Series 2000: Site Clearance Table of Content

SERIES 2000: SITE CLEARANCE


TABLE OF CONTENT

DIVISION 2100: CLEARING AND GRUBBING.............................................................................2 2101 Scope ................................................................................................................................2 2102 Description of Work .........................................................................................................2 2103 Execution of Work............................................................................................................3 2104 Measurement and Payment...............................................................................................4 Item 21.01 Clearing and grubbing ...................................................................................4 Item 21.02 Removal and grabbing of large trees and tree stumps...................................4 Item 21.03 Reclearing of surfaces ...................................................................................4 Item 21.04 Removal and storage of selected vegetation: ................................................4 DIVISION 2200: DEMOLITION, REMOVAL, DISPOSAL OR STORAGE OF EXISTING STRUCTURES AND INSTALLATIONS...........................................................................................5 2201 Scope ................................................................................................................................5 2202 Construction Requirements for Demolition and Removal of Existing Structures ...........5 2203 Construction Requirements for Demolition And Removal of Existing Road Pavements.........................................................................................................................5 2204 Construction Requirements for Existing Public Utilities .................................................6 2205 Measurement and Payment...............................................................................................6 Item 22.01 Clearing and grubbing at inlets and outlets of hydraulic structures ..............6 Item 22.02 Cleaning out of hydraulic structures..............................................................6 Item 22.03 Take up or down and set aside for reuse or remove to store off Site ............6

Ethiopian Roads Authority

Page 2000-1

Series 2000: Site Clearance Division 2100: Clearing And Grubbing

Standard Technical Specification -2002

DIVISION 2100: CLEARING AND GRUBBING


2101 SCOPE
This Division covers the clearing of the Site and grubbing necessary for the construction of the Works covered by the Contract, in accordance with these Specifications, and the removal and disposal of materials resulting from clearing and grubbing. This work shall also include the preservation from injury or defacement of all vegetation and objects designated to remain.

2102 DESCRIPTION OF WORK


(a) Clearing Clearing shall consist of the removal of all trees, brush, other vegetation, rubbish, fences and all other objectionable material including the disposal of all material resulting from the clearing and grubbing. It shall also include the removal and disposal of structures that obtrude, encroach upon or otherwise obstruct the work and which can be cleared by means of a bulldozer of approximately 22 tons mass and flywheel power of approximatel 270kW. The moving of a certain amount of soil or gravel material may be inherent to or unavoidable during the process of clearing and no extra payment will be made for this. Clearing shall include the removal of all rocks and boulders of up to 0.15 cu.m. in size which are exposed or lying on the surface. Where fences have to be taken down and the material sorted, coiled and stacked, payment for this work shall be made under series 9000. (b) Grubbing Where directed by the Engineer, all stumps and roots larger than 75mm in diameter shall be removed to a depth of not less than 600 mm below the finished road level and a minimum of 75 mm below original ground level. Where the existing ground has to be compacted, all stumps and roots including matted roots shall be removed to a depth of at least 200 mm below the cleared surface, except where otherwise specified or directed by the Engineer. Except at borrow areas the cavities resulting from the grubbing shall be backfilled with approved material and compacted to a density not less than the density of the surrounding ground. (c) Conservation of topsoil Where suitable topsoil exists within the limits of the area to be cleared and/or grubbed, the Contractor shall, if ordered by the Engineer, remove the topsoil together with any grass and other suitable vegetation. If not used immediately, the topsoil shall be transported and deposited in stockpiles for later use. The Contractor will not be required to remove topsoil to an average depth of less than 150 mm from any particular area.

Page2000-2

Ethiopian Roads Authority

Standard Technical Specification - 2002

Series 2000: Site Clearance Division 2100: Clearing And Grubbing

This work shall be measured and paid for under Division 9600, payitem 96.01. Where topsoil can be removed without the necessity of first performing clearing and grubbing, no payment will be made for clearing and grubbing under this Division. (d) Conservation of vegetation Where provided for in the project specification, certain designated plants encountered in the road reserve and borrow areas shall be carefully protected by the Contractor.

