The first two volumes of this series provide a statistical summary of the first
decade of the National Aeronautics and Space Administration (NASA). It was a
pioneering decade, characterized by public and congressional support, growth, and
adventure. While Volume I introduces the researcher to NASA finances, personnel,
and installations, the second volume contains information on the agency's major
programs and projects-the raison d'etre for the "dollars, people, and things"
previously measured.
Established by the National Aeronautics and Space Act of July 1958, NASA, a
civilian organization, was charged with managing those aeronautics and space ac-
tivities sponsored by the United States that fell outside the purview of the Depart-
ment of Defense. Included in the space act were eight general objectives for the new
agency: (1) to expand man's knowledge of phenomena in the atmosphere and space;
(2) to improve the usefulness and performance of aeronautical and space vehicles;
(3) to send instrumented vehicles into space that could support life; (4) to study the
long-range benefits that might result from utilizing space; (5) to preserve the role of
the U.S. as a technological leader; (6) to support national defense by providing other
agencies with information on new discoveries; (7) to cooperate with other countries
in the peaceful utilization and exploration of space; and (8) to utilize existing scien-
tific and engineering facilities and personnel. To meet these objectives, NASA
channeled its resources into five programs: space science and applications, manned
spaceflight, launch vehicle development, tracking and data acquisition, and ad-
vanced research and technology.
The procurement and development of launch vehicles was a critical first step for
NASA. Chapter 1 discusses the military vehicles used by the agency in its early years
and the stable of launchers designed and developed by NASA and its contractors.
Saturn V, the largest and most powerful of these vehicles, was built for a specific
purpose--manned expeditions to the moon. Chapter 2 outlines for the reader
NASA's manned spaceflight program. Project Mercury proved that one man could
safely orbit the earth at_,t return. Pairs of astronauts in larger vehicles performed
larger, more sophisticated missions during Project Gemini. But it was the ambitious
Apollo program that captured the attention and the purse of the nation. In 1961 in
answer to Yuri A. Gagarin's successful orbital flight, which preceded John H.
Glenn, Jr.'s orbital mission by 10 months, President John F. Kennedy declared that
before the end of the decade the U.S. would send a man to the moon. At the close of
NASA's first decade, three Americans circled earth's natural satellite aboard Apollo
4
iii
iv NASA
HISTORICAL
DATABOOK
8; in July 1969 the first of six Apollo lunar landers touched down safely on the
moon. Although it received less fiscal support, the space science and applications
program brought the agency its first and steadiest supply of results.
Chapter 3 explores the disciplines NASA's space scientists sought to study and
describes the many vehicles they used-from small sounding rockets and the Ex-
plorer family of satellites to large orbiting-laboratory satellites. In addition to sup-
porting "pure" scientific research, NASA specialists also developed satellites of a
more "practicaL" nature that contributed to such fields as meteorology and com-
munications. NASA also applied its expertise to aeronautical research, continuing a
practice begun by the National Advisory Committee for Aeronautics in 1915. Also
included in the advanced research and technology program, desci'ibed in Chapter 4,
were investigations in the fields of space vehicle systems, electronics and control,
human factor systems, and space power and propulsion. Scientific satellites,
manned spacecraft, and experimental aircraft all demanded accurate tracking pro-
cedures and sophisticated data acquisition and analysis equipment, which is discuss-
ed in Chapter 5. During the first 10 years, the agency's tracking and data acquisition
program supported three networks: the Space Tracking and Data Acquisition Net-
work (satellites), the Manned Space Flight Network, and the Deep Space Network.
Each of the five chapters is divided into three sections. The narrative introduction
to each chapter includes information on the changing management of the program
offices at NASA Headquarters. In the budget sections, tables provide a fiscal history
of each program and the many flight and research projects sponsored by NASA.
The bulk of the book is devoted to describing these projects, including data on the
projects' origins. For example, in Chapter 3, the material is divided among six broad
categories: physics and astronomy, lunar and planetary, life sciences, meteorology,
communications, and applications (including geodesy). In turn, the physics and
astronomy section is organized by project: Explorer, Orbiting Solar Observatory,
Orbiting Astronomical Observatory, Orbiting Geophysical Observatory, sounding
rockets, Vanguard, and miscellaneous projects (including several international ven-
tures). For each flight, a data sheet gives a physical description of the spacecraft and
information on objectives, results, and participants. Throughout the book, the
reader will find material that is duplicative. This is necessary to give the researcher
who is interested in only one program or one project a more complete story.
The authors of the NASA Historical Data Book series have made no attempts to
interpret or judge the events they describe; instead they have provided only the facts,
figures, and background. Such an approach does not lend itself to volumes that are
read from cover to cover, but it does provide students, writers, and others-especial-
ly those without ready access to primary documentation-objective material with
which to begin their research. The second volume also gives historians, managers,
engineers, and scientists working in the field quick answers to specific questions such
as: Who initiated the Explorer series of satellites? How large was the Ranger
spacecraft? When did the Space Task Group become the Manned Spacecraft
Center? How many NASA pilots flew the X-15? What steps did the agency take to
expand its research abilities in the field of electronics in the 1960s? Taken as a unit,
each chapter will give the more serious reader a complete look at a program, its pre-
NASA origins, objectives, constituents, and results.
PREFACE v
LindaNeumanEzell
Spring1982
CONTENTS
vii
CHAPTER ONE
LAUNCH VEHICLES
CHAPTER ONE
LAUNCH VEHICLES
Before the National Aeronautics and Space Act was signed on July 29, 1958, the
art of launch vehicle development was the exclusive concern of the Department of
Defense (DoD). With the passage of the act, the National Aeronautics and Space
Administration (NASA), the new civilian agency charged with managing the coun-
try's space program was given the authority to initiate its own launch vehicle pro-
gram. From an amalgam of civilian and military groups and organizations, NASA's
managers began to gather the expertise and hardware they required, but for several
years NASA would depend largely on DoD-developed missiles to launch its civilian
payloads.
When NASA was organized, DoD's Scientific Satellite Project, which included
the Naval Research Laboratory's Vanguard Division and its upper atmosphere
sounding rocket team, was transferred to the new agency. In addition to several
satellite and probe projects, NASA acquired the F-I engine development project
from the Air Force. On December 3, 1958, the facilities and 2300 employees of the
Jet Propulsion Laboratory (JPL) in Pasadena, California, were transferred to
NASA from the Army. For 22 years, this research group had been studying liquid
and solid propellant rockets and recently had been supporting the Army Ballistic
Missile Agency's work on Explorer 1, America's first successful artificial satellite. At
NASA's Langley Research Center, a facility inherited from the National Advisory
Committee for Aeronautics, the Scout solid propellant rocket was being developed.
Scout, the agency's first launch vehicle program of its own, was an assembly of ex-
isting components gathered from the Navy's Polaris missile project, JPL's Sergeant
missile, and the Vanguard satellite launcher. In October 1959, the decision was made
to transfer to NASA the Army Ballistic Missile Agency's important Development
Operations Division, the Wernher von Braun team. This group was developing a
large clustered-engine rocket called Saturn (formerly known as Juno V), which agen-
cy planners had identified as a potential booster for advanced manned vehicles.
NASA had been seeking to acquire the competence of the von Braun team since its
founding and on July 1, 1960 officially assumed responsibility for some 4000 per-
sonnel and part of the division's facilities near Huntsville, Alabama, which were
renamed the George C. Marshall Space Flight Center. The civilian agency also had
been given authority to develop the Thor-Delta vehicle and the Vega upper stage and
in 1960 took over from the Air Force the Centaur high-energy upper stage, which
could be used with either the Atlas or the Titan booster. With the acquisition of the
Missile Firing Laboratory at Cape Canaveral, Florida, in 1960, NASA possessed the
2 NASA HISTORICAL DATA BOOK
*For further information on NASA facilities, see Jane Van Nimmen and Leonard C. Bruno with
Robert L. Rosholt, NASA Historical Data Book, 1958-1968; NASA Resources, vol. 1, NASA SP-4012
(Washington, 1976), pp. 13-50. Also useful are Charles D. Benson and William B. Faherty, Moonport: A
History of Apollo Launch Facilities and Operations, NASA SP-4204 (Washington, 1978); Manned
Spacecraft Center, White Sands Tesl Facility, "MSC White Sands Test Facility History, July
1965-December 1967," MSC rep. [no number], Dec. 1967; Kennedy Space Center Public Affairs Off.,
"The Kennedy Space Center Story," Jan. 1968; NASA, "Wallops Station Handbook; General Informa-
tion," vol. 1, April 3, 1961; and NASA Hq., Off. of Facilities, National Aeronautics and Space Ad-
ministration Facilities Data (Washington, 1974).
LAUNCH
VEHICLES
133_
o
F _ I |
• °I 8
133_
@ =
_{o o
o
o u-,
,n._ o o
co Q
, D
m,_ o
_z m _
0c_C o
9w
> m_
O g
8 °
m
§£ oo
8 8 _
>
a:
I-
,:_=,z_Z3 0 _n _o
9_ o $
= <= N
mc_
5 8
U
::/: o0 _
........ ,,,,
g _ R ° '-_- >- r_
,x,7,
SU313_ o- _
4 NASA HISTORICAL DATA BOOK
responsible for such areas as solid rocket development and nuclear engines answered
to Hyatt. In late 1959, a Launch Vehicle Programs Office was established, with
Director Ron R. Ostrander reporting to the agency's associate administrator. A
November 1961 reorganization divided launch vehicle management among the Of-
fice of Advanced Research and Technology (OART), the Office of Manned Space
Flight (OMSF), and the Office of Space Science (OSS), later the Office of Space
Science and Applications (OSSA). Managed in this fashion, nuclear and other ad-
vanced power systems were the responsibility of OART (see also chapter 4 for more
on OART). Launch vehicles intended for use in unmanned space science projects
were under the purview of Director of Launch Vehicles and Propulsion Programs
Donald H. Heaton (replaced by Richard B. Morrison in 1962). As director of launch
vehicles and propulsion in OMSF, Milton W. Rosen oversaw those vehicles that
would boost men into space. In 1963, because NASA in general and the Apollo
lunar exploration program in particular had become so very large, a major restruc-
turing of the organization took place. The management of launch vehicles for un-
manned projects was not affected. Project managers for the various vehicles con-
tinued to report to the director of launch vehicles and propulsion programs (Vincent
L. Johnson replaced Morrison in 1964; Joseph B. Mahon assumed the role in 1967).
Management of the manned vehicles, however, underwent a change. Instead of in-
dividuals assuming responsibility for specific components of the Apollo space vehi-
cle and the Saturn launcher, Associate Administrator for Manned Space Flight
George E. Mueller divided the authority for Apollo five ways: program control,
systems engineering, testing, flight operations, and reliability and quality. For exam-
ple, the director for systems engineering would be concerned with the Apollo com-
mand module, the launch vehicle, the lunar module, and any other component of
Apollo for which systems engineering was required. There was no longer a launch
vehicle manager per se in OMSF. (See table l-I for more information on the
organization of the several offices concerned with the management of launch vehicle
development and operations.)
LAUNCH VEHICLES
Table 1-1.
Four Phases of Launch Vehicle Management, NASA Headquarters
Phase I
Administrator/Deputy Administrator
Associate Administrator
Director, Space Flight Development (Abe Silverstein)
Assistant Director, Propulsion (Abraham Hyatt)
Chief, Rocket Vehicle Development (Milton W. Rosen)
Chief, Solid Rocket Development (Elliot Mitchell)
Chief, Liquid Fuel Rocket Engines (Adelbert O. Tischler)
Chief, Space Propulsion and Auxiliary Power Units (William Cooley)
Chief, Analysis and Requirements (Eldon W. Hall)
Phase I1
Dec. 1959-Nov. 1%1
Administrator/Deputy Administrator
Associate Administrator
Director, Launch Vehicle Programs (Don R. Ostrander)
Deputy Director (Hyatt; Rosen, Jan. 1%1)
Assistant Director, Vehicles (Rosen; Donald H. Heaton, Jan. 1961)
Assistant Director, Propulsion (Mitchell)
Assistant Director, Launch Operations (Samuel Snyder)
Assistant Director, Nuclear Propulsion (Harold B. Finger)
Phase III
Nov. 1961-Oct. 1963
Administrator/Deputy Administrator
Associate Administrator
Director, Office of Advanced Research and Technology (Ira H. Abbott; Raymond L. Bisplinghoff,
Aug. 1962)
Director, Nuclear Systems (Finger)
Director, Propulsion and Power Generation (William H. Woodward; John L. Sloop, Feb.
1962); office combined with Nuclear Systems in 1963
Director, Office of Space Science (Homer E. Newell)
Director, Launch Vehicles and Propulsion Programs (Heaton; Richard B. Morrison, June 1%2)
Deputy Director, Launch Vehicles and Propulsion Programs (Sloop); office dropped in early
1962
Coordinator, Launch Operations (John W. Rosenberry); office dropped in 1963
Head, Small Vehicles and International Projects (Vincent L. Johnson; Roll D. Ginter, July
1%2)
Head, Centaur (W. Schubert; Johnson, 1962)
Head, Agena (Dixon L. Forsythe; Joseph B. Mahon, 1963)
Program Manager, Scout (Ginter; Warren A. Guild, July 1962)
Program Manager, Delta (Johnson; Theodrick B. Norris, 1%2)
Program Manager, San Marco (Ginter); office added in late 1962
Head, Advanced Projects (Alfred M. Nelson; J. A. Salmanson, 1963)
Director, Office of Manned Space Flight (D. Brainerd Holmes; George E. Mueller, Sept. 1963)
Director, Launch Vehicles and Propulsion (Rosen; Robert F. Freitag, April 1963); office
dropped in 1%3 (see discussion above)
Assistant Director, Vehicle Engineering (Hall; Rosen, acting, late 1962); office dropped in
1963 (see discussion above)
NASA HISTORICAL DATA BOOK
Table 1-1.
Four Phases of Launch Vehicle Management, NASA Headquarters (Continued)
Assistant Director, Vehicles (Richard B. Canright; Stanley M. Smolensky, acting, late 1962);
office dropped in 1963 (see discussion above)
Assistant Director, Propulsion (Tischler); functions transferred to OART
Assistant Director, Launch Operations (Gus A. D'Onofrio, acting; John K. Holcomb, June
1962); office dropped in 1963 (see discussion above)
Phase IV
Nov. 1963-Dec. 1968
Administrator/Deputy Administrator
Associate Administrator
Associate Administrator, Office of Advanced Research and Technology (Bisplinghoff; Mac C.
Adams, Oct. 1965; James M. Beggs, June 1968)
Division Director, Chemical Propulsion (Tischler)
Division Director, Nuclear Systems and Space Power (Finger; Woodward, April 1967);
office renamed Space Power and Electric Propulsion in April 1967
Associate Administrator, Office of Space Science and Applications (Newell)
Director, Launch Vehicles and Propulsion Programs (Morrison; Johnson, June 1964;
Mahon, Dec. 1967)
Program Manager, Centaur (Johnson; Ginter, 1964; Norris, 1967)
Program Manager, Small Vehicles and International Projects (Ginter); office
dropped in 1964 but reestablished in 1967 (R. W. Manville)
Program Manager, San Marco (Ginter); office dropped in 1964
Program Manager, Delta (Norris; Manville, 1966; 1. T. Gillam, 1967)
Program Manager, Scout (Guild; R. K. Sherburne, 1966; Paul E. Goozh, 1967)
Program Manager, Agena (Mahon; W. L. Lovejoy, 1968)
Program Manager, Advanced Programs and Technology Support (Salmanson,
acting; Joseph E. McGolrick, 1964)
Program Manager, Medium Launch Vehicles (Norris); office added in 1968
Associate Administrator, Office of Manned Space Flight (Mueller)
BUDGET
NASA's budget process, from requests for funds to programming the funds
granted, was a complex one involving the agency, the Bureau of the Budget (BOB),
and Congress. The agency was always considering three budgets simultaneously: the
current operating budget, the budget for the ensuing fiscal year, and the preliminary
budget for the following fiscal year (the fiscal year beginning July 1). In addition to
asking for specific dollar amounts in each year's request, NASA's managers also had
to explain and justify each budget category.
LAUNCH
VEHICLES 7
Table 1-2.
Simplified Steps of the Budget Process
1. Program Operating Plans submitted quarterly to NASA Headquarters program offices by the field
installations.
2. First draft of preliminary budget prepared by Office of Programming.
3. First internal NASA semiannual budget review (March).
4. Preliminary budget review by BoB, which leads to NASA-BoB negotiations and BoB targets (sum-
mer).
5. Second internal NASA semiannual budget review (fall).
6. Formal submission of requests to BoB (Sept. 30).
7. Requests readied and justified for review by congressional authorization and appropriation commit-
tees (by Jan.).
8. Initial hearings before House and Senate authorization committees, followed by reporting out of an
authorization bill.
9. Similar review by House and Senate appropriations subcommittees.
10. Conference committees resolve any differences.
1I. Debate on floor of House and Senate, followed by passage of NASA authorization and appropria-
tion acts.
From fiscal years 1963 through 1969, NASA's budget was divided into three'ac-
counts: Research and Development (R&D), Administrative Operations (AO), and
Construction of Facilities (CoF).* R&D and AO were funded on a no-year basis;
that is, the funds were made available over an undefined multiyear period and did
not have to be spent in one particular fiscal year. NASA was also permitted to
reprogram internally among the three accounts (as of 1965, transfer authority was
reduced from 3 °70 to 0.5 °7oof the total R&D authorization). This volume will only be
concerned with R&D funds. For budget purposes, R&D was defined loosely to in-
clude more than pure research and development. For example, R&D funds were
used not only to develop but also to procure launch vehicles and spacecraft after
they were being produced in quantity. Severable equipment (equipment not per-
manently attached to a structure) could be financed with R&D funds, and non-
NASA personnel supporting or working directly on an agency project could be paid
from R&D accounts.
The Bureau of the Budget was responsible for most of the cuts suffered by
NASA budgets months before Congress acted on the requests. In the tables that
follow, the "request" column represents the amounts agreed to by NASA and BoB.
Data on submissions (requests) for this volume are taken from the yearly budget
estimates prepared by NASA's Office of Administration, Budget Operations Divi-
sion, and from chronological histories prepared for each fiscal year by the same of-
rice. In Congress, the authorization committees and their several subcommittees in-
tensely examined NASA's requests and the programs for which the funds would be
spent. The House committee, for example, was divided into subcommittees cor-
responding to each NASA program office. NASA managers reported regularly to
these subcommittees to keep them informed, because they had the authority to in-
*R&D and AO were combined in FY 1963-1964 and called Research, Development, and Operations
(RDO).
8 NASA HISTORICAL DATA BOOK
crease or decrease the agency's budget requests. The authorization committees set a
maximum over which funds could not be appropriated; they imposed limitations or
preconditions on how funds could be spent; they determined how the agency could
reprogram or transfer its monies among accounts.
The "authorization" column in the following charts is the ceiling set by the
authorization committees. Authorizations were not always listed for individual proj-
ects in the chronological histories, especially in the early 1960s. To determine the
amount authorized for the general category or program under which a certain proj-
ect fell, consult the chronological histories. The appropriations committees had the
power to restore funds cut by the authorization committees or make further ad-
justments to the requests. Generally, however, the appropriations committees did
not scrutinize NASA's budgets as closely as did the authorization subcommittees.
Also, funds were not appropriated by "line item," an individual listing in the re-
quest, as they were authorized; for example, a sum would be appropriated for
launch vehicle development, but the amount would not be itemized for each launch
vehicle. Therefore, there are no appropriations columns in the tables to follow
(however, see table 1-3 for a summary of appropriations for the three accounts).
Data on authorizations and appropriations for this volume are taken from the
annual chronological histories mentioned above. The last column, "programmed,"
represents the funds spent during the fiscal year as reported in the NASA budget
estimates (for example, funds programmed in FY 1964 were reported in the FY 1966
estimate). However, to account for all the funds expended for a major NASA
Table 1-3
NASA Appropriations, 1959-1968 (in millions of dollars)
Fiscal Salaries & Expenses/ Research & Construction & Equipment Total
Year Administrative Operations a Development Construction of Facilities b
1959 c 86.3 a 196.6 48.0 330.9
! 960 91.4 347.6 84.6 523.6
1961 170.8 670.4 122.8 964.0
1962 206.8 1302.5 316.0 1825.3
1963 .... 2897.9 d 776.2 3674.1
1964 494.0 3926.0 680.0 5100.0
1965 623.5 4363.6 262.9 5250.0
1966 584.0 4531.0 60.0 5175.0
1967 640.0 4245.0 83.0 4968.0
1968 628.0 3925.0 35.9 4588.9
Total 3524.8 e 26 405.6 f 2469.4 32 399.8
research
anddevelopment project, one would also have to consider such things as
funds reprogrammed from other accounts, special facilities built to support a par-
ticular project, salaries for NASA employees, and support activities. .4
To review the budgets of various launch vehicle programs, consult such obvious
budget categories in the tables to follow as the name of the vehicle in which you are
interested (arranged alphabetically), but do not overlook the miscellaneous
categories included in table 1-31. Summary information can be found in tables 1-3
through 1-5. Valuable information is provided in the following tables in the bottom
notes. For example, prior to FY 1966, portions of individual spacecraft project
budgets were earmarked for launch vehicles. Of the FY 1964 request for Mariner
($100 000 000), $15 600 000 was requested for Atlas-Agena and $9 700 000 for Cen-
taur. But the requests were not always written so precisely. In the FY 1965 request
for Mariner ($54 100 000), $10 900 000 was requested for launch vehicles, which
would be divided between Atlas-Agena and Centaur; the request did not specify the
amount to be budgeted for each vehicle. In using these tables, carefully review the
bottom notes before making conclusions about totals for any particular vehicle or
year.
*For further information on NASA's budget process, see Arnold Levine, Managing NASA in the
Apollo Era (1963-1969), NASA SP-4102 (Washington, 1982).
Table 1-4
NASA Research and Development Funds, 1959-1968
(in millions of dollars)
_a
o0
_5
_._.
rj_--
E
E
o
LAUNCH VEHICLES l l
r_
oo
0',
O_
o I o
o oo
,=_
o! ,,_ -4.
¢.1 e.l
e.le.l ._-_
12 NASA HISTORICAL DATA BOOK
Table 1-6.
Table 1-7.
Atlas-Able Funding History
(in thousands of dollars) a
Table 1-8.
Atlas-Agena B and D Funding History
(in thousands of dollars) a
1959 3500 b
1960 7706 c
1961 16 500 d 16 670 e
1962 113 675 f 53 500 g
1963 93 581 h 58 874 i
1964 132 800 j __ _k
1965 97 3001 __ m
1966 _ __ _n _ __ _o
1967 -- -- -P _ _ _q
1968 r _ __ s
Table 1-9.
Atlas-Antares Funding History
(in thousands of dollars)
Table 1-10.
Atlas-Centaur Funding History
(in thousands of dollars)
alncludes $6 700 000 from the Surveyor request, and $5 370 000 from the Mariner request.
b Includes a $9 000 000 supplementary request.
CFrom the Surveyor budget.
alncludes $17 300 000 from the Surveyor request, and $17 100 000 from the Mariner request.
elncludes $42 000 000 from the Surveyor request, and $9 700 000 from the Mariner request.
fTotal 1966 request for launch vehicle procurement was $194 500000; total authorized was
$178 700 000 (authorizations were not itemized by launch vehicle).
sit was noted by the Conference Committee that $4 000 000 of the $9 250 000 reduction in the launch
vehicle procurement budget was against Centaur, bringing the authorization to $60 000 000.
LAUNCH
VEHICLES 15
Table1-11.
JunoII Funding
History
(inthousands
ofdollars)
Year Request Programmed
alncludes $8 540 000 from the scientific satellites budget, and $2 150 000 from the communications
budget.
b lncludes funds from the following scientific satellite budgets: gamma ray astronomy satellite
($870 837), ionosphere direct measurements satellite ($870 837), and ionosphere beacon satellite
($1 741 672).
Clncludes funds from the following scientific satellite budgets: ionospheric air measurements
($730 000), gamma ray satellite ($705 000), and ionospheric beacon satellite ($1 413 000).
Table 1-12.
Jupiter (Juno I) Funding History
(in thousands of dollars) a
Table 1-13.
Little Joe I Funding History
(in thousands of dollars)
a From the manned spaceflight budget. In addition, $1 170 000 was programmed for Little Joe I special
purpose test apparatus and airframe development.
b It was estimated in the FY 1961 budget estimate that $1 300 000 would be programmed for Little Joe I
special purpose test apparatus and airframe development.
CTotal programmed for all Mercury launch vehicles (Little Joe I, Atlas, and Redstone) was
$30 836 000.
16 NASA HISTORICAL DATA BOOK
Table 1-14.
Little Joe II Funding History
(in thousands of dollars)
Table 1-15.
Nova Funding History
(in thousands of dollars)
a NASA's adoption of the Saturn C-5 in July 1962 effectively cancelled Nova. In the FY 1963 request, it
was estimated that $6 322 000 would be programmed for Nova in FY 1962.
Table 1-16.
Redstone Funding History
(in thousands of dollars) a
Table 1-17.
a Funded as a separate launch vehicle project in the FY 1959-1963 requests, as part of the OMSF launch
vehicle and propulsion systems project in the FY 1964 request, and as part of Project Apollo in the FY
1965-1966 requests (funds for procuring Saturn vehicles were also included in the FY 1964 request as part
of Apollo).
b Funded by DoD.
CAn additional $47 870 000 was programmed for the development of the Saturn family by DoD.
NASA programmed its funds for Saturn vehicle development, of which the Saturn I was the first step.
d Requested for Saturn vehicle development, of which the Saturn I was the first step; however, some of
these funds were being requested for work on advanced Saturn hardware.
e Distinctions between procurement and development were not usually made in the Saturn launch vehi-
cle budget (as they were for the launch vehicles used by OSSA). The procurement figures for 1962 and
1964 are exceptions; the procurement figure for 1963 is from the advanced manned spaceflight budget.
Table 1-18.
Saturn IB Funding History
(in thousands of dollarsp
a Included as part of the OMSF launch vehicle and propulsion systems program and Project Apollo in
the FY 1964 request, as part of Project Apollo in the FY 1%5-1967 and 1970 requests, and as parl of
Project Apollo and Apollo applications in the FY 1968-1969 requests.
t, Distinctions between procurement and developmenl were not usually made in the Saturn launch vehi-
cle budget (as they were for OSSA launch vehicles). The procurement figure shown for FY 1964 (from the
Apollo request) was an exception; the procurement figures shown for FY 1966-1968 are from the Apollo
applications budget.
18 NASA
HISTORICAL
DATABOOK
Table1-19.
SaturnV FundingHistory
(inthousands
of dollars)
a
Year Request Authorization Programined
aFunded as a separate launch vehicle program in the FY 1963 request, as part of the OMSF launch
vehicle and propulsion systems program in the FY 1964 request, as part of Project Apollo in the FY
1965-1967 and 1970 requests, and as part of Project Apollo and Apollo applications in the FY 1968-1969
requests.
b Supplementary request.
Clncludes a supplementary request of $110 000 000.
d Includes $210 000 for Voyager studies of a Saturn V launch vehicle system.
e Distinctions between procurement and development were not usually made in the Saturn launch vehi-
cle budget (as they were for OSSA launch vehicles). The procurement figures shown for FY 1967-1968 are
for Apollo applications.
flncludes $1 500 000 for Voyager studies of a Saturn V launch vehicle system.
SThe authorization was not itemized by individual items; the total authorization for Project Apollo
was $2 521 500 000.
LAUNCH VEHICLES 19
Table 1-20.
Scout Funding History
(in thousands of dollars)
Table 1-21.
Thor Funding History, a
(in thousands of dollars)
Table 1-22.
Thor-Able Funding History
(in thousands of dollars)
a Includes $2 120 000 from the scientific satellites budget, and $2 843 000 from the lunar and planetary
budget.
hAs reported in the FY 1961 request, it was estimated that $727 000 of the scientific satellites budget
would be programmed for Thor-Able.
Table 1-23.
Thor-Agena B & B Funding History FY 1959-1968
(in thousands of dollars) a
Table 1-24.
Thor-Delta Funding History
(in thousands of dollars)
Table 1-25.
Titan II Funding History
(in thousands of dollars) a
1962 22 391
1963 50000 63 709
1964 46 900 _ _ _b
1965 66 900 66 900 _ _ _c
1966 ___d ___d
1967 __ _e _ __e
Table 1-26.
Vega Funding History
(in thousands of dollars)
1959 14 291
1960 42 800 42 800 4000
Table 1-27.
--- 50 849
1961 ---
--- 48 320
1962 ---
1963 55 316 55 316 53 703
1964 54 100 54 100 61 954
1965 64 100 64 100 62 396
__b
1966 52 500 ---
___¢
1967 41000 ---
1968 ___d ...... e
a Funded as part of the liquid propulsion program in the FY 1963 request, as part of the OMSF launch
vehicle and propulsion systems program in the FY 1964 request, and as part of Project Apollo in the FY
1965-1968 requests.
bThe amount programmed for Apollo engine development (F-l, H-l, and J-2) was $133 200 000.
CThe amount programmed for Apollo engine development (F-I, H-I, and J-2) was $49 800 000.
d FY 1968 was the last year NASA requested funds for Apollo engine development. The request of
$24 500 000 was for the F-l, H-I, and J-2. The procurement of engines for the Saturn launch vehicles was
charged to the appropriate Saturn account.
eThe amount programmed for Apollo engine development (F-I, H-l, and J-2) was $20 500 000.
LAUNCH VEHICLES 23
Table 1-28.
H-1 Engine Development Funding History
(in thousands of dollars) a
a Funded as part of the OMSF launch vehicle and propulsion systems program in the FY 1964 request
and as part of Project Apollo in the FY 1965-1968 requests.
bThe amount programmed for Apollo engine development (F-l, H-I, and J-2) was $133 200 000.
CThe amount programmed for Apollo engine development (F-l, H-l, and J-2) was $49 800 000.
oFy 1968 was the last year NASA requested funds for Apollo engine development. The request of
$24 500 000 was for the F-1, H-l, and J-2. The procurement of engines for the Saturn launch vehicles was
charged to the appropriate Saturn account.
eThe amount programmed for Apollo engine development (F-l, H-l, and J-2) was $20 500 000.
Table 1-29.
J-2 Engine Development Funding History
(in thousands of dollars) a
aFunded as part of the liquid propulsion program in the FY 1963 request, as part of OMSF launch
vehicle and propulsion systems program in the FY 1964 request, and as part of Project Apollo in the FY
1965-1968 requests.
bThe amount programmed for Apollo engine development (F-l, H-l, and J-2) was $133 200 000.
CThe amount programmed for Apollo engine development (F-l, H-l, and J-2) was $49 800 000.
dFy 1968 was the last year NASA requested funds for Apollo engine development. The request of
$24 500 000 was for the F-l, H-l, and J-2. The procurement of engines for the Saturn launch vehicles was
charged to the appropriate Saturn account.
e The amount programmed for Apollo engine development (F-1, H-l, and J-2) was $20 500 000.
24 NASAHISTORICAL
DATABOOK
Table 1-30.
RL-10 Engine Development Funding History
(in thousands of dollars) a
a Funded as part of the OMSF launch vehicle and propulsion systems program in the FY 1964 request,
as part of Project Apollo in the FY 1965 request, and as part of Project Apollo and the Centaur develop-
ment project in the FY 1966-1967 requests. The procurement of RL-10 engines was charged to the ap-
propriate launch vehicle accounts.
CHARACTERISTICS
The launch vehicles utilized by NASA during the agency's first 10 years are
described in the following tables. Two boosters borrowed from the military, Atlas
and Thor, were used with several different upper stages. Atlas was paired with Able,
Agena, Antares, and Centaur; it also stood alone as the standard Mercury launch
vehicle for orbital missions. Able, Agena, and Delta were added to Thor to increase
that missile's range and versatility. Juno and Vanguard vehicles contributed to
NASA's early space science program. Redstone missiles were man-rated to boost the
first Mercury astronauts onto ballistic trajectories, and Gemini astronauts rode
modified Titan IIs into orbit. Two distinct vehicles, Little Joe I and Little Joe II,
were used to test and qualify launch techniques and hardware for the Mercury and
Apollo programs. The Saturn family of launch vehicles was developed specifically to
support the Apollo lunar exploration venture. And Scout, which changed over time
as its engines were upgraded and its reliability improved, was NASA's first contribu-
tion to the launch vehicle stable. Two proposed vehicles, Vega and Nova, are also
discussed. 5
In some cases, finding the "official" figures for the height, weight, or thrust of a
particular launch vehicle was not possible. It was not uncommon to find several
NASA sources with conflicting data on the same vehicle. Measurements, therefore,
may be approximate. Height may be measured several different ways, and there was
some disagreement in the source material over where an upper stage begins and ends
for measuring purposes. The height of a launch vehicle stack does not usually in-
clude the payload (spacecraft); weight, however, does. Weight of the individual
stages includes propellant (wet weight). Diameter does not take into consideration
the base of the booster stage, which is often much wider than the rest of the cylin-
drical vehicle due to the addition of fins or strap-on engines.
LAUNCH
VEHICLES 25
I O I_ I
18
;A
0
,t=
Ox
"G ¢q
_ _I_ ¢-I ¢'I
._o o
0 e
*" O 0 0
p_ e¢l
I_ ID.
"1=1
_B
I:_ alB
0 0
.Z:
O
I.UD_
O
,-. "_ _ "6
O
,._ _ O _1 ,.tD
0 0
-_-_ _ .. _ _ _ _-'= o
m_mZZNm_ m g
0 0 _
26 NASA HISTORICAL DATA BOOK
Engine number changes may not always be noted if only minor modifications of
the engines precipitated the changes. The following abbreviations for propellants
were used throughout the following tables:
IRFNA = inhibited red fuming nitric acid
LH2 = liquid hydrogen
LOX = liquid oxygen
N204 = nitrogen tetroxide
RP-1 = kerosene
UDMH = unsymmetrical dimethylhydrazine
WFNA = white fuming nitric acid
100
8O
o /
= 60
40 f J
0
1958 1959 1960 1961 1962 1963 1964 1965 1966 1967 1968 TOTAL
VEHICLE ATTEMPTS 4 14 17 24 27 15 30 30 36 27 23 247
PERCENT SUCCESSFUL 0 57 59 67 85 93 90 87 94 93 83 82
I-
_- i Z_ "_'
-II -I I
o_
,-.1
_oolII11
28 NASA HISTORICAL DATA BOOK
i-
t-
O
___,-
_.._ .o
LAUNCH VEHICLES 29
Table 1-33.
Atlas D/Atlas SLV-3 (Standard
Launch Vehicle-3) Characteristics
Payload capacity: With Centaur, 1133 kg to a parking orbit trajectory to the moon
Origin: Funds were spent in FY 1965 and 1966 to "stretch out" the standard Atlas, thereby
increasing its propellant capacity.
Contractors: Consolidated Vultee Aircraft Corp. (Convair/General Dynamics), prime
Rocketdyne Div., North American Aviation, Inc., engines
How utilized." With Centaur and Agena D upper stages to launch unmanned payloads, from 1966.
Remarks: First used on Oct. 26, 1966 for an Atlas-Centaur R&D launch.
See also: Atlas D/Atlas SLV-3, Atlas-Agena D, and Atlas-Centaur.
Table 1-34.
Atlas SLV-3X/Atlas SLV-3C Characteristics
Table 1-35.
Listing of Atlas D Boosters
126 Nov. 27, 1963 R&D launch with Centaur (AC-2) Yes
135 June 30, 1964 R&D launch with Centaur (AC-3) Yes
146 Dec. 11, 1964 R&D launch with Centaur (AC-4) Yes
151 Aug. 11, 1965 R&D launch with Centaur (AC-6) Yes
156 March 2, 1965 R&D launch with Centaur (AC-5) No (propellant feed
failure)
174 Oct. 26, 1966 R&D launch with Centaur (AC-9) Yes
Yes
179 Aug. 27, 1962 Mariner 2 (Atlas-Agena B)
Yes
184 April 7, 1966 R&D launch with Centaur (AC-8)
Table 1-35.
Listing of Atlas D Boosters (Continued)
5303 May 17, 1966 Gemini target (Agena D) No (flight control failure)
Table 1-36.
Chronology of Atlas Development and Operations
Date Event
1946 Contract awarded by U.S. Air Force to Consolidated Vultee Aircraft Cor-
poration (Convair) to develop a long-range missile, the MX-774.
1947 Contract with Convair cancelled due to budget restraints; Convair continued
research on its own.
Jan. 1951 Convair contract with Air Force reinstated (Project MX-1953); proposed
missile named Atlas.
March 1958 NACA Langley designers considered Atlas for the first U.S. manned
spaceflight program.
Oct. 17-18, 1958 Langley personnel opened negotiations with the Air Force Ballistic Missile
Division to procure Atlas vehicles.
Nov. 24, 1958 Atlas flew its designed range for the first time.
Dec. 18, 1958 First orbital launch of entire vehicle (Air Force Project Score).
Sept. 9, 1959 NASA successfully conducted Mercury Big Joe boilerplate test with Atlas
IO-D (the Atlas, however, suffered an electrical failure).
Nov. 26, 1959 Unsuccessful launch of Atlas-Able with a Pioneer lunar probe; failure due to
upper stage malfunctions; first time Atlas was used with an upper stage.
June 18, 1960 Atlas 50-D delivered to Cape Canaveral for first Mercury-Atlas mission
(MA-I).
July 29, 1960 MAd launch was unsuccessful because of launch vehicle and adapter struc-
tural failure.
April 25, 1961 MA-3 launch was unsuccessful because of launch vehicle failure to assume
proper trajectory.
Sept. 13, 1961 MA-4 launch was successful; Atlas declared safe for manned launch.
Nov. 29, 1961 MA-5 launch was successful with chimpanzee aboard.
Feb. 20, 1962 MA-6 launch was successful; first manned flight using Atlas launch vehicle.
1965-1966 Funds were spent to modify the Atlas; by stretching out the vehicle's tanks its
propellant capacity was increased; work was accomplished by Convair.
Oct. 26, 1966 First launch of stretched-out Atlas with Centaur upper stage (R&D launch)
was successful.
34 NASA HISTORICAL DATA BOOK
Table 1-37.
Atlas-Able Characteristics
Diameter (m): 3
Launch weight (kg): 117 780 2265 390 154 120 589
Propulsion system
Stages:
Powerplant: MA-5 A J10-101 Altair X-248 injection rocket
propulsion
system
Thrust (newtons): 1 601 280 33 360 13 344 1930 1 649 914
Propellant: LOX/RP-I WFNA/UDMH Solid hydrazine
Payload capacity: 680 kg to 555 km earth orbit
227 kg to lunar impact
136 kg to escape trajectory for interplanetary mission
Origin: Able stages derived from the Vanguard launch vehicle.
Con tractors: Space Technology Laboratories, Able assembly, instrumentation, checkout, and
Pioneer payload (4th stage)
Consolidated Vultee Aircraft Corp. (Convair/General Dynamics), Atlas
Rocketdyne Div., North American Aviation, Inc., Atlas engines
Aerojet-General, 2d-stage engine
Alleghany Ballistics Laboratory, Hercules Powder Co., 3d stage engine
How utilized." Pioneer lunar probe (with Atlas booster stage).
Remarks: Failed due to upper stage malfunctions in all three attempts to launch the Pioneer
lunar probe; retired in 1960.
First configuration in which the Atlas was mated with an upper stage.
See also: Atlas D/Atlas SLV-3, Thor-Able, and Vanguard.
LAUNCH VEHICLES 35
Table 1-38.
Chronology of Atlas-Able Development and Operations
Date Event
Dec. 6, 1957 First Vanguard test vehicle launch with live second stage (TV-3); vehicle ex-
ploded due to first stage malfunction.
Late 1957 Air Force requested Aerojet-General to modify stage for use in ICBM nose
cone reentry tests. Two months later the first Able upper stage was delivered.
It was used with the Thor booster as the Thor-Able RTV (reentry test
vehicle).
March 17, 1958 First successful Vanguard launch; second stage performed as expected.
Vanguard was used through 1959.
March 27, 1958 NACA directed the Air Force Ballistic Missile Division to proceed with the
procurement of two Able probes, Able 3 and 4.
Fall 1958 Atlas-Able combination suggested to NASA by Abe Silverstein, director, Of-
fice of Space Flight Development, to launch small probes to the moon.
Nov. 1958 Work was begun on Atlas-Able probe project under agreement between NASA
and Air Force Ballistic Missile Division. Space Technology Laboratories began
constructing Able 3 and 4.
Sept. 24, 1959 Atlas-Able vehicle exploded on pad during ground tests.
Nov. 26, 1959 Unsuccessful launch of Pioneer lunar probe with Atlas-Able.
Sept. 25, 1960 Second unsuccessful launch of Pioneer lunar probe with Atlas-Able.
Dec. 15, 1960 Third unsuccessful launch of Pioneer lunar probe with Atlas-Able. Atlas-
Able vehicle retired without a successful launch.
36 NASA HISTORICAL DATA BOOK
Table 1-39.
Atlas-Agena A Characteristics
Propulsion system
2
Stages:
Powerplant: MA-5 Bell XLR-81 (model
propulsion system 8001; upgraded to model
8048)
Thrust (newtons): 1 601 280 67 610 1 668 890
Table 1-40.
Atlas-Agena B Characteristics
7.2 30.6
Height (m): 21.9
1.5
Diameter (m): 3
Launch weight (kg): 117 780 7022 124 802
2
Propulsion system
Stages:
Powerplant: MA-5 Bell XLR-8 l-Ba-9 (model
propulsion system 8081; upgraded to 8096)
Thrust (newtons): 1 601 280 71 168 i 672 448
Table1-41.
Atlas-Agena
D Characteristics
1st stage 2d stage Total
(Atlas) (Agena D) (w/adapter)
Work was underway in 1967 for an uprated Agena D Bell engine, model 8533.
See also: Atlas D/Atlas SLV-3, Atlas SLV-3C, Atlas-Agena A, Atlas-Agena B, and Thrust-
Augmented Thor-Agena B and D.
38 NASAHISTORICAL
DATABOOK
Table1-42.
Listingof AgenaB andDStages
VehicleDate
of BorD Mission Agena Stage
Serial
# Launch Model Successful*
6001 Aug.23,1961 B Ranger
1(Atlas-Agena) No(failed torestart)
6002 Nov.18,1961 B Ranger 2 (Atlas-Agena) No (attitude control
system failed)
6501 Sept.
5,1964 B OGO 1 (Atlas-Agena) Yes
ADT1/5001
Nov.11,1966 D GATV 5001, Gemini 12 Yes
(Atlas-Agena)
AD82/5002
Oct.25,1965 D GATV 5002, Gemini 6A No (probable hard
start)
AD108/5003
March
16,1966 GATV 5003, Gemini 8 (Atlas- Yes
Agena)
AD109/5004
May17,1966 D GATV 5004, Gemini 9A N/A (Atlas stage
failed)
(Atlas-Agena)
AD129/5005
July18,1966 D GATV 5005, Gemini 10 ,Yes
(Atlas-Agena)
AD130/5006
Sept.
12,1966 GATV 5006, Gemini 11 Yes
(Atlas-Agena)
AD136/6151
Dec.6,1966 D ATS 1 (Atlas-Agena) Yes
AD137/6152
Apr.5,1967 D ATS 2 (Atlas-Agena) No (failed to restart)
AD140/6153
Nov.5,1967 D ATS 3 (Atlas-Agena) Yes
AD165/6221
May18,1968 D Nimbus B (Thor-Agena) N/A (Thor stage
failed)
AD123/6311
June
23,1966 D PAEGOS 1 (Thor-Agena) Yes
AD171/6503
March
4,1968 D OGO 5 (Atlas-Agena) Yes
LAUNCH
VEHICLES 39
Table 1-42.
Table 1-43.
Chronology of Agena Development and Operations
Date Event
Oct. 1956 Development began at Lockheed under contract to the Air Force Ballistic
Missile Division to develop an advanced military satellite system (WS 117L)
and its associated upper stage vehicle, which would be capable of in-orbit
propulsion and control. The upper stage was called Hustler after its Bell
engine, and later renamed Agena. The Hustler engine had been under Bell
Aerospace's purview since 1956. It was designed to provide 66 720 newtons of
thrust for an air-to-surface missile which would be carried by a B-58 bomber.
When requirements for the missile were dropped, the engine was transferred
to the Agena project.
1957 The Air Force Ballistic Missile Division contracted with Lockheed for the
Agena.
Jan. 1959 NASA had plans for using Agena with Thor and Atlas boosters.
Feb. 28, 1959 First Air Force launch of an Agena with a Thor first stage. Used by the Air
Force to launch the Discoverer satellite series from Feb. 28, 1959 through
Sept. 13, 1960.
April 24, 1959 Air Force issued a contract amendment to Lockheed for the development of
an advanced Agena, to be known as Agena B.
• Dec. 11, 1959 NASA's Vega launch vehicle program was cancelled in favor of the Air Force
Atlas-Agena B. An Agena B Coordinating Board was established to assist the
Air Force and NASA in coordinating the development and utilization of the
new Agena.
Early 1960 NASA's Marshall Space Flight Center, Huntsville, AL, was given authority
to supervise procurement of Agena B vehicles for NASA from the Air Force
Ballistic Missile Division, who would acquire them directly from Lockheed.
April 1960 Agreement was reached between NASA and Lockheed for the purchase of 16
Agena B vehicles over the next three years.
40 NASA
HISTORICAL
DATABOOK
Table1-43.
Chronology
ofAgena
Development
andOperations
(Continued)
Date Event
May1960 Firstsuccessful
launch
ofAtlas-Agena
A,carryingtheMidas 2satellite.
Oct.26,1960 UnsuccessfullaunchofAirForceThor-AgenaBwithDiscoverer satellite;
failure
duetostage separation
malfunction.
Nov.12,1960 FirstAirForce launch
ofAgena BonanAtlasbooster.
1961 Atlas-AgenaAdiscontinuedbytheAirForceinfavoroffollow-on Atlas-
Agena B.
Feb.
1961 Agreement signedbetweenNASA andAirForce regarding procurement of
Agena Bvehicles.
Aug.23,1961 NASA's firstlaunchofAtlas-Agena
BwithRanger 1, a lunar probe, as the
payload. The Agena stage failed to restart, and the probe was injected into
low earth orbit.
May29,1962 NASA memorandum of agreement was issued stating that the adoption of an
improved Agena model, the Agena D, was desirable.
June
1962 Air Force successfully flight tested the Agena D.
Sept.
1963 New agreement between Air Force and NASA was reached regarding pro-
curement of Agena vehicles and cooperation between the two organizations.
1964-1968 From Nov. 5, 1964 through 1968, Atlas-Agena D was used 20 times to launch
6 Project Gemini targets, PAEGOS 1, Mariner3 through 5, Lunar Orbiter 1
through 5, A TS 1 through 3, and OG05. The March 4, 1968 launch of OGO
5 utilized the stretched-out Atlas SLV-3C. (NASA also used the Thor-Agena
D configuration four times in 1965-1968.)
LAUNCH VEHICLES 41
Table 1-44.
Atlas-Antares Characteristics
Table 1-45.
Chronology of Atlas-Antares Operations
Date Event
April 14, 1964 Launch of FIRE 1 (Flight Investigation Reentry Environment) was suc-
cessful.
Table 1-46.
Atlas-Centaur Characteristics
Table 1-47.
Listing of Centaur Vehicles
Table 1-48.
Date Event
Oct. 1957 Studies for a Centaur prototype were completed; General Dynamics began
discussions with the Advanced Research Projects Agency (ARPA).
Aug. 28, 1958 ARPA requested the Air Force Research and Development Command to
oversee a contract with General Dynamics for the development of an upper
stage for Atlas to be propelled by liquid oxygen and liquid hydrogen (con-
tract executed on Nov. 14). Pratt & Whitney received a contract for the
stage's engine development.
July 1960 NASA proposed to utilize Centaur, which was being managed by the new
Marshall Space Flight Center, for 1962 Venus and Mars missions.
Jan. 1961 The Centaur launch schedule was revised due to problems with engine
Oct. 30, 1961 First flight vehicle shipped to Cape Canaveral by General Dynamics.
May 8, 1962 First Atlas-Centaur test launch (AC-I) was unsuccessful due to Centaur fair-
ing failure. Launch schedule revised again with first mission set for 1965.
June 30, 1964 AC-3 R&D launch achieved majority of objectives, but experienced
premature Centaur engine shutdown.
Dec. 11, 1964 AC-4 R&D launch with model of Surveyor lunar probe was successful, but
secondary two-burn inflight experiment was not completed.
March 2, 1965 AC-5 R&D launch was unsuccessful due to premature shutdown of Atlas
stage.
Aug. 11, 1965 AC-6 R&D launch with new propellant utilization system was successful
(simulated Surveyor launch).
April 7, 1966 AC-8 R&D launch was unsuccessful; the dummy payload was not put into
the planned parking orbit.
Oct. 26, 1966 AC-9 R&D launch with stretched-out Atlas SLV-3C was successful.
Dec. 1966 NASA decided to launch OAO and ATS satellites with Atlas-Centaur rather
than Atlas-Agena D.
April 17, 1967- Atlas-Centaur successfully launched Surveyor 3 through 7 and OAO 2. The
Dec. 7, 1968 attempt to launch ATS 4 on Aug. 10, 1968 failed when Centaur ignition did
not occur and the spacecraft and second stage did not separate.
LAUNCH
VEHICLES 45
Table 1-49.
Table 1-50.
Date Event
Fall 1958 Vega design was conceived by NASA engineers as an interim upper stage to
be used with Atlas booster for a variety of unmanned and manned missions
until Atlas-Centaur was available.
Dec. 15, 1958 Atlas-Vega design was proposed by NASA in an interagency meeting on U.S.
launch vehicles; it was described as a three-stage vehicle with a thrust of near-
ly two million newtons.
Jan. 30, 1959 Funds were made available to the Jet Propulsion Laboratory for third stage
development.
March 18, 1959 Convair, General Dynamics Corp., was awarded the prime contract for
Atlas-Vega development and production.
March 18, 1959 General Electric Co. was awarded a contract for the second stage engine.
April 4, 1959 Launch schedule plan was adopted for Vega, with the first flight set for Aug.
1960.
Oct. 13, 1959 Civilian-Military Liaison Committee recommended that the Vega stage be
dropped in favor of the DoD-sponsored Agena B.
Dec. 11, 1959 Vega was cancelled in favor of Agena B, which had a similar payload capaci-
ty and development schedule.
46 NASA HISTORICAL DATA BOOK
Juno 1 and II
NASA adopted the Juno I and Juno II military vehicles to launch its early Ex-
plorer satellites and probes. Juno I, made from a modified Jupiter C, successfully
launched the first American satellite, Explorer 1, for the Army in 1957. Juno I was
transferred to NASA shortly after the civilian agency was established and was used
only once unsuccessfully before it was replaced by Juno II. An extended Jupiter in-
termediate ballistic missile served as Juno II's booster stage. NASA used Juno II in
1958-1961 with poor results: only 3 successful missions in 10 attempts. NASA's own
Scout launch vehicle replaced Juno as the primary launcher for the Explorer series. 7
Table 1-51.
Juno I Characteristics
hydrazine
Payload capacity: 18 kg to 555 km earth orbit
Origin: Developed by the Army Ballistic Missile Agency and the Jet Propulsion Laboratory.
Contractors." Chrysler, prime
Rocketdyne Div., North American Aviation, Inc., lst-stage engine Jet Propulsion
Laboratory, upper-stage engines
How utilized: To launch early Explorer satellites.
Remarks." Juno I is sometimes incorrectly referred to as Jupiter C, which was a three-stage
launch vehicle used by the Army for reentry nose cone tests. Juno 1 is an adaptation
of Jupiter C.
See also." Mercury-Redstone and Juno I1.
LAUNCH
VEHICLES 47
Table 1-52.
Chronology of Juno I Development and Operations
Date Event
Sept. 20, 1956 The Army conducted the first long-range firing of Jupiter C, a three-stage
vehicle (Redstone, plus two solid-fuel upper stages). Jupiter C was used for
missile nose cone reentry tests by the Army.
Nov. 8, 1957 The Army was directed to launch a scientific satellite for the International
Geophysical Year with a modified Jupiter C with an added fourth stage, a
single Sergeant motor. This launch vehicle became known as Juno.
Jan. 31, 1958 Launch of Explorer 1, the first American satellite, by the Army Ballistic
Missile Agency was successful.
Aug. 24, 1958 Launch of Explorer 5 was unsuccessful; satellite failed to achieve orbit.
Oct. 22, 1958 Launch of Beacon 1, a suborbital atmospheric physics test developed by
Langley Research Center, was unsuccessful due to premature upper stage
separation.
Table 1-53.
Juno II Characteristics
Height (m): 19.6 approx. 1.2 approx. 1.2 approx. 1.5 23.5
Diameter (m): 2.7
Launch weight (kg): 49 000 575 244 varied 50 111
Propulsion system
Stages: 4
Powerplant: Rocketdyne 11 scaled-down 3 scaled-down 1 scaled-down
5-30 Sergeants, Sergeants, Sergeant
clustered clustered
Table 1-54.
Chronology of Juno II Development and Operations
Date Event
1955 Work began on the Jupiter intermediate range ballistic missile by the Army
Ballistic Missile Agency.
Sept. 1958 Chrysler delivered first flight qualification missile to Army Ballistic Missile
Agency. Jupiter was named as the new booster stage for the Juno launch
vehicle, which was redesignated Juno 11.
Dec. 6, 1958 Launch of Pioneer3 lunar probe was unsuccessful due to several launch vehi-
cle malfunctions that prevented the spacecraft from escaping earth orbit.
March 3, 1959 Launch of Pioneer 4 was unsuccessful; the probe was put into heliocentric
rather than lunar orbit when the second stage fired too long.
July 16, 1959 Launch of Explorer probe was unsuccessful; the vehicle was destroyed short-
ly after launch when it deviated sharply from its course.
Aug. 14, 1959 Launch of Beacon 2 was unsuccessful due to booster and attitude control
system malfunctions.
March 23, 1960 Launch of Explorer probe was unsuccessful due to upper stage malfunction.
Aug. 1960 Marshall Space Flight Center assumed overall responsibility for Juno I1;
prior to this time JPL had shared the authority with Marshall.
Feb. 24, 1961 Launch of Explorer probe was unsuccessful; the probe did not achieve proper
orbit.
May 24, 1961 Launch of Explorer probe was unsuccessful due to second-stage failure.
NASA engineers designed Little Joe I and Little Joe II to serve as test vehicles
for two manned spacecraft projects. The two vehicles are not related, but were both
used to verify spacecraft abort systems and to simulate other mission phases.
Little Joe I, the airframes for which were manufactured by North American
Aviation, was first put on the launch pad at Wallops Island in August 1959 with a
boilerplate model of the Mercury capsule. In the event of a malfunctioning Redstone
or Atlas booster, Mercury astronauts would need an escape system. With Little Joe
I, this system was verified under a variety of conditions. Two of the eight payloads
carried biological payloads, as well. The last test took place in April 1961. For more
information see table 2-29.
Little Joe II served the Apollo program. Built by Convair/General Dynamics,
Little Joe I1 demonstrated the Apollo abort system at transonic, high-altitude, and
intermediate-altitude phases of launch. Four Apollo boilerplate models were
launched by the test vehicle in 1964-1966 at White Sands. (For more information see
table 2-51). 8
LAUNCH VEHICLES 49
Table 1-55.
Little Joe I Characteristics
Table 1-56.
Chronology of Little Joe I Development and Operations
Date Event
Aug. 1958 NACA's Langley Research Center Pilotless Aircraft Research Division was
requested to prepare specifications for a vehicle capable of launching full-
scale and full-weight manned spacecraft for tests to a maximum altitude of
160 kilometers.
Nov. 1958 Twelve companies responded to NASA's invitation for bids to construct Lit-
tle Joe airframes.
Dec. 29, 1958 North American Aviation was assigned the prime contract.
Aug. 21, 1959 Thirty minutes before the first Little Joe scheduled launch (L J-l), the rocket
fired prematurely. Capsule and tower combination were launched on an off-
the-pad abort trajectory.
Oct. 4, 1959 Little Joe 6 (also called L J-I) launch was successful with a Mercury
boilerplate model.
Nov. 4, 1959 Little' Joe IA (also called LJ-2) launch was successful with a Mercury
boilerplate model.
Dec. 4, 1959 Little Joe 2 (also called L J-3) launch was successful with a Mercury
boilerplate model and a biological payload (a rhesus monkey).
Jan. 21, 1960 Little Joe IB (also called LJ-4) launch was successfull with a Mercury
boilerplate model and a biological payload (a rhesus monkey).
Nov. 8, 1960 Little Joe 5 launch with Mercury production capsule was unsuccessful;
escape rocket and tower jettison rocket ignited prematurely; booster, cap-
sule, and tower did not separate.
March 18, 1961 Little Joe 5A (also called L J-6) launch with a production capsule was a par-
tial success; the escape rocket fired prematurely.
April 28, 1961 Little Joe 5B (also called L J-7) launch with a production capsule was suc-
cessful; two of the Castor motors carried ballast rather than propellant.
50 NASA HISTORICAL DATA BOOK
Table 1-57.
Little Joe II Characteristics
Height (m): 10
Diameter (m): 3.9
Launch weight (kg): 25 924--63 368
Propulsion system
Stages: 1
Powerplant: 1 Aerojet-General Algol ID + 6 Thiokol Recruit TE-29s
Thrust(newtons):459034 + (148563×6=891 379) = 1 350413
Propellant: solid
Payload capacity: 12 69g kg to an altitude of 35 km on a ballistic path
Origin: NASA design
Contractors: General Dynamics/Convair, prime
Aerojet General, propulsion system Thiokol
Chemical Corp., propulsion system
How utilized." Simulations of flight conditions to be experienced during Apollo missions. Struc-
tural design and escape system of Apollo command module was tested under max-
imum aerodynamic conditions.
Remarks: Completely different design from Mercury's Little Joe 1, but used for the same kind
of program-testing of a spacecraft abort system and simulation of mission
characteristics. First U.S. launch vehicle to utilize a corrugated skin.
Table 1-58.
Chronology of Little Joe I1 Development and Operations
Date Event
June 1961 Apollo engineers suggested using a fin-stabilized, clustered-rocket, solid pro-
pellant booster for boilerplate flight tests of Apollo.
April 6, 1962 A request for proposals was issued for the production of an Apollo test
launch vehicle.
May 11, 1962 Convair/General Dynamics was selected to develop the Little Joe vehicle; a
letter contract was awarded.
Feb. 18, 1963 A definitive contract was negotiated with Convair/General Dynamics.
July 16, 1963 Convair delivered the first flight vehicle to the White Sands test facility.
Aug. 28, 1963 The first launch of Little Joe II demonstrated the overall capability of the
vehicle for Apollo simulations.
May 13, 1964 Launch of A-001 (Apollo Transonic Abort) with Apollo boilerplate was suc-
cessful.
Dec. 8, 1964 Launch of A-002 (Apollo Max q Abort) with Apollo boilerplate was suc-
cessful.
May 19, 1965 Launch of A-003 (Apollo High Altitude Abort) with Apollo boilerplate was
unsuccessful. However, the launch escape system took the boilerplate safely
away from the malfunctioning launch vehicle, which was what the mission
was designed to accomplish.
Jan. 20, 1966 Launch of A-004 (Intermediate Altitude Abort) with Apollo boilerplate was
successful.
LAUNCH VEHICLES 51
Mercury-Redstone
Project Mercury, the first step in the NASA manned spaceflight program, was
undertaken to prove that one man could safely orbit earth and return to a predeter-
mined point. The Atlas missile was being modified to boost astronauts to orbit, but
a less powerful, less expensive vehicle was required for the manned ballistic tests that
would precede orbital flight. Two of the Army's missiles became candidates for the
role.
In October 1958, days after the space agency was officially opened for business,
NASA requested eight Redstone and three Jupiter missiles from the Army for Proj-
ect Mercury. In the interest of simplifying launch operations, the requirement for
Jupiter was soon dropped. Redstone was modified for manned use by Chrysler Cor-
poration, its manufacturer, and was ready for verification tests by late 1960. A
chimpanzee was Mercury-Redstone's first passenger. In 1961, two missions were
launched successfully with astronauts on board. (For more information see chapter
2 under Mercury.) 9
Table 1-59.
Mercury-Redstone Characteristics
Height (m): 18 (25.3 w/spacecraft)
Diameter (m): 1.8
Launch weight (kg): 29 931
Propulsion system
Stages: 1
Powerplant: Rocketdyne A-7
Thrust (newtons): 346 944
Propellant: LOX/RP-1
Payload capacity: 1814 kg to an altitude of 189 km on a ballistic path.
Origin: Army ballistic missile.
Con tractors: Chrysler Corp., prime
Rocketdyne Div., North American Aviation, Inc., engine
How util&ed: Project Mercury launch vehicle for ballistic shots.
Remarks: First large ballistic missile developed by the U.S. Redstone propellant
tanks elongated for Mercury.
See also: Juno I.
52 NASA HISTORICAL DATA BOOK
Table 1-60.
Date Event
1950 The Army's Guided Missile Center recommended further development of the
proposed Hermes CI surface-to-surface missile and the North American
XLR43-NA-1 engine to meet Department of the Army's requirements for a
tactical missile system.
March 27, 1951 Contract was awarded to North American to modify their engine for the
missile system.
April 8, 1952 The new missile was assigned the name Redstone.
Oct. 28, 1952 Chrysler was issued a letter contract as prime contractor for Redstone pro-
duction.
Oct. 6, 1958 Tentative agreement was reached between NASA and the Army Ordnance
Missile Command whereby the Army would supply 10 Redstones and 3
Jupiters for NASA's manned program.
Jan. 8, 1959 NASA supplied funds to the Army Ordnance Missile Command for 8
Redstones; the Army Ballistic Missile Agency began production planning of
Mercury-Redstone.
July 1, 1960 Authority for the Mercury-Redstone was transferred from the Army Ballistic
Missile Agency to Marshall Space Flight Center.
Nov. 21, 1960 Launch of MR-I was unsuccessful due to premature booster cutoff.
Dec. 19, 1960 Launch of MR-IA to qualify abort system and spacecraft-launch vehicle
combination was successful.
Jan. 31, 1961 Launch of MR-2 with a biological payload (chimpanzee) was successful, but
a malfunction caused the engine to operate at a higher thrust level, which
caused the capsule to impact beyond the target area.
July 21, 1961 Launch of MR-4 with a man aboard was successful.
Nova
Table 1-61.
Proposed Nova Characteristics
Table 1-62.
Chronology of Nova Development
Date Event
Jan. 1959 Nova was officially proposed by NASA to serve as a "super rocket" more
powerful than the Saturn; it would utilize a 6 700 000-newton thrust single-
chamber engine under development by the Air Force. Nova would be capable
of direct ascent to the moon. Rocketdyne was awarded a contract by NASA
for F-I engine development.
Aug. 1959 Launch vehicle managers at NASA Headquarters recognized the possibility
of conflicts between Saturn and Nova proponents.
Early 1961 The yon Braun team indicated that NASA would be overextended if it pur-
sued development of both Saturn C-2 and Nova.
Jan. 24, 1962 NASA awarded a contract for M-I engine development to Aerojet-General.
March 28, 1962 Marshall Space Flight Center issued a request for proposals for Nova systems
definition and preliminary design.
July 1962 General Dynamics and Martin Marietta were chosen for Nova study con-
tracts.
July 11, 1962 NASA endorsed the Saturn C-5 and the lunar rendezvous mode for its first
lunar program, thereby cancelling an immediate need for Nova.
Oct. 1, 1962 Martin Marietta was awarded a Nova launch facilities study contract.
1963-1964 Nova studies were continued as part of post-Saturn planning funded by Mar-
shall's Future Projects Office, but no large booster beyond the Saturn class
was seriously considered by NASA.
Wernher von Braun's earliest proposals to the U.S. Army were for large
clustered-engine rockets. With such a vehicle, heavy payloads could be put into orbit
or spacecraft could reach the moon. The Advanced Research Projects Agency ap-
proved plans for an Army Ballistic Missile Agency clustered-engine booster in
August 1958. Von Braun's multistage vehicle was called Juno.
The first contracts let for Juno were to the engine maker. Rocketdyne (later a
division of North American Aviation) set to work uprating its Thor-Jupiter engine
(H-l) and developing an even larger powerplant, the F-1 (also being considered for
the proposed Nova vehicle). In November 1959, NASA assumed management
responsibility for the large booster program, which had been redesignated Saturn.
The agency soon recommended that long-range development include a family of
Saturn launch vehicles. By the summer of 1962, Saturn had a firm assignment: it
would boost Apollo astronauts to the moon.
The first member of the family was the two-stage Saturn I (originally called
Saturn C-I). Powered by engines made at Rocketdyne and Pratt & Whitney, both
stages were flight tested in a 1964 launch. Five Apollo boilerplate models were
launched by Saturn I in 1964-1965 as a step toward qualifying the spacecraft for
manned flight.
LAUNCH VEHICLES 55
Saturn IB (also called C-1B and Uprated Saturn) was a step closer to the vehicle
required for lunar missions. Used to perform the earth-orbital phase of Apollo, it
depended on nine Rocketdyne engines in its two stages. Saturn IB helped qualify the
Apollo spacecraft three times in 1966 and 1968. On October 11, 1968, it boosted
Apollo 7 with a crew of three astronauts into orbit.
Plans for Saturn V (also called Saturn C-5), NASA's largest launch vehicle, were
officially approved in January 1962. Powered by 11 Rocketdyne engines, its first
launch took place in 1967. Saturn V's three stages sent an Apollo spacecraft to lunar
orbit for the first time in December 1968 (Apollo 8). This reliable vehicle would be
used in the next decade of NASA's operations for lunar exploration and Apollo ap-
plications (Skylab) missions.
The Marshall Space Flight Center oversaw the work of many Saturn contrac-
tors. The major ones were Rocketdyne Division of North American Aviation
(Saturn I first-stage propulsion, Saturn IB first- and second-stage propulsion, and
Saturn V first-, second-, and third-stage propulsion, plus Saturn V second-stage air-
frame), Chrysler Corporation (Saturn I first-stage airframe, Saturn IB first-stage
airframe), Pratt & Whitney Aircraft Company (Saturn I second-stage propulsion),
Douglas Aircraft Corporation (Saturn I second-stage airframe, Saturn IB second-
stage airframe, Saturn V third-stage airframe), and Boeing Company (Saturn V
first-stage airframe). _]
APOLLO
SPACECRAFT
LEM
ADAPTER
¢/ INSTRUMENT
UNIT
•APOLLO S-IVB
BOOSTER
f1_ SPACECRAFT
LEM
APOLLO J S-II
BOOSTER
;-"_i / SPACECRAFT ADAPTER T
_# INSTRUMENT
::T S-IC
BOOSTER
i Itlrl_ s,
BOOSTER r
--, I/.I
Source: From Courtney G. Brooks, James M. Grimwood, and Loyd S. Swenson, Chariots for Apollo; A History of Manned
Table 1-63.
Saturn I Characteristics
Propulsion system
Stages: 2
Table 1-64.
Chronology of Saturn I Development and Operations
Date Event
April 1957 Studies were begun by the Army's yon Braun team at Redstone Arsenal on
darge boosters capable of launching 9070 to 18 140 kilograms into orbit or
2721 to 5442 kilograms to an escape trajectory.
Dec. 1957 The Army Ballistic Missile Agency proposed to DoD a booster capable of
6 672 000 newtons of thrust with a cluster of four Rocketdyne engines.
Aug. 15, 1958 The Advanced Research Projects Agency (ARPA) authorized the Army
Ballistic Missile Agency to conduct an R&D program at Redstone for a
6 672 000-newton booster (unofficially known as Juno V).
Sept. 11, 1958 Contract was awarded to Rocketdyne to update the Thor-Jupiter engine,
which became the H-I.
Oct. 1958 ARPA tentatively identified the advanced multistage launch vehicle as Juno
V.
April 28, 1959 First production H-I engine was delivered to the Army Ballistic Missile
Agency.
Dec. 1959 ARPA and NASA requested an engineering study for a three-stage Saturn
from the Army Ordnance Missile Command.
LAUNCH
VEHICLES 57
Table 1--64.
Chronology of Saturn I Development and Operations (Continued)
Date Event
Dec. 15, 1959 Saturn Vehicle Evaluation Committee recommended a long-range develop-
ment program for a family of Saturn launch vehicles, the first to be called
C-1.
Jan. 18, 1960 The Saturn project was formally approved and given the highest national
priority.
April 26, 1960 NASA awarded Douglas Aircraft Co. a contract to develop the Saturn sec-
ond stage (S-IV).
July 1, 1960 Program was formally transferred to the Marshall Space Flight Center.
Aug. 10, 1960 NASA awarded a contract to Pratt & Whitney to develop the LR-119 engine
for the S-IV and S-V stages of the C-I vehicle.
Oct. 21, 1960 NASA awarded a study contract to Convair for the S-V upper stage, but the
requirement for an S-V stage on the C-I was dropped in Jan. 1961.
March 1961 Marshall redirected Pratt & Whitney's development of the LR-119; instead,
the RL 10-A-1 would be used for Centaur and the S-IV stage.
April 29, 1961 First flight qualification test of SA-I booster was successful.
June 1961 Contract was awarded to Chrysler for the management of the quality and
reliability testing program required to qualify the various Saturn booster
components.
July 1961 Rocketdyne static fired the F-1 engine. Contracts were awarded to General
Dynamics, Douglas, Lockheed, and Martin Marietta to study a nuclear-
powered upper stage for Saturn.
Sept. 15, 1961 SA-I vehicle was completely assembled on the launch pedestal at launch com-
plex 34, Cape Canaveral.
Oct. 27, 1961 SA-1 launch was almost flawless (first stage test only; dummy second stage).
Nov. 6, 1961 S-I1 stage was redesigned to incorporate five J-2 engines.
Nov. 17, 1961 Chrysler Corp. was selected to build 20 S-I boosters.
Nov. 19, 1961 RL-10 engine was successfully tested (first U.S. liquid hydrogen engine).
April 25, 1962 SA-2 launch was successful (first-stage test only; second stage was filled with
water-called Project Highwater).
May 1962 S-II stage was lengthened from 22.9 meters to 24.8 meters; S-IC stage was
shortened from 43 meters to 42 meters.
Nov. 16, 1962 SA-3 launch was successful (first-stage test only).
March 28, 1963 SA-4 launch was successful (first-stage test only).
June 1963 Dynamics test of S-IV stage with Apollo boilerplate and launch escape system
was completed.
Oct. 30, 1963 Saturn 1 manned missions were dropped from NASA's plans, thereby
deleting the need for six Saturn I vehicles. Later that winter a third Pegasus
meteoroid detector satellite mission was planned for the 10th Saturn I launch.
58 NASA
HISTORICAL
DATABOOK
Table1-64.
Chronology
of Saturn
I Development
andOperations
(Continued)
Date Event
Oct.31,1963 Marshall
received
thefirstproductionmodelF-1engine.
Jan.29,1964 SA-5launch
wassuccessfulwithlivefirstandsecondstages.
May28,1964 SA-6launch
was successful
withtheguidance system
active forthefirsttime
andanApolloboilerplate
model includedintheconfiguration.
Sept.
18,!964 SA-7launch
withApollo boilerplate
command andservicemodules was suc-
cessful.
Saturn
I wasdeclaredoperational.
Feb.16,1965 SA-9launchwithApolloboflerplate andPegasus 1 meteoroid detection
satellite was successful.
May25,1965 SA-8 launch with Apollo boilerplate and Pegasus 2 was successful (first
contractor-built S-I stage).
July30,1965 SA-10 launch with Apollo boilerplate and Pegasus 3 was successful; this
marked the conclusion of the Saturn I program.
Table 1-65.
Saturn IB Characteristics
Table 1-66.
Chronology of Saturn 1B Development and Operations
Date Event
March 31, 1961 NASA approved the accelerated development of the Saturn C-2 vehicle.
June 23, 1961 Design work on C-2 was discontinued in favor of C-3 and Nova concepts.
Dec. 21, 1961 Douglas was selected to modify the second stage (S-IVB) by installing a single
J-2 engine capable of 889 600 newtons thrust.
July 11, 1962 NASA announced the need for a new t_'o-stage Saturn for manned earth-
orbital missions with full-scale Apollo spacecraft.
Aug. 1963 Contracts were awarded to Chrysler for the S-IB stage and to Douglas for the
S-IVB stage.
Nov. 8, 1963 Marshall Space Flight Center directed Rocketdyne to develop an uprated H-I
engine.
June 1964 Rocketdyne delivered the first four uprated H-I engines.
April 1, 1965 First stage was successfully static-fired for the first time; Rocketdyne was
authorized to increase the H-l's capability to 911 840 newtons.
July 1965 Rocketdyne initiated a development program to uprate the thrust capability
of the J-2 engine to 1 023 040 newtons.
Aug. 9, 1965 Chrysler shipped the first IB booster to Kennedy Space Center.
Oct. 28, 1965 Rocketdyne delivered to Chrysler the first two H-1 uprated engines.
Dec. 26, 1965 An Apollo spacecraft was added to the launch vehicle; together they were
designated AS-201.
Feb. 26, 1966 Launch of AS-201 was successful (suborbital test of Apollo command
module heat shield).
July 5, 1966 Launch of AS-203 without a spacecraft was successful (observation of liquid
hydrogen in zero gravity).
Aug. 25, 1966 Launch of AS-202 was successful (test of command module heat shield).
Jan. 22, 1968 Launch of Apollo 5 (AS-204) with lunar module was successful.
Oct. 11, 1968 Launch of Apollo 7 (AS-205) with crew of three was successful.
60 NASA HISTORICAL DATA BOOK
Table 1-67.
Saturn V Characteristics
Table1-68.
Chronology
ofSaturn
V Development
andOperations
Date Event
Sept. 11, 1961 NASA selected North American to develop and build the S-I! stage for an ad-
vanced Saturn.
Nov. 10, 1961 NASA received proposals from five firms for the development and produc-
tion of advanced Saturn boosters.
Dec. 15, 1961 Boeing was selected as the most likely candidate for prime contractor of the
S-IC stage of advanced Saturn.
Dec. 21, 1961 Douglas was selected to modify the second stage of Saturn IB by installing a
single J-2 engine of 889 600 newtons thrust. Called the S-IVB stage, it would
be used as the third stage in the advanced Saturn.
Jan. 25, 1962 NASA approved the development of the three-stage Saturn C-5 for the
manned lunar program.
Feb. 9, 1962 Preliminary contract was awarded to North American to design and fabricate
the S-II stage of C-5.
Mid-May 1962 Marshall Space Flight Center directed Douglas to increase the diameter of the
S-IVB stage to 6.6 meters.
Aug. 6, 1962 Boeing was awarded a contract for the development of the C-5 booster.
Aug. 8, 1962 Douglas was awarded a contract for 11 S-IVB stages.
Aug. 15, 1962 Rocketdyne was awarded a contract to continue H-1 engine R&D.
Feb. 1963 Saturn C-5 was renamed Saturn V.
May 1963 The J-2 engine was successfully fired for the first time.
April 23, 1966 First captive firing of Saturn V second stage test vehicle, which developed
more than 4 million newtons of thrust.
Aug. 26, 1966 First Saturn V flight booster was shipped to Kennedy Space Center.
Jan. 21, 1967 First S-If stage arrived at Kennedy.
Jan. 27, 1967 Jet Propulsion Laboratory issued a request for proposals for preliminary
design studies of unmanned Voyager missions to Mars to be launched by
Saturn V.
April 27, 1967 Saturn upper stage model outfitted as a manned orbital workshop arrived at
Marshall.
May1967 S-IVB orbital workshop design review was held at Marshall.
June 1967 AS-501 was erected.
July 11, 1967 First and second stages of AS-502 were mated.
Aug. 3, 1967 Successful completion of Apollo-Saturn V dynamic test program.
Aug. 26, 1967 Rollout of first Saturn V vehicle, the AS-501, at Kennedy.
Nov. 9, 1967 Launch of Apollo 4 (AS-501) was successful.
April 4, 1968 Launch of Apollo 6 (AS-502) was partially successful (premature second-
stage engine shutdown and third-stage failure to restart).
Dec. 21, 1968 Launch of Apollo 8 (AS-504) with crew of three was successful; the
spacecraft orbited the moon.
Scout
Scout was NASA's most frequently used small launch vehicle. A product of the
Langley Research Center, its development was initiated in 1957 when the laboratory
was part of the National Advisory Committee for Aeronautics. Scout's designers
created a vehicle that depended on off-the-shelf components and a small budget; ac-
cordingly, it was dubbed the "poor man's rocket." Both NASA and the Air Force
recognized the importance of the solid-fuel Scout for launching small payloads and
pushed for its early completion. Vought Astronautics of Chance Vought Aircraft
62 NASA HISTORICAL DATA BOOK
Table 1-69.
Scout Characteristics (as of 1968)
r.-.r
wE
'..D
O',
6 _ <_ -_.
',D
e-, O',
c5
I"--
i
F-
.-_ t"4
0'3
8
=_" c,
',,D
eq eq "q
_J
e-
_ _ ___
64 NASA HISTORICAL DATA BOOK
Table 1-71.
Listing of Scout Vehicles
S-114 Aug. 31, 1962 R&D launch (plus Reentry No (3d-stage failure)
Heating Experiment 2)
Table 1-71.
S-147C June 10, 1966 NASA launch of Air Force OV3- Yes
IV research satellite
Table 1-72.
Chronology of Scout Development and Operations
Date Event
July 1957 The Pilotless Aircraft Research Division (PARD) at NACA's Langley center
recognized the need to extend the performance capabilities of existing
research rockets.
Feb. 27, 1959 Memorandum of understanding between NASA and the Air Force, which
was also developing a small all-solid-fueled launch vehicle was signed to
avoid duplication. NASA would have responsibility for Scout development
while the Air Force would make the necessary modifications it required to
Scout for military payloads.
March 1, 1959 NASA and the Air Force officially announced their joint Scout program; the
Air Force's version of the vehicle would be called Blue Scout.
April 1959 Vought was awarded a contract for the airframes and the launch tower.
April 18, 1960 During a component test to analyze first- and third-stage performance, the
vehicle broke up after first-stage burnout.
July 1, 1960 First complete Scout launch from Wallops Station; fourth-stage separation
was not accomplished.
Dec. 4, 1960 Beacon satellite launch was unsuccessful due to second-stage failure.
Feb. 16, 1961 Explorer 9 launch was successful (first satellite launch with Scout).
March 1961 Decision was announced to increase the performance of Scout's third and
fourth stages, the work to be funded jointly by NASA and the Navy.
March 29, 1962 Launch of P-21A probe was successful (first flight with X-259 engine).
Aug. 31, 1962 Scout R&D launch to test an improved first stage (Algol liB) was unsuc-
cessful due to a third-stage electrical malfunction.
LAUNCH VEHICLES 67
Table 1-72.
Chronology of Scout Development and Operations (Continued)
Date Event
June 28, 1963 Launch of an Air Force research payload was successful (first flight of ABL
X-258 engine on fourth stage).
Nov. 1963 The Air Force and the Navy urged NASA to improve the reliability of Scout.
Nov. 21, 1964 Two Explorer satellites were successfully launched with a single Scout.
1965 Second and fourth stages were upgraded.
Aug. 10, 1965 R&D launch to evaluate upgraded second and fourth stages was successful.
Table 1-73.
Thor Characteristics
Height (m): 17
Diameter (m): 2.4
Launch weight (kg): 48 978
Propulsion system
Stages: 1
Powerplant: Rocketdyne
MB-1 Basic
LR79-NA-9
Thrust (newtons): 676 096
Propellant: LOX/RP-1
Payload capacity: 243 kg to an altitude of 463 km on a ballistic path
Origin: Air Force IRBM.
Contractors: Douglas Aircraft Co., Inc. (McDonnell Douglas), prime
Rocketdyne Div., North American, propulsion system
How utilized: To launch inflation tests for Echo.
With Able, Agena B, Agena D, and Delta upper stages to launch a variety of un-
manned payloads.
Remarks: Echo inflation test launch vehicles used an MB-3 propulsion system capable of
733 920 newtons of thrust.
The standard model Thor used was the DM-18.
Thor was upgraded in some configurations with the addition of strap-on engines and
by the elongation of its tanks. See following tables.
See also: Thor-Able, Thor-Agena B, Thrust-Augmented Thor-Agena B and D, Long-Tank,
Thrust-Augmented Thor-Agena D, and Thor-Delta.
Table 1-74.
Table 1-74.
Listing of Thor Stages (Continued)
Table1-74.
Listing
ofThorStages
(Continued)
Vehicle
Manufactur- Date Mission Thor
Stage
Successful*
ingno./Model
no.
460/DSV-3E Dec.16,1965 Pioneer 6 (Thor-Delta) Yes
Table 1-75.
Date Event
Dec. 27, 1955 Ballistic Missile Office, Air Materiel Command, awarded a contract to the
Douglas Aircraft Company for the development of Weapon System 315A, an
intermediate range ballistic missile.
Oct. 26, 1956 Douglas delivered the first WS-315A missile, which became known as Thor.
Jan. 25, 1957 Missile 101 launch was unsuccessful due to the rupture of the liquid oxygen
tank.
Sept. 20, 1957 Missile 105 launch was the first completely successful Thor launch.
Oct. 24, 1957 Missile 109 launch proved that the vehicle could fly its required 3200-
kilometer range.
1958 The Thor booster was used with the Able upper stage by the Air Force and by
NASA (NASA had responsibility for the October 11 and November 8 launch
attempts of Pioneer 1 and 2 lunar probes; in both cases the launch vehicles'
upper stages malfunctioned).
1959 The Thor booster was mated with the Agena upper stage by the Air Force.
May 13, 1960 The Thor booster was used with the Delta upper stage by NASA in the at-
tempted launch of an Echo satellite; the Delta stage malfunctioned.
Aug. 12, 1960 First successful Thor-Delta launch by NASA (Echo 1) took place. Thor-Delta
proved to be a highly successful configuration (used 61 times by NASA in
1960-1968).
Sept. 29, 1962 The Thor-Agena B configuration was used by NASA for the first time in the
launch of OGO 2; this configuration was used four times by NASA in
1965-1968.
72 NASA HISTORICAL DATA BOOK
Table 1-76.
Thor-Able Characteristics
Propulsion system
Stages:
Powerplant: Rocketdyne A.ll0-41 or Altair ABL ARC 1
MB-I Basic AJI0-42 X 248 KS 420
LR79-NA-9
Table 1-77.
Chronology of Thor-Able Development and Operations
Date Event
1955 Aerojet-General was awarded an Air Force contract to design and produce a
second-stage propulsion system based on the Aerobee-Hi sounding rocket for
the Vanguard launch vehicle.
Dec. 6, 1957 Vanguard with live second stage (TV-3) exploded due to a first-stage
malfunction.
Late 1957 Air Force requested Aerojet-General to modify the stage for use in ICBM
nose cone reentry tests; the Able stage was the result of those modifications.
Air Force established a space probe program that would utilize the Able up-
per stage.
March 17, 1958 First successful launch of Vanguard; second stage performed as pro-
grammed.
April 23, 1958 Attempted launch of Thor-Able combination by the Air Force was unsuc-
cessful.
July 9, 1958 Successful launch of Thor-Able; first test of a full-scale ICBM nose cone at
ICBM ranges and velocities.
Aug. 17, 1958 Thor-Able 1, an Air Force attempt to launch a lunar probe, was unsuccessful;
the first-stage engine exploded 77 seconds after liftoff; there was also uneven
separation of the second and third stages.
Oct. 11, 1958 NASA's attempt to launch the Pioneer 1 lunar probe was unsuccessful.
Nov. 8, 1958 NASA's attempt to launch the Pioneer 2 lunar probe was unsuccessful; the
third stage failed to ignite.
Table 1-78.
Thor-Agena B Characteristics
Table 1-79.
Chronology of Thor-Agena B Development and Operations
Date Event
Oct. 1956 Development began at Lockheed under contract with the Air Force for an ad-
vanced military satellite system and its associated upper stage vehicle; this up-
per stage became the Agena.
1957 The Air Force contracted with Lockheed for production of the Agena upper
stage.
Jan. 1959 NASA announced plans to use the Agena with Atlas and Thor.
April 24, 1959 The Air Force issued a contract amendment to Lockheed for the development
of an advanced Agena, to be known as Agena B.
Dec. 11, 1959 NASA cancelled its Vega upper-stage development program in favor of the
Agena B.
Oct. 26, 1960 The Air Force failed in its attempt to launch a Thor-Agena A; failure was due
to stage-separation malfunction.
Feb. 1961 An agreement was signed between NASA and the Air Force regarding
NASA's procurement of Agena B vehicles.
Sept. 29, 1962 NASA successfully launched Alouette 1 with a Thor-Agena B (first NASA
launch from the Western Test Range).
Jan. 25, 1964 Thor-Agena B launch of Echo 2 passive communications satellite was suc-
cessful.
Aug. 28, 1964 Thor-Agena B launch of Nimbus 1 meteorological satellite was successful.
Nov. 29, 1965 Thor-Agena B dual launch of Alouette 2 and Explorer 31 was successful.
Table 1-80.
Thrust-Augmented Thor-Agena B and D Characteristics
Table 1-81.
Chronology of Thrust-Augmented Thor-Agena B & D
Development and Operations
Date Event
1962 Air Force ordered the Thrust-Augmented Thor from Lockheed; the vehicle
consisted of a standard Thor with three strap-on solid-propellant Castor I
motors.
Feb. 28, 1963 First Air Force launch of a Thrust-Augmented Thor was unsuccessful; the
vehicle was destroyed when it veered off course.
March 18, 1963 The Air Force launched a payload into polar orbit with a Thrust-Augmented
Thor-Agena D.
Oct. 14, 1965 NASA launch of OGO 2 was successful with Thrust-Augmented Thor-Agena
D.
May 15, 1966 NASA launch of Nimbus 2 was successful with Thrust-Augmented Thor-
Agena B.
June 23, 1966 NASA launch of PAGEOS 1 was successful with Thrust-Augmented Thor-
Agena D.
July 28, 1967 NASA launch of OGO 4 was successful with Thrust-Augmented Thor-Agena
D.
76 NASA HISTORICAL DATA BOOK
Table 1-82.
(Thorad-Agena D) Characteristics
Table 1-83.
Chronology of Long-Tank, Thrust-Augmented
Thor-Agena D (Thorad-Agena D) Development and Operations
Date Event
1966 The Thor booster was uprated by stretching the stage; the result was the
Long-Tank Thor, or Thorad. The liquid oxygen and RP-1 tanks were
lengthened, giving the booster 65 more seconds of burn time and the capabili-
ty to lift 20 percent more payload.
Jan. 5, 1966 21 Thorad boosters were purchased from Douglas by the Air Force; all subse-
quent new-production Tbors were the Thorad version.
May 18, 1968 NASA attempted to launch Nimbus B and Secor satellites on a simple
Thorad-Agena D vehicle; the vehicle was destroyed at launch when it
malfunctioned.
Table 1-84.
Thor-Delta Characteristics
Thor-Delta A
Propulsion system
Stages: 3
Propulsion system
Stages: 3
Table 1-84.
Thor-Delta Characteristics (Continued)
Propulsion system
Stages: 3
Powerplant: Rocketdyne + 3 Thioko[ AJ10-118D Altair X-258
MB-3 Basic TX-33-52 strap-
LR79-NA-13 ons
Thrust (newtons): 765 056 719 775 34 694 25 576 I 545 101
Propellant: LOX/RP-I solid IRFNA/ solid
UDMH
Payload capacity: 590 kg to 185 km earth orbit
LAUNCH
VEHICLES 79
Table 1-84.
Listing of Thor Stages (Continued)
27.4
Height (rn): 15.9 5.2
Diameter (m): 2.4 1.4
Launch weight (kg): 48 978 6167 67 798
12 653 (strap-
ons)
Propulsion system
2
Stages."
Po werplant: Rocketdyne + 3 Thiokol AJ10-118E ---
MB-3 Basic TX-33-52 strap-
LR79-NA-13 ons
Thrust (newtons): 765 056 719 775 34 694 1 519 525
Propellant." LOX/RP-1 solid IRFNA/UDMH
................................................... _ ......................................
(TX°33-52)
strap-ons)
13 333
(TX-354-3)
strap-ons)
Propulsion system
Stages: 3
Powerplant: Same as for AJ 10-118E Thiokol
Delta E TE-364-3
Thrust (newtons): 765 056 719 775 34 694 44 480 1 564 005
Propellant: LOX/RP-1 solid IRFNA/ solid
UDMH
Table1-84.
Listing
of ThorStages(Continued)
1ststage 2dstage 3dstage Total
(Thorad) (Delta) (Delta) (w/adapters)
Thrust (newtons): 765 056 719 775 34 694 42 256 l 561 781
Propellant: LOX/RP-I solid IRFNA/ solid
UDMH
Origin: NASA design produced by Douglas Aircraft to extend usefulness of Thor booster.
Con tractors: Douglas Aircraft Co., Inc. (McDonnell Douglas), Thor prime and Delta prime
Rocketdyne Div., North American, Thor propulsion system
Thiokol Chemical Corp., Thor strap-ons and third stage
Aerojet-General, Delta stage propulsion system
Alleghany Ballistics Laboratory, Hercules Powder Co., third stage
United Technology Center, third stage
How utilized." With the Thor booster in a variety of configurations to boost many different classes
of satellites to several kinds of orbits; included in the payloads launched by Delta
combinations were Echo, Tiros, Relay, Explorer, lntelsat, OSO, HEOS, and ESSA
satellites.
Remarks: The Thor-Delta configurations were often referred to only as "Delta." Thor-Delta
was often called the workhorse of NASA's unmanned program.
See also: Thor, Thrust-Augmented Thor-Agena B & D, and Long-Tank, Thrust-Augmented
Thor-Agena D.
LAUNCH
VEHICLES 81
Table1-85.
ListingofDeltaVehicles
Vehicle
Serial
#/ Date Mission Delta
Stages
Delta Model # Successful*
Table 1-85.
Listing of Delta Vehicles (Continued)
Table1-86.
Chronology
ofThor-Delta
Development
andOperations
Date Event
Feb. 3, 1959 Douglas Aircraft responded to a NASA request for proposals to develop a
modified launch vehicle based on the Thor booster. NASA wanted to extend
the usefulness of the Thors the agency had purchased from the Air Force by
creating a vehicle based on the Thor-Able. The second stage was a modified
Vanguard second stage with an improved guidance and attitude control
system. It was redesignated Delta. A Vanguard X-248 third stage would serve
as Thor-Delta's third stage.
April 1, 1959 Douglas was awarded a contract by NASA to produce the Delta, which was
defined as an "interim" launch vehicle. It was intended to be used only as a
temporary vehicle, with Scout and Vega serving as the primary launch
vehicles of the future.
May 13, 1960 First launch of Thor-Delta with an Echo passive communications satellite
was unsuccessful due to a second-stage failure.
Nov. 23, 1960 Thor-Delta configurations were used successfully to launch many different
Dec. 18, 1968 payloads to a variety of orbits,
Oct. 2, 1962 Thor-Delta A model was used for the first time successfully.
Dec. 13, 1962 Thor-Delta B model was used for the first time successfully.
Nov. 26, 1963 Thor-Delta C model was used for the first time successfully.
April 6, 1965 Thor-Delta D model with thrust augmentation was used for the first time suc-
cessfully.
Dec. 11, 1959 NASA's Vega second-stage project was cancelled in favor of the Agena B,
and the agency continued to use Thor-Delta as a standard launch vehicle.
Nov. 6, 1965 Thor-Delta E model with improved Delta stage was used for the first time
successfully.
May 25, 1966 Thor-Delta C-1 model was used for the first time successfully.
July 1, 1966 Thor-Delta E-1 model was used for the first time successfully.
July 4, 1968 Thor-Delta J model was used for the first time successfully.
Aug. 16, 1968 Thor-Delta N model was used for the first time successfully.
Sept. 18, 1968 Thor-Delta M model with Thorad was used for the first time; the attempt to
launch a dual payload was unsuccessful because Delta's third stage malfunc-
tioned.
system necessary for the potentially explosive Redstone, Atlas, and Saturn boosters.
The vehicle was not without its difficulties, however. Problems with second-stage
combustion stability and a tendency for the entire vehicle to oscillate during launch
forced a delay in scheduling the first two-man Gemini mission to earth orbit.
The Gemini Launch Vehicle (GLV) was qualified in a test launch in April 1964.
Less than a year later, it boosted the first of 10 crews to orbit. NASA put Titan II on
the launch pad 12 times in 1964-1966; all the launches were successful. For more in-
formation see also chapter 2 under Gemini.14
Table 1-87.
Titan II (Gemini Launch Vehicle, GLV) Characteristics
Table 1-88.
Chronology of Titan II (Gemini Launch Vehicle, GLV)
Development and Operations
Date Event
May 2, 1955 The Air Force approved the development of an ICBM airframe, which
became the Titan missile.
June 1960 The Air Force awarded a contract to the Martin Co. (later Martin Marietta)
for the development of a Titan 1I; the primary difference between the two
missiles was Titan II's ability to use a storable hypergolic liquid propellant
that would not require liquid oxygen.
Spring 1961 NASA engineers considered Titan lI for launching an improved Mercury
(Gemini) manned spacecraft.
Fall 1961 Air Force Titan II was officially selected by NASA as the Project Gemini
launch vehicle.
March 1962 First operational launch of Titan I ICBM by the Air Force, preceded by 51
R&D and test launches.
March 16, 1962 First R&D launch of Air Force Titan I1.
Spring 1963 Together NASA and the Air Force solved second-stage combustion instabili-
ty and vehicle vibration-oscillation (called the Pogo effect) problems with
Titan II; these problems had to be corrected before the missile could be man-
rated. Gemini's schedule was delayed because of launch vehicle difficulties.
Fall-Winter 1963 NASA considered substituting the Saturn I for Titan II as the Gemini launch
vehicle. However, problems with Titan were solved during the various test
flights (Nov. 1963 to April 1964).
April 8, 1964 Launch of Gemini 1 to qualify the launch vehicle was successful.
Jan. 19, 1965 Launch of Gemini 2 to qualify the spacecraft was successful.
March 23, 1965 Launch of Gemini 3 with crew of two was successful.
Dec. 4, 1965 Launch of Gemini 7 with crew to act as a rendezvous target for Gemini 6.4
was successful.
Dec. 15, 1968 Launch of Gemini 6,4 with crew was successful.
Vanguard
Vanguard, the launch vehicle and the satellite, was the product of the Naval
Research Laboratory (NRL). The Navy team, which had experience with sounding
rocket research, began in 1955 to design a small vehicle capable of orbiting a satellite
for the American committee of the International Geophysical Year (IGY). NRL
received official approval for the project from the Department of Defense (DoD) in
August 1955. In less than a month, they had awarded the prime contract for the
three-stage launcher to the Martin Company.
Table 1-89.
Vanguard Characteristics
Propulsion system
3
Stages:
Aerojet-General Grand Central ABL X-248
Powerplant: GE X-405
A J-10 Rocket Co.
133-KS-2800
Thrust (newtons): 124 544 33 360 10 230 10 675 168 134-168 579
Because NRL suffered delays in the development of the Vanguard launch ve-
hicle, DoD gave the Army Ballistic Missile Agency, which had also submitted an
IGY satellite proposal, approval to participate. Explorer 1, launched by a Juno I,
became the first American satellite to orbit earth on January 31, 1958. Vanguard I
followed less than two months later. When NASA was established in October 1958,
Vanguard and the group at NRL responsible for the project were transferred to the
new civilian agency. NASA tried four times in 1959 to orbit scientific payloads with
Vanguard; only one was successful. For more information see also chapter 3 under
Vanguard. _5
Table 1-90.
Chronology of Vanguard Development and Operations
Date Event
1955 Early in the year, Naval Research Laboratory (NRL) scientists and engineers
started working on the design of a three-stage vehicle capable of launching a
small satellite, in reply to interest expressed by the international scientific
community and the military in orbiting artificial satellites.
July 6, 1955 The Committee on Special Capabilities (the Steward Committee within DoD)
heard NRL's proposal for a scientific satellite program.
Aug. 24, 1955 The Steward Committee approved NRL's proposal for launching an Interna-
tional Geophysical Year satellite with a three-stage vehicle (Viking first stage,
Aerobee second stage, new third stage).
Sept. 9, 1955 NRL was authorized to proceed with its proposal for Project Vanguard.
Sept. 23, 1955 The Martin Co. was awarded the prime contract for development and pro-
duction of Vanguard; Martin subcontracted with General Electric for the
first-stage engine.
Nov. 1955 Aerojet-General was awarded a contract for the second stage.
March 1956 Grand Central Rocket Co. and Alleghany Ballistics Laboratory were award-
ed contracts for third stages.
Dec. 6, 1957 TV-3 launch was the first complete Vanguard launch with three live stages.
Feb. 17, 1959 SLV-4 launch Vanguard 2 into orbit, but the third stage reignited and
bumped the payload, impairing the scientific value of the satellite.
Feb. 13, 1959 SLV-5 Vanguard launch with a magn0meter satellite was unsuccessful
because of second-stage malfunction.
June 22, 1959 SLV-6 Vanguard launch with a scientific satellite was unsuccessful because
tank pressure dropped after second-stage ignition.
Sept. 18, 1959 TV-4BU, with ABL third stage, successfully launched Vanguard 3 scientific
satellite into orbit.
CHAPTER TWO
MANNED SPACEFLIGHT
CHAPTER TWO
MANNED SPACEFLIGHT
Wartime research in the fields of aeronautics and rocketry guaranteed that the
1950s would be a promising decade for American engineers and pilots who sought
aircraft that would fly faster and higher, and for military specialists and scientists
who recognized the rocket's potential. Private industry, the military, and one of the
country's chief civilian research organizations, the National Advisory Committee
for Aeronautics (NACA), sought to apply the new technology spawned by the crises
of a world war to more nationalistic goals. Improved radar and radio interferometry
equipment on missile ranges allowed the military to evaluate captured German
rockets and their own sounding rockets and fledgling missiles more effectively.
Specially-instrumented aircraft proved out new design concepts and operational
procedures over California deserts. On the Atlantic coast, engineers used small
rockets to conduct materials testing at high speeds. Frontier beyond the atmosphere
was the goal of these and other exercises. By mid-decade, the Navy, Army, and Air
Force were all exploring different paths by which to reach that frontier.
Rivalry among the services to become the leader of an American "space pro-
gram" almost swept aside NACA. This advisory-research body was traditionally
committed to methodical investigations that would assist the user agency (usually
the military) in its mission; space spectaculars and quantum overnight leaps in the
state of the art were not its way of doing business. But it was an age of rapid ac-
celeration, and there were pockets of enthusiasm for the new pace even within the
conservative NACA.
Sending biological payloads, animal and later human, into space was seemingly
a logical extension of two ongoing activities: the scientific satellite-sounding rocket
program being conducted by the Naval Research Laboratory, the Army, and others,
and the Air Force-NACA hypervelocity research aircraft program.* If intercon-
*During the postwar years, the Army experimented with animals (monkeys and mice) as part of the
V-2 program at White Sands Missile Range, while the Air Force conducted similar investigations with
Aerobee sounding rockets at Holloman Air Force Base. From 1953 through 1957, however, medical ex-
perimentation with animals was discontinued as the military ballistic missile project monopolized night
opportunities and funds. Investigators had to be content with aircraft-borne experiments. In the USSR
during the 1950s, researchers sent numerous biological payloads on rocket flights, with dogs being fre-
quent test subjects. For more information, see Loyd S. Swenson, Jr., James M. Grimwood, and Charles
C. Alexander, This New Ocean; A History of Project Mercury, NASA SP-4201 (Washington, 1966), pp.
37-38; Edward C. Ezell and Linda N. Ezell, The Partnership; A History of the Apollo-Soyuz Test
Project, NASA SP-4209 (Washington, 1978); and Joel Powell, "Animal Precursors to Manned Space
Flight," Spaceflight 22 (Sept.-Oct. 1980), pp. 315-18.
91
92 NASA
HISTORICAL
DATABOOK
A view popular with the Air Force was that the skies belonged to it, and this
branch of the military was not going to allow the absence of an atmosphere to
restrict its domain. With the Atlas intercontinental ballistic missile, under develop-
ment at Convair since 1946, the Air Force sought to defer "Soviet aggression." In in-
creasingly sophisticated aircraft, Air Force test pilots in the mid-1950s were flying
three times the speed of sound and approaching altitudes of 20 000 meters. Space
medicine proved to be a natural extension of aviation medicine, and the Air Force
established several special facilities for human factors research as it related to space
travel. NACA supported these Air Force programs with research in the fields of
aerodynamics, propulsion, structures, and materials. Protection of a warhead dur-
ing reentry was one critical problem that NACA specialists at the Ames and Langley
aeronautical laboratories tackled. Since 1954, the Air Force and NACA, along with
the Navy, had also been formally involved in a joint hypersonic research aircraft
project that the Air Force labeled X-15.* Flying at speeds in excess of Mach l had
been "round one." The X-15 with a design speed of Mach 6 at 76 000 meters was
"round two." The third round would hopefully take the Air Force into space.
The Soviet Union's unexpected success in orbiting two satellites in 1957, the sec-
ond one with a biological payload, interfered with the Air Force's incremental plans.
The U.S. desperately needed to get into space soon, and with a manned mission,
warned military leaders. The Air Force could not hope to launch its weighty X-20
Dyna-Soar (round three, based on a delta-wing flat-bottom glider design favored at
NACA's Langley Memorial Aeronautical Laboratory) in the near future, but there
was a more feasible alternative: send a man into orbit in a ballistic-shaped capsule
*See chapter I, pp. 44-51, for more information on the Atlas missile and chapter 4, pp. 202-24, for
more on the joint hypervelocity research aircraft program.
MANNED SPACEFLIGHT 93
atop an ICBM.* NACA engineers at Langley had been studying this possibility, and
they agreed that a conical spacecraft with a blunt reentry surface could be launched
by missiles currently available. Abandoning for the present a scheme for a mission
launched by a two-stage vehicle under development, the Air Force proposed to
NACA in January 1958 that the Committee join them in supporting a two-phase
manned program. First they would get "Man-in-Space-Soonest" using the ballistic
missile (Atlas) approach; then they would proceed with their boost-glide vehicle.'
Before NACA and the Air Force could formalize any agreement, events in
Washington of a more political nature overtook them. President Dwight D.
Eisenhower, personally committed to keeping space a peaceful frontier, submitted a
bill to Congress in April in which he recommended establishing a new civilian agency
based on the National Advisory Committee for Aeronautics that would manage this
country's space program. NACA waited for Congress to act before committing itself
to the Air Force's proposal.
The Army Ballistic Missile Agency (ABMA) at Redstone Arsenal, Huntsville,
Alabama, was also anxious to expand its ongoing intermediate range ballistic missile
projects into a program involving spaceflight. Under the leadership of Wernher von
Braun and other German rocket specialists brought to the U.S. after World War II,
ABMA had successfully developed several tactical missiles for the Army. The
Redstone missile was sent on its first test flight in 1953. Building on this reliable
booster, yon Braun's team added two upper stages with which to conduct their own
nose cone reentry tests (Jupiter C). Adding to the stack again, ABMA offered the
Juno I to the American International Geophysical Year (IGY) committee in 1955 as
the best vehicle for launching this country's first artificial satellite. In competition
with a project sponsored by the Naval Research Laboratory, the Army orbited the
first American satellite (Explorer) in January 1958. With success on their side, von
Braun angled for a manned spaceflight assignment, using proposals for a huge
clustered-engine rocket as bait. According to specialists in Alabama, not only was
orbital manned flight possible, it was a first step to manned lunar bases and space
stations. The Advanced Research Projects Agency (ARPA), established in February
1958 to oversee the various space projects and proposals, approved ABMA's scheme
for the powerful rocket in August.t The Army, however, was not destined to
manage its own manned space program. In Washington, planners of the new civilian
space agency were assessing the possible value of yon Braun's rocket. 2
The Naval Research Laboratory (NRL) near Washington had been the home of
sounding rocket research in the U.S. since 1945. Refinements of these small rockets
during the postwar years inspired a group of engineers and scientists to respond to
the IGY call for a satellite. Although the Army, not NRL, launched the first orbiting
payload, Project Vanguard did add to the country's growing pool of knowledge
* Chap. 4, pp. 112-13, discusses Project Dyna-Soar. This glider design, which hv/d been promoted by
experts at Langley, was a lifting body-type vehicle. It was designated X-20 in 1962.
t During 1958, the Army was also suggesting that the Redstone missile could be used to launch a man
along a steep suborbital trajectory, after which he would splash down in the Atlantic. When Air Force of-
ficials declined to get involved in Project Man Very High, the Army renamed their plan Project Adam.
The proposal was not considered a practical one by the Department of Defense or ARPA and was not
funded.
94 NASA HISTORICAL DATA BOOK
about space. Within the Navy, there were other groups, the missile contingent
among them, who were interested in even more ambitious programs. With the Air
Force and NACA, the Navy contributed to the X-15 project, and the service sup-
ported aerospace medicine research) In 1958, the Navy added to the growing
number of proposals for manned spaceflight. Their study of a "Manned Earth
Reconnaissance" mission included plans for a cylindrical spacecraft with spherical
ends, which could be transformed into a delta-wing inflated glider once in orbit.
Project MER was not funded beyond a feasibility study.
The National Advisory Committee for Aeronautics met the space age introspec-
tively. It had changed since its birth in 1915 from a strictly advisory group to a
research organization and policy maker, but it was little known outside the military
and the aircraft industry. The NACA laboratories' engineers conducted studies, car-
ried out research, and delivered their reports, but it was not their job to apply the
results. The Committee's leaders of the 1940s had been reluctant to commit the
organization to a role in rocket propulsion research or the risky new field of
astronautics, and it was not until 1952 that a move was made to seriously study flight
in the upper atmosphere and space. One small group at the Langley laboratory, the
Pilotless Aircraft Research Division (PARD), was already using rockets as a
research tool on nearby Wallops Island, Virginia. Since 1945, PARD (originally the
Auxiliary Flight Division) had been measuring the effects of hypervelocity flight and
the resultant heating on models launched by small rockets: In California at the
Ames Research Laboratory, aerodynamicists working with H. Julian Allen con-
ducted wind tunnel experiments with missile nose cone models for the Air Force.
They discovered that a blunt-bodied configuration rather than the sharp-nosed one
being considered at Convair for Atlas would survive atmospheric reentry. These
nose cone studies led Allen and his colleagues Alfred J. Eggers, Jr., and Stanford E.
Neise to speculate on designs suitable for manned spacecraft of the future. In an im-
portant paper, the three men discussed ballistic, skip, and glide vehicles)
As the Air Force Air Research and Defense Command's interest in manned
spaceflight grew, so did the amount of spaceflight-related research at NACA,
although it still remained low priority relative to aeronautics work. By 1957,
however, an estimated 40 to 50 percent of NACA's assignments involved space
research. Supporters of all three of the proposed general designs for a manned
spacecraft existed at NACA, with the early favorite, especially at Langley, being a
delta-wing fiat-bottom glider. Eggers borrowed from this configuration and the
ballistic shape to design what came to be called a lifting body- a semiballistic vehicle
with a certain amount of aerodynamic lift with a nearly flat top and a round bottom
(the M-l). This design was further refined, and models were built and flight-tested at
the Flight Research Center near Edwards Air Force Base, California.* PARD
engineers led by Maxime A. Faget and Paul E. Purser stuck by their original studies,
* See chapter 4, pp. 110-24, for more on NASA's lifting body program.
MANNED
SPACEFLIGHT 95
which favored the ballistic shape. While the Langley researchers worked in their
spare time on refining their suggestions for a manned spaceflight, the Soviets orbited
the first two artificial satellites. NACA Headquarters in Washington reacted to
Sputnik with a new committee: the Special Committee on Space Technology; its
members were charged with finding ways in which NACA could participate more
aggressively in upper atmosphere and space research.
NACA was not the only body to form investigating committees in response to
the Soviet Union's mechanical moons. A U.S. Senate committee chaired by Lyndon
B. Johnson met to review America's prospects for a national space program. The
Secretary of Defense established ARPA. And President Eisenhower instructed his
new President's Scientific Advisory Committee (PSAC) to study the legality and
feasibility of a federally funded space program. In mid-April, the president sent his
proposed space bill to Congress, which reflected the advice of his scientific commit-
tee and a White House Advisory Committee on Government Organization. It did
not take the lawmakers long to revise and approve the National Aeronautics and
Space Act of 1958. Passed on July 16, the act was signed into law on the 29th, but it
took another month for the White House to assign the important manned
spaceflight task to the new civilian National Aeronautics and Space Administration
(NASA). Robert R. Gilruth, the first chief of PARD and Langley's assistant director
when the space act was passed, was named to chair a NASA-ARPA Manned
Satellite Panel in September. These experts, who met for the first time in late
September 1958, would provide specific recommendations and a basic procedural
plan for NASA's manned program.
96 NASA HISTORICAL DATA BOOK
Table 2-1.
Events that Influenced NASA's Manned Spaceflight Program prior to the Agency's
Establishment
Date Event
May 7, 1945 The Langley Memorial Aeronautical Laboratory of the National Advisory
Committee on Aeronautics (NACA) created an Auxiliary Flight Division,
with an operational Research Station located at Wallops Island, Virginia. In
1946, this group, which carried out materials testing and other investigations
by means of small rocket launchings, was renamed the Pilotless Aircraft
Research Division (PARD). Robert R. Gilruth was chief of this division until
1952.
1946 The Air Force awarded a contract to Convair to develop a long-range missile,
the MX774. Although the Air Force's missile program was cancelled the next
year, Convair continued its research in-house.
Nov. 1948 At Randolph Air Force Base, a panel under the direction of Harry G. Arm-
strong discussed "Aeromedical Problems of Space Travel." Three months
later Armstrong established a Department of Space Medicine at Randolph
under the direction of Hubertus Strughold.
Jan. 1951 With the reestablishment of the Air Force missile program, the Convair con-
tract was reinstated; the proposed missile was named Atlas.
Summer 1953 In August, the Army fired its first research and development model of the
Redstone missile and began to study nose cone reentry thermodynamics at
Redstone Arsenal. At Holloman AFB, the Space Biology Branch of the
Aeromedical Field Laboratory began a program that would last more than
five years to study weightlessness during parabolic flights. (Other groups in-
terested in weightlessness studies at this time included the Department of
Space Medicine, Randolph AFB; the Wright Air Development Center,
Wright-Patterson AFB; the Navy School of Aviation Medicine; and NACA's
Lewis Flight Propulsion Laboratory.)
Dec. 23, 1954 Representatives from NACA, the Air Force, and the Navy signed a
memorandum of understanding establishing a joint hypersonic research air-
craft program. A design for the aircraft proposed at Langley had been ac-
cepted earlier in the year. The project was designated X-15 by the Air Force.
1955-1956 At the request of the Air Force, Army, and Navy, NACA tested materials
suitable for use as heat sinks and ablatives. The PARD group studied the heat
MANNED SPACEFLIGHT 97
Table 2-1.
Events that Influenced NASA's Manned Spaceflight Program prior to the Agency's
Establishment (Continued)
Date Event
Table 2-1.
Events that Influenced NASA's Manned Spaceflight Program prior to the Agency's
Establishment (Continued)
Date Event
Jan. 23, 1958 Senator Lyndon B. Johnson summarized the findings of the Senate
Preparedness Investigating Committee formed to review the U.S. space pro-
gram. Their 17 recommendations included establishing an independent space
agency.
Jan. 24, 1958 The ARDC's plan for astronautics called for reconnaissance, communica-
tions, and weather satellites, recoverable data capsules, manned capsules,
manned stations, and eventually a manned lunar base.
Jan. 29-31, 1958 At a closed conference, 11 aircraft and missile companies outlined for the Air
Force and NACA their various proposals for manned satellite vehicles.
Jan. 31, 1958 The Air Force formally invited NACA to participate in its man-in-space pro-
gram. The Committee was asked to support both a one-orbit manned flight
and a boost-glide research airplane (Project Dyna-Soar, a design based on
Langley's delta-wing flat-bottom glider).
Feb. 1958 The Secretary of Defense created the Advanced Research Projects Agency
(ARPA) to manage all existing space projects. President Dwight D.
Eisenhower instructed the President's Scientific Advisory Committee (PSAC)
to study the feasibility of government-financed astronautical ventures and a
national space science program. Late in the month, a PSAC subcommittee
suggested establishing a new civilian space agency to be built around NACA.
Also during February, the NACA Committee on Aerodynamics was renamed
the Committee on Aircraft, Missile, and Spacecraft Aerodynamics.
March 1958 ARPA recognized the Air Force's responsibility to accomplish manned
satellite flight as soon as the technology permitted, and the Department of
Defense authorized the Air Force to develop a liquid propellant upper stage
(Agena) to be used with Atlas or Thor. The ABMA also proposed a manned
spaceflight program, which included von Braun's ideas for a clustered-engine
booster. On March 10-12, ARDC held a conference in Los Angeles for Air
Force, NACA, and industry specialists who were working in the fields of
rocketry, aeronautics, or biotechnology. Most attendees agreed that a simple
ballistic capsule would offer the quickest means for getting man into orbit.
On the 14th, NACA officially informed the Air Force that it would cooperate
in drawing up a detailed manned satellite development plan. Also on the
14th, a NACA Conference on High-Speed Aerodynamics began at Ames, at
which Faget (PARD) presented a paper favoring the wingless nonlifting
ballistic configuration for manned spaceflight. (The paper was coauthored by
Faget, Benjamin J. Garland, and James J. Buglia).
Winter-Spring 1958 At Langley, PARD and other research divisions devoted their time to work-
ing out the details of a manned mission that would utilize the ballistic-type
spacecraft and the Atlas missile. On another front, working to determine the
human body's tolerance to increased gravity, it was discovered at l-tolloman
AFB on a rocket-driven impact sled that 83g represented the limit of human
tolerance for deceleration. Using centrifuges at the Navy's Aviation Medical
Acceleration Laboratory and at the Air Force's Aeromedical Laboratory,
specialists determined that 8g represented the acceleration safety limit.
April 1958 When the Air Force refused to participate in the Army's plans for an inter-
service "Man Very High" spaceflight project, the ABMA devised an Army-
MANNED SPACEFLIGHT 99
Table 2-1.
Events that Influenced NASA's Manned Spaceflight Program prior to the Agency's
Establishment (Continued)
Date Event
Navy proposal called Project Adam. Using a modified Redstone, von Braun
and his colleagues wanted to launch a man in a sealed capsule along a steep
ballistic trajectory, after which the capsule would land in the ocean and be
recovered.
April 14, 1958 President Eisenhower sent his proposed space bill (based largely on PSAC's
advice and the White House Advisory Committee on Government Organiza-
tion's suggestions) to Congress; special committees began hearings on the
bill.
May 2, 1958 Air Force Headquarters was sent detailed designs and procedures for the
ARDC Ballistic Missile Division's "Man-in-Space-Soonest" scheme.
Mid-May 1958 NACA and the Air Force tabled their agreement to work together on a
ballistic manned spacecraft project.
June 16, 1958 ARPA approved a revised Air Force Man-in-Space-Soonest proposal that
called for using the Atlas rather than a proposed two-stage vehicle. However,
only funds for life support system studies were granted.
July 16, 1958 Congress passed the National Aeronautics and Space Act of 1958, creating
the National Aeronautics and Space Administration; Eisenhower signed the
act into law on the 29th.
Aug. 1958 Eisenhower assigned the new space administration specific responsibility for
developing and carrying out the mission of manned spaceflight. The Air
Force Man-in-Space-Soonest project was cancelled, money earmarked for it
being transferred to NASA. But the Air Force was allowed to proceed with
development of Dyna-Soar in conjunction with NASA. On the 15th, ARPA
provided the Army Ordnance Missile Command with the authority to
develop the Juno V launch vehicle based on von Braun's plans for a large
clustered-engine rocket.
Sept. 1958 A NASA-ARPA Manned Satellite Panel (Gilruth of Langley, chairman) was
formed to generate specific recommendations and a basic procedural plan for
NASA's manned satellite project. The panel began holding meetings during
the last week of the month.
From the Langley engineers' studies of reentry configurations grew Project Mer-
cury, NASA's first entry in the manned space program.* Project Mercury would
prove that one man could be safely launched into earth orbit in a ballistic-shaped
spacecraft, that he could survive increasing lengths of time in the weightlessness of
space, that his progress could be monitored by a global network of ground stations,
and that he could return safely to a predetermined splash-down point where crews
waited to recover him. Beyond earth orbit was the moon, orbiting space stations,
perhaps manned exploration of the planets. Mercury was only a simple first step. 6
NASA officials were working steadily toward manned orbital flight in the
spring of 1961, anticipating the first suborbital piloted missions that were scheduled
to take place soon, when the USSR launched another "space first." Yuri A. Gagarin
in Vostok 1 circled the earth on April 12. The U.S. was still 10 months away from its
first orbital manned mission. NASA had tested full-scale models of the Mercury
spacecraft during suborbital flights, had a team of astronauts in training, and had
successfully flight-tested the Redstone and Atlas boosters, but a Russian astronaut
had earned the title "first man in space." An American president would once again
react to Soviet space feats with a countermove. The United States was the
technological leader of the world, President John F. Kennedy asserted just weeks
after the Gagarin flight, and NASA would prove it by landing a man on the moon
and returning him safely by the end of the decade- an ambitious goal for the young
agency. 7 Project Apollo, NASA's proposed lunar enterprise, was thus given the ad-
ministration's highest priority. Apollo would require great sums of money and most
of the agency's attention during its first decade. Before John Glenn could make the
first U.S. orbital flight aboard his Mercury Friendship 7 spacecraft in February
1962, NASA had already reorganized its headquarters management to reflect the in-
creased commitment it had given Apollo.
However, NASA did not leap from Mercury to Apollo. Project Gemini, the in-
termediate step, called for a spacecraft larger than Mercury to accommodate two
passengers for longer missions. With more control over their spacecraft, Gemini
astronauts would demonstrate rendezvous and docking with other vehicles while in
orbit. These second-generation spacecraft circled earth in 1965 and 1966 on missions
lasting from 4 hours to 13 days. The highly successful project gave NASA's opera-
tions people experience with tracking and supporting two manned spacecraft
simultaneously and an appreciation for the mechanics of orbital rendezvous and ex-
travehicular activity. It also gave von Braun's team in Alabama and the engineers at
the Manned Spacecraft Center in Houston the time they needed to develop the
powerful Saturn V launch vehicle and the complex Apollo spacecraft.
*At an important meeting at Ames in March 1958, Faget delivered a formal paper defining the
ballistic-shaped manned spacecraft (Maxime A. Faget, Benjamin J. Garland, and James J. Buglia,
"Preliminary Studies of Manned Satellites- Wingless Configuration: Nonlifting," in "NACA Conference
on High-Speed Aerodynamics, Ames Aeronautical Laboratory, Moffett Field, Calif., Mar. 18, 19, and
20, 1958: A Compilation of Papers Presented," pp. 9-34, reissued as NASA Technical Note D-1254,
Langley Research Center, 1962).
MANNED
SPACEFLIGHT 101
*The existence of an actual race to the moon with the Soviets is still under debate. Most experts
believe that any early discussions by Soviet spokesmen of manned flights to the moon and beyond were
political in nature or at least premature and not based on the actual hardware under development. The
Soviets relied on automatic spacecraft to explore the moon and the planets, devoting their manned pro-
gram to increasingly sophisticated earth-orbital activities. During the early 1960s, however, it was the
firm conviction of many Americans that success with Project Apollo would prove the technological, and
thus the military, superiority of the U.S.
102 NASA
HISTORICAL
DATABOOK
*Of the 36 original members of the STG from Langley, 14 were drawn from PARD (William M.
Bland, Jr., Aleck C. Bond, Maxime A. Faget, Edison M. Fields, Jack C. Heberlig, Clairborne R. Hicks,
Jr., Alan B. Kehlet, Ronald Kolenkiewicz, John B. Lee, Betsy F. Magin, Paul E. Purser, Herbert G. Pat-
terson, Frank C. Robert, and Julia R. Watkins); 5 from the Flight Research Division (Robert G. Chilton,
Jerome B. Hammack, Christopher C. Kraft, Jr., Charles W. Mathews, and John P. Mayer); 2 from the
Instrument Research Division (William J. Bayer and Harry H. Ricker, Jr.), 2 from the Office of the
Assistant Director (Charles J. Donlan and Robert R. Gilruth), 2 from the Stability Research Division
(George F. MacDougall, Jr., and Charles H. Zimmerman), 1 from the Structures Research Division
(Melvin S. Anderson), 1 from the Full-Scale Tunnel Research Division (Paul D. Taylor), 1 from the
Dynamic Loads Division (William T. Lauten, Jr.), plus 1 each from the planning and fiscal offices
(William C. Muhly and Ronelda F. Sartor), and 3 stenographers and 3 file clerks. Ten other specialists
from the Lewis Research Center brought the total number of scientist-engineers to 38.
MANNED SPACEFLIGHT 103
* During August 1961, a site selection team led by John F. Parsons (Ames Research Center) evaluated
20 cities in their search for a location that met 10 specific requirements for the new manned spaceflight
center. These requirements included available facilities for advanced scientific study, power facilities and
utilities, water supply, mild climate, adequate housing, at least 1003 acres of land, available industrial
facilities, transportation, including water for shipping by barge, jet service airport, and local cultural and
recreational facilities. Sites considered were Tampa and Jacksonville, Florida; New Orleans, Baton
Rouge, Shreveport, and Bogalusa, Louisiana; Houston, Beaumont, Corpus Christi, Victoria, Liberty,
and Harligen, Texas; St. Louis, Missouri; Los Angeles, Berkeley, San Diego, Richmond, Moffett Field,
and San Francisco, California; and Boston, Massachusetts. On September 19, it was announced that
MSC would be constructed on 1000 acres donated by Rice University southeast of Houston. On
November 1, the STG was officially redesignated the Manned Spacecraft Center, with Gilruth as director.
104 NASA HISTORICAL DATA BOOK
Table 2-2.
Four Phases of Manned Spaceflight
Management, NASA Headquarters*
Phase I
Oct. 1958-Oct. 1961
Director, Space Flight Development (Abe Silverstein); office renamed Space Flight Programs in 1960
Assistant Director, Advanced Technology (Newell D. Sanders); office renamed Applications and
Manned Flight Programs in 1960
Phase lI
Nov. 1961-Winter 1962-1963
Administrator/Deputy Administrator
Associate Administrator
Deputy Director, Launch Vehicles and Propulsion (Stanley M. Smolensky); office added
Aug. 1962
Assistant Director, Launch Vehicle Engineering (Eldon W. Hall; Rosen, acting, 1962)
Assistant Director, Launch Operations (Gus A. D'Onofrio; John K. Holcomb, June 1962)
Chief, Future Projects, Plans, and Evaluations (Waugh, 1962); office dropped in 1962
Assistant Director, Systems Engineering, Vehicle and Spacecraft (Eldon W. Hall); office
renamed Design and Performance in 1962
Assistant Director, Flight Systems (Michael Yarymovych); office added in Oct. 1962
Table
2-2.
FourPhases
of MannedSpaceflight
Management,
NASAHeadquarters*
(Continued)
Assistant
Director,
DesignPractices
andReliability
(JamesE.O'Neill)
Director,
Systems
Studies
(WilliamA.Lee)
Assistant
Director,
Evaluation
Studies
(Douglas R.Lord); officerenamed Systems
Studies
MissionPlanning
inearly1962andthenProgram Planninglaterin1962
Assistant
Director,
Engineering
Studies
(WilliamB.Taylor)
Assistant
Director,
Human Factors
(William
A.Lee)
Assistant
Director,
Space
ScienceStudies(vacant)
Director,
Aerospace
Medicine
(CharlesH.Roadman)
Deputy Director,
Aerospace
Medicine(GeorgeM.Knauf); officeadded inJan.1962
Executive
Assistant
(J.RobertBrown)
Technical
Assistant,
Program ControlandSystems (Alfred
M.Mayo); officedropped
in1962
Assistant
Director,
Analysis
(JamesP.Nolan, Jr.);office
renamed Plans andPrograms
in 1962
Assistant
Director,
Medical
Operations(W.R.Turner; DavidH.Stoddard, 1962)
Assistant
Director,
Advanced Technical
Development (Frank
B.Voris; Joseph Connor,
1962);
officerenamed
TestandEvaluation
in1962
Director,
Program
ReviewandResources Management (WilliamE.Lilly)
Assistants,
ProgramManagment (Secrest
L.BerryandJuanita Hathcock)
Assistant Director, Plans and Resources (William P. Risso)
Director, Integration and Checkout (James E. Sloan; directorate added in Feb. 1962)
Phase III
Administrator/Deputy
Associate Administrator
Table 2-2.
Four Phases of Manned Spaceflight
Management, NASA Headquarters* (Continued)
Table 2-2.
Four Phases of Manned Spaceflight
Management, NASA Headquarters* (Continued)
Phase IV
Sept. 1963-1968
Administrator/Deputy Administrator
Associate Administrator
Special Assistants (Everett E. Christiansen and Joe T. Dickerson); office added in 1964 and
dropped in 1965
Deputy Associate Administrator (Management) (William B. Rieke, Nov. 1964-June 1965; Frank
A. Bogart, Sept. 1965)
Deputy Associate Administrator (Programs) (David M. Jones, Nov. 1964); office dropped in
May 1967
Deputy Associate Administrator (Technical) (Shea, Apr.-July 1%7; Harold T. Luskin, March-
Apr. 1968; Charles J. Donlan, May 1968)
Deputy Associate Administrator, Manned Space Flight Operations (Walter C. Williams,
Nov. l%3-Apr. 1964); office dropped in Apr. 1964
Executive Secretary, Manned Space Flight Experiments Board (Denicke; William O. Armstrong,
1967); briefly during 1965 this function was assigned to the Advanced Manned Mission Program
Office
Deputy to Commander for Space, Manned Space Flight, Air Force Systems Command (AFSC)
(Ritland; Harry L. Evans, 1%6), directorate reduced in size in early 1%7 and dropped later
that year
Assistant Deputy to Commander for Space, Manned Space Flight, AFSC (Shelton); office
dropped in 1964 but reactivated as Assistant Deputy to Commander for Space Systems in early
1967 to oversee reduced operations (Walter R. Hedrick)
Executive Officer (Chickering); office dropped in 1964
Director, AFSC Directorate, NASA Program Support (John M. Coulter, 1964; Harry B. Allen,
1964); office added in 1964; redesignated Chief, NASA Programs Support Division in early
1967
Director, Gemini Program Support (M. P. Yopchick; W. J. Fry, 1%5; Herman Dorfman,
1%6); office dropped in early 1967
Director, Apollo and MOL Program Support (Dorfman, 1965; James E. Miller, 1%7); office
changed to Systems Officer, Apollo and MOL, in 1%7
Director, Advanced Manned Mission Support (Coulter, 1964; Allen, 1964; John R. Burke,
1965; James E. Miller, 1966)
Director, Program Support (Lutman; Yopchick, 1%5; James E. Miller, 1965); office
redesignated Systems Officer, Program Support, in 1967
Director, Biomedical Support (Donald C. Almy, 1964; H. Grady Wise, 1%5); office
redesignated Systems Officer, Biomedical Support, in 1%7
Director, Procurement Processes Support (Alvin E. Greenhorn); office added in 1%5 and
dropped in 1966
Director, Manned Space Flight Field Center Development (Freitag)
108 NASA HISTORICAL DATA BOOK
Table 2-2.
Four Phases of Manned Spaceflight
Management, NASA Headquarters* (Continued)
Deputy Director, Manned Space Flight Field Center Development (Smolensky; Freitag, acting,
1968; V. John Lyle, Aug. 1968); office added in Nov. 1963
Director, Technical Staff (William F. Moore); position called Executive Assistant in 1964-1965,
and Chief, Technical Staff, in 1965-1967
Director, Logistics (Smolensky; office renamed Center Development Planning in 1964 and
dropped in 1965
Director, Manpower (Freitag, acting, 1964-1965; Smolensky, acting, 1966; William J. Bolce,
1967); office renamed Special Operations in 1964 and Special Staff in 1965
Director, Manned Space Flight Program Control (Lilly; Bogart, acting, March 1967; Maynard E.
White, June 1967; Jerald R. Kubat, Jan. 1968)
Director, Facilities Management (Diaz; Maynard E. White, acting, 1967; Harry Mitchell, 1968);
office known as Facilities Programming Construction in 1964-1967; office dropped in 1968
Director, Test Systems Requirements (Lilly, acting, 1965); office operated only briefly in 1965
Director, Manned Space Flight Management Operations (Bothmer; Bogart, Feb. 1965; Cotton,
Sept. 1965; White, Jan. 1968)
Director, Management Assistant and Personnel (William R. Sweeny; C. C. Coyne, 1965); office
added in 1964
Director, Procurement Management (M. J. Barkdull Kahao; Charles J. Bingman, July 1966;
Cotton, acting, June 1967; William P. Davis, 1968)
Director, Space Medicine (Knauf, acting; W. Randolph Lovelace, II, Apr. 1964; Jack Bollerud,
acting, Feb. 1966; James W. Humphreys, June 1967)
Deputy Director, Space Medicine (Knauf, Apr.-Dec. 1964; Bollerud, June 1965-June 1967); of-
fice dropped in 1967
Director, Medical Science and Technology (Sherman P. Vinograd); office called Professional
Services in 1963-1964
Director, Medical Operations (Knauf, acting; vacant, 1965-1966); office dropped in 1966
Director, Lunar Receiving Operations (John Pickering); office added in 1966; earlier that year
Picketing held the post Special Assistant to Director, Space Medicine
Director, Gemini Program (Low, acting; Mueller, acting, 1965-1968); directorate was downgraded
in early 1967 and disbanded entirely in 1968
Special Assistant (Samuel H. Hubbard); Hubbard continued in this post until the directorate
was disbanded in 1968
Deputy Director, Gemini Program (William E. Schneider; LeRoy E. Day, acting, Oct. 1965;
John A. Edwards, July 1966)
Director, Program Control (Richard C. Henry; Anthony L. Liccardi, acting, 1964; J. Pemble
Field, 1965; William A. Summerfelt, acting, 1965)
Table 2-2.
Four Phases of Manned Spaceflight
Management, NASA Headquarters* (Continued)
Director, Test (Day; Charles W. McGuire, acting 1965-1966; Clarence C. Gay, Jr., 1966)
Director, Flight Operations (Edwards; Hubbard, July 1966)
Director, Reliability and Quality (Dwight C. Cain; Schneider, acting, 1965; Day, 1965-1966; Ed-
wards, July 1966)
Director, Apollo Program (Mueller, acting; Samuel C. Phillips, Oct. 1964)
Deputy Director, Apollo Program (Phillips, Jam-Oct. 1964; Lee B. James, Feb. 1967; George
H. Hage, Jan. 1968)
Deputy Director (Programs) (Turnock); office added in 1966 and dropped in 1968
Deputy Director (Engineering) (Hage, Oct. 1967-Jan. 1968; William E. Stoney, Sept. 1968); of-
fice added in 1967
Special Assistant (Operational Readiness) (Harold G. Russell); office added in 1966 and
dropped in 1967
Special Assistant (Allen Jones); office operated only briefly in 1967
Assistant Director (Management) (Thomas E. Jenkins); office added in Feb. 1968
Mission Director (Schneider); office added in July 1967
Assistant Mission Directors (Chester M. Lee, Aug. 1966-1968; and Thomas H. McMullen,
1968); both men served as assistant directors in 1968
Director, Program Control (Phillips, acting, 1964; Milo L. Seccomb, 1965; Kubat, July 1967;
James B. Skaggs, Jan. 1968)
Director, Test (Disher; Melvyn Savage, Aug. 1965; Day, July 1966)
Director, Flight Operations (Williams, acting; Holcomb, Nov. 1963)
Director, Reliability and Quality Control (Turnock; George A. Lemke, 1964; George C. White,
Jr., Nov. 1966)
Director, Apollo Lunar Exploration (Lee R. Scherer); directorate added in Dec. 1967; the
several assistant directorships were added during 1968
Assistant Director, Flight Systems Development (William T. O'Bryant)
Assistant Director, Lunar Science (R. J. Allenby)
Assistant Director, Lunar Sample Program (Benjamin Milwitsky)
Assistant Director, Lunar Sample Program (Verl R. Wilmarth)
Director, Advanced Manned Missions Program (Edward Z. Gray; George S. Trimble, Apr. 1967;
Lord, acting, Oct. 1967; Cortright, acting, early 1968; Donlan, acting, May 1968)
Executive Assistant (William A. LaRue)
Deputy Director, Advanced Manned Missions Program (Lord); office added in Nov. 1966
NASA-USAF Technical Director, MOL (Yarymovych); office added in 1965 and dropped in
1968
Table 2-2.
Director, Systems Engineering (Lord, Eldon W. Hall, Nov. 1966; Brian T. Howard, Dec. 1967)
Director, Manned Space Flight Advanced Technology (William D. Greene); office dropped in
1965
Director, Vehicle Studies (Lester K. Fero; A. Daniel Schnyer, March 1965); office renamed
Transportation Systems in 1968
Director, Earth Orbital Mission Studies (Yarymovych, acting; Maurice J. Raffensperger, 1974);
office dropped in March 1968
Director, Lunar Mission Studies (Thomas C. Evans, acting; Franklin P. Dixon, acting, Feb.
1965; Thomas E. Hanes, spring 1965; Philip E. Culbertson, Sept. 1965; P. Grosz, May 1967);
office dropped in March 1968
Director, Planetary Mission Studies (Lord, acting; Dixon, June 1964); office dropped in March
1968
Director, Experiments (Lord, acting; Armstrong, 1967); office added in 1965 and renamed
Payloads in March 1968
Executive Secretary, Manned Space Flight Experiments Board (Denicke); office added in sum-
mer 1965, but by year's end it was moved back to the direct purview of the Associate Ad-
ministrator for Manned Space Flight
Director, Mission Planning and Operations (Raffensperger; Lord, acting, Apr. 1968; Jack W.
Wild, winter 1968); office added in March 1968
Director, Mission Operations (Christensen; John D. Stevenson, Feb. 1967); directorate added in
Jan. 1965
Executive Assistant (Joseph W. Cover; L. K. Abernethy, acting, winter 1967; Archer W. Kinny,
1968)
Deputy Directors, Mission Operations (Carroll H. Bolender, Schneider, and Roderick O. Mid-
dleton); offide added in 1966 and dropped in mid-1967
Mission Directors (Bolender, Jan. 1965-early 1966; and Robert Thompson, June 1965-early
1966); this office was dropped in early 1966 and the mission director function transferred to the
various program offices
Assistant Mission Director (Apollo) (Chester M. Lee); this office was briefly part of Mis-
sion Operations in 1967; function was assumed by the Apollo Program Office
Chief, Ground Operations Support Systems (William E. Miller); office renamed Information
and Control Systems in 1967
Chief, Flight Crew Support (Reuben P. Prochard, Jr.; Thomas U. McElmurry, 1965; John Pro-
dan, 1967)
Chief, Operations Planning (Chester M. Lee, Aug. 1965-July 1966; Nolan, mid-1967 to
mid-1968); office added in Aug. 1965
Director, Saturn/ Apollo Applications (Harold G. Russell; David M. Jones, acting, mid-1965;
Mathews, Dec. 1966; Luskin, May 1968); directorate added in Apr. 1965 as the Saturn IB/Centaur
Program; it was renamed and expanded later in 1965 and then renamed again in late 1967 to
Apollo Applications Program
Table 2-2.
Four Phases of Manned Spaceflight
Management, NASA Headquarters* (Continued)
Director, Apollo Extension Systems (Taylor; Culbertson, May 1967); office renamed Project
Integration in mid-1967
Director, Systems Engineering (Bellcomm) (P. L. Havenstein; George M. Anderson, acting,
1966; Donald R. Hagner, 1967)
Director, Manned Space Flight Safety (Jerome Lederer); directorate added in June 1967
Deputy Director, Manned Space Flight Safety (Philip H. Bolger); office added in Nov. 1967
*These four phases represent composites for each time period. Refer to Appendix A and other NASA
historical publications for complete organization charts. Phase four (Sept. 1963-1968) includes many offices
whose existence was short-lived within the 11 OMSF directorates; extra information has been included to in-
dicate when these offices were added or dropped.
112 NASA
HISTORICAL DATA BOOK
Table 2-3.
Phase I
1959-Oct. 1961
Important points regarding Phase I: The first organization chart drawn up for the Space Task Group was
dated Sept. 1959, but it was functioning as an organization by Oct. 7, 1958. The third chart (Sept. 1960)
gave Faget's flight systems division responsibility for Mercury and Apollo. Astronaut activities were
directly under the office of the director. Reporting to the Flight Systems Division were the following
branches: electrical systems, flight dynamics, life systems, systems engineering, and structures. Reporting
to the Engineering and Contract Administration Division were branches for contracts and scheduling and
project engineering. Four branches added to the Operations Division in 1960 managed mission analysis,
flight control, recovery operations, and launch operations. Although an Apollo office was established in
Sept. 1960, a manager for that office was not selected until the next major reorganization.
MANNED
SPACEFLIGHT 113
Table 2-3.
Six Phases of Space Task Group-
Manned Spacecraft Center Organization, 1959-1968
Phase II
Nov. 1961-1962
Director (Gilruth)
Associate Director (Williams)
Special Assistant (Purser)
Executive Assistant (Zavasky)
Technical Assistant (Don T. Gregory)
Assistant, Human Factors (Voas)
Special Assistant, Astronaut Affairs (Ford Eastman); office added in June 1962
Manager, Mercury Program Office (Kenneth S. Kleinknecht)
Manager, Gemini Project Office (Chamberlin)
Manager, Apollo Program Office (Charles W. Frick)
Assistant Director, Administration (Wesley L. Hjornevik)
Assistant Director, Research and Development (Faget)
Chief, Spacecraft Research Division (Mathews)
Chief, Life Systems Division (White)
Chief, Systems Evaluation and Development Division (Bond)
Chief, Space Physics Division (vacant)
Assistant Director, Operations (Mathews; vacant, Jan. 1962)
Chief, Aerospace Medical Operations (Charles A. Berry)
Chief, Preflight Operations (Preston)
Chief, Flight Operations Division (Kraft)
Chief, Flight Crew Operations (Warren J. North)
Important points regarding Phase II: This phase represents the Space Task Group's reorganization as the
Manned Spacecraft Center. Offices for the three flight programs stood alone outside the directorates.
During this period, Kraft's Flight Operations Division in the operations directorate grew dramatically as
the center readied for Mercury's first orbital missions. Astronaut training was part of flight crew opera-
tions in the operations directorate. An assistant director for engineering support with four chiefs assigned
to him was carried on the operations directorate's organization chart during this period, but the positions
were not filled.
1 14 NASA HISTORICAL DATA BOOK
Table 2-3.
Six Phases of Space Task Group-
Manned Spacecraft Center Organization, 1959-1%8 (Continued)
Phase III
Spring-Fall 1963
Director (Gilruth)
Manager, Apollo Program Office (Robert Piland, acting; Joseph F. Shea, Oct. 1963)
Important points regarding Phase III: The spring 1963 reorganization was an attempt to divide MSC's
operational activities from its developmental work. Crew, flight, preflight, and medical operations all fell
under the supervision of the director.
MANNED SPACEFLIGHT 115
Table 2-3.
Six Phases of Space Task Group-
Manned Spacecraft Center Organization, 1959-1968 (Continued)
Phase IV
Nov. 1963-1965
Director (Gilruth)
Deputy Director (Elms; George M. Low, Feb. 1964)
Special Assistant (Purser)
Senior Engineering Advisor (Chamberlin); office dropped in late 1964
Executive Assistant (Zavasky, Nov. 1963-1ate 1964; Stanley P. Weiss, acting, 1965); office dropped in
1965
Technical Assistant (Gregory, Nov. 1963-1ate 1964; Weiss, 1965); office dropped in 1965
Manager, Gemini Program Office (Mathews)
Table 2-3.
Six Phases of Space Task Group-
Manned Spacecraft Center Organization, 1959-1%8 (Continued)
Manager, MSC Florida Operations (Preston); office dropped in Dec. 1964 when the Kennedy
Space Center assumed the duties
Important points regarding Phase I V: With a Nov. 1963 reorganization, MSC settled back into the three-
directorate pattern (plus the administrative directorate). Mercury personnel were reassigned elsewhere
(primarily to Gemini and Apollo). The engineering and development directorate expanded noticeably.
Astronaut Slayton became assistant director for a new flight crew operations directorate, and Kraft, with
his growing flight operations team, assumed leadership of the operations directorate. Two separate of-
fices were established to handle life sciences matters: center medical programs and center medical office.
Two offices directed off-site operations at the Cape and at White Sands.
Phase V
1966-1%7
Director (Gilruth)
Special Assistant, Long-Range Planning (Julian M. West); office briefly called Advanced
Spacecraft Planning in early 1966
Executive Assistant (M. Scott Carpenter; vacant, May 1%6); office dropped in mid-1966
Assistant Manager(s), Apollo Spacecraft Program Office (Lee, Jan. l%6-spring 1967; Kotanchik,
Jan.-mid-1966; Markley, spring 1967; Kleinknecht, spring-summer 1%7)
Manager, Lunar Module (Lee; C. H. Bolender, fall 1967); office added in spring 1967
Manager, Command and Service Module (Kleinknecht); office added in Feb. 1%7
Chief, Systems Engineering (Maynard; Robert W. Williams, spring 1%6; Maynard, fall 1967)
Chief, Reliability, Quality, and Test (Morris; Bland, spring 1966; Donald D. Arabian, late 1967);
called Reliability and Test in early 1966, while a separate office attended to Checkout and Test
(Bland); the two were combined in spring 1966 under Bland
Chief, Lunar Module Project Engineering and Checkout (Morris); office added in spring 1966
MANNED SPACEFLIGHT 1 17
Table 2-3.
Six Phases of Space Task Group-
Manned Spacecraft Center Organization, 1959-1968 (Continued)
Chief, Command and Service Module Project Engineering and Checkout (Lanzkron); office added
in spring 1966
Chief, Mission Operations (Maynard); office added in spring 1966
Chief, Mission Support (A.D. Mardel); office added in 1967
Chief, Test Division (Mardel); office added in fall 1967 in addition to Reliability, Quality, and Test
under Bland
Manager, Apollo Applications Program Office (Low, acting; vacant, Apr.-Nov. 1967; Thompson,
Dec. 1967); office added in July 1966 and expanded in early 1967
Table 2-3.
Chief, Lunar and Earth Sciences Division (vacant; Persa R. Bell, fall 1967)
Chief, Test and Operations Office (Norman G. Foster)
Director, Medical Research and Operations (Berry); office established in May 1966 (Berry was Chief,
Center Medical Programs for the first four months of 1966)
Chief, Occupational and Environmental Medicine Office (Coons, acting; Edward L. Beckman,
mid-1966)
Manager, Lunar Receiving Laboratory Program (Joseph V. Piland, fall 1966); office dropped in 1967;
the laboratory was briefly part of the engineering and development directorate when it was established in
spring 1966 (James C. McLane, Jr., acting manager)
Important points regarding Phase IT..-The 1966-1967 period brought several important changes to MSC.
Management of Project Apollo was assumed by George Low in 1967, who instituted some organizational
changes in the program office. Project Gemini met its final objectives in Nov. 1966. An Apollo applica-
tions office was established to investigate how the agency might use the Apollo spacecraft in the future.
Charles Berry became the assistant director of a new medical research and operations directorate, which
centralized the center's several life sciences interests in one office.
Phase VI
1968
Director (Gilruth)
Table 2-3.
Table2-3.
SixPhases
ofSpace TaskGroup-
Manned
Spacecraft
Center
Organization, 1959-1%8 (Continued)
Manager, Advanced Systems (Pearce; Jackson, mid-1968); office dropped in late 1968
Manager, Mapping Sciences Laboratory (James H. Sasser, acting)
Director, Medical Research and Operations (Berry)
Deputy Director, Medical Research and Operations (A. D. Catterson)
Deputy Director, Medical Requirements (Coons)
Assistant Director, Research (Dietlein)
Chief, Biomedical Research (Dietlein; Beckman, mid-1968)
Chief, Preventive Medicine (John J. Dreoscher, Jr.; Walter K. Kemmerer, Jr., mid-1968)
Chief, Medical Operations (Hawkins)
Head, Biomedical Technology Group (George G. Armstrong, Jr.)
Director, Flight Crew Operations (Slayton)
Chief, Astronaut Office (Shepard)
Chief, Aircraft Operations Office (Algranti)
Chief, Flight Crew Support Division (North)
Director, Flight Operations (Kraft)
Deputy Director, Flight Operations (Sjoberg)
Chief, Flight Control Division (Eugene F. Kranz, acting)
Chief, Landing and Receiving Division (Hammock)
Chief, Mission Planning and Analysis Division (Mayer)
Chief, Flight Support Division (Dunseith)
Director, Lunar Exploration Working Group (Hodge); office added in Sept. 1968
Manager, MSC White Sands Test Facility Operations (Raines)
Important points regarding Phase VI: During 1968, Gilruth reorganized the center's administrative staff
arm. Wesley J. Hjornevik, long-time assistant director for administration at MSC, became associate
director, with directors for administration and program control reporting to him. An advanced program
office was added to explore mission possibilities beyond the Apollo era. Faget got the help of three as-
sistant directors in managing the multifaceted engineering and development directorate.
* These six phases represent composites for each time period. Refer to appendix A and other NASA
historical publications for complete organization charts (especially helpful for the early years is "Key
Management Progression involving Project Mercury," app. 8, James M. Grimwood, Project Mercury: A
Chronology, NASA SP-4001 (Washington, 1963), pp. 215-21). These-six phases emphasize operational
and developmental activities rather than administrative and staff activities. See the notes following each
phase for a summary of the important changes for each time period.
MANNED SPACEFLIGHT 121
BUDGET
For general information on the NASA budget and the budget charts in this
book, consult chapter 1, pages 7 to 11. Other charts that may assist the researcher in-
terested in the cost of NASA's manned spaceflight program include budget tables in
chapter 1 for Atlas, Atlas-Agena, Jupiter, Little Joe I, Little Joe II, Redstone,
Saturn I, Saturn IB, Saturn V, and Titan II; see chapter 4 for budget tables for Scout
Reentry Heating Project, Project FIRE, lifting bodies, Project RAM, human factor
systems, and X-15; chapter 5 provides budget information for manned flight track-
ing network operations and manned network equipment and components. For a
more detailed breakdown of the flight project budgets, consult the NASA annual
budget estimates. Review the bottom notes of the following charts carefully before
making conclusions about totals for any particular project or year.
The total cost of NASA's manned spaceflight programs and in particular the
cost of the lunar landing, is a figure sought frequently by friends and foes of the
agency. Because it was such a huge undertaking with a fixed deadline and because it
demanded quantum state-of-the-art leaps in several fields (especially computeriza-
tion and miniaturization), the costs were high. Totals for any one program are hard
to determine, but NASA issued the following figures for its major manned ventures:
Mercury, $392.6 million; Gemini, $1.283 billion; and Apollo, $25 billion ($21.35
billion through the first lunar landing in July 1969). If we add another $2.6 billion
for Skylab and $250 million for the Apollo-Soyuz Test Project, the grand total for
the "expendable-generation" manned spaceflight program was $29.5 billion. _1 These
totals include facilities, salaries, research and development, operations, and hard-
ware (spacecraft and launch vehicles) expenditures. The following charts are con-
cerned with only OMSF research and development monies (spacecraft, some launch
vehicle costs, and supporting development).
122 NASA HISTORICAL DATA BOOK
Table 2-4.
Total Manned Spaceflight Costs
(in thousands of dollars)
alncludes $124 330 000 for Project Mercury, and $6 266 000 for advanced manned spaceflight.
b Includes $13 259 000 for Project Mercury, and $863 628 000 for advanced spaceflight.
c The OMSF budget for FY 1964 was divided among manned spacecraft systems (see following charts),
launch vehicle and propulsion systems (see chapter 1), aerospace medicine (request, $16 700 000;
authorization, $11 000000), integration and checkout (request, $153 000000; authorization,
$125 000 000); and systems engineering (request and authorization, $37 000 000). The budget was usually
divided among the various flight projects (Mercury, Gemini, Apollo, and advanced programs).
MANNED SPACEFLIGHT 123
_o
e_o
0 0
I
124 NASA HISTORICAL DATA BOOK
Table 2-6.
Total Mercury Funding History
(in thousands of dollars)
aln the FY 1961 and FY 1962 budget estimates, the Mercury budget was in two parts: advanced
technical development and flight research.
bIncludes $16 460 000 for a "one-day mission," a Mercury mission of longer duration than the initial
flights. At one time, four such missions were planned for 1963. MA-9, lasting more than 34 hours, was
considered the Mercury one-day mission, but the designation was not widely used.
CIncludes $12 180 000 for the "one-day mission" from the advanced manned spaceflight budget; see
note "b" above.
dNot included as an item in the FY 1965 budget estimate, however, it was estimated in the FY 1964
budget estimate that $3 342 000 and $17 957 000 would be programmed in FY 1963 for Mercury and a
"one-day mission," respectively. No funds were programmed after FY 1963.
Table 2-7.
Mercury-Spacecraft Funding History
(in thousands of dollars)
aThe Mercury budget was not itemized in the FY 1964 budget estimate; total programmed was
$31 060 000, which included funds for a "one-day mission."
blncludes $4 500 000 from the advanced manned spaceflight budget for a "one-day mission."
¢Does not include funds for a "one-day mission."
dMercury was not included as an item in the FY 1965 budget estimate. It was estimated in the FY 1964
budget estimate that $21 299 000 would be programmed for Mercury for FY 1963, which included funds
for a "one-day mission." No funds were programmed after FY 1963.
MANNED SPACEFLIGHT 125
Table 2-8.
Mercury-Operations Funding History
(in thousands of dollars)
1959 ...... 7a
1960 ...... 3193 b
1961 39 670 c --- 30 283 d
1962 28 235 e ...... f
1963 13 370 g 5690 a __i
Table 2-9.
Mercury-Supporting Development Funding History
(in thousands of dollars)
alncludes $170 000 for biological and human engineering studies, and $3 100 000 for a Mercury
development program.
b For advanced technical development.
c Includes $2 090 000 for biological and human engineering studies, $4 050 000 for a Mercury develop-
ment project, $800 000 for advanced reentry configuration development, and $200 000 for reentry
guidance and control system technical development.
dThe Mercury budget was not itemized in the FY 1964 budget estimate. Total programmed was
$31 060 000, which included funds for a "one-day mission." No funds were programmed after FY 1962.
126 NASA
HISTORICAL DATA BOOK
Table 2-10.
Mercury-Launch Vehicles Funding History
(in thousands of dollars)
"The Mercury budget was not itemized in the FY 1904 budget estimate. Total programmed was
$31 060 000, which included funds for a "one-day mission." No funds were programmed after FY 1962.
Table 2-11.
Total Gemini Funding History
(in thousands of dollars)
Table 2-12.
Gemini-Spacecraft Funding History
(in thousands of dollars)
Table2-13.
Gemini-Operations
andSupportFunding
History
(inthousands
ofdollars)
Year Request Authorization Programmed
Table 2-14.
Gemini-Launch Vehicles Funding History
(in thousands of dollars)
Table 2-15.
Total Apollo Funding History
(in thousands of dollars)
aThe first request for Apollo submitted to Congress was for $29 500 000; the request was increased in
response to the presidential mandate that NASA land a man on the moon by the end of the 1960s.
bFrom the advanced manned spaceflight budget; there was no item labeled "Apollo" in the FY 1963
budget estimate.
c$60 000 000 was available in unobligated funds to finance Apollo, bringing the actual request to
$2 546 500 000.
dThe sum was further reduced to $2 496 000 000 by the Appropriations Conference Committee on
Table 2-16.
Table 2-17.
Apollo--Spacecraft, Lunar Module Funding History
(in thousands of dollars)
Table 2-18.
Apollo-Spacecraft, Other Costs, Funding History
(in thousands of dollars)
Table 2-19.
Apollo-Operations Funding History
(in thousands of dollars)
Table 2-20.
Apollo-Supporting Development Funding History
(in thousands of dollars)
alncludes $63 900000 for orbital flight tests, $16 550000 for biomedical flight research, and
$27 550 000 for high-speed reentry tests.
b For systems engineering, mission control systems, and supporting technology and development.
c Includes $25 000 000 for supporting development, and $2 292 000 for research and development
facilities.
d Includes systems engineering and supporting development.
Table 2-21.
a Most of the OMSF launch vehicle and propulsion systems budget in the FY 1964 estimate was devoted
to Apollo launch vehicle and engine development.
b From the advanced manned spaceflight budget.
MANNED SPACEFLIGHT 131
Table 2-22.
Total Apollo Applications Funding History
(in thousands of dollars)
Table 2-23.
Apollo Applications-Space Vehicles Funding History
(in thousands of dollars)
alt was estimated in the FY 1969 budget estimate that $86 000 000 would be programmed for Apollo
applications space vehicles in FY 1968.
Table 2-24.
Apollo Applications--Mission Support Funding History
(in thousands of dollars)
alt was estimated in the FY 1969 budget estimate that $28 200 000 would be programmed for Apollo
applications mission support in FY 1968.
132 NASA HISTORICAL DATA BOOK
Table 2-25.
Apollo Applications--Experiments Funding History
(in thousands of dollars)
a It was estimated in the FY !969 budget estimate that $I 39 000 000 would be programmed for Apollo
applications experiments in FY 1968.
Table 2-26.
Total Advanced Missions Funding History
(in thousands of dollars)
aNot included as a line item in the FY 1970 budget estimate. It was estimated in the FY 1969 budget
estimate that no funds would be programmed for the advanced missions program in FY 1968.
MANNED
SPACEFLIGHT 133
Table2-27.
Manned
Spaceflight-Other
Costs
Funding
History
(in thousands of dollars)
a From the advanced manned spaceflight budget: $2 020 000 for manned spaceflight technology, and
$4 246 000 for aerospace medicine.
blncludes $5 164000 for manned spacecraft systems supporting research and technology,
$386 153 000 for launch vehicle and propulsion systems, $7 854 000 for aerospace medicine, $1 250 000
for integration and checkout, and $992 000 for systems engineering.
c From the advanced manned spaceflight budget: $11 764 000 for manned spacecraft technology, and
$19 320 000 for aerospace medicine.
dThe following are estimates as per the FY 1964 budget estimate (these categories did not appear as
items in the FY 1965 estimate): aerospace medicine, $7 000 000; integration and checkout, $38 500 000;
systems engineering, $26 500 000; mission control center operations, $10 500 000; supporting research
and technology, $8 100 000; and launch vehicle and propulsion systems, $734 057 000.
elncludes $21 100 000 for manned spacecraft systems research and technology, $21 800 000 for mis-
sion control center operations, $1 168 500 000 for launch vehicle and propulsion systems, $153 000 000
for integration and checkout, $37 000 000 for systems engineering, and $16 700 000 for aerospace
medicine.
fThe authorization for launch vehicle and propulsion systems was $1 147 500, for aerospace medicine
$11 000 000, and for integration and checkout $125 000 000. For other categories the authorizations were
the same as the request (as per note "e" above).
gThese several categories were assumed by the Gemini and Apollo budgets as per the FY 1965 budget
estimate.
134 NASA HISTORICAL DATA BOOK
CHARACTERISTICS-PROJECT MERCURY
Project Mercury's goals were simply stated in 1958 when it was officially chosen
as this country's first step toward manned spaceflight: (1) launch a manned
spacecraft into earth orbit; (2) assess man's performance capabilities and his ability
to function in the space environment; and (3) recover the pilot and spacecraft safely.
In developing the ballistic-shaped spacecraft, NASA proposed to rely on existing
technology and off-the-shelf equipment when practical and to follow the simplest,
most reliable approach to system design.i2 These guidelines, of course, echoed the
advice of engineers at the Langley Research Center who had been studying the
feasibility of sending man into orbit in a nose cone-type spacecraft months prior to
NASA's organization in October 1958 (see discussion above). Designer Maxime
Faget and his colleagues favored the Air Force's Atlas missile for a Mercury launch
vehicle, and suggested a test program for both the spacecraft and the booster that
would guarantee that the hardware was "man-rated."
Mercury was not the sleek, sophisticated-looking craft that most dreamers of
manned flight would have designed. It was small (1 cubic meter in the crew compart-
ment), a blunt cone with zero lift (2.1 meters at its widest, 3.4 meters nose to
retrorocket), and at launch it perched atop a modified ICBM. If some thought it an
ignoble way to fly-"the man in the can"-those same critics probably paled at the
thought of reentering earth's atmosphere on their backs protected by a heat shield in
preparation for a splash-down in the ocean (see figs. 2-1 and 2-2). But it was the only
approach to manned flight that could be supported by existing launch vehicles.
Boosters powerful enough to send "space planes" into orbit were still decades away.
(See table 2-28 for a chronology of key Project Mercury events.)
To prepare for the first orbital mission, originally scheduled for 1960, NASA
personnel in the Space Task Group (redesignated the Manned Spacecraft Center in
1961 and moved from Langley Research Center in Virginia to Houston, Texas)
devised a hardware test plan that called for ground simulations and flight tests. Mer-
cury's heat shield and basic reentry attitude had to be proved, as did its environmen-
tal control system and other critical subsystems. In addition to evaluating changes
made to the basic Atlas missile, propulsion experts were charged with designing a
launch escape system that would carry the manned capsule away from a malfunc-
tioning launch vehicle and a retrorocket system capable of supplying the impulse
necessary to bring the spacecraft out of orbit for return to earth. Beyond laboratory
and wind tunnel tests of these Mercury features conducted at the Langley, Ames,
and Lewis centers, the Space Task Group relied on ballistic flights to qualify hard-
ware. Rather than depend exclusively on the more expensive Atlas for test flights,
NASA procured eight Redstone missiles from the Army Ballistic Missile Agency and
awarded North American Aviation a contract to build airframes for a new Mercury
test launcher, the Little Joe I.* Suborbital launches of Mercury spacecraft
boilerplate models using Little Joe began in 1959 at Wallops Island. The spacecraft
abort system was not qualified under maximum dynamic pressure with Little Joe un-
*NASA had originally planned to also include the Army's Jupiter missile in the Mercury test flight
scheme but dropped the requirement in favor of exclusive use of Redstone for suborbital missions. The
solid propellant Little Joe was used primarily to test the spacecraft abort system. (Seechap. 1 for more in-
formation on the Mercury launch vehicles.)
MANNED SPACEFLIGHT 135
ESCAPE TOWER
RECOVERY
COMPARTMENT
3.34
PRESSURIZED
RETROGRADE
PACKAGE
_1.89
Figure 2-1. Mercury Spacecraft (dimensions in meters). The exterior shape of the Mercury spacecraft
was conical, with a segment of a sphere for the heatshield and a cylindrical afterbody at the apex
of the cone. Two crew access hatches were included, one for entrance and egress on the side of
the spacecraft and the other for exit through the cylindrical section. A large window and an instru-
ment panel were provided for crew monitoring of flight events and systems operation. Thermal pro-
tection was provided by an ablative heatshield on the blunt face and radioactive-type shingles on
the afterbody. Environmental control was made possible in part by evaporative cooling in two separate
circuits, one for the cabin and one for the astronaut's suit. A stabilization and control system with
a three-axis gyro package erected by horizon scanners provided attitude references for the displays
and the two automatic control modes. Attitude changes were effected through a redundant system
of hydrogen peroxide-fueled reaction control engines. Three silver-zinc batteries were the source of
electrical power. Reentry retrofire maneuvers were accomplished by three solid-fuel rockets. (See
also tables 2-54 and 2-55 for more information on the spacecraft and its major subsystems.)
136 NASA HISTORICAL DATA BOOK
.5
_o__ I.l.I kl.I
c_
(.9 O0
121 ZZ_Z
0 mz_o
_-_ .Z I-
Z -...1
_ ",m
_ <_'£
en II1 ,_ oO Z t.l.l --
x _t_
z_5,x
_.1 uJ
_w
o
On.
_0
_Zo3
z
O
a to
I--
rr"
o
CO
kl_
o
-1-
I---
_J
I---
w (D I--I ,,,
_Z,--- r,.-
O
¢O c"q b
° o
_- ,,--_ _oz ,'," _
w_
MANNED SPACEFLIGHT 137
til April 1961 (Lj-5B). _3 From the Eastern Test Range (formerly the Atlantic Missile
Range) in Florida, the first attempt to launch a Mercury production capsule in a
qualification flight ended in a malfunction of the Atlas vehicle in February 1961
(MA-2). The first successful orbital test took place seven months later in September
(MA-4), followed by an all-systems two-orbit test flight in November (MA-5).
Redstone also malfunctioned during its first Mercury test in November 1960
(MR-l), but performed more satisfactorily one month later (MR-1A). Redstone
boosters would send NASA's first astronauts into space on suborbital missions in
1961. (See table 2-29 for a list of Mercury development flights.)
Manufacture of the spacecraft was assigned to McDonnell Aircraft Corporation
in January 1959, one of 11 firms to submit proposals to NASA (see table 2-56 for a
list of major contractors). STG personnel were assigned to the contractor's facilities
in St. Louis, where they worked together to produce 20 Mercury spacecraft. The
builders of the spacecraft had to allow for the incorporation of a life support system
(100 percent oxygen supplied as a gas at a pressure of 258 mm mercury, with
removal of carbon dioxide and humidity by lithium hydroxide canisters) and flight
couches that conformed to each astronaut's body. The inclusion of redundant
systems and manual as well as automatic controls where possible was another impor-
tant requirement. 14 McDonnell delivered the last spacecraft to the launch complex in
April 1963.*
Qualifications for astronauts to man Mercury spacecraft were first established
in January 1959: a candidate had to be under 40 years of age, less than 180 cen-
timeters (5'11'3 tall, in excellent physical condition, holder of a bachelor's degree or
its equivalent, a graduate of test pilot school, and a qualified jet pilot with 1500
hours of flight time. From the files of 508 military test pilots, a NASA committee
found 110 apparently qualified candidates, of which 69 were interviewed. Of these,
56 took a battery of written exams; 32 were left in March to undergo mental and
physical testing. By April, the field had been narrowed to 7 men, who reported to
the Space Task Group at Langley for training.t The astronaut training program in-
*This capsule was to have been used for MA-10, which was cancelled in June 1963.
tThe NASA astronaut candidate evaluation committee was led by Charles Donlan, assistant director of
the STG. He was assisted by Warren North, a test pilot-engineer, Stanley C. White and William S. Auger-
son, flight surgeons, Allen O. Gamble and Robert B. Voas, psychologists, and George E. Ruff and Edwin
Z. Levy, psychiatrists. The Lovelace Foundation for Medical Education and Research, Albuquerque,
New Mexico, and the Aeromedical Laboratory, Wright Air Development Center, Dayton, Ohio, were
used to conduct many of the physical tests during the evaluations; NASA specialists were supported by
military medical personnel. STG Director Gilruth endorsed the final list of seven candidates and passed it
to Abe Silverstein, director of space flight development, and Administrator Keith Glennan for final
review in April 1959. The Mercury astronauts named later that month were M. Scott Carpenter (Lt.,
Navy), L. Gordon Cooper (Cpt., USAF), John H. Glenn, Jr. (Lt. Col., USMC), Virgil I. Grissom (Cpt.,
USAF), Walter M. Schirra, Jr. (Lt. Com., Navy), Alan B. Shepard, Jr. (Lt. Com., Navy), and Donald K.
Slayton (Cpt., USAF).
Medical personnel played an important part during astronaut training. They measured, monitored,
or tested every bodily function, component, and product. To monitor the astronaut's body temperature
(with a rectal thermistor), respirations (with a pneumograph on MA-8 and MA-9), heart action (with elec-
trocardiographic electrodes), and blood pressure (with a unidirectional microphone and cuff during
MA-7, MA-8, and MA-9) during flight, new biomedical sensors were developed. To supplement this
data, the flight surgeon could also evaluate the astronaut's actions, his voice quality, and his answers to
specific questions. Scientists and doctors were especially interested in determining man's physiological
responses to weightlessness, acceleration and deceleration forces, radiation, and stress.
138 NASA HISTORICAL DATA BOOK
As discussed above, the Space Task Group was established in 1958 to manage
Project Mercury. Even though the team was located at Langley Research Center,
Robert Gilruth, leader of the group, reported directly to NASA Headquarters. The
STG was declared an independent operation in January 1961 and was assigned a new
name and a permanent home in November, the Manned Spacecraft Center, in
Houston, Texas. James Chamberlin as engineering chief and chair of the Capsule
Coordination Committee assumed a large share of the project's management in
1959. In a reorganization in November 1961, Kenneth Kleinknecht became manager
of the Mercury Program Office. He was assisted by chiefs for engineering opera-
tions, project engineering, and engineering data and measurement (see also table 2-3
for information on the changing organization of STG-MSC).
Three useful sources for the reader interested in Project Mercury are the follow-
ing NASA publications: Loyd S. Swenson, Jr., James M. Grimwood, and Charles
C. Alexander, This New Ocean; A History of Project Mercury, NASA SP-4201
(Washington, 1966); Grimwood, Project Mercury; A Chronology, NASA SP-4001
(Washington, 1963); and NASA, Mercury Project Summary including Results of the
Fourth Manned Orbital Flight, May 15 and 16, 1963, NASA SP-45 (Washington,
1963). The summary volume is a compilation of papers given at the October 3-4,
1963, Mercury conference held in Houston.
Table 2-28.
Chronology of Key Project Mercury Events*
Date Event
Oct. 6, 1958 Langley Research Center personnel opened negotiations with the Army
Ballistic Missile Agency (ABMA) to procure Redstone and Jupiter launch
vehicles for a manned satellite project; on the 17th they began discussions
with the Air Force Ballistic Missile Division regarding procurement of Atlas
vehicles.
Oct. 7, 1958 NASA Administrator T. Keith Glennan approved plans for a manned
satellite project.
Oct. 21, 1958 A bidders conference was held concerning a Little Joe launch vehicle to be
used for development testing of the manned capsule. Design work was com-
pleted by December 1.
Oct. 23, 1958 Preliminary specifications for a manned spacecraft were distributed to in-
dustry. Another set of specifications was mailed on Nov. 14 to 20 firms that
wanted to be considered bidders. Deadline for proposal submission was
December 11.
Nov. 5, 1958 The Space Task Group (STG) was officially formed at Langley to manage the
manned program.
Nov. 14, 1958 NASA requested DX priority procurement rating for the manned spacecraft
project, which was accorded on April 27, 1959.
Nov. 24, 1958 The STG ordered one Atlas launch vehicle for a development launch of a
boilerplate spacecraft model (Big Joe); nine Atlas vehicles would be required
according to a December 8 memo. A total of 15 had been approved by FY
1962.
Nov. 26, 1958 The name "Mercury" was agreed on for the manned project.
Dec. 11, 1958 Eleven firms submitted proposals for a manned spacecraft. STG members
began assessing them on the 12th; they forwarded their findings to NASA
Headquarters on the 30th.
140 NASA HISTORICAL DATA BOOK
Table 2-28.
Date Event
Dec. 29, 1958 NASA awarded a contract to North American Aviation for the design and
construction of the Little Joe I airframe (letter of intent dated December 31,
1958). The first two airframes were delivered on May 28, 1959.
Jan. 5, 1959 Guidelines were established for choosing astronaut candidates.
Jan. 9, 1959 McDonnell Aircraft Corporation's proposal for developing and producing
the Mercury spacecraft was chosen as the winning bid. Preliminary negotia-
tions began on the 14th, with a contract being signed on February 6. By FY
1962, 26 spacecraft had been ordered. Also on the 9th, NASA and Depart-
ment of Defense (DoD) officials met to coordinate requirements for
spacecraft tracking.
Jan. 16, 1959 NASA ordered eight Redstones and two Jupiters for Mercury from the
Army; the requirement for the Jupiters was dropped on July 1, 1959.
Jan. 29, 1959 The Little Joe test program was drafted; it was updated on April 14, 1959.
Feb. 12, 1959 NASA and Navy officials met to discuss Mercury recovery needs; a NASA-
Navy committee met formally for the first time on the 17th.
March 8, 1959 The first abort test of a full-scale model of the Mercury spacecraft was con-
ducted at Wallops Island. On the 1 lth, a full-scale pad-abort test took place.
March 31, 1959 STG officials met with Atlantic Missile Range (AMR) personnel to discuss
launch requirements.
Apr. 2, 1959 NASA held a preliminary briefing for prospective bidders on the Mercury
tracking network.J" Also on the 2d, it was announced that the selection of
seven Mercury astronauts had been made; the candidates were announced
publicly on the 9th. Training began on the 27th.
Apr. 12, 1959 A second full-scale beach abort was successful.
Apr. 19, 1959 The STG organized a Mercury Capsule Coordination Office under James A.
Chamberlin; a Capsule Review Board, Paul E. Purser, chairman, was also
formed.
July 22, 1959 NASA selected B. F. Goodrich Company as contractor for the Mercury
pressure suit. Specifications were issued on October 2, 1959, and production
began in May 1960. Also on the 22d, another successful pad-abort test took
place using an escape rocket made by Grand Central Rocket Company.
Aug. 21, 1959 Little Joe 1 (L J-l) beach-abort was unsuccessful.**
Sept. 9, 1959 Big Joe 1 was successful.
Oct. 4, 1959 L J-6 was successful.
Nov. 1959-Jan. 1960 The general design work on the Mercury couch was completed.
Nov. 4, 1959 LJ-IA was unsuccessful.
Nov. 8-Dec. 5, 1959 Tentative design and layout of the Mercury control center was completed.
Dec. 4, 1959 L J-2 was successful.
Jan. 15, 1960 NASA approved an "Overall Plan for Department of Defense Support for
Project Mercury Operations"; DoD approval came in March.
May 9, 1960 A beach-abort test was successful.
June 20, 1960 Tests of the spacecraft environmental control system were begun.
July 29, 1960 Mercury-Atlas 1 (MA-1) was unsuccessful.
Sept. 1960 Pressure suits were tested to determine final adjustments; a number of im-
provements had been suggested and changes made by April 1963. The suit
evolved with the program.
Nov. 8, 1960 L J-5 was unsuccessful.
Nov. 21, 1960 Mercury-Redstone 1 fMR-1) was unsuccessful.
Dec. 19, 1960 MR-IA was successful.
Jan. 3, 1961 The STG was declared a separate NASA field element.
Jan. 31, 1961 MR-2 was successful.
MANNED
SPACEFLIGHT 141
Table2-28.
Chronology
of KeyProject
MercuryEvents*
(Continued)
Date Event
Feb.
21,1961 MA-2 was successful. Also on the 21st, astronauts John H. Glenn, Jr., Virgil
I. Grisson, and Alan B. Shepard, Jr., were selected to begin training for the
first manned flight.
March18,1961 LJ-5A was unsuccessful.
March24,1961 A Mercury Redstone-Booster Development (MR-BD) test was successful.
Apr.12,1961 Soviet cosmonaut Yuri A. Gagarin made an orbital flight on Vostok 1.
Apr.25,1961 MA-3 was unsuccessful.
Apr.28,1961 LJ-5B was successful.
May5,1961 MR-3, piloted by Shepard, successfully completed NASA's first manned
suborbital mission (see table 2-30).
May25,1961 President John F. Kennedy called for an accelerated space program, leading
to a manned lunar landing before the end of the decade.
July21,1961 MR-4, manned by Grissom, successfully completed a suborbital mission (see
table 2-31).
Aug.1961 A site selection team evaluated locations for a Manned Spacecraft Center;
Houston was chosen as the best site in September.
Sept.
13,1961 MA-4 was successful.
Nov.l, 1961 The STG was redesignated the Manned Spacecraft Center (MSC); Robert R.
Gilruth was retained as director.
Nov.29,1961 MA-5, the last unmanned development test, was successful. Also on the 29th,
Glenn was selected as pilot of the first orbital mission.
Jan.15,1962 Organization of MSC was completed.
Feb.
1962 Kenneth S. Kleinknecht was appointed Project Mercury manager.'_t
Feb.
20,1962 MA-6, manned by Glenn, successfully completed NASA's first manned or-
bital mission (see table 2-32).
May24,1962 MA-7, with M. Scott Carpenter onboard, successfully completed an orbital
mission (see tabler 2-33).
July1,1962 Relocation of the MSC group from Langley Research Center to the Houston
site was completed.
Sept.
18,1962 Donald K. Slayton was designated coordinator of astronaut activities at
MSC.
Oct.3,1962 MA-8, manned by Walter M. Schirra, Jr., successfully completed an orbital
mission (see table 2-34)
May15-16,
1963 MA-9, manned by L. Gordon Cooper, Jr., successfully completed an orbital
mission lasting more than 34 hours, concluding the Mercury flight program
(see table 2-35).
June
12,1963 NASA Administrator James E. Webb announced that because Mercury had
accomplished its goals, MA-10 would not be flown. McDonnell's Mercury
spacecraft contract was terminated the next day.
Oct.3-4,1963 A Project Mercury summary conference was held in Houston.
*For a more detailed calendar of events, see James M. Grimwood, Project Mercury: A Chronology,
NASA SP-4001 (Washington, 1963).
tFor further details on events that led to the establishment of the Manned Space Flight Network, see
table 5-24.
**For further details on this and other developmental flights, consult table 2-29.
_i'Kleinknecht replaced James Chamberlin, who was reassigned to the new Project Gemini office as
manager. Chamberlin's STG titles had been chief of the engineering division and chairman of the Capsule
Coordination Committee, effectively making him "project manager" of Mercury.
142 NASA
HISTORICAL
DATABOOK
Table2-29.
Developmental
Tests/Flights,
ProjectMercury
LaunchDate Test/
(location) Flight Objectives/Results
Aug.21,1959 LJ-1 Unsuccessful
beach
aborttest.When
theescape
rocketfired
(Wallops) prematurely
duringthecountdown,
thevehicle
roseto an
altitude of 600 m and landed some 600 m from the launch site.
Sept.
9,1959 BigJoe1 Successful launch (suborbital) of a full-scale instrumented
(ETR) Mercury boilerplate spacecraft to an altitude of 160 km; cap-
sule survived reentry heat of more than 5800 ° K.
Oct.4,1959 LJ-6 :Successful launch of a boiierpiate Mercury (suborbital) to
(Wallops) check the integrity of the launch vehicle airframe and motor, to
verify launch operations, and to test the destruct system.
Nov.4,1959 LJ-1A Suborbital test of the abort maneuver under high aerodynamic
(Wallops) load conditions (repeat of L J-l). Maneuver was not accom-
plished at the desired pressure.
Dec.
4,1959 LJ-2 Successful suborbital test of spacecraft-escape tower during
(Wallops) high-altitude abort. Entry dynamics and the effects of accelera-
tion on a rhesus monkey (Sam) were also studied.
Jan.21,1969 LJ-1B Successful beach abort test (repeat of L J-l) with a rhesus
(Wallops) monkey (Miss Sam) onboard. The Mercury helicopter recovery
system was also exercised.
May9,1960 Beach abort Successful performance evaluation of the escape system,
(Wallops) (Mercury parachute-landing system, and recovery operations in an off-
spacecra_ 1) the-pad abort. McDonnell's first production spacecraft was
used in the test.
July 29, 1960 MA-I Launch of a Mercury production capsule was unsuccessful due
(ETR) (spacecraft 4) to launch vehicle failure.
Nov. 8, 1960 LJ-5 Unsuccessful test of spacecraft abort under most severe launch
(Wallops) (spacecraft 3) conditions. The escape rocket ignited prematurely, and the
spacecraft did not detach from the vehicle until impact.
Nov. 21, 1960 I_R-I Premature booster cutoff caused the vehicle to settle back
(ETR) (spacecraft 2) down on the pad after barely leaving the ground. The Mercury
capsule was reused in MR-IA.
Dec. 19, 1960 MR-1A Successful suborbital reentry test (repeat of MR-l).
(ETR) (spacecraft 2)
Jan. 3, 1961 MR-2 Suborbital flight of fully operational Mercury with chimpanzee
(ETR) (spacecraft 6)
March 18, 1961 LJ-5A Second unsuccessful attempt to test spacecraft abort system
(Wallops) (spacecraft 14) under most severe conditions. Premature escape rocket ignition
was again the cause of the failure.
March 24, 1961 MR-BD Successful booster development test flight of the Redstone,
Table 2-29.
Developmental Tests/Flights, Project Mercury
*Spacecraft 10 was used at McDonnell's St. Louis facility in an environmental test; 12B had been
scheduled for a manned one-day mission which was cancelled (12B was not delivered); 15B had been
scheduled for a manned one-day mission also, which was cancelled after the successful MA-9 (15B not
delivered); 17 was delivered to Cape Canaveral in April 1963 to be used as parts support for planned one-
day missions; 19 was not delivered when the manned orbital mission for which it was scheduled was
cancelled after the successful MA-8.
Table 2-30.
Mercury-Redstone 3 (MR-3) Characteristics
Table 2-31.
Mercury-Redstone 4 (MR-4) Characteristics
Table 2-32.
Mercury-Atlas 6 (MA-tO Characteristics
Table 2-33.
Mercury-Atlas 7 (MA-7) Characteristics
Spacecraft shape,
dimensions (m): see table 2-30
Crew: Carpenter
Backup crew: Schirra
Table2-34.
Mercury-Atlas 8 (MA-8) Characteristics
Table 2-36.
Project Mercury Flight Experiments
Experiment Mercury-Atlas
6 7 8 9
Astronaut observations x
Light visibility observations x x
Ground flare visibility x
Air glow observations x
Flashing light experiment x
Photography studies x x x
Infrared weather photography x
Dim-light photography x
Horizon definition photography x
Zero g liquid behavior x
Tethered inflatable balloon x
Radiation studies x x
Ablative materials investigation x
Long before the first American astronaut was boosted into orbit, engineers at
the Space Task Group and at McDonnell Aircraft Corporation were making changes
on paper to the Mercury design that would lend it to longer, more useful missions.
In late 1961, these engineers were given the opportunity to fit their "improvements in
the abstract" to a set of specific mission goals. President Kennedy's decision to ex-
hibit American technical prowess through a manned expedition to the moon had
given NASA a revised timetable for finding answers to a broad range of questions.
What effect would several days of weightlessness have on a crew? If a spacecraft
were not sent to the moon directly but relied on maneuvers in earth orbit to prepare
it for a translunar trajectory, how complicated would rendezvous and docking in
space be?* 19 Could an astronaut perform tasks outside his spacecraft? Gemini
would be NASA's vehicle for investigating these and other unknowns. (See table
2-37 for a chronology of key events.)
At McDonnell Aircraft, contractor to NASA for the Mercury spacecraft,
designers had two advanced craft in mind. One would require a minimum number of
changes to the basic Mercury spacecraft, which would extend its mission lifetime.
The second called for major modifications that would provide space for a second
crewman, more consumables, and experiment hardware. Mercury Mark II, as this
upgraded design was called, would also be a more controllable spacecraft during
reentry, although it would retain its predecessor's ballistic shape. When NASA
*Besides direct ascent and earth orbit rendezvous modes for reaching the moon, one other possibili-
ty, lunar orbit rendezvous, gained wide support among NASA personnel in 1962 and was later chosen as
the best solution. See the discussion of the Apollo program elsewhere in this chapter for more informa-
tion.
150 NASA HISTORICAL DATA BOOK
5.74 -- _1
_----- ADAPTER(2.286)MODULE
.... = = RE-ENTRY(3.545)MODULE
( CONTROL
FAIRING_ --
! I _jL_
10o SLOPE
Ftgure 2-. General Arrangement of the Gemini Spacecraft (dimensions in meters). The conical Gemini
spacecraft had two major assemblies: the adapter module, which was jettisoned in two parts before
reentry; and a reentry module. Heat resistant titanium and magnesium were used to fabricate the
spacecraft, with externally-mounted shingles (Rene 41 on the conical section; beryllium on the small
end) giving extra protection. The vehicle's primary protector during reentry was a silicone elastomer
ablative heatshield on the large blunt end of the reentry module. Two access hatches were provided
in the cabin section (reentry module), each fitted with windows. Spacecraft attitude was controlled
with eight Ill-newton thrusters and translation along any axis by s_ 445-newton thrusters and two
378-newton thrusters. Four retrograde rockets for reentry deceleration were located in the retrograde
section of the adapter module. Electrical power was provided by silver-oxide batteries and a fuel
cell built by General Electric (see also tables 2-54 and 2-55 for more information on major spacecraft
systems). From P. W. Malik and G.A. Sourly, Project Gemini; A Technical Summary, NASA CR-1106
(Washington, 1968), p. 5.
MANNED SPACEFLIGHT 151
tion seats and parachutes would take Gemini crews away from malfunctioning
boosters). The Titan II ICBM, however, was still in the development stage, with the
first of 33 research and development flights taking place in March 1962. The Air
Force and the Martin Company, prime contractor for the Titan, spent months
massaging the design to rid it of its problems. Its tendency to oscillate longitudinally
(called the pogo effect) made the missile unsafe for manned use, as did its potential
second-state combustion instability and a number of other minor design flaws.
Troubles with the launch vehicle forced mission planners to substitute unmanned
flights for the first two missions to verify further the Gemini launch vehicle.* By the
spring of 1964, Titan was ready. 20
The mechanics of rendezvous and docking became Gemini's most important ob-
jective when lunar orbit rendezvous was chosen over direct ascent or earth orbit
rendezvous for the Apollo mission mode. One rendezvous and docking maneuver
would take place shortly after leaving earth orbit enroute to the moon; a second
would be required in lunar orbit. NASA chose another Air Force vehicle to serve as
Gemini's target in orbital exercises. Agena, a second stage manufactured by
Lockheed Missiles and Space Company for the Air Force, would be launched into
orbit where it would be available for maneuvers. Agena was considered especially
suitable because it had the capability to restart its engines (NASA required five
restarts for Gemini); its propulsion system could thus be used to maneuver the two
vehicles while they were docked (see fig. 2-4 for spacecraft details). Gemini was pro-
AFT SECTION
N
AI-rlTUDE CONTROL GAS TANKS_
Figure 2-4. Gemini Agena Target Vehicle. The Gemini Agena Target Vehicle (GA TV) was 10.28
meters long with launch shroud and booster adapter intact, Z92 meters long in orb#. Its diameter
was 1.52 meters. Total thrust from its primary propulsion system and two secondary engines was
73,000 newtons. Equipment added to the standard Agena D upper stage for the Gemini program
included a docking collar, compatible radar transponder, strobe lights, secondary propulsion system,
ground control equipment, and a multi-restartable engine (see also chap. 1 for more information
on the Agena vehicle as an upper stage).
152 NASA HISTORICAL DATA BOOK
*There were two classes of EVA. One was called "standup" and did not involve leaving the
spacecraft. The crew member opened the hatch and performed various tasks while still in the cabin. "Um-
bilical" EVA involved leaving the spacecraft, tethered to it by a life line. One modification to Gemini that
made EVA easier was the addition of more restraint straps and handholds outside the spacecraft. Hand-
held maneuvering units were tested on GT-4 and GT-IO. These gas-expulsion devices could produce up to
8.89 newtons of thrust. An astronaut maneuvering unit devised by the Air Force was carried on GT-9A
but not evaluated because the crew member conducting EVA was bothered by visor-fogging and
overheating. This backpack unit had pitch, roll, and yaw controls, with 20 newtons of thrust.
See the section on the Apollo program for more on astronaut selection.
MANNED SPACEFLIGHT 153
White, II, spent four days in orbit and conducted the first extravehicular activity.
They were followed two months later by Gordon Cooper and Charles Conrad, Jr.,
in a seven-day mission. The first attempt to conduct a mission with the Agena target
vehicle failed when the target did not go into orbit in October 1965. In its place, a
dual manned spacecraft mission was performed in December. GT-7with Frank Bor-
man and James A. Lovell, Jr., aboard rendezvoused with GT-6A manned by Walter
M. Schirra, Jr., and Thomas P. Stafford. In addition to their successful joint exer-
cise, the GT-7 crew set an endurance record of more than 13 days in space. The
docking of GT-8 and an Agena target vehicle in March 1966 was marred by a
spacecraft thruster malfunction. Astronauts Neil A. Armstrong and David R. Scott
had to undock and use their reentry thrusters to control their rolling spacecraft; this
led to an early return to a secondary landing area. In May, another Agena failure led
to a backup mission plan. Stafford and Eugene A. Cernan in GT-9 attempted to
dock with a contingency target (an Augmented Docking Target Adapter built by
McDonnell and launched by an Atlas), but its launch shroud failed to jettison, leav-
ing the docking cone covered. Cernan performed tasks outside the spacecraft for
more than two hours, and GT-9 accomplished rendezvous maneuvers. Crewmen
Young and Michael Collins conducted the first completely successful docking mis-
sion aboard GT-IO in July 1966. During the next mission two months later, GT-11
and an Agena target docked during Gemini's first orbit. Conrad and Richard F.
Gordon, Jr., then maneuvered the docked vehicle into a high-altitude orbit. The last
crew, Lovell and Edwin E. Aldrin, Jr., in GT-12, also docked successfully with their
target.* Gemini missions became almost routine for the press and public; for the
launch and test teams at Cape Kennedy and for the mission controllers in Houston it
never became routine, but it did become operational (see tables 2-39 through 2-48
for mission details).
The lengthy missions planned for Gemini and the spacecraft's increased payload
capacity prompted NASA officials to sponsor an experiments program for manned
spaceflight missions. The agency solicited proposals for investigations that required
crew participation from universities, other government agencies, private research
groups, and its own field centers. Once the Gemini Experiments Office (part of the
Gemini Project Office, later called the Experiments Program Office and moved to
the science and applications directorate at MSC) had determined an experiment's
suitability and had identified missions that could accommodate it, the Manned
Space Flight Experiments Board at NASA Headquarters made a specific flight
assignment, t Implementing approved experiments into the mission plan and into the
spacecraft hardware was MSC's task. A total of 52 different experiments was flown
on Gemini, many on more than one mission. Of the 52, 17 were classified scientific,
27 technological (in support of spacecraft development or operational techniques),
and 8 medical (in addition to routine medical monitoring). The Department of
* Gemini crews completed 10 rendezvous maneuvers using 7 different rendezvous modes. They com-
pleted 9 docking exercises.
i The Manned Space Flight Experiments Board, organized in January 1964 to support Gemini and
Apollo, also collected proposals submitted by MSC, the Office of Space Science and Applications, the
Space Medicine Office, and the Office of Advanced Research and Technology and transmitted them to
the Gemini Experiments Office. In turn, the Gemini Experiments Office consulted recovery operations,
flight crew support, medical, and flight operations to determine a proposal's feasibility.
154 NASA HISTORICAL DATA BOOK
Defense was the largest contributor outside NASA with 15 investigations, all in the
technological category. GT-12 carried the largest number of experiments, and the
crew spent 30 percent of its flight time performing them. The various photography
experiments, of which at least one was flown on all missions but the first, provided
investigators and the public with the extensive series of "space photographs," more
than 2400 images. 24 (See table 2-49.)
Because of Project Gemini's use of two Air Force launch vehicles, the Air Force
played a larger part in project management than the service had in Mercury. In addi-
tion, the Navy and the Air Force supported launch, tracking, and recovery opera-
tions. After several months of dispute over DoD's role in Gemini, a January 1963
joint agreement established a NASA-DoD Gemini Program Planning Board to coor-
dinate the two groups' activities. 25
At NASA Headquarters for most of the project's lifetime, George E. Mueller,
associate administrator for manned spaceflight, also acted as Gemini program direc-
tor. Mueller was assisted by Special Assistant Samuel H. Hubbard and by directors
for program control, systems engineering, test, flight operations, and reliability and
quality. At the Manned Spacecraft Center in Houston, James Chamberlin served as
Gemini's first manager. Chamberlin had worked with the technical people at
McDonnell in St. Louis when NASA first considered upgrading the Mercury design.
In 1964, when Gemini, plagued by several major hardware problems, started run-
ning over budget and behind schedule, Charles Mathews took over the manager's
job and reorganized the program office. Personnel from MSC monitored progress
at the Martin Company in Baltimore (Titan II), at Lockheed in California (Agena
target vehicle), at McDonnell in St. Louis (Gemini spacecraft), and at the Cape.
Kenneth Kleinknecht, Mathews' deputy in the Gemini Project Office, was supported
by managers for program control, spacecraft management, and vehicles and mis-
sions. (See also tables 2-2 and 2-3.)
MANNED SPACEFLIGHT 155
Table 2-37.
Chronology of Key Project Gemini Events*
Date Event
May 25-26, 1959 During its first meeting, a NASA committee chaired by Harry J. Goett (Ames
Research Ctr.) considered possibilities for a post-Mercury manned spaceflight
project. Ideas included an enlarged Mercury craft that could support a crew of
two for three days.
Aug. 12, 1959 The Space Task Group's (STG) New Projects Panel instructed the Flight Systems
Division of STG to initiate a program that would lead to a second-generation
spacecraft with advances over the Mercury vehicle. The Mercury spacecraft con-
tractor, McDonnell Aircraft Corporation, was also studying possible modifica-
tions that would improve the vehicle.
Apr. 5, 1960 The STG issued specifications by which to modify the Mercury spacecraft (e.g.,
the addition of a reentry control navigation system). Besides reentry control,
designers also wanted to include orbital controls so that orbital rendezvous
techniques would be possible. (Rendezvous was later seen as a necessary require-
ment for a lunar mission and included as an objective for Gemini.)
Apr. 14, 1961 Following discussions between NASA and McDonnell personnel in February
regarding an advanced Mercury design, NASA issued a study contract to
McDonnell for improving the Mercury. Their work would be concentrated on
two versions of an advanced spacecraft: one with minor changes that would sus-
tain one man for 18 orbits; and a second that would be capable of more ad-
vanced missions with two men, requiring more radical modifications. The im-
proved Mercury concept came to be called Mercury Mark 11.
May 8, 1961 Personnel from the Martin Company, manufacturer of the Titan missile system
for the Air Force, briefed NASA officials on the Titan and its possible applica-
tions to the future manned program. During July, Martin submitted a proposal
for a Titan-boosted Mercury-type vehicle.
May 17, 1961 To allow for a controlled descent on land of a manned spacecraft, the STG
issued a statement of work for a design study of a "paraglider" landing system.
The design study (conducted at Goodyear Aircraft Corp., North American Avia-
tion, Inc., and Ryan Aeronautical Co.) became phase one of a paraglider
development program.
Nov. 1, 1961 STG was redesignated the Manned Spacecraft Center (MSC).
Nov. 21, 1961 NASA issued a letter contract to North American to proceed with phase II-A of
the paraglider development program; the final contract was awarded on
February 9, 1962.
Dec. 7, 1961 NASA Associate Administrator Robert C. Seamans approved a Mercury Mark
II development plan prepared by the STG in October. The plan called for a two-
man version of the Mercury spacecraft capable of longer missions to be launched
by a modified Titan II; the spacecraft would conduct orbital rendezvous and
docking maneuvers with an Agena B target vehicle placed in orbit by an Atlas
booster. A controlled land landing of the returning spacecraft was an additional
project objective. Flights would begin in 1%3.
Dec. 15, 1961 NASA awarded McDonnell a letter contract for the development of 12 Mark 1I
spacecraft. The final contract was not signed until April 2, 1963 (it called for 13
spacecraft, one of which would be used for ground testing).
Dec. 26, 1961 MSC directed the Air Force Space Systems Division to authorize its launch vehi-
cle contractors (primarily Martin) to begin the work necessary to modify the
Titan II for the Mercury Mark I1 program. A letter contract with Martin for 15
launch vehicles was issued on January 19, 1962.
Jan. 3, 1962 "Gemini" became the official designation of the Mercury Mark II program. On
the 15th, a Gemini Project Office was established at MSC, with James
Chamberlin as manager.
Jan. 31, 1962 MSC notified the Marshall Space Flight Center that it should procure through
the Air Force 11 Agena B target vehicles and Atlas boosters for Gemini. The Air
Force Space Systems Division awarded a letter contract to Lockheed Missiles and
156 NASA HISTORICAL DATA BOOK
Date Event
Space Company for 8 modified Agenas on May 1. Marshall was actively in-
volved in the Atlas-Agena procurement cycle until January 1963, when MSC
assumed the responsibility.
March 16, 1962 The Air Force successfully conducted the first full-scale test launch of a Titan 11
ICBM. In all, 33 Titan research and development flights took place, the last on
April 9, 1964. From the standpoint of a Gemini mission, 22 would be judged suc-
cessful.
March 27, i962 Air Force and NASA official_ _igued a Gemini Operational and Managcmcnt
Plan that outlined the roles NASA and DoD would play in the program. DoD
was responsible for the Titan II and Atlas-Agena B launch vehicles from
development through launch and for range and recovery support.
March 31, 1962 The Gemini spacecraft configuration was formally frozen.
MSC awarded B. F. Goodrich a contract for the development of prototype
April 4, 1962
Gemini pressure suits. The first suit was delivered on November 6.
May 1962 Tests began at Ames Research Center to evaluate a half-scale paraglider wing.
Tests ran through July. North American also began drop tests of the emergency
parachute system for their half-scale paraglider. North American was authorized
to begin phase II-B of the paraglider program on June 20.
July 1962 During Gemini launches, ejection seats rather than escape rockets would be used
to carry astronauts away from a malfunctioning booster. Simulated off-the-pad
ejection tests began in July at the Naval Ordnance Test Station.
Aug. 2, 1962 NASA and Air Force officials decided to substitute the uprated, more versatile
Table2-37.
(Continued)
Chronology
ofKeyProject
Gemini
Events*
Date Event
August,
September,
andOctober. At Ames,
windtunneltests
ofa half-scale
vehicle
wereconductedinJulyandAugusttoverify
design
changes.
Inadesign
engineering
inspection
in August,
NorthAmericanwasrequested
tomake 30
modifications
tothefull-scale
testvehicle.
June
13,1963 Thecontract
fortheGemini spacesuit
wasawardedtotheDavidClarkCom-
pany. A prototype suit was delivered in July.
Aug.25,1963 McDonnell completed the first Gemini spacecraft. It arrived at Cape Canaveral
on October 4.
Oct.1963 North American completed the first full-scale prototype paraglider wing and sent
it to Ames for wind tunnel tests.
Oct.18,1963 Another 14 astronauts were added to the team at MSC.
Oct.26,1963 The first Titan launch vehicle for Gemini arrived at the Cape; spacecraft and
launch vehicle were mechanically mated on March 5, 1964.
Dec.
22,1963 Charles Mathews was appointed manager of the Gemini Project Office, having
been acting manager since March 19 when Chamberlin became an advisor to the
MSC director.
Jan.1964 North American began development flights of the full-scale paraglider test vehi-
cle; only 6 of the 25 tests were completely satisfactory. In February, NASA
eliminated all plans for paraglider from the Gemini schedule; Gemini would rely
on water landings. While the concept was still judged a sound one, paraglider
hardware development and qualification could apparently not be completed in
time for Gemini.
Apr8,1964 A successful unmanned orbital test (Gemini-Titan 1) of the launch vehicle and
spacecraft was conducted from the Eastern Test Range (ETR). No recovery was
planned (see table 2-38 for details on this and other developmental flights).
Apr.13,1964 It was announced that Virgil Grissom and John Young would make the first
manned Gemini flight.
Oct.1964 The manned spaceflight tracking network as configured for Gemini was exer-
cised.
Jan.19,1965 A successful unmanned suborbital test (GT-2) of the reentry systems was
launched from ETR. The spacecraft was recovered from the Atlantic.
March
23,1965 GT-3, manned by Grissom and Young, successfully demonstrated the integrity
of the spacecraft in a three-orbit mission (see table 3-39).
June
3,1965 James A. McDivitt and Edward H. White, II, in GT-4 conducted the first long-
duration mission. White demonstrated extravehicular activity (EVA). After four
days of activities, the crew splashed down in the Atlantic (see table 2-40).
Aug.21,1965 The next mission, GT-5, with Gordon Cooper and Charles Conrad, Jr., lasted
twice as long. The crew evaluated the rendezvous guidance and navigation
system; landing was on the 29th (see table 2-41).
Oct.25,1965 An attempt to orbit a Gemini-Agena D target vehicle as part of the GT-6 mission
was unsuccessful because of an engine malfunction shortly after stage
separation. The launch of GT-6 was postponed and a review board formed to
investigate the failure.
Dec.
4,1965 In addition to further demonstrating long-duration flight, GT-7, with Frank
Borman and James A. Lovell, Jr., at the controls, acted as a substitute target
vehicle for GT-6A. After 14 days, the spacecraft made its landing (see table
2--42).
Dec.15,1965 Walter M. Schirra, Jr., and Thomas P. Stafford on GT-6A accomplished
rendezvous and stationkeeping maneuvers with GT-7. The mission ended on the
16th (see table 2-43).
Feb.
23-24,
1966 A mid-program conference was held at MSC.
Feb.28,1966 Elliott M. See, Jr., and Charles A. Bassett, II, the two astronauts chosen for the
ninth mission, were killed when their T-38 jet trainer crashed in the fog near St.
Louis.
158 NASA
HISTORICAL
DATABOOK
Table2-37.
Chronology
of KeyProject
Gemini
Events*
Date Event
March
16,1966 Inthefirstmission
tosuccessfully
utilize
theAgena
target
vehicle,
NellA.
Armstrong and David R. Scott docked their GT-8 spacecraft to the Agena D
stage. Because of a spacecraft thruster malfunction, however, the crew was
forced to undock after 27 minutes and use the reentry control system to control
their spacecraft. The mission was terminated early; landing took place in the
Pacific some 10 hours into the flight (see table 2-44).
May17,1966 Because of a short in the servo control circuit, the target vehicle planned for use
with GT-9 did not achieve orbit. In its place, NASA decided to launch an
augmented target docking adapter, a backup to the Agena vehicle, which was
built by McDonnell.
June
1,1966 The alternative docking target was launched successfully, but the launch of GT-
9A was postponed by a ground equipment failure.
June
3,1966 In GT-9A, Stafford and Eugene A. Cernan began their rendezvous mission.
Because the launch shroud was still attached to the docking adapter when the
crew reached it, they could not dock. Several secondary rendezvous objectives
and an EVA exercise were accomplished. Landing took place on the 6th (see
table 2-45).
July18,1966 An Atlas-Agena target vehicle and GT-IO were both successfully launched from
ETR. Pilots Young and Michael Collins docked their spacecraft with the Agena
about six hours later. The mission ended on the 21st (see table 2-46).
Sept.
12,1966 An Atlas-Agena D and GT-II were launched successfully. Astronauts Conrad
and Richard F. Gordon, Jr., docked their spacecraft with the target vehicle and
met all mission objectives. The mission ended on the 15th (see table 2-47).
Nov.11,1966 In the last Gemini mission, an Atlas-Agena target vehicle and GT-12 with Lovell
and Edwin E. Aldrin, Jr., aboard were launched during the afternoon.
Rendezvous, docking, and EVA were accomplished. Splashdown took place on
the 15th (see table 2-48).
Feb.
1-2,1967 The Gemini Project Office was abolished on the 1st, and a two-day summary
conference was held at MSC.
*For a more detailed calet_lar of events, see James M. Grimwood and Barton C. Hacker with Peter
J. Vorzimmer, Project Gemini Technology and Operations; A Chronology, NASA SP-4002
(Washington, 1969).
Table 2-38.
Developmental Flights, Project Gemini
April 8, 1964 GT-I (Gemini Successful orbital test of the Titan II launch vehicle,
(ETR) spacecraft 1) spacecraft structural integrity, and launch vehicle-
(Gemini launch spacecraft compatibility (no recovery operations plann
vehicle 1) ed; reentry and disintegration 3 V2 days after launch).
Jan. 19, 1965 (ETR) GT-2 (spacecraft 2) Successful suborbital reentry test at maximum heating
(GLV 2) rate; spacecraft was recovered after parachute landing
in the Atlantic.
MANNED SPACEFLIGHT 159
Table 2-39.
Gemini-Titan 3 (GT-3)
Table 2-40.
Gemini-Titan 4 ( GT-4) Characteristics
Table 2-41.
Gemini-Titan 5 (GT-5) Characteristics
Table 2-42.
Spacecraft shape,
dimension (m): see table 2-39
Crew: Borman, Lovell
Backup crew: VV titre, Ml_hae, Cu..,_
Cap corns: Alan L. Bean (Cape); See, Eugene A. Cernan, Charles A. Bassett I1
(Houston)
Apogee/perigee at
insertion (km): 328/161.5
No. of orbits: 206
Period: 01:29:23
Length of mission: 330:35:01 (13 + days)
Mission events (date, time, ground elapsed time):
launch Dec. 4 2:30:03 p.m., EST
main engine shutoff 2:32:39 00:02:36
orbital insertion 2:36:11 00:06:08
initiation of retrofire Dec. 18 8:28:07 a.m. 329:58:04
splashdown 9:05:04 330:35:01
Distance traveled (km): 9 200 459
Landing point: 25°25'N, 70°7'W (12 km from target)
Recovery ship: USS Wasp (crew onboard in 33 min.)
Mission objective: Conduct a long-duration flight of 14 days, evaluating spacecraft and crew
performance; execute 20 experiments; serve as a target for GT-6A rendez-
vous and stationkeeping maneuvers.
Results: Rendezvous with GT-6A took place on December 15-16. The crew ex-
perienced a number of minor hardware problems on this long-duration
flight, including difficulty with the fuel cell, an onboard tape recorder
failure, trouble with two attitude thrusters, and difficulty with experiment
equipment. (See also table 2-43.)
Reference: Gemini Mission Evaluation Team, "Gemini Program Mission Report
Gemini Vii," MSC-G-R-66-1, Jan. 1966.
MANNED SPACEFLIGHT 163
Table 2-43.
Gemini-Titan 6A (G T-6A ) Characteristics
Table 2-44.
Gemini-Titan 8 ( GT-8) Characteristics
Date of launch (ETR pad #): March 16, 1966 (19) GATV: March 16, 1966 (14)
Launch vehicle
TLV-5302
designation: GLV-8
8097
Spacecraft weight (kg): 3788
Spacecraft shape,
dimensions (m): see table 2-39 cylindrical
diam., 1.52
Crcw: Armstrong, David R. Scott length in orbit, 7.92
Backup crew: Conrad, Richard F. Gordon, Jr.
Cap coms: R. Walter Cunningham (Cape), Lovell (Houston)
Apogee/perigee at
insertion (km): 271.7/159.8
No. of orbits: 7
Period: 01:28:50
Length of mission: 10:41:26
Mission events (date, time, ground elapsed time):
GATV launch March 16 10:00:03 a.m., EST
launch 11:41:02
main engine shutoff 11:43:36 00:02:34
orbital insertion 11:47:36 00:06:06
initiation of retrofire 9:45:49 p.m. 10:04:47
Table 2-45.
Gemini-Titan 9A (GT-9A) Characteristics
Date of launch (ETR pad #): June 3, 1966 (19) ATDA: June 1, 1966 (14)
Spacecraft designation: Gemini 9 ATDA
Launch vehicle
designation: GLV-9 TLV-5304
Spacecraft weight (kg): 3750 1088
Spacecraft shape,
dimensions (m): see table 2-39 cylindrical
diam., 1.52
Crew: Stafford, Cernan length in orbit, 3.41
Backup crew: Lovell, Aldrin
Cap coms: Aldrin (Cape, Houston); Armstrong, Lovell, Gordon (Houston)
Apogee/perigee at
insertion (km): 266.7/158.7
No. of orbits: 45
Period: 01:28:47
Length of mission: 72:20:50 (3 + days)
Mission events (date, time, ground elapsed time):
ATDAlaunch June 1 10:00:02 a.m., EST
launch June3 8:39:33 a.m.
main engine shutoff 8:42:05 00:02:32
orbital insertion 8:45:40 00:06:07
initiation of retrofire June 6 8:26:17 a.m. 71:46:44
splashdown 9:00:23 72:20:50
Distance traveled (km): 2 020 741
EVA time: 02:07:00
Landing point: 27°52_, 75°0'W (.7 km from target)
Recovery ship: USS Wasp (crew onboard in 52 min.)
Mission objectives: Rendezvous and dock with a target vehicle; conduct EVA; execute seven
experiments; test the Air Force astronaut maneuvering unit.
Results: GT-9 was postponed when TLV 5303 with GATV 5004 malfunctioned on
May 17. In its place, a substitute target was used for GT-9A; the
Augmented Target Docking Adapter (ATDA) was launched by an Atlas
on June 1; however, GT-9A was not launched on the same day as planned
due to a guidance system computer problem. After a brief hold, the
spacecraft was launched on the 3d. Upon maneuvering with the target,
the crew discovered that the launch shroud protecting the ATDA had not
been jetissoned, precluding any attempts to dock. Instead GT-9A per-
formed a number of rendezvous maneuvers, including a Simulation of
lunar module rendezvous (Apollo). During EVA maneuvers, Cernan's
visor became fogged, and he was unable to test the Air Force maneuver-
ing unit. The crew remained inside their spacecraft during recovery opera-
tions. The original crew for GT-9, Elliott M. See and Charles Bassett,
were killed in an airplane crash on February 28, 1966. The backup crew
was named to the prime crew positions.
Reference: Gemini Mission Evaluation Team, "Gemini Program Mission Report
Gemini IX-A," MSC-G-R-66-6, July 1966.
166 NASA HISTORICAL DATA BOOK
Table 2-46.
Gemini-Titan 10 (GT-IO) Characteristics
Date of launch (ETR pad #): July 18, 1966 (19) GATV: July 18, 1966 (14)
Spacecraft designation: Gemini 10 GATV-5005
Launch vehicle
designation: GLV- 10 TLV-5305
Spacecraft shape,
dimension (m): see tables 2-39 and 2-44
Crew: Young, Collins
Backup crew: Bean, Williams
Cap coms: Cooper (Cape, Houston), Aldrin (Houston)
Apogee/perigee at
insertion (km): 268.7/159.8
No. of orbits: 43
Period: 01:28:47
Length of mission: 70:46:39(2+ days)
Mission events (date, time, ground elapsed time):
GATV launch July 18 3:39:46 p.m., EST
launch 5:20:26 a.m.
main engine shutoff 5:22:59 00:02:33
orbital insertion 5:26:38 00:06:12
initiation of retrofire July 21 3:30:50 p.m. 70:10:24
splashdown 4:07:05 70:46:39
Distance traveled (km): 1 968 823
EVA time: 01:29:00 (umbilical, 00:39:00; standup, 00:50:00)
Landing point: 26°45'N, 71°57'W (6 km from target)
Recovery ship: USS Guadalcanal (crew onboard in 28 min.)
Mission objectives: Rendezvous and dock with an Agena target vehicle; conduct dual
rendezvous maneuvers using the target vehicle's propulsion systems; con-
duct EVA; practice docking maneuvers; execute 15 experiments; evaluate
various docked spacecraft systems.
Results: Docking took place about 6 hours after GT-IO liftoff. Because more fuel
was used than planned during the first rendezvous exercise the spacecraft
remained docked with the GATV for 39 hours so that it could take advan-
tage of the target vehicle's propulsion system for docked maneuvers. The
spacecraft also rendezvoused with GATV 5003 from the GT-8 mission,
which had been in orbit since March 1966. During umbilical EVA, Collins
retrieved an experiments package from GATV 5003.
Reference: Gemini Mission Evaluation Team, "Gemini Program Mission Report
Gemini X," MSC-G-R-66-7, Aug. 1966.
MANNED SPACEFLIGHT 167
Table 2-47.
Gemini-Titan 11 (GT-11) Characteristics
Date of launch (ETR pad #): Sept. 12, 1966 (19) GATV: Sept. 12, 1966 (14)
Spacecraft designation: Gemini 11 GATV-5006
Launch vehicle
designation: GLV-11 TLV-5306
Spacecraft weight (kg): 3798 8097
Spacecraft shape,
dimension (m): see tables 2-39 and 2-44
Crew: Conrad, Gordon
Backup crew: Armstrong, William A. Anders
Cap corns: Williams (Cape), Young, Bean (Houston)
Apogee/perigee at
insertion (km): 276.3/159.6
No. of orbits: 44
Period: 01:28:59
Length of mission: 71:17:08 (2+ days)
Mission events (date, time, ground elapsed time):
GATV launch Sept. 12 8:05:01 a.m., EST
launch 9:42:27
main engine shutoff 9:45:00 00:02:33
orbital insertion 9:48:28 00:06:01
initiation of retrofire Sept. 15 8:24:03 a.m. 70:41:36
splashdown 8:59:35 71:17:08
Distance traveled (km): 1 983 565
EVA time: 02:43:00 (umbilical, 00:33:00; standup, 02:10:00)
Landing point: 24 ° 15'N, 70°0'W (5 km from target)
Recovery ship: USS Guam (crew onboard in 24 min.)
Mission objectives: Rendezvous and dock with an Agena target vehicle during the first orbit;
conduct docking practice, including docked maneuvers at a high altitude;
conduct a tethered-vehicle test during EVA; execute 11 experiments;
demonstrate automatic reentry.
Results: The mission was postponed twice; on September 9 due to a small leak in
the first-stage oxidizer tank of the GLV; and on the 10th due to a
suspected malfunction of the autopilot on the GLV. On the day of
launch, there was a 16-minute hold due to a suspected leak around the
command pilot's hatch. Once under way, the mission went as planned
with a successful first-orbit docking. The GATV propulsion system put
the two spacecraft into a high-altitude orbit (1373.3/289.5 km) 40½
hours into the mission. During EVA, astronaut Gordon tethered the two
spacecraft together with a 30-meter line. Automatic reentry was suc-
cessful.
Reference: Gemini Mission Evaluation Team, "Gemini Program Mission Report
Gemini XI," MSC-G-R-66-8, Oct. 1966.
168 NASA HISTORICAL DATA BOOK
Table 2-48.
Gemini-Titan 12 ( GT-12) Characteristics
Date of launch (ETR pad #): Nov. 11, 1966 (19) GATV: Nov. 11, 1966 (14)
Spacecraft designation: Gemini 12 GATV-5001
Launch vehicle
designation: GLV-12 TLV-5307
Spacecraft shape,
dimension (m): see tables 2-39 and 2-44
Crew: Lovell, Aldrin
Backup crew: Cooper, Cernan
Cap coms: Stuart A. Roosa (Cape); Conrad, Anders (Houston)
Apogee/perigee at
insertion (km): 270.6/160.8
No. of orbits: 59
Period: 01:28:52
Length of mission: 94:34:31 (3 + days)
Mission events (date, time, ground elapsed time):
GATV launch Nov. 11 2:07:58 p.m., EST
launch 3:46:33
main engine shutoff 3:49:08 00:02:35
orbital insertion 3:52:40 00:06:07
initiation of retrofire Nov. 15 1:46:31 p.m. 93:59:58
splashdown 2:21:04 94:34:31
Distance traveled (km): 2 574 950
EVA time: 05:30:00 (umbilical, 02:06:00; standup, 03:24:00)
Landing point: 24°35'N, 69°57'W (5 km from target)
Recovery ship: USS Wasp (crew onboard in 30 min.)
Mission objectives: Rendezvous and dock with an Agena target vehicle; conduct EVA three
times; practice docking; accomplish tethered-vehicle stationkeeping; per-
form docked exercises with the GATV propulsion system, including high-
altitude maneuvers; use controlled reentry technique.
Results: Initial docking took place about 4 ¼ hours into the mission. High-altitude
docked maneuvers were cancelled when flight controllers noted fluctua-
tions in GATV's primary propulsion system; instead an eclipse of the sun
was photographed on the 10th orbit. The crew experienced problems with
the fuel cell and the orbital attitude and maneuvering system. Aldrin's
EVA went as planned, as did reentry.
Reference: Gemini Mission Evaluation Team, "Gemini Program Mission Report
Gemini XII," MSC-G-R-67-1, Jan. 1967.
MANNED
SPACEFLIGHT 169
Table 2-49.
Results1"
Gemini-Titan
No* Experiment 3 4 5 6A 7 8 9A 10 11 12
Table2-49.
ProjectGemini
FlightExperiments
(Continued)
Results*
Gemini-Titan
No* Experiment 3 4 5 6A 7 8 9A 10 11 12
*The letter prefixes to the experiment numbers correspond to the following: M=manned
spaceflight; MSC = Manned Spacecraft Center; T= technological; D= Department of Defense; and
S = scientific.
tX = experiment performed successfully
P = experiment performed partially
N = experiment not performed
MANNED SPACEFLIGHT 171
NASA's first 10-year plan, drawn up by the headquarters Program Planning Of-
fice in late 1959, scheduled manned circumlunar missions and permanent earth-
orbiting space stations for the late 1960s. Manned exploration of the moon's surface
was reserved for the next decade, when the "super boosters" considered necessary
for lunar landing missions would be operational. Advanced planners forecast that a
direct-ascent flight from earth to the moon would require more than 50 million
newtons of thrust; Atlas, which was being readied for Project Mercury, was capable
of only 1.6 million newtons (see the discussion of Project Mercury elsewhere in this
chapter). Furthering the development of large rocket engines and establishing a na-
tional space vehicle program that would provide increasingly powerful boosters were
critical first steps to the moon. 26 In 1959, NASA proposed to develop four boosters
that would fulfill all the agency's heavy-payload needs during the coming years.
Nova, the most powerful and the least defined of the four, would boost man directly
to the moon.* From the Army Ballistic Missile Agency came another scheme for
lunar missions that did not require a vehicle in the Nova class. Instead of launching
the lunar spacecraft in one package in a direct ascent to the moon, Wernher von
Braun suggested assembling a vehicle in earth orbit from propulsion and spacecraft
components put there by boosters much smaller than the proposed Nova. From or-
bit (in zero gravity), it would require far less thrust to send a spacecraft on its way to
the moon. The clustered-engine booster von Braun had in mind was Juno V. Work-
ing in-house with proponents of both lunar mission modes, NASA designers began
conceptualizing an advanced spacecraft that would take man beyond earth.t (See
table 2-50 for a listing of key program events.)
In July 1960, manned spaceflight officials held the first of several conferences at
which they acquainted industry with NASA's plans for circumlunar missions and
"Apollo," the designation given the agency's advanced spacecraft. Apollo would be
designed to support three astronauts for up to 14 days on a lunar reconnaissance
mission. Three contractors were chosen that fall to prepare feasibility studies for
such a spacecraft. Meanwhile in Alabama, von Braun's rocket team was transferred
to NASA and instructed to continue development of its family of clustered-engine
rockets, which had been redesignated Saturn. New studies suggested that multistage
Saturns might be powerful enough for NASA's lunar program. Judged by some to
be an unneccessary complication, a third method for reaching the moon had sur-
faced that year at the agency's Langley Research Center. Direct ascent and earth or-
bit rendezvous both assumed landing the entire spacecraft package on the moon,
along with the large amount of propellant that would be required to lift the return-
ing spacecraft off the moon. Rather than fly this very heavy configuration, Langley
researchers suggested a much smaller two-part spacecraft. From orbit around the
moon, crewmen in a lunar module would separate from the main spacecraft and
land on the moon; when surface operations were completed they would return to the
* The four vehicles were Vega and Centaur, which were upper stages, and Saturn and Nova, which
were multistage launchers. For more information, see chap. 1.
1"STG engineers were led by Mercury designer Maxime Faget. Jack Heberlig drafted the first hard-
ware guidelines for the Apollo command center spaceflight.
172 NASA HISTORICAL DATA BOOK
orbiting ship, leaving behind the craft's landing legs. Before their return to earth,
the crew would jettison the module. While such a scenario would require a more
modest launch vehicle than Nova and only one launch rather than the multiple
launches characteristic of earth orbit rendezvous, it also demanded the precise coor-
dination of two vehicles far from earth. If the crew should miss in their attempt to
rendezvous, the returning lunar module could just drift off into space, warned the
opponents of lunar orbit rendezvous. .27
Days after the Martin Company, General Electric, and the Con-
vair/Astronautics Division of General Dynamics submitted Apollo feasibility
studies to NASA, President John Kennedy made a speech that dramatically affected
the agency's plans for lunar missions. 2s Before Congress on May 25, 1961, the presi-
dent called for an accelerated space program that would land a man on the moon
before the end of the decade, a program that would prove America's technical prow-
ess to the world. NASA was still nine months away from orbiting a man about earth,
and Apollo was in its earliest stages of definition. To accomplish a manned landing
by 1969 would require an enormous effort and a huge purse.
Reacting to Kennedy's challenge, NASA assigned several new committees and
working groups the task of evaluating the three mission modes proposed for a lunar
landing. 29 Although the agency went ahead with its plans to invite 12 firms to bid for
the Apollo spacecraft contract, the vehicle's final configuration would depend on
what route it would take to its destination and by what means. _ It was quickly deter-
mined that NASA would not have time to develop a Nova-class launch vehicle.
Apollo would have to depend on a three- or four-stage version of Saturn. As for
mission mode, this left earth orbit rendezvous as the clear favorite at NASA Head-
quarters and the Marshall Space Flight Center in Alabama, while the Manned
Spacecraft Center in Houston, the new home and designation of the Space Task
Group, began to see the practicality of lunar orbit rendezvous. Of the five teams that
submitted proposals to design and manufacture the Apollo command and service
modules, NASA chose the Space and Information Systems Division of North
American Aviation. ** The day before the decision was announced on November 27,
1961, the manned spacecraft team had expanded the Apollo contract statement of
work considerably to include all major spacecraft subsystems. North American
would have to employ a small army of subcontractors to provide many of Apollo's 2
million functional parts (see fig. 2-5 for a description of the Apollo spacecraft and
table 2-56 for a list of contractors).
On January 15, 1962, two new offices were opened at the Manned Spacecraft
Center. In addition to the Apollo Spacecraft Project Office (ASPO), NASA
* A fourth mission mode suggested by personnel at the Jet Propulsion Laboratory involved assembl-
ing on the moon an earth-return vehicle from components deposited there by unmanned landers. Lunar
surface rendezvous was not seriously considered for Apollo.
_The first contract NASA let for Apollo was to the Instrumentation Laboratory of MIT (Aug. 1961)
for the development of a guidance and navigation system. It was recognized that this system was a long
lead-time item that would be required regardless of which mission mode was chosen.
** The definitive contract with North American, signed on Aug. 14, 1963, called for 11 mockups of
the CSM, 15 boilerplate models, and 11 spacecraft.
MANNED SPACEFLIGHT 173
LAUNCH
ESCAPE
SYSTEM
10.06
| COMMAND
3.63
MODULE
SERVICE
6.88
MODULE 25.88
SPACECRAFT 8.53
LM
ADAPTER
| !
INSTRUMENT UNIT .91
x\ |
I I
I I
Figure 2-5. Apollo Spacecraft (dimensions in meters). This drawing represents the Apollo stack at
launch. The launch escape system (3 solid-propellant motors) was included to propel the command
module to safety in the event of an aborted launch. If it were not required, the LES was jettisoned
shortly after launch. The command module, equipped with 3 couches, served as the crew compart-
ment and control center. A forward docking ring and harch allowed the spacecraft to dock with
the lunar module (stowed in the spacecraft LM adapter during launch). The command module was
capable of attitude control about 3 axes (with its I0 reaction control system engines) and some lateral
lift translation in the atmosphere. Made from aluminum, the command module had 2 hatches and
5 windows. Thermal protection during reentry was provided by ablative heatshields of varying
thicknesses. The service module provided the primary propulsion and maneuvering capability for
the spacecraft. Most of the consumables (oxygen, hydrogen, propellant) was also stored in this module.
Prior to reentry, the crew jettisoned the service module. Inside the spacecraft LM adapter, the lunar
module was stowed. The instrument unit, part of the launch vehicle, contained guidance, naviga-
tion, and control equipment. (See also tables 2-54 and 2-55 for more information on major spacecraft
subsystems and spacecraft characteristics.)
174 NASA HISTORICAL DATA BOOK
*MSC engineers favored lunar orbit rendezvous because it promised the highest payload efficiency,
the smallest size for the landing module, and the least compromise on spacecraft design. Headquarters
determined that this mode would cost 10 to 15 percent less than direct ascent or earth orbit rendezvous.
MANNED
SPACEFLIGHT 175
DOCKING
RENDEZVOUS TARGET
RADAR ANTENNA
S-BAND IN-FLIGHT
ANTENNA (2) k J
RCS THRUST
CHAMBER
ASSEMBLY
LANDING 3.75
GEAR
ASCENT
STATE 'r
FORWARD
HATCH DESCENT' 6.9
STAGE
FORWARD
3.23
LANDING
PAD (.95
DIAM)
LADDER
EGRESS
PLATFORM
DESCENT
ENGINE
SKIRT
Figure 2-6. Apollo Lunar Module (dimensions in meters). Because the lunar module (LM) wouM
operate only in space, its designers couM ignore the aerodynamic streamlining demanded by behicles
that flew in Earth's atmosphere. Un ungainly looking vehicle was the result. The two-stage spacecraft
carried to the vicinity of the moon by the Apollo command and service module (CSM)--the points
of interface being the apex of the conical command module and the top surface of the LM ascent
stage---was designed to land two of the three Apollo crewmen on the surface in a controlled fashion.
From lunar orbit where it was released by the CSM, the LM's descent and ascent stages functioned
as a unit. During surface operations, the ascent stage served as a home for the astronauts, when
it was time to return to the orbiting CSM the descent stage provided a launch platform for the
ascent stage. It took more than two years to design the LM, with its makers fighting weight gain
long after a configuration was approved. The most troublesome, critical, and heavy of the LM's
components were its entines--18 of them (1 large engine for each stage: descent propulsion system
at 43,900 newtons thrust, ascent propulsion system at 15,500 newtons," and 16 smafl attitude control
engines clustered in quads around the ascent stage). Propellant for these systems accounted for more
than 70 percent of the LM's total weight of 1,500 kilograms (propulsion for the variable-thrust des-
cent engine along came to nearly 55 percent). The ascent stage was basically cylindrical (4.29-meter
diameter) but with angular faces; its aluminum skin was encased by a mylar thermal-micrometeorite
shield. The cruciform structure of the descent stage supported the descent engine and 4 propellant
tanks. Four legs, the struts of which were filled with crushable aluminum honeycomb for absorbing
the shock of landing, were capped by footpads. The descent stage was also constructed of aluminum
alloy. A ladder attached to one of the legs gave the crew access to the surface. A docking tunnel
(0.81-meter diameter) was provided for crew transfer between the command module and the LM
ascent stage. After the surface operations were completed and the crew returned via the ascent stage
to the CSM, the LM was jettisoned. A LM was included on a manned Apollo mission for the first
time in March 1969 (Apollo 9); the first manned lunar landing took place in July 1969 (Apollo
11). For more information on spacecraft systems, see table 2-55.
176 NASA HISTORICAL DATA BOOK
At North American, work was under way on two versions of the command and
service module: Block I for earth-orbit operations and Block II for lunar missions.
The prime contractor's greatest problem was ensuring the compatibility of
thousands of interfaces, those points at which two or more components were joined.
Grumman's greatest difficulty was weight gain on the lunar module. Development
of propulsion units for the CSM and the LM was another stumbling block. When
schedules started to slip and hardware problems failed to disappear, NASA ex-
pressed its dissatisfaction with North American. In early 1966, the agency converted
both North American and Grumman's contracts from cost-plus-fixed-fee to cost-
plus-incentive-fcc in an attempt to improve performance at the firms.
By early 1967, hardware and software schedules were keeping better pace with
NASA's mission plans. Ground personnel and astronaut training had begun; the
new mission control center in Houston was in operation. Long-duration missions
and rendezvous and docking had been proved during Gemini flights. Unmanned
Surveyor and Lunar Orbiter spacecraft were sending much needed data on the lunar
surface to Apollo technicians and scientists. Apollo's first crew, Virgil I. Grissom,
Edward H. White, and Roger B. Chaffee, was due to fly an earth-orbital mission in
February. Tragically, however, a fire claimed the lives of these astronauts and
forced the agency to review its lunar exploration program meticulously. In a
simulated countdown of CSM 204 on January 27, 1967, arcs from electrical wiring
in an equipment bay on the command module started a fire (no single ignition point
was identified); in the 100 percent oxygen atmosphere the crew died in minutes of
asphyxia. Faced with its first tragedy, the agency convened an Apollo 204 Review
Board to investigate, which in turn established 21 task panels to scrutinize every
aspect of the accident, from the configuration of spacecraft during the test to the
disposition of the surviving service module. Led by Floyd L. Thompson, the board
in its final report, submitted in April, called for a number of significant hardware
design, test operations, and flight plan changes. Redefinition of the Block II CSM
was also demanded. Tests in 100 percent oxygen environments had already been for-
bidden.* Specific recommendations included the restriction of combustible
materials in the command module, simplifying crew egress procedures, testing for
fire safety on full-scale mockups of a reconfigured CSM, and an in-depth review of
the environmental control system. For five months, a NASA team oversaw Block II
work at North American. 3°
Apollo began to fly in November 1967 with the first "all-up" orbital test of the
Saturn V (Apollo 4), followed by an equally successful orbital trial of the lunar
module (Apollo 5). The second Saturn V-launched mission (Apollo 6) did not meet
its objectives, however, because of several launch vehicle malfunctions. Apollo 7,
now slated to carry the first crew into earth orbit, passed its flight readiness review in
early October 1968. Walter Schirra, Donn F. Eisele, and R. Walter Cunningham
were at the controls of the Block II CSM on October 11 when it was put into orbit by
a Saturn IB. During the 1 l-day mission, the spacecraft performed admirably, allow-
ing the crew to complete all their test objectives (see table 2-52). Months before this
first flight, George Low, Apollo spacecraft project manager at MSC, made a deci-
*Future tests would be performed at 60 percent oxygen-40 percent nitrogen levels; launch operations
would also be conducted using this ratio; 100 percent oxygen would be reserved for flight operations.
MANNED SPACEFLIGHT 177
sion to accelerate the schedule if the first flight were successful. If NASA wanted to
reach the moon before 1970, it would have to sacrifice some of the intermediate
steps. Apollo 8, the second manned mission, would orbit the moon.
On December 21, 1960, Apollo 8 with Frank Borman, James Lovell, and
William A. Anders aboard, was boosted along its translunar path. After 69 hours of
flight, the crew reached their destination, the first men to travel to the vicinity of the
moon. After some 20 hours in lunar orbit, Apollo 8 returned to earth for a
December 27 splashdown in the Pacific (see fig. 2-7 and table 2-53). Apollo 8, a
milestone mission, was the last flight in NASA's first decade.
NASA's corps of astronauts grew considerably during the Apollo years. The
first addition to the original seven Mercury pilots was on September 17, 1962, when
nine men joined the group to fly Gemini and Apollo missions. They were sup-
plemented by another 13 on October, 18, 1963. Prompted by the scientific com-
munity, four scientist-astronauts (two physicists, one physician, and one geologist)
were signed on in June 1965 for lunar landing flights. The largest single group of
pilot-astronauts (18) joined NASA on April 4, 1966. Another seven were chosen on
August 4, 1967 to fill support and backup crew slots. .31 There were three Apollo
crew positions for each mission: commander, command module pilot, and lunar
module pilot. The prime and backup crews followed the one spacecraft that had
been assigned for their flight through its testing program at the factory and through
preparations at the launch site. This kept the crew up to date on modifications that
were made to spacecraft hardware. In addition to "living with their spacecraft," the
astronauts had to train for their specific missions on simulators and trainers, keep
physically fit, and maintain proficiency in flying jet aircraft. To help them coor-
dinate these many activities, each crew had a support crew assigned to it. As they
had during Mercury and Gemini, Apollo astronauts acted as "capsule com-
municators" at mission control during the flights, serving as voice links between
spacecraft and ground control.
In a 1962 summer study conference sponsored by NASA and the National
Academy of Sciences, scientists concluded that the most important tasks that would
face Apollo astronauts once they reached the moon would involve educated observa-
tions of natural phenomena, the collection of samples, and the installation of
monitoring instruments. From these general guidelines, an Ad Hoc Working Group
on Apollo Experiments built its recommendations for Apollo science: (1) the ex-
amination of physical and geological properties in the area near the spacecraft; (2)
geological mapping; (3) investigation of the moon's interior; (4) studies of the lunar
atmosphere; and (5) radio astronomy from the surface. Evaluating proposals for ex-
periments, developing an Apollo lunar surface experiments package, integrating ex-
periments with spacecraft hardware, and preparing special facilities on earth in
which to examine lunar samples kept a cadre of scientists and engineers busy for
years before the first Apollo landing. Apollo 7 and 8, which were basically engineer-
ing missions, did not carry scientific equipment, with the exception of biomedical
* On August 13, 1969, a final group of four astronauts was added to the NASA team as Apollo sup-
port crew members. These men transferred from the USAF Manned Orbiting Laboratory (MOL) pro-
gram, which had been cancelled.
178 NASAHISTORICAL
DATABOOK
MANNED
SPACEFLIGHT 179
sensors and cameras.* In fact, until the first landing and return were accomplished,
enthusiasm for mission science took a decided second place to concerns for engineer-
ing and operational matters. The success of the post-1968 missions, however,
"stimulated a more vigorous interest in the solar system and established the study of
the moon as a modern interdisciplinary science. ''32
A November 1961 agency-wide reorganization put George Low in charge of
spacecraft and flight missions in the NASA Headquarters Office of Manned Space
Flight (OMSF). Reporting to Low was John H. Disher, assistant director for Apollo
spacecraft development. When George MueUer took over as associate administrator
of manned spaceflight in 1963, he kept hold of the Apollo program reins until its
growth demanded a full-time program director. General Samuel C. Phillips was
chosen as director in October 1964, a post he would keep for many years (see table
2-2). Houston's Manned Spacecraft Center was responsible for executing the pro-
gram. The Apollo Project Office added in September 1960 grew in importance with
a 1961 reorganization (see table 2-3). Charles W. Frick was MSC's first Apollo
manager. Joseph F. Shea, assisted by Robert Piland and William A. Lee, saw the
program through its formative years (1963-1966). When George Low took over as
manager of the Apollo Spacecraft Program Office at MSC in April 1967, he faced
the aftermath of the Apollo 204 accident and a compromised flight schedule.
Apollo's circumlunar mission in 1968 was testimony to Low's ability to make bold
decisions.
Every NASA center made some contribution to Apollo, but MSC, the Marshall
Space Flight Center, and the Kennedy Space Center were the major participants (see
also chapter 5 for a discussion of the roles the Goddard Space Flight Center and the
Jet Propulsion Laboratory played in Apollo tracking and data acquisition). In late
1964, MSC's Florida Operations Office was absorbed in a reorganization of KSC;
Kurt H. Debus as director of launch operations managed Apollo's activity at the
Cape.t Marshall, provider of the launch vehicle, was directed by von Braun, who as
leader of the Saturn team, had a very personal interest in Apollo.t "33 Apollo
managers geared their activities to correspond with a series of reviews, inspections,
and certifications that served as key checkpoints for spacecraft design and hardware
production. The six steps were preliminary and critical design reviews, flight article
configuration inspection, certification of flight worthiness, design certification
review, and flight readiness review. This last two-part review confirmed the
readiness of hardware and facilities for each mission. 34 Cooperating with NASA of-
ficials at each of these checkpoints was a legion of contractor and subcontractor
employees whose job it was to ready the spacecraft for launch. North American
Aviation (later called North American Rockwell) led the command and service
module team, Grumman the lunar module team (see table 2-56 for a listing of con-
tractors).
*Apollo 7 carried experiments S-005, synoptic terrain photography, and S-006, synoptic weather
photography; Apollo 8 carried S-151, cosmic ray detector, and the crew conducted lunar mission
photography.
i'Other launch sites that were used during the Apollo testing program were Wallops Station and
** Marshall also supervised Apollo support activities at the Michoud Assembly Facility in New
Orleans, the Mississippi Test Facility at Bay St. Louis, and the Slidell Computer Facility, Slidell, Louisi-
ana.
180 NASA HISTORICAL DATA BOOK
Table 2-50.
Date Event
Dec. 3, 1958 An Army-NASA agreement established that the Army Ordnance Missile
Command (AOMC), of which Wernher von Braun's rocket team was a part,
was to be responsive to NASA requirements for launch vehicles.
Jan. 19, 1959 NASA awarded North American Aviation, Inc., a contract to develop a
large-class single-chamber rocket engine, called the F-I (to be used in the pro-
posed Nova launcher). The F-1 was static-fired for the first time on March 3.
Apr. 1959 A Research Steering Committee on Manned Space Flight was organized to
assist with long-range planning and basic research. Chaired by Harry J.
Goett of Ames Research Center, the group met for the first time on May
25 -26.
June 8, 1959 The Army, in developing a plan for establishing manned lunar outposts
(Project Horizon), predicted that the first landing could take place in 1965.
June 18, 1959 NASA authorized the AOMC to study possibilities for using the proposed
Saturn launch vehicle for lunar missions. These studies were discussed at a
meeting of NASA's Research Steering Committee on Manned Space Flight
later that month.
Aug. 12, 1959 The Space Task Group's (STG) New Projects Panel, chaired by H. Kurt
Strass, met for the first time to discuss future manned programs. The panel
recommended that work start immediately on an advanced capsule and
assigned panel member Alan B. Kehlet to begin a program that would lead to
a second-generation three-man capsule with a potential for near-lunar return
velocities. Kehlet presented his initial findings at a meeting of the panel on
September 28.
Dec. 31, 1959 A Saturn Vehicle Team led by Abe Silversteln recommended that NASA pur-
sue development of the Saturn C-I.
March 15, 1960 The Army Ballistic Missile Agency's Development Operations Division (von
Braun's group) and the Saturn program were transferred to NASA; the facili-
ty was named the George C. Marshall Space Flight Center (MSFC).
Apr.-May 1960 STG personnel wrote guidelines for the design of an advanced spacecraft.
May 25, 1960 STG formed an Advanced Vehicle Team with Robert O. Piland as leader.
This team would make preliminary design studies for an advanced vehicle
capable of carrying several crew members.
July 25, 1960 "Apollo" was chosen as the name for NASA's advanced manned spaceflight
program, which included plans for a manned lunar landing and a permanent
space station.
July 28-29, 1960 The first of a series of NASA-Industry Program Plans Conferences was held
to acquaint industry with the agency's plans for advanced spacecraft and cir-
cumlunar missions.
Oct. 17, 1960 At NASA Headquarters, a small working group was formed by George M.
Low, chief of manned spaceflight, to establish ground rules for manned
lunar landings, determine spacecraft weights, specify launch vehicle re-
quirements, and prepare a development plan.
Table2-50.
Chronology
of Key Apollo Program Events* (Continued)
Date Event
Nov. 1960 Technical Liaison Groups were established by STG to coordinate work and
discussions among center employees involved with advanced spacecraft
design. Nine groups were formed.
Dec. 10, 1960 Personnel at Langley Research Center briefed STG members on an alter-
native to direct ascent to the moon: lunar orbit rendezvous. (Other mission
modes under discussion were earth orbit rendezvous and direct ascent.) The
lunar orbit rendezvous mode reduced launch vehicle power requirements.
Later that month Grumman Aircraft Engineering Corporation funded an in-
house study of lunar orbit rendezvous. Langley and STG personnel met again
to discuss this mode on January 10.
Jan. 9, 1961 A newly formed Manned Lunar Landing Task Group led by Low met for the
first time to consider how the objective of a lunar landing fit into the agency's
future plans and to prepare a position paper on the subject for FY 1962
budget hearings. Their report, submitted on February 7, suggested that a
manned lunar landing could be accomplished during the 1960s using direct
ascent or earth orbit rendezvous (Saturn C-2, three or four stages).
Jan. 19, 1961 MSFC awarded contracts to Douglas Aircraft Company and Chance Vought
Corporation to study the earth orbit rendezvous mode for manned lunar and
interplanetary missions.
May 5, 1961 STG completed its first draft of general requirements for the Apollo
spacecraft.
May 15-17, 1961 The Martin Company, GE, and Convair/Astronautics submitted their final
feasibility studies of an advanced spacecraft.
May 25, 1961 In a speech before Congress, President Kennedy called for new long-range
goals for the space program, including a lunar landing before the end of the
decade.
June 10, 1961 The Lundin Committee, established by NASA the day of Kennedy's speech,
completed a study of vehicle systems that could support manned lunar land-
ings. The committee preferred earth orbit rendezvous as a means for putting
together a lunar vehicle package, using two or three Saturn C-3 launches.
Another study group, the Fleming Committee, appointed on May 2, conclud-
ed that a lunar landing was feasible before 1970.
July 18-20, 1961 A NASA-Industry Apollo Technical Conference was held for representatives
of 300 potential Apollo contractors.
July 20, 1961 A NASA-Department of Defense (DoD) Large Vehicle Planning Group,
directed by Nicholas E. Golovin, was established to study large vehicle
systems such as those needed for a direct ascent mission to the moon.
July 28, 1961 NASA invited 12 companies to submit proposals due on October 9 for the
Apollo spacecraft prime contract.
Aug. 1961 An Ad Hoc Task Group for Study of Manned Lunar Landing by Rendezvous
Techniques reported that the earth orbit rendezvous mode offered the earliest
possibility for a lunar landing. Meanwhile, John C. Houbolt of Langley
made another presentation on lunar orbit rendezvous to STG.
182 NASA HISTORICAL DATA BOOK
Table 2-50.
Date Event
Oct. 27, 1961 Saturn SA-1 (first stage with a dummy second stage) was launched successful-
ly. The booster was a cluster of eight H-1 engines. (See table 2-51 for details
on this and other Apollo-Saturn developmental flights.)
Nov. 15, 1961 In a letter to NASA Associate Administrator Robert C. Seamans, Houbolt
made his case for the lunar orbit rendezvous mode for Apollo.
Nov. 20, 1961 A working group led by Milton W. Rosen, director of launch vehicles and
propulsion in the Office of Manned Space Flight (OMSF), reported that the
direct ascent mode for a lunar landing was the most promising, using the pro-
posed Nova.
Nov. 28, 1961 NASA chose the Space and Information Systems Division of North
American Aviation to design and build the two-module Apollo spacecraft.
North America's proposal had been selected by technical assessment panels
and a source evaluation board over those submitted by four other teams:
General Dynamics/Astronautics Avco Corporation; General Electric Missile
and Space Vehicle Department-Douglas-Grumman-Space Technology
Laboratories; McDonnell Aircraft Corporation-Lockheed Aircraft
Corporation-Hughes Aircraft Company-Chance Vought; and the Martin
Company. On the previous day, the Apollo spacecraft statement of work had
been expanded substantially. North American's letter contract was signed on
December 12, the definitive contract on August 14, 1963.
Jan. 15, 1962 An Apollo Spacecraft Project Office (ASPO) was established at the Manned
Spacecraft Cemer (MSC), STG's new designation, with Charles W. Frick as
manager.
Jan.-June 1962 Grumman conducted another in-house study of lunar orbit rendezvous
techniques.
Feb. 6, 1962 Houbolt and Charles W. Mathews of MSC made a presentation on lunar or-
bit rendezvous to the Manned Space Flight Management Council.
March 1962 NASA Headquarters approved plans for the development of a Little Joe 11
test launch vehicle with which to verify various Apollo spacecraft systems.
General Dynamics/Convair was awarded a contract to design and manufac-
ture the vehicle on May 11.
March 2-3, 1962 At a meeting at NASA Headquarters, lunar orbit rendezvous was reviewed as
a possible mission mode for Apollo. It would require a single Saturn C-5
(three stages).
Apr. 11, 1962 Kennedy assigned the Apollo program the highest national priority category
(DX) for procurement action.
Apr. 16, 1962 MSC representatives made a lunar orbit rendezvous presentation at MSFC;
additional presentations were made at Headquarters in May.
Apr. 25, 1962 Saturn SA-2 with a water-filled second stage was launched successfully.
June 7, 1962 MSFC's von Braun recommended that the lunar orbit rendezvous mode be
adopted for Apollo.
June 22, 1962 The Manned Space Flight Management Council announced that it favored
lunar orbit rendezvous. Other NASA officials agreed, and on July 11 the
agency announced that this mode had been selected for Apollo. A lunar
module capable of landing two men on the moon's surface and returning
them to the orbiting command and service module would be required.
MANNED
SPACEFLIGHT 183
Table 2-50.
Date Event
July 25, 1962 MSC invited 11 firms to submit proposals due on September 4 for an Apollo
lunar excursion module.
Sept. 17, 1962 Nine new astronauts were added to NASA's flight team.
Sept. 26, 1962 NASA announced plans for constructing the Mississippi Test Facility for
testing the Saturn stages.
Nov. 7, 1962 NASA selected Grumman to build the lunar module. Grumman was chosen
over eight other firms. A definitive contract was signed on March 11, 1963.
Nov. 16, 1962 Saturn SA-3 with a water-filled second stage was launched successfully.
Feb.-March 1963 The MSC Lunar Surface Experiments Panel, formed to study and evaluate
proposals for lunar surface investigations, met for the first time.
Feb. 27, 1963 NASA established an Apollo Mission Planning Panel to develop mission
design, coordinate trajectory analyses, and produce contingency plans for all
manned missions.
March 28, 1963 Saturn SA-4 was launched successfully (last first-stage test of Saturn I).
Sept. 4, 1963 At MSC, a Manned Spacecraft Criteria Board was established to determine
engineering, design, and procedural standards for spacecraft systems.
Sept. 16-18, 1963 The first lunar module mockup review was held at Grumann.
Oct. 18, 1963 NASA selected another 14 astronauts for training for Gemini and Apollo.
Oct. 30, 1963 NASA cancelled plans for four manned earth orbital missions launched by
Saturn I vehicles. The first manned Apollo test flight would be powered by a
Saturn IB.
Nov. 1, 1963 Apollo's launch escape system was successfully tested at White Sands (Pad
Abort-l).
Jan. 29, 1964 Saturn SA-5 with a powered second stage was launched successfully (second
stage put into orbit).
Feb. 3, 1964 NASA selected 14 more astronauts for Gemini and Apollo.
Apr. 14, 1964 FIRE 1, a reentry heating test of an Apollo-shaped vehicle, was carried out
successfully.
Apr. 28-30, 1964 A mockup review of the Block I (earth orbital) Apollo command and service
module (CSM) was held at North American; a second review followed on
July 8-9.
May 28, 1964 The first orbital flight of an Apollo boilerplate model with a Saturn 1 (A-IOI)
took place successfully.
Sept. 30, 1964 A review of a Block II (lunar mission) Apollo CSM mockup was held. NASA
gave North American a formal go-ahead for manufacture on November 23.
Jan. 6-8, 1965 NASA held a preliminary design review of the Block II CSM.
June 29, 1965 NASA announced the selection of six additional astronauts for Apollo; these
newest astronauts were chosen because of their academic training in the
sciences (only four became active).
Nov. 1965-Jan. 1966 The critical design review of the lunar module was conducted by five teams:
structures and properties; communications, instrumentation and electrical
power; stabilization and control, navigation and guidance, and radar; crew
systems; and mission compatibility and operations.
184 NASA HISTORICAL DATA BOOK
Table 2-50.
Chronology of Key Apollo Program Events* (Continued)
Date Event
Nov. 30, 1965 The first of two Apollo mission simulators was shipped from the Link Group
of General Precision to MSC.
Dec. 6-17, 1965 The critical design review of the Block I1 CSM (mockup 27A) was held.
Dec. 15, 1965 In a letter to North American President J. L. Atwood, Apollo Program
Director Samuel C. Phillips expressed NASA's dissatisfaction with the firm's
progress with the manufacture of the Apollo spacecraft and the Saturn S-II
stage.
Jan. 14, 1966 Grumman's lunar module contract was converted from cost-plus-fixed-fee to
cost-plus-incentive-fee; North American's contract was likewise changed on
the 21st.
Feb. 26, 1966 A suborbital launch vehicle development test of the Saturn IB was carried
out; an Apollo CSM served as payload (AS-201).
July 5, 1966 A successful orbital launch vehicle development test of the Saturn IB (for a
time called Uprated Saturn I) was conducted (AS-203).
Aug. 25, 1966 A second suborbital test of the Saturn IB was launched successfully (AS-202).
Oct. 19, 1966 It was announced that the crew of the first manned Apollo mission, AS-204,
would be Virgil I. Grissom, Edward H. White, II, and Roger B. Chaffee. The
earth-orbital flight was scheduled for February 12, 1967.
Jan. 23, 1967 A Lunar Mission Planning Board established at MSC met for the first time.
Jan. 27, 1967 During a pre-launch test of AS-204 at Launch Complex 34 at the Kennedy
Space Center, fire swept through the command module, killing all three crew
members (Grissom, White, and Chaffee). The next day a review board was
formed to investigate the accident; Floyd L. Thompson, director of Langley,
was appointed chairman. On February 1, MSC instructed contractors and
other government agencies to stop all MSC-related manned testing in high-
oxygen environments.
Feb. 5, 1967 The Apollo 204 Review Board submitted its final report. Arcs from electrical
wiring in an equipment bay on the command module had started the fire; in
the 100 percent oxygen atmosphere the crew had died of asphyxia due to in-
halation of toxic gases. The board's report included a number of significant
suggestions for hardware and operational changes.
Apr.-Aug. 1967 A NASA task team charged with overseeing Block II CSM redefinition
worked at North American to provide input on detail design, overall quality
and reliability testing, and scheduling. Astronaut Frank Borman led the
group.
Nov. 9, 1967 Apollo 4, the first "all-up" orbital test of the Saturn V vehicle, was conducted
successfully. The command module's reentry simulated the most severe con-
ditions that were expected on a lunar-return trajectory.
Jan. 22, 1968 Apollo 5, the first development test flight that included a lunar module in the
payload, was launched successfully with a Saturn lB. The lunar module,
S-IVB stage, and launch vehicle instrument unit were put into orbit. A second
unmanned lunar module flight was cancelled.
March 6-7, 1968 Design certification reviews of CSM 101 (to be flown on the first manned
Apollo flight) and LM-3 were held at MSC.
MANNED
SPACEFLIGHT 185
Table 2-50.
Chronology
of KeyApolloProgramEvents*
(Continued)
Date Event
Apr.4,1966 The Saturn V-launched Apollo 6 mission did not meet its primary objectives
because of launch vehicle malfunctions. The CSM was put into orbit and
recovered from the Pacific.
Aug.9-17,
1968 In a series of top-level meetings initiated by ASPO Manager George Low, it
was decided that the second manned Apollo mission (Apollo 8) would be a
lunar-orbit mission if all went well on the Apollo 7 earth orbital flight. Plans
made in late 1967 did not call for a lunar mission until the fourth manned
flight, but Low and others argued that if they were to meet the end-of-the-
decade deadline they would have to seek as soon as possible firsthand
knowledge of communications, navigation, and thermal control in deep
space. The decision for a December 1968 lunar orbit mission was not made
public until November 12.
Oct.3,1968 The flight readiness review for Apollo 7 was held at KSC, with crew and ve-
hicle being declared ready for the mission.
Oct. 11-22, 1968 Apollo 7, the first manned Apollo flight, was conducted successfully with
Astronauts Walter Schirra, Donn F. Eisele, and R. Walter Cunningham at
the controls (before the 204 fire and the death of the crew, these three men
had been scheduled to pilot the second flight). During their nearly 11 days in
orbit, the crew made a live television broadcast from their spacecraft and per-
formed all their test objectives. The Block II CSM was launched by a Saturn
IB (see table 2-52).
Dec. 21-27, 1968 Apollo 8 became the first manned spacecraft to circle the moon. Frank Bor-
man, James Lovell, and William Anders reached the moon in 69 hours and
orbited the satellite for 20 hours. Splashdown was in the Pacific (see table
2-53.
186 NASA HISTORICAL DATA BOOK
Table 2-51.
Oct. 27, 1961 SA-1 Successful launch vehicle development test (Saturn
Nov. 16, 1962 SA-3 Successful launch vehicle development test (Saturn
Aug. 28, 1963 Little Joe I1 (LJ-II) Successful flight qualification test of Little Joe I1
Nov. 7, 1963 Pad Abort-1 (boiler- Successful test of Apollo launch escape system (LES)
(White Sands) plate spacecraft 6) with a boilerplate model of the spacecraft (no launch
vehicle was required).
Apollo A-O01 Successful suborbital LES test, using the LJ-II and a
May 13, 1964
(White Sands) (BP-12) CSM boilerplate model.
May 28, 1964 Apollo A-101 Orbital compatibility test of an Apollo boilerplate
(SA-6) (BP-13) model and a Saturn 1; reentry took place on June 1 after
(ETR)
54 orbits.
Dec. 8, 1964 Apollo A-002 Successful test of the Apollo LES using L J-11.
May 19, 1965 Apollo A-003 During a planned high-altitude test of the Apollo abort
(White Sands) (BP-22) system, the LJ-II vehicle malfunctioned; the LES func-
tioned and lifted the spacecraft clear of the defective
launcher.
Table 2-51.
June 29, 1965 Pad Abort-2 Successful test of the LES to function from the launch
(White Sands) (BP-23A) pad; no launch vehicle was required.
Jan. 20, 1966 Apollo A-004 Successful medium-altitude test of the Apollo LES, us-
(White Sands) ing an LJ-II.
Aug. 25, 1966 AS-202 Successful suborbital launch vehicle development test
(ETR) (CSM-O 11 ) (Saturn IB); the Apollo heatshield and the spacecraft
rapid restart capability were also evaluated; the com-
mand module was recovered.
Jan. 22, 1968 Apollo 5 Successful orbital launch vehicle development test
(ETR) (AS-204) (LM-I) (Saturn IB) and spacecraft development test; the LM
was tested for the first time and recovered on Jan. 24.
Table 2-52.
Apollo 7 Characteristics
Table
2-53.
Apollo 8 Characteristics
Table 2-54.
Size and Performance Comparisons of Mercury, Gemini, and Apollo
Apollo Apollo
Mercury Gemini CSM LM
Crew size 1 2 3 2
Suit usage cabin backup cabin backup cabin backup cabin backup
ejection EVA crew transfer
EVA crew transfer surface
From Maxime A. Fagnet, "An Overview of United States Manned Spaceflight from Mercury to the
Shuttle," paper, 32d Congress, International Astronautical Federation, Rome, Sept. 6-12, 1981.
MANNED
SPACEFLIGHT 191
Table2-55.
MajorSubsystem
Comparison
forMercury,
Gemini,
andApollo
Mercury Gemini Apollo Apollo
CSM LM
Life support 100°70 02; water 100% O:; same as 10007o 02; water
evaporators for radiator and Gemini sublimators for
cooling evaporators for cooling
cooling
Table 2-55.
From John H. Boynton and Kenneth S. Kleinknecht, "Systems Design Experience from Three Manned
Space Programs," paper 69-1077, AIAA 6th Annual Meeting, Anaheim, CA, Oct. 20-24, 1969.
Table 2-56.
Major Contractors for Mercury, Gemini, and Apollo Spacecraft
CMheatshield
Avco Corp., Space
Systems Div.
Electro-Mechanical data
ECS ECS
Garrett Corp., environmental
AiResearch Manufacturing control system
Co. (ECS)
Table 2-56
Major Contractors for Mercury, Gemini, and Apollo Spacecraft-- (Continued)
Table 2-56.
Major contractors for Mercury, Gemini, and Apollo Spacecraft (Continued)
Contractor Mercury Gemini Al_ollo
Thiokol Chemical Corp. retrograde rocket retrograde rockets launch escape tower
motor
SPACE SCIENCE
AND APPLICATIONS
With the launching of small sounding rockets in the 1940s, scientists were able
to extend their observations and measurements into the upper atmosphere. When
larger rockets became available, they were put to work carrying sophisticated instru-
ment packages to even higher altitudes. Rockets and spacecraft were "revolutionary
tools," which were used on a large scale by the National Aeronautics and Space Ad-
ministration (NASA) when the agency was established in 1958. _ Taking advantage
of the momentum inspired by the International Geophysical Year, which saw the
launching of the first Explorer and Vanguard satellites, NASA managers organized
a space science program around the several disciplines that would benefit from
sounding rocket, satellite, probe, and manned spaceflight projects. The agency
made a conscious effort to build its scientific programs along the guidelines sug-
gested by the nation's leading scientists, and continued throughout its first 10 years
to seek outside advice and support. Applying this new wealth of scientific return to
practical uses was another part of NASA's mandate as a body supported by public
funds.
The legislation that called for the establishment of a civilian space agency
directed the new administration to expand the body "of human knowledge of
phenomena in the atmosphere and space," a broad dictim. 2 Most of the scientists
and engineers who hoped to achieve this goal came to NASA from other government
agencies, namely the Naval Research Laboratory, the Jet Propulsion Laboratory,
and the National Advisory Committee for Aeronautics. Members of the Naval
Research Laboratory's Vanguard division and the upper atmosphere sounding
rocket team formed the nucleus around which the Goddard Space Flight Center
(originally called the Beltsville Space Center) in Maryland was built. Goddard's per-
sonnel were responsible for many of NASA's unmanned spacecraft projects and
sounding rocket experiments, in addition to operating a satellite tracking network.
Besides working in the field of propulsion, specialists at the Jet Propulsion
Laboratory (JPL) in Pasadena, California, were also involved with the Army's early
satellite program. When JPL was assigned to NASA in 1958 as a contractor facility,
its scientists became part of the agency's unmanned lunar and planetary exploration
team. JPL also found a network for communicating with lunar and planetary
spacecraft. The Langley Research Center, which had been part of the National Ad-
visory Committee for Aeronautics, also played a role in the unmanned space pro-
gram when its personnel began taking part in NASA's lunar and planetary projects
197
198 NASA HISTORICAL DATA BOOK
in the 1960s. Unmanned space science payloads were launched from Wallops Sta-
tion, the Eastern Test Range, and the Western Test Range.*
Along with facilities and personnel, NASA inherited some ongoing space
science projects-the Vanguard satellite, various sounding rocket investigations,
and the Air Force's Pioneer deep space probe. Building on these activities, NASA's
managers and scientists were able to shape a space science program that embraced
many areas of research: geodesy, meteorology, atmospheric and ionspheric physics,
magnetospheric research, lunar and planetary science, solar studies, galactic
astronomy, and bioscience. For management purposes, NASA throughout its
reorganizations of the space science and applications program grouped these
disciplines and their related flight projects into several divisions--physics and
astronomy, lunar and planetary, life sciences, meteorology, communications, and
applications. Thus organized and funded, "NASA proceeded to attack the scientific
problems of the atmosphere and space that the scientists.., deemed most impor-
tant and most likely to produce significant new information," with the approval of
Congress. 3
To ensure that NASA's space science program reflected the interests and con-
cerns of the nation's scientists, the agency's managers invited several advisory groups
to take part in program planning. The National Academy of Science's Space Science
Board was an important and influential source of input, but NASA also established
a series of advisory committees that involved a broader segment of the scientific
community. The subcommittees of the Space Science and Applications Steering
Committee were highly specialized groups that could furnish advice in a number of
particular fields, while an Astronomy Missions Board and a Lunar and Planetary
Missions Board offered broader commentary on NASA's programs. Working rela-
tions between NASA and its various advisory bodies were not always smooth, and
friction among those bodies was not unknown. But, it is generally agreed that the
content of NASA's science programs accurately mirrored the priorities and objec-
tives of most American space scientists. In addition to the scrutiny given them by ad-
visory groups, NASA's space activities were analyzed by the president's science ad-
viser, the Space Science and Technology Panel of the President's Science Advisory
Committee, the Subcommittee on Space Science and Applications of the House
Committee on Science and Astronautics, and the Senate Committee on Aeronautical
and Space Sciences.
"Pure scientists" do not always concern themselves with the practical applica-
tions of their research, but NASA managers in justifying the budgets for their
science programs often were forced to explain to Congress what the public could ex-
pect in return for tax dollars spent on space science. As funds for the space program
and other large government programs not directly related to defense or public
welfare became harder to obtain in the late 1960s and as the Apollo lunar expedi-
tions took more and more of the agency's budget, it became increasingly important
to realize some practical benefits from scientific projects. NASA had to balance the
desirability of basic research, which could answer fundamental questions about the
nature of matter and the forces of the universe and which might have some unfore-
seen practical benefits, and the need for applied research, which could be geared
toward a planned application. Both were critical components of the agency's scien-
* See chapter 1 for details on the launch vehicles used for space science and applications missions.
SPACE
SCIENCE
AND APPLICATIONS 199
tific program? Meteorology and communications are two obvious fields to which
NASA's scientific research was applied that benefited the public. Land and water
management, cartography, forestry, and aircraft design are other examples. NASA,
a research and development organization, relied on other government agencies, in-
dustry, and universities for the actual appliction of its work to products or services.
Space science was always an integral part of NASA's organization. Until late
1961, space science was part of the Office of Space Flight Development, becoming a
directorate by itself in a November 1961 reorganization of the agency. Homer E.
Newell, Jr., led the space science team from 1958 until October 1967. In March
1960, life sciences was organized as a separate directorate, but in November 1961 it
became part of the space science program. There were separate directors for space
science and for applications from November 1961 until June 1963, when the two in-
terests were combined into one office. Directors and division directors were respon-
sible to Associate Administrator Newell for their various program areas and flight
projects. In October 1967, John E. Naugle became responsible for the management
of space science and applications as the associate administrator. 5 (See table 3-1 for
details on how the organization of space science and applications evolved through
1968.)
NASA's space science missions experienced their share of failures during the late
1950s, but by the end of the next decade the agency saw 80.8 percent of its scientific
and applications experiments to successful or partially successful conclusions (this
figure does not include sounding rocket projects). However, there was more to the
success story than perfect launches and the operation of complex equipment.
Beyond the tally of successful flights were the many discoveries made in several
areas of study as a result of new data returned from scientific satellites and probes
and the practical applications of these discoveries that have made new products and
services possible. Add to this the overall progress made in the earth and planetary
sciences that have advanced man's knowledge and understanding of the universe and
opened new fields for investigation. While scientific and applications missions con-
sistently took second place to manned spaceflight in NASA's search for funds, for
most of the agency's first 10 years it was the science and applications program that
provided the larger return on the nation's investment in space. 6
200 NASA HISTORICAL DATA BOOK
Table 3-1.
Phase I
Oct. 1958-Jan. 1960
Phase 1I
Feb. 1960-Oct. 1961
Assistant Director, Applications and Manned Flight Programs (NeweU D. Sanders); office
dropped in 1961 and replaced by Advanced Technology Programs (Sanders) and Manned Space
Flight Programs (George M. Low)
Assistant Director, Bioengineering (Alfred M. Mayo); office dropped in mid-1961 (Mayo became
acting director for life sciences)
Assistant Director, Grants and Contracts (Freeman H. Quimby); office dropped in mid-1961
Assistant Director, Program Planning and Coordination (G. Dale Smith); established in mid-1961
Phase III
Nov. 1961-Oct. 1963
Administrator/Deputy Administrator
Associate Administrator
Director, Launch Vehicles and Propulsion (Donald H. Heaton; Richard B. Morrison, June
1962)
SPACE
SCIENCE
ANDAPPLICATIONS 201
Table
3-1.
FivePhases
of Space
(Continued)
Director,
Geophysics
andAstronomy Programs(JohnF.Clark;
JohnE.Naugle,
May1962)
Director,
Program
ReviewandResources Management (John
D.Nicolaldes)
Director,
Lunar
andPlanetaryPrograms(Oran W.Nicks)
Director,
Bioscience
Programs(OrrE.Reynolds)
Director,
Applications
(Stoller)
Director,
Meteorological
Systems (Morris
Tepper)
Director,
Communications
Systems (LeonardJaffe)
Director,
Program
ReviewandResourcesManagement (Carl
Freedman)
Director,
Future
Applications
(vacant);
office
droppedinNov.1962
Director,
Industrial
Applications
(Louis
B.C.Fong, Nov.1962);
office
dropped
inApril1963
Phase
IV
Nov.1963-Sept.
1967
Administrator/Deputy
Administrator
Associate
Administrator
Associate
Administrator,
Space
Science
andApplications
(Newell)
DeputyAssociate
Administrator,
SpaceScience
andApplications
(Cortright)
Deputy Associate
Administrator
(Sciences),
Space ScienceandApplications
(Naugle);
office
established
inMay1966
Director,
Sciences
(Clark;
Naugle,acting,
July1965);office
dropped
inMay1966
Director,
Applications
(Robert
F.Garbarini);
office
replaced
in1964
(Garbarini
became
direc-
torofengineering)
Division
Director,
Bioscience
Programs(Reynolds)
Division
Director,
Communications
andNavigation
Programs (Jaffe);
officedropped
in1966
Director,
Physics
andAstronomy
(Naugle;
Jesse
Mitchell,
May1966)
Director,
Grants
andResearch
Contracts
(Smull);
officedroppedin1967
Director,
LaunchVehicles
andPropulsion
Programs (Morrison;VincentL.Johnson,
Aug.
1964)
Director,
LunarandPlanetary
Programs
(Nicks)
Division
Director,
MannedSpaceScience
(Willis
B.Foster);office
droppedin1967
Division
Director,
Meteorological
Programs(Tepper);
office
droppedin1966
Division
Director,
ProgramReview
andResources
Management (EldonD.Taylor)
Director,
Voyager
Program(Nicks);
officeestablished
inmid-1967
Phase
V
Oct.1967-Dec.
1968
Administrator/Director
Administrator
Associate
Administrator
Associate
Administrator,
Space
Science
andApplications
(Naugle)
DeputyAssociate
Administrator,
SpaceScience
andApplications
(Nicks)
DeputyAssociate
Administrator
(Sciences),
SpaceScience
andApplications
(Naugle;
Henry
J.
Smith,April1968)
202 NASA HISTORICAL DATA BOOK
Table 3-1.
Five Phases of Space (Continued)
Assistant Associate Administrator (Manned Flight Experiments), Space Science and Applications
(Foster); office dropped in mid-1968
Director Advanced Programs (Pitt Thome)
Director Program Review and Resources Management (Taylor)
Director Bioscience Programs (Reynolds)
Director Space Applications (Jaffe)
Director Launch Vehicles and Propulsion Programs (Joseph B. Mahon)
Director Voyager Program (Donald P. Hearth); office dropped in late 1968
Director Lunar and Planetary Programs (Hearth)
Director Physics and Astronomy Programs (Mitchell)
Table 3-2.
Science and Applications
Satellites and Probes, 1958-1968
Number of Missions
Mission Type Successful a Partially Unsuccessful a Total
Successful a
aAs reported in Kennedy Space Center, A Summary of Major NASA Launchings, KSC Historical,
report 1 (Kennedy Space Center, rev. 1970).
blncludes a number of international missions.
Clncludes Telstar and INTELSAT.
SPACE SCIENCE AND APPLICATIONS 203
BUDGET
Each year, NASA's managers confronted the Bureau of the Budget and
members of Congress with their wish list of scientific projects.* They needed funds
for basic research, for the development of spacecraft and experiment hardware, and
for launch vehicles. President John F. Kennedy's decision in May 1961 to assign
NASA the task of landing a man on the moon before the end of the decade pushed
science projects that did not directly support the lunar landing into a decidedly sec-
ond place in the budget queue. For most of the agency's first decade, Apollo, the
manned lunar venture, would have priority. However, NASA's scientists still
managed to assemble a respectable program in several fields of research. For each of
these disciplines, budget tables are provided in this chapter, along with tables for in-
dividual flight projects (e.g., in the discipline of lunar and planetary studies, Ranger
was a flight project.)t For a more detailed breakdown of flight projects budgets con-
sult the NASA annual budget. In addition to funds for flight projects, each
discipline was also granted money for supporting research and advanced studies.
The following categories represent the changing organization of NASA's space
science and applications program. Review the many bottom notes of the budget
tables carefully before making conclusions about totals for any particular project or
fiscal year. Summary information can be found in tables 3-3 and 3-4.
* It would be useful to review the introduction to the budget section in chap. 1 for general informa-
tion on NASA's budget and on the sources and format used for the budget tables in this book.
t If a project's activity were limited to two years, it is included in a miscellaneous category for the ap-
propriate discipline.
204 NASA HISTORICAL DATA BOOK
Table 3-3.
Total Space Science and Applications Funding History _
a For those years before there was an Office of Space Science and Applications, totals have been figured
by adding together the funds requested, authorized, or programmed for the various space science, ap-
plications, and research projects; see following notes for details.
b Includes $3 995 000 for research grants and contracts, which was used for "the conduct of fundamen-
tal and applied research necessary for advancing aeronautical and space technology." Research grants
and contracts were replaced in part by the sustaining university program in the FY 1965 budget estimate.
In the FY 1963 and 1964 estimates, there was no corresponding budget item. The total also includes
$21 944 000 for Vanguard, which in 1959 was funded as a program separate from scientific satellites.
c Includes $4 869 370 for research grants and contracts; see further note b above.
d Includes $10 000 000 for research grants and contracts; see further note b above. After the Authoriza-
tion Conference Committee approved the $131 000 000 budget for FY 1961, the appropriation con-
ference committee awarded an additional $29 000 000 in a supplemental appropriation in June 1960.
elncludes $5 000 000 for research grants and contracts; see further note b above; this was the amount
established in the FY 1962 budget estimate; by the FY 1963 budget estimate this category had been
dropped.
flncludes $7 600 000 for research grants and contracts; see further note b above.
STotal reduced to $538 000 000 by the appropriation conference committee in October 1967.
SPACE SCIENCE AND APPLICATIONS 205
_ r_
_o o
_o I"-- o_
oo O O ¢',1
oO ¢q ¢q ¢',,I ¢q
d, I I
I I
0 r.- I
e_
.o i_-
M
_I __
_'-6
• ...9."_
_m __I __
r-- o
_1_ r_
_ 0
N_N eq
f_
¢'4 O0 0
¢q
0
f_ I
P_
0"_
i-q
"1= _1
_0_
_o
_.__
_._
_0 _
o_0=_
_0_
o
0_'_
-- _ _ _ _ _ _
._NNN
_mOOO_
206 NASA HISTORICAL DATA BOOK
.u_ 0;
¢4 _ ¢q
O '_
oo o
;u
oa
_d .o
O O
o0
[-
O __, ,, _
_3
E
o .__ _
e N_
- " r;N
_._0_
SPACE SCIENCE AND APPLICATIONS 207
Table 3-5.
Research Grants and Contracts Funding History _
(in thousands of dollars)
aTo utilize the capabilities of nongovernment organizations in carrying out research; dropped as a
category by FY 1963.
blncludes $966 510 provided under salaries and expenses.
Clt was estimated in the FY 1962 budget estimate that $5 000 000 would be programmed in FY 1961 for
research grants and contracts; this category had been dropped by the FY 1963 estimate.
Table 3-6.
Physics and Astronomy (Scientific Satellites) Funding History a
(in thousands of dollars)
aln the FY 1961-63 budget estimates, this program was called scientific satellites; in the FY 1964-65
estimates it was renamed geophysics and astronomy; it was changed to physics and astronomy in the FY
1966 estimate.
bIncludes $21 944 000 for Vanguard, which in 1959 was funded as a program separate from scientific
satellites.
c FY 1960 appropriation reduced to $130 000 000 by the appropriations conference committeee in Oc-
tober 1967.
208 NASA HISTORICAL DATA BOOK
Table 3-7.
Physics and Astronomy Supporting Research and
Technology and Advanced Studies Funding History a
aprior to the FY 1964 budget estimate, supporting research was budgeted as advanced research (FY
1962-63), development of advanced instrumentation/advanced technical development (FY 1961-63), and
scientific and technical studies (FY 1961).
blncludes $1 520 000 for development of advanced instrumentationadvanced technical development,
and $1 155 00 for scientific and technical studies.
c Includes $2 332 000 for development of advanced instrumentationadvanced technical development,
and $1 680 000 for advanced research.
a Includes $6 000 0120 for development of advanced instrumentation/advanced technical development,
and $2 000 000 for scientific and technical studies.
elncludes $6 207 000 for development of advanced instrumentation/advanced technical development,
and $6 794 000 for advanced research.
flncludes $8 326 000 for development of advanced instrumentation/advanced technical development,
and $4 043 000 for advanced research.
Includes $16 261 000 for development of advanced instrumentation/advanced technical development,
and $17 418 000 for advanced research.
SPACE SCIENCE AND APPLICATIONS 209
Table 3-8.
Total Physics and Astronomy Flight Projects Funding History a
(in thousands of dollars)
fThe House authorization committee suggested that failures with the Orbiting Astronomical Obser-
vatories and Orbiting Geophysical Observatories warranted a decrease in the funds requested. The Senate
authorization committee, however, restored the funds.
Table 3-9.
Physics and Astronomy Soundings Funding History a
(in thousands of dollars)
aBefore the FY 1964 estimate, physics and astronomy soundings were budgeted under the general
category sounding rocket program (see table 3-57).
210 NASA HISTORICAL DATA BOOK
Table 3-10.
Explorer-Class Satellites Funding History a
(in thousands of dollars)
alncluded in this category, in addition to Explorer satellites, are funds spent from FY 1959-1963 on
satellite projects that were listed in the budget estimates under names other than Explorer but that subse-
quently were flown as Explorers, and some projects that were not flown but were in the Explorer class.
b Includes $5 000 000 for Explorer 6, $557 000 for an ionospheric beacon satellite, $220 000 for an
ionospheric direct measurements satellite, $180 000 for an advanced radiation belt satellite, $145 000 for
an atmospheric structures satellite, and $150 000 for a radiation belt satellite.
Clncludes $2 267 000 for Explorer 6, $1 420 000 for Explorer 7, $51 000 for a 3.66-meter sphere,
$565,000 for a radiation balance experiment, $829 000 for an energetic particles satellite, $2 487 000 for
an ionospheric beacon satellite, $1 942 000 for an ionospheric direct measurements satellite, $565 000 for
an atmospheric structures satellite, $2 185 000 for a gamma ray astronomy satellite, $225 000 for a Scout
micrometeroid satellite; $125 000 for an air density drag measurements satellite, and $304 000 for a fixed-
Table 3-11.
Orbiting Solar Observatories Funding History
(in thousands of dollars)
alncluded $550 000 for a solar observatory satellite, and $1 930 000 for a solar geophysical satellite.
bIncludes $11 687 000 for an advanced solar observatory.
Table 3-12.
Orbiting Astronomical Observatories Funding History
(in thousands of dollars)
Table 3-13.
Orbiting Geophysical Observatories Funding History
(in thousands of dollars)
Table 3-14.
Miscellaneous Physics and Astronomy Projects Funding History
(in thousands of dollars)
alncluded $1 468 000 for general payload instrumentation and $21 944 000 for Vanguard, which in
1959 was funded as a program separate from scientific satellites.
b lncludes $2000 for a Jupiter nuclear emulsions project, $10 000 for integration of the emulsion
package, $445 000 for a recoverable nuclear emulsions probe, and $197 000 for electron density profile
probes.
c Includes $260 000 for general payload instrumentation and $1 220 000 for a geodetic satellite.
alncludes $89 000 for modifying an X-15 for an astronomy payload, $167 000 for Vanguard 3,
$2 673 000 for international ionospheric satellite UK-I, $60 000 for international project satellite UK-2,
and $4 571 000 for electron density profile probes.
e Includes $1 231 000 for international ionospheric satellite UK 1, $1 000 000 for international project
satellite UK-2, $420 000 for international project satellite UK-3, $1 330 000 for a recoverable nuclear
emulsions probe, and $193 000 for electron density profile probes.
fFor international satellite projects.
glncludes $338 000 for international ionospheric satellite UK-1, $5 247 000 for international project
satellite UK-2, $1 654 000 for international project satellite UK-3, $1 719 000 for international satellite
no. 4, and $4 397 000 for geoprobes.
hlncludes $7 000 000 for international satellite projects and $6 200 000 for geodesy projects.
iFor Sunblazer, a small interplanetary probe project that was not authorized for budgetary reasons.
Table 3-15.
Physics and Astronomy Data Analysis Funding History
(in thousands of dollars)
Table 3-16.
aAfter the authorization conference committee approved the $45 000 000 budget for FY 1961, the
appropriation conference committee awarded an additional $5 000 000 in a supplemental appropriation
in June 1960.
bFY 1968 appropriation was reduced to $125 000 000 by the appropriation conference committee in
October 1967.
Table 3-17.
Lunar and Planetary Supporting Research and
Technology and Advanced Studies Funding History a
(in thousands of dollars)
cprior to the FY 1964 budget estimate, supporting research was budgeted as advanced technical
development (FY 1959-63) and advanced research (FY 1960-63).
bFor advanced technical development.
CIncludes $6 449 000 for advanced technical development and $1 858 000 for advanced research.
_For advanced technical development.
e Includes $11 670 000 for advanced technical development and $4 432 000 for advanced research.
f Includes $12 080 000 for advanced technical development and $6 023 000 for advanced research.
gIncludes $17 000 000 for advanced technical development and $15 000 000 for advanced research.
h Includes $12 000 000 budgeted for advanced planetary missions technology, a budget item introduced
in the FY 1970 estimate.
214 NASA HISTORICAL DATA BOOK
Table 3-18.
Total Lunar and Planetary Flight Projects Funding History
(in thousands of dollars)
_-- 23 780 a
1959 ---
_-- 41 690
1960 ---
1961 36000 a __- 73 917
1962 141 796 --- 150 941
1963 241 560 231 160 200597
1964 302 600 254 400 183 762
1965 282 300 265000 h 181 887
1966 178 815 176 315 c 181 300
1967 157 800 170 800 161 800
1968 121 100 111 000 127000
Table 3-19.
Pioneer Lunar Probes (Atlas-Able) Funding History
(in thousands of dollars)
___ 6237 a
1959 ---
1960 7140 b 7140 b 18 349 ¢
___ 5975 ¢
1961 ---
Table 3-20.
--- 19 542
1960 ---
--- 45066
1961 ---
1962 64 754 --- 63 430
1963 44 022 --- 88 816
1964 90000 65000 30 306
1965 10 800 10 800 11 037
1966 1415 1415 1000
SPACE SCIENCE AND APPLICATIONS 215
Table 3-21.
Surveyor Funding History
(in thousands of dollars)
Table 3-22.
Lunar Orbiter Funding History
(in thousands of dollars)
1963 ...... 4
1964 ...... 20 000
1965 49 300 44 300 49 500
1966 37 000 36 000 58 081
1967 24 600 24 600 26 000
1968 10 000 10 000 9500
Table 3-23.
Prospector Funding History
(in thousands of dollars)
aDuring the authorization process, funds for Prospector, a proposed heavy lunar lander, were denied
because of its high cost and because the proposed launch vehicle, Saturn, would not be ready for some
time.
216 NASA HISTORICAL DATA BOOK
Table 3-24.
aFund were requested and authorized for unspecified deep space probes.
b For Pioneer 5 a precursor to the later Pioneer probe series.
CFor a magnetometer probe, Explorer 10, the program's second interplanetary probe.
aFunded by the physics and astronomy budget in FY 1968-1969 estimates.
Table 3-25.
Mariner Funding History
(in thousands of dollars)
as10 100 1300 for two Mariner Mars flyby probe projects was not authorized because current funding
already provided for a 1969 Mariner Mars project and because the Voyager program would also provide
for the detailed exploration of Mars.
SPACE
SCIENCE
ANDAPPLICATIONS 217
Table3-26.
VoyagerFundingHistory
a
(inthousands
of dollars)
Year Request Authorization Programmed
1962 349 ...... b
1963 6800 ...... e
1964 ___d ...... e
1965 ---f --- 7168
1966 43000 43000 17097g
1967 10000 23000 12 670
1968 71 500 g 42000 h 350
aNot to be confused with the Voyager interplanetary probe series of the 1980s; these funds were
budgeted for a large Mars lander project, which was replaced by the Viking project in 1969.
b $330 000 from supporting research and technology funds was programmed for a Voyager study, but
no funds were programmed for a Voyager flight project.
¢$3 069 000 from supporting research and technology funds was programmed for advanced studies,
which included a Voyager study; this category was not broken down further in the estimate.
d $900 000 of the supporting research and technology request was for a Voyager study; no funds were
requested for a flight project.
e$2 236 000 from supporting research and technology funds was programmed for advanced studies,
which included a Voyager study; this category was not broken down further in the estimate.
fAlthough no funds were requested for a Voyager flight project, funds from the supporting research
and technology budget were designated for a Voyager study and for sterilization studies; this category
was not broken down further.
s Voyager was listed as a separate program in the FY 1968-1970 budget estimates rather than as a lunar
and planetary flight project.
h The Senate authorization committee initially declined any funds for Voyager because of the large-
scale expenditures it would require over the next several years, but in response to the House authorization
committee's reasoning that the exploration of the nearby planets was one of the most significant objec-
tives of the space program the Senate committee agreed to an authorization of $42 000 0O0. Subsequent-
ly, the House appropriations committee in August 1967 denied funds for Voyager, recognizing the finan-
cial burdens of the Vietnam conflict and other domestic needs; but the Senate appropriations committee
in October 1967 restored $36 000 000 to the appropriation. Later in October, the appropriations con-
ference committee denied funding, thereby terminating the program.
Table 3-27.
alncludes $2 843 000 for Thor-Able, $3 500 000 for Atlas-Agena, and $11 200 000 for unspecified
payloads.
bIncludes $9 500 000 for Atlas-Agena and $26 500 000 for unspecified payloads.
CThis is the estimated amount programmed for FY 1964 as found in the FY 1965 budget estimate for
manned space science; by the FY 1966 estimate this item had been dropped. The manned space science
project dealt with the engineering and operational development of manned spacecraft systems.
d For manned space science.
218 NASA HISTORICAL DATA BOOK
Table 3-28.
Lunar and Planetary Data Analysis Funding History
(in thousands of dollars)
Table 3-29.
Total Meteorology Funding History a
(in thousands of dollars)
aFrom FY 1959 to 1967, meteorology was funded as a program with research and flight project funds
as part of the Office of Applications or the Office of Space Science and Applications. In the FY
1968-1970 budget estimates, meteorology flight projects were funded as part of OSSA's space applica-
tions program. Research funds for meteorology came from the space application program's supporting
research and technology budget.
bFrom the space applications budget; see note a below.
SPACE
SCIENCE
ANDAPPLICATIONS 219
Table3-30.
Meteorology
Supporting
Research
andTechnology
andAdvanced Studies Funding History
(in thousands of dollars)
aprior to the FY 1964 budget estimate, supporting research was budgeted as advanced technical
development (FY 1959-63) and advanced research (FY 1960-63).
bFor advanced technical development.
Clncludes $1 706 000 for advanced technical development and $1 331 000 for advanced research.
dFor advanced technical development.
elncludes $3 350 000 for advanced technical development and $1 870 000 for advanced research.
flncludes $3 350 000 for advanced technical development and $1 300 000 for advanced research.
gIncludes $9 605 000 for advanced technical development and $1 808 000 for advanced research.
hAs of the FY 1968 budget estimate, funds for meterology research came from the space applications
program's supporting research and technology budget.
iAuthorized as space applications supporting research and technology, of which meteorology was a
part.
Table 3-31.
Total Meteorology Flight Projects Funding History
(in thousands of dollars)
aIncludes $5 700 000 for launch vehicles for the flight research program.
bin the FY 1968-1970 budget estimates, meteorology flight projects were funded as part of OSSA's
space applications program.
220 NASA HISTORICAL DATA BOOK
Table 3-32.
Soundings (Meteorology) Funding History a
aSee also the meteorology projects funded under the sounding rocket program, FY 1959-1963 (table
3-67).
Table 3-33.
TIROS-TOS Funding History
(in thousands of dollars)
Table 3-34.
Nimbus Funding History
(in thousands of dollars)
Table 3-35.
Flight Experiments (Meteorology) Funding History
(in thousands of dollars)
Table 3-36.
Cooperative Applications Satellite (French Satellite FR-2) Funding History a
(in thousands of dollars)
aA joint American-French project that culminated in the launching of the French meteorology satellite
CAS-1 (Eole) in 1971.
Table 3-37.
Communications Total a
(in thousands of dollars)
a From FY 1959 to 1966, the communications program (with research and flight project funds) was part
of the Office of Applications or the Office of Space Science and Applications. As of FY 1967,
meteorology and Applications Technology Satellite (ATS) projects were combined into a single OSSA
program called space applications; in the FY 1968-1970 budget estimates, communications was also part
of this program.
bAfter the authorization conference committee approved the $5 600 000 budget for FY 1961, the ap-
propriations conference committee awarded an additional $24 000 000 in a supplemental appropriation
in June 1960.
c Includes research funds for communications and the Applications Technology Satellite.
dFrom the space applications budget.
eAuthorized as space applications, of which communications was a part.
222 NASAHISTORICAL
DATABOOK
Table 3-38.
Communications Supporting Research and Technology and
Advanced Studies Funding History a
(in thousands of dollars)
aprior to the FY 1964 budget estimate, supporting research was budgeted as advanced technical
development (FY 1959-63) and advanced research (FY 1960-63).
bFor advanced technical development.
Clncludes $705 000 for advanced technical development and $817 000 for advanced research.
dFor advanced technical development.
e Includes $790 000 for advanced technical development and $1 250 000 for advanced research.
flncludes $3 650 000 for advanced technical development and $800 000 for advanced research.
glncludes $2 473 000 for advanced technical development and $2 688 000 for advanced research.
hFor communications and applications technology satellite.
i As of the FY 1968 budget estimate, funds for supporting research for communications and navigation
came from the space applications program's supporting research and technology budget.
JAuthorized as space applications supporting research and technology, of which communications was a
part.
Table 3-39.
Total Communications Flight Projects Funding History
(in thousands of dollars)
alncludes $2 150 000 for boosters and $46 000 for tracking and communications for the flight research
program.
blncludes $1 300 000 for tracking and communications for the flight research program.
aAs of the FY 1968 budget estimate, communications flight projects were a part of the space applica-
tions program.
SPACE
SCIENCE
ANDAPPLICATIONS 223
Table3-40.
EchoFundingHistory
(in thousands of dollars)
alncludes $3 200 000 for Thor and $2 200 000 for Thor-Agena launch vehicles.
blncludes $400 000 for Thor launch vehicle.
Clncludes $1 000 000 for Thor and $4 800 000 for Thor-Agena launch vehicles.
dIncludes $500 000 for Thor-Agena launch vehicle.
Table 3-41.
Relay Funding History
(in thousands of dollars)
alt was estimated in the FY 1967 budget estimate that $200 000 would be programmed in FY 1966 for
Relay; by the FY 1968 estimate this item had been dropped.
Table 3-42.
Rebound Funding History
(in thousands of dollars)
aSupplemental request, of which $1 400 000 was for Atlas-Agena B launch vehicle.
b Includes $5 700 000 for Atlas-Agena B and $3 500 000 for Centaur launch vehicles.
Clt was estimated in the FY 1963 budget request that $13 500 000 would be programmed for Rebound
in FY 1962; by the FY 1964 request this item had been dropped.
d Includes $11 828 000 for Atlas-Agena launch vehicles.
224 NASA
HISTORICAL
DATABOOK
Table3-43.
SyncomFunding History
(inthousands
of dollars)
Year Request Authorization Programmed
1962 ...... 12612
a
1963 22688 b --- 13013
1964 44000 c 37000 d 2511
1965 2000 2000 168
1966 100 100 ___e
Table 3-44.
Miscellaneous Communications Flight Projects Funding History
(in thousands of dollars)
aFor a radiation measurement satellite. It was estimated in the FY 1962 budget that $5 000 000 would
be programmed for a transitional satellite system; by the FY 1963 estimate this item had been dropped.
bFor a transitional satellite system.
CFor an intermediate-altitude satellite.
dFor an early gravity gradient experiment.
Table 3-45.
Total Applications Technology Satellite Funding History _
(in thousands of dollars)
Table 3-47.
Applications Technology Satellite Flight Program Funding History
(in thousands of dollars)
Table 3-48.
Total Space Applications Funding History a
(in thousands of dollars)
aAs of the FY 1968 budget estimate, the space applications program replaced the separate
meteorology, communications, and Applications Technology Satellite programs.
b For industrial applications.
Clt was estimated in the FY 1964 budget estimate that $2 370 000 would be programmed for space ap-
plications in FY 1963; by the FY 1965 estimate this item had been dropped.
d Total reduced to $88 000 000 by the appropriations conference committee in October 1967.
226 NASA
HISTORICAL
DATA BOOK
Table 3-49.
Space Applications Supporting Research and
Technology and Advanced Studies Funding History
(in thousands of dollars)
Table 3-50.
Total Space Applications Flight Projects Funding History _
(in thousands of dollars)
aSee also meteorology (table 3-31), communications (table 3-39), and Applications Technology
Satellite (table 3-47).
b $5 000 000 for Nimbus and $4 700 000 for geodetic satellites was undistributed in the authorization.
Table 3-51.
Geodetic Satellites Funding History a
(in thousands of dollars)
aBefore FY 1966, this flight project was included in the Explorer class of satellites funded by the
physics and astronomy program.
bFunds not distributed in the authorization.
Table 3-52.
Miscellaneous Space Applications Flight Project Funding History
(in thousands of dollars)
aFor a voice broadcasting satellite, which was not authorized because the authorization committee
believed that such a venture should be commercially funded since the project obviously had commercial
applications.
bFor an earth resources survey satellite.
SPACE SCIENCE AND APPLICATIONS 227
Table 3-53.
Total Bioscience (Life Sciences) Funding History
(in thousands of dollars)
Table 3-54.
Bioscience Supporting Research and Technology and
Advanced Studies Funding History a
(in thousands of dollars)
a Before the FY 1964 budget estimate, supporting research was budgeted as advanced technical develop-
ment (FY 1961-62) and advanced research (FY 1961-62).
bFunded under scientific satellites (physics and astronomy).
Clncludes $6 330 000 for advanced research and $4 870 000 for advanced technical development.
Table 3-55.
Biosatellite Funding History
(in thousands of dollars)
Table 3-56.
Planetary Quarantine Funding History
(in thousands of dollars)
Table 3-57.
Total Sounding Rockets Funding History a
(in thousands of dollars)
aAs of the FY 1964 budget estimate, sounding rockets as a separate program was dropped. For FY
1964-1968, see physics and astronomy soundings (table 3-10) and meteorological soundings (table 3-32).
Table 3-58.
Table 3-59.
Table 3-60.
Total Sounding Rockets Flight Program Funding History
(in thousands of dollars)
Table 3-61.
Solar Physics and Astronomy Soundings Funding History
(in thousands of dollars)
Table 3-62.
Energetic Particles and Magnetic Field Soundings Funding History
(in thousands of dollars)
Table 3-63.
Ionosphere-Plasma and Ionospheric Physics Soundings Funding History
(in thousands of dollars)
Table3-64.
AeronomySoundings
Funding History
(inthousands
of dollars)
Year Request Programmed
1960 --- 745
1961 --- 1077
1962 980 ---
1963 1329 ---
Table 3-65.
Galactic Astronomy Soundings Funding History
(in thousands of dollars)
Table 3-66.
Meteorite-Micrometeorite Soundings Funding History
(in thousands of dollars)
1960 --- 83
1961 ......
1962 94 ---
1963 115 ---
Table 3-67.
Miscellaneous Sounding Rocket Flight Projects Funding History
(in thousands of dollars)
1960 ...... a
1961 226 b 365c
1962 ......
1963 1946 d ---
alt was estimated in the FY 1961 budget estimate that $115 000 would be programmed for atmospheric
soundings for FY 1960; by the FY 1962 estimate this item had been dropped.
bFor atmospheric soundings.
¢Includes $146 000 for a meterology probe, $49 000 for magnetodynamics, and $170 000 for space
chemistry studies.
dlncludes $40 000 for a meteorology probe, $405 000 for magnetodynamics, $1 386 000 for space
chemistry, and $115 000 for astrophysics studies.
SPACE
SCIENCE
ANDAPPLICATIONS 231
Table3-68.
SoundingRocketSupport-Analysis
Funding
History
_
(inthousandsofdollars)
Year Request Programmed
1959 --- 894
1960 --- 5536
1961 1111 4483
1962 5466 ---
1963 6565 ---
aFunded
fromflightproject
monies.
Table
3-69.
OSSALaunchVehicle
Development
a
(inthousands
ofdollars)
Year Request Authorization Programmed
1962 ...... 85661
1963 ...... 105
729
1964 130700 127
700 111
900
1965 128200 128
200 96500
1966 63600 63600 57790
1967 33700 33 700 31 200
Table 3-70.
OSSA Launch Vehicle Procurement Funding History _
(in thousands of dollars)
aFor more information on launch vehicle procurement, see chapter 1, table 1-21).
bTotal reduced to $145 000 000 by the appropriations conference committee in October 1967.
NASA HISTORICAL DATA BOOK
The goals of the physics and astronomy program during NASA's first 10 years
were broad: "to increase our knowledge of the environment of the earth and in-
terplanetary space; to study the sun and to determine its influence in interplanetary
space and on the environment of the earth; to expand our knowledge of the structure
and history of the universe through astronomical observations; and to extend our
knowledge of astrophysical laws through the conduct of experiments in space. ''7 In
accomplishing these goals, the program embraced several scientific disci-
plines-astronomy and geodesy, solar physics, particles and fields, ionospheric
physics, and radio physics among others. Generally, NASA physics and astronomy
projects were designed to obtain new information about the stars, interplanetary
space, and the sun that was not obtainable with ground-based instruments. Sup-
plemented by balloons and aircraft-borne experiments, the physics and astronomy
flight projects included sounding rockets, small scientific satellites (Explorers),
Pioneer probes, and geophysical, astronomical, and solar orbiting observatories
(platforms).
NASA's scientific investigations revealed a space environment full of surprises.
In 1958, the model of earth's environment as generally envisioned had an at-
mosphere and an ionosphere limited to low altitudes with a dipole-like magnetic
field in which the field lines presumably extended without limit into the vacuum of
space. But scientists discovered a very active region above earth containing highly
energetic particles controlled by earth's magnetic field. The solar wind, an ionized
gas, was found to be blowing in interplanetary space, which reacts with earth's
magnetic field limiting that field's extension in all directions. Observations of the
sun gave researchers new information about ultraviolet rays and x-rays and their ef-
fect on earth's environment. By sending instruments above this planet's obscuring
atmosphere, astronomers gathered new data on the sun, other stars and planets, and
the interplanetary medium. Supporting research and technology funds also made
possible theoretical work and laboratory developments not specifically related to a
given flight project. Funds for data analysis ensured that scientific returns would be
studied and the findings distributed to the scientific community.
In an agency-wide reorganization in November 1961, a director for geophysics
and astronomy programs was added to the space science directorate. John F. Clark
was director until May 1961, when John E. Naugle took the post, which he held until
May 1966 (the program was renamed physics and astronomy in June 1963). Jesse
Mitchell saw the program through the remainder of the agency's first decade. Re-
porting to the director were chiefs of the various disciplines (e.g., astronomy and
particles and fields) and as of June 1963 managers of flight programs (e.g., in-
terplanetary and solar probes and solar observatories).
Explorer
The Explorer program was already under way when NASA was established in
1958. Of the five launches attempted by the Army Ballistic Missile Agency, three
had returned valuable scientific data. Used for investigations of the earth's environ-
SPACE SCIENCE AND APPLICATIONS 233
Table 3-71.
Chronology of Explorer Development and Operations
Date Event
July 1, 1955 The Army Ballistic Missile Agency (ABMA) and the Jet Propulsion
Laboratory (JPL) proposed a plan for launching a small satellite with
Sergeant solid-fuel rockets (2d, 3d, 4th stages) atop a Redstone booster.
July 28, 1955 U.S. officially announced plans to launch a satellite as part of the IGY.
Aug. 3, 1955 The Department of Defense (DoD) Advisory Group on Special Capabilities
(Stewart Committee), in choosing an IGY satellite, selected the Naval
Research Laboratory's (NRL) Vanguard project over the Army's proposal,
called Orbiter.
1956 Both the Army and Navy continued to develop their launch vehicles, the
Navy's booster being based on the Viking missile and the Army's on Redstone
(se also chapter 1).
Nov. 1957 After delays with its Vanguard launch vehicle, NRL transferred one of its
satellite experiments to ABMA for use in their satellite project, now called
Explorer. The experiment, sponsored by James Van Alien, State University
of Iowa, was integrated into a fourth-stage Sergeant motor by JPL in three
months.
Nov. 8, 1957 DoD officially directed the Army to proceed with their Explorer program to
launch a satellite for the IGY; the modified Jupiter C launch vehicle
(Redstone Booster) would be called Juno I.
Jan. 31, 1958 Explorer 1, the first successful U.S. satellite (13.6 kg, torpedo-shaped), was
launched by the Army with a Juno I vehicle.
March 5, 1958 A second Explorer failed to achieve orbit when the launch vehicle malfunc-
tioned (ABMA).
Aug. 24, 1958 The fifth Explorer failed to achieve orbit because it collided with the booster
after separation.
July 16, 1959 Explorer S-I, an energetic particles Explorer, failed when the launch vehicle
malfunctioned (ABMA).
Aug. 7, 1959 Explorer 6 was launched, the first NASA Explorer put into orbit.
March 23, 1960 Explorer S-46, an energetic particles Explorer, failed when the launch vehicle
malfunctioned.
Feb. 24, 1961 Explorer S-45, an ionospheric beacon Explorer, failed because of malfunc-
tion after separation from the booster.
May 24, 1961 Explorer S-45A, an ionospheric beacon satellite, failed when the launch vehi-
cle malfunctioned.
Table 3-71.
Date Event
Oct. 27, 1962 Explorer 15 was launched as part of Project SERB (Study ofthe Enhanced
Radiation Belt)
Nov. 26, 1963 Explorer 18 was launched (first interplanetary monitoring platform).
March 19, 1964 Explorer S-66, an ionospheric measurements Explorer, failed when the
launch vehicle malfunctioned.
Nov. 21, 1964 Explorer 24 and 25 were launched together (first successful dual launch by
NASA). This was a joint NASA-State University of Iowa project.
Nov. 6, 1965 Explorer 29 was launched (part of the U.S. Geodetic Satellite Program).
Nov. 29, 1965 Erplorer 31 was launched with a Canadian satellite in a dual launch (joint
NASA-Canadian Defense Research Board project).
Jan. 11, 1968 Explorer 36 was launched (part of the U.S. Geodetic Satellite Program).
Aug. 8, 1968 Explorer 39 and 40 were launched logether (joint NASA-State University of
Iowa project).
SPACE
SCIENCE
ANDAPPLICATIONS 237
Table3-72.
Explorer 6 (S-2) Characteristics
Table 3-73.
Explorer 7 (S-la) Characteristics
Table 3-74.
Explorer 8 (S-30) Characteristics
Table 3-75.
Explorer 9 (S-56a) Characteristics
Table 3-76.
Explorer 10 (P-14) Characteristics
Table 3-77.
Explorer 11 (S-15) Characteristics
Table 3-78.
Explorer 12 (S-3) Characteristics
Table 3-79.
Explorer 13 (S-55a) Characteristics
Table 3-80.
Date of launch
(location): Oct. 2, 1962 (ETR)
Launch vehicle: Thor-Delta
Weight (kg): 40.4
Shape: Octagonal platform atop a truncated cone with 4 solar panels
Dimensions (In): .43 x .7 x .7
Power source: AgCd batteries plus solar ceils
Date of reentry: July 1, 1966
Cognizant NASA GSFC
center:
Project manager: Paul G. Marcotte
Project scientists: F. B. McDonald
Contractor: Raymond Engineering Laboratory, Inc., spacecraft structure
Class of Explorer : Energetic particles
Objectives: Continuation of Explorer 12"s mission; gather information on radiation, solar par-
ticles, and the solar wind.
Experiments, Proton analyzer, ARC
responsible Fluxgate magnetometer, University of New Hampshire
institution: Trapped particle radiation study, State University of Iowa
Various radiation detectors, GSFC
Results: Studied earth's radiation belt as planned.
242 NASA HISTORICAL DATA BOOK
Table 3-81.
Explorer 15 (S-3b) Characteristics
Table 3-82.
Explorer 16 (S-55b) Characteristics
Table 3-83.
Explorer 17 (S-6) Characteristics
Table 3-84.
Explorer 18 (IMP-A) Characteristics
Table3-85.
Explorer 19 (AD-A) Characteristics
Table 3-86.
Explorer 20 (S-48) Characteristics
Table 3-87.
Explorer 21 (IMP-B) Characteristics
Table 3-88.
Table 3-89.
Explorer 23 (S-55c) Characteristics
Table 3-90.
Explorer 24 and 25 (AD-Injun B) Characteristics
Table
3-91.
Explorer 26 (EPE-D) Characteristics
Table 3-92.
Explorer 27 (BE-C) Characteristics
Table3-93.
Explorer 28 (IMP-C) Characteristics
Table 3-94.
Explorer 29 (GEOS-A) Characteristics
Table 3-95.
Table 3-96.
Explorer 31 (DME-A) Characteristics
Table 3-97.
Explorer 32 (AE-B) Characteristics
Shape: Spherical
Dimensions (m): Diameter, .89
Power source: AgZn batteries plus solar cells
Date of reentry: In orbit
Table 3-98.
Explorer 33 (IMP-D) Characteristics
Shape: 2-piece axial-thrust tube with a Delta attach-flange on one end and a retromotor
flange on the other connected to an octagonal equipment deck with 4 solar cell pad-
dles and 2 booms for magnetometers
Dimensions (m): Width with paddles extended, 2.78
Height, 1.12
Power source: Battery plus solar cells
Date of reentry: In orbit
Table 3-99.
Explorer 34 (IMP-F) Characteristics
Table 3-100.
Table 3-101.
Explorer 36 (GEOS-B) Characteristics
Table 3-102.
Explorer 37 (SE-B) Characteristics
Table 3-103.
Explorer 38 (RAE-A) Characteristics
Table 3-104.
Explorer 39 and 40 (AD-Injun E) Characteristics
The dominant position of the sun in our solar system and its profound effect on
earth's atmosphere has made it the subject of extensive examinations by space agen-
cy scientists. To study the sun, NASA planned an earth-orbiting platform-smaller
and less sophisticated than the proposed Orbiting Astronomical Observatories (see
elsewhere in this chapter) - equipped with instruments to measure solar radiation,
x-rays, gamma rays, and dust particles. 8
Called a "streetcar" satellite because it could carry interchangeable scientific in-
struments aboard as passengers, the Orbiting Solar Observatory (OSO) consisted of
two main sections. The lower wheel-like structure was composed of nine wedge-
shaped compartments, five of which housed scientific apparatus. Three spheres on
extended arms held pressurized nitrogen for stabilization. The top part of the
spacecraft was a stable fan-shaped array to which silicon solar cells were attached.
Experiments that required a fixed orientation with respect to the sun could be
housed in this section. In 1962, 1965, and 1967, four OSOs were orbited successfully
by Thor-Delta launchers, sending back a wealth of data about the sun and sun-earth
relationships.
Managed at NASA headquarters by the physics and astronomy directorate,
OSO 1 was the responsibility of Irwin Cherrick, program manager. From June 1963
through 1965, Richard E. Halpern was OSO program manager, and Dixon L. For-
sythe was solar observatories manager from January 1965 until mid-1967, when C.
Dixon Ashworth assumed these duties (Ashworth managed both astronomical and
solar observatory programs from December 1967). The Goddard Space Flight
Center was responsible for the individual flight projects (see the following tables for
project managers), with the launches taking place at the Eastern Test Range. Ball
Brothers Research Corporation of Boulder, Colorado, designer of the spacecraft,
was the prime contractor. The firm has worked with Goddard on the design even
before the first OSO contract was awarded in October 1959. The experimenters in-
volved with the program were from Goddard, NASA's Ames Research Center, the
University of Rochester, the University of California at San Diego, Harvard, the
Naval Research Laboratory, the University of Minnesota, the University of New
Mexico, the Air Force Cambridge Research Laboratory, MIT, the University of
Michigan, University College (London), and American Science and Engineering,
Inc.
The Orbiting Solar Observatories opened a new era in solar astronomy, but the
spacecraft had its limitations. To carry larger instruments with high spectral and
spatial resolution, NASA proposed in 1962 an advanced OSO to carry on observa-
tions beyond the eight planned OSOs. After Goddard specialists had completed
negotiations with Republic Aviation Corp. for such an advanced spacecraft, the
project was cancelled because of budget cuts in late 1965. However, each succeeding
OSO flight offered investigators new opportunities to confirm their data and im-
prove their instruments. In addition, OSO 4 was able to carry 90 kilograms more
payload than OSO 1.
For more information, consult GSFC, Orbiting Solar Observatory Satellite,
OSO 1, the Project Summary, NASA SP-57 (Washington, 1965); [Alfred Rosenthal
and William R. Corliss], Encyclopedia of Satellites and Sounding Rockets, August
1959 to December 1969 (Beltsville, MD: GSFC [1970]); and Corliss, Scientific
Satellites, NASA SP-133 (Washington, 1967).
SPACE SCIENCE AND APPLICATIONS 255
Table 1-105.
Date Event
April 16, 1959 Measurements of the sun from a spacecraft with pointing controls were in-
cluded among NASA's immediate space science flight program objectives.
Aug. 17, 1959 An Orbiting Solar Observatory (OSO) was included in an "Office of Space
Sciences Ten Year Program" document (pp. VII-15 through 17, table VII-8)
as one of the solar physics projects underway at the Goddard Space Flight
Center (GSFC), with Ball Brothers Research Corp. being considered a poten-
tial prime contractor; the first launch was tentatively scheduled for December
1960.
By Sept. 30, 1959 Goddard and Ball Brothers had completed part of the preliminary engineer-
ing for an OSO to weigh about 136 kilograms.
Oct. 1959 The first contract with Ball Brothers for OSO instrumentation was signed
($250 000, initial funding); additional contracts were awarded in 1961.
Aug. 15, 1962 NASA awarded three study contracts for the design of a new series of
spacecraft with which to study the sun (Ball Brothers, Republic Aviation, and
Space Technology Laboratories, $100 000 each).
Oct. 22, 1962 NASA and Republic initiated discussions for a development studies contract
for an advanced OSO ($1.9 million estimated contract).
Feb. 6, 1964 The General Accounting Office reported to Congress that NASA had in-
curred $799 000 in unnecessary costs on OSO because of mismanagement.
April 14, 1964 OSO-B's third-stage launch vehicle motor (X-248) ignited accidentally while
mated to the spacecraft at Goddard; three men were killed. Some parts were
salvaged for OSO-B2.
April 16, 1965 NASA signed a contract with Ball Brothers to build two more OSOs ($9.6
million).
Aug. 25, 1965 OSO-C failed to achieve orbit due to launch vehicle malfunction.
Aug. 30, 1965 NASA negotiated with Ball Brothers to purchase three more OSOs, bringing
the total to eight.
Oct. 1, 1965 Goddard and Republic completed negotiations for an advanced OSO ($58.4
million, estimated contract).
Dec. 15, 1965 An advanced OSO development program was cancelled because of budgetary
considerations.
April 10, 1968 A request for proposals for OSO-H was issued by Goddard.
256 NASA HISTORICAL DATA BOOK
Table 3-106.
OSO 1 (OSO-A) Characteristics
(location):
Launch vehicle: Thor-Delta
Shape: 2 main sections, each capable of movement; fan-shaped sail with solar cells atop a
lower wheel-like structure composed of 9 wedge-shaped compartments; 3 stabiliza-
tion arms
Dimensions (m): Upper Section, diameter, 1.12
Lower section, diameter, 1.12; height, .23
Overall height, .95
Power source: NiCd batteries plus solar ceils
Date of reentry: Oct. 8, 1981
Cognizant NASA GSFC
center:
Project manager, John C. Lindsay
scientist:
Contractor: Ball Brothers Research Corp., spacecraft and integration
Objectives: Measure solar electromagnetic radiation in ultraviolet, x-ray, and gamma ray
regions; investigate dust particles in space; improve future spacecraft design.
Experiments, X-ray spectrometer, GSFC
responsible Gamma ray monitor, GSFC
institution: X-ray monitors, GSFC
Dust particle experiment, GSFC
Emissivity stability, ARC
Photoelectric error sensor stability, Ball Brothers
Solar radiation, GSFC
Solar ultraviolet radiation, GSFC
Solar gamma ray radiation, GSFC
Earth horizon sensor, GSFC
High-energy gamma ray, University of Rochester
Neutron flux, University of California at San Diego
Proton-electron flux, University of California at San Diego
Results: Collected 2000 hours of data; detected rapid fluctuations in the x-ray flux emitted by
the sun and a correlation between the temperature of earth's upper atmosphere and
the intensity of ultraviolet radiation from the sun striking the atmosphere. Tracking
and data operations for the spacecraft ceased on August 6, 1963.
SPACE
SCIENCE
ANDAPPLICATIONS 257
Table3-107.
OSO 2 (OSO-B2) Characteristics
Table 3-108.
0S0-3 (OSO-E) Characteristics
Table 3-109.
OSO 4 (OSO-B2) Characteristics
returned led to an extensive review of the spacecraft's design and some systems
modifications. OAO 2 was a highly successful spacecraft, providing an abundance
of information on ultraviolet, gamma ray, x-ray, and infrared radiation, on the
structure of stars, and on the distribution and density of the interstellar medium.
A physics and astronomy project, the Orbiting Astronomical Observatory was
managed at NASA Headquarters by Allan H. Sures from June 1963 until early 1966,
when C. Dixon Ashworth took this position (Ashworth managed both OAO and
OSO from December 1967). While personnel at Ames Research Center prepared the
preliminary engineering specifications for OAO, technical management of the flight
projects was assigned to the Goddard Space Flight Center in February 1960 (see the
following tables for project managers). Grumman Aircraft Engineering Corp.,
Bethpage, New York, was the prime contractor for OAO. Major.subsystem contrac-
tors included General Electric, Radio Corporation of America, IBM, Westinghouse,
and Kollsman Instrument Corp. The scientific investigators were recruited from
Goddard, Lockheed, MIT, the University of Wisconsin, and the Smithsonian
Astrophysical Observatory.
For more information, see Alfred Rosenthal and William R. Corliss, En-
cyclopedia of Satellites and Sounding Rockets, August 1959 to December 1969
(Beltsville, MD: GSFC, 1970); Corliss, Scientific Satellites, NASA SP-133
(Washington, 1967); Robert S. Rudney, "A Preliminary History of the OAO Pro-
gram (1966-1968)," NASA HHN-115, Sept. 1971, prepared for NASA Historical
Off.; GSFC, The Observatory Generation of Satellites, Session H of a Special
Astronautics Symposium Held at the Franklin Institute, Philadelphia, December 27,
1962, during the 129th Annual Meeting of the American Association for the Ad-
vancement of Science (Washington, 1963); and James E. Kupperian, Jr., and
Robert R. Zeimer, "Satellite Astronomy," International Science and Technology
(March 1962): 48-56.
SPACE SCIENCE AND APPLICATIONS 261
Table 3-110.
Chronology of Orbiting Astronomical Observatories (OAO) Development and Operations
Date Event
May 15, 1958 In a preliminary study, the staff at the Langley Memorial Aeronautical
Laboratory (National Advisory Committee for Aeronautics) suggested that
the new civilian space agency consider stabilized and oriented astronomical
observatories as a long-range goal with practical equipment being provided
by 1960.
Oct. 1958 NASA established a working group under Nancy Roman to study the
March 1959 feasibility of launching large orbiting astronomical observatories.
April 1959 Stable orbiting platforms with telescopes to make observations in the in-
frared, optical, ultraviolet, and x-ray regions of the spectrum beyond earth's
obscuring atmosphere were proposed as part of the space sciences long-range
flight program.
Dec. 1, 1959 An OAO project briefing was held at NASA Hq. for potential industry par-
ticipants to provide further information on requirements and planning (150
attendees).
Feb. 1960 Technical management of OAO was assigned to the Goddard Space Flight
Center.
Apr. 1960- Having circulated OAO design specifications, NASA evaluated the 11 pro-
Sept. 1960 posals received for an OAO spacecraft. Experiments suitable' for an OAO
were under way at Goddard, Princeton, the University of Wisconsin,
Smithsonian Astrophysical Observatory, and the University of Michigan
Observatory.
Oct. 10, 1960 NASA announced plans to negotiate with Grumman Aircraft Engineering
Corp. for a contract for a 1360-kilogram OAO $23 million contract
estimate).
Oct. 1960- Grumman negotiated four subsystem development contracts: General Elec-
June 1961 tric, spacecraft stabilization and control; Radio Corp. of America, television
scanner; IBM, data processing; and Westinghouse Electric Corp., ground
operating equipment.
April 1961 Booz-Allen Company was awarded a contract for a study of an independent
NASA reliability control program for OAO.
Jan. 1962 Kollsman Instrument Div. was awarded a contract for the primary mirror for
the OAO telescope.
Aug. 7, 1962 GE announced that the control system for OAO had completed its first
simulated flight tests.
Oct. 29, 1962 Three photometers developed for OA0 were flight-tested on an Aerobee
sounding rocket launched from Wallops Island.
Feb. 24, 1964 General Dynamics/Astronautics was awarded a contract for the OAO shroud
system.
June 16, 1964 NASA ordered a third OAO from Grumman and took an option for two
more ($20 million, estimated contract for one spacecraft; $50 million for
three).
April 9, 1965 Grumman was given the go-ahead to convert its prototype OAO into a flight-
ready spacecraft to be called OAO-A2.
May 12, 1965 Grumman was awarded a contract for a fourth OAO.
262 NASA HISTORICAL DATA BOOK
Table 3-110.
Date Event
April 8, 1966 0.40 1 was launched successfully and placed in circular orbit. After 1 ½ days
(22 orbits), the spacecraft power system failed when the battery overheated.
No data were returned.
April 21, 1966 A NASA review board was established to examine observatory-class
satellites.
Dec. 23, 1966 NASA announced that Atlas-Centaur would replace Atlas-Agena D as the
launch vehicle for future OAO missions; it would be capable of boosting 40
percent more payload.
Jan.-June 1967 OAO-A2 underwent extensive systems redesign to prepare it for flight; the
launch date was slipped from 1967 to late 1968.
April 30, 1968 NASA ordered two additional Centaur rockets from General Dynamics
Astronautics for OAO.
Dec. 7, 1968 OAO-2 was launched successfully and placed in orbit. All systems and ex-
periments functioned as planned.
Table 3-111.
OAO 1 (OAO-A1) Characteristics
Table 3-111.
OAO 1 (OAO-A1) Characteristics (Continued)
Results: Spacecraft failed after 1V2days (22 orbits) because of battery malfunction; when the
battery overheated the power supply system would not respond to ground com-
mands to switch over to the two backup batteries; no data received.
Remarks: As a result of this failure, 0.40 2"s power system was redesigned. OAO l's loss
forced NASA's managers to function as a review team as they scrutinized and
reworked a design they had previously judged to be satisfactory.
Table 3-112.
OAO 2 (OAO-A2) Characteristics
Table 3-113.
Chronology of Orbiting Geophysical Observatory (OGO)
Development and Operations
Date Event
May 15, 1958 In a preliminary study, the staff at the Langley Memorial Aeronautical
Laboratory (National Advisory Committee for Aeronautics) suggested that
the new civilian space agency consider a large satellite-platform with stable
orientation for geophysical meausurements as a long-range goal.
Mid-1959-
mid-1960 Personnel at the Goddard Space Flight Center did preliminary design work
on a new-generation satellite with a standard structure into which many ex-
periments could be integrated from mission to mission.
July 1960 Eccentric and polar orbit missions were considered for ionospheric physics
investigations.
Aug. 30, 1960 A bidder's conference was held at Goddard for 17 companies interested in
constructing an Orbiting Geophysical Observatory, a 450-kilogram-class
satellite.
Dec. 21, 1960 NASA issued a letter contract to Space Technology Laboratories, Inc. (later
a division of TRW) to proceed with preliminary analytical and design studies
for three OGOs ($15 million).
April 1961 NASA and STL agreed on a 400-kilogram box-like structure for OGO with
movable solar panels and extendable booms.
April 1964 NASA began negotiations with TRW to provide a fourth and fifth OGO.
June 1964 OGO-A was transported to the Kennedy Space Center for final assembly,
checkout, and integration with the launch vehicle.
Sept. 5, 1964 OGO 1 was launched into eccentric orbit, but an attitude control system
failure left the spacecraft in a fixed position.
Oct. 24, 1965 OGO 2 ceased operations after its attitude control system gas supply was
depleted; the spacecraft was put into a spin mode with some of its ex-
periments still working.
Jan. 24, 1966 NASA began contract negotiations with TRW for a sixth OGO.
April 1966 OGO l's batteries failed, leaving three experiments operational.
July 27, 1966 OGO 3 was placed into a fixed spin mode after its attitude control system
failed.
Aug. 1966 The House Science and Astronautics Committee on NASA Oversight began
inquiries into spacecraft failures, including OGO 1, 2, and 3.
July 28, 1967 OGO 4 was launched into polar orbit; attitude control problems detected
after orbital insertion were corrected by ground control.
266 NASA HISTORICAL DATA BOOK
Table 3-113.
Chronology of Orbiting Geophysical Observatory (OGO)
Development and Operations (Continued)
Date Event
Sept. 19, 1967 All four OGOs transmitted data simultaneously for the first time.
Nov. 1967 OGO 2 was shut down and put into a standby mode.
Jan. 29, 1968 Funds were approved for one additional OGO; after a proposed sixth mission
the program would be phased out.
Table 3-114.
OGO 1 (OGO-A) Characteristics
experiments:
Results: The immediate failure of 2 booms to deploy properly caused the unscheduled use of
attitude control gas, leaving the spacecraft in a fixed position. Because of this orien-
tation, solar aspect was_periodically unfavorable, resulting in a regular low-power
period of 6 weeks every 4V2 months. Although 6 of the 20 experiments could not
function as planned, the data returned were judged to be valuable. Experiments
were turned off November 25, 1969.
SPACE SCIENCE AND APPLICATIONS 267
Table 3-115.
OGO 2 (OGO-C) Characteristics
Table 3-116.
OGO 3 (OGO-B) Characteristics
experiments:
Results: Maintained planned 3-axis stabilization for 46 days; a failure in the attitude control
system in July 1966 forced the spacecraft into a permanent spin mode. By June
1969, data acquisition was limited to half of the orbit. Before operations were
suspended in December 1969, 15 of the 21 experiments were still operating with
more than 375 000 hours of data returned. Operations were terminated on February
29, 1972.
SPACE SCIENCE AND APPLICATIONS 269
Table 3-117.
OGO 4 (OGO-D) Characteristics
Table 3-118.
OGO 5 (OGO-EB) Characteristics
Sounding Rockets
The sounding rocket story begins long before NASA's organization in 1958. As
early as July 1929, Robert H. Goddard included two measuring instruments on one
of his test rockets, and in 1933 Mikhail K. Tikhonoravov, a Russian, launched a
liquid-fuel sounding rocket. At last, scientists could send their instruments into and
above earth's atmosphere to make in situ measurements. Early investigators had
taken their measuring devices to high mountains and exploited high-flying balloons
when they became available, but this still limited their area of study to about 40
kilometers, the maximum balloon altitude. But rockets, which could surpass that
altitude several times, could be instrumented and fired along a vertical or nearly ver-
tical trajectory, taking measurements on the way up and again as the rocket fell back
to earth (a vertical profile).
The further refinement of small rockets after World War II offered scientists
vehicles that could carry a few hundred kilograms of instruments to altitudes ex-
ceding 250 kilometers for several minutes of observation time above the atmosphere.
SPACE SCIENCE AND APPLICATIONS 271
I
274 NASA HISTORICAL DATA BOOK
Table 3-119.
Year
lO-year
Discipline total
1959 1960 1961 1962 1963 1964 1965 1966 1967 1968
Aeronomy 5 10 21 30 35 51 45 31 28 31 287
Biology 0 0 2 0 0 0 0 0 1 2 5
Energetic particles 0 16 1 0 2 16 15 14 11 21 96
Fields 0 2 3 0 1 9 13 5 12 12 57
Galactic astronomy 0 4 5 4 5 11 10 1i 16 19 85
Ionospheric physics 4 8 10 14 27 22 46 25 20 21 197
Meteorology 0 5 13 14 11 34 53 59 57 48 294
Radio astronomy 0 0 0 1 0 1 2 1 1 1 7
Solar physics 0 4 1 2 6 1 5 9 10 12 50
Test and miscellaneous 7 11 14 13 6 7 2 3 6 7 76
From William R. Corliss, NASA Sounding Rockets, 1958-1968: A Historical Summary, NASA SP-4401
(Washington, 1971), p. 146.
Table 3-120.
Sounding Rocket Projects Summary, 1959-1968
1959 1960 1961 1962 1963 1964 1965 1966 1967 1968 10-yr Success
Total (%)
Aerobee 4 8 2 14 92
Aerobee 150/150A 4 11 8 20 30 26 29 29 35 37 229 94
Aerobee 300/300A 3 2 1 2 2 1 11 100
Aerobee 350 1 1 2 100
Arcas 13 9 16 6 44 95
Arcon 6 6 100
Astrobee 1500 1 1 2 1 5 80
Black Brant IV 2 2 100
Iris 2 1 1 4 75
Javelin 1 5 8 2 2 7 7 6 9 4 51 94
Journeyman 1 2 1 1 2 7 100
Nike-Apache 5 11 36 76 92 57 48 50 375 98
Nike-Asp 5 10 8 3 1 27 63
Nike-Cajun 24 23 37 20 38 43 43 35 38 301 97
Nike-Tomahawk 3 12 15 30 60 98
Skylark 4 4 100
Special (other) .... 1 2 1 2 6 12 83
From Alfred Rosenthal and William R. Corliss, Encyclopedia of Satellites and Sounding Rockets,
August 1959 to December 1969 (Beltsville, MD: GSFC [1970]), p. 320.
SPACE
SCIENCE
ANDAPPLICATIONS 275
Table3-121.
Chronology
ofSounding
RocketsDevelopment
andOperations
Date Event
1919 Robert H. Goddard suggested in A Method of Reaching Extreme Altitudes
that rockets could be used for upper atmosphere research.
July 17, 1929 An aneroid barometer and a thermometer were included on a test of one of
Goddard's rockets, which attained an altitude of 52.1 meters.
Dec. 1934 The A-2 rocket, a predecessor to the V-2, was launched by the German
Army.
Jan. 1944 The U.S. Army Signal Corps expressed a need for a high-altitude sounding
rocket that could carry 11.3 kilograms of meteorological instruments.
1944-1945 Germany used the V-2 (A-4) rocket as a weapon during World War II; it
could carry 907 kilograms of explosives to an altitude of about 322
kilometers.
July 1945 Live tests of the Baby Wac (Corporal) being designed by the Jet Propulsion
Laboratory for upper atmosphere research were performed.
Sept. 26, 1945 The first launch of a Wac Corporal was successful; it reached an altitude of
70 kilometers.
Dec. 17, 1945 The Naval Research Laboratory (NRL) Rocket-Sonde Research Branch was
formed to develop a sounding rocket to carry scientific instmments.
Jan. 16, 1946 An informal meeting was held at NRL to discuss the possibility of working
with the Army Ordnance Department in implementing a scientific research
program to use with the captured German V-2s, which the Army would
launch from White Sands, New Mexico. After agreeing to cooperate with the
Army, the group established a V-2 Upper Atmosphere Research Panel on
February 27, which would include representatives from government, in-
dustry, and universities.
Feb. 22, 1946 Aerojet Engineering submitted a proposal to the Applied Physics Laboratory
of Johns Hopkins to develop a sounding rocket capable of carrying a payload
weighing from 136 to 680 kilograms to an altitude of 182 880 meters.
April 16, 1946 First U.S. launch of a V-2. A total of 67 V-2s were fired from White Sands as
part of the Hermes program.
May 17, 1946 Aerojet was awarded a contract for 20 liquid-fuel rockets; 15 would go to the
Applied Physics Laboratory and 5 to NRL; the Aerojet rocket was called
Aerobee.
Aug. 1946 The Navy awarded contracts to Glenn L. Martin Co. and Reaction Motors
for the construction of a rocket called Viking designed by NRL; NRL's
rocket was capable of launching a payload larger than Aerobee's. The
original contract called for 10 Vikings.
1952-1953 Aerojet developed an improved rocket, the Aerobee-Hi, for the Air Force
and Navy.
276 NASA HISTORICAL DATA BOOK
Table 3-121.
Chronology of Sounding Rockets Development and Operations (Continued)
Date Event
1953 NACA's Pilotless Aircraft Research Division mated a Nike I guided missile to
the Deacon motor to form the Nike-Deacon configuration, which could
launch 23 kilograms to an altitude of 111 kilometers.
June 20, 1956 First firing of the Cajun motor took place. When the Cajun was combined
with the Nike I guided missile, the resulting rocket could lift 23 kilograms to
167 kilometers.
July 1957- During the International Geophysical Year (IGY), the U.S. launched 210
Dec. 1958 sounding rockets (mainly Aerobee His -the improved version of the Aerobee
150-and Nike-Cajuns).
Feb. 18, 1958 First firing of the improved Aerobee (Aerobee 150) took place. It was capable
of launching 18 kilograms to 160 kilometers.
Oct. 25, 1958 First firing of the Aerobee 300 took place, an Aerobee 150 with a motor from
the Sparrow missile.
Dec. 28, 1958 Some members of NRL's Rocket-Sonde Branch were transferred to NASA
and assigned to the Beltsville Space Center (later called the Goddard Space
Flight Center).
July 1959 First firings of the Arcas rocket developed by the Army and the Navy took
place.
July 22, 1960 First firing of the Iris rocket designed by NRL (pre-NASA design) took place.
It could send 45 kilograms to 320 kilometers.
June 18, 1965 First launch of the Aerobee 350 sounding rocket took place.
Dec. 10, 1967 NASA launched a sounding rocket (an Aerobee 150) equipped with the solar
pointing Aerobee rocket control system (SPARCS) developed at Ames
Research Center.
May 7, 1968 NASA launched its first British Black Brant IV.
SPACE SCIENCE AND APPLICATIONS 277
"_ _ _ _
_._.__ _ -=_,
_._
0
_'_ "_,
v
_u
< <
oO
_0
Ox
_'_o
_.8o :"
•r. _ .._
0
E-_ --.
e,I "_
0 e_ _
0 _'_
<oz
Z
t_
0 t_
z_ cq
.....
_o
_0
o'_
_o
o,,
oo oo
0
<<
278 NASA HISTORICAL DATA BOOK
D,
_.__
.__a_x_ _o._ _ _
_ _-_ -
o_ _._._ _ _ _._
--.8_= z _
r.
oo
,=J3g
¢q
.E_ e,_o
O
< e,i ,_ -
_-o
,t:: e., _o
(0 ¢',1
¢,1
o'_
"_.
o_
,< <
SPACE
SCIENCE
ANDAPPLICATIONS 279
__ .-" t_ ,_ _ "" .
_._
z __ ,_z _ <mt_
_ _- o_
O _ _._
O_
7. •_ _o
.-6
_'_._ _--
8 _'_" '=_' _ _ R
I
_,_
E-g
< ¢q
r/9
<
Z
r_
¢q
8 o
< <
280 NASA HISTORICAL DATA BOOK
._ _
_._ -_ _-_ _ _ _ _.
__ _ _ _ _= __o
_" ._o_
_ _ ._-o _ _ _ -_
C9
e_
o
oo
i
e_ _0 t_
e_ u_
oq
<
<
Z
t'q
m o0
c_
e-
_o
o'1
ee_
=_
u_
SPACE SCIENCE AND APPLICATIONS 281
_ 0
r' 0 _3 _''
_ < _ "_
_o _ _'_=
..o -.'-
_ _
_ _ "0 _ 0 _ _ 0 .
o.o
° _._
_.=- _ _=_ _z _ _ 8.
8
L_
o _=o
< o'_
oo
g:
_ ._.o
8 0
I xO
44
88
q,J
oo
_o
t_
¢q
oo
o,
r_
282
_0 _.o
"g' m_
e-
f-
o
t-_ 1-
oo
_e;_ __
i
eq
t_
I
em _t) ' [" e,I
&
L;.l
_
Z Q
r]?
<
r.t3
<
z
rm
_o
Z
SPACE SCIENCE AND APPLICATIONS 283
e_
=_'_ _ __
_ ._ -_ -
ea o '_'_
-- _.t_
e_
_ _ _Z_-r. _<._
°-
_ _.__
,,¢
¢q
¢q
¢q
Z_'_
A_
09
O']
Z
¢q cq
¢q
f-
O
oo
Ox
2_
n_
284 NASA HISTORICAL DATA BOOK
• .- 5
_._ _,_._ d _
.-
_.=
- o
_, _=
_- m
"_"o °_
o
O
o_
o
_'._ _ o_-
_.__
__ • _ 0o-
_°=
o._ ._ .
0 Z e_
_;_ __ _.__
< _3,_ o_. o_
SPACE SCIENCE AND APPLICATIONS 285
< ._ .o _ o
<.o 8
o
E=
'_..£
o _.__
_ 8e .
_ -_
_"6 8o-o
_'_, _.._
_ _'a. a
"=o_ "- '_ ,o
o'_
• o
e_ej
o'= ,u "_
_c.o°
_Nt:
g o I.-.
u
0._ ._
-d -'_ _ "-_ o
z_ z,_
..6
o _ _ _.
o._ o _
,,., _ -
286 NASA HISTORICAL DATA BOOK
Vanguard
Table 3-124.
Vanguard 2 Characteristics
Table 3-125.
Vanguard 3 Characteristics
Results:
Transmitted data for 85 days, providing a comprehensive survey of magnetic fields,
a detailed location of the lower edges of the Van Allen Belt, and an accurate count
of micrometeorite impacts; the satelfite was put into orbit with the third stage.
288 NASA HISTORICAL DATA BOOK
*The 10 members of ESRO were Belgium, Denmark, France, the Federal Republic of Germany,
Italy, the Netherlands, Spain, Switzerland, and the United Kingdom.
SPACE SCIENCE AND APPLICATIONS 289
Table 3-126.
Alouette 1 Characteristics
Table3-127.
Alouette 2 Characteristics
Table 3-128.
Ariel 1 (UK-I) Characteristics
manager:
Contractor: Washington Technological Associates, spacecraft structure
Objectives: Ionospheric investigations; measure electron density and temperature and the com-
position of positive ions; monitor ultraviolet radiation and x-rays; measure cosmic
rays.
Experiments, Cosmic ray detector, Imperial College
responsible Electron density plasma probe, University of Birmingham
institution: Ionospheric composition probe, University College
Solar emissions measurement, University College
Electron temperature density probe, University College
X-ray counters and gages, University of Leicester
Results: Much useful data on the ionosphere were returned, including information on a new
ion layer at an altitude of 725-800 kilometers; satellite was damaged by an American
atomic test in September 1962 but transmissions continued until June 1964; restarted
in August 1964 for two months.
Remarks: Joint NASA-U.K. project; first international satellite.
292 NASA
HISTORICAL
DATABOOK
Table 3-129.
Ariel 2 (UK-C) Characteristics
Shape: Cylindrical with a spherical section at each end, plus 4 solar paddles and 2
1.22-meter booms
Dimensions (m): Cylinder, .27 × .58
Spheres, .14 x .13
Power source: NiCd batteries plus solar cells
Date of reentry: Nov. 18, 1967
Cognizant NASA GSFC
center:
Project manager: Emil Hymoqitz
Project scientist: Lawrence Dunkelman
UK project M. O. Robbins
manager:
Contractors: Washington Technological Associates, spacecraft structure
Westinghouse Electric Corp., several satellite subsystems and integration
Objectives: Measure vertical distribution of the ozone; study galactic radio noise; measure
micrometeroid flux.
Experiments, Galactic radio noise receiver, University of Cambridge
responsible Ozone photometers and spectrometer, Air Ministry
institution: Micrometeoroid detectors, University of Manchester, Jodrdl Bank
Results: Made a global survey of the ozone; designed for a longer life than Ariel 1.
Remarks: Joint NASA-U.K. project
SPACE
SCIENCE
ANDAPPLICATIONS 293
Table3-130.
Ariel 3 (UK-E) Characteristics
Results: Much useful data on the upper atmosphere were returned; transmitter was turned
off after 28 months.
Remarks: Joint NASA-U.K. project.
294 NASA HISTORICAL DATA BOOK
Table 3-131.
ESRO 1 (Aurorae) Characteristics
Table 3-132.
ESRO 2B (IRIS) Characteristics
Table3-133.
FR-1 Characteristics
Table 3-134.
HEOS 1 Characteristics
Results: Good data returned until October 1975; barium cloud experiment performed on
March 18, 1969.
Remarks: HEOS stands for Highly Eccentric Orbit Satellite; launched for ESRO (European
Space Research Organization) by NASA.
Table 3-135.
P-21 Characteristics
Table 3-136,
P-21A Characteristics
Table 3-137.
PAGEOS 1 (PAGEOS-A) Characteristics
Table 3-138.
S-66 Polar Ionosphere Beacon Characteristics
Table 3-139.
San Marco 1 Characteristics
Table 3-140.
San Marco 2 Characteristics
Date of launch April 26, 1967 (Formosa Bay, Indian Ocean; near coast of Kenya)
(location):
Launch vehicle: Thrust-augmented Improved Thor-Delta (TAID)
Weight (kg): 129.3
Shape: Spherical
Dimensions (m): Diameter, .66
Power source: Batteries
Date of reentry: Oct. 14, 1967
Cognizant NASA GSFC
center:
Project manager: A. J. Caporale, Hq.
Contractor: Centro Richere Aerospaziale, University of Rome, spacecraft design and fabrication
(Italian contract)
Objectives: Measure upper atmosphere air density, electron density; study radio wave propaga-
tion.
Experiments Air density triaxial balance, University of Rome, Electron content and wave pro-
responsible pagation, University of Florence
institution:
Results: All experiments returned data as expected.
Remarks: Italian satellite launched by NASA; first satellite to be launched from a sea plat-
form.
Beyond the examination of our own planet's upper atmosphere, the unmanned
exploration of earth's moon and the other planets was an especially attractive goal
for NASA's space scientists. Telescopes and other instruments sent into orbit around
earth had relayed clearer, improved images of these distant bodies and new informa-
tion about the interplanetary medium. This wealth of new data, plus increasingly
powerful launch vehicles and improved telemetry systems, recording devices, and
scientific instruments, made it possible for man's machines to explore new worlds.
The Soviet Union's success with Sputnik and Luna spacecraft added an extra sense
of urgency to NASA's early plans for lunar and interplanetary investigation.
Schemes for sending automated spacecraft to the vicinity of the moon certainly
predate NASA. The moon was one of the goals military launch vehicle specialists
and civilian scientists alike had in mind when it became apparent that powerful
boosters capable of launching large payloads could be perfected over time. In the
spring of 1958, advanced planners at the Langley Memorial Aeronautical
Laboratory, part of the National Advisory Committee for Aeronautics were sug-
gesting that the new civilian space agency being organized launch a 34-kilogram
probe to the vicinity of the moon to acquire "scientific information on the
characteristics of space between the earth and the moon, and on the physical,
biological, and chemical characteristics of the moon itself." Probes would be fol-
lowed by orbiters and then landers. A secondary benefit from these scientific in-
vestigations, of course, would be data that could also be applied to manned
SPACE
SCIENCE AND APPLICATIONS 301
spaceflight. There were many unknowns. How many meteorites would a spacecraft
encounter during its trip to the moon? Precisely what was the moon's mass? What
was the radioactivity level at the surface? What were the constituents of the at-
mosphere? Would the crust be made of volcanic rock or dust? For many par-
ticipants and bystanders, unmanned exploration and the search for answers to scien-
tific questions were overshadowed by the glamor of manned expeditions. As early as
the summer of 1959, the Office of Space Science recognized this: "If one goal were
to be selected which would most influence the overall NASA program during the
next decade it would be manned flight to the moon. The manned space flight pro-
gram, the program of unmanned lunar exploration and the booster development
program are all oriented toward this goal." The Langley people believed that NASA
could take its first steps in this direction by late 1959, with landers reaching the
moon "within a few years. ''9
NASA's early attempts to send a probe to the moon were unsuccessful. From
the Department of Defense's Advanced Research Projects Agency, NASA had in-
herited a lunar probe program called Pioneer. Launch vehicle malfunctions in 1958
prevented three Pioneer probes from obtaining the velocity necessary to escape
earth's gravity, and Pioneer 4 in early 1959 did not pass close enough to the moon
for its photoelectric scanner to operate. Three more attempts in 1959 and 1960 with
Atlas-Able vehicles also were failures. It was 1964 before NASA had an unqualified
success. Ranger 7 orbited the moon sending back good-quality photographs and im-
pacted on the lunar surface on command. Two other Ranger missions were carried
out successfully, followed by five lunar Orbiters, also successful. Five of the seven
Surveyor spacecraft soft-landed on the moon in 1966-1968. Much of the lunar sur-
face was photographed, and millions of bits of scientific data were telemetered to
earth, the sheer bulk of which led to the establishment of the Lunar Science Institute
in 1968 to serve as a center for the analysis and study of data being generated by un_
manned and manned lunar programs.
Beyond the moon were more unknowns: the other planets, our sun, the medium
surrounding them. The first thing scientists wanted to determine was the
astronomical unit, the semi-major axis of earth's orbit about the sun, so that in-
terplanetary trajectories could be plotted precisely. The size of the planets, the com-
position of their atmospheres, and their physical, biological, and chemical proper-
ties were other subjects for investigation. The early planners again suggested a three-
tiered approach: trackable spacecraft that would escape earth's gravitational field
but remain in a nearby orbit of the sun, followed by planetary orbiters of the nearby
planets, and finally by landers. _0 This was basically the approach NASA followed.
Five very successful Pioneer interplanetary probes were sent on a variety of missions
from 1960 through 1968. A Mariner spacecraft passed by Venus in 1962 and another
took 22 photographs of Mars as it passed by that planet in 1964. Another Mariner
flew by Venus in 1967. NASA's plans for a Mars Voyager lander were cancelled in
1967 by a budget cut demanded by Congress, but it was replaced by Project Viking,
which would send two orbiter-landers to the Red Planet in the 1970s.
NASA in its initial organization had a chief of planetary science programs, John
F. Clark. In an early 1960 reorganization, Edgar M. Cortright was named assistant
director for lunar and planetary programs. In November 1961, Oran W. Nicks
assumed this position, managing the programs until late 1967. With the growing im-
portance of the Apollo Program and the conclusion of the automated lunar explora-
tion program, lunar science was assigned to the Office of Manned Space Flight in
302 NASA
HISTORICAL
DATA BOOK
December 1967. R. J. Allenby became assistant director for lunar science under Lee
R. Scherer, director for Apollo lunar exploration, both of whom were formerly of
the Office of Space Science and Applications. Donald P. Hearth was named director
of planetary programs. Managers of the various flight programs reported to him.
Project managers were named at the appropriate centers-the Jet Propulsion
Laboratory, Langley Research Center, and Ames Research Center.
Pioneer
quarters in 1963 for the second Pioneer series. In 1966 and 1967, however, Reiff
devoted all his energies to Mariner 4 and 5, and management of Pioneer was as-
signed to the physics and astronomy program under Marcel T. Aucremanne's direc-
tion. Reiff resumed authority for Pioneer in 1968. Charles F. Hall led the Ames
Pioneer team from its first informal study of solar probes in 1960. TRW was the
prime contractor for the design and fabrication of the interplanetary Pioneers
(Herbert Lasser of TRW was responsible for the spacecraft's configuration).
For more information on the interplanetary Pioneers, see William R. Corliss,
The Interplanetary Pioneers, 3 vols., NASA SP-278, 279, and 280 (Washington,
1972); and TRW Systems Group, Pioneer Handbook, 1965-I969 (Ames Research
Center, 1968).
Table 3-141,
Date Event
March 27, 1958 The Secretary of Defense announced that the Advanced Research Projects
Agency of the Department of Defense would proceed with several programs
for launching unmanned spacecraft. One of these programs, which called for
three lunar probes, was assigned to the Air Force Ballistic Missile Division;
two other probes were assigned to the Army. The Air Force planned to
use a Thor-Vanguard launch vehicle for the lunar probes, which would be
launched during the International Geophysical Year.
1958 Space Technology Laboratories was awarded a contract by the Air Force for
designing and building the probe and modifying the second and third stages
of the launch vehicle, which came to be called Thor-Able.
Aug. 17, 1958 Attempted launch of a small lunar probe failed when the Thor-Able I vehicle
exploded 77 seconds after liftoff.
Oct. 1, 1958 The lunar probe program was assigned to NASA, which delegated authority
back to the Army and the Air Force.
Oct. 11, 1958 Pioneer I was launched on an Air Force Thor-Able I; because the second and
third stages of the vehicle did not separate evenly, the probe did not reach the
velocity required for a lunar trajectory. The lunar probe program was of-
ficially called Pioneer by this time, but the individual spacecraft were still
sometimes referred to as Ables.
Fall 1958 The Atlas-Able launch vehicle combination was suggested as a possible
launcher for NASA's lunar probe.
Nov. 8, 1958 Pioneer 2 launch by an Air Force Thor-Able I was unsuccessful; the third
stage of the vehicle failed to ignite, and the probe did not reach the required
altitude.
Dec. 6, 1958 Pioneer 3 launch by an Army Juno II was unsuccessful; the first stage of the
vehicle cut off prematurely, and the probe did not reach the required altitude.
Feb. 1959 Negotiations were conducted between the Air Force-NASA team and Space
Technology Laboratories for two Able stages and payloads.
March 3, 1959 Pioneer 4 launch by an Army Juno II was successful, but the probe did not
pass close enough to the moon for its instruments to function.
304 NASA HISTORICAL DATA BOOK
Table 3-141.
Date Event
Nov. 26, 1959 An attempt to launch a lunar orbiter with an Atlas-Able was unsuccessful;
the payload shroud broke away 45 seconds after liftoff (Able 4).
May 1960 Ames Research Center begun an informal study of solar probes.
Sept. 25, i960 An attempt to launch a lunar orbiter with an Atlas-Able was unsuccessful;
the second stage of the vehicle malfunctioned (Able 5A).
Dec. 15, 1960 An attempt to launch a lunar orbiter with an Atlas-Able was unsuccessful;
the first stage of the vehicle malfunctioned (Able 5B).
April 1962 TRW completed a feasibility study for Ames on designing an interplanetary
Pioneer.
Nov. 6, 1962 NASA approved a new series of interplanetary Pioneers and assigned
management responsibility to Ames.
Nov. 9, 1962 Project approval document for the Pioneer series was signed.
Jan. 29, 1963 A request for proposals for building the spacecraft was issued.
Feb. 1, 1963 A request for proposals for experiments to be carried on the Pioneer missions
was issued.
July 23, 1963 An initial set of experiments for Pioneer was selected.
Aug. 5, 1963 TRW received a letter contract for the fabrication of five Pioneer spacecraft
($1.5 million, maximum contract value).
Dec. 5, 1965 The first of the Pioneer spacecraft arrived at the Kennedy Space Center.
Feb. 22, 1966 The fifth spacecraft was eliminated from TRW's contract due to budget cuts.
April 28, 1966 TRW's contract was amended further; a fifth spacecraft would be con-
structed from spare parts.
Table 3-142.
Pioneer 1 Characteristics
Table 3-143.
Pioneer 2 Characteristics
Table3-144.
Pioneer 3 Characteristics
Table 3-145.
Pioneer 4 Characteristics
Table 3-146.
Pioneer 5 Characteristics
Table 3-147.
Pioneer 6 Characteristics
Table 3-148.
Pioneer 7 Characteristics
Table 3-149.
Pioneer 8 Characteristics
Table 3-150.
Pioneer 9 Characteristics
Ranger
Project Ranger, like the early Pioneers, was established in response to increas-
ing scientific interest in the moon and to the successful lunar flight program of the
Soviet Union. The design of the spacecraft was first suggested during studies done at
the Jet Propulsion Laboratory (JPL) when advanced planners were considering
Vega-launched lunar and planetary missions. After the Vega launch vehicle program
was cancelled (see chapter 1) in favor of the Air Force Atlas-Agena B in December
1959, the design group at JPL was directed to adapt its Vega lunar spacecraft and
experiment packages to an Atlas-Agena B mission. Lunar photography was con-
sidered a prime objective since it would support future manned lunar landings and
provide a valuable scientific data base.
The lunar program, tentatively named Ranger in 1960 and assigned to JPL,
called for two lunar near-misses, or probes (called Block I), and three impact mis-
sions (Block II). Ranger 1 and 2 were to be launched in highly elliptical earth orbits
that would take them near the moon so that their eight scientific instruments could
measure radiation, solar emissions, and magnetic fields in the cis-lunar environment
and serve as a test for the new hexagonally-shaped solar-powered spacecraft.
Because of launch vehicle failures, the first two Rangers (1961) were boosted only
310 NASA HISTORICAL DATA BOOK
into low earth orbit, to reenter shortly thereafter. The next three Rangers, the cap-
sules for which were built by the Aeronautics Division of Ford Motor Company,
also failed. Equipped with television camera systems provided by RCA, Ranger 3
and 4 impacted the moon, but without the ability to transmit telemetry. Ranger 5
missed the moon by 725 kilometers. Block III spacecraft carried only a televsion
system-no other onboard experiments-in an effort to simplify the mission and en-
sure a successful lunar impact with photographs. Even before Ranger 6, too, failed
to return any data, NASA Headquarters directed JPL to terminate its follow-on
Ranger activities, which had called for Block IV and V spacecraft that could survive
a hard landing. The failures of all six Rangers led to investigations by Congress,
JPL, and independent boards appointed by NASA. With an increased number of
design and hardware reviews, revised schedules, closer monitoring of the subcon-
tractors, and more intense participation by NASA Headquarters personnel, Ranger
7, 8, and 9 were all highly successful missions. They returned over 17 000 high-
quality images of the lunar surface, which were studied by hundreds of scientists and
by manned spaceflight specialists looking for their first Apollo lunar landing site.
Early program failures, budget cuts, and plans for Lunar Orbiter and Surveyor pro-
grams forced NASA to terminate Ranger after the third successful mission.
Newton W. Cunningham led the NASA management of Ranger as program
manager within the Office of Lunar and Planetary Programs. At JPL, J. D.
Burke, who had been deputy director of the Vega program, was Ranger project
manager from October 1960 until December 1962, when Harris M. Schurmeier took
the post. JPL not only oversaw the work of many subcontractors, but also per-
formed most of the spacecraft integration and testing in-house and established a
deep space tracking network with which to communicate with the spacecraft.
For more information, see R. Cargill Hall, Lunar Impact: A History of Project
Ranger, NASA SP-4210 (Washington, 1977); and Hall, Project Ranger: A
Chronology, JPL HR-2 (Pasadena, CA: JPL, 1971).
SPACE SCIENCE AND APPLICATIONS 311
Table 3-151.
Date Event
April 1958 JPL's Functional Design Group was established to study possibilities for a
160-kilogram spacecraft capable of a Mars mission.
Feb. 6-7, 1959 NASA Headquarters and JPL officials established management respon-
sibilities for Vega and proposed payloads for lunar and deep space missions.
Lunar probes would be followed by lunar orbiters and then lunar landers,
with the first probe mission tentatively scheduled for August 1960.
Dec. 11, 1959 The Vega launch vehicle program was cancelled in favor of Atlas-Agena B.
Dec. 21, 1959 JPL was directed to establish a post-Vega lunar and interplanetary flight pro-
gram with missions through 1962. High-resolution photography was judged
the most urgent goal of this new program. Five Atlas-Agena B-launched
lunar reconnaissance missions were suggested for 1961-1962.
Jan. 12, 1960 NASA chose eight experiments for the first two near-lunar missions.
Jan. 21, 1960 The first of two lunar near-misses (Block I) was scheduled for February 1961,
with the first of three impact missions (Block II) scheduled for August 1961.
Jan. 26, 1960 The lunar spacecraft was tentatively designated Ranger. C. I. Cummings and
J. D. Burke were named program director and deputy director of JPL's new
Lunar Program Office.
Feb. 5, 1960 NASA Headquarters officially approved the Agena B program and gave JPL
permission to proceed with Ranger.
March 1, 1960 JPL awarded study contracts for Ranger design to North American Aviation,
Hughes Aircraft, and the Aeronautics Div. of Ford Motor Co.; reports were
due on April 15.
March 25, 1960 A letter contract was awarded to RCA for a lunar impact TV camera system.
April 27, 1960 JPL awarded a contract to Ford for the development of five rough-landing
capsules ($4.8 million, contract value).
June 30, 1961 JPL plans for Ranger follow-on missions, the first flight of which was
scheduled for January 1963, were delivered to Headquarters; included were
four Ranger missions (Block III) with emphasis on lunar photography. Head-
quarters approved these follow-on plans in August.
Aug. 23, 1961 Ranger 1 was launched on the fifth countdown; the spacecraft did not
achieve its planned orbit.
Nov. 18, 1961 Ranger 2 was launched on the fourth countdown; the spacecraft did not
achieve its planned orbit.
Dec. 1, 1961 Final approval was given for four experiments for the Block II Rangers.
Jan. 26, 1962 Ranger 3 was launched; lunar impact was not achieved.
April 23, 1962 Ranger 4 was launched; telemetry transmissions before impact failed.
June 1962 Initial planning was started for a Block IV series. Northrop contributed a
preliminary design study for a soft-landing capsule. Tentative launch dates
(1964) were released in October; by late fall as many as 20 flights were being
considered.
312 NASA
HISTORICAL
DATABOOK
Table3-151.
Chronology
ofRanger
Development
andOperations
(Continued)
Date Event
Oct. 18, 1962 Ranger 5 was launched; it did not impact on the moon.
Oct. 29, 1962 Headquarters established a Ranger board of inquiry, who submitted its final
report on November 30.
Dec. 7, 1962 H. M. Schurmeier was named JPL project manager, replacing Burke.
Feb. 12-13, 1963 At a Ranger reprogramming meeting, it was decided that Block Ill and IV
spacecraft would be impacting-photography missions, with additional ex-
periments incorporated into 1V only; planning for Block V (12 hard landers)
was approved.
March 8, 1963 Northrop was selected to provide support for Block III and V and to
fabricate Block V spacecraft.
July 12, 1963 Headquarters directed JPL to terminate all its efforts on impact missions
beyond Block III. While Block V- redesignated Block IV- landers were not
eliminated, JPL was asked to study the possibility.
Dec. 13, 1963 Headquarters directed JPL to cancel all activities beyond Block Ill.
Jan. 30, 1964 Ranger 6 was launched successfully, but it transmitted no telemetry before
impact.
Feb. 2-3, 1964 JPL and independent Ranger 6 review boards were established. The inde-
pendent board's final report was issued in March.
Feb. 16, 1964 A TV subsystem for the next Ranger spacecraft was returned to RCA for
reexamination.
April-May 1964 The House of Representatives Committee on Science and Astronautics Sub-
committee on NASA Oversight investigated Project Ranger.
July 28, 1964 Ranger 7 was launched successfully with good data return.
Feb. 17, 1965 Ranger 8 was launched successfully with good data return.
March 21, 1965 Ranger 9 was launched successfully with good data return.
SPACE SCIENCE AND APPLICATIONS 313
Table 3-152.
Ranger 1 Characteristics
Table 3-153.
Ranger 2 Characteristics
Table 3-154.
Ranger 3 Characteristics
center:
Project manager: J. D. Burke
Contractors: Aeronutronic Div., Ford Motor Co., lunar capsule subsystem
Radio Corporation of America-Astro-Electronics Div., TV camera subsystem
Type of Ranger: Block II
Objectives: Collect in-flight data on gamma rays; make a rough landing on the moon at a
predetermined sight; transmit data on seismic activity and temperature and TV pic-
tures prior to impact.
Experiments, TV cameras, JPL et al.
Table 3-155.
Ranger 4 Characteristics
Results: The spacecraft impacted the backside of the moon on April 26; a possible failure of
the spacecraft central computer and sequencer caused the master clock to stop; no
telemetry was received.
316 NASA HISTORICAL DATA BOOK
Table 3-156.
Ranger 5 Characteristics
Shape: Hexagonal base with 2 trapezoidal solar panels, 1 pointable high-gain antenna, a
radar altimeter antenna, and a landing capsule
Dimensions (m): Diameter, 1.5
Overall height, 3.6
Full span, 5.2
Power source: AgZn batteries plus solar cells
Date of reentry: In orbit around the sun
Results: Ranger power failure rendered all systems and experiments useless; spacecraft
passed within 725 kilometers of the moon; four hours of data were received from the
gamma ray experiment before battery depletion.
Table 3-157.
Ranger 6 Characteristics
Shape: Hexagonal base with 2 rectangular solar panels, pointable high-gain antenna, and
omnidirectional low-gain antenna
Dimensions (m): Diameter, 1.5
Overall height, 3.6
Full span, 4.6
Power source: AgZn batteries plus solar cells
Date of reentry: Impacted on moon
Cognizant NASA JPL
center:
Project manager: H. M. Schurmeier
Contractors: Radio Corp. of America-Astro-Electronics Div., TV camera subsystem
Type of Ranger: Block III
Objectives: Obtain television pictures of the lunar surface before impact for scientific study and
for the support of Apollo.
Experiments, TV cameras, University of Arizona, U.S. Geological Survey, Unversity of Califor-
responsible nia at San Diego, JPL
institution:
Results: Ranger TV cameras failed; spacecraft impacted in Sea of Tranquility area on
February 2, 1964; no data were returned.
SPACE
SCIENCE
ANDAPPLICATIONS 317
Table
3-158.
Ranger 7 Characteristics
Table 3-159.
Ranger 8 Characteristics
Objectives: Obtain television pictures of the lunar surface before impact for scientific study and
for the support of Apollo.
Experiments, TV cameras, University of Arizona, U.S. Geological Survey, University of Califor-
responsible nia at San Diego, JPL
institution:
Results: Spacecraft transmitted 7137 photographs of the moon; impacted in Sea of Tran-
quility area on Feb. 20, 1965.
318 NASA HISTORICAL DATA BOOK
Table 3-160.
Ranger 9 Characteristics
Shape: Hexagonal base with 2 rectangular solar panels, pointable high-gain antenna, and
omnidirectional low-gain antenna
Dimensions (m): Diameter, 1.5
Overall height, 3.6
Full span, 4.6
Power source: AgZn batteries plus solar cells
Date of reentry: Impacted on moon
Cognizant NASA JPL
center:
Project manager: H. M. Schurmeier
Contractor: Radio Corp. of America-Astro-Electronics Div., TV camera subsystem
Type of Ranger: Block III
Objectives: Obtain television pictures of the lunar surface before impact for scientific study and
for the support of Apollo.
Experiments, TV cameras, University of Arizona, U.S. Geological Survey, University of Califor-
Lunar Orbiter
The Surveyor lunar orbiter project as approved in 1960 was a two-part under-
taking. An orbiter would be used for lunar reconnaissance and a lander for surface
exploration. However, development problems with the Centaur launch vehicle, early
failures with Project Ranger, and increasing demands from the Office of Manned
Space Flight for information on the lunar surface that would assist them in finding
landing sites for Apollo, led Office of Space Sciences personnel to look for an alter-
native to the Surveyor orbiter. In 1962 and 1963, working groups at Headquarters
and NASA's Langley Research Center were formed to study the requirements of an
orbiter mission and suggest a center to manage its development and operations, and
by March 1963 designers at Langley had completed plans for a lightweight orbiter.
This was the Virginia center's first major spaceflight project, and the personnel
at Langley were especially anxious for it to be a successful one. Proposals from five
companies for an orbiter were studied during 1963, with a contract being awarded to
the Boeing Company in May 1964. This also was Boeing's first spacecraft venture.
The 385-kilogram orbiter constructed by Boeing carried a photography system
developed by Eastman Kodak and three scientific experiments sponsored by Langley
and JPL-selenodesy (the lunar equivalent to geodesy), meteoroid detection, and
radiation measurement. While the scientific and photographic returns of the Lunar
Orbiter missions would, of course, be of high interest to scientists, the data would
contribute to the Surveyor lander project and to the Apollo lunar landings, the agen-
cy's most popular and visible program. Lunar Orbiter 1 through 5 were all suc-
cessful, returning hundreds of high- and medium-resolution orbital photographs of
the moon that were orders of magnitude better than those returned by Ranger or
Surveyor. By the end of the third mission, the manned program's requirements of
Lunar Orbiter had been met. In addition to prospective landing sites, other areas of
the moon were photographed, and by the end of the project a broad systematic
survey had been accomplished, including the moon's dark side. Scientists and
designers of lunar landers received much useful data on radiation, gravity, and
micrometeorites, and the manned program's tracking network had several oppor-
tunities to practice tracking a spacecraft in the vicinity of the moon.
The highly successful Lunar Orbiter was managed at NASA Headquarters by
the Office of Lunar and Planetary Programs, with Lee R. Scherer as program
manager. At Langley, C. H. Nelson served as project manager. The Boeing Com-
pany was the prime spacecraft contractor, with Eastman Kodak supplying the essen-
tial photographic subsystem and RCA providing the communications subsystem.
For more information on Lunar Orbiter, see Bruce K. Byers, Destination Moon:
A History of the Lunar Orbiter Program, NASA TM X-3487 (Washington, 1977).
320 NASA HISTORICAL DATA BOOK
Table 3-161.
Chronology of Lunar Orbiter Development and Operations
Date Event
May 1958 Long-range planners at the National Advisory Committee for Aeronautics
suggested that the new civilian space agency being formed should send or-
biters to the moon to gather data on its mass, magnetic field, and radioactivi-
ty and general information on its surface, with the first mission taking place
by 1960.
May 1960 NASA approved the Surveyor lunar program, to consist of an orbiter and a
lander for photographic coverage and surface exploration. JPL was assigned
responsibility for the project (see table 3-167).
Sept. 1962 Because of problems with Ranger at JPL, demands from the Apollo program
for more detailed information on the lunar surface, and delays in the
development of the Centaur launch vehicle on which the Surveyor orbiter
would be launched, the Office of Space Sciences (OSS) was examining alter-
nate hardware and launch vehicles for a lunar orbiter mission. An OSS work-
ing group was formed to study the problem.
Oct. 1962 A joint Office of Manned Space Flight-Office of Space Sciences working
group was formed to study the requirements for an Agena-class orbiter. The
OSS group recommended giving Space Technology Laboratories (STL) a
study contract for an orbiter, which NASA did.
Jan. 1963 Langley Research Center personnel were asked to study the feasibility of that
center managing a lunar orbiter project.
Feb. 1963 STL's study was reviewed at a major planning meeting at Langley.
March 1963 Langley formulated a project approval document for a lightweight orbiter
mission; five companies began to develop proposals.
Aug. 30, 1963 A request for proposals for an orbiter mission and spacecraft was released to
industry, and a Lunar Orbiter Project Office was established at Langley
under the direction of Clifford H. Nelson.
Sept.-Nov. 1963 A Langley Source Evaluation Board studied proposals from Hughes Air-
craft, Boeing, TRW (of which STL was now a division), Martin Co., and
Lockheed for orbiters and from Eastman Kodak for a photographic system
to be used with the proposed Boeing orbiter. The board favored Boeing's pro-
posal and recommended it to Headquarters.
Dec. 20, 1963 Boeing was selected as prime contractor for the Lunar Orbiter and the launch
shroud.
May 7, 1964 Boeing's contract was signed by NASA's administrator ($75.8 million, con-
tract value).
Oct. 1964 A subcontract was awarded to Eastman Kodak for the photographic sub-
system. A Lunar Orbiter preliminary spacecraft design review was held.
Feb. 1965 A subcontract was awarded to RCA for the communications subsystem.
July 25, 1986 A flight readiness review for the first spacecraft was held at the Kennedy
Space Center.
Aug. 10, 1966 Lunar Orbiter I was launched successfully with good data return.
Nov. 6, 1966 Lunar Orbiter 2 was launched successfully with good data return.
Feb. 4. 1967 Lunar Orbiter 3 was launched successfully with good data return.
May 4, 1967 Lunar Orbiter 4 was launched successfully with good data return.
July 24, 1967 Plans for a possible sixth mission were not approved by Headquarters.
Aug. 1, 1967 Lunar Orbiter 5 was launched successfully with good data return.
SPACE SCIENCE AND APPLICATIONS 321
Table 3-162.
Lunar Orbiter I Characteristics
Table 3-163.
Lunar Orbiter 2 Characteristics
(location):
Launch vehicle: Atlas-Agena D
Weight (kg): 385.6
Shape: Truncated cone with 4 solar panels projecting from base (2-part primary struc-
ture- main equipment mounting deck, and an upper module supported by trusses
and an arch)
Dimensions (m): Stowed, 1.64 x 1.67
With antennas and panels deployed, 5.6 x 3.7
Po wer source: NiCd battery plus solar cells
Date of reentry: Impacted on moon
Cognizant NASA LaRC
cen ter:
Project manager: Clifford H. Nelson
Con tractors: Boeing Co., prime
Eastman Kodak, TV camera subsystem
Radio Corp. of America, communications subsystem
Objectives: In lunar orbit, obtain high- and medium-resolution images of various types of lunar
terrain suitable for Surveyor and Apollo landing sites; provide information of
gravitational field through tracking exercises; measure radiation and detect
micrometeorites.
Experiments, Same as for Lunar Orbiter 1 (table 3-162).
responsible
institution:
Results: Transmitted 211 high- and medium-resolution photographs and monitored radia-
tion in the lunar environment; photographed i 3 primary Apollo target sites (36 000
square kilometers). Mission was terminated by crashing the spacecraft onto the
lunar surface on October 11, 1967 (perilune, 196 kilometers).
SPACE
SCIENCE
ANDAPPLICATIONS 323
Table 3-164.
Lunar Orbiter 3 Characteristics
Table 3-165.
Lunar Orbiter 4 Characteristics
Table3-166.
Lunar Orbiter 5 Characteristics
Surveyor
flights, the first of which was planned for launch on Atlas-Centaur in 1963. Unfor-
tunately, the new Centaur stage did not cooperate, and repeated schedule delays
with the launch vehicle forced Surveyor managers to postpone the lander's first mis-
sion. Surveyor's designers also had to pare down the spacecraft's size so that it was
compatible with Centaur's more limited lifting capabilities-from an original 1134
kilograms with a 156-kilogram payload to a 953-kilogram spacecraft with 52
kilograms of instruments. It was 1966 before Atlas-Centaur was operational, but the
new booster launched all seven Surveyors into the proper trajectories.
Surveyor lander was roughly triangular in shape with two equipment compart-
ments and a vertical mast to hold a solar panel and several antennas° The three-
meter-high craft was supported on three landing legs with shock absorbers and foot-
pads. Its controlled landing was accomplished by three vernier engines and a
retrorocket. The first two landers were equipped with only a television camera
(capable of both 25- and 6-degree fields of view) for taking post-landing
photographs. Surveyor 1 landed on the moon on June 2, 1966, three days after it
started its journey from the Eastern Test Range. Transmitting more than 10 000
high-quality images, it remained operational until the following January. Trouble
with the vernier engines caused the second lander to crash into the moon, but
Surveyor 3 with added features returned an abundance of data. Besides 6315
photographs, the earth-bound specialists received information on the composition
and surface-bearing strength of the lunar crust as the television camera focused on a
surface sampler as it dug trenches in the soil and on thermal and radar reflectivity.
Surveyor 4 failed; minutes before it was due to land something went wrong, and the
spacecraft either exploded or crashed onto the moon's surface. The last three mis-
sions all returned thousands of photographs and supplied data on chemical elements
in the soil, touchdown dynamics, and the surface's magnetic properties. Mission
specialists had a great deal of control over the Surveyor spacecraft and could correct
its trajectory if needed and otherwise maneuver it. Surveyor 6was even restarted and
moved three meters on the surface. Apollo designers had met all their objectives
with Surveyor by the end of the sixth flight, and NASA managers cancelled any
follow-on Block II or III missions. Scientists, too, especially geologists, benefitted
from the vast photographic archives made possible by Surveyor (some of the
photographs were in color). Surveyor 7 landed in an area of high scientific interest
outside the Apollo target area.
Surveyor was managed by the NASA Headquarters Office of Lunar and
Planetary Programs within the Office of Space Science and Applications (OSSA).
Benjamin Milwitzky served as program manager. At JPL, Walker E. Gibberson led
the Surveyor team in its early days, with Robert J. Parks taking over in 1965.
Howard H. Haglund assumed the role in late 1966. Hughes Aircraft Company was
the prime spacecraft contractor.
No single source can be suggested for further reading, but several volumes
published by NASA record the results of the project. Among them, the following is
perhaps the most useful: NASA, Office of Space Science and Applications, comp.,
Surveyor Program Results, NASA SP-184 (Washington, 1969).
SPACE SCIENCE AND APPLICATIONS 327
Table 3-167.
Chronology of Surveyor Development and Operations
Date Event
May 1960 NASA approved the Surveyor launch program to consist of two parts-an
orbiter for photographic coverage and a lander for surface exploration. The
Jet Propulsion Laboratory (JPL) was assigned project responsibility for
Surveyor and for Ranger.
July 1960 Four Surveyor study contracts were awarded to Hughes Aircraft, North
American, Space Technology Laboratories, and McDonnell Aircraft, with
JPL providing design requirements. Eight study contracts for experiment
proposals also were let.
Jan. 19, 1961 Hughes was selected as contractor to build seven Surveyor landers; a letter
contract was issued on March 1. The first launch was scheduled for August
1963 on an Atlas-Centaur.
Mid-1962 Because of Centaur development problems, early failures with Ranger, and
increasing demands for information on the lunar surface for Apollo, the or-
biter portion of Surveyor was dropped and replaced by Lunar Orbiter, to be
managed at Langley Research Center. Problems with the Centaur stage
forced the postponement of the first Surveyor launch.
Early 1963 Initial testing of the first proof test model was completed.
Nov. 27, 1963 The second Atlas-Centaur test launch was successful.
Aug. 11, 1965 Atlas-Centaur launched a Surveyor model successfully, putting the dummy
spacecraft into a highly elliptical orbit to simulate lunar transfer orbit.
Feb. 1, 1966 A soft-landing retrorocket system was tested successfully by Hughes and
JPL.
April 7, 1966 Atlas-Centaur launched a Surveyor model, but the vehicle failed to achieve
double ignition, and the dummy spacecraft remained in earth orbit.
May 11, 1966 The Surveyor spacecraft accomplished a soft-landing test under its own
power.
May 30 1966 Surveyor 1 was launched successfully, landing on the moon on June 2.
June 1, 1966 A General Accounting Office report charged NASA with spending $2.5
million on Surveyor experiments it had not required.
Sept. 20, 1966 Surveyor 2 was launched successfully, but the spacecraft crashed into the
lunar surface on September 22 due to vernier engine failure.
Dec. 13, 1966 NASA dropped plans for three additional Surveyors (Block II) and a possible
Surveyor rover because of good results with later Ranger spacecraft, Lunar
Orbiters, and Surveyor I and because of budgetary considerations.
April 17, 1967 Surveyor 3 was launched successfully, landing on the moon on April 19.
July 14, 1967 Surveyor 4 was launched successfully, but the spacecraft failed minutes
before its scheduled landing.
Sept. 8, 1967 Surveyor 5 was launched successfully, landing on the moon on September 10.
Nov. 7, 1967 Surveyor 6 was launched successfully, landing on the moon on November 9.
Jan. 7, 1968 Surveyor 7 was launched successfully, landing on the moon on January 9.
June 28, 1968 JPL's Surveyor project office was closed.
328 NASA HISTORICAL DATA BOOK
Table 3-168.
Surveyor 1 (Surveyor-A) Characteristics
Results: Soft-landed on the moon June 2 in the Ocean of Storms area; returned more than
10 000 high-quality images and selenological data; completed primary mission July
13 with communications reestablished periodically through January 1967.
Remarks: First spacecraft to soft-land on the moon.
Table 3-169.
Surveyor 2 (Surveyor-B) Characteristics
Table3-170.
Surveyor 3 (Surveyor-C) Characteristics
Table 3-171.
Surveyor 4 (Surveyor-D) Characteristics
Table 3-172.
Surveyor 5 (Surveyor-E) Characteristics
Results: Soft-landed on the moon in Sea of Tranquility area on September 10; returned
18 000 images, some converted to color; obtained data on lunar surface radar and
thermal reflectivity; performed other investigations as planned. Complete signal was
lost on December 16, 1967.
Table 3-173.
Surveyor 6 (Surveyor-F) Characteristics
Table 3-174.
Surveyor 7 (Surveyor-G) Characteristics
Mariner
dataabouttheatmosphere
andsurfaceof theplanet.Mariner 3 and 4, flyby mis-
sions, were approved in late 1962 as Mariner-Mars 1964. Again, only one of the pair
was successful. Mariner 4 reached Mars in 228 days, sending back 21 Y2 photographs
of the Red Planet's surface and information about its atmosphere. Mission planners
and scientists, anxious to send orbit-landers to Mars and Venus, designed a heavy,
sophisticated spacecraft called Voyager in 1962, but Voyager plans were never
translated into flight hardware. Money and launch vehicles were once again the
problems. The proposals or cancellations of Mariner-Mars 1966 (flyby), Advanced
Mariner 1969 (Mars orbiter-lander), Mariner-Venus 1967 (flyby), Mariner-Mars
1969 (flyby), Mariner-Mars 1971 (orbiter), and Mariner Venus-Mercury 1973 (flyby)
were all affected in some way by Voyager's postponements and cancellation. The
one other Mariner launched during NASA's first decade was Mariner 5, which took
advantage of the 1967 Venus launch windows. The spacecraft flew by this cloud-
shrouded planet on October 19, 1967 and reported on its atmosphere, mass, and
solar wind interaction.
The first five Mariners were in the 200-260-kilogram class and were launched by
Atlas-Agena B or D vehicles. Their hexagonal or octagonal frame bases held scien-
tific instruments designed by personnel from NASA's centers and from American
universities. Solar panels provided spacecraft powers, and the Deep Space Network
at the Jet Propulsion Laboratory (JPL) was responsible for tracking and com-
munications. Many companies contributed components to the Mariners, acting as
subcontractors to the Jet Propulsion Laboratory, where the spacecraft were
assembled and tested.
At NASA Headquarters, the Mariner program was managed by Fred D. Kochen-
dorfer of the Office of Lunar and Planetary Programs until 1963, when Donald P.
Hearth began acting as Pioneer and Mariner manager. Glenn A. Reiff took over in
1965. In mid-1967, Reiff took responsibility for Mariner-Mars 1967 only, and
Newton W. Cunningham managed Mariner-Mars 1969, with Earl W. Glahn becom-
ing manager of Mariner-Mars 1971 in late 1968. At JPL, Jack N. James was
Mariner project manager until January 1965, when Dan Schneiderman assumed the
job.
For an overall look at Mariner history, see chapters 2, 3, 6, and 9 of Edward C.
and Linda N. Ezell, On Mars: Exploration of the Red Planet, 1958-1978, NASA
SP-4212 (Washington, 1984). Many NASA publications have been issued on the
Mariner projects and their results; three useful ones are JPL, Mariner-Venus 1962
Final Project Report, NASA SP-59 (Washington, 1965); JPL, Mariner-Mars 1964
Final Project Report, NASA SP-139 (Washington, 1967); and JPL, Mariner-Venus
1967 Final Project Report, NASA SP-190 (Washington, 1971).
SPACE SCIENCE AND APPLICATIONS 333
Table 3-175.
Mariner Proposals, 1960-1968
Mariner-Mars 1964 1962 Mars flyby (1964) Led to the launches of Mariner 3 and 4 in
1964.
Mariner-Mars 1966 1963 Mars flyby (1966) Cancelled in 1966 and replaced by a pro-
(to replace posal for Advanced Mariner 1969.
Mariner B)
Advanced Mariner 1964 Mars orbiter-lander Cancelled in 1964 for budgetary reasons.
1969 (to replace (1969)
Mariner-Mars 1966)
Mariner-Mars 1969 1965 Mars flyby (1969) Led to the launches of Mariner 6 and 7 in
(in answer to 1969.
Voyager postpone-
ment)
Mariner-Venus 1967 1965 Venus flyby (1967) Led to the launch of Mariner 5 in 1967.
(in answer to
Voyager postpone-
ment)
Mariner-Mars 1971 1967 Mars orbiter (1971) Led to the launches of Mariner 8 and 9 in
(in answer to 1971.
Voyager cancella-
tion)
Mariner Venus- 1968 Venus and Mercury Led to the launch of Mariner 10 in 1973.
Mercury 1973 flybys (1973)
(proposed by the
Space Science
Board)
*Does not necessarily indicate official proposal; for further details see table 3-176.
334 NASA HISTORICAL DATA BOOK
Table 3-176.
Chronology of Mariner Development and Operations
Date Event
1958-1959 Several feasibility studies for unmanned lunar and planetary missions
resulted in conceptual designs for spacecraft using the planned Atlas-Centaur
launch vehicle; the earliest mission was scheduled for 1962 to Venus.
July 1960 A study was begun at the Jet Propulsion Laboratory (JPL) for a Mariner A
mission that would fly by Venus in 1962 and a Mariner B mission for an in-
strumented landing on Venus or Mars in 1964.
Feb. 1961 Revised plans for Mariner A called for missions to Venus in 1962, 1964, and
1965; revised plans for Mariner B dropped the Venus landing from considera-
tion.
Aug. 1961 A study was begun at JPL for a Mariner-Venus 1962 flyby mission (also call-
ed Mariner R), which led to Mariner 1 and 2.
Aug. 30, 1961 Mariner A was cancelled due to the projected unavailability of the Atlas-
Centaur; Mariner-Venus 1962 was approved.
Early 1962 JPL began a design study for a Mariner-Mars 1964 craft for a flyby mission
to Mars, which led to Mariner 3 and 4.
April 9, 1962 Mariner B's Mars landing option was dropped and the Venus landing recon-
sidered.
July 22, 1962 Mariner 1 launch was unsuccessful when the launch vehicle malfunctioned.
Aug. 27, 1962 Mariner 2 launch was successful; the spacecraft passed by Venus on
December 14.
March 1, 1963 A project approval document for Mariner-Mars 1964 was signed; the Atlas-
Agena launch vehicle was substituted for Atlas-Centaur, which was still
behind schedule.
March 14, 1963 The Mariner B mission was changed to a pre-Voyager checkout flight to Mars
with a lander.
April 11, 1963 The selection of 10 experiments for Mariner-Mars 1964 was announced.
May 6, 1963 A Mariner-Mars 1966 flyby project was proposed, which took the place of
Mariner B.
June-Dec. 1963 A Mariner-Mars 1964 spacecraft proof-test model was assembled and testing
begun.
July 28, 1964 Mariner-Mars 1966 was effectively cancelled, with official termination com-
ing on September 4; it would be replaced by Advanced Mariner 1969.
Aug. 2, 1964 A project approval document for Advanced Mars 1969 was signed.
Sepl. 11, 1964 Mariner-Mars 1964 spacecraft arrived at the Kennedy Space Center.
Nov. 5, 1964 Mariner 3 launch was unsuccessful due to the failure of the shroud to jettison
properly.
Nov. 19, 1964 Lewis Research Center undertook the supervision of Lockheed's design and
development of a metal shroud for the next Mariner launch; the metal shroud
would replace the fiberglass one that had failed on Mariner 3.
SPACE SCIENCE AND APPLICATIONS 335
Table 3-176.
Chronology of Mariner Development and Operations (Continued)
Date Event
Nov. 20, 1964 Advanced Mariner 1969 was cancelled because of budgetary considerations.
Nov. 28, 1964 Mariner 4 was launched successfully; the spacecraft passed by Mars on July
14, 1965.
Dec. 22, 1965 A Mariner-Mars 1969 flyby project _was tentatively approved when the
Voyager Venus-Mars project was postponed (this led to Mariner 6 and 7).
Dec. 25, 1965 A Mariner-Venus 1967 flyby project was approved when the Voyager Venus-
Mars project was postponed (this led to Mariner 5).
March 28, 1966 A project approval document for Mariner-Mars 1969 was signed.
June 14, 1967 Mariner 5 launch was successful; the spacecraft passed by Venus on October
19.
Nov. 1967 Mariner-Mars 1971 was proposed after cancellation of Voyager (this led to
Mariner 8 and 9).
June 1968 Mariner Venus-Mercury 1973 was proposed by the Space Science Board (this
led to Mariner 10). The first Mariner-Mars 1969 spacecraft was assembled.
Aug. 23, 1968 A project approval document for Mariner-Mars 1971 was signed.
Nov. 14, 1968 JPL was authorized to begin work on Mariner-Mars 1971.
Table 3-177.
Mariner I (Mariner R-I) Characteristics
Table 3-178.
Shape: Hexagonal frame base with 2 solar panels; antennas mounted atop the base
Dimensions (m): Base, 1.04 x .36
Overall height, 3.66
Span with panels deployed, 5.05
Po wet source: AgZn battery plus solar cells
Date of reentry: in orbit around sun
Objectives: Send spacecraft to near-vicinity of Venus; establish and maintain two-way com-
munications with the spacecraft throughout flight; obtain data on the environment
in interplanetary space and near Venus; survey the planet's surface characteristics.
Experiments, Same as for Mariner 1 (table 3-177).
responsible
institution:
Results: Passed within 34 762 kilometers of Venus on December 14 and made a 42-minute in-
strument survey of the atmosphere and surface of the planet before going into
heliocentric orbit; made comprehensive measurements of the solar wind; transmis-
sions received until January 4, 1963, from a maximum distance of 87.4 million
kilometers.
Remarks." First spacecraft to scan another planet.
SPACE SCIENCE AND APPLICATIONS 337
Table 3-179.
Mariner 3 (Mariner C, Mariner-Mars 1964) Characteristics
Table 3-180.
Mariner 4 (Mariner D, Mariner-Mars 1964) Characteristics
Two other lunar and planetary projects were funded during the 1960s by
NASA's space science and applications program, but not beyond the paper study
phase. At one time, the unmanned lunar program called for three vehicles- Ranger,
Surveyor, and Prospector. Prospector, first funded in 1961, was the next step
kilograms, Prospector would "rove across the land, pick samples, deposit in-
strumented packages, take many close looks at the surface, detonate explosive
charges at various points for seismic measurements, and report all its findings back
to Earth." _t Prospector's designers at the Jet Propulsion Laboratory (JPL) even had
plans for a sample return task for the craft, and by 1963 Apollo planners wanted to
use the large spacecraft to store equipment that the astronauts would require when
landing on the moon. The first Prospectors were scheduled for launch in 1965-1966.
When Congress cut more than $23.5 million from the FY 1963 lunar and planetary
budget, this third class of unmanned lunar spacecraft was eliminated from the
roster.
SPACE SCIENCE AND APPLICATIONS 339
Table 3-181.
Mariner 5 (Mariner E, Mariner-Venus 1967) Characteristics
Mars in 1976 would make use of the many mission design studies, hardware and
scientific evaluations, and landing site surveys conducted in Pasadena. At NASA
Headquarters, Donald P. Hearth acted briefly as Voyager program manager before
Oran W. Nicks was named to that position in 1968. Donald P. Burcham led the ef-
fort at JPL, where Voyager design studies prepared by General Electric, Avco, and
others were evaluated.
For further information on Voyager, see chapter 4 of Edward C. and Linda N.
Ezell, On Mars: Exploration of the Red Planet, 1958-1978, NASA SP-4212
(Washington, 1984).
Except for a brief time (March 1960 to October 1961) during NASA's first I0
years, the life sciences was not centrally organized as a program on par with manned
spaceflight or space science, but was variously divided among the Office of Space
Science and Applications (OSSA), the Office of Manned Space Flight (OMSF), and
the Office of Advanced Research and Technology (OART). Life sciences meant
many things at NASA, and it was this multitude of different interpretations that
kept it from becoming a strong program in its own right. For the team charged with
sending man into space and eventually to the moon, life science investigations could
help answer many questions: What kind of environment would man require inside
his spacecraft? What were the effects of prolonged weightlessness on the car-
diovascular system? What were the maximum acceleration forces he could withstand
during launch and reentry?* Crew training and selection would also require a
medical doctor's expertise, as would monitoring the health of a crew in flight.
Management of "aerospace medicine" was assumed by NASA's manned spaceflight
experts. The designers of flight garments, spacecraft systems, and hardware with
which astronauts and pilots would work also needed the advice of specialists who
understood the physical and psychological needs and limits of man. Such
"bioengineering" projects were sponsored by OMSF and the advanced research and
technology office. The study of terrestrial life forms exposed to the conditions of
space (space biology) and the search for extraterrestrial life (exobiology) was left to
the agency's space scientists.
As most of the space biologist's work was done in laboratories under controlled
conditions that simulated the environment of space, not many flight projects were
totally devoted to biological payloads. Some experiments were performed on sound-
ing rockets (e.g., BIOS 1, a 1961 Journeyman-launched reentry experiment spon-
sored by the Goddard Space Flight Center) and on high-altitude balloon flights (with
monkeys, hamsters, insects, and microscopic specimens being sent aloft). The one
spaceflight project funded exclusively by the life sciences program, Biosatellite, was
*Long before NASA was established, the Air Force had set up several aviation and aerospace
medicine institutions committed to answering the same kind of questions. For more information on Air
Force programs in this field and how the existence of Air Force medical research centers affected NASA's
organization in the early 1960s, see John A. Pitts, The Human Factor: Biomedicine in the Manned Space
Program to 1980, NASA SP-4213 (Washington, 1985), chapters l and 2.
SPACE
SCIENCE
ANDAPPLICATIONS 341
judgedonlya partialsuccess
(seefollowingtables).Scientists
attempted
to observe
theeffectsof prolonged
weightlessness
andradiationonthegrowthof plantsand
animalscarriedonsmallsatellites,
buta retrorocket
failureterminated
thefirst mis-
sion, and bad weather and hardware problems contributed to the second spacecraft's
early return. Much of the data that was generated by the space biology program in
laboratories and with other small flight experiments was directly applicable to the
design of manned spacecraft and life support equipment and to aerospace medicine.
Exobiology was a more "purely" scientific endeavor, and it did not contribute to
the manned spaceflight program. But finding life elsewhere in the solar system
would most certainly have had a profound impact on scientists concerned with
discovering the origins and composition of earth-based life forms. Exobiologists
studied data returned by lunar and interplanetary spacecraft and pored over
photographs of the moon, Venus, and Mars for clues, chemical or geological, that
might lead them to some extraterrestrial life or to an environment that seemed con-
ducive to harboring carbon-based life. With the increasing sophistication of in-
terplanetary spacecraft capable of long-duration flights, scientists began designing
hardware for life-detecting instruments that could be sent near or to Venus and
Mars. Project Voyager would have been the exobiologists' first opportunity for a
lander mission on another planet, but its cancellation in 1967 put a temporary end to
years of work on Mars- and Venus-bound experiments. Most of this activity,
however, was redirected to Project Viking in the 1970s.
Before March 1960, biology and biotechnology was the exclusive concern of
manned spaceflight and advanced technology directorates, but in the spring of 1960
Administrator T. Keith Glennan took the advice of his Bioscience Advisory Com-
mittee and established a separate Office of Life Sciences, with Clark T. Randt as
director (see table 3-1). Five assistant directors (for bioengineering, grants and con-
tracts, space biology, program planning, and aerospace medicine) were assigned to
Randt. This office would supplant the Special Committee on Life Sciences, which
had been formed by Glennan in 1958 to serve as an advisory body to Project Mer-
cury personnel. The Bioscience Advisory Committee also recommended that NASA
establish a central laboratory for life sciences research. Ames Research Center in
California was chosen as the most likely site for such a facility, and Richard S.
Young was assigned to Ames in early 1961 to establish more formal life sciences ac-
tivities there. However, the first new facilities at Ames were not constructed until
1963-1964. These new laboratories were equipped with the tools required by space
biologists and exobiologists, including a large animal shelter (vivarium) to house the
thousands of laboratory animals required for research.
With the change of administrations in Washington in November 1961 came a
change in NASA's organization. The new administrator, James E. Webb, abolished
the Office of Life Sciences Programs and reassigned the personnel throughout the
agency, mainly to the new Office of Manned Space Flight. A director of bioscience
programs, Orr E. Reynolds, was named in the space sciences directorate, but his
staff and budget were small. Reynolds served as the head of NASA Headquarters'
bioscience program throughout the remainder of NASA's first decade and beyond.
Reporting to Reynolds were chiefs of exobiology, environmental biology, physical
biology, behavioral biology, and planetary quarantine.
For further reading, see the following: on how life sciences fit into NASA's
space science and applications program, Homer E. Newell, Jr., Beyond the At-
mosphere: Early Years of Space Science, NASA SP-4211 (Washington, 1980), chap.
342 NASAHISTORICAL
DATA
BOOK
16;on AmesResearch
Center's
rolein thelifesciences,
EdwinP. Hartman,Adven-
tures in Research: A History of Ames Research Center, NASA SP-4302
(Washington, 1970), pp. 321-23, 325, 426-28, 478-87, 496-502; and Elizabeth A.
Muenger, Searching the Horizon: A History ofAmes Research Center, 1940-1976,
NASA SP-4304 (Washington, 1985), chap. 5; and on space medicine, John A. Pitts,
The Human Factor: Biomedicine in the Manned Space Program to 1980, NASA
SP-4213 (Washington, 1985); on exobiology, Edward C. and Linda N. Ezell On
Mars: Exploration of the Red Planet, 1958-1978, NASA SP-4212 (Washington,
1984), chap. 3; and on NASA's changing organization, Robert L. Rosholt, An Ad-
ministrative History of NASA, 1958-1963, NASA SP-4101 (Washington, 1966).
Biosatellite
First with balloons and later with sounding rockets and airplanes, biologists and
physicians had been observing the effects of high altitudes on living specimens for
many years before NASA was organized. In an environmentally controlled
spacecraft, scientists could study phenomena that were relative to their laboratory
investigations but often impossible to simulate on earth (for example, prolonged
weightlessness). Internal discussions among NASA personnel concerning a
recoverable biological probe or satellite mission date from early 1959, with a Na-
tional Academy of Sciences Space Science Board summer study group endorsing the
suggestion in 1961. During such a mission, specialists could observe the effects of
radiation and weightlessness on plants, insects, and small animals and study how liv-
ing systems react to being deprived from their normal day-night cycle.
Six Biosatellite flights were approved by NASA in 1962 and the project assigned
to Ames Research Center, Moffett Field, California.* The missions would become
increasingly complex over time, progressing from two 3-day flights with a payload
of plant and insect matter, to two 21-day flights with a more sophisticated general
biology package, and culminating in two 30-day flights with a primate on board.
The response from the scientific community for experiments was enthusiastic, with
some 170 proposals being submitted for consideration. The 3-day missions could ac-
commodate 14 relatively simple experiments (13 were actually flown); 4 investiga-
tions could be selected for the 21-day missions; and 4 areas of investigation were
allowed for the 30-day primate mission. In January 1964 after more than a year's
evaluation, the Bioscience Program Office at NASA Headquarters recommended 22
experiments to be included in the Biosatellite program.
Experiments on the first two flights would be exposed to one of two en-
vironments: radiation and weightlessness, or weightlessness only with no radiation.
Provisions were made in the capsule for an essentially radiation-free area to house
control experiments or those that did not require exposure to radiation, for an area
where radiation exposures were to be precisely timed (1 rad/day), and for an area
*For more on this project's management and the conflict it raised between the Office of Space
Science and Applications and the Office of Advanced Research and Technology, see John Pitts, The
Human Factor: Biomedicine in the Manned Space Progam to 1980, NASA SP-4213 (Washington, 1985),
pp. 82-84.
SPACE
SCIENCE
ANDAPPLICATIONS 343
in 1969, did not go according to plan either. On the eighth day of flight, the primate
appeared unresponsive, and the team called the spacecraft down.
Managment of the Biosatellite project was static during its seven years. At
Headquarters, Thomas P. Dallow was Biosatellite chief, reporting to Director of
Bioscience Programs Orr Reynolds. Charles A. Wilson, taking over for retiring
Carlton Bioletti, led the team at Ames Research Center as project manager from
March 1965 until the project's termination. Project Biosatellite was under the direc-
tion of Ames's assistant director for development rather than the assistant director
for life sciences.
The best single source for further information is J. W. Dyer, ed., Biosatellite
Project Historical Summary Report (Moffett Field, CA: Ames Research Center,
1969).
Table 3-182.
Chronology of Biosatellite Development and Operations
Date Event
April 1959 NASA's Office of Space Science included among its goals a recoverable
payload mission that would subject living things to the environment of space.
Nov. 1960 In a planning document, the Office of Space Hight Programs suggested a
flight project with biological experiments to study the effects of space en-
vironment on living things (frog eggs, germinating seeds, bacteria, algae).
Several contracts were let for studies.
Summer 1962 The Space Science Board of the National Academy of Sciences considered
methods by which NASA could held solve basic biological problems and sug-
gested the study of the effects of weightlessness, disassociation of living
systems from day-night cycles, and radiation on various living things.
July 1962 NASA announced that specialists at its centers were studying plans for a
biological project of three to six flights.
Oct. 1962 Ames Research Center was assigned the management of a biological satellite
project, unofficially called Biosatellite.
Dec. 1962 Six Biosatellite flights (3-, 21-, and 30-day missions) launched by Thor-Delta
vehicles were approved by NASA Headquarters, with the first launch
scheduled for late 1965. The Bioscience Subcommittee of NASA's Space
Science Steering Committee reviewed preliminary proposals for experiments.
Jan. 1963 The name Biosatellite was officially reserved for the project.
March 1, 1963 A request for proposals was issued for design and development studies of a
Biosatellite spacecraft.
April 11, 1963 General Electric, Northrop Aircraft Corp., and Lockheed Aircraft Corp.
were awarded eight-week preliminary design study contracts.
May 1963 Panels of specialists convened to evaluate further proposals for experiments
to be carried on Biosatellite missions.
Aug 21, 1963 GE was selected for negotiations for a Biosatellite contract.
Jan. 16, 1964 The Bioscience Programs Office recommended 22 experiments for the three
classes of missions.
Feb. 1964 Payload selection was made by the Office of Space Science and Applications.
March 19, 1964 GE was awarded a letter contract for design and fabrication of six spacecraft.
SPACE
SCIENCE
ANDAPPLICATIONS 345
Table 3-182.
Chronology
of Biosatellite Development andOperations (Continued)
Date Event
Dec.14,1966 Biosatellite 1 was launched successfully, but controlled reentry was not
achieved three days later because a retrorocket failed.
Jan.1967 A failure analysis review board was established.
Spring
1967 Publicity was generated over Biosatellite cost overruns.
Sept.
7,1967 Biosatellite 2 was launched successfully; the payload was recovered on
September 9, one day ahead of schedule because the spacecraft was not
responding satisfactorily to commands and because inclement weather
threatened the recovery area.
July30,1968 GE's contract was modified to cover continuation of work on four remaining
spacecraft.
July-Aug. 1968 A month-long laboratory test of systems designed to maintain a primate for a
30-day mission was completed.
Dec. 16, 1968 NASA terminated plans for Biosatellite C and D 21-day missions.
Table 3-183.
Biosatellite 1 (Biosatellite-A) Characteristics
Table 3-184.
Biosatellite 2 (Biosatellite-B) Characteristics
(location):
Launch vehicle." Thrust-augmented Thor-Delta (TAD)
Weight (kg): 381 (reentry vehicle, 199.6; adapter section, 181.4)
Shape: Cylindrical cone adapter and instruments section, plus a blunt-cone reentry vehicle
with heat shield
Dimensions (m): Adapter section, length, 2.06; diameter, 1.02-1.45
Reentry vehicle, length, 1.22; diameter at base, 1.02
Total length, 2.44
Diameter at point of mating with Delta, 1.37
Power source: AgZn batteries
Date of reentry: Oct. 4, 1967
Cognizant NASA ARC
center:
Project manager: Charles A. Wilson
Project scientist: C. M. Wignet
Contractor: General Electric, prime
Objectives: Observe the effects of weighlessness and gamma radiation on the growth of plants
and animals over a three-day period; recover payload.
program finished out the decade as part of the Space Applications Programs Office
of OSSA. William K. Widger was in charge of meteorological satellites until 1962;
Michael L. Garbacz assumed these duties in 1963. William C. Spreen was the
meteorology sounding rockets manager for most of the decade. Richard L. Haley
worked as advanced technology and projects manager or as Nimbus program
manager from 1964. Meteorology flight projects were assigned to the Goddard
Space Flight Center, where they were managed first by the aeronomy and
meteorology division, part of the Office of Space Science and Satellite Applications
(William G. Stroud, chief), and then from 1965 on by the projects directorate.
Since the data returned by the meterology satellites were of immediate use to
many parties, NASA worked with various agencies to ensure that the information
was disseminated through the National Weather Satellite Center to the proper
authorities and users and that the agency met the needs of the Department of
Defense, ESSA (formerly the Department of Commerce Weather Bureau), and
other groups. Interagency coordination committees further oversaw and reviewed
the government's requirements. Since weather forecasting was by necessity a global
undertaking, NASA also worked with private international meterological organiza-
tions and foreign government agencies in setting up workshops, establishing sound-
ing rocket launch facilities and recovery operations, and developing direct data
readout capabilities.
Tiros/TOS/ESSA
Thebasicconfiguration
oftheTirossatellitechangedlittleovertheyears.It was
an18-sided hatbox-shaped
cylinderwitha diameterof 1.07metersanda heightof
.48to .57meter,weighing120to 147kilograms.Tiroswascovered withsolarcells
that chargednickelcadmiumbatteries,whichpowered the criticaltwo-camera
television
system.
Onthefirsteightmissions,thecameras weremountedonthebot-
tom of the spacecraft,
but on Tiros 9 the two cameras were positioned on the
satellite's curved outer ring pointing in opposite directions; as the spacecraft turned
on its side it rolled through space like a slow-turning wheel on an imaginary track
(the so-called cartwheel mode). Early Tiros satellites were launched in east-west or-
bits, but later weather satellites were put into polar north-south paths, which pro-
vided more ideal photographic lighting conditions and better coverage. The televi-
sion system became more sophisticated, too, with the addition of an automatic pic-
ture transmission (APT) system on Tiros 8, which allowed for the transmission of
real-time cloud cover pictures to any APT ground receiver within audio range of the
satellite in a fashion similar to radio photograph transmissions. An advanced
vidicon camera system (AVCS) could take 6 or 12 pictures per orbit at 260-second
intervals, each image covering an area 3160 by 3160 kilometers, thereby obtaining
global coverage. Images were stored in an onboard tape recorder for transmission to
the National Environmental Satellite Center. In addition to the television cameras,
some Tiros spacecraft carried infrared-scanning and temperature-probing in-
struments.
The Weather Bureau (later the Environmental Science Services Administration)
participated in the Tiros project from its beginnings in the late 1950s, and this
Department of Commerce agency was responsible for disseminating data returned
by satellites to weather services and scientists. A formal agreement on an operational
satellite system was first reached by NASA and the Weather Bureau in March 1964.
Once Tiros became operational, the Bureau assumed its management, while NASA
was charged with spacecraft-launch vehicle development and procurement on a cost-
reimbursable basis. Tiros Operational System missions (ESSA 1 through 9) were all
successful, providing daily information on cloud cover, upper winds, pressure, and
precipitation on a global scale. This kind of data made possible daily weather
forecasts, storm and marine advisories, gale and hurricane warnings, cloud
analyses, and polar and Great Lakes navigational information.
At NASA Headquarters, Morris Tepper as chief of meteorology programs was
in charge of Tiros management, sharing the responsibilities with William K. Widget
in 1962. In mid-1963, Michael L. Garbacz was named flight project program
manager and led the Tiros-TOS team at Headquarters for the remainder of the
decade. Tiros, assigned to the Goddard Space Flight Center, was managed by
William G. Stroud (Tiros 1), Rudolf A. Stampfl (Tiros2), Robert M. Rados (Tiros3
through ESSA 1), and William W. Jones (ESSA 2 through 8). RCA served as prime
spacecraft contractor.
For further reading on the early history of Tiros, see John H. Ashby, "A
Preliminary History of the Evolution of the TIROS Weather Satellite Progam,"
NASA HHN-45, Aug. 1964; and GSFC and U.S. Weather Bureau, Final Report on
the Tiros I Meteorological Satellite System, NASA TR-R-131 (Washington, 1962).
350 NASA HISTORICAL DATA BOOK
o__
o_
_J
t---
z
1 I
_a: D I
'-rtu
,,_Z I
I
z_
O_u
I ¢/3
I
E
,t, t
t
_ z
_ _ o
.L
o_
I.-- _._ e¢-
T
z
_z
,< _ [
_0
Z ,-'
tu _
_-_
.__
_-_
SPACE SCIENCE AND APPLICATIONS 351
Table 3-185.
Chronology of Tiros/TOS/ESSA
Development and Operations
Date Event
1946 In a report for the Air Force, Douglas Aircraft (Project RAND) suggested
that weather forecasting could be one of the uses to which orbiting satellites
could be put.
1951
RAND contracted with the Radio Corporation of America (RCA) to study
the feasibility of using cameras on orbiting satellites.
1956 RCA, acting on its own, submitted proposals to the Department of Com-
merce Weather Bureau and the military for a television-equipped weather
reconnaissance satellite. The Army Ballistic Missile Agency (ABMA) con-
tracted with RCA for work on such a spacecraft (called Janus), to be launch-
ed with Jupiter C in the spring of 1958.
Feb. 1958 The Advanced Research Projects Agency (ARPA) assumed responsibility for
the television satellite project, with new emphasis being placed on its use as a
meteorology satellite.
March 1958 RCA redesigned Janus for use with the Juno II launch vehicle (Army Ord-
nance Missile Command); the satellite effort as redirected toward a
meteorology mission was called Tiros (Television Infra-Red Observation
Satcllite).
Summer-Winter 1958 Tiros was assigned a new more powerful launch vehicle-first Juno IV,
which was cancelled, and then Thor-Able. RCA's contract with ARPA called
for the manufacture of 10 satellites.
April 13, 1959 Project Tiros was transferred to NASA, with Goddard Space Flight Center
being assigned project management responsibility.
Sept. 26, 1969 The first flight model of Tiros was readied for systems integration.
March 7, 1960 Tiros A-I was shipped to the launch facility in Florida.
Oct. 10, 1960 An interagency meeting was held on the establishment of an operational
meteorology satellite system.
June 1961 NASA awarded a letter contract to RCA for four Tiros satellites.
April 15, 1962 The U.S. Weather Bureau began daily international transmissions of cloud
cover maps based on Tiros 4 photographs.
Sept. 18, 1962 Tiros 6 was launched successfully; for the first time two Tiros satellites were
in operation simultaneously.
Feb. 12, 1963 RCA was awarded a letter contract for _even Tiros satellites.
March 20, 1964 NASA and the Weather Bureau reached an agreement on an operational
satellite system, utilizing an improved Tiros.
July 15, 1964 RCA was awarded a contract for the Tiros Operational Satellite (TOS) pro-
gram.
Jan. 22, 1964 Tiros 9 was launched successfully (first of the cartwheel-mode spacecraft).
July 2, 1965 Tiros 10 was launched successfully (funded by the Weather Bureau).
352 NASA
HISTORICAL
DATABOOK
Table3-185.
Chronology
of Tiros/TOS/ESSA
Development
andOperations(Continued)
Date Event
Feb.
3,1966 ESSA 1 was launched successfully (first satellite of the TOS system, all of
which would be funded by the Environmental Science Services Administra-
tion, formerly the Weather Bureau).
Feb.
28,1966 ESSA 2 was launched successfully.
May11,1966 NASA announced that it would negotiate with RCA for a design study of an
improved Tiros.
Table 3-186.
Tiros 1 (Tiros-A-l) Characteristics
Table 3-187.
Tiros 2 (Tiros-B, -A-2) Characteristics
Table 3-188.
Tiros 3 (Tiros-C, -A-3) Characteristics
Table 3-189.
Tiros 4 (Tiros-D, -A-9) Characteristics
Table 3-190.
Tiros 5 (Tiros-E, -A-50) Characteristics
Table 3-191.
Tiros 6 (Tiros-F, -A-51) Characteristics
Table 3-192.
Tiros 7 (Tiros-G, -A-52) Characteristics
Table 3-193.
Table 3-194.
Table3-195.
Tiros 10 (OT-I) Characteristics
Table 3-196.
ESSA 1 (OT-3) Characteristics
Table 3-197.
ESSA 2 (OT-2) Characteristics
Table 3-198.
ESSA 3 (TOS-A) Characteristics
Table 3-199.
ESSA 4 (TOS-B)
Table3-200.
ESSA 5 (TOC-C) Characteristics
Table 3-201.
ESSA 6 (TOS-D) Characteristics
Table 3-202.
ESSA 7 (TOS-E) Characteristics
Table 3-203.
Nimbus
Shortly after the launch of the first Tiros weather satellite in the spring of 1959,
NASA officials informed Congress of their plans for a second-generation
meteorology payload that would orbit earth on a near-polar trajectory. This new
satellite would provide sophisticated global coverage for an extended lifetime. _3 The
spacecraft's stabilization system would be designed to give the flight team greater
control over the spacecraft's position and, thereby, over the readings and
photographs Nimbus would take. In addition to automatic picture transmission and
advanced vidicon camera systems that could produce very high-quality cloud cover
photographs, Nimbus spacecraft would be equipped with high-resolution and
medium-resolution radiometers for nighttime infrared readings, which would give
meteorologists information on heat retention on a global scale. Mapping water
vapor and stratospheric temperature patterns also would be made possible with data
returned by Nimbus.
Project Nimbus, approved by NASA Headquarters officials in the summer of
1959, fell behind schedule and overran its budget, which prompted the scrutiny of
Congress. A horizon scanner, which would allow the spacecraft to be operated in a
sun-synchronous orbit, and overall hardware weight gains were the spacecraft's ma-
jor problems. The butterfly-shaped Nimbus (360-410 kilograms) was developed and
fabricated by General Electric's Spacecraft Department under the direction of the
Goddard Space Flight Center. Rotating solar paddles, although they malfunctioned
on Nimbus 1, provided enough storable energy to power the spacecraft's instruments
for nighttime use. By using Nimbus cloud cover photographs, which covered almost
2 million kilometers per sequence, NASA and the Weather Bureau (and additionally
the Department of Defense) hoped to establish an operational weather observation
system. Because of early setbacks with the development of hardware and reported
plans for reducing the expected lifetime of the spacecraft, the Weather Bureau aban-
doned its plans and its funding support for a Nimbus Operational System (NOS) in
September 1963. NASA, however, continued Nimbus as a research and development
project aimed at developing an observatory system that would meet the future needs
of the nation's atmospheric and earth scientists.
The first Nimbus spacecraft was orbited in August 1964. The images received
from Nimbus 1 were remarkably clear and much better than Tiros images, but a
hardware problem forced the mission's premature termination on orbit 371, in the
second month of operations. By using the more powerful Thrust-augmented Thor-
Agena B, NASA was able to design a heavier payload for Nimbus 2. This second
spacecraft returned data for more than 32 months (1966-1969), including the
"satellite pictures" that became a popular feature on television news and weather
programs. Because a Thor engine malfunctioned on the long-tank Thorad-Agena D
during the launch of the third Nimbus, the entire vehicle was destroyed 121 seconds
after liftoff on May 18, 1968. The Nimbus B mission, repeated in 1969, was more
sophisticated than the first two, having two infrared spectrometers, an interrogation
and location system for determining the position of other man-made objects in
space, two radiometers, an ultraviolet radiation flux experiment, and an image
dissector camera system system capable of taking daytime pictures of the entire
earth with a resolution of 3.2 kilometers at picture center. The 570-kilogram satellite
was powered by a new radioisotope thermoelectric generator (SNAP-19) augmented
SPACE SCIENCE AND APPLICATIONS 361
*For more on the SNAP-19 RTG and sources for nuclear onboard electric power, see chapter 4.
Table 3-204.
Chronology of Nimbus Development and Operations
Date Event
April 1959 An advanced meteorology satellite research and development project was
described by NASA at FY 1960 authorization hearings before the House of
Representatives and at FY 1959 supplementary appropriations hearings.
Aug. 1959 A Nimbus research and development program was approved by NASA
Headquarters.
March 8, 1960 The Weather Bureau solicited proposals for an engineering design study of an
infrared spectrometer for a weather statellite.
June 1960 The Weather Bureau Panel on Observations over Space Data Regions issued
a report suggesting the need for a research and development satellite beyond
Tiros.
Fall 1960 NASA issued a request for proposals for Nimbus spacecraft design.
Dec. 1960 The Radio Corporation of America (RCA) was awarded a contract for
development and fabrication of an advanced vidicon camera system (AVCS)
for Nimbus.
Feb. 3, 1961 General Electric (GE) was selected as contractor for spacecraft fabrication
and subsystems integration for two Nimbus satellites. GE was chosen over
Temco, RCA, Grumman Aircraft Engineering Corp., Bendix, and Republic
Aviation Corp.
April 1961 The Panel on Operation Meteorological Satellites, an interagency group,
recommended expanding the Nimbus research and development project into
a Nimbus Operation System (NOS); this would be a joint undertaking
(NASA and the Weather Bureau).
Nov. 1961 A preliminary project development plan was prepared at NASA's Goddard
Space Flight Center.
Jan. 1962 The Nimbus spacecraft underwent a rigorous test program at GE. NASA and
the Weather Bureau signed an agreement providing for implementation of
NOS. The Weather Bureau approved the preliminary project development
plan.
Aug-Sept. 1962 The House of Representatives Science and Astronautics Applications Sub-
committee held hearings on the effects of postponing the first Nimbus
launch.
362 NASA HISTORICAL DATA BOOK
Table 3-204.
Chronology of Echo Development and Operations (Continued)
Date Event
Dec. 1962 The Weather Bureau reprogrammed funds from NOS to the Tiros Opera-
tional System (TOS).
Jan. 1963 AVCS was qualified as a subsystem. The Department of Defense (DoD)
questioned the adequacy of Nimbus for military requirements.
June 1963 The Weather Bureau provided NASA with DoD-Weather Bureau re-
quirements for Nimbus.
July 1963 The project development plan was revised to incorporate DoD-Weather
Bureau recommendations.
Sept. 1963 DoD and the Weather Bureau advised the Bureau of the Budget that NASA's
research and development program for meteorology satellites should be
placed under their control; the Weather Bureau advised NASA that it was
withdrawing from NOS as of October 4.
Sept. 18, 1963 GE was awarded a contract for developing operating procedures for the Nim-
bus control center.
Oct. 1963 NASA advised the Weather Bureau of its intentions of continuing a Nimbus
research and development project; a revised project development plan was
approved by NASA Headquarters on October 10.
Aug. 11, 1964 A faulty relay box in the Thor-Agena B launch vehicle postponed the first
Nimbus launch.
Aug. 28, 1964 Nimbus 1 was launched successfully, but the spacecraft ceased operating on
September 23, 1964, because of malfunctions.
Jan. 29, 1965 A General Acccounting Office report accused NASA of spending $1.2
million unnecessarily on Nimbus by failing to react to new spacecraft weight
design goals.
June 1965 The project development plan was revised to reflect the cancellation of NOS
and operation of a second Nimbus mission.
Aug. 13, 1966 A NASA review board and the House of Representatives Science and
Astronautics Committee NASA Oversight Subcommittee began inquiries
into OGO, OAO, and Nimbus (Nimbus 1) failures.
May 18, 1968 An attempted Nimbus launch using a long-tank Thorad-Agena D failed
because the Thor malfunctioned; the entire vehicle was destroyed 121 seconds
after liftoff.
Dec. 1968 Hittan Associates, Inc., was chosen to evaluate the SNAP-19 nuclear power
system for the Nimbus B spacecraft.
SPACE
SCIENCE
ANDAPPLICATIONS 363
Table3-205.
Nimbus 1 (Nimbus-A) Characteristics
Table 3-206.
Nimbus 2 (Nimbus-C) Characteristics
DESCRIPTION-COMMUNICATIONS PROGRAM
SPECIAL ASSISTANT
TO THE PRESIDENT
PRESIDENT
FOR
TELECOMMUNICATIONS
DIRECTOR OF
TELECOMMUNICATIONS
MANAGEMENT
EXECUTIVE SECRETARY
[ E.ASST DIRECTOR, I AGENT OF
NCS DEFENSE
OFFICE OF I
ASSISTANT
NATIONAL
E2GE___C_:LAN
COMMUNICATIONS
2,N_J
FOR [
SYSTEM
MANAGER, DIRECTOR,
NATIONAL DEFENSE
COMMUNICATIONS COMMUNICATIONS
SYSTEM AGENCY
I i I
ARMY NAVY AIR FORCE
Figure 3-5. The National Communications Systems encompasses total Federal assets.
Table 3-207.
Comparison, Relay, Telstar, Syncom
Table 3-208.
Organizational Interactions
Communication & Navigation Satellite Programs
ITU
NASA Flight Programs NAV CSC PARTICI-
ECHO RELAY SYNCOM ATS PROGRAM PROGRAM PATION
DOD X X X X X
STATE X X
TREASURY X
INTERIOR X
COMMERCE X
FAA X X X
USIA X X X
FOC X X X
BROADCASTERS X X X
COM SAT CORP X X
FOREIGN PARTICIPANTS X X X X
SCIENTIFIC COMMUNITY X X X X
NAT'L SPACE COUNCIL X X X X X X X
DIR. TELECOMM'S.
MGMT. X X X X X X X
From NASA Hq., "Program Review Document, Communication & Navigation Programs," Sept. 22,
1964. p. 21.
Echo
Echo was NASA's first communications satellite flight project. The balloon-like
passive reflector was initially sponsored by the National Advisory Committee for
Aeronautics (NACA) as an International Geophysical Year (IGY) air density experi-
ment. In 1956 at NACA's Langley research facility, William J. O'Sullivan, after
assessing the value of prospective IGY experiments designed to measure the density
of earth's atmosphere, proposed that a low-density inflatable structure that could be
tracked optically would serve as a good measure of aerodynamic drag. Twice at-
tempts were made to launch O'Sullivan's spheres along with IGY payloads, but
launch vehicle malfunctions with Juno I and Vanguard thwarted the Langley team's
efforts.*
If a satellite of the type O'Sullivan envisioned were equipped with small radio
beacons, it could be followed by radar and optical means, significantly increasing
*An attempt on August 14, 1959, to launch a Beacon inflatable satellite also failed because Juno ll's
fuel supply was depleted prematurely. The air density experiment was finally realized as Explorer 9
(February 16, 1961), Explorer 19 (December 19, 1963), and Explorer39 (August 8, 1968).
SPACE
SCIENCE
ANDAPPLICATIONS 369
the period during each orbit it could be tracked. And if the satellite carried a reflec-
tor or acted as a reflector as a whole, sending back radar signals to a specific point, it
could be tracked day or night. According to O'Sullivan, "it was a simple next step"
to consider using the satellite for communications purposes. _7 As early as April
1958, NACA Director Hugh L. Dryden had told Congress that such a passive
satellite could be orbited and inflated in space. To be sure, Langley's air density
balloon would have to grow considerably in size to provide the maximum surface
from which to bounce signals, and the surface would have to possess increased
reflectivity characteristics. John R. Pierce of Bell Telephone Laboratories had been
contemplating such a communications experiment since 1955, and by 1959 Bell and
the new civilian space agency, which had inherited NACA's balloon project, were
working together on a passive communications satellite project called Echo.
Technicians at Langley (now a part of NASA) had three major requirements in
designing a balloon satellite that measured 30.48 meters in diameter and would in-
flate in orbit into a perfectly smooth surface: a suitable material for the sphere, an
inflation system, and a canister in which to launch the folded-up balloon. And since
there was no way to run ground tests that simulated the space environment on such a
large sphere, NASA would have to relay on suborbital flight tests. The G. T.
Schjeldahl Company fitted and cemented together 82 _eparate fiat gores of
aluminized Mylar film (.5 millimeter thick) supplied by E. I. Dupont to form the
Echo sphere. Benzoic acid was selected as the sublimating agent (i.e., going from a
solid to a gaseous state without liquifying) that would be used to inflate the struc-
ture. Kaiser-Fleetwing manufactured a spherical metal canister impregnated with
plastic to contain the deflated satellite. The Langley crew assembled the first Echo
test model by the fall of 1959. In October, it was launched to an altitude of 400
kilometers (Project Shotput), where the sphere ruptured. On the fourth try (April
1960), the balloon inflated successfully at 375 kilometers. After a first launch at-
tempt failed, Echo 1 was placed in orbit and inflated on August 12, 1960. For the
next four and a half months, it was utilized for experiments by Bell Telephone
Laboratories in New Jersey and the Jet Propulsion Laboratory in California. Even
after the balloon's skirt had been damaged repeatedly by micrometeoroids and its or-
bit affected by solar wind, Echo 1 was used to reflect a variety of communications
signals to and from ground stations around the globe.* As it was visible from the
ground, it also served as a popular symbol of the peaceful and practical uses of space
research.
The second-generation Echo was larger (41.15-meter diameter), heavier, and
more durable. Fabricated from 106 gores of Mylar three layers thick bonded be-
tween two sheets of soft aluminum foil, the improved Echo maintained its rigidity
for a longer time. Pyrazol was used as the inflating medium, and a new canister was
made by the Grumman Aircraft Company from magnesium forgings. First test-
inflated in a dirigible hanger, the new Echo was tested several times under suborbital
conditions (Project Big Shot). Echo 2 was put into orbit on January 25, 1964, and
used successfully for more than a year by a number of groups for communications
*The Echo 1 configuration was also used for PAGEOS 1, launched on June 23, 1966. It served as a
point source of light for a tracking network; the resulting data were used for mapping and other geodetic
purposes (table 3-137).
370 NASA
HISTORICAL
DATA BOOK
*NASA had let several feasibility study contracts to determine the best shape, structure, and
materials for a future passive communications satellite. The agency briefly contemplated a three-balloon
experiment dubbed Rebound.
Table 3-209.
Chronology of Echo Development and Operations
Date Event
April 15, 1958 Launched by a Nike-Cajun, a 3.66-meter inflatable sphere was successfully
erected.
Oct. 22, 1958 An attempt to launch a 3.66-meter inflatable sphere (called Explorer 6, but
not the same spacecraft that was launched in August 1959) failed when the re-
quired orbit was not achieved.
April 13, 1959 Because of Vanguard launch vehicle malfunctions, an attempt to place a
.76-meter inflatable sphere into orbit failed.
April-Sept. 1959 Personnel at NASA's Langley Research Center constructed a 30.48-meter in-
flatable sphere satellite.
Oct. 28, 1959 NASA launched a 30.48-meter inflatable sphere to an altitude of 400
kilometers with a Sergeant-Delta; the sphcrc ruptured (Project Shotput).
Jan. 16, 1960 NASA launched a 30.48-meter inflatable sphere to an altitude of 400
kilometers with a Sergeant-Delta; the sphere ruptured (Project Shotput).
Feb. 27, 1960 NASA launched a 30.48-meter inflatable sphere to an altitude of 400
kilometers; radio transmissions were reflected via the sphere from Holmdel,
New Jersey, to Round Hill, Massachusetts, before it ruptured (Project Shot-
put).
SPACE
SCIENCE
ANDAPPLICATIONS 371
Table3-209.
Chronology
of EchoDevelopment
andOperations
(Continued)
Date Event
April1,1960 A 30.48-meter inflatable sphere was launched and inflated successfully by
NASA at 380 kilometers (Project Shotput).
May13,1960 An attempt to launch an Echo satellite failed when the Thor-Delta vehicle
malfunctioned.
July15,1960 Hughes Aircraft Co. was awarded a seven-month contract for developing
techniques to rigidize structures so that they would maintain their reflectivity
in sunlight or shadow.
Aug.12, 1960 Echo 1 was launched successfully; experiments were performed on August
18.
Feb. 21, 1961 NASA awarded a contract to the G. T. Schjeldahl Co. for nine inflatable
spheres for Project Echo.
May 18, 1961 The first test inflation of an improved Echo balloon was conducted in a
dirigible hanger.
Jan. 15, 1962 A suborbital test of a modified Echo inflation system was launched by a
Thor-Agena from the Western Test Range (Project Big Shot).
Sept. 28, 1962 Plans were announced for launching two Echo-type helium balloons to deter-
mine skin smoothness characteristics for an advanced Echo.
Oct. 20, 1962 A 30.48-meter Echo /-type balloon was launched; it ruptured at 35
kilometers.
Dec. 5, 1962 The U.S. and the USSR agreed to cooperate in the coming year's experiments
with Echo.
Feb. 25, 1963 NASA announced that in light of the formation of the Communications
Satellite Corporation (COMSAT) and the cancellation of the Department of
Defense Advent active communications satellite project, the agency would
focus its efforts on synchronous-orbit active satellites. NASA cancelled ad-
vanced passive and intermediate-altitude communications satellite projects.
May 13, 1963 Langley issued a request for proposals for a feasibility study for an inflatable
lenticular passive communications satellite.
Aug. 12, 1963 Schjeldahl was selected to build three second-generation Echo satellites, a
project which was cancelled.
Table 3-210.
Echo ! (Echo A-11) Characteristics
Table 3-211.
Echo 2 (Echo C) Characteristics
Telstar
Table 3-212.
Chronology of Telstar Development and Operations
Date Event
1959 An ad hoc group was formed at Bell Telephone Laboratories to study the
feasibility of developing an active communications satellite.
Aug. 24, 1959 A Bell company memorandum outlined plans for an active repeater com-
munications satellite experiment.
1960 Bell experimented with and tested many of the components for the active
satellite that would become Telstar.
Oct. 21, 1960 The Federal Communication_ Commission (FCC) was asked to approve
plans for an American Telephone & Telegraph (AT&T) satellite experiment,
which would use the Bell satellite.
Jan. 19, 1961 FCC authorized the AT&T experiment and allocated it frequencies for one
year.
July 27, 1961 NASA announced that it would launch and test two AT&T active com-
munications satellites on a reimbursable basis.
The Senate Commerce Committee heard testimony from NASA officials and
Aug. 23-24, 1961
the assistant attorney general on Telstar costs.
Oct. 18, 1961 The AT&T satellite was officially designated Telstar.
Dec. 1961 The West German Post Office announced that it would construct a ground
station near Munich that could be used with Telstar and NASA's Relay com-
munications satellite.
June 5, 1962 NASA announced plans for a cooperative program for testing Relay and
Telstar.
July 10, 1962 Telstar 1 was launched successfully; demonstrations of television transmis-
sions began shortly after launch.
Dec. 30, 1962 AT&T announced plans to launch a second satellite in the spring of 1963.
Table3-213.
Telstar 1 Characteristics
Table 3-214.
Telstar 2 Characteristics
Relay
and Navigations Programs. At Goddard Space Flight Center, Joseph Berliner and
Wendell S. Sunderlin were project managers for Relay 1 and 2, respectively.
For further reading, see GSFC, Final Report on the Relay I Program, NASA
SP-76 (Washington, 1965); and GSFC, Relay Program Final Report, NASA SP-151
(Washington, 1968).
Table 3-215.
Chronology of Relay Development and Operations
Date Event
Nov. 21, 1960 The Unmanned Spacecraft Panel of the Aeronautics and Astronautics Coor-
dinating Board, an interagency body, issued a "Statement on NASA Program
Philosophy on Communications Satellites," in which NASA expressed its in-
tentions to develop low-altitude active repeater satellites.
Late Nov. 1960 NASA awarded a contract to Space Technology Laboratories for a
spacecraft design study of an active communications satellite system that
would lead to a commercial communications satellite system.
Jan. 13, 1961 Preliminary specifications for a low-altitude communications satellite (Relay)
were drawn up at the Goddard Space Flight Center.
Jan. 25, 1961 Industry was briefed on the requirements for Project Relay, and a request for
quotations was issued. The project was officially named Relay.
Feb. 1961 NASA signed agreements with the U.K. and France to establish government
programs for testing communications satellites in 1962 and 1963 (Relay and
Rebound).
May 18, 1961 NASA awarded a contract to the Radio Corporation of America (RCA),
Astro-Electronics Division, for the development of three Relay spacecraft.
Dec. 1961 The West German Post Office announced that it would construct a ground
station near Munich to be used with AT&T's Telstar and Relay.
June 5, 1962 NASA announced a cooperative program for testing Relay and Telstar.
Feb. 25, 1964 Goddard recommended not launching a third Relay (the backup satellite);
since Relay I and 2 and Project Syncom were meeting their schedules and ob-
jectives there was no need for a third Relay mission.
378 NASA HISTORICAL DATA BOOK
Table 3-216.
Relay 1 (Relay A-15) Characteristics
Syncom
Table3-217.
Relay 2 (Relay-B) Characteristics
own payload from a Pacific island near the equator. By the spring of 1961, it was
becoming clear to the Army that Advent was still several years away from being
ready, partly due to delays with the Centaur stage of the launch vehicle, and already
over budget. Meanwhile, NASA's Leonard Jaffe had become convinced that Syn-
com was the logical next step for the agency's communications satellite program.
With President John F. Kennedy's mandate to accelerate the communications
satellite program and DoD support of a NASA synchronous-orbit project, the path
was cleared for Hughes. By August 1961, NASA had named Hughes its contractor
for Project Syncom.
At an altitude of about 35 800 kilometers above the equator, the Syncom
satellite could orbit at the same relative speed of earth, appearing to be always in one
location. In this position, a single satellite could give communications coverage to
appxoximately one-third of the globe. This altitude also would ensure that the
satellite's solar cells received the sun's rays continuously. Precise spacecraft attitude
control, a necessity, was achieved by spin stabilization and two attitude control jets.
Another activity critical to Syncom was the development of a lightweight traveling
wave tube. J. T. Mendel at Hughes was charged with designing this component,
which had to weigh less than half a kilogram. DoD, taking advantage of those
systems that were already being readied for Advent, offered to provide and pay for
the entire ground station complex, the stations, crews, and the control center
380 NASA HISTORICAL DATA BOOK
I I I I
z '
0 c01-o
Z -
_o
I--
Z tr _ i.=-
_ I'--A tr
_ -
>..m> .
tr t_ _ t._
N
I--
e_
e_
0 I
I I L I
0 0 0 0 0
tO O_ O_
382 NASA HISTORICAL DATA BOOK
Table 3-218.
Date Event
Late 1958 A task group led by Harold A. Rosen was established at Hughes Aircraft
Company to investigate communications satellite experiments beyond the
company's work on advanced radar.
1959 Rosen and Donald Williams at Hughes studied the problems associated with
a synchronous-orbit active communications satellite.
March 1, 1960 Hughes authorized its engineers to proceed with the development of Syncom
without NASA's support.
April-May 1960 Hughes made Syncom presentations to the Department of Defense (DoD).
July 11, 1960 Hughes made Syncom presentations to the President's Science Advisory
Committee.
Aug. 16, 1960 Hughes made another presentation to NASA, and Administrator T. Keith
Glennan suggested that Hughes apply its activities to a low-altitude satellite
project.
Oct.-Dec. 1960 Hughes made Syncom presentations to GT&E, Bell Telephone Laboratories,
IT&T, Stanford Research Institute, Aerospace Corporation, the U.S. Air
Force, and to British military and civilian delegations.
Spring 1961 Leonard Jaffe at NASA Headquarters urged agency managers to adopt a
synchronous-orbit satellite.
June 23, 1961 DoD announced its support of a NASA synchronous-orbit communications
satellite project.
Aug. 10, 1961 Goddard Space Flight Center personnel prepared a preliminary project
development plan in coordination with the U.S. Army Advent Management
Agency for a Syncom project.
Aug. 21, 1961 Hughes was named NASA contractor for Syncom.
March 1, 1962 In Senate hearings, Hughes advocated that any future public communica-
tions satellite corporation should adopt Syncom as its primary system.
Nov. 9, 1962 Hughes reported that the final assembly of the first Syncom spacecraft had
been completed.
Jan. 1963 NASA announced that the first launch of Syncom would take place the next
month.
Feb. 14, 1963 Syncom I was launched successfully, but contact with the spacecraft was lost
when the apogee motor was fired to place the satellite in the required orbit.
Feb. 25, 1963 NASA announced that in light of the formation of the Communications
Satellite Corporation (COMSAT) and DoD's cancellation of Advent, the
agency would focus its efforts on synchronous active communications
satellites and cancel passive and intermediate-altitude projects.
Dec. 31, 1964 NASA began the transfer of the Syncom system to DoD for use in Asia and
the Indian Ocean; the transfer was completed by April l, 1965.
SPACE
SCIENCE
ANDAPPLICATIONS 383
Table3-219.
Syncom 1 (Syncom-A) Characteristics
Table 3-220.
Syncom 2 (Syncom-B) Characteristics
Table 3-221.
Syncom 3 (Syncom-C) Characteristics
INTELSAT
91
SIGNATORY
OWNERS _= ur _._r,,,_]l_
IIIIIII1 "
CONTRACTORS
CINTRIBUTIO _ INTELSAT
us .s i ,
EXECUTIVE MANAGEMENT
ORGAN SERVICES
(SECRETARY CONTRACTOR
GENERAL) (COMSAT)
m
SPACE SCIENCE AND APPLICATIONS 387
INTELSAT IVA
INTELSAT I
IMPROVED LONG-TANK
ATLAS/CENTAU RATLAS/C ENTAUR
LAUNCH VEHICLE THOR-DELTA THOR-DELTA THOR-DELTA
TRANSPONDERS 2 1 2 12 20
From B.L Edelson, H. I4I. Wood, and C.J. Reber, "Cost Effectiveness in Global Satellite Communications,"
Table 3-222.
Chronology of INTELSAT Development and Operations
Date Event
Aug. 31, 1962 The Communications Satellite Corporation (COMSAT) was authorized by
Congress.
Dec. 22, 1963 COMSAT issued a request for proposals for an engineering design study for
a commercial communications satellite system.
Dec. 1963 Hughes Aircraft Co. submitted a proposal to COMSAT for the development
of an initial communications satellite for commercial use (synchronous
orbit).
March 1964 COMSAT awarded Hughes a contract for the development and fabrication
of the proposed Early Bird experimental operational communications
satellite.
July 1964 Satellite design studies were begun by the Radio Corporation of America
(RCA) and Bell Telephone Laboratories (random medium-altitude satellites),
TRW and ITT (phased medium-altitude satellites), and Hughes
(synchronous-orbit satellites) for COMSAT; reports were due on March 1,
1965.
Nov. 1964 Six companies submitted proposals for COMSAT ground stations.
Dec. 1964 NASA and COMSAT signed a formal agreement outlining their cooperation
on a satellite project, with an initial launch planned for March 1965.
Sept. 30, 1965 COMSAT asked the Federal Communications Commission for authority to
fund four new satellites to provide private communications services and to
support NASA's Project Apollo.
Dec. 16, 1965 COMSAT and TRW opened negotiations for a contract that called for the
development and fabrication of a second-generation satellite to be used in a
global communications satellite system.
Dec. 29, 1965 COMSAT issued a request for design study proposals for a multipurpose
communications-navigation satellite.
July 1966 NASA and COMSAT reached an agreement on the launching of two more
INTELSAT satellites.
Oct. 22, 1966 INTELSA T II-A was launched, but it failed to achieve synchronous orbit,
limiting the spacecraft's usefulness.
Table 3-222.
Chronology of INTELSAT Development and Operations (Continued)
Date Event
Feb. 1968 COMSAT opened bids for the design of INTELSATS 1II, IV, and V.
Sept. 18, 1968 The launch of INTELSATIIlF-1 was unsuccessful because the launch vehi-
cle failed; the spacecraft and launch vehicle were destroyed.
Oct. 4, 1968 A contract between COMSAT and Hughes for the INTELSAT IV series was
approved by INTELSAT.
Table 3-223.
INTELSA T I Characteristics
Table 3-224.
INTELSA T II-A Characteristics
Table 3-225.
INTELSA T II-B Characteristics
Table 3-226.
INTELSA T II-C Characteristics
Table 3-227.
INTELSA T II-D Characteristics
Table 3-228.
INTELSA TIII F-I Characteristics
Table 3-229.
INTELSA T III F-2 Characteristics
DESCRIPTION-APPLICATIONS TECHNOLOGY
SATELLITE (ATS) PROGRAM
Shortly after the Syncom project was approved by NASA, designers at Hughes
Aircraft Company began investigating ways in which the basic configuration might
be exploited in the future. Officials at Goddard Space Flight Center were en-
thusiastic about expanding the capabilities of this yet-to-be-tried synchronous-orbit
satellite to include a multiple communications access capability between fixed points
and a phased-array antenna. NASA Headquarters approved a feasibility study for
such a spacecraft in 1962. Early the following year, Hughes personnel were anxious
for the agency to sanction an Advanced Syncom flight project, but their proposals
were poorly timed. Heated debates were raging in Congress during FY 1964 budget
appropriations hearings over NASA's relations with the newly organized Com-
munications Satellite Corporation (COMSAT), which had been charged by Con-
gress to establish a commercial operational communications network. Some
members of Congress believed that the privately-run COMSAT, which seemingly
had a monopoly in the communications satellite field, would be the sole benefactor
of NASA's advanced research and development communications projects; as they
saw it the government space agency would be subsidizing a private corporation.
NASA countered that its mandate was to further the state of the art; the agency had
no intentions of getting into the "communications satellite business." NASA's
authorization for Advanced Syncom was $7 million less than the request, and
managers at Headquarters decided to avoid future open criticism by dropping their
plans for an advanced communications flight project.
Advanced Syncom, however, was a sound design, and specialists at Hughes,
Goddard, and NASA Headquarters sought ways to integrate their ideas for com-
munications, meteorology, and navigation-traffic control satellites into a single
package that could be carried on one spacecraft. In February 1964, NASA officials
signed off on a project approval document for an Advanced Technological Satellite,
which was renamed Applications Technology Satellite (ATS) that spring. The
Department of Defense (DOD) also played a part in influencing NASA to redirect its
plans from a synchronous-orbit communications satellite to a multipurpose project.
Military officials had become convinced that Syncom, while highly useful, was also
very vulnerable; feasibly it could be manuevered, interfered with, or put out of
commission by an enemy ground station. For more secure communications, the
military planned some 60 randomly spaced medium-altitude satellites. DoD
specialists also were interested in an experimental gravity-gradient stabilized
spacecraft, one plane of which would always face earth; and the military suggested
that NASA explore this area of spacecraft design.*
In May 1964, Hughes was instructed to build five Applications Technology
Satellites, which would accomodate a variety of communications, meteorology, and
*A gravity-gradient stabilized spacecraft required long booms attached to a main body that would
respond to earth's gravitational pull. Those booms nearest earth would tend to remain pointed at earth
since the gravity exerted on them would be slightly greater than that exerted on the booms most distant
from earth. This would keep the spacecraft fixed with one plane always facing earth, another always fac-
ing away.
SPACE
SCIENCE
ANDAPPLICATIONS 393
Table 3-230.
Applications Technology Satellite Experiments
SPACECRAFT
EXPERIMENT A B C D E
Microwave Communications X X X X X
VHF Communications X X
WEFAX (see also meteorology experiments)
Ground to Aircraft
Propagational Effect of VHF
Navigational Systems
STADAN Calibration
Millimeter Wave Communications
Meteorological Experiments
Spin Scan Cloud Cover Experiment (SSCCE)
Black and White X
Color
Advanced Videcon Camera System (AVCS) X
WEFAX X
Image Dissector Camera System (1DCS)
OMEGA Position Location Experiment (OPLE)
Image Orthican Day/Night Camera X
Gravity Gradient X X X
Antenna
Phased Array X
Mechanically Despun
Nutation Sensor X
Subliming Solid Jet X X X
Hydrazine Rocket X X
Resistojet X X X
Ion Engine X X
Reflectometer
Self-Contained Navigation System
Environmental Measurements Experiments
Omnidirectional Particle Telescope (UCSD) X X
Omnidirectional Particle Telescope (Aerospace) X
Particle Detector (BTL) X
Proton/Electron Spectrometer (U. of Minn.) X
Solar Cell Damage (GSFC-Dr. Waddel) X X
Thermal Coatings (GSFC-J. Triolo) X X
Ion Detector (Rice Univ.) X
Magnetometer (UCLA) X
VLF Detector (BTL) X
Cosmic Radio Noise (GSFC-Dr. Stone) X X
Electric Field Measuremet (GSFC-Dr. Aggson) X X
Trapped Radiation Detector (UCB) X
Proton/Electron Detector (Lockheed) X
Spacecraft Charge Measurement (GSFC-Dr. Aggson) X X
From Gilbert D. Bullock, comp. and ed., "ATS Program Summary," rev. April 1968, p. 12.
Table 3-231.
Date Event
Oct.-Nov. 1961 Hughes Aircraft Company personnel began investigating ways to improve
the existing configuration of Syncom.
Feb. 1962 Hughes proposed an advanced Syncom to NASA Headquarters and Goddard
Space Flight Center personnel.
June 1962 A project development plan for an advanced stationary communications
satellite was prepared at Goddard.
June 18, 1962 A project approval document was issued for the study of an advanced
synchronous-orbit satellite. Hughes was selected to prepare a feasibility study
for an advanced Syncom.
Feb. 14, 1963 Syncom 1 went silent shortly after its apogee motor was fired.
March 8, 1963 Hughes presented plans'to NASA Headquarters for an advanced Syncom
flight program, with the first launch scheduled for the second half of 1964.
Spring 1963 Congressional debates took place over the relationship between NASA's
communications research and development program and the Communica-
tions Satellite Corp. (COMSAT).
April 1, 1963 Leonard Jaffe testified at congressional hearings that NASA was interested
in using an advanced synchronous-orbit satellite to accomplish communica-
tions and meteorology tasks.
May 1963 Hughes's design study contract for advanced Syncom was extended through
August; in June it was extended again until October.
June 27, 1963 Hughes proposed an intermediate Syncom.
July 26, 1963 Syncom 2 was launched successfully, and the feasibility of the basic
spacecraft demonstrated.
Sept. 1963 Goddard supported an advanced Syncom in recommendations to Head-
quarters.
Fall 1963 NASA terminated its plans for an advanced Syncom flight project, and per-
sonnel at Goddard, Headquarters, and Hughes studied ways to reorient the
advanced Syncom design to include more areas of research.
Nov. 1, 1963 A four-month feasibility study for integrating requirements for several areas
of research into one flight program was started at Hughes; advanced Syncom
came to be called Advanced Technological Satellite.
Feb. 13, 1964 A project approval document for Advanced Technological Satellite was
issued.
May 1964 The program was unofficially renamed Applications Technology Satellite
(ATS).
May 13, 1964 A NASA letter contract was issued to Hughes for development and fabrica-
tion of the ATS spacecraft.
May 14, 1964 General Electric was selected to design and build a gravity-gradient stabiliza-
tion system for ATS.
June 26, 1964 NASA issued a request for proposals from scientists for experiments to be
carried on five ATS spacecraft (a second request to industry was issued in
September).
Aug. 19, 1964 Syncom 3 was launched successfully.
Aug. 1964 Goddard personnel submitted a proposed procurement plan for an advanced
ATS to NASA Headquarters.
Oct. 4, 1964 The name Applications Technology Satellite was officially approved.
Aug. 11, 1965 Control Data Corp., Philco, Bell Aerospace, and Electro-Optical Systems,
Inc., were selected by NASA to prepare feasibility studies for ATS experi-
ment hardware.
Aug. 25, 1965 Sylvania was chosen to build a transportable ground system for ATS.
Sept. 1965 NASA issued a request for proposals for a second-generation ATS.
SPACE
SCIENCE
AND APPLICATIONS 397
Table 3-231.
Date Event
March 1, 1966 GE, Fairchild-Hiller, and Lockheed were selected to receive six-month
feasibility design study contracts for a second-generation ATS. Studies were
to be completed in December.
Dec. 6, 1966 A TS 1 was launched successfully.
April 5, 1967 The launch of A TS 2 was unsuccessful because the second stage of the launch
vehicle malfunctioned; the satellite was not put into the correct orbit.
Nov. 5, 1967 A TS 3 was launched successfully.
May 22, 1968 NASA selected Fairchild-Hiller, GE, and Lockheed for competitive contract
negotiations to develop spacecraft designs for ATS-F and ATS-G.
Aug. 10, 1968 The launch of A TS 4 was unsuccessful because the Centaur stage of the
launch vehicle failed; the satellite was not injected into the required orbit.
Aug. 12, 1968 An A TS 4 failure review board was established by NASA's Office of Space
Science and Applications.
Summer 1968 The National Academy of Sciences-National Research Council conducted a
space applications summer study.
Table 3-232.
A TS 1 (ATS-B) Characteristics
Table 3-233.
A TS 2 (ATS-A) Characteristics
Table 3-234.
A TS 3 (ATS-C) Characteristics
......................
Table 3-235.
A TS 4 (ATS-D) Characteristics
DESCRIPTION-GEODETIC INVESTIGATIONS
Satellites are also a useful research tool for geodesists. By coordinating tracking
data collected on a global scale, specialists can determine the exact positions of par-
ticular points on earth's surface, the exact shape of the planet, and the locations
where the gravitational field is anomalous. This information gives cartographers the
many reference points required to prepare a 1:25 000 scale map of the planet. Such
precise measurements also are necessary to calculate launch trajectories. In addition,
geologists can profit from information on deviations from the normal pull of gravi-
ty; such anomolies hint at what kind of materials lay beneath the earth's crust.
In 1965, NASA established a National Geodetic Satellite Program to coordinate
the activities of those government agencies (namely NASA, the Department of
Defense, and the Department of Commerce) that required geodetic data and the
several groups working in the field (the National Geodetic Survey, Ohio State
University, the Smithsonian Astrophysical Observatory, and the European Satellite
Triangulation Network among others). NASA's Goddard Space Flight Center with
its tracking and data acquisition facilities was assigned a major responsibility for the
agency's part in the national program. Jerome D. Rosenberg, who directed the na-
tional effort, was also geodetic satellites program manager at NASA Headquarters.
Vanguard 1 provided the first geodetic data for investigators in the U.S., when
analysis of its orbit indicated that earth's equatorial bulge was not quite as large as
previously calculated and that the southern hemisphere was flatter than the northern
half. This gives earth its pear shape. Although tracking data from all orbital
400 NASA HISTORICAL DATA BOOK
spaceflights are applicable to the geodesist's mission, NASA devoted three flight
projects exclusively to geodesy investigations-two Explorers and a passive balloon
project. Explorer 29 and Explorer 36 (also called GEOS 1 and GEOS 2) were
equipped with flashing light beacons and radio equipment by which to track them
(see tables 3-94, 3-101). PAGEOS 1, passive like the Echo balloons, was tracked op-
tically by stations around the world (table 3-137). The Explorer satellites helped
geodesists define earth's gravity and pinpoint the magnitude and location of signifi-
cant irregularities, improve tracking capabilities, and more accurately determine
datum points. By simultaneously photographing the light source provided by the
passive PAGEOS 1 with two or more widely separated ground-based cameras,
specialists determined the relative spatial coordinates of each camera position. It
took five years to collect enough data to provide a purely geometric determination
of the planet's shape. In addition to geometric and gravimetric applications, infor-
mation gathered by geodetic satellites was also useful to scientists working in the
fields of earth geophysics and geology, meteorology and aeronomy, space dynamics
and astronomy, and oceanography. For example, such data were helpful in deter-
mining continental drift, ice motion in Antarctica and Greenland, and snow and ice
accumulation. Additionally, the findings were used to select the best sites for deep-
space-probe tracking stations.
For a detailed report on the subject, see S. W. Henriksen, ed., National
Geodetic Satellite Program: A Report Compiled and Edited for NASA by the
American Geophysical Union, 2 pts., NASA SP-365 (Washington, 1977).
CHAPTER FOUR
ADVANCED RESEARCH
AND TECHNOLOGY
CHAPTER FOUR
ADVANCED RESEARCH
AND TECHNOLOGY
More than any other directorate, NASA's advanced research and technology
arm was tailored after a pattern established by the National Advisory Committee for
Aeronautics (NACA). Although NASA's research agenda necessarily emphasized
those problems posed by spaceflight, the agency also was charged with continuing
the role NACA had played for 43 years in the field of aeronautics. Congress had ap-
proved NACA's formation in 1915 to address a variety of problems that the airplane
and its new technology had brought to the military, the fledgling aviation industry,
and the increasing number of civilian users of aircraft. From an advisory body that
was limited to proffering opinions on such policy matters as licensing agreements
and civil aviation legislation and to coordinating the research efforts and re-
quirements of others, NACA had evolved into a national research organization with
its own aeronautical laboratory by 1920. Sharing the fundamental work of "un-
covering the basic, underlying, scientific principles applicable to all kinds of avia-
tion" with the National Bureau of Standards, subcommittees within NACA claimed
responsibility for various research topics-powerplants for aircraft, aerodynamics,
materials and structures, aircraft construction, and operating problems-with
aerodynamics and wind tunnel research being NACA's major field of interest for
several decades. 1 In the mid-1940s, the Pilotless Aircraft Research Division at
NACA's Langley Memorial Aeronautical Laboratory expanded its duties to include
the study of guided missiles and rockets.* By the time its functions were assumed by
the National Aeronautics and Space Administration in 1958, NACA was conducting
a wide variety of research at four centers across the country.t
Certainly harder to define and usually less visible than the activities of NASA's
manned program or of the space science and applications program, the basic and ap-
plied research conducted under the auspices of the agency's Office of Advanced
Research and Technology (OART) was equally important. Without it, NASA
specialists could not have provided in a timely fashion the advanced electronic
equipment, engines, attitude control devices, and related items for the sophisticated
missions NASA conducted during its first decade. Basic research (that which had no
application to any specific mission and ranged from very fundamental studies into
*Through its Research and Development Board, the military assumed major responsibility for the
new field of missiles and rockets and for nuclear propulsion and supersonic flight.
tFor more information on NACA, seeAlex Roland, Model Research: A History of the NationalAd-
visory Committee for Aeronautics, 1915-1958, NASA SP-4103 (Washington, 1985).
403
404 NASA
HISTORICAL
DATABOOK
*Before the Office of Advanced Research and Technology was established in the November 1961
agencywide reorganization, research tasks had been assigned to the Office of Aeronautical and Space
Research, renamed the Office of Advanced Research Programs in 1959.
"fAbbott chaired the NACA Ad Hoc Committee on NASA Organization, commonly called the Ab-
bott Committe, from April to August 1958. This committee's suggestions contributed to the new agency's
initial structure.
ADVANCED
RESEARCH
ANDTECHNOLOGY 405
*Wallops Station (renamed Wallops Flight Center in 1974) wasestablished as a Langley subsidiary in
1945. Used primarily as a launching center by NASA, Wallops was also responsible for some advanced
aeronautical research projects.
tThe Flight Research Center was renamed the Hugh L. Dryden Flight Research Center in 1976.
**Budget reductions forced NASA to close the Electronics Research Center in 1969.
t For example, NASA was a nonvoting member of the Interservice Group for Flight Vehicle Power.
* ** For example, in 1967 PSAC recommended that NASA's advanced research and technology program
be maintained at a higher level.
t t t In 1968, Raymond L. Bisplinghoff, former director of OART, was named to chair a new Research
and Technology Advisory Council. Work of the group was divided among seven committees, which func-
tioned much as the research advisory committees had.
406 NASA HISTORICAL DATA BOOK
counted every airplane, helicopter, launch vehicle, and spacecraft that benefited in
some way from an OART research project-and the benefits would range from im-
proved ailerons and flight couches to new rocket motors to concepts for landing on
the surface of Mars. This chapter will discuss the major research projects that were
under way during 1958-1968 and indicate how this research was used to develop new
flight subsystems or hardware or how it contributed to the solution of flight prob-
lems.
Table 4-1.
Three Phases of Advanced Research and
Technology Management, NASA Headquarters
Phase I
Oct. 1958-Oct. 1961
Chief, University Research (Lloyd A. Wood); office renamed Research Grants and Contracts in
mid-1959 and dropped in 1961
Phase II
Administrator/Deputy Adminstrator
Associate Administrator
Director, Advanced Research and Technology (Abbott; Raymond L. Bisplinghoff, Aug. 1962)
Director Nuclear Systems (Harold B. Finger)
Director. Aeronautical Research (John P. Stack; Charles H. Zimmerman, June 1962)
Director. Propulsion and Power Generation (William H. Woodward; John L. Sloop, Feb. 1962)
Director Program Review and Resources Management (Boyd Myers II)
Table
4-1.
Three
Phases
of Advanced
Research
and
Technology Management, NASA Headquarters (Continued)
Phase III
Administrator/Deputy Administrator
Associate Administrator
Associate Administrator, Advanced Research and Technology (Bisplinghoff; Mac C. Adams, Oct.
1965; James M. Beggs, June 1968)
Deputy Associate Administrator (Operations) (Myers)
Deputy Associate Administrator (Aeronautics) (Charles W. Harper); office added in May 1967
Division Director, Aeronautical Research (Albert J. Evans, acting; Harper, Oct. 1964;
Evans, May 1967)
Division Director, Biotechnology and Human Research (Konecci; Walton L. Jones, Oct.
1964)
Division Director, Chemical Propulsion (Adelbert Tischler); office added in Jan. 1964
Division Director, Electronics and Control (Kelley; Francis J. Sullivan, May 1965)
Division Director, Nuclear Systems and Space Power (Finger; Woodward, April 1967);
office renamed Space Power and Electric Propulsion in April 1967
Division Director, Programming and Resources Management (Powell M. Lovell; Merrill
H. Mead, 1964; Walter C. Scott, 1965; William E. Hanna, Jr., 1967; Paul E. Cotton,
1968)
Division Director, Research (Kurzweg)
Division Director, Space Vehicle Research and Technology (Ames)
Division Director, Mission Analysis (Leonard Roberts); office added in 1967"*
Manager, AEC-NASA Space Nuclear Propulsion Office (Finger; Milton Klein, March
1967)
Division Director, Space Flight Programs (R. D. Ginter); office added in 1967 and
renamed Special Programs in 1968
Director, Research and Technology Support (Clarence R. Morrison); office added in
1967 and dropped in 1968
*Prior to July 1962, Alfred M. Mayo was serving as a special assistant to the director of OART to ac-
tivate an Office of Bioresearch.
**As of February 1965, many advanced planning and mission analysis tasks were assigned to the Mis-
sion Analysis Division at Ames Research Center. This group identified options for future planning and
estimated the time in which a certain technology would be needed.
408 NASA
HISTORICAL
DATABOOK
BUDGET
For general information on the NASA budget and the budget charts in this
chapter, consult chapter 1. For a more detailed breakdown of flight project budgets,
consult the NASA annual budget estimates. Review the bottom notes of the follow-
ing charts carefully before making conclusions about the totals for any specific proj-
ect or area of research.
Advanced research and technology funds were divided among broad disciplines;
for example, basic research, space vehicle systems, and aeronautics. The budget was
further broken down by research field or research project; for example, fluid
physics, lifting bodies, and hypersonic aircraft. For each discipline, a total budget
chart is provided, along with individual project charts. The following categories
represent the changing organization of OART. For instance, space power was com-
bined with nuclear-electric systems as of the FY 1966 budget estimate (consult table
4-3).
As explained above, projects in other directorates also were awarded supporting
research and technology funds. For these figures, see the budget charts under the ap-
propriate discipline; for example, table 3-46 deals with Applications Technology
Satellite supporting research and technology and advanced studies.
Table 4-2.
Advanced Research and Technology Funding History
(in thousands of dollars)
a Total for aeronautical and space research (support of NASA plant and research grants and contracts);
see also table 1-31 for research related to launch vehicles.
bTotal for aeronautical and space research (support of NASA plant and research grants and contracts)
plus spacecraft technology; see also table 1-31 for research related to launch vehicles.
CTotal for spacecraft technology and aircraft and missile technology; see also table 1-31 for research
related to launch vehicles.
dTotal for support of NASA plant, research grants and contracts, and spacecraft technology.
eTotal for spacecraft technology and aircraft and missile technology.
fThe appropriations conference committee reduced the final total to $301 500 000 on October 25,
1967.
ADVANCED
RESEARCH
ANDTECHNOLOGY 409
Table 4-3.
Programmed Costs by Advanced Research and Technology Project
(in thousands of dollars)
Project 1959 1960 1961 1962 1963 1964 1965 1966 1967 1968
Support of
NASA Plant 2271 27 762 ___a ..................
Basic Research
Scout reentry
heating ...... 500 3000 c 1383 305 400 3000 1800 ___d
FIRE ......... 3969 e 13 912 f 7037 1811 .........
Scout-launched
meteoroid
Electronic Systems
SRT --- 4933 15 535 26 380 23 222 29 848 32 302 37 557
RAM ______j ___k 1305 450 900 1300 1000 500
Scanner ---J --- 110 1800 1500 1152 295 ---
Gemini optical
Human Factor
Systems SRT --- 1984 9678 13 200 12 160 13 000 14 765 18 228
Small flight projects --- 420 112 000 1160 1900 1500 1600
Nuclear-Electric
Systems SRT --- 8210 19 463 26 749 36 770 38 200 34 940 42 385
SNAP-8 --- 6103 15 994 15 465 19 150 4000 5500 ___1
Electric engine
Solar and
Chemical Power
Aeronautics
SRT --- 30000 u 996 6580 9195 8163 10 186 35900 66 800
X-15 _-_ 7000v ___w 5580 9_0 1425 883 ___x ___y
Table 4-3.
Programmed Costs by Advanced Research and Technology Project
(in thousands of dollars) (Continued)
Project 1959 1960 1961 1962 1963 1964 1965 1966 1967 1978
Supersonic
transport ...... 100 1958 2513 8821 19 953 12 331 __z ___aa
z bb
XB-70A ..................... 9896 ......
V/STOL ...... 757 __cc 925 2879 2987 3200 __dd ___ee
aEstimate as per the FY 1962 budget estimate was $48 203 000; by the FY 1963 estimate this category
was dropped.
b For spacecraft technology.
c For launch vehicles.
d$2 206 000 was programmed for Scout-launched reentry technology flight experiments from the
space vehicle aerothermodynamics budget.
c Included $2 400 000 for the Atlas-Antares launch vehicle.
f Included $4 000 000 for the Atlas-Antares launch vehicle.
glncluded $800 000 for the launch vehicle.
h$1 336 000 was programmed for small flight experiments from the space vehicle aerother-
modynamics budget.
i$1 200 000 was programmed for lifting body tests from the space vehicle aerothermodynamics
budget.
)Funded as a small space vehicle flight experiment.
kS1 635 000 was programmed for RAM from operation of installation funds.
187 500 000 was programmed for SNAP-8 technology in the SRT budget.
mlt was estimated in the FY 1965 budget estimate that $600 000 would be programmed for small
nuclear-electric propulsion and power flight projects (MECCA); this category was dropped in the FY
1966 budget.
nlt was estimated in the FY 1964 budget estimate that $5 500 000 would be programmed for electric
engine development projects; this category was dropped in the FY 1965 budget estimate.
°Included $1 500 000 for the Scout launch vehicle.
Plncluded $6 700 000 for the Scout launch vehicle.
q Included with nuclear-electric systems.
rlncluded with space power and electric propulsion systems.
Slncluded as part of the liquid propulsion program in the FY 1963 request, as part of the OMSF
launch vehicle and propulsion systems program in the FY 1964 request, and as part of the OAR'I-
chemical propulsion program in the FY 1965-1968 requests.
tFunded by the U.S. Air Force.
UFor aircraft and missile technology.
vFor X-I 5 hypersonic environmental studies.
w$539 000 was programmed for X-15A research from the operation of installations budget.
x$6 280 000 was programmed for hypersonic aircraft technology supporting research from the
research and technology budget (formerly SRT).
Y$3 448 000 was programmed for the X-15 from the hypersonic aircraft research and technology
budget (formerly SRT).
z$14 040 000 was programmed for supersonic aircraft technology supporting research from the
aeronautics research and technology budget (formerly SRT).
aa$24 050 000 was programmed for supersonic aircraft technology supporting research from the
aeronautics research and technology budget (formerly SRT).
bbof the $24 050 000 programmed for supersonic aircraft technology supporting research from the
aeronautics research and technology budget (formerly SRT), $10 000 000 was for the XB-70A.
cc$182 000 was programmed for V/STOL from the operation of installations budget.
dd$4 440 000 was programmed for V/STOL from the aeronautics research and technology budget
(formerly SRT).
_$7 057 000 was programmed for V/STOL from aeronautics research and technology funds
(formerly SRT).
ADVANCED
RESEARCH
ANDTECHNOLOGY 411
Table
4-4.
Support
of NASAPlantFunding
History
(inthousands
ofdollars)
a
Year Request Authorization Programmed
1959 ...... 2271
1960 ...... 27762
1961 51345 51345 ___b
1962 89110 89110 ---
aIncludes
thefollowing
categories:
transportation,
communications
services,
othercontractual
serv-
ices,
supplies
andmaterials,
andequipment. These
funds
were
distributed
amongallNASA installations
andwereused
forawide variety
ofexpenses.
bEstimate
aspertheFY1962 budget was$48203
000;
bytheFY1963estimate
thiscategory
had
beendropped.
Table4-5.
TotalBasicResearch
Funding
History
(inthousands
ofdollars)
Year Request Authorization Programmed
aFor research grants and contracts in the following fields: physical science, cosmological science,
bioscience, engineering science, socioeconomic studies, propulsion science, and miscellaneous.
bEstimate as per the FY 1962 budget estimate was $5 000 000; by the FY 1963 estimate this category
had been dropped.
CNo corresponding line item.
d Final total was decreased to $20 000 000 by the appropriations conference committee on October
25, 1967.
Table 4-6.
Basic Research Supporting Research and Technology Funding History
(in thousands of dollars)
Table4-7.
Basic
Research
Supporting
Research
andTechnology--Fluid
Physics
Funding
History
(inthousands
ofdollars)
Year Request Authorization Programmed
a Authorization not broken down by individual supporting research and technology project.
Table 4-8.
Basic Research Supporting Research and Technology--Electrophysics Funding History
(in thousands of dollars)
a Authorization not broken down by individual supporting research and technology projects.
Table 4-9.
Basic Research Supporting Research and Technology-Materials Funding History
(in thousands of dollars)
a Authorization not broken down by individual supporting research and technology projects.
ADVANCED RESEARCH AND TECHNOLOGY 413
Table 4--10.
a Authorization not broken down by individual supporting research and technology projects.
Table 4-11.
Total Space Vehicle Systems Funding History
(in thousands of dollars)
Table 4-12.
Space Vehicle Systems Supporting Research and Technology Funding History
(in thousands of dollars) a
aSRT funds supported work in several fields: spacecraft and launch vehicle aerothermodynamics,
spacecraft and launch vehicle loads and structures, space vehicle environmental factors, advanced space
vehicle concepts, and space vehicle design criteria.
bFor vehicle systems technology.
CFor space systems technology.
d For spacecraft technology advanced research.
eAuthorization not broken down by line item.
fAll items were described as research and technology projects (there were no flight project
categories): space vehicle aerothermodynamics, $11 815 000; space vehicle structures, $9 779 000; space
environmental protection and control, $10 754 000; and space vehicle design criteria, $1 752 000.
Table 4-13.
Space Vehicle Systems Flight Projects Funding History
(in thousands of dollars)
Table 4-14.
Space Vehicle Systems Flight Projects-Scout Reentry Heating Funding History
(in thousands of dollars)
Table 4-15.
Space Vehicle Systems Flight Projects--FIRE Funding History
(in thousands of dollars)
Table4-16.
Space
Vehicle
Systems
FlightProjects-Scout-Launched
Meteoroid
Experiments
FundingHistory
(inthousands
ofdollars)
a
Year Request Authorization Programmed
1962 ...... 878
b
1963 3500 c --- 2805
1964 950 d 950 362
1965 ...... 175
aSee also table 3-10. These funds were for Explorer 23.
blncludes $800 000 for tile launch vehicle.
¢Includes $2 000 000 for launch vehicle.
dlncludes $500 000 for the launch vehicle.
Table 4-17.
Space Vehicle Systems Flight Projects-Project Pegasus Funding History
(in thousands of dollars) a
Table 4-18.
Space Vehicle Systems Flight Projects-Lifting Bodies Funding History
(in thousands of dollars)
Table4-19.
Space
Vehicle
Systems
FlightProjects-Other
SmallProjects
Funding
History
(inthousands
of dollars)
Year Request Authorization Programmed
1961 ...... 750
a
1962 ...... 295
b
1963 6990 c --- 1724
d
1964 4050 e 4050e 1959
f
1965 3000 g ___h 1010
i
1966 2000j 2000j 3000
_
1967 1500 i 1500i 4262
i
1968 2500 i ___h ___k
aIncludes
$500 000forradio
attenuation measurements,
$50 000 forTrailblazer
reentry
project,and
$700 000forhorizonsensors.
blncludes
$719 000forexperimentsdealing withbehavior andhandling ofcryogenic
propellants,
$113 000forwindshearmeasurements,
$535 000forameteorology simulationexperiment,
$84 000 fora
reentrydetection
experiment,and$273000forameteoroid penetration probe.
cIncludes
$4000 000forenvironmental experiments
(ofwhich $2000000wasforaScout launch
vehicle),
$1950000forengineering
testflightexperiments, $140 000 forarecoverable
micrometeoroid
probe,$700000forhorizon sensors,
and$200 000foraTrailblazer reentry
project.
dForameteoroid penetration
probe. Inaddition, $925000 was provided fromoperation
ofinstalla-
tionsfunds.
elncludes
$550 000forenvironmental experiments,$1650000 forexperimentsdealing
withthe
behaviorofcryogenic
propellants,
$600 000 forwindshear measurements, $600 000forameteorsimula-
tionexperiment,
$200 000foraTrailblazer reentryproject,
and$450 000forameteoroidpenetration
probe.
flncludes
$1050000forexperiments dealingwiththebehavior ofcryogenic
propellants,
$117 000
forwindshear measurements,
$640000forameteor simulationexperiment,$63000forreentry detec-
tion,and$89000 forameteoroidpenetration probe.
gIncludes
$640 000forexperiments
dealing withthebehaviorofcryogenic propellants,
$200 000 for
windshearmeasurements,$610000forameteor simulation
experiment, $150 000forreentry
detection,
and$1400 000forsecondaryenvironmental experiments.
hAuthorization
notbrokendown bylineitem.
iForplanetary
entrytechnology
andheat shield
materials
technology.
JIncludes
$95 000forwindshear measurements, $325
000formeteor simulation
experiment,and
$1580000formaterials andstructures
tests.
ks1 336 000 was programmed for parachute-decelerator flight experiments from the space vehicle
aerothermodynamics technology research budget.
418 NASA
HISTORICAL
DATABOOK
Table4-20.
TotalElectronic
SystemsFundingHistory
(inthousands
ofdollars)
Year Request Authorization Programmed
aThe authorization was not broken down by line item to indicate from what projects the $1 400 000
was subtracted.
bThe authorization was not broken down by line item to indicate from what projects the $1 000 000
was subtracted. The total was reduced further to $35 000 000 by the appropriations conference commit-
tee on October 25, 1967.
Table 4-21.
Electronic Systems Supporting Research and Technology Funding History
(in thousands of dollars)
Table 4-22.
Electronic Systems Flight Projects Funding History
(in thousands of dollars)
1961 ......... a
1962 .........
1963 ___a ___ 1536
1964 3750 3750 2320
1965 3000 ___b 2400
1966 4400 4400 2452
1967 2800 2800 1295
1968 1000 ___b 500
1961 ......... a
1962 ......... b
1963 ...... 1305
1964 2000 ___c 450
1965 2000 ___c 900
1966 3400 3400 1300
1967 1300 1300 1000
1968 400 ___c 500
Table 4-24.
Electronic Systems Flight Projects-Project SCANNER Funding History
(in thousands of dollars)
1961 ......... a
1962 .........
1963 __a ___ 110
1964 1750 ___b 1800
1965 1000 __b 1500
1966 1000 1000 1152
1967 1000 c 1000 ¢ 295
1968 600c ___b ___d
Table 4-25.
Electronic Systems Flight Projects-Other Small Projects Funding History
(in thousands of dollars)
Table4-26.
TotalHumanFactor
Systems
Funding History
(inthousands
ofdollars)
Year Request Authorization Programmed
1960 ......... a
1961 ___b ......
1962 ...... 2404
1963 ...... 9790
1964 18 200 13 200 13 200
1965 16 200 15 500 13 320
1966 14 900 14 900 14 900
1967 17 000 17 000 16 265
1968 21 000 21 000 19 828
a$917 000 was programmed for biosciences, which included some human factors research, in the
research and grants budget.
b$2 000 000 was requested for biosciences, which included some human factors research, in the
grants and contracts budget.
Table 4-27.
Human Factor Systems Supporting Research and Technology Funding History
(in thousands of dollars)
Table 4-28.
Human Factor Systems Small Flight Projects Funding History
(in thousands of dollars)
Table4-29.
TotalSpace
PowerandElectric
Propulsion
Funding
History
(inthousands
ofdollars)
Year Request Authorization Programmed
1962 ...... 20458
1963 ...... 39893
1964 68768 68768 45963
1965 48100 47100b 58220
1966 27000 33000 45200
1967 42500 44500 40440
1968 45000 44000 43735
aThiscategory
wascalled
nuclear-electric
systems untiltheFY1967 budget
estimate.
AsoftheFY
1966estimate,
funds
forspacepowerwere added tothenuclear-electric
systems
budget.
AsoftheFY
1967estimate,
funds
forsolar
andchemical powerwere added tothiscategory.
See
alsotable
1-31.
bThe authorization
wasnotbrokendown bylineitemtoindicatefromwhat
projects
the$1000000
wassubtracted.
Table4-30.
Space
Power
andElectric
Propulsion
Supporting
Research
andTechnology
Funding
History
(inthousands
ofdollars)
Year Request Authorization Programmed
1962 ...... 8210
1963 ...... 19463
1964 20 018 20 018 26 749
1965 25 000 ___a 36 770
1966 24 000 24 000 38 200
1967 37 000 37 000 34 940
1968 34 200 ___a 42 385
Table 4-3 I.
Space Power and Electric Propulsion Flight Projects Funding History
(in thousands of dollars)
Table4-32.
Space
Power
andElectric
Propulsion
FlightProjects--SNAP-8
Funding
History
(inthousands
ofdollars)
Year Request Authorization Programmed
a$9 000 000 of the total was set aside specifically for flight evaluation, of which $500 000 was for a
Thor launch vehicle.
bAuthorization not broken down by line item.
c$7 500 000 was programmed for SNAP-8 technology in the supporting research and technology
budget.
Table 4-33.
Space Power and Electric Propulsion Flight Projects-Project SERT Funding History
(in thousands of dollars)
Table 4-34.
Space Power and Electric Propulsion Flight Projects-Other Small Projects Funding History
(in thousands of dollars)
Table4-35.
TotalSpacePowerFunding History
(inthousands
of dollars) a
a Combined with the nuclear-electric systems budget as of the FY 1966 budget estimate. See also table
1-31.
bSee table 4-29.
Table 4-36.
Space Power Supporting Research and Technology Funding History
(in thousands of dollars)
Table 4-37.
Total Solar and Chemical Power Funding History
(in thousands of dollars) a
aAs of the FY 1967 budget estimate, this category was combined with the nuclear-electric systems
budget.
bSee table 4-29.
Table 4-38.
Solar and Chemical Power Supporting Research and Technology Funding History
(in thousands of dollars)
Table4-39.
TotalNuclear
Rockets
FundingHistory
(inthousands
ofdollars)
a
Year Request Authorization Programmed
Table 4-40.
Nuclear Rockets Supporting Research and Technology Funding History
(in thousands of dollars)
Table 4-41.
Nuclear Rockets Flight Projects Funding History
(in thousands of dollars)
Table 4-42.
Nuclear Rockets Flight Projects-Kiwi Funding History
(in thousands of dollars)
Table 4-43.
Nuclear Rockets Flight Projects--RIFT Funding History
(in thousands of dollars)
Tabie 4-44.
Nuclear Rockets Flight Projects--NERVA Funding History
(in thousands of dollars)
Table 4-45.
Nuclear Rockets Flight Projects-Nuclear Rocket Development Station Funding History
(in thousands of dollars)
Table4-46.
TotalChemical
Propulsion
Funding History
(inthousands
ofdollars)
a
Year Request Authorization Programmed
Table 4-47.
Chemical Propulsion Supporting Research and Technology Funding History
(in thousands of dollars)
Table 4-48.
Chemical Propulsion Flight Projects Funding History
(in thousands of dollars)
alncluded as part of the liquid propulsion program in the FY 1963 request, as part of the OMSF
launch vehicle and propulsion systems program in the FY 1964 request, and as part of the OART
chemical propulsion program in the FY 1965-1968 requests.
b Supplementary request.
CThis amount was programmed for experimental engines, of which the M-1 was the major project.
dThe total amount requested for experimental engines, of which the M-I was the major program,
was $38 000 000.
e The total amount authorized for experimental engines, of which the M-I was the major project, was
$37 000 000. There is no indication in the chronological budget history for FY 1965 from which project
the $1 000 000 was subtracted. See also table 4-50.
fAlthough NASA did not request funds in FY 1968 for the M-I, Congress authorized $7 500 000 for
the project.
Table 4-50.
Chemical Propulsion Flight Projects-Large Solid Motor Funding History
(in thousands of dollars)
Table 4-51.
Chemical Propulsion Flight Projects-Other Small Projects Funding History
(in thousands of dollars)
Table4-52.
TotalAeronautics
Funding History
(inthousands
of dollars)
Year Request Authorization Programmed
Table 4-53.
Aeronautics Supporting Research and Technology Funding History
(in thousands of dollars)
aFor aircraft and missile technology advanced research ($15 200 000 for supersonic commercial
transport, $2 300 000 for V/STOL aircraft, $3 500 000 for multicapability aircraft, and $1 000 000 for
hypersonic aircraft) and advanced technical development ($8 000 000).
bFor aircraft and missile technology advanced research ($18 000 for supersonic commercial trans-
port, $4 500 000 for V/STOL aircraft, $4 500 000 for multicapability aircraft, and $3 000 000 for hyper-
sonic aircraft) and advanced technical development ($9 500 000).
CThe increase was to fund supporting research for the SST, V/STOL, and hypersonic ramjet
projects.
dAII line items are described as research and technology projects (there are no flight project monies):
advanced research and technology, $3 730 000; general aircraft technology supporting research,
$200 000; V/STOL aircraft technology supporting research, $5 550 000; subsonic aircraft technology
supporting research, $6 100 000; supersonic aircraft technology supporting research, $14 040 000; and
hypersonic aircraft technology supporting research, $6 280 000.
CAll line items are described as research and technology projects (there are no flight project monies):
advanced research and technology, $12 800 000; general aviation aircraft technology, $450 000; V/STOL
aircraft technology, $7 057 000; subsonic aircraft technology, $7 905 000; supersonic aircraft
technology, $24 050 000; and hypcrsonic aircraft technology, $14 538 000.
ADVANCED
RESEARCH
ANDTECHNOLOGY 429
Table4-54.
Aeronautics
FlightProjects
Funding
History
(inthousandsofdoUars)
Year Request Authorization Programmed
Table 4-55.
Aeronautics Flight Projects--X-15 Funding History
(in thousands of dollars)
Table 4-56.
Aeronautics Flight Projects-Supersonic Transport Funding History
(in thousands of dollars)
Table 4-57.
Aeronautics Flight Projects-V/STOL Funding History
(in thousands of dollars)
a$182 000 from the operation of installations budget was programmed for V/STOL.
bAn increase in the authorization ($2 000 000) was to be used for the SST, V/STOL, and hypersonic
ramjet projects.
c$5 550 000 was programmed for V/STOL technology supporting research; see table 4-53, note d.
d$7 057 000 was programmed for V/STOL technology supporting research; see table 4-53, note e.
Table 4-58.
Aeronautics Flight Projects--Hypersonic Ramjet Funding History
(in thousands of dollars)
aAn increase in the authorization ($2 000 000) was to be used for the SST, V/STOL, and hypersonic
ramjet projects.
bSee table 4-53, notes d and e.
ADVANCED RESEARCH AND TECHNOLOGY 431
Table 4-59.
Aeronautics Flight Projects-XB-70 Funding History
(in thousands of dollars)
a$14 040 000 was programmed for supersonic aircraft technology supporting research; see table
4-53, note d.
bof the $24 050 000 programmed for supersonic aircraft technology supporting research,
$10 000 000 was for the XB-70; see table 4-53, note e.
Table 4-60.
Aeronautics Flight Projects-Other Small Projects Funding History
(in thousands of dollars)
aof the $6 100 000 programmed for subsonic aircraft supporting research, $4 400 000 was for air-
craft noise reduction and $1 716 000 was for quiet engine research; see table 4-53, note d.
blncludes $3 500 000 for aircraft noise reduction, $2 000 000 for quiet engine development,
$2 000 000 for the F-106, and $500 000 for the F-111.
CSee table 4-53, note e.
In the early 1960s, basic research tasks were often the responsibility of applied
research divisions within the Office of Advanced Research and Technology; for ex-
ample, research in fluid physics was supported by the spacecraft technology budget.
But the FY 1963-1968 budgets provided funds for four distinct categories of basic
research-fluid physics, electrophysics, materials, and applied mathematics. The
overall purpose of basic research was not to contribute to some specific mission or
discipline, but to "institute and administer" fundamental research with the aim that
the increase and distribution of scientific knowledge would lead to a better
understanding of the physical and mathematical laws that governed all NASA's
projects. 6
With the November 1961 agencywide reorganization, Hermann H. Kurzweg
was named OART's director of research at NASA Headquarters. He was still serv-
ing in this capacity in 1968. Although it was never a heavily funded program,
various basic research projects were supported at all NASA's research centers and by
a large number of contractors.
432 NASA HISTORICAL DATA BOOK
Fluid Physics
Electrophysics
engineering advances in such fields as space power, radiation effects, and electronic
communications. Laboratory work in electrophysics was conducted at the Lewis,
Langley, Ames, and Electronics Research Centers and at the Jet Propulsion
Laboratory, and at the facilities of many contractors. The University of Chicago,
the Johns Hopkins University, University of Michigan, Stanford University,
Virginia Polytechnic Institute, William and Mary College, University of Virginia,
Massachusetts Institute of Technology, and Columbia University were major par-
ticipants.
Research into the mechanisms of energy transfer in the atomic levels of solids
and gases led investigators to new sources for the stimulated emission of coherent
electromagnetic waves (lasers) in the region from gamma ray to millimeter
wavelengths. In turn, this led to the development of new signal sources for electronic
communications and spacecraft navigation devices. Superconductors (zero electrical
resistance at very low temperatures) made of niobium-tin were scrutinized by NASA
and contractor scientists to determine the precise relationship of the current and the
magnetic field. It was believed that the magnetic fields produced by superconducting
coils could be used to shield spacecraft from solar particle radiation; other potential
applications for superconductors included their use on electric power lines, rotating
electrical motors and generators, and gyroscopes. Electron movement through
titanium dioxide placed between aluminum films also was being studied to deter-
mine if a device capable of detecting long wavelength infrared radiation could be
developed. Many other research tasks with possible applications to space science and
vehicle design were conducted during the decade, including the study of antimatter,
high-frequency acoustic waves, lasers, and the fission-electron cell. Another area of
research that caught the attention of NASA electrophysicists concerned the electrical
forces responsible for the high velocity of tornado clouds.
One man, Harry Harrison, led the electrophysics research team during NASA's
first 10 years. He held the position of chief for electrophysics in OART's basic
research program office.
Materials
Applied Mathematics
expertsalsocouldcalculate
energy
requirements,
determine
thedistortion and bend-
ing of vehicles that could be expected during launch, and assess how the spinning
rate of spacecraft in orbit would affect tracking maneuvers or how heat flow would
affect the path of a reentering spacecraft. Researchers at the Marshall Space Flight
Center developed a numerical technique called the Runge-Kutta transformation
method that was especially applicable to solving celestial mechanics problems. Ames
Research Center mathematicians developed a numerical integration technique for
solving systems of ordinary differential equations that was applied to the calculation
of flows behind normal shock waves at very high speeds and low density.
Mathematical analyses also aided aircraft and spacecraft designers. Using
mathematical formulas, engineers could determine, for instance, the optimum
aerodynamic shape for the wings of supersonic or hypersonic aircraft. Tracking and
data processing mathematics research was devoted to such problems as numerical er-
ror analysis of tracking systems and data reduction.
Applied mathematics research had one chief during the November 1961-December
1968 period--Raymond H. Wilson, Jr.
Milton B. Ames and his space vehicle systems team were responsible for a broad
spectrum of applied research tasks designed to identify and solve problems that
launch vehicles and spacecraft might experience during launch and ascent through
the atmosphere, flight in space, entry into the atmosphere of earth or other planets,
and landing. In addition to theoretical studies and laboratory work, this group also
conducted several flight projects and participated as investigators on three Explorer
satellite missions. Through the examination of problems with existing vehicles, these
specialists also advanced the state of the art of future space vehicle design. The pro-
gram was divided into three broad areas-advanced design criteria, environmental
factors and aerodynamics (which included aerothermodynamics), and structures.
To ensure that the latest information from NASA's many research projects
could be applied to the design of future space vehicles, it was translated into space
vehicle design criteria, an organized set of engineering guides. The advanced design
criteria division was responsible for evaluating new data applicable to design prob-
lems and making that data available to engineers and designers.
The bulk of the work preformed by the space vehicle systems group was in the
field of environmental factors and aerodynamics. Aerothermodynamics specialists
investigated the special problems associated with spacecraft high-speed entry into a
planet's atmosphere, which led to research with recovery systems (parachutes,
paragliders, and flexible wings), reusable vehicles (lifting bodies), and special reen-
try heating spacecraft (Project FIRE and the Scout Reentry Heating Project).
Studies in this area also dealt with launch vehicle exhaust and acoustics problems.
The broad goal of the evironmental factors group was to gain a detailed understand-
ing of the space environment in which vehicles would travel. Vehicles would have to
be protected from radiation and extreme temperatures (research with special
shielding and materials) and meteoroids (Project Pegasus meteoroid studies).
436 NASA
HISTORICAL
DATABOOK
Many of the space vehicle failures that occurred during the agency's early years
were traced to the application of inadequate or inappropriate design conditions or
procedures. To prevent structural failures, the advanced design criteria group, part
of OART's space vehicle systems program, provided designers and project managers
with a continual stream of new technical information suitably filtered from the total
mass of data available and arranged in a useful form for uniform application to
design studies. These design criteria (engineering guides) took the form of
monographs. Representative topics included solar electromagnetic radiation, buc-
kling of thin-walled cylinders, and aerodynamic and ground-wind loads. It was the
responsibility of the advanced design criteria team to identify design problems, for-
mulate existing technical information bearing on the problems into authoritative
guides, distribute the guides to NASA and industry users, and update them as re-
quired. This work usually fell into four broad categories: environmental factors,
structures, proplusion, and stability, guidance, and control.
Personnel at all of NASA's centers prepared advanced design criteria, with three
of the centers functioning as lead centers: Langley (structures), Lewis (propulsion),
*For a time in 1962-1963, there was an assistant director for aerodynamics (Pearson) and an assistant
director for environmental effects (May); when the two research fields were combined Pearson was
named assistant director and May programs chief.
ADVANCED
RESEARCH
ANDTECHNOLOGY 437
Environmental
Factors and Aerodynamics
Of the three major divisions of space vehicle systems, the environmental factors
and aerodynamics group had the broadest range of responsibilities. These specialists
were concerned with every aspect of flight from launch to landing, with particular
emphasis on understanding the environment of space and protecting the vehicle
from that environment and on reentry (or entry) and recovery. Environmental fac-
tors research included many topics-determination of the meteoroid environment
and means for protecting the vehicle against penetration, the effects of high-energy
charged-particle radiation and shielding against it, thermal vacuum effects on
spacecraft temperature control, storage of cryogenic liquids for long periods,
behavior and control of fluids under reduced gravity conditions, and structural con-
cepts that take advantage of the very low gravitational and aerodynamic forces in
space.
Penetration of a vehicle by meteoroids was one of the early fears expressed by
spacecraft designers. While data on the velocity, density, and composition of large
meteoroids were obtained by ground-based photography and radar (Harvard Col-
lege Observatory had contracts to study meteors by optical and radio reflection
techniques), more information was needed on possible meteoroid hazards in space.
While micrometeoroid detectors were included on many astronomy and physics
satellites (Vanguard, Explorer, OGO, Ariel),* three Explorers were devoted ex-
clusively to this investigation (Explorer 13, 16, and 23; see table 3-79, 3-82, and
3-89). They carried piezoelectric, wire-grid, cadmium sulphide-cell, foil-gauge, and
impact detectors to record the size, frequency, and velocity of micrometeoroids. To
provide long-term meteorite data applicable to future manned and scientific satellite
missions, OART funded Project Pegasus, three large meteorite detection satellites.
Saturn I launch vehicles orbited the Pegasus series in 1965, with data being returned
for 13 to 15 months on meteorites in the zone 480 to 725 kilometers above earth.
Meteoroids were discovered to pose no real threat to earth-orbiting satellites, and
even less danger was expected in cislunar space. Specialists at Ames Research
Center, Marshall Space Flight Center, and Langley Research Center supported these
activities (for more information see space vehicle systems flight projects).
Since high-energy radiation is detrimental to sensitive equipment and hazardous
to humans, engineers sought to protect spacecraft from the radiation they would en-
counter in space. Research into high-energy proton and electron radiation effects
was one of the responsiblities of the OART environmental factors team, which
*Some experiments were also performed using sounding rockets and simulated meteors to determine
the heating and entry phenomena of natural meteors.
438 NASA
HISTORICAL
DATABOOK
1965.ProjectFIREwasdesigned to gatherdataontotalandradiantheatingand
radiosignalattenuation andto evaluate a berylliumheatshield.(Formoreinforma-
tion, seeunderspace vehiclesystems flightprojects).
In additionto lookingat protectiveshieldingfor blunt-nosed cone-shaped
nonliftingspacecraft, NASAdesigners alsoinvestigated otherpossible configura-
tions for future spacecraft that wouldgivethe vehicleimprovedmaneuvering
capabilitiesduringreentryplusprotectionfromreentryheating.NASAjoinedthe
Air Forcein testingaclassofvehicles calledliftingbodies (ormediumlift-drag-ratio
maneuvering vehicles).Includedin this testingprogramwereNASA'sM-2 and
HL-10andtheAir Force'sX-24A.Personnel atAmesandLangley Research Centers
participated in designandengineering studiesandwindtunneltests,withflighttest
landingstakingplaceattheFlightResearch Center(formoreinformationseeunder
space vehiclesystems flightprojects).
To assistwith the final landingand recoverysequences of conventional
truncated-cone-shaped spacecraft,NASA designers and contractorslookedat
severalparachute configurations. Cooperating with specialistsfrom the manned
spaceflight program,OARTpersonnel testedlargedrogueparachutes capableof
handling13600kilograms duringawaterlanding.Butmoresteerable devices would
be requiredfor mannedspacecraft touchdowns onland,andOART specialists
studiedseveralkindsof controllable, gliding-type parachutes calledparagliders or
parawings. LangleyResearch Center*wasthesiteof paraglider research andwind
tunneltesting,withflighttestingbeingconducted atHouston's MannedSpacecraft
Center,FlightResearch Center,andtheJointParachute TestFacilityatE1Centro,
California.Sincetheparaglidermadefeasiblea controlled descent in a shallow
glide,mannedspaceflight personnel seriouslyconsidered it for ProjectGemini.
Several contractors, NorthropVenturaandB. F. Goodrichamongthem,alsopar-
ticipatedin paraglider research andfabrication. 9Designing a parachute system that
wouldoperatein thethin atmosphere of MarswasanothertaskthatheldOART's
attention.Thedeployment of largelightweight parachutes at relativelyhighspeeds
wouldberequiredforthelargeVoyager Marslander.Small-scale andfull-scale tests
of parachute concepts fora terminaldescent onMarswereconducted in 1966-1968.
Nikesounding rocketsandballoonswereusedtocarrytheseparachutes aloftwhere
theyweredeployed. Specialists at AmesandLangley participated in this research.
UntilErnestO. Pearson, Jr., became MiltonAmes'sdeputyin 1966,heledthe
enviromental factorsandaerodynamics officewithinOART'sspace vehiclesystems
groupat NASAHeadquarters. RalphW. May,programs chief,wasassisted for
manyyearsby Clotaire Wood (vehicle technology flight experiments), Fred J.
DeMerritte (aerothermodynamics), and J. Warren Keller (environmental factors).
As with other research fields, the space vehicle structures program had many
parts. Its broad objective was to identify and solve critical spacecraft and launch
*Francis M. Rogallo of Langley originated the stowable flexible-wing paraglider concept in the
1950s.
440 NASA HISTORICAL DATA BOOK
Pegasus. Personnel at'the Marshall Space Flight Center, physicist Ernst Stuhi-
inger among them, proposed a Saturn-launched meteoroid detection satellite to
NASA planners in late 1962. The original proposal called for exposing to possible
meteoroid penetrations large areas of aluminum of different thicknesses (meteoroids
range in size from microscopic particles to huge fragments). By December 1962,
NASA had requested proposals from industry for designing and constructing two
large satellites with expandable wings, which would provide more than 185 square
meters for detection equipment. Explorer 16, a meteoroid detection experiment
launched in 1962, had had only 2.3 square meters available for detectors. NASA
scientists and designers needed more data on the quantity, size, and velocity of
meteoroids so they could protect from possible hazards scientific satellites and
probes being planned for increasingly long lifetimes and manned spacecraft destined
for earth orbit and cislunar space.
Fairchild Stratos Corporation (later known as Fairchild-Hiller) was awarded a
contract to build two flight models of a Micrometeoroid Detection Satellite (MDS)
in early 1963. The satellite's wings would consist of 208 panels, each about 0.5 by 1
ADVANCED
RESEARCH
ANDTECHNOLOGY 441
*Pegasus represents a deviation from the usual practice of designating a satellite of this class one of
the Explorer series.
442 NASA HISTORICAL DATA BOOK
flux of small particles decreased rapidly with distances from earth combined to cut
short plans for any advanced meteoroid detection satellite.
Fairchild Stratos (Fairchild-Hiller) was the prime contractor; G. T. Schjeldahl
fabricated the detector panels. Marshall Space Flight Center monitored these con-
tracts, with William G. Johnson acting as project manager. OART funded the
project.
Table 4-61.
Chronology of Pegasus Development and Operations
Date Event
1962 Personnel at the Marshall Space Flight Center proposed using the Saturn
vehicle to launch a micrometeoroid detection experiment.
Dec. 30, 1962 NASA issued a request for proposals for the design and construction of a
large-surfaced micrometeoroid detection satellite.
Feb. 5, 1963 NASA announced it would negotiate with Fairchild Stratos Corp. to build
two flight models of a micrometeoroid detection satellite.
March 4, 1963 NASA awarded Fairchild a contract for the construction of such a satellite,
unofficially called Pegasus.
Dec. 1963 Marshall personnel considered using the SA-10 vehicle for a third Pegasus
satellite.
April 1964 NASA Headquarters approved a third Pegasus. The Martin Co. was awarded
a contract by Langley Research Center for a design study of an advanced
Pegasus that would be launched by a Saturn IB-Centaur to investigate
cislunar and interplanetary space.
July 21, 1964 The name Pegasus was officially approved by NASA for the micrometeoroid
satellite project.
May 1965 NASA awarded a phase two contract to Martin for an advanced Pegasus
study.
March 1, 1966 The last hit was recorded on Pegasus 1; only engineering data were recorded
thereafter.
July 21, 1966 Marshall let a contract to Emerson Electric to study the feasibility of Gemini
astronauts visiting Pegasus to retrieve panels for return and analysis.
Aug. 16, 1967 The last hit was recorded on Pegasus 3; only engineering data were recorded
thereafter.
Oct. 31, 1967 The last hit was recorded on Pegasus 2; only engineering data were recorded
thereafter.
Table4-62.
Pegasus
Characteristics
Date of launch (location): Feb. 16, 1965 May 25, 1965 July 30, 196'_
(ETR) (ETR) (ETR)
Launch vehicle: Saturn I Saturn 1 Saturn I
(SA-9) (SA-8) (SA-10)
Weight (kg): 2675 plus:
Attached second stage, 6575
Instrument unit, 1180
Boiler plate Apollo module, 1435
Propellant, 700
Shape: Fuselage-shaped center section with 2 wings, which were folded and
stowed during launch
Dimensions(m): Length of center stage and attached second stage, 22
Width, wing tip to wing tip, 29
Width of wing, 4.3
Power source: NiCd batteries plus solar cells
Date of reentry: Sept. 17, 1978 Nov. 3, 1979 Aug. 4, 1969
Cognizant NASA center: MSFC
Project manager: William G. Johnson
Contractor: Fairchild Stratos (later known as Fairchild-Hiller), prime
G. T. Schjeldahl, detector panels
Objectives: Detect the frequency, velocity and size of meteoroids at an altitude of
480-725 kilometers.
Experiments: Capacitor detectors
Results: All three satellites returned information on meteoroid penetrations, plus
data on the Van Allen radiation belts, earth albedo, and thermal control
systems. The satellites were silenced in Aug. 1968.
Remarks: Through October 1967, a total of 2265 hits had been recorded. Pegasus 1
started sending signals again intermittently in June and July 1977.
Scout Reentry Heating Project. The effects of high-velocity reentry heating and
the search for materials that could withstand reentry had long been a concern of
specialists at Langley Research Center, even before the facility became part of
NASA. It was an even more crucial concern for manned spaceflight. Speeds in ex-
cess of 33 800 kilometers per hour had been reached under laboratory conditions in
the early 1960s, but actual flight experiments would be necessary to duplicate the
conditions a manned crew might face on their return from earth orbit or the moon.
In 1961, space vehicle systems engineers and manned spacecraft designers perceived
a four-stage program for gathering pertinent data on reentry heating and the ability
of specific materials to withstand the reentry environment. First and already under
way were experiments in wind tunnels and laboratories. Second was a Scout-
launched* reentry project scheduled for December 1961 to September 1962, follow-
ed by an Atlas-Agena B-launched Project FLARE (Flight Investigation of Apollo
*Plans called for a five-stage Scout; the vehicle as developed included only four stages. However, the
designers might have been considering a velocity package that would have given the reentry payload in-
creased speed as a "fifth stage."
444 NASA HISTORICAL DATA BOOK
'ffhe first reentry experiment, R-I, was a secondary experiment on this eighth Scout development
flight; proving the launch vehicle was the primary mission goal.
ADVANCED
RESEARCH
ANDTECHNOLOGY 445
Table 4-63.
Date Event
Aug. 1961 A preliminary project development plan for Project FLARE (Flight Investiga-
tion of Apollo Reentry Environment) included a series of Scout-launched
reentry experiments in 1963, to precede the higher-velocity Atlas-launched
experiments.
Fall 1961 NASA Headquarters approved the Scout Reentry Heating Project and
assigned project management to Langley Research Center.
July 20, 1963 An attempt to launch R-3 was unsuccessful because the launch vehicle
malfunctioned; the entire vehicle was destroyed.
Spring-Summer 1965 Studies were under way at Langley that were designed to investigate the
usefulness of extending the project to include two more flights; two more
flights were approved that fall.
Dec. 16, 1965 NASA issued a request for proposals for the design and fabrication of a sixth
reentry experiment to be housed in a slender cone.
March 8, 1966 NASA selected the Missiles and Space Division of General Electric to build
the R-6 spacecraft, one prototype, and one backup.
Dec. 1968 Langley officials investigated the possibility of using the R-6 backup for a
seventh reentry experiment.
ADVANCED RESEARCH AND TECHNOLOGY 447
Table 4-64.
Scout Reentry Heating Project
Date of launch March 1, 1962 Aug. 31, 1962 July 20, 1963 Aug. 18, 1964 Feb. 9, 1966
(location): (Wl) (Wl) (Wl) (wl) (Wl)
Launch vehicle: Scout Scout Scout Scout Scout
(ST-8) (S-114) (S-II0) (S-129R) (S-141C)
Weight (kg):
Reentry experiment: 70.4 70.4 77 82.6 95.3
With rocket motor: 158.8 158.8 170.1 145.1 156.5
Shape: Blunt-nosed cone
Dimensions (m):
Length: 0.94
Base diameter: 0.514
Nose diameter: 0.29
Date of reentry: Ballistic trajectories
Cognizant NASA LaRC
center:
Project manager: Andrew G. Swanson Joseph M. Hallissy
Contractor: Naval Ordnance Test Station, payload rocket motor
(LaRC) provided the reentry payload.)
Objectives: To gather information on heat transfer during high-velocity reentry and to
evaluate various heat shield materials.
Experiments: Temperature-measuring thermocouples (R-I through R-5)
Springwire ablation sensors (R-3 through R-5)
Lightpipe ablation sensors (R-5)
Results: R-1 and R-2 were successful in returning heat transfer data; R-3 failed because
the launch vehicle malfunctioned; R-4 and R-5 successfully tested various heat
shield materials.
448 NASA HISTORICAL DATA BOOK
Table 4-65.
Scout Reentry Heating Project (R-6) Characteristics
*A three-stage Scout launched R-6 (four stages was the standard configuration).
escape velocities. The reentry capsule would be made of Mercury spacecraft com-
ponents, and the experiments would give Project Mercury personnel extra ex-
perience with tracking and data acquisition procedures. This idea was abandoned in
vironment, Project FLARE (also briefly called Project Calorie). Plans called for
four Atlas-Agena B-launched flights in 1963. The recoverable payload would resem-
ble a small Apollo command module (a truncated cone) and be fitted with a
beryllium calorimeter-heat shield. By early 1962, the project had been redesignated
Project FLARE, the launch vehicle had been changed to Atlas-Antares,* and the
number of missions had been reduced to two. Funds were first programmed for
FIRE in FY 1962.
Project FIRE reentry payloads reached speeds in excess of 40 000 kilometers per
hour, the velocity a spacecraft returning from the moon was expected to reach. Out-
fitted with multilayer heat shield-calorimeters, the FIRE vehicles measured radiative
and conductive heat transfer and returned data on the radiant energy and spectral
*I'hc Antares stage was an ABL X-259 motor, also used as Scout's third stage. FIRE was the only
NASA project that utilized the Atlas-Antares configuration. The ballistic trajectory called for did not re-
quire the more powerful Atlas-Agena B, and the Antares stage could be procured more inexpensively
than the Agena B.
ADVANCED RESEARCH AND TECHNOLOGY 449
content of the hot gas cap, that area just ahead of a reentering body that is heated by
energy transferred from the vehicle. Secondary objectives included measuring the
response of heat shield materials to the reentry environment and monitoring radio
attenuation effects during the reentry blackout period. The blunt end of the trun-
cated cone consisted of three beryllium calorimeters, which were instrumented with
thermocouples interleaved with three phenolic asbestos ablative heat shields. All but
the last two layers were designed to burn away or be jettisoned during the 45-second
high-heating reentry period. By periodically jettisoning heat shield layers to expose
fresh calorimeters to the reentry environment, readings on the heating phenomena
were taken during the earliest portion of reentry, at the peak, and near the end of the
heating period. Two radiometers measured total radiant energy, and a spectral
radiometer relayed data on reentry heating caused by radiation from the hot gases
and the chemical content of the gases. Each FIRE reentry vehicle carried 258 ther-
mocouples.
At launch, the Antares velocity package was connected to the Atlas stage by an
adapter, and the reentry vehicle was fitted to the cylindrical Antares. The Antares
stage separated from the Atlas booster about 5 minutes after launch, with ignition of
the second stage taking place at about 26 minutes; separation of the reentry vehicle
from the Antares stage came about 1 minute later. Traveling at 40 000 kilometers
per hour, the spacecraft headed for splashdown near Ascension Island in the south
Atlantic. In addition to the onboard sensors, information also was gathered from
Ascension Island with a telespectrograph, a light-gathering telescope equipped with
a slitless spectrograph. This instrument measured the spectrum of light generated
during reentry in the visible and near-infrared wavelength ranges, defining the
chemical constituents of the incandescent gas.
FIRE 1 was launched on April 14, 1964, from the Eastern Test Range. The
32½-minute flight was successful, and a Nike-Apache sounding rocket launched
from Ascension Island gathered supplementary data on weather conditions near the
reentry area after splashdown. FIRE 2, on May 22, 1965, validated the findings of
the first mission during its 32-minute flight. Heat shield ejection times were revised
slightly on FIRE 2, and the reentry vehicle was instrumented with additional
pressure sensors. After the successful flight, another Nike-Apache was launched
from Ascension to measure density, temperature, pressure, and wind conditions.
The two FIRE experiments provided data that indicated that the radiation and the
temperatures that would be experienced during an Apollo spacecraft reentry were
less severe than had been expected. Spacecraft engineers made use of this informa-
tion in designing and qualifying Apollo's heat shield. FY 1964 funds for an advanced
FIRE that would have duplicated the reentry of spacecraft from interplanetary mis-
sions at an even greater velocity were not approved by Congress.
Project FIRE was managed by Langley Research Center. Herbert A. Wilson,
Jr., was project manager for FIRE 1, David G. Stone for FIRE 2. Under contract to
Langley, Chance Vought Corporation of Ling-Temco-Vought, Inc., fabricated the
velocity package; Republic Aviation built the reentry vehicle; General
Dynamics/Astronautics served as integration manager. At NASA Headquarters in
the Office of Advanced Research and Technology, Ralph W. May, Jr., was FIRE
program manager.
450 NASA HISTORICAL DATA BOOK
Table 4-66.
Chronology of FIRE
Development and Operations
Date Event
Sept. 1960 An entry test vehicle project was proposed by NASA personnel. Mercury-like
payloads, launched into ballistic trajectories by Atlas-Agena B vehicles,
would reenter the atmosphere at near-escape speeds, allowing researchers to
investigate reentry heating.
Aug. 1961 Langley Research Center personnel prepared a preliminary development plan
for Project FLARE (Flight Investigation of Apollo Reentry Environment).
The plan called for four small recoverable reentry payloads that resembled
Apollo command modules in shape. A beryllium calorimeter-heat shield
would be tested and temperature measurements taken at velocities reaching
11 000 meters per second.
Sept. 13, 1961 NASA Headquarters proposed designating the Apollo reentry environment
experiments Project Calorie, a name which was not adopted.
Feb. 18, 1962 NASA announced plans for Project FIRE (Flight Investigation Reentry En-
vironment), as the reentry experiment had been renamed. Atlas D boosters
would launch two reentry vehicles into ballistic trajectories in 1963-1964.
March 29, 1962 Republic Aviation was named prime contractor for FIRE reentry vehicles
and Chance Vought contractor for the FIRE velocity package (Antares sec-
ond stage).
Nov. 20, 1962 General Dynamics/Astronautics was named contractor for FIRE systems in-
tegration.
Summer 1964 Republic Aviation and Chance Vought were given the go-ahead to begin
work on the second FIRE velocity reentry vehicle and velocity package.
Table 4-67.
Project FIRE Characteristics
FIRE 1 FIRE 2
During the late 1950s and early 1960s, specialists at Langley and Ames conducted
studies independent of one another of several lifting body designs and ran wind tun-
nel tests on various scale models.
Egger's design for a reentry vehicle caught the attention of engineer Robert Dale
Reed at NASA's Flight Research Center (FRC) in California. Reed built several
small models of this lifting body and suggested that the design could be flown in a
towed fashion for testing.* In turn, Reed's models intrigued several of the Air Force
and NASA test pilots stationed at Edwards Air Force Base.l" By the fall of 1962,
FRC Director Paul F. Bilke had approved the construction of a lightweight full-scale
lifting body to be designated the M2-F1 (M for manned; F for flight model). With
the assistance of a local glider manufacturer, Sailplane Corporation of America,
engineers built the M2-F1 in-house at FRC from plywood and tubular steel and sent
it to Ames for wind tunnel verification tests. The first successful ground-towed ex-
periments, which used an uprated Pontiac convertible as the towing vehicle, were
*Ground-towing had been used successfully at FRC to test out steerable parachute concepts.
l'The Air Force Flight Test Center was at Edwards Air Force Base.
452 NASA HISTORICAL DATA BOOK
carried out in April 1963, with the first air-towed flight via a C-47 taking place the
following August. Equipped with an ejection seat, the half-coned M2-F1 was towed
to an altitude of 3048 meters and released for about 3 minutes of free flight, using its
tricycle landing gear to set down on the dry lake beds of Edwards. Over two Years,
five pilots flew the vehicle (labeled the "flying bathtub") during hundreds of flight
experiments (ground- and air-towed).
The next step in FRC's lifting body program called for the construction of an
M-2 flight vehicle of heavier all-metal construction. Norair Division of Northrop
built the 2300-kilogram M2-F2 lifting body in 1964-1965, and specialists at Ames
conducted a series of wind tunnel tests on the new vehicle in early 1966. In July, the
M2-F2 was carried aloft under the wing of a B-52 and released at 14 000 meters for a
successful first flight. The amount of free flight time was still very limited, but with
rudder and flaps and the vehicle's high-lift body four test pilots maneuvered the
M2-F2 for landings at Edwards. On the 16th flight experiment on May 10, 1967, the
pilot crash-landed without his landing gear down, after an unusually low flare
maneuver executed to recover from a lateral oscillation. The vehicle turned over
several times, injuring the pilot and the craft. In the spring of 1968, NASA Head-
quarters authorized a Northrop-FRC team to restore the damaged M2-F2.
Redesignated the M2-F3, the lifting body was repaired and flown again in
1970-1972.
From their studies of lifting body designs at NASA's Langley Research Center,
advanced researchers had come up with a configuration they called HL-10 (HL for
horizontal landing); it was the 10th design they examined in the spring of 1962.
Though similar in general shape, size, and weight to the M2-F2, Langley's vehicle
was round on top and flat on the bottom (the opposite of the M2), plus it had a third
vertical tail fin (in the center) and more of a delta-wing shape overall. It did not have
the M2's bubble-type cockpit canopy. Northrop built the HL-10 and the M2-F2
under the same contract, completing the HL-10 in early 1966. The test-flight phase
of the Virginia center's lifting body project also was conducted at FRC, with the first
successful flight on December 22, 1966. Nearly 15 months went by before the second
experiment took place, while engineers ground-tested the vehicle further and
modified the design somewhat to increase its stability. From 1966 to 1970, the
HL-10 (sometimes called a "flying flatiron") was flown 37 times by 5 test pilots. As
with the M2, the HL-10 was launched from under the wing of a B-52. To test the lift-
ing body concept at greater speeds and altitudes, the HL-10 and M2-F2 were both
designed to accommodate a jet engine. In November 1968 on the vehicle's 13th
flight, HL-10 experiments were expanded to include powered flight. Augmented by
an XLR-11 jet engine, the HL-10 could travel at 1915 kilometers per hour at 24 000
meters.
The Air Force also was interested in the lifting body concept as it applied to
future spacecraft designs. Project Dyna-Soar (for dynamic soaring), the Air Force's
first entry in the manned lifting body program, had been designed around a Titan-
.launched vehicle to be built by Boeing. Designated the X-20 in the summer of 1962,
the first launch of Dyna-Soar was to have taken place in 1966, but this project was
cancelled in December 1963 because it had become too expensive and overly com-
plex, The Air Force redirected its energies to Project START (Spacecraft
Technology and Advanced Reentry Test), whose first product was the SV-5D
PRIME (Precision Recovery Including Maneuvering Entry). Later called the X-23A,
this lifting body was made by Martin Marietta and test launched (unmanned) on an
ADVANCED
RESEARCH
ANDTECHNOLOGY 453
Atlas launch vehicle in 1967. The wedge-shaped X-24A, a modified and enlarged
X-23A, was ready for manned flight tests in 1969. NASA and the Air Force had
been officially coordinating their manned lifting body programs since early 1964,
sharing testing facilities, pilots, and test results. An agreement between NASA and
the Air Force on testing NASA's M2-F2 and HL-10 was reached in April 1965, and it
was extended to include the Air Force X-24A in November 1967. NASA's Flight
Research Center had responsibility for maintenance, instrumentation, and ground
support of its craft, while the Air Force Flight Test Center assumed responsibility
for the launch aircraft, support aircraft, medical assistance, the rocket power plant,
and the pilot's personal equipment. The two organizations shared management of
the overall flight operations, flight data analysis, test range support, and advanced
planning.
The many theoretical studies, wind tunnel tests, and lifting body flights that
NASA conducted or sponsored in 1958-1968 proved the feasibility of an advanced
reusable spacecraft (or space transportation system, as it was being called in the late
1960s) based on the gliding reentry mode. Feasibility studies initiated by several
NASA centers looked at such refinements of the lifting body concept as increasing
its size to accommodate a larger crew and payload. Although NASA Headquarters
officials decided in 1966 not to approve an orbital flight test of the lifting body con-
figuration,* the extensive flight test program with the M2, HL-10, and X-24 series of
vehicles gave pilots and designers experience with developing improved procedures
and mechanical controls for reentry and landing maneuvers that some future-
generation spacecraft would surely require.
At NASA Headquarters, Milton B. Ames, director of OART's space vehicle
systems directorate, had overall responsibility for the lifting body program.
Langley's Eugene S. Love and Ames's Alfred Eggers and Clarence A. Syverston
played key roles in designing and testing lifting body configurations. The team at the
Flight Research Center, always a small group, was led by John McTigue. NASA
pilot Milton O. Thompson played an important role throughout the program as
pilot, researcher, and manager.l°
*It was not clear at this time what direction the post-Apollo manned program would take, and agency
officials were hesitant to invest in costly manned projects beyond the use of available Apollo hardware
and technology.
454 NASA HISTORICAL DATA BOOK
Table 4-68.
Chronology of Lifting Body Development and Operations
Date Event
Summer 1952 NACA engineers at Ames Aeronautical Laboratory began wind tunnel ex-
periments with several possible configurations for spacecraft, including a
gliding craft. Their conclusion was that a blunt-bodied vehicle rather than a
sharp-nosed one would survive the heat of atmospheric reentry.
1954-1955 Specialists at Ames conducted theoretical analysis and wind tunnel research
on the impact of reentry heating on hypervelocity missiles.
1956-1957 NACA engineers at the Langley, Lewis, and Ames laboratories carried out
feasibility and design studies in cooperation with the Air Force Air Research
and Development Command. The spacecraft design most favored was a flat-
top round-bottom configuration. (In a January 1957 summary report in
which the Ames people described this configuration, a minority report from
Langley favoring a nonlifting spherical capsule was included.)
June 10-13, 1957 At an American Rocket Society meeting, Alfred J. Eggers, Jr., a research
scientist at Ames, compared ballistic, skip, and glide vehicles, concluding
that a blunt-nosed slender vehicle with low-aspect-ratio delta wings (highly
swept, blunt leading edges) and a vertical tail would be most suited for
manned spaceflight.
Mid-late 1957 Realizing the glider configuration would be too heavy for existing launch
vehicles, Eggers revised his design to combine features of the ballistic and
glider crafts. The result was a semiballistic vehicle, blunt but with a certain
amount of aerodynamic lift, with a nearly flat top and a round bottom for
heat protection. This design was known as the M-I.
Oct. 15, 1957 At a NACA conference at Ames, three schools of thought were evident re-
garding the shape a manned spacecraft should take: (1) a delta-wing flat-
bottom glider (favored by many at Langley)*; (2) a ballistic capsule (con-
sidered by the Pilotless Aircraft Research Division of Langley to be the
quickest solution to finding a workable-launchable-configuration);_ and
(3) a compact low lift-to-drag vehicle with little or no wings and a blunt nose
(Eggers's M-I design).
1958-1960 Specialists at Ames continued testing models of lifting bodies in wind tunnels
and in the atmosphere entry simulator, continually refining the designs.
April 11-14, 1960 An Air Force-NASA Joint Conference on Lifting Manned Hypervelocity and
Reentry Vehicles was held at Langley Research Center.
1961-1962 Robert Dale Reed at NASA's Flight Research Center (FRC) built small
models of the M-I design and demonstrated the possibility of towing a
lightweight lifting body for testing purposes.
Spring 1962 Personnel at Langley began to study a lifting body configuration they called
HL-10.
Summer 1962 FRC was planning to construct several lightweight full-scale glider vehicles
for a lifting body flight test program.
Oct. 1962 FRC management approved the construction of a test-flight model of the
M-I; it was designated the M2-FI. Fabrication began in-house with the
assistance of Sailplane Corporation of America.
March 1, 1963 An attempt to ground-tow the M2-FI was unsuccessful because of its poor
lateral control.
March 1963 The Air Force proposed to NASA that the two agencies jointly manage the
Air Force X-20 program.
ADVANCED
RESEARCH
ANDTECHNOLOGY 455
Table 4-68.
Chronology of Lifting Body Development and Operations (Continued)
Date Event
April 5, 1963 The M2-F1 was ground-towed successfully for the first time.
Aug. 16, 1963 The M2-FI was carried aloft to 4000 meters on a C-47 and released for its
first glide to a controlled landing.
Dec. 18, 1963 Langley personnel suggested that the center sponsor a study of hypersonic
lifting vehicles with propulsion systems.
Jan. 7, 1964 NASA established an Ad Hoc Committee on Hypersonic Lifting Vehicle with
Propulsion.
Feb. 19, 1964 FRC issued a request for proposals for developing two advanced lifting
bodies.
April 14, 1964 A subpanel for coordinating manned lifting reentry vehicle studies was
established by the Manned Space Flight Panel of the Aeronautics and
Astronautics Coordinating Board (AACB).
April 20, 1964 A project approval document for the lifting body program was signed by
NASA Headquarters officials.
April 21, 1964 Norair Division of Northrop was chosen by NASA to build two advanced
lifting bodies-one M2 and one HL-10-for a flight test program (contract
awarded on June 2, 1964).
Summer 1964 NASA engineers conducted design studies for incorporating the XLR-I 1 jet
engine into the lifting bodies being constructed.
June 18, 1964 The AACB ad hoc committee on lifting reentry vehicles submitted their final
report.
Nov. 11, 1964 Ames Research Center issued a request for proposals for a feasibility study of
lifting body "space shuttle" vehicles with emphasis on aerodynamic
characteristics.
Feb. 1, 1965 FRC issued a request for proposals for two preliminary feasibility studies for
a manned lifting reentry vehicle.
March 26, 1965 Ames issued a request for proposals for a study of the protective equipment
required on a "space shuttle" lifting body.
April 19, 1965 A NASA-Air Force agreement on testing the M2-F2 and HL-10 was signed.
April 30, 1965 FRC awarded McDonnell Aircraft Company and Northrop contracts for
feasibility studies for a manned lifting body flight program.
June 15, 1965 A roll-out ceremony was held at Northrop for the M2-F2.
Jan. 1966 Langley issued' a request for proposals for a study on how the size of a lifting
body would influence research potential and project costs.
March 23, 1966 The first captive flight with the M2-F2 attached to a B-52 took place at FRC.
April 8, 1966 NASA selected the Martin Company to study the costs, crew size, and com-
plexity of a flight research program that used a manned lifting body.
April 18, 1966 NASA Headquarters decided not to proceed with plans for an orbital flight
test of a lifting body configuration, as had been suggested by the project per-
sonnel.
July 12, 1966 The M2-F2 successfully performed its first flight; it was released from a B-52
at 14 000 meters.**
Dec. 22, 1966 The HL-10 successfully performed its first flight at FRC. By this time, the
M2-F2 had been flown 14 times.
456 NASAHISTORICAL
DATABOOK
Table
4-68.
Chronology
ofLiftingBodyDevelopment
andOperations
(Continued)
Date Event
May10,1967 Duringthe16thM2-F2 testfight,thepilotwasforcedto makea
350-kilometer-per-hour
landingwiththelanding gear
up;thecraftrolled over
sixtimes,
injuring
thepilot.Thevehicle wassubsequently rebuilt asthe
M2-F3.
July11,1967 MartinCompany'sX-24
(SV5-P)liftingbody sponsored bytheAirForce was
rolled
outforinspection.
NASA was to participate in flight tests at FRC.
Nov.7,1967 The NASA-Air Force agreement was extendcd to include testing of the
X-24A.
March
1968 NASA Headquarters gave its authorization to restore the damaged M2-F2.
Feb.-April
1968 The X-24A underwent wind tunnel tests at Ames.
March
15,1968 Flights resumed with the HL-10 after the craft had been modified to improve
its stability.**
Oct.23,1968 First attempt to fly a powered HL-10 failed because the XLR engine shut
down prematurely.
Nov.13,1968 First successful powered flight of the HL-10 took place at FRC.
Dec.
9,1968 The HL-10 took its 14th flight.
*This design would become the Air Force X-20 lifting body. Northrop was interested in pursuing this
concept. The Martin Company was the firm finally selected to build the lifting body configuration.
"[With modifications, this design became the Mercury truncated cone flown by NASA.
**See table 4-72 for a flight log of M2-F2 and HL-10 activity.
Table 4-69.
M2-F1 Lifting Body Characteristics
Shape: 130-degree half-cone body with a blunt nose and vertical tail fins
Dimensions (m):
Length: 6.1
Width: 3.96
Height: 3
Weight (kg): 513
Construction: Plywood, tubular steel, fiberglass
Controls: 2 vertical rudders for yaw; 2 trailing-edge flaps for pitch; 2 elevons working in syn-
chronization for pitch and in opposition for roll
First Flight:
Ground-tow: April 5, 1963
Air-tow: Aug. 16, 1963
Times flown:*
Ground-tow: 400
Air-tow: 100
Test pilots: Milton O. Thompson, Charles Yeager, William H. Dana, Fred Haise, Bruce A.
Peterson, Tom Millick
Cognizant ARC (design)
NASA Center: FRC (flight testing)
Program manager." Robert Dale Reed
Project leader: Vic Horton
Contractor: Sailplane Corporation of America, hull
Mode of operation: Ground-towed or air-towed (C-47)
Table 4-71.
HL-10 Lifting Body Characteristics
Shape: Half-cone body (round top, flat bottom) with blunt nose and three vertical tail fins
Dimensions (m):
Length: 6.75
Width: 4.597
Height: 3.48
Weigh t (kg): 2400 (with water ballast test tanks full, 4100)
Construction: Aluminum
Controls: Thick elevon between each fin and center fin for pitch and roll; split rudder on
center fin for yaw and speed brake
First flight: Dec. 22, 1966
Last flight: July 17, 1970
Times flown: 37
Test pilots: Bruce A. Peterson, Jerauld R. Gentry, John A. Manke, William H. Dana, Peter
Hoag
Cognizant LaRC (design)
NASA Center: FRC (flight testing)
Program manager: John McTigue, FRC
Contractor: Northrop Corporation, prime
Remarks: In the fall of 1968, an XLR-I 1 engine was installed to give the HL-10 the capability
of powered flight (it was still launched from a B-52, however); the first powered
flight took place on October 23, 1968, but the attempt failed because the engine shut
down prematurely; a second attempt on November 13, 1968 was successful.
Mode of operation: Released in mid-air from under the wing of a B-52
458 NASA HISTORICAL DATA BOOK
Table 4-72.
MS-F2 and HL-10 Flight Log, 1966-1968
1966
1967
1968
*Vehicle letter code plus flight number of that particular vehicle plus B-52 carrier flight number
(M = M2-F2 and H = HL-10).
tThe altitude at which the lifting body was released from the B-52 carrier.
posure to the harsh environment of space, and atmospheric reentry. Private com-
panies were seldom interested in making one-of-a-kind or extremely-limited-
production items, and university research in electronics was not expanding at a fast
enough rate. When Albert J. Kelley was appointed NASA's first director of elec-
tronics and control, he was charged with assessing the agency's needs and
capabilities in basic electronics research and then proposing whatever steps would be
necessary to ensure that all elements of the space program could be satisfied by in-
house competence.
Not surprisingly, Kelley's fall 1962 report called for a significant increase in elec-
tronics research within NASA. Rather than step up electronics research at the
several NASA centers that had requirements in this field or assign a particular center
the role of coordinator of electronics research in addition to its other functions,
Kelley recommended that a new research facility be established that would be
dedicated to electronics. Electronics was too important to become an appendage to
some existing center, and many specialists- managers and technical people-agreed
that electronics work would be most successful if it were centralized in one location.
This new center would be capable of providing agencywide leadership and act as an
information channel for new requirements and new data. Administrator James E.
Webb agreed with Kelley's analysis, but also was acutely aware of the possible
political problems that a proposal for a new NASA center might bring. NASA did
not immediately request funds for the new facility in the FY 1964 budget (which was
being prepared in the fall of 1962), but planned to reprogram from other sources the
money it might need in the early phases of the new center's development (estimated
at $5 million for the first year). Selecting a prime site for the research center was not
difficult, but getting the site approved was a long, often unpleasant affair. Webb,
Kelley, and others agreed that Boston offered the best environment for an elec-
tronics center. MIT, Harvard, and many industrial concerns that also conducted
electronics research would be close by, which would contribute to a productive
research and development atmosphere. Members of Congress, however, heatedly
argued for other sites and delayed approval for NASA's new center until spring
1964.11 The Electronics Research Center (ERC) was formally activated on
September 1, 1964 in Cambridge, Massachusetts.*
The Electronics Research Center, with Winston E. Kock as director and Albert
Kelley as deputy director, parceled the research tasks into several logical divisions:
systems, components, guidance and control, instrumentation and data processing,
and electromagnetic research. At headquarters, Francis J. Sullivan became OART's
director for electronics and control. Reporting to the director were chiefs for
guidance and navigation (later guidance and control), control and stabilization (later
requirements and systems), communications and tracking (later microwaves and op-
tics), and instrumentation and data processing; electronics technology and com-
ponents was a fifth division added in 1968.
All NASA centers participated to some extent in electronics research or compo-
nent testing, with ERC serving as the prime investigator, coordinator, and clear-
inghouse.t ERC worked closely with its many contractors as new components were
* ERC absorbed NASA's North Eastern Office, which since August 14, 1962, had acted as the agen-
cy's liaison with industry in the northeastern states.
J Because of post-Apollo budget reductions, NASA was forced to close ERC in 1970. The facilities
were transferred to the Department of Transportation.
ADVANCED RESEARCH AND TECI4NOLOGY 461
developed and tested to meet specific project needs and as basic research was ex-
panded to include such new fields as microwaves and optics. When test conditions
could not be adequately simulated in the laboratory, OART funded flight projects
to verify new hardware or theories. These included Project RAM (Radio Attenua-
tion Measurements), with two flights in the 1958-1968 period, SCANNER, and
other small experiments sent aloft on sounding rockets or incorporated into satellite
payloads on a noninterfering basis. Most of the research conducted in the electronics
and control program was funded by supporting research and technology monies.
From the initial planning for manned lunar missions and long-life scientific
satellites, it was obvious that launch vehicles and spacecraft would have to be
equipped with instruments that would stabilize them during all phases of flight and
guide them, either automatically or manually, to their destinations. Guidance
systems research was directed toward designing simple, lightweight, reliable sensors,
reference elements, and associated components that made up an onboard guidance
system. By studying sensors and control mechanisms, control systems researchers
sought to optimize flight stabilization techniques, improve visual displays, and
develop adaptive automatic controls. Personnel at several NASA centers worked in
this area of research. At the Electronics Research Center two laboratories supported
guidance and control studies: the Guidance Laboratory and the Control and Infor-
mation Systems Laboratory.
Work on guidance systems was generally divided among four categories: inertial
reference sensors and systems, navigation techniques and displays, electromagnetic
sensors, and guidance theory and trajectory analysis. Work on developing improved
gyroscopes (cryogenic and electrostatic) was going on at Marshall Space Flight
Center and at the Jet Propulsion Laboratory before the projects were transferred to
ERC. The electrostatic gyro was flight-tested in aircraft in 1968. The sun, stars, and
planets, primary targets for space navigation and reference systems, are located
automatically by onboard electromagnetic sensors or electro-optical star trackers or
manually with hand-held sextants. Finding the simplest and most reliable systems
for navigation on a manned flight was a major goal of the 1960s. In addition, several
experiments were performed that measured the radiance characteristics of earth's
horizon to serve as a basis for developing highly accurate navigation and attitude
control sensors.
Three major tasks faced control systems specialists: research into very high-
performance automatic control systems necessary to achieve the precise pointing
characteristics required of communication satellites, development of manual control
systems in which the crew played an active part, and furthering the study of control
and information theory. One important development in this area was the control
moment gyro, a momentum storage device used to stabilize the Apollo telescope
mount (which became a major experiment and structural element on Skylab) or
other large spacecraft. Gravity gradient stabilization (as employed by some Applica-
tion Technology Satellites) also was investigated, at the Air Force's suggestion.
Mathematical modeling was used by researchers in their analysis of pilot per-
formance with different manual control systems and various information display
devices.
462 NASA
HISTORICAL
DATABOOK
for data handling and processing, on the ground and onboard spacecraft. Computer
technology was forced to advance rapidly with the space program. In the early
1960s, NASA specialists used computers to calculate trajectories or to control a
launch, but by the end of the decade they required a system that could process and
store the millions of bits of information per second that a television camera could
produce. In addition to lightweight high-performance computers, the agency needed
high-capacity onboard data storage devices. Researchers also looked for ways to
compress data mathematically so that it could be transmitted in less time. A long-
range research task in this field was the development of optical techniques for
spacecraft computer memories. Automated flight-failure warning systems for air-
craft also were under study. Another group of experts monitored man-computer in-
teractions. In addition to work at NASA's other centers, ERC set up a Computer
Laboratory to conduct basic and applied research to meet computer and data proc-
essing requirements of future NASA missions.
Reliability was the chief concern of researchers working in the techniques and
components field. The technology of microelectronics and the materials and proc-
esses used to fabricate the components of a microelectronic system were of special
interest. These specialists also developed test procedures for inspecting parts made
by contractors and methods for analyzing electrical failures. Research to extend the
reliable lifetime of parts was under way, as well. Work at ERC's Electronics Com-
ponents Laboratory was divided into four branches: solid-state, materials, vacuum
devices, and electromechanical.
Improved and new electronic components were tested on almost every NASA
flight project, as were new techniques for tracking, communications, and data proc-
essing. However, proving some minor new electrical part or system was hardly ever
listed as a prime mission objective. But in addition to early tracking experiments
designed for Beacon-Explorer satellites (S-66, Explorer 22, and Explorer 27), three
flight experiments in the 1958-1968 era were linked to the electronics and control
program.
Project SCANNER. The objective of Project SCANNER (also called Horizon
Definition Research Project) was to make detailed measurements of earth's horizon
radiation profile and to determine the existence of relatively stable gradients in the
profile that could be used to design precise horizon sensors. Project SCANNER was
undertaken as an extension of laboratory research on horizon characteristics to
verify theoretical predictions of the existence and nature of radiation gradients. Two
ballistic flights, launched from Wallops Island in 1966 by modified Scout launchers,
measured the energy radiated from the horizon.* The data collected allowed re-
*The Air Force was conducting similar experiments with the support of the Ohio State University
Research Foundation. The Air Force planned six Trailblazer (Air Force designation for its Scout launch
vehicle and the same vehicle used by NASA for SCANNER) flights for 1966-1967.
464 NASA HISTORICAL DATA BOOK
Table 4-73.
Project SCANNER Characteristics
Flight 1 Flight 2
Table 4-74.
Project RAM A and B Characteristics
RAM A-1 RAM A-2 RAM B-1 RAM B-2 RAM B-3
Date of launch Aug. 30, 1961 Feb. 21, 1962 Sept. 21, 1962 May 28, 1963 April 10, 1964
(location): (WI) (WI) (Wl) (WI) (WI)
Launch vehicle: Hybrid vehicle sometimes hybrid vehicle sometimes called RAM Bt
called RAM A*
Weight (kg): approx. 34 approx. 34 80 112 112
Shape: hemispherically blunted blunt-cone cylinder
9 degree half-angle cone
Dimensions (m):
Length: 3.7 (with the 4th stage) 1.7
Date of reentry: Ballistic trajectories
Cognizant NASA LaRC
center:
Project manager: Theo E. Sims
Objective: To explore the communications blackout problem experienced during
spacecraft reentry at velocities up to 5500 meters per second.
Results: All experiments except B-1 returned data as expected; RAM B-I was unsuc-
cessful because the launch vehicle's second stage malfunctioned.
*This four-stage vehicle consisted of a Castor XM 33E3 first stage with two auxiliary Recruit XM 19
engines, two XM 45 stages, and another Recruit XM 19 as the fourth stage. It was 19.8 meters tall and
weighed 6500 kilograms.
tThe Ram B vehicle had three stages: a Castor E-8 first stage, an Antares (X-254-AI) second stage,
and an Alcor (A J-10) third stage. Launched by the rail method, the vehicle was 12.8 meters tall and
weighed 6000 kilograms. It was similar to the Air Force Blue Scout.
466 NASA
HISTORICAL
DATABOOK
Table
4-75.
Project
RAMC Characteristics
RAMC-1 RAMC-2
Date of launch (location): Oct. 19, 1967 Aug. 22, 1968
(Vii) (WI)
Launch vehicle: Scout Scout
(S-159C) (?)
Weight (kg): 117 120
Shape: hemispherical cone
Dimensions (m):
Length: 13.9
Largest diameter: 0.66
Smallest diameter: 0.3
Date of reentry: Ballistic trajectories
Cognizant NASA center: LaRC
Project manager: Theo E. Sims
Contractor: Ling-Temco-Vought, systems integration
Objective: To explore the communications blackout problem experienced during
spacecraft reentry at velocities up to 8200 meters per second.
Experiments: VHF telemetry transmissions
X-band transmissions
L-, S-, and K a- band transmissions (C-2 only)
water injection (C-1 only)
Langmuir probe
Results: All experiments returned data as planned.
take the medical and human factors work that was required.* In the late 1950s,
NASA managers had no precise idea as to what the future held for the manned pro-
gram and, therefore, had given little thought to the advanced research that would be
needed for future manned systems; emphasis was on Mercury and today's re-
quirements.
Faced with the need to coordinate the Space Task Group's biomedical activities
with NASA Headquarters program planning and prompted by advice from his staff
and special advisory groups (and charges from academia that basic research in
biology was being ignored), NASA Administrator T. Keith Glennan sought to cen-
tralize and strengthen the agency's life sciences program by creating an Office of
Life Sciences Programs in March 1960 (on par with the Office of Space Flight Pro-
grams). But the experiment was short-lived. The office was abolished in August 1961
for several reasons: lack of support, financial and managerial; unclear lines of
authority; and no precise goals for the future. An agencywide reorganization in
November 1961 in response to a major expansion in the scope of the manned pro-
gram gave bioscience a more secure niche as part of the Office of Space Sciences. t
The Office of Manned Space Flight (OMSF) was given authority for aerospace
medicine. Advanced human factor research, however, was not given a place in
OART until July 1962 (see fig. 4-1). This tripartite organization of the life sciences
would survive through the rest of the agency's first decade, but not without a great
deal of destructive competition between bioscience (OSSA) and human factor
systems (OART) for limited funds and managerial support. And relations between
the human factor researchers and OMSF's biomedical people was seldom an easy
one. To make matters worse, some members of Congress always suspected that
NASA's research in advanced human factor systems only duplicated that being con-
ducted by the Air Force, while the Air Force felt it was competing with the civilian
agency for dwindling research dollars. It was a difficult set of circumstances under
which to work, but NASA's advanced human factor specialists did manage to con-
tribute to the lunar exploration program and to the design of advanced systems for
spacecraft and aircraft.
The basic premise assumed by researchers in OART's human factor systems
program was that man was a critical component of the spacecraft; together they
were a man-machine system. Research activities fell into four categories. (1) Man-
*The Air Force had long been interested in aerospace medicineand human engineering.A depart-
ment of space medicinewas establishedin 1950at the USAF Schoolof AviationMedicine,Wright Air
Force Base. In the early 1950sat the Aviation(later Aerospace)MedicalLaboratory at Wright-Patterson,
researchers were investigatingthe possible effects of spaceflight on man. At the AeromedicalField
Laboratory at Holloman Air ForceBasein 1948,specialistsbegan theirinvestigationsof the effects that
the space environment would have on subhuman organisms.Although the Navy had little interest in
spaceflightbefore 1957,three Navyinstitutions wereconductingresearchthat would proveapplicableto
the space program. The NavalSchool of AviationMedicine,the Navy'scenter for flightsurgeontraining,
sponsored studies of the effectsof high stress and extremeenvironmentson pilots. Biomedicalresearch
and development work was conducted at the Aviation Medical Acceleration Laboratory (human
research) and at the Naval EquipmentCenter (biotechnology).
tSee also chapter 3, pages 252-62,for more information on the OSSAbiosciencesprogram.
468 NASA HISTORICAL DATA BOOK
machine integration studies were concerned with "critical points of contact of man
with his vehicle," that is, the interfaces that "involve man's health, comfort, sur-
vival, observation, decision-making, integrative and manipulative skills," and the
ways "in which man's limitations may affect this system." Of particular interest were
studies of how well an astronaut could perform "routine" tasks outside the
spacecraft and on the lunar surface. At Langley, specialists simulated a one-sixth
gravity environment to evaluate man's ability to work and use tools on the moon. At
the Manned Spacecraft Center, neutral buoyancy simulators were used in training to
determine the possible impacts of weightlessness on crew activity. Requirements for
long-term interplanetary and lunar bases was another topic of interest, as was air-
craft safety. (2) Biotechnology, the design and engineering of life support systems,
protective equipment, information displays, communications devices, and controls
for manual operations, was an area in which the engineer and the medical specialist
worked closely. These experts determined what effect man's needs would have on
spacecraft design. Space suits also came under this group's purview, along with port-
able life support systems for extravehicular activity. The most visible of
NASA ADMINISTRATOR I
I !
OFFICE OF OFFICE OF MANNED
i_mmmo ADVANCED RESEARCH
SPACE SCIENCE SPACE FLIGHT
AND TECHNOLOGY
I I 1
DIRECTOR,
DIRECTOR, DIRECTOR, DIVISION OF
DIVISION OF
BIOSCIENCES BIOTECHNOLOGY AND
AEROSPACE
DIVISION HUMAN RESEARCH
MEDICINE
I !
I
I
Figure 4-1. NASA Life Sciences Elements, August 1962. * The reorganization of 1961-1962 created
three separate, functionally independent life sciences components and placed them under the manage-
ment jurisdiction of three different program office administrators.
* From John Pitts, The Human Factor: Biomedicine in the Manned Space Program to 1980, NASA Sp-4213
(Washington, 1985), p. 79.
ADVANCED
RESEARCH
ANDTECHNOLOGY 469
biotechnology projects was the search for a regenerative life support system.
Langley personnel were testing a closed regenerative system built by General
Dynamics/Astronautics in the late 1960s capable of housing a crew of four for 100
days. (3) Human research was perhaps the most general category of the four. The
objective here was to understand the physiological and psychological reactions of
man to long-term exposure to the hostile environment of space and the rigors of
flight, and to predict how these reactions would affect his performance and well be-
ing. The phenomena under examination were many: zero gravity, extreme accelera-
tion forces, vibration, solitary confinement, radiation, artificially-produced at-
mospheres. Radiobiology and acceleration research were of special importance.
Researchers also investigated how lengthy space missions would affect metabolism,
nutritional needs, and the cardiovascular system. (4) The final area of research was
called advanced concepts, but as all OART's work was "advanced" we can take this
title to mean research on systems that would require even greater advances in the
state of the art. Bionics and cybernetics were among the fields studied in the search
for new ways to further integrate man into the operational systems of spacecraft and
aircraft. Inflatable space suits and direct eye or nerve-impulse control over
spacecraft instruments are examples of futuristic concepts under study in 1964-1968.
The human factor systems team did not sponsor any major flight projects, but it
did have funds for small biotechnology flight experiments to supplement the
laboratory work conducted at Ames, Langley, the Manned Spacecraft Center, and
elsewhere.* These experiments (testing new components, observing the effects of a
particular environment on a subhuman organism, evaluating some new material)
were flown by sounding rockets, balloons, and high-speed aircraft or on satellites
and manned flights where the configuration allowed. One project involved the col-
lection of physiological data from a large number of individuals who spent long
periods of time under stressful conditions representative of those encountered dur-
ing spaceflight. For several months, students at the Air Force Aerospace Test Pilots
School at Edwards Air Force Base wore special instruments that monitored certain
body systems. With these data, specialists developed new standards for "normal"
heartbeat, blood pressure, and respiration for astronauts functioning for prolonged
periods under stress.
Eugene B. Konecci was OART's first director for human factor systems
research, taking the job in July 1962. He strongly favored the systems approach to
solving the life sciences problems of manned spaceflight. He viewed man and the
vehicle as individual total systems made up of numerous subsystems. The ultimate
object of life sciences research and development, as Konecci saw it, was to optimize
the integration of man and spacecraft in terms of their subsystems. Orr Reynolds,
director of OSSA's bioscience program, saw life sciences research on a more general
and purely scientific scale. These two men, with their basic academic disagreements,
competed for funds and facilities; there was little cooperation between the two
groups. Walton L. Jones took over the human factor systems post in October 1964.
Answering to the director were chiefs for man-system integration, biotechnology,
human research, and advanced concepts.
*John Pitts in The Human Factor argues that Ames Research Center with its special life sciences
facilities more directly supported bioscience investigations than human factor research.
470 NASA HISTORICAL DATA BOOK
In the 1960s, NASA's advanced planners were predicting that future spaceflight
projects would send increasingly heavy payloads on lengthy interplanetary and lunar
missions. To send manned spacecraft to the outer reaches of our solar system and to
support lunar and orbital laboratories, NASA would require boosters much more
powerful than the 1960s-era chemical rockets plus lightweight onboard power
systems that produced megawatts of electricity. Research leading to advanced power
and propulsion systems, originally under the direction of NASA's radioisotope vehi-
cle offices (see chap. 1), was assigned to OART in 1961. Larger chemical rockets,
more efficient solar cells, solid- and liquid-core nuclear reactors, generators, and
spacecraft stationkeeping propulsion devices were among the topics investigated by
several OART divisions. Most of these projects were expensive, long-term, and com-
plex. They often required close coordination with other government agencies, and
usually the technology under development was not applicable to any ongoing flight
projects. The great expense and the lack of specific requirements for the new systems
made this field difficult to defend against the scrutiny of budget conscious managers
and members of Congress. But if the U.S. wished to continue its role as a peaceful
space-exploring and space-exploiting nation, NASA would have to initiate in the
1960s research that would lead to the development of new technology it would re-
quire in the 1970s and 1980s. As NASA managers and mission planners had
discovered with the Centaur upper stage, propulsion systems required particularly
long development lead times.
The changing management structure of OART's power and propulsion divisions
reflected the agency's changing attitude toward different energy sources. After
OART was established in 1961, Harold B. Finger became director of nuclear systems
(in addition to being manager of the joint Atomic Energy Commission-NASA Space
Nuclear Propulsion Office, which he had headed since August 1960), and W.H.
Woodward became director of propulsion and power generation. In 1963, Finger
and Woodward's offices joined forces in a new nuclear systems and space power
division, while authority for advanced chemical propulsion went to the Adelbert O.
Tischler in a new chemical propulsion division. The next year Finger and Wood-
ward's operation was streamlined somewhat, and in 1967 the division name was
changed to space power and electric propulsion (see table 4-76). Finger, Woodward,
and Tischler were all former NACA propulsion specialists who had spent their early
careers at the Lewis Flight Propulsion Laboratory before coming to Washington as
headquarters managers.
Advanced propulsion experts were looking to three fields for systems that would
provide power to boost spacecraft weighing up to 4500 kilograms to escape velocity.
In addition to operating lunar ferries that could transport some 1.8 million kilograms
of payloads over a six-year period between earth and the moon, NASA wