risk Monitoring Final stage of the risk management is the risk monitoring and the process of risk monitoring should assure the appropriate control in place for organizations activities and that the procedures, understood and followed (Tah and Carr 2000). Further, during the risk monitoring, it should monitor the result of risk management approaches also and it will provide basis for the updating of existing risk management approach to get success output (Kerzner 2001 cited Thilakarathne 2007).

2.5 PROPERTIES OF PROJECT RISK


Construction projects are unique and built only once and they involve a temporary project team that assembles from different companies, countries, cultures, etc.

Construction Risk: Further Consideration of Technical Risk

24

Literature Review on Risk Management

Moreover, the size and complexity of construction projects is also higher (El-Sayegh 2007). Due to that reason construction project expose to risk (Flanagan and Norman 1993). Trying to eliminate all the risks, which are occurs in construction projects also is impossible (Wang et al. 2004).

2.5.1 GENERAL PROJECT RISK CHARACTERIZATION


El-Sayegh (2007, p. 431) defines the project risk as an uncertain event or condition that, if it occurs, has a positive or negative effect on at least one project objective, such as time, cost, scope or quality. Furthermore, construction project risk can broadly classify as either objective or subjective (Flanagan and Norman 1993). Risks relate to rewards and some risks should accept as long as they are in line with the rewards (Barber 2005). Due to that, every project contains some degree of risk (El-Sayegh 2007) and risks are threats to project success (Barber 2005) Failure to adequately deal with risks has been shown to cause cost and time overruns in construction projects (And 2006).

2.5.1.1 NEED OF RISK MANAGEMENT IN CONSTRUCTION PROJECTS Clients, contractors, the public, and others have suffered, because of the construction, industry has a poor reputation in coping with risks and due to that many projects failing to meet deadlines and cost targets (Edwards 1995). Besides, previous researchers (Shen 1997), (Hillson 2003), (Kangari 1995), (El-Sayegh 2007) Suggested that, construction activities are particularly subjected to risk. Then naturally, construction projects expose to risk. Furthermore, that creates uncertainty in construction projects (Flanagan and Norman 1993). Moreover according to Hillson (1999 cited Hillson 2003); risk management has been accepted as a significant advance to dealing with the predictable uncertainty, aiming to minimize threats and maximize opportunities while maintaining a focus on success of objectives. Therefore, it is important to employing effective risk management techniques to deal with risks associated variable construction activities, which are related construction
Construction Risk: Further Consideration of Technical Risk 25

Literature Review on Risk Management

projects. Because effective risk management will ensure project objectives including time, cost, quality, safety and environmental sustainability (Zou et al. 2007).

2.5.1.2

RISK

MANAGEMENT

STRATEGIES

IN

CONSTRUCTION

PROJECTS Once the risks of a project have identified and analyzed, appropriate risk response strategies must be adopted to cope with the risks in the project implementation (Adams 2006). The treatment measures on each risk base on the nature and impact of the risk. Further, the main aim is to remove as much as possible the potential negative impact and to increase the level of control of the risks. However, the process of risk management does not aim to eliminate all risks but to identify appropriate strategies to assist project stakeholders to manage them (Perry and Hayes 1985 cited Zou et al. 2007). These strategies apply in situations experiencing uncertainty in order to ease decision-making regarding the projects future. These beneficial and practicable developments have resulted in construction practitioners becoming progressively aware of the importance of using these techniques at various stages of a project to achieve greater project success. However, there is a significant shortfall in the available risk management techniques. (Thevendran and Mawdesley 2004)

2.6 CONTRACTING PARTIES BEHAVIOR WITH PROJECT RISK


Many kinds of risk are inherent in the construction process and contractors are mange it, owners pay for it (Kangari 1995). Further, according to Andi (2006) risk has to be shared among contracting parties. Moreover, contracting parties behaviour with construction project risk illustrate by using following topics,

Construction Risk: Further Consideration of Technical Risk

26

Literature Review on Risk Management

2.6.1 OWNERS ROLE AND PROJECT RISK


As the project originator, the owner is the one who determines the nature and scope of the project (Flanagan and Norman 1993). Accordingly, the owner is the one who initially bears all of the risks of unsatisfactory results. However, the owner also has the unique ability to transfer or allocate these risks (Andi 2006).

According to, American Council of Engineering Companies and Associated General Contractors of America, there are two ways owner can address the project risk as follows; Transfer all risk of loss to other construction project parties Sensible allocation and management of risk

2.6.2CONTRACTORS ROLE AND PROJECT RISK


Primarily burden of risk in construction project falls between the contractor and client and insurers will often carry low probability high impact risk, such as fire or collapse (Flanagan and Norman 1993). Furthermore according to Rahman and Kumaraswamy (2005) most of the construction related risk/ Technical risk is affected to the contractor in the construction/production phase and therefore there is a need of identification of project risk in construction projects to successfully manage them to achieve clients and contractors objectives within the forecasted time, budget, and quality.

2.6.3 CONSULTANTS ROLE AND PROJECT RISK


Consultants are the professionals who advise to the client on the investment, the design, cost, and contractual arrangements and all the other facets of construction project (Flanagan and Norman 1993). Further, consultants must use their skills, experience, and Knowledge with care to ensure the clients interests are protected. However, consultants carry very little risk because they only give advice, but loss that arises because of bed advice can be very significant (Andi 2006). Due to that consultant also has to be knowledgeable about the construction risk.

Construction Risk: Further Consideration of Technical Risk

27

Literature Review on Risk Management

2.7 THE ROLES OF THE PROJECTS DIFFERENT PHASES IN RISK MANAGEMENT


According to Osipova (2007), construction process is traditionally divided into four main phases: Programme (Inception):- client has an idea about the project and analyses conditions for its execution Planning: - architects produce construction drawings according to the clients requirements Procurement (Tendering):- parties sign the contract. Production: - contractor executes the job Since, foreseen all risk at the inception stage is impossible and due to tendency of identified risk in the programme stage to change during project implementation, joint and consistent risk management is required throughout all projects (Rahman and Kumaraswamy 2005). Furthermore, occurrence and effect of construction project risk in different phases to the project participants difficult to foresee all risk only can predict to some extend based on the available information in the early stages of the construction project (Osipova 2007). Moreover, several authors highlighted the importance of identification of project risk in the early stage of the construction project life cycle ( Uher and Toakley 1999), (Rahman and Kumaraswamy 2005), (Flanagan and Norman 1993), (Andi 2006). Aforementioned facts create the need of developing a risk management framework within construction project to identify the performance of risk in the construction life cycle.

Construction Risk: Further Consideration of Technical Risk

28

Literature Review on Risk Management

2.6 PROJECT RISK CLASSIFICATION AND TECHNICAL RISK IDENTIFICATION REGARDING TO SYSTEMATIC RISK MANAGEMENT

2.6.1 PROJECT RISK CLASSIFICATION


Project risk classification is an important step in risk assessment process, because it attempts to structure the various risks that may affect a project. There is various classification of project risk with respect to deferent purposes (Edwards and Browen 1998), (Al-Bahar 1990 cited Ahmed and Azhar 2004), (Wong and Hui 2006), (Stoner et al. 1997). Specially the construction risk is generally perceived as events that influence project objectives of cost, time and quality and some of the project risks can be predictable or foreseen (identifiable) while other may totally unforeseen. Due to that, also it is very much important to classify project risks (Al-Bahar 1990 cited Ahmed and Azhar 2004). According to Edwards and Browen (1998), project risk classifies using the risk source as the basis; primary classification would be human and natural. Natural risks occur outside the human agencies, while human risk arise the humanly organized system and this classification is illustrated following figure. Human risks relating to construction project classifies further as social, political, economic, financial, legal, managerial, technical, and cultural risks. Risk Natural Weather system Geological system Human Social Political Economic Financial Legal Health Managerial Technical Cultural
Construction Risk: Further Consideration of Technical Risk 29

(Source- Edwards and Brown 1998)

Literature Review on Risk Management

Figure 2. 10: Risk Classification

2.6.1 TECHNICAL RISK


Any construction work will be subject to some technical risks, such as changes and errors in design, equipment failure (Shen 2007). Most of the researchers technical risk refers as construction related risk (Al-Bahar 1990, cited Ahmed and Azhar 2004), (Flanagan and Norman 1993), (Wong and Hui 2006). According to Edwards and Brown (1998), Andi (2006) and Kangari (1988), Shen et al. (2001) technical risk is mainly include following factors, Design failures Equipment and system failures New technology failures Estimation errors Accident/ Collision Site Location and access Inadequate program scheduling and tight program scheduling Design changes / Design variations by client Hazards of environmental regulations Incompetence of transportation facilities Increase in site overheads Industrial disputes Local firms incompetence and low credibility
30

Construction Risk: Further Consideration of Technical Risk

Literature Review on Risk Management

Materials shortage Obsoleteness of building equipment Poor quality of procured accessory facilities Poor quality of procured materials Problems due to partners different practice Shortage in accessory facilities Shortage in skillful workers Shortage in supply of water, gas, and electricity Subcontractors low credibility Unknown site physical conditions

2.7 RISK MANAGEMENT IN BUILDING CONSTRUCTION IN SRI LANKA


Risk is everywhere and strictly contacts with each and every aspects of construction industry same whether it is civil or buildings (Flanagan and Norman 1993). Further, as indicated by Thompson and Perry (1993), risk involvement is high in building construction industry and civil construction industry. Observe to the above subject, it is compulsory to find out why building projects are more susceptible for risk. Particularly in Sri Lanka, as a developing country should pay more attention for the reason for high degree of risk involvement within building construction projects. Further, Thilakarathne (2007), Hamshani (2007), and Pushpakumara (1997) have figured out that, Sri Lankan construction industry seriously exposes to the risk. Based on aforementioned particulars, it is same in Sri Lanka also prevails unforeseen environment and considering building projects or infrastructure development projects such as transportation, irrigation etc. are more vulnerable to rapid changes as it more exposes to this environment.
Construction Risk: Further Consideration of Technical Risk 31

Literature Review on Risk Management

Besides, it was quite evident that there is an immense requirement of identifying the potential risk factor both occurrence and influence in prevailing building construction industry and concern of risk handling. Thus, it focuses onto the risk identification and risk response, which are two specific stages in risk management process.

