Académique Documents
Professionnel Documents
Culture Documents
Universidad de Oviedo
Project Management
Risk Management
Lecturer: Javier Daz lvarez
Risk Management
Introduction Plan Risk Management Risks Identification Risk Analysis Risk Responses Monitor and Control Risks
Categories of Risk
Known risks: has been identified, has been analyzed and can be managed. Unknown risks: may be addresed through a general contingency based on experience with similar projects. Threats (negative) Opportunities (positive)
Exercise 4.1
Project. Promotion and construction (civil works, transport and erection o a wind farm of 40 MW (20 wind turbines) in Leon mountains (1500 masl).
Preliminar Risks Identification. Write them in 5 minutes. Compare the responses of the assitants and save them.
Risk Management
Introduction Plan Risk Management Risks Identification Risk Analysis Risk Responses Monitor and Control Risks
Risk Categories
Technical Law related issues Organizacional Project Management External
Requirements
Permitting
Project Dependencies
Estimating
Technology
Contracts
Resources
Planning
Regulatory
Legal proceedings
Funding
Controlling
Market
Priorization
Communication
Customer
Quality
Weather
Insignificant < 1% increase increase Insignificant < 5% increase increase Barely noticeable decrease
Time
Scope
Quality
Barely Only very Sponsor noticeable demanding approval degradation applications required are affected
Risk Management
Introduction Plan Risk Management Risks Identification Risk Analysis Risk Responses Monitor and Control Risks
Risks Identification
Risk events must be specific and must be completely defined. It must include what, when and the impact of each risk. Identification process should be done from the task list. Develop a complete risk list. Identification tasks should be done as team work or in different teams constituted by members of the team project. Focus on Risk Identification, do not try to analyze them at this moment
Experts identification
Brainstorming
Analogy method
Stage 1
Identify similar projects Stage 2 Focus on similar components of the project Accumulate useful data Stage 3 Analyze data Include the conclusion in the list of risks
Stage 4
List of Risks
Risk Code Category (task) Threat / Opportunity event Probability Impact Prob x Imp Priority
Risk Register
At the end of the proccess, the Risk Register will be done. It is an evolutionary document that serves to capture risk information. It includes:
List of Risks List of potencial responses Root causes of risks Update of the Risk Cathegories Chart
Exercise 4.2
Project. Promotion and construction (civil works, transport and erection o a wind farm of 40 MW (20 wind turbines) in Len mountains (1500 masl).
Starting from the Tasks List and using some of the explained tools, write the List of Risks. Assign probability and impact and complete List of Risks Chart. Elaborate a list of potencial responses. Find root causes of the risks Make a proposal for updating the Risk Cathegories Chart
Risk Management
Introduction Plan Risk Management Risks Identification Risk Analysis Risk Responses Monitor and Control Risks
Probability
Impact
Impacts description:
Very low impact. If the event occurs, it will not impact in cost, time, quality or client satisfaction. Low impact. If the event occurs, it will have a mild effect. Medium impact. If the event occurs, it will impact moderately. High impact. If the event occurs, it will have a significant effect. Very high impact. If the event occurs, it will have a very important effect.
30+0,01*800+0,99*0= 38 k
1 week; 30 k 99%
0+0,05*800+0,95*0=40 k
95%
Pass
Exercise 4.3
Project 40 MW in Leon (3000 neh/year). Analyze the possibility of starting the works one week before obtaining the work licence using the decision tree analysis.
80/MWh 60% possibility of the stop of the works (0,5 weeks of delay) and 150 k penalty 30% possibility of 150 k penalty 10% possibility of nothing
Exercise 4.3
Stop Works + Penalty
60% 30%
Penalty
Nothing
0 k
1 week; 62,5 neh. 40 MW x 250 neh/month x 1 month /4,2 weeks x 80 /MWh = 190,4 k 0,5 weeks ? 190,4 k / 2 = 95,2 k
37
Comparison of methods
Qualitative
Fast and easy to administrate Difficult of using in a uniform way in the organizacin Ir requires definitions, rules, standards and processes
Quantitative
It is preferred (most of the times obligued) by the direction More time is required, it needs estimation Numbers give a precission image, but it depends on the precission of the estimation It is difficult if team project doesnt want to give figures It allows to see tendences Easier to predict More valuable
Network diagram
Example Calculate critical path using a balanced average time: (Optimistic value + 4*Probable value + Pesimistic value)/6
Exercise 4.4
The activities for the construction of one new wind turbine in an existing wind farm are the following:
Activity 1.- Wind turbine foundation digging 2.- Wind turbine erection 3.- Cable conection to wind turbine and tests 4.- Trench digging 5.- Cable lying 6.- Cable connection to substation 7.- Tests and energizing Balanced Predeccessor Optimistic Expected Pesimistic average time 1 2, 5 4 5 6 2 3 1 2 1 1 0,5 5 5 4 5 4 2 1 7 7 8 14 10 4 10 4,83 5,00 4,17 6,00 4,50 2,17 2,42
Draw network diagrams and calculate critical paths for Expected Values and for Balanced Average time: (Optimistic value + 4*Probable value + Pesimistic value)/6
Exercise 4.4
0 Task 1 (5) 0 0 Start 0 0 Task 4 (5) 1 6 6 5 5 Task 5 (4) 10 11 9 9 Task 6 (2) 13 13 11 11 Task 7 (1) 14 12 14 5 5 5 5 Task 2 (5) 10 10 10 10 Task 3 (4) 14 14 End 14
4,8 5,9
9,8 10,9
6,0 6
10,5 10,5
12,7 12,7
15,1 15,1
45
Expected Value
Best case Base case Concrete problem Productivity increase Snow in april Total 10.000 0 -200 0 9.800 50% 10% 50% Probabilit y Expected Value Worst case 10.000 200 -20 400 10.580 10.000 400 0 800 8.800
Prioritize Risks
Project Team must prioritize the risks which should be taken into account because there will not be enough time and resources to respond to risks. Prioritization must be done from Risk Register. Work should be done by all the team. In this stage, do not think about responses.
Prioritize Risks
Qualitative method. Clasify taking into account only the impact (not the probability). Do two lists, one with cost impacts and another one with time impacts. Quantitative method. Clasify risks according to their Expected Value (probability x impact). Filtered. Elaborate a list of questions and filter all the risks. Ask each question to all the remaing risks. Start with the first question and discard the risks with non significative impact. Then the second question.
Filtered method
Filter one. Is the impact significative (performance, quality, cost, time, scope)? Filter two. Has anybody seen it before? Do conditions or circunstances which make the risk more probable exist? Filter three. Does the risk have an inmediate effect on the project? Does it require a long actuation? Do we have to act in a short time? Filter four. Does the risk have a solution that is out of Board control?
Exercise 4.5
Project 40 MW in Leon.
Starting from the Risk Register, prioritize risks using the filtered method.
Risk Management
Introduction Plan Risk Management Risks Identification Risk Analysis Risk Responses Monitor and Control Risks
Strategies
Strategy for threats and opportunities
Accept
Accept
Acceptance:
Active. Develope a contingency plan Passive. Do not do anything. Accept consecuencies.
Mitigate
Take specific actions to:
Reduce risk probability Reduce risk impact
Estimate and evaluate mitigation strategy Document and communicate strategy Keep reevaluating the risk during the life of the project
Transfer
Subcontract Use guaranties (Warranties) Contractual guaranties (Guaranties) Ensurances Contract with client
Avoid
If risk exposure is not acceptable or mitigation and/or transfer are not enough, risk cause must be avoide and threat must be eliminated. Review tolerances of the organization. Evaluate task Vs avoid the project Document and communicate strategy Keep reevaluating the risk during the life of the project
Exploit (making sure that the opportunity is materialized) Share (assign part of the bennefit to a third party)
- Try to identify responses that mitigate several risks at the same time. - For positive impacts, write + - For negative impacts, write - If impacts do not exist, dont write anything
Reserves
Provision to mitigate risks (cost or time). It is an amount of money or time which is used to reduce deviation risk. To determine rerseves, consider the following:
Tipe of contracts Threaten exposure Tolerance to risk Consecuences of deviation Learnt lessons
Exercise 4.6
Project 40 MW in Leon.
Starting from the filtered risks register, develope the risks responses.
Risk Management
Introduction Plan Risk Management Risks Identification Risk Analysis Risk Responses Monitor and Control Risks
Exercise 4.7
Think about other risks triggers
Risks reevaluation
What new risks are due to time or cost variations? What new risks are due to changes in client requirements? What new risks are a result of changes of personnel or stakeholders? What new risks are result of organizacional or environmental changes? What new risks are possible due to changes in resources or its utilization? Which of the identified risks have changed?
Exercise 4.8
Question: when do you think that a new risk reevaluation should be done?
Risk Documentation
It is the base for risk analysis in future projects Learnt lessons should be transmited to all the organization to avoid that the same problems could happen again It could be used to demonstrate to the direction of the company the work that has been done and when they were involved in project problem solutions.