2103 EXECUTION OF WORK


(a) Areas to be cleared and/or grubbed. The portions of the road reserve that fall within the limits of the road prism as well as certain borrow areas may require to be cleared and/or grubbed. The Engineer shall designate the areas to be cleared and such areas shall not necessarily be limited to those mentioned above. The Contractor shall note that in order to avoid reclearing, the clearing and/or grubbing may have to be done immediately before subsequent construction activities. Individual trees designated in writing by the Engineer shall be left standing and uninjured. A penalty equal to the amount specified in the project specifications shall be imposed for every such tree, which is unnecessarily removed or damaged. (b) Cutting of trees The Contractor shall take the necessary precautions to prevent damage to structures and other private or public property. If necessary trees shall be cut in sections from the top downwards. The branches of trees to be left standing shall be trimmed so as not to intrude into the space for up to 7 m in height above the roadway. (c) Disposal of material Material obtained from clearing and/or grubbing shall be disposed of, as indicated by the Engineer, in borrow pits or other suitable places and covered up with soil or gravel. The burning of combustible material will normally be permitted but may only be done with the prior written approval of the Engineer. Care must be taken to observe any regulations concerning pollution of the air. All tree trunks and branches in excess of 150 mm in diameter shall be cleaned of secondary branches, sawn into suitable lengths and stacked at sites indicated by the Engineer. Such timber shall not be used by the Contractor for any purpose and shall remain the property of the Employer unless otherwise agreed with the Engineer. Fencing wire shall be neatly wound into reels and all such wire, together with all fence posts and other usable material from structures, etc., shall be stacked at sites indicated by the Engineer.

Ethiopian Roads Authority

Page 2000-3

Series 2000: Site Clearance Division 2100: Clearing And Grubbing

Standard Technical Specification -2002

2104 MEASUREMENT AND PAYMENT


Item 21.01 Clearing and grubbing..........................................................................hectare The unit of measurement for clearing and grubbing is the hectare. The quantity shall be taken as the area in hectares (to the nearest 0.1 ha) designated by the Engineer and cleared and grubbed in accordance with these Specifications. The area occupied by the existing road prism will be included. The tendered rate shall include full compensation for all work necessary for the clearing of the surface, the removal and grubbing of trees and tree stumps, cutting of branches, backfilling of cavities, demolishing and disposal of structures and the removal, transporting and disposal of material all as specified in this Division. Item 21.02 Removal and grabbing of large trees and tree stumps (a) (b) (c) Girth exceeding 1 m up to and including 2 m........................................number (No) Girth exceeding 2 m up to and including 3 m........................................number (No) Etc. in steps of 1 m girth.

The girth of trees or stumps shall be measured at the narrowest point of the tree or stump in the first meter of its height above ground level. Trees and stumps with a girth exceeding 1 m shall be measured individually and classified according to size in increments of 1 m as indicated above. Item 21.03 Reclearing of surfaces (on the written instructions of the engineer only) .. ........................................................................................................ hectare (ha) The unit of measurement for reclearing areas which have previously been cleared shall be the hectare. The quantity shall be measured to the nearest 0.1 ha. Item 21.04 Removal and storage of selected vegetation: (a) Cost of removal, storing, protection and replanting in a protected and fenced-off area of selected vegetation ..............................................................................provisional sum (b) Charge on provisional sum ............................................................... percentage (%)

Page2000-4

Ethiopian Roads Authority

Standard Technical Specification - 2002 Series 2000: Site Clearance Division 2200: Demolition, Removal, Disposal Or Storage Of Existing Structures And Installations

DIVISION 2200: DEMOLITION, REMOVAL, DISPOSAL OR STORAGE OF EXISTING STRUCTURES AND INSTALLATIONS
2201 SCOPE
This Division covers the demolition, disconnection, removal or part removal, disposal and or storage of buildings, bridges, drainage structures, retaining walls, wells, buildings, service ducts, foundations, fencing, walls, kerbs, old pavements, abandoned pipelines, disused public utilities and any other obstructions which are not designated or permitted to remain, except for the obstructions to be removed and disposed of under other items in the contract.

2202 CONSTRUCTION REQUIREMENTS FOR DEMOLITION AND REMOVAL OF EXISTING STRUCTURES


Existing structures and installations shall be demolished as described in the Contract or as instructed by the Engineer. The existing structures and installations shall be removed in such a way as to leave no obstructions to the new Works. Those structures and installations, which are to be partially demolished, shall be shored, braced and supported in such a manner that the integrity of the structure shall be maintained. All supports shall be kept outside the right of way. The Contractor shall carefully remove and store materials salvaged from demolished structures and installations. Unless otherwise stated in the Contract, such materials shall become the property of the owner. This material shall be carefully transported and stored in an acceptable manner upon the owner's adjacent property or at a location to be identified by the Engineer. (i) Whenever materials are stored within the right-of-way, the Contractor shall be responsible for its care and preservation until its authorised removal. The Contractor shall satisfactorily dispose of all material designated by the Engineer as having no salvage value in accordance with the requirements of Division 1600. The Contractor shall remove structures and installations or part of structure and installations, which obstruct with the installation of a new structure or installation. (ii) Unless otherwise directed by the Engineer any voids below ground level in existing structures or installations shall be filled with natural sand or crushed fine aggregate. Latrine pits, septic tanks etc. shall be cleaned out and disinfected and the contents disposed of in accordance with the requirements of Division 1600 before the filling with approved material.

2203 CONSTRUCTION REQUIREMENTS FOR DEMOLITION AND REMOVAL OF EXISTING ROAD PAVEMENTS
(a) Method and Equipment Existing road pavements shall be demolished by excavation, scarifying or milling using appropriate equipment approved by the Engineer.

Ethiopian Roads Authority

Page 2000-5

Series 2000: Site Clearance Standard Technical Specification -2002 Division 2200: Demolition, Removal, Disposal Or Storage Of Existing Structures And Installations

(b) Disposal or Storage of Materials Material resulting from the demolition of existing road pavements shall be disposed of or stored as instructed by the Engineer.

2204 CONSTRUCTION REQUIREMENTS FOR EXISTING PUBLIC UTILITIES


(a) Disconnections Before the commencement of demolition operations, the Contractor shall notify the Engineer who shall arrange for the disconnection of all disused public utilities, including electricity, telephone, sewer, water and other facilities encountered. (b) Protection of Existing Public Utilities Existing utilities, which are to remain in place, such as sewers, drains, water pipes, conduits, poles, etc. are to be carefully protected from injury and are not to be displaced. (c) Relocation of Existing Public Utilities The Contracting Authority shall arrange with the appropriate authorities for the necessary relocation of any public utilities, which would otherwise obstruct the Works. The Contractor shall comply with the requirements of Clause 1207.

2205 MEASUREMENT AND PAYMENT


Item 22.01 Clearing and grubbing at inlets and outlets of hydraulic structures ........... ...............................................................................................square meter (m2) The unit of measurement for clearing and grubbing at inlets and outlets of hydraulic structures is in square meter (m2) measured within the limits of the areas designated by the Engineer, which are cleared and grubbed in accordance with these Specifications. Item 22.02 Cleaning out of hydraulic structures (a) (b) (c) (d) Pipes with an internal diameter up to and including 750 mm .........cubic meter (m3) Pipes with an internal diameter exceeding 750 mm ........................cubic meter (m3) Box culverts up to and including 1.5 m vertical dimension ........... cubic meter (m3) Box culverts exceeding 1.5 m vertical dimension ......................... cubic meter (m3)

The unit of measurement shall be the cubic meter (m3) of material removed from hydraulic structures where instructed by the Engineer so that the structures are cleaned as specified. Payment under this item will normally only be made once during the duration of the contract. Item 22.03 Take up or down and set aside for reuse or remove to store off Site the following (i) Blockwork and stone work .............................................................cubic meter (m3)

Page2000-6

Ethiopian Roads Authority

Standard Technical Specification - 2002 Series 2000: Site Clearance Division 2200: Demolition, Removal, Disposal Or Storage Of Existing Structures And Installations

(ii)

Paved areas and the like, brickwork............................................. square meter (m2)

(iii) kerbs, channels, edgings, combined drainage and curb blocks, fencing, safety fences and the like, copings, string courses and the like .............................linear meter (lm) (iv) Cable............................................................................................... linear meter (lm) (v) Road lighting columns, brackets and wall mountings, traffic signs, reflecting road studs, gates, stiles, street furniture, communications cabinets, posts, brackets, signal indicators, shelves, racking, frames, electronic units and the like............................... number (vi) (vii) Chamber covers and frames, gully gratings and frames and the like.............number Individual blocks, features or stones ............................................................ number

The measurement for take up or down and set aside for reuse or remove to store off Site blockwork, stonework, paved areas and the like, brickwork, kerbs, channels, edgings, combined drainage and kerb blocks, fencing, safety fences and the like, copings, string courses and the like, cable, road lighting columns, brackets and wall mountings, traffic signs, reflecting road studs, gates, stiles, street furniture and the like; communications cabinets, posts, brackets, signal indicators, shelves, racking, frames, electronic units and the like; chamber covers and frames, gully, gratings and frames and the like; individual blocks, features or stones shall be the volumes, areas, lengths or numbers stated in the Contract.