Machine Measurements
Machine Measurements
u Introduction u Test u Test
Preparation Procedures
Not typically verified by field tests Parameters may change (aging, tuning)
Power Technologies, Inc.
Possible increase in power transfer capability Equally possible decrease in power transfer capability Increased accuracy in calculation of transient and dynamic stability limits
Power Technologies, Inc.
Plant and generator protection remains intact No interruption of CT signals Unit instantly available if needed
Information
One-line diagram showing metering, protection, and supply to auxiliaries Generator and turbine nameplate data Manufacturers data
Reactances and time constants Saturation curves and Vee curves Reactive capability curve Exciter and governor models, equipment info
Power Technologies, Inc.
Information (cont.)
Plant data
Hydro unit - physical description (measurements) of flow path (penstock, surge tank, tailrace) Steam unit - heat balance diagram All units - Allowed operating ranges (local criteria or practices)
Signals
Accessibility & Location Preconditioned? Transducers? Time delay? Determine location of test equipment Wire signals to common terminal block Signal electrical isolation
Power Technologies, Inc.
control room
Note meter locations and signal ranges Determine feasibility of getting steady state data from SCADA printouts on demand Determine method of communications between operator and test engineers
Test Sequence
Test Procedure
Plant Operators and Engineers Plant Informs System Dispatchers No operator adjustments during data recording Tests typically require 1-2 days, including instrumentation setup
Machine Measurements
u u u u
Machine Measurements
DSM System 200 u Portable Version
Measurement Equipment
u Clamp-on
CT
Core CT
Transducer
Pick-up
Pick-up
State Tests
Tests
Machine Measurements
Open Circuit Test Procedure
u Goal:
Machine Measurements
Open Circuit Test Procedure (cont.)
u Terminal
30%, 40%, 50%, 60%, 70%, 75%, 80%, 85%, 90%, 95%, 100%, 104%, 108% of rated.
u Take
backup readings (DVM, SCADA) when possible u Make sure generator is isolated from auxiliary loads
Power Technologies, Inc.
Machine Measurements
Open Circuit Test Coordination Requirements
u Plant
Operators:
Need to be able to hold unit at rated speed, open circuit (no power)
Hydro units - vibration, controls Steam units - turbine heating, controls Gas turbines - generally no problems
Machine Measurements
Open Circuit Test Procedure (cont.)
Machine Measurements
Vee Curve Test Procedure (cont.)
u Measured
Values:
Terminal voltages (from PTs) Armature currents (from CTs) Generator field voltage (direct) and current (from shunt) Exciter field voltage (direct) Turbine speed (automatic from DSM) Control signal from governor, valve/gate position, etc. Power angle (requires special instrumentation) if possible
u Calculated
Values:
Machine Measurements
Vee Curve Test Procedure (cont.)
u Measurement
Points
Based on unit reactive capability curve Five MW levels (0, 25, 50, 75, 100%) Five MVAr levels at each MW level
Max (+,-) VARs that you are comfortable with 50% of maximum (+,-) Unity power factor
Machine Measurements
Vee Curve Test Procedure (cont.)
u Example
MVARS ABSORBED
OVEREXCITATION REGION
B 50
MVARS SUPPLIED
D 50 UNDEREXCITATION REGION
Machine Measurements
Vee Curve Test Procedure (cont.)
u Measurement
Typical V Curve Measurement Points 500 MW Unit
MW 0 40 80 125 170 210 250 290 330 375 420 460 500 MVAR -250, -125, 0, 125, 250 0 0 -250, -125, 0, 125, 250 0 0 -200, -100, 0, 100, 200 0 0 -150, -75, 0, 75, 150 0 0 -100, 0, 100
Machine Measurements
Vee Curve Coordination Requirements
u Plant
Operators:
Machine Measurements
Vee Curve Coordination Requirements
u System
Operators:
Machine Measurements
Partial Load Rejection Test Procedure
u Goals:
Generator transient and subtransient reactances and field time constants Turbine-generator inertia Excitation system model parameters Governor model parameters
Machine Measurements
Partial Load Rejection Test Procedure
u Procedure:
Five partial load rejections Purpose: provide disturbance to excite unit and determine dynamic response Tests are designed to isolate parameters in order to simplify analysis
Machine Measurements
Load Rejection Coordination Requirements
u Plant
Operators:
Need to go to desired loading (real and reactive power) Isolate generator from auxiliary loads Will open main breaker to initiate test Coordinate opening with measurement team No operator adjustments until recording of test completed Re-synchronization following test and preparation for next test
Power Technologies, Inc.
Machine Measurements
Load Rejection Coordination Requirements
u System
Operators:
Inform system operator that test is imminent System will see loss in real and/or reactive power Change in frequency very small for systems with large generating capacity Change in line flows or bus voltages may be significant Preventative dispatch or other operating changes?
Power Technologies, Inc.
Machine Measurements
Partial Load Rejection Test Procedure
u Test
unit so open circuit voltage is lower than operating voltage u Generator saturation minimized
Power Technologies, Inc.
Machine Measurements
Partial Load Rejection Test Procedure
u Test
26 24 Terminal Voltage (kV) 22 20 18 16 14 12 0 5 10 15 Tim e ( S e c o n d s ) 20 25 30
Machine Measurements
Partial Load Rejection Test Procedure
u Test
0 MW -30% MVAR
Limit var absorption so that field voltage does not go below 50% of value at rated voltage, no load.
Machine Measurements
Partial Load Rejection Test Procedure
u Test
25.6 25.4 Terminal Voltage (kV) 25.2 25 24.8 24.6 24.4 0 2 4 6 8 10 Time (Seconds)
Machine Measurements
Partial Load Rejection Test Procedure
u Test
u AVR
Machine Measurements
Partial Load Rejection Test Procedure
u Test
u Small
Machine Measurements
Partial Load Rejection Test Procedure
u Test
limit determination
Machine Measurements
Partial Load Rejection Test Procedure
u Test
3% Overspeed
system step test on a nuclear unit u Plot of terminal voltage versus time
Time (cycles)
Power Technologies, Inc.
dleiF
Time (cycles)
Power Technologies, Inc.
Time (cycles)
Time (cycles)
Governor load rejection test. 44 MVA hydro unit (4.8 MW rejection) Plot of generator speed deviation versus time (measured and from simulation model)
Speed
Time (Seconds)
Power Technologies, Inc.
Gate
Time (Seconds)
Power Technologies, Inc.
sition
Governor load rejection test. 45 MVA gas turbine unit (5.4 MW rejection) Plot of generator speed deviation versus time (measured and from simulation model)
Time (Seconds)
Power Technologies, Inc.
Same governor load rejection test. (45 MVA gas turbine) Plot of FSR (fuel command voltage) versus time (measured and from simulation model)
FSR
Time (Seconds)
u)
Same governor load rejection test. (45 MVA gas turbine) Plot of exhaust temperature (oC) versus time (measured and from simulation model)
oC)
Time (Seconds)
Power Technologies, Inc.
Governor load rejection test. Same 45 MVA gas turbine unit 12.9 MW load rejection Plot of generator speed deviation versus time (measured and from simulation model)
d e e p S
Time (Seconds)
FSR
Same governor load rejection test. (45 MVA gas turbine - 12.9 MW rejection) Plot of FSR (fuel command voltage) versus time (measured and from simulation model)
Time (Seconds)
Power Technologies, Inc.
u)
Same governor load rejection test. (45 MVA gas turbine - 12.9 MW rejection) Plot of exhaust temperature (oC) versus time (measured and from simulation model)
oC)
Time (Seconds)
Governor load ramp test. Same 45 MVA gas turbine unit Plot of generator electric power versus time (measured and from simulation model)
E el c cirt
Time (Seconds)
Power Technologies, Inc.
FSR
Time (Seconds)
Power Technologies, Inc.
u)
Plot of exhaust temperature (oC) versus time (measured and from simulation model)
oC)
Time (Seconds)
Power Technologies, Inc.