2.8 APPROACH TO THE RESEARCH PROBLEM


Any construction work will be subject to some technical risk (Shen 2007). Further, according to Edwards and Brown (1998), usually the research regarding the technical risk factors such as equipment and system failures, new technology failures, estimation errors, collision, accident, site Location and access, etc. not much and they not well represented in literature even. In order to fulfill, this requirement, through this research, technical risk was considered in construction projects. Further technical risk is the most occurring risk in the construction project and it is significantly affect to the contracting parties especially to the contractor and client. Due to occurrence of technical risk, usually contractors fail to complete the project within the time limit and budget limit. Moreover, risk cannot be eliminated only it can be allocate among the construction parties and proper allocation of consequence of risk among contracting parties will ensure the proper management of risk. Besides, foreseen of risk in the early phases of the construction project life cycle is difficult so it is important to consider the magnitude of technical risk in stages of construction project life cycle and allocation of construction risk among contracting parties. To fill that gap of understanding, it is worthwhile to identify, what are the influencing factors in attaining the project ultimate goals, cost, time, and quality achievements and magnitude of technical risk in stages of construction project life cycle and allocation of construction risk among contracting parties The aforesaid details, would provide a strong based for deciding on a research area where the research should be touched, Based on the common areas covered in above discussion, this research is more emphasized on, Identify the technical risk factors associated with building construction Analyze the allocation of risk factors among construction parties.

Construction Risk: Further Consideration of Technical Risk

32

Literature Review on Risk Management

Figure out consequences of above risks on project goals Identify the performance of technical risk in construction lifecycle.

By considering following Risk factors which are taken from the researchers conducted by Edwards and Brown (1998), Andi (2006), Shen et al. (2001) and Kangari (1988), Design failures Equipment and system failures New technology failures Estimation errors Accident/ Collision Site Location and access Inadequate program scheduling and tight program scheduling Design changes / Design variations by client Hazards of environmental regulations Incompetence of transportation facilities Increase in site overheads Industrial disputes Local firms incompetence and low credibility Materials shortage Obsoleteness of building equipment Poor quality of procured accessory facilities Poor quality of procured materials

Construction Risk: Further Consideration of Technical Risk

33

Literature Review on Risk Management

Problems due to partners different practice Shortage in accessory facilities Shortage in skillful workers Shortage in supply of water, gas, and electricity Subcontractors low credibility Unknown site physical conditions

2.9 SUMMERY
Studying about the construction risk is very much important to be success in decision making each and every aspect of construction activities. It would be impose significance and value to the decision and at present, more researchers have gone through the risk aspect of the construction projects. According to Edwards and Brown (1993) and (Al- Bahar1990) construction project can be classified broadly as social, political, economic, financial, legal, managerial, technical (most of the time refers as construction related risk) and cultural risks. Risk is rapidly increasing with complexity and dynamic nature of construction projects and it is inherent to all nature of construction works. It affects to time and quality of the construction and due to that, most of the construction projects are experiencing cost and time overruns and poor quality, especially concerning the building construction projects. Further, the technical risk or the construction related risk has considerably affected to the construction project (Shen 2007). Moreover, there are only few consideration has been done according to the literature. Ultimately, those aforementioned facts create the need of developing a risk management framework within building construction project to engage in these unpredictable conditions.

Construction Risk: Further Consideration of Technical Risk

34

Literature Review on Risk Management

In order to fulfill, this requirement, through this research problem Construction Risks: Further Consideration of Technical Risks has investigated to identify prevailing technical construction risk factors, analyze the construction industry practitioners perceptions about allocation of all risk factors among construction parties, figure out consequences of risk factors to project goals and figure out the magnitude of technical risk in stages of building construction project lifecycle.

Construction Risk: Further Consideration of Technical Risk

35

Research Methodology

Chapter 03
3. RESEARCH METHODOLOGY
3.1 INTRODUCTION
Main aim of this chapter is to outline the research methodology for this research and specially illustrate the research design, which was followed throughout this research. Initially, it is describing the research Process of this particular research and it illustrates completely the Process of this research in a systematic manner using figures. Further, it is illustrating the research design together with the steps of the research design and applicability of research design steps also illustrate.

3.2RESEARCH PROCESS
This research carried out mainly to identify the prevailing technical risk factors and thereafter to analyze the allocation of risk among contraction parties, figure out consequences of above risk of contracting parties, moreover to identify the performance of technical risk in construction life cycle. Thus, it was essential to think off an appropriate research Process, which is competent of identification risk factors, which is paramount. Further, by using a proper research process can be minimized the errors that can be occurred during our research and can be reduced the mistakes done by the researcher. Research process for this particular research illustrates using following figure,

Construction Risk: Further Consideration of Technical Risk

36

Research Methodology

Research Question Background study

Establish Aim & objective Literature Review Data Collection Preliminary Survey Interviewing
Guide to Sampling and Factor Selection

Literature Review

Sample Collect ion

Further Research

Structured Interview

Questioner Survey

Data Analysis

Conclusion & Recommendation

Figure 3.1: Research Process

Construction Risk: Further Consideration of Technical Risk

37

Research Methodology

3.3 RESEARCH DESIGN


Research design is complying with three key steps; in sequent, identifying research philosophy, identifying research approach, identifying research technique (Kagioglou et al. 2000 cited Senarathne 2005) Where the selection of research techniques for data collection and data analysis is based on research approach and the selection of research approach is based on the research philosophy.

(Source- Kagioglou et al. 2000 cited Senarathne 2005)


Figure 3.2: Nested reseach methodology

Further, research methodology illustrated by the Saunders et al. (2003) as shown in the following figure,

Construction Risk: Further Consideration of Technical Risk

38

Research Methodology

(Source- Saunders et al. 2003)


Figure3.3: Research methodology illustration

3.3.1 RESEARCH PHILOSOPHY


Research philosophy selection is the initial step of research designing and it is depend on the way researcher think about to develop the knowledge. Further, it directs to the researcher to select appropriate research strategy among one of followings, Positivism: - are the natural science researchers. In positivism, working with an observable social actuality and the finished product of the research can be generalized (Remenyi et al. 1998 cited saunders et al. 2003) Interpretivism: - try to discover the details of the situation to understand the reality or perhaps reality is working behind them (Remenyi et al. 1998 cited Saunders et al. 2003). Realism: - believe that the reality is subjective and interior to the people and it shares the both view of positivism and interpretivism. By considering the nature of this research problem it is obvious that this piece of research needs a vigilant observations and identification about the construction project risk to manage the to overcome problems created by the construction project

Construction Risk: Further Consideration of Technical Risk

39

Research Methodology

risk to the construction parties throughout the construction project life cycle. Due to that reason interpretivism select as the research philosophy for this research.

3.3.2 RESEARCH APPROACH


Appropriate research approach should select to deal with the research question according with the research philosophy. Research approach approaches are about to organise research activities, especially including the collection of data from the population in a way that meet the reach problems aims and objectives. According to Saunders et al. (2003), research approach can be divided in to two categories, Deductive:- first develop a theory and hypothesis, and design research strategy to test the hypothesis and moreover this is owes to positivism, Inductive:- first collect data and develop a theory as a result of the data analysis, and moreover this is owes to interpretivism, When considering circumstance of the this research problem, it is important to identify the technical risk factors , consequences of them and their performance in the construction life cycle. Therefore as the research approach to this research deductive approach is selected. According to the study of, Kagioglou et al. (2000 cited Senarathne 2008); following approaches are the most popular and widely used research approaches in the world.

Experiments laboratory, quasi-experiments Surveys Case study research Ethnography Action research Grounded theory

Construction Risk: Further Consideration of Technical Risk

40

Research Methodology

In this research Survey method has been identified as the most appropriate approach. Because of, it was needed to get perceptions of building construction practitioners.

3.3.2.1 SURVEY RESEARCH APPROACH Survey research is one of the most common quantitative research approaches. Main characteristics of the survey research are (Kraemer 2002), Getting information from a sample Asking questions from respondents Based on statistical sampling A representative sample is selected

3.3.2.3 JUSTIFICATION OF USING SURVEY APPROACH In identifying risk factors and their management control, survey approach provides a better access to the information through the design of questionnaire in concise and precise manner (Katam and Katam 2001). Accordance with the research problem, it is important to quantitatively investigate and identify prevailing technical construction risk factors, analyze perception of construction practitioners about the allocation of all risk factors among construction parties, figure out consequences of risk factors to project goals, and figured out magnitude of technical risk in stages of building construction project lifecycle. Thus, it is evident that in this research can be implemented through a questionnaire survey in obtaining relevant data under this research topic. Moreover, need to generalize the result to some extend and by using survey, approach can get the following advantages for this research (Saunders et al. 2003),

Surveys are relatively inexpensive (especially self-administered surveys). Surveys are useful in describing the characteristics of a large population. No other method of observation can provide this general capability.

Construction Risk: Further Consideration of Technical Risk

41

Research Methodology

Consequently, very large samples are feasible, making the results statistically significant even when analyzing multiple variables. Many questions can be asked about a given topic giving considerable flexibility to the analysis. There is flexibility at the creation phase in deciding how the questions will be administered: as face-to-face interviews, by telephone, as group administered written or oral survey, or by electronic means.

Standardized questions make measurement more precise by enforcing uniform definitions upon the participants. Standardization ensures that similar data can be collected from groups then interpreted comparatively (between-group study).

3.3.3 RESEARCH TECHNIQUE


3.3.3.1 DATA COLLECTION TECHNIQUE By considering the circumstances of this of this particular research, especially neediness of the identification and perceptions of construction industry practitioners about the allocation of technical risk factors among contract parties, questioner survey selected as the basic technique to collect data. Furthermore, for fill the gap creating by the questioner survey, semi structured interview was used for the critically identify the actual scenario.

Preliminary Survey Preliminary survey carried out to find out, current prevailing condition of the risk in building construction industry and to identify the significance technical risk factors relate to building construction industry. Moreover, it was conducted in two ways,

Construction Risk: Further Consideration of Technical Risk

42

Research Methodology

By using literature review: - found out the most significance technical risk factor relate to building construction industry.

By interviewing practitioners: - carried out for selected practitioners who are working in contraction organizations. Purpose of this survey was to figure out applicability of the risk factor selected from the literature and to select the sample in an efficient way.

Further, the data collected from this preliminary survey supported to define the sample and collect data using structured interview, and questioner survey. Sample Sampling defined as the method of selecting from a population (Tan 2002 cited Hamshyani 2007). Thus, selecting most appropriate sample is quite difficult for the research. Special for this piece of research, sampling was done using the information collected by the preliminary survey.

Questioner Survey Questioners were prepared with the guidance of preliminary survey and literature review. This questioner was design to probe the cross-sectional behavioural pattern of individual construction parties to towards the technical risk and the validity of questions and answers ensured by the structured interview and the documentary survey. The quesionnaire was structured to get perception of two main sections. The first was intend to get respondents profile. The second section was intended to gather perception on the rating of each technical risk factors which were collected through the litrature survey. The first question relates to the probability of the technical risk events occurring on Sri Lankan construction projects. The respondents were asked to choose between very low, low, medium, high and very high. The second question refers to impact on project objectives namely time quility and cost once the technical risk event ouccers. The third question refers to performance of technical risk in

Construction Risk: Further Consideration of Technical Risk

43

Research Methodology

construction life cycle. Ultimatly, in the forth question relates to the proper allocation of the risk among construction parties namely cotractor, client and consultant. The questionnaire survey forms were distributed to construction professionals associated with the Sri Lankan construction industry. The completed responses collected personally. Structured Interviews With the guidance of the preliminary survey, structure for the structured interview was prepared and moreover allocation of risk, consequence, and occurrence of that particular risk factors within the construction lifecycle was try to figure out. This was conducted together with the questioners and interviewed the construction practitioners. In most of the cases interviewed Project manager, Project Engineer, Site Engineers, and specially quantity surveyor to ensure the monitory terms relate to technical risk.

3.3.3.2 DATA ANALYSIS TECHNIQUE Collected data from above three methods evaluate systematically to achieve proper answer to the research question. For analyze the allocation of risk to the contracting parties, figure out the consequences of above risk of contracting parties, and identify performance of risk in construction life cycle from the collected data. Likert Scale was used in questioner survey. Likert Scale Likert scale can be recognized as the technique of measuring the different attitudes towards a statement by asking the respondent to indicate their preference in a series of short statement on a given range of responses. It can be analyzed the general

Construction Risk: Further Consideration of Technical Risk

44

Research Methodology

attitude or the opinion of respondents and come to a conclusion of a research topic (Ginige 2005). Relative Important Index (RII) The technique used to evaluate the collected data was Relative Important Index (RII). RII for each risk was calculated using Eq. (01). An RII was calculated for the probability, impact and rating. The risk rating was calculated by multiplying the probability and impact for each risk. The risk rating can be used to prioritize risks for further quantitative assessment or response planning. The specific combinations of probability and impact lead to a risk being rated as high, moderate, or low importance (El-Sayegh 2008).

0 1

Wi Xi i

:- weight assigned to ith response; Wi = 1,2,3,4, and 5 for i=1, 2, 3, 4, and 5 respectively : - frequency of the ith response : - response category index = 1, 2, 3, 4 and 5 for very low, low, moderate, high and very high, respectively

Cronbach's Alpha Cronbach's alpha is a test for a model or survey's internal consistency. In addition, it identified as 'scale reliability coefficient' sometimes. Cronbach's Alpha is a measure of how well each individual item in a scale correlates with the sum of the remaining items. It measures consistency among individual items in a scale (Streiner and Norman 1989), (Nunnally and Bernstein 1978). The standardized Cronbach's can also be defined as;

Construction Risk: Further Consideration of Technical Risk

45

Research Methodology

Where N is the number of components

equals the average variance and

is the

average of all covariances between the components (Cronbach 1951). According to Nunnally and Bernstein (1978), in a reliable data set the alpha should be above 0.7. Cronbachs alpha calculated using SPSS and calculation of Cronbachs alpha was done according to appendix 04.

3.4 CONCLUSION AND RECOMMENDATION


Using the evaluated data, it was concluded the findings with respect to aim of this research and objectives. Ultimately, did the recommendation and figured out consequences should consider for the future researches and areas should consider in this particular area.

3.5 SUMMARY
This chapter considered the methodology of this particular research. The survey method figured out as the best method to collect data from the construction industry together with structured interviews and documentary survey.

Construction Risk: Further Consideration of Technical Risk

46

Data Analysis and interview analysis

Chapter 04
4 DATA ANALYSIS AND INTERVIEW ANALYSIS
4.1 INTRODUCTION
With the aim of upgrading the knowledge in realm of risk management, the research had first conducted a board literature review in the risk management field with particular prominence in building construction projects in Sri Lankan perspective. Prime intention of this chapter is to analysis the degree of risk management aspects using in technical risk management in construction projects in Sri Lanka. Chapter 2 provided the rigid knowledge of risk management and risk management measures concerning the technical risk management. Besides, the behavior of the contraction projects and construction project partys behavior regarding risk management. This chapter completely based on information collected from construction industry practitioners through questioner survey and interviews. Within this chapter consists of the results, after analyzing the data, collected from questionnaire survey and interview. Moreover, ultimately, discussion carried out with the intention of approaching the conclusion of this study.

Construction Risk: Further Consideration of Technical Risk

47

Data Analysis and interview analysis

4.2 PRELIMINARY SURVEY


4.2.1 RISK FACTOR IDENTIFICATION
Various risks were identified in the first stage of this research and they were illustrated broadly in the chapter 02. This was accomplished mainly through literature review. Twenty four technical risk factors were identified through the literature review.

For the fulfillment of aim and objective of the research respondents were asked to state availability of the listed risk factors which were found out though the literature review. That was asked to do considering respondents knowledge and experience about listed technical risk factors. This was done with the intention of removing risk factors where none of respondent stated as; a particular risk factor could not be seen in Sri Lankan construction industry. However, according to finding of the preliminary survey, technical risk identification can be illustrated by following figure 4.1. According to figure 4.1, all the risk events identified were there in Sri Lankan construction industry. Based on the survey result, thirty-four respondents out of forty stated that they have faced to estimation errors considering their experience. Eighty five percent of the total projects were having estimation errors. Moreover, design failures/ design variation by client is the second highest technical risk factor. Thirty three out of forty respondents mentioned that they faced that. Thirty two out of forty respondents had faced to shortage in skillful workers within their projects. It means there is an 80% probability of having shortage in skillful workers for a project. Apart from above mention three technical risk factors, according to respondents identification there were 6 risk factors having more than 50% probability of occurrence in a particular project.

Construction Risk: Further Consideration of Technical Risk

48

Data Analysis and interview analysis

Figure 4. 1: Risk identification

4.3 THE QUESTIONNAIRE SURVEY


As mentioned in the earlist chapter 3.3.3.1 data collection technique, the questionnaire was designed to fulfill the aims and objectives of this reseach topic. The questionnaire was design based on the litrature survey and preliminary survey. The questionnaire survey forms were distributed to construction profetionals associated with the Sri Lankan building construction industry. The completed response were collected personally.

Construction Risk: Further Consideration of Technical Risk

49

Data Analysis and interview analysis

Response rate There were 45 practitioners who were selected randomly from client oraganisations, contractors organizations and consultant organizations uniformly. Out of 45 distributed questionnaiars, 43 was returned (or Collected). Forty out of 43 questionnairs, were completed and used in the analysis. It represented a response rate of more than 85% overall. The response rate for completed questionnaire according to their type of respective organization was shown in table 4.1.

Table 4. 1: Response rate

Respondent s Client Contractor Consultant Overall Distributed Returned Response rate 15 11 73% 15 14 93% 15 15 100% 45 40 89%

Classification of respondents Table 4.2 and figure 4.2 summarizes the respondents profile. Fifty eight percent of the respondents had more than 10 years of experience. More over, 38%, 35% and 27% of the respondents were sequentailly from consultant, contractor and client. The results show that, 43% out of respondents projects contract sums are grater than 1000 million.

Table 4.2: Respondents Profile

Construction Risk: Further Consideration of Technical Risk

50

Data Analysis and interview analysis

Figure 4. 2: Respondents Profile

4.3.1 RSEARCH FINDINGS


4.3.1.1 SIGNIFICANCE OF TECHNICAL RISK FACTORS Based on the survey results, the relative importance index (RII) was calculated for each risk based on probability, impact and rating. These risks were then ranked according to their RII. The results are presented in tables and figures for easy illustration. Significance of technical risk was measured considering the project perspectives independently such as, Impact to the cost of the project Impact to the time of the project

Subject Number of Respondents Less Than 5 Years 5-10 Years Above 10 Years Project Scale less than 500 million 500-1000 million Above 1000 million

No of Respondents
Client Contractor Consultant Total

11 1 1 9 1 5 5

14 5 4 5 2 7 4

15 6 0 9 6 5 5

40 12 5 23 9 17 14
51

Construction Risk: Further Consideration of Technical Risk

Data Analysis and interview analysis

Impact to the quality of the project

Reliability of data Considering the data set gain from the questionnaire survey for the probability, Cronbach's Alpha was calculated for the data set. The alpha is 0.743. According to Nunnally and Bernstein (1978), in a reliable data set the alpha should be above 0.7. It means the data set collected to calculate RII for each risk based on probability is reliable. Moreover, considering the data set collected to calculate RII for each risk based on cost impact, Cronbachs alpha was calculated. The alpha is 0.840. It denoted that the data set collected through questionnaire to calculate RII for each risk factor based on cost impact is reliable. Furthermore, for data sets collected for the time impact and quality impact also Cronbachs alphas were calculated. Alphas are consequently 0.794 and 0.829. According to Nunnally (1978), those are reliable data sets.

4.3.1.1.1 SIGNIFICANT TECHNICAL RISK FACTORS CONSIDERING COST OF THE PROJECT Cost of the project is one of the most important project perspectives when considering the budget of the project, which is allocated by the employer, or the owner of the project. Therefore, it is more important to consider impact to the cost of the project by the technical risk factors. Based on the survey, the results are presented in table 4.3. Table 4.4 presents the top 10 technical risks in the Sri Lankan construction industry based on the risk rating considering impact to the cost of the project. According to risk rating values, most significant technical risk is estimation errors. The RII is 11.970. Estimation errors are the key technical risk when considering the cost perspective of the project in Sri

Construction Risk: Further Consideration of Technical Risk

52

Data Analysis and interview analysis

Lankan construction industry. Because in most of the cases construction estimates are taken roughly at the tendering stage due to following reasons, Incomplete drawings and specification Not following proper standards to prepared it Less experience Time limitations Persons, who are involving with the estimation process, are not capable enough to do it. They may not either be or doing their jobs correctly

Construction Risk: Further Consideration of Technical Risk

53

Data Analysis and interview analysis Table 4. 3: Significance of Risk Considering Cost of the Project

No. RISK FACTORS


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Design failures Equipment and system failures New technology failures Estimation errors Accident/ Collision Site Location and access Inadequate program scheduling and tight program scheduling Design changes / Design variations by client Hazards of environmental regulations Incompetence of transportation facilities Increase in site overheads Industrial disputes Local firms incompetence and low credibility Materials shortage Obsoleteness of building equipment Poor quality of procured accessory facilities Poor quality of procured materials Problems due to partners different practice Shortage in accessory facilities Shortage in skillful workers Shortage in supply of water, gas, and electricity Subcontractors low credibility Unknown site physical conditions Unusual weather and force majeure

Cost Impact RIIRank (1) 3.075 5 2.375 20 2.450 19 3.600 2 2.200 23 2.000 24 3.175 2.675 2.850 2.825 3.350 3.775 2.850 2.775 2.550 2.725 2.925 2.575 2.875 2.550 2.250 2.375 2.700 3.075 4 15 9 11 3 1 9 12 17 13 7 16 8 17 22 20 14 5

Probability Rating RIIRIIRank Rank (2) (3) 2.050 20 6.304 14 2.150 19 5.106 21 2.200 18 5.390 20 3.325 3 11.970 1 2.500 12 5.500 19 2.500 12 5.000 23 2.975 3.475 2.525 2.200 2.725 2.200 2.325 3.150 2.000 2.025 2.300 2.700 1.975 3.500 1.925 2.550 2.750 2.925 5 2 11 16 8 16 14 4 22 21 15 9 23 1 24 10 7 6 9.446 9.296 7.196 6.215 9.129 8.305 6.626 8.741 5.100 5.518 6.728 6.953 5.678 8.925 4.331 6.056 7.425 8.994 2 3 10 15 4 8 13 7 22 18 12 11 17 6 24 16 9 5

Moreover, interviewed respondents also illustrated that the estimation errors could happen due to documentation errors. Those kinds of errors can only be identified at the tendering and production stages.

Construction Risk: Further Consideration of Technical Risk

54

Data Analysis and interview analysis

The second risk is owners often impose tight construction schedule (RII=9.446) that might be difficult and impractical to achieve. This might be caused by the importance of time to market but often is caused by political reasons. The third technical risk is design changes or design changes by client (RII=9.296). This is especially true for the building construction in industry because most of the time owners tend to change the design or they try to introduce new designs to the project.

Table 4.4: Top Ten Ranked Risk Factors Considering Significance Risk

No RISK FACTORS
a b c d e f g h i j Estimation errors Inadequate program scheduling and tight program scheduling Design changes / Design variations by client Increase in site overheads Unusual weather and force majeure Shortage in skillful workers Materials shortage Industrial disputes Unknown site physical conditions Hazards of environmental regulations

RII
11.97 0 9.446 9.296 9.129 8.994 8.925 8.741 8.305 7.425 7.196

Rank
1 2 3 4 5 6 7 8 9 10

Increasing site overhead is also an important risk (RII=9.129). This mainly occurs due to improper management of the site overhead. Unusual weather and force majeure is ranked fifth (RII=8.994). This is a risk, which cannot be easily predictable but effect to the project is considerably high. Most importantly material shortage which ranked 6th (RII= 8.925) also has an impact to the project but it will depend on the economy condition of the country and is caused primarily because of the large demand. Shortage in skillful workers is a technical risk that is ranked 7 th (RII=8.741). This happens because; there is no regular labour force for the construction industry. It changes from time to time with the seasons. Industrial disputes is ranked eighth (RII = 8.305) in Sri Lankan construction industry. It means the bodies, which are participating in the construction have misunderstandings and disputes. That could happen mainly due to, claim from one party to other to gain time or money from one party to sustain their losses.
Construction Risk: Further Consideration of Technical Risk 55

Data Analysis and interview analysis

The 9th risk (RII= 7.425) is unknown site and physical conditions. That is difficult to predict at the preliminary stage. Mainly it will be a risk to owner. Tenth risk is the hazarders of environmental regulations. It is important to state that the significance of technical risk considering the cost perspective of the project will be a more vital factor when deciding whether implementing a project. For proper evaluation of the construction risk, one must consider both the probability of risk occurrence and the impact on cost of the project once, technical risk event occurs. Some authors contented that multiplying the probability and impact values might be misleading (Wong and Chou 2003), (Kartam and Kartam 2001). This is achieved best by plotting the risk probability- cost impact matrix (figure 4.3). In the matrix, the x- axis represents the impact value while the yaxis represents the probability value. Both scales are 1-5 (one being very low to 5 being very high).

Figure 4. 3: Cost Significance of Technical Risk

The matrix shows 7 of the risks to be high (probability >3 and cost impact>3). It shows that the majority of the risks are medium (probability 2-3 and Cost impact >2.5). There is one technical risk that have probability of less than 2 and risks with cost impact less than 2.5. These are considered low.

Construction Risk: Further Consideration of Technical Risk

56

Data Analysis and interview analysis

4.3.1.1.2 SIGNIFICANCE CONSIDERING TIME OF THE PROJECT Time of the project is one of the most important project perspectives. When considering time limitation that is given by the owner. That could be due to demand to the project at market. Therefore, it is more important to consider impact to the time of the project by the technical risk factors.

Table 4. 5: Significance of Risk Considering Time of the Project

Construction Risk: Further Consideration of Technical Risk

57

Data Analysis and interview analysis

No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

RISK FACTORS Design failures Equipment and system failures New technology failures Estimation errors Accident/ Collision Site Location and access Inadequate program scheduling and tight program scheduling Design changes / Design variations by client Hazards of environmental regulations Incompetence of transportation facilities Increase in site overheads Industrial disputes Local firms incompetence and low credibility Materials shortage Obsoleteness of building equipment Poor quality of procured accessory facilities Poor quality of procured materials Problems due to partners different practice Shortage in accessory facilities Shortage in skillful workers Shortage in supply of water, gas, and electricity Subcontractors low credibility Unknown site physical conditions Unusual weather and force majeure

ImpactTime RIIRank (1) 3.100 7 2.675 17 2.875 11 2.881 10 2.400 22 2.550 21 3.825 3.300 2.825 2.800 2.900 3.425 2.775 3.675 2.675 2.675 2.650 2.825 2.225 3.450 2.325 2.750 3.100 3.700 1 6 12 14 9 5 15 3 17 17 20 12 24 4 23 16 7 2

Probability RIIRank (2) 2.050 20 2.150 19 2.200 18 3.325 3 2.500 12 2.500 12 2.975 3.475 2.525 2.200 2.725 2.200 2.325 3.150 2.000 2.025 2.300 2.700 1.975 3.500 1.925 2.550 2.750 2.925 5 2 11 16 8 16 14 4 22 21 15 9 23 1 24 10 7 6

Rating RII(3) 6.355 5.751 6.325 9.579 6.000 6.375 11.379 11.468 7.133 6.160 7.903 7.535 6.452 11.576 5.350 5.417 6.095 7.628 4.394 12.075 4.476 7.013 8.525 10.823 Rank 15 20 16 6 19 14 4 3 11 17 8 10 13 2 22 21 18 9 24 1 23 12 7 5

Based on the survey, the results are presented in table 4.5. Table 4.6 presents the top 10 technical risks in the Sri Lankan construction industry based on the risk rating considering impact to the time of the project. According to risk rating values, most

Construction Risk: Further Consideration of Technical Risk

58

Data Analysis and interview analysis

significant technical risk is Shortage in skillful workers. The RII is 12.075. As illustrated in 4.3.1.1.1, construction industry is not having permanent labour force. Therefore, shortage in skillful workers might be a key risk to the project significance considering the time impact of the project.

Table 4.6: Top Ten Ranked Risk Factors Considering Significance Risk

The fourth risk is owners often impose tight construction schedule (RII=11.379) that might be difficult and impractical to achieve. This might be caused by the importance of time to market but often is caused by political reasons. Due to difficult and impracticality this will definitely influence time of the project.

Unusual weather and force majeure is ranked fifth (RII=10.823). This is a risk, which

No RISK FACTORS
a b c

RII

Rank

1 Shortage in skillful workers 12.075 2 Materials shortage 11.576 3 Design changes / Design variations by client 11.468 Inadequate program scheduling and tight 4 d 11.379 program scheduling 5 e Unusual weather and force majeure 10.823 6 f Estimation errors 9.579 7 g Unknown site physical conditions 8.525 8 h Increase in site overheads 7.903 9 i Problems due to partners different practice 7.628 10 j Industrial disputes 7.535 cannot be easily predicted but effect to time of the project is considerably high. Most importantly estimation errors which ranked 6th (RII= 9.579) will also be an impact to the project as described in section 4.2.1.2.1. Unknown site physical condition is ranked 7th (RII =8.525). This is also impulsive risk at the planning stage and occurring of this technical risk event will influence time of the project. The eighth risk event is contractor related. Increasing site overhead is the ranked eighth (RII= 7.903). Problems arising out of partners deferent practice also create impact to time of the project. It is ranked ninth (RII= 7.628). Tenth risk is the industrial disputes.
Construction Risk: Further Consideration of Technical Risk 59

Data Analysis and interview analysis

Based on the argument, mentioned in section 4.3.1.1.1 Wong and Chou (2003), and Kartam and Kartam (2001) is contented that, multiplying the probability and impact values might be misleading. This is achieved best by plotting the risk probabilitycost impact matrix (figure 4.4).

Figure 4. 4: Time Significance of Technical Risk Factors

The matrix shows6 of the risks to be high (probability >3 and cost impact>3). It shows that the majority of the risks are medium (probability 2-3 and Cost impact >2.5). There are two technical risks that have probability of less than 2 and risks with cost impact less than 2.5. These are considered low.

4.3.1.1.3 SIGNIFICANT OF TECHNICAL RISK FACTORS CONSIDERING QUALITY OF THE PROJECT Quality of the output is also most important project perspectives. Owner are manly requires a quality product within their budget. Therefore, it is more important to consider the impact to the quality due to technical risk events. Based on the survey, the results are presented in table 4.7 Table 4.8 presents the top 10 technical risks in the Sri Lankan construction industry based on the risk rating

Construction Risk: Further Consideration of Technical Risk

60

Data Analysis and interview analysis

considering impact to the quality of the project. According to risk rating values, most significant technical risk is Shortage in skillful workers. The RII is 12.775. As illustrated in 4.3.1.1.1 construction industry is not having permanent labour force. Therefore, shortage in skillful workers might be a key risk to the project significance considering the quality impact of the project.
Table 4. 7: Significance of Risk Considering Quality of the Project

Construction Risk: Further Consideration of Technical Risk

61

Data Analysis and interview analysis

NO. RISK FACTORS


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Design failures Equipment and system failures New technology failures Estimation errors Accident/ Collision Site Location and access Inadequate program scheduling and tight program scheduling Design changes / Design variations by client Hazards of environmental regulations Incompetence of transportation facilities Increase in site overheads Industrial disputes Local firms incompetence and low credibility Materials shortage

Construction Risk: Further Consideration of Technical Risk

Obsoleteness of building equipment Poor quality of procured accessory facilities Poor quality of procured materials Problems due to partners 2.350 different practice 2.25 Shortage in accessory facilities 0 3.65 Shortage in skillful workers 0 Shortage in supply of water, gas, 2.17 5 and electricity 2.27 Subcontractors low credibility 5 2.47 Unknown site physical conditions 5 Unusual weather and force 2.50 0 majeure

Quality RIIRank (1) 3.02 2 5 2.30 13 0 2.32 12 5 2.10 17 0 1.52 23 5 1.75 21 0 2.87 3 5 2.45 9 0 1.55 22 0 1.52 23 5 1.85 20 0 2.05 18 0 1.92 19 5 2.70 5 0 2.35 10 0 2.72 4 5 2.700 5 10 15 1 16 14 8 7

Probability RIIRank (2) 2.050 2.150 2.200 3.325 2.500 2.500 2.975 3.475 2.525 2.200 2.725 2.200 2.325 3.150 2.000 2.025 2.300 2.700 1.975 3.500 1.925 2.550 2.750 2.925 20 19 18 3 12 12 5 2 11 16 8 16 14 4 22 21 15 9 23 1 24 10 7 6

Rating RIIRank (3) 6.201 4.945 5.115 6.983 3.813 4.375 8.553 8.514 3.914 3.355 5.041 4.510 4.476 8.505 4.700 5.518 6.210 6.345 4.444 12.77 5 4.187 5.801 6.806 7.313
62

10 15 13 6 23 20 2 3 22 24 14 17 18 4 16 12 9 8 19 1 21 11 7 5

Data Analysis and interview analysis

The second risk is owners often impose tight construction schedule (RII=8.553) that might be difficult and impractical to achieve. This might be caused by the importance of time to market but often caused by political reasons. The third technical risk is design changes or design changes by client (RII=8.514). This is especially true for the building construction in industry because most of the time owners tend to change the design or they try to introduce new designs to the project.

Table 4.8: Top Ten Ranked Risk Factors Considering Significance Risk

RISK FACTORS Shortage in skillful workers Inadequate program scheduling and tight program scheduling Design changes / Design variations by client Materials shortage Unusual weather and force majeure Estimation errors Unknown site physical conditions Problems due to partners different practice Poor quality of procured materials Design failures

RII 12.7 75 8.55 3 8.51 4 8.50 5 7.31 3 6.98 3 6.80 6 6.34 5 6.21 0 6.20 1

Rank
1 2 3 4 5 6 7 8 9 10

The fourth risk is Material Shortage (RII=8.505). Similarly as mentioned in section 4.2.1.1.1, this happens due to high demand of material in the industry. There are not enough resources to cater that demand. Even if there are, that materials are not in required quality level so that automatically leads to impact to the quality of the product. Unusual weather and force majeure is ranked fifth (RII=7.313). This is a risk, which cannot be easily predicted but effect to the project is considerably high. Most importantly estimation errors which ranked 6th (RII= 6.983) also impacts to the project as described in section 4.2.1.1.1. Due to the errors of the estimation construction cost may go high at the construction period than estimated at the
Construction Risk: Further Consideration of Technical Risk 63

Data Analysis and interview analysis

planning stage. That will automatically lead owner to reduce quality to do his job within his budget. Unknown site physical condition is ranked seventh (RII =6.806). This is also impulsive risk at the planning stage occurring of this technical risk event will influence quality of the project. Problems arising out of partners different practice also create impact to quality of the project. It is eighth ranked (RII= 6.345). Poor quality of procured material is the 9th ranked (RII= 6.201) risk event that could impact on quality of the output. Tenth risk is the design failures. Failures due to design will lead to impact on quality of output. Based on the argument mentioned in section 4.2.1.2.1, multiplying the probability and impact values might be misleading. This is achieved best by plotting the risk probability- cost impact matrix (figure 4.5).

Figure 4. 5: Quality Significance of Technical Risk Factors

The matrix shows five of the risks to be high (probability >3 and cost impact>3). It shows that the majority of the risks are medium (probability 2-3 and Cost impact >2.5). There are two technical risks that have probability of less than two and risks with cost impact less than 2.5. These are considered low. 4.3.1.2 PERFORMANCE IN CONSTRUCTION LIFE CYCLE

Construction Risk: Further Consideration of Technical Risk

64

Data Analysis and interview analysis

The performance in construction project life cycle analysis in figure 4.6 and table 4.9 illustrates the performance in each stage of the construction life cycle simply. According to figure 4.6, construction stage of the construction life cycle is having highest performance of technical risk. Considering data set collected through the questionnaire survey to measure the magnitude of performance level of risk events in construction life cycle, Cronbachs alpha was calculated for each data set. The alpha values for data set using for the analysis of performance of risk events in programming stage is = 0.959, planning stage is 0.755, tendering stage is 0.777 and for the production stage data set = 0.949. According to Nunnally and Bernstein (1978) as described in 4.2.1.2, they are reliable data sets. A careful look at Figure 4.6 confirms the argument that the highest magnitude or the performance of technical risk in the construction life cycle is in the construction stage. When comes to construction stage to the inception or the programming stage, it is reducing. Unusual weather and force majeure and shortage in skillful workers are having highest magnitude at the construction stage (RII= 4.000). Second highest are unknown site physical conditions and local firms incompetence and low credibility. That is because such kind of technical risk events are having more probability of occurrence at that stage. Moreover, third highest is design changes/ design variation by client. Clients tend to do design changes and variation at this stage as they realize the actual design requirements only at this stage. According to table 4.9 and figure 6, it is clear that there are only several risk events in the tendering stage, which are having high performance. Estimation errors, design failures, inadequate program scheduling and tight program scheduling, design changes, / design variations by client are that risk events.

Table 4. 9: Performance of risk events in construction life cycle

Construction Risk: Further Consideration of Technical Risk

65

Data Analysis and interview analysis

NO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

RISK FACTORS Design failures Equipment and system failures New technology failures Estimation errors Accident/ Collision Site Location and access Inadequate program scheduling and tight program scheduling Design changes / Design variations by client Hazards of environmental regulations Incompetence of transportation facilities Increase in site overheads Industrial disputes Local firms incompetence and low credibility Materials shortage Obsoleteness of building equipment Poor quality of procured accessory facilities Poor quality of procured materials Problems due to partners different practice Shortage in accessory facilities Shortage in skillful workers Shortage in supply of water, gas, and electricity Subcontractors low credibility Unknown site physical conditions Unusual weather and force majeure

Programme RII 1.750 2.275 1.575 1.750 1.825 1.750 2.150 2.150 1.575 1.450 1.475 1.500 1.675 1.700 1.500 1.375 1.550 1.425 1.725 1.725 1.425 1.575 1.625 1.475

Planning RII 3.175 2.000 2.150 2.825 2.325 2.650 2.900 2.650 2.650 1.825 1.675 2.325 2.575 1.925 1.950 1.700 2.100 1.925 2.250 1.850 1.850 1.525 2.250 1.975

Tendering RII 3.125 2.35 2.550 3.550 2.000 2.775 3.100 3.000 2.175 2.075 2.575 2.575 2.450 2.525 2.000 1.925 2.075 2.675 2.250 2.225 1.825 1.900 2.825 1.975

Production RII 3.5 3.475 3.225 3.475 3.275 3.425 3.575 3.850 3.100 3.150 3.550 3.025 2.975 3.725 2.975 3.075 3.325 3.225 3.225 4.000 3.300 3.325 3.725 4.000

Construction Risk: Further Consideration of Technical Risk

66

Data Analysis and interview analysis

In the planning stage, only design failures are having high performance. All the other events are having medium performance. That is because at that stage there is only documentation part there practical problems are not much arising. All the risk factors in the programming stage are having low performance. That might happen, due to, that stage is the inception stage of the construction process, and parties may not have higher risk of involving to it.

Figure 4. 6: Performance of risk events in construction life cycle

4.3.1.3 RISK ALLOCATION Risk allocation is a vital issue. It refers to the proper allocation of risks to the contracting party, mainly the owner, the contractor, or the consultant. Occasionally, one party alone cannot handle risks so the two share that risk. Generally, risks should be apportioned to the parties that could best handle or manage it. However, due to an irregularity in commercial influence, there are no rules regarding risk allocation in

Construction Risk: Further Consideration of Technical Risk

67

Data Analysis and interview analysis

construction contracts as owners can place any risks to the contractor. Contractors usually respond to these risks by increasing their contingency and markup, which ultimately increase the contract price to the owner. Interviewed respondents indicated that risks are not allocated appropriately in the Sri Lankan construction industry. The analysis of actual and expected risk allocations based on the questionnaire survey results are presented in table 4.10 and figure 4.7. The table and figure denote subjective analysis. Moreover, considering the data set gained from the questionnaire survey for the allocation of risk events among contracting parties, Cronbach's Alpha was calculated for the data set. The alpha values for data sets taken for the analysis (Annexure 05) are above than the value stated in section 4.3.1.1. Therefore, data taken for the analysis are reliable. In accordance with figure 4.7, the majority of the technical risk events allocated to contractors. This is probably due to the culture and widespread use of traditional contracts that places most of the risk on the contractor. Allocation of risk among parties in the event of design failure is too high to the consultant. Even though figure is showing that, most of the interviewed respondent pointed out that, the risk allocation to consultant is not properly practiced in Sri Lanka. In the event of consultant failure, there is no a remedial action. In such kind of situation usage of personal indemnity assurance is very much low (less than 17%). It is clearly shown by following figure 8. It is almost zero, where the consultant and client both are Sri Lankan companies. Risk allocation to the client is very much low according to findings of interviews. In practical situation consultant, risk also has to be endured by the client in Sri Lanka. Because contractor always try to price the risk, but there is a limitation. If he or she price every risk, in the event of competitive tendering there is a probability of losing it. Therefore, he may price most important risk events only.

Construction Risk: Further Consideration of Technical Risk

68

Data Analysis and interview analysis

Table 4. 10: Performance of risk events in construction life cycle

NO.

RISK FACTORS Design failures Equipment and system failures New technology failures Estimation errors Accident/ Collision Site Location and access Inadequate program scheduling and tight program scheduling Design changes / Design variations by client Hazards of environmental regulations Incompetence of transportation facilities Increase in site overheads Industrial disputes Local firms incompetence and low credibility Materials shortage Obsoleteness of building equipment Poor quality of procured accessory facilities Poor quality of procured materials Problems due to partners different practice Shortage in accessory facilities Shortage in skillful workers Shortage in supply of water, gas, and electricity Subcontractors low credibility Unknown site physical conditions Unusual weather and force majeure

RISK ALLOCATION CONSULTANT CONTRACTOR

CLIENT

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

RII 4.325 2.625 2.825 3.175 2.050 1.850 3.075 3.450 2.225 1.725 1.575 2.225 1.900 1.750 2.225 2.300 2.450 2.275 1.775 1.750 1.474 1.650 2.500 2.075

RII 2.200 3.775 3.450 3.025 4.100 3.575 3.750 3.075 3.375 3.925 3.825 3.600 3.425 3.900 3.300 3.450 3.975 3.725 3.500 4.275 3.625 4.000 3.725 3.350

RII 3.475 2.900 2.875 3.050 2.250 3.275 2.925 3.700 3.300 2.800 2.475 3.125 3.025 3.100 2.975 2.950 3.500 3.175 2.650 2.925 2.650 3.125 3.700 3.675

Construction Risk: Further Consideration of Technical Risk

69

Data Analysis and interview analysis

Figure 4. 7: Risk allocation of technical risk factors

Figure 4. 8: usage of PIA

Most significant risk factor is the Accident/ collision to contractor, where majority of respondents are considered that the in the event of accident /collision, risk allocation to the contractor is considerably high. According to table 4.10, it is high. According to questionnaire survey findings and interviews findings consultant is the person, who is having lesser allocation of technical risk. Based on the questionnaire findings, design changes / design variations by client is the technical risk having higher allocation to the client (RII= 3.700).
Construction Risk: Further Consideration of Technical Risk 70

Data Analysis and interview analysis

4.3.1.3.1 PROPER ALLOCATION OF TECHNICAL RISK IN CONTRACT Proper contractual arrangements determine who is more capable of controlling various specific risks. Generally, the local construction contracts mainly use condition of contract to do it. Usage of condition of contract type is shown in figure 4.9. Considering the findings of the structured interviews, ICTAD is the most using document as the condition of contract for the building projects, but interviewed respondents pointed out that the usage of the type of document will depend on the type of the client. Usage of ICTAD is 67% percentage. For the government project they most of the time use ICTAD. However, for the foreign Clients have to use FIDIC condition of contract.

Figure 4. 9: Type of condition of contract use in Sri Lankan building construction industry

However, interviewed respondents indicated that, allocation of technical risk between consultant and client in a contract is very much low in Sri Lanka. In most of the cases client has to suffer them. Because usage of condition of contract between consultant and client does not much consider about the risk allocation. In addition, they have argued that, effective allocation of technical risk among parties is a good risk mitigation strategy.

4.4 REVIEW OF FINDINGS


Any construction work will be subject to some technical risks, such as changes in design, equipment failure, shortage in skillful workers, material shortage, accident/ collision, etc. However, through this research it was attempted to forecast typical

Construction Risk: Further Consideration of Technical Risk

71

Data Analysis and interview analysis

technical risks associated with Sri Lankan building construction industry with questionnaire survey and structured interviews. Based on the questionnaire survey findings and interview findings, figure 10 shows most critical technical risk factors. Those were drafted by getting common risk factors from top ten significant risk factors, considering the significance of cost, time, and quality respectively. Those technical risk events are the most critical events when considering the impact and the probability. When considering the consequences and magnitude of impact to the project from the risk events which are very much higher than other factors, were considered in this particular research. Moreover, factors shown in the figure 4.10 are the highest ranked factors, when considering the impact to the time of the project, cost of the project and quality of the project. Based on the questionnaire survey findings, seven technical risk factors were identified as most critical risk events in figure 4.10. According to figure 4.10, shortage in skill full workers is the most critical risk factor. It is highly affect to the time, cost, and quality similarly. Shortage in skillful workers is a most significant risk to the contractor at the production stage. Therefore it is highly considerable technical risk factor in the construction industry.

Figure 4. 10: Most critical risk factors

Construction Risk: Further Consideration of Technical Risk

72

Data Analysis and interview analysis

Figure 4.11: Most Significant Risk factors performance in life cycle

Furthermore, figure 11 illustrates the performance of most significant technical risk factors within the life cycle of construction project in Sri Lankan construction industry. According to above argument, most significant risk factor is shortage in skillful workers. It is regularly in the production stage. Moreover, according to figure 12, shortage of skillful workers is risk to contractor than other parties in the construction industry. However, it is not much affecting to consultant but to some extent affect to the client.

Construction Risk: Further Consideration of Technical Risk

73

Data Analysis and interview analysis Figure 4.12: Most Significant Risk Factors Allocation among Contracting Parties

Second most significant technical risk according to figure 4.10 is inadequate program scheduling and tight program scheduling. That is happening due to, owners often impose tight construction schedule that might be difficult and impractical to achieve. Although, it is effecting to client, consultant, and contractor equally, contractor is the person much effected. It will occur in every stage of the construction life cycle, but it will considerably effect to the construction stage. Design changes / design variations by client, is the third critical technical risk event. It also similarly troubling to every contracting party, but higher portion allocation is going to client in the construction stage. Figure 4.11 and figure 4.12 showed performance in construction life cycle and allocation of critical technical risk factors illustrated in figure 4.10. Moreover, based on the interviewed respondents illustration, client is the person always suffered in every risk than other parties in Sri Lankan construction sector. Consultants errors are unable to clamed within the condition of contract according to Sri Lankan practice. If client needs get a claim, he has to go to court, because usage of PIA is very much less according to findings of this research. Furthermore, type of condition of contract between consultant client and contractor client is the other important factor considering the risk mitigation framework in the construction project. According to interviews findings, usage of Standard biding document prepared by ICTAD is much higher than the FIDIC condition of contract in Sri Lankan building construction industry. FIDIC document is mainly used when the client is a foreign company. For the government project most of the time SBD is used as the condition of contract. Therefore, there is a difference in such situation when considering the risk management. Even contractors risks are also attempted to be reduced by pricing the risk with the tender. Therefore, naturally allocation of risk to client will increase.

Construction Risk: Further Consideration of Technical Risk

74

Data Analysis and interview analysis

Construction Risk: Further Consideration of Technical Risk

75

Conclusion and Recommendation

Chapter 05
5 CONCLUSIONS AND RECOMMENDATION
5.1 CONCLUSION
Completion of construction project within the set down budget, time, and quality is becoming a very serious concern due to the regular cost overrun, time overrun and poor quality of the project. This consequence comes in the building construction automatically. Therefore, an enormous understanding of technical risk in construction project has become an imperative aspect for the building construction in competitive environment of Sri Lanka. To fill that gap of understanding, it is worthwhile to identify, what are the influencing factors in attaining the project ultimate goals, cost, time, and quality achievements and magnitude of technical risk in stages of construction project life cycle and allocation of construction risk among contracting parties. This particular research was mainly focused on to identification of currently prevailing technical risk factors in Sri Lankan building construction industry and finding out the significance of them considering project goals, cost, time, and quality. Moreover, it was also focused to find out the magnitude of technical risk factors in each stage of the construction project life cycle and to find out perceptions of construction industry practitioners about the technical risk allocation among contracting parties. This research was conducted with questionnaire survey and structured interviews. The survey was carried out based on the construction practitioners in Sri Lankan building construction industry. The quesionnaire was structured to get perception of two main sections. The first was intended to get respondents profile. The second section was intended to gather perception on the rating of each technical risk factors which were collected through the litrature survey. The first question relates to the probability of the technical risk
Construction Risk: Further Consideration of Technical Risk 76

Conclusion and Recommendation

events occurring on Sri Lankan construction projects. The respondents were asked to choose between very low, low, medium, high and very high. The second question refers to impact on project objectives namely time quility and cost, once the technical risk event ouccers. The third question refers to performance of technical risk in construction life cycle. Ultimatly, the forth question relates to the proper allocation of the risk among construction parties namely cotractor, client and consultant. The technique used to evaluate the collected data was RII. Reliability of collected data was checked by using Cronbach's Alpha. Moreover, interview guidelines were prepared to fulfill the gap in the questionnaire. Six practitioners were selected by getting two from each, client, consultant, and contractor. Throughout the literature survey, 24 technical risk factors were identified in the building construction industry. Respondents were asked to mention about their experience with that factors. Based on the collected data from the questionnaire survey, RII was calculated. Based on the calculated RII, consequences of technical risk factors and performance of each risk factor in stages of construction life cycle where figured out. Furthermore, the perception of building construction industry practitioners about the technical risk allocation among parties was figured out. Ultimately, all of the findings were drafted to expose most critical risk factors prevailing in the building construction industry. According to finding of the questionnaire survey, there were seven more critical risk events, when considering significance of technical risk factors to the project goals, time, cost, quality. Those can be listed as follows;

Construction Risk: Further Consideration of Technical Risk

77

Conclusion and Recommendation

Design changes / Design variations by client Estimation errors Inadequate program scheduling and tight program scheduling Materials shortage Shortage in skillful workers Unknown site physical conditions Unusual weather and force majeure

Moreover, whenever a project needs to consider more about the time then time significant technical risk factors has to be taken in to account. If quality is the most considerable project perspective, then quality significant risk factors have to be taken in to account. Where, the project having a limited budget cost has to take in to consideration more about the cost significant risk factors. Commonly for any type of building construction project most critical technical risk factors in overall has to be taken in to consideration. This will lead to completion the building construction project by achieving all project goals namely; within the time limit, within the budget limit, and with quality achievement. Among those critical risk factors most severe one is the shortage in skillful workers. It affects highly to the contractor rather than other parties. Commonly, it will occur in the production stage. Over eighty percent of practitioners have faced it within their projects. It means probability is also much higher. Second risk factor having more severity happens as a result of, owners often imposing tight construction schedule that might be difficult and impractical to achieve. According to perception of practitioners, allocation of that risk is higher to contractor and it will highly effect to the construction stage to the project. Over sixty percent of respondents had faced to that risk event. Design changes / design variation by client is the third severe risk factor, when concerning the significance of the risk. For that also, more then 70% percent of respondents indicated that, they had faced them. Similarly, all the other four risk factors out of selected seven factors affect to the project.
Construction Risk: Further Consideration of Technical Risk 78

Conclusion and Recommendation

Apart from that there were seventeen other technical risk factors such as design failures, accident/ collision, site location and access, etc. which were not as severe as aforesaid factors, but when concerning risk managing approaches, these factors should also be considered in total risk management strategy. Based on the interview findings, it was able to figure out usage of type of condition of contract and usage of PIA in Sri Lankan building construction industry. According to interviewed respondents, risks were allocated more to the client ultimately. Because, contractors risk is capable to be priced and consultant risk automatically comes to client according to Sri Lankan practice. This study is important as it sheds the light on the risks in a booming Sri Lankan construction industry. Technical risk identification and assessment is an important step in project risk management and shows the significance of several risks that are present in the industry. This study lays the foundation to assists local companies in negotiating their contracts as to the proper allocation of risks. This study also helps in decision making regarding risk response planning and control. Moreover, all of this mentioned critical technical risk factors more relevant to quantity surveyor than other professionals in the building construction industry. That is because, client quantity surveyor, consultant quantity surveyor or contractor quantity surveyor most of the time try to give a monitory value for that particular risk by predicting them at the initial stage. That would be the most efficient method of mitigation of risk and minimizing the effect of the risk to the building construction project. Therefore, the quantity surveyor needs to be more concerned about especially critical risk factors.

5.2 RECOMMENDATION
Considering all facts above discussed and identified, the cost, time and quality achievement of the building construction projects are effected by several critical technical risk factors, which are uncontrollable or unforeseeable by the parties to the

Construction Risk: Further Consideration of Technical Risk

79

Conclusion and Recommendation

contract at the initial stage. All those risk factors cannot be eliminated completely and the best would be to minimize the occurrence and impact to the project objectives by implementing proper mitigation process from initial stage with proper coordination among parties. Moreover, using proper condition of contract among parties can also manage the risk. Through considering project perspectives, risk mitigation process can be decided along these lines;

Whenever a project needs to consider more about the time then time significant technical risk factors has to be taking in to account.

If quality is the most considerable project perspective, then quality significant risk factors have to be taking in to account.

Where, the project having a limited budget cost. Cost significant technical risk factors have to be taken into consideration.

Besides, commonly for any type of building construction project most critical technical risk factors have to be taken into consideration.

It will lead to complete the building construction project by achieving all project goals namely; within the time limit, within the budget limit, and with quality achievement. Further, it recommends, improving the knowledge on risk management techniques and its applications; there should be a proper training or learning of the risk management field which is important to practitioners in the industry

5.3 FURTHER RESEARCH


The research was carried out within building construction project, and same

research can be done to the civil construction projects.


Construction Risk: Further Consideration of Technical Risk 80

Conclusion and Recommendation

The effectiveness of contingency in covering unforeseeable risk involvement in

building projects. Suitability of risk handling tools in better recovery of risk, in the contractors

perspective. Proper usage of condition of contact to handle construction risk.

Construction Risk: Further Consideration of Technical Risk

81

References

References

1) Adams, A.K., 2006. Expert elicitation and Bayesian analysis of construction contract risk: an investigation. Construction management and economics, 24, 81-96. 2) Ahmed, S.M. and Azhar, S.A., 2004. Risk management in the Florida Construction Industry. Challenge and opportunities for engineering education, research and development 2-4 June 2004, Miami, Florida, USA. Sustainable Environment, Track-Paper No. 077, 25(3), 601614. 3) Akintoye, A.S. and Macleod, M.J., 1997. Risk analysis and management in construction. International journal of project management, 15(1), 31-38. 4) Akintoye, A.S. and Macleod, M.J., 1997. Risk analysis and management in the construction. International journal of project management, 15(1), 31-38. 5) Al-Bahar, J.F., 1990. Systematic risk management approach for construction projects. Journal of construction engineering and management, 116(3), 530538. 6) Andi, 2006. The importance and allocation of risks in Indonesian construction projects. Construction management and economics, 24(1), 69 80. 7) Archbold, A.C., 2005. Managing the bottom line: risk management in policing. International journal of police strategies & management, 28(1), 3048. 8) Bajaj, D., Oluwoye, J. And Lenard, D., 1997. An analysis of contractors approaches to risk identification in new south wales, Australia. Construction management and economics, 15, 363-369.

Construction Risk: Further Consideration of Technical Risk

82

References

9) Baker, S., Ponniah, D. and Smith, S., 1999. Risk response techniques employed currently for major projects, Construction management and economics, 17, 205-213. 10) Barber, R., 2005. Understanding internally generated risks in projects. International journal of project management, 23(8), 58490. 11) Carter, R.L. and Doherty, N.A., 1974. Handbook of Risk Management, Kluwer-Harrap Handbooks: London. 12) Chapman, R.J., 2001. The controlling influences on effective risk identification. International Journal of project management, 19, 147160. 13) Chicken, J.C. and Posner, T., 1998. The philosophy of risk. Thomas Telford. 14) Cronbach, L. J., 1951. Coefficient alpha and the internal structure of tests. Psychometrika, 16(3), 297-334 15) Dallas, M., 2006. Value and risk management. Blackwell: UK 16) Dhanasinghe, I., 2007. Risk allocation and risk handling of road project in sri lanka . Unpublished Dissertations (BSc). University of Moratuwa, Sri Lanka. 17) Edwards, R.J. and Browen, P.A., 1998. Risk and risk management in construction: a review and further directions for research. Construction and architectural management, 5(4), 339-349. 18) El-Sayegh, S.M., 2008. Risk assessment and allocation in the UAE construction industry. International journal of project management, 26(1), 431-438. 19) Flanagan, R. and Norman, G., 1993, Risk Management and Construction, Blackwell Science Ltd: Oxford. 20) Fong, S. W., 1987. Risk management. The Cost Engineer, 2, 12-16.

Construction Risk: Further Consideration of Technical Risk

83

References

21) Ginige, K.N., 2005, Public image on the construction industry: an opinion survey, Unpublished Dissertation (BSc). University of Moratuwa, Sri Lanka.

22) Hamshayini, K., 2007. Construction project risks: further consideration for contractors pricing in Sri Lanka. Unpublished Dissertations (BSc). University of Moratuwa, Sri Lanka. 23) Hassanein, A.A.G. and Afify, A.F., 2007. A risk identification procedure for construction contracts-a case study of power station project in Egypt. Civil engineering and environmental systems, 24(1), 3-14. 24) Highways Agency, 2001. Highways agency framework for business risk management. Report of the Highways Agency, London: England, http://wwwcf.fhwa.dot.gov/exit.cfm? 25) Hilson, D., 2003. Using a risk management breakdown structure in project management. Journal of facilities management, 2(1), 8597. 26) Jamil, M., Mufti, N.A. and Khan, H.A., 2008. Risk Identification for International Joint Venture Construction Projects. First international conference on construction in developing countries, 4-5 August 2008, Karachi,, Pakistan. 291-301. 27) Kangari, R., 1988. Construction risk management. Civil engineering and environmental systems, 5 (3), 114120. 28) Kangari, R., 1995. Risk management perceptions and trends of US construction. Journal management in engineering, 121 (4), 422429. 29) Kartam, N.A. and Kartam, S.A., 2001. Risk and its Management in the Kuwaiti Construction Industry: a Contractors Perspective, International journal of project management, 19, 325-335. 30) Kerzner, H., 2001, Project management: A System approach to Planning, Scheduling & Controlling, 7th ed. Wiley & Sons, Inc: New York.

Construction Risk: Further Consideration of Technical Risk

84

References

31) Kolltveit, B.J. Karlsen, J.T. and Gronhaug, K., 2004. Risk Exploiting opportunities in uncertainty during the early phase. Journal of construction engineering and management, 134140.

32) Kraemer, L.K., 2002. Survey research methodology in management information systems: an assessment. Working paper on graduation of management of school, University of California, California. 33) Kwak, Y.H. and Dewan, S., 2001. Risk management in international development projects, Project Management Institute Annual Seminars & Symposium, 1-10. 34) Mak, S. and Picken, D., 2000. Using risk analysis to determine construction project contingencies. Journal of construction engineering and management, 126( 2) 130-136. 35) Mills, A., 2001. A systematic approach to risk management for construction. Structural survey, 5, 254252. 36) Nunnally, J. C. and Bernstein, I., 1978. Psychometric Theory, 3rd ed. USA: McGraw- Hill Humanities 37) Osama, J.A. and Almishari, S., 2003. Risk assessment in construction. Journal of construction engineering and management, 129(5), 492-500. 38) Osipova, E., 2007. Risk management in the different phases of a construction project- a study of actors involvement. Mining and Environmental Engineering, 1-13. 39) Patrick, X.W.Z., Zhang, G. And Wang, J., 2007. Understanding the key risks in construction projects in china. International journal of project management, 121(4), 422429. 40) Pennock, M. and Haimes, Y., 2001. Principles and Guidelines for Project Risk Management. Systems Engineering, 5(2), 89-108.

Construction Risk: Further Consideration of Technical Risk

85

References

41) Perera, K.B.D., 2006. Simulation modeling for time and cost overruns in road rehabilitation projects in Sri Lanka. Unpublished Dissertations (BSc). University of Moratuwa, Sri Lank. 42) 521.
[

Perry J.G. and Hayes, R.W., 1985. Risk and its management in

construction projects. Proceedings of institute of civil engineers , 78(1), 499

43) Peter, D., (1997). Risk analysis and management for major construction projects. Cobra 1997 [online], Available foundationorg/aboutus.html 44) Poh, Y.P. and Tah, J.H.M., 2006. Integrated durationcost influence network for-modeling risk impacts on construction tasks. Construction management and economics, 24(8), 861868. 45) Pushpakumara, P.A.D., 1997. Managing the pricing risks and uncertainties on below ground construction works in buildings. Unpublished Dissertations (BSc). University of Moratuwa, Sri Lank. 46) Rahman, M.M. and Kumaraswamy, M.M., 2005. Assembling integrated project teams for joint risk. Journal of construction engineering and management, 23(4), 365375. 47) Rowe, W.D., 1977. An anatomy of risk. New York: Wiley. 48) Saunders, M., Lewis, P. and Thornhill, A., 2004, Research Methods for Business Students, 3rd ed, Singapore: Pearson Education Pte Ltd. 49) Senarathne, S., 2005. A knowledge-based approach to managing project change in the construction phase within collaborative ream settings. Unpublished Thesis (PhD). University of Salford: UK 50) Shen, L.Y., 1997. Project risk management in Hong Kong. International Journal of project management, 15(2), 101105. from: http://www. Rics-

Construction Risk: Further Consideration of Technical Risk

86

References

51) Shen, L.Y., Wu, G.W.C. and Ng, C.S.K., 2001. Risk assessment for construction joint ventures in china. Journal of construction engineering and management, 127(1), 76-81. 52) Stoner, J.A.F., Freeman, R.E. and Gilbert, D.R., 1995. Management. 6th ed. Prentice-Hall, Inc: New Jersey. 53) Streniner, D.L. and Norman, G.R., 1989. Health measurement scales a practical guide to their development and use . New York: Oxford University Press. 54) Tah, J.H.M. and Carr, V., 2000. Information modeling for a Construction Project Risk Management System, Engineering, construction and architectural management, 72, 107-119. 55) Tchankova, L., 2002. Risk Identification-basic stage in risk management. Environmental management and health, 13(3), 290297. 56) Thevendran, V. And Mawdesley, M.J., 2004. Perception of human risk factors in construction projects: an exploratory study. International journal of project management, 22(2), 131137. 57) Thilakarathne, W.B.M., 2007. Risk Identification and Risk Handling of Road Rehabilitation Projects in Sri Lanka. Unpublished Dissertation (BSc). University of Moratuwa, Sri Lanka. 58) Thompson, P. and Perry, J., 1992. Engineering Construction Risks: A Guide to Project Risk Analysis and Risk Management. Thomas Telford: London. 59) Uher, T.E. and Toakley, A.R., 1999. Risk management in the conceptual phase of construction. International journal of project management, 25(3), 601614. 60) Wang, M. and Chou, H., 2003. Risk allocation and risk handling of highway projects in Taiwan. Journal of Management Engineers, 19(2), 6080.

Construction Risk: Further Consideration of Technical Risk

87

References

61) Wang, S.Q., Dulaimi, M.F. and Aguria, M.Y., 2004. Risk management framework for construction projects in developing countries. Construct management and economics, 22(3), 237252. 62) Woodward, J.F., 1997. Construction project management. USA: Thomas Telford services. 63) Yin, R., 1994. Case study research: design and methods. 2nd ed. CA: Sage.

Construction Risk: Further Consideration of Technical Risk

88

Appendix

Appendix

Construction Risk: Further Consideration of Technical Risk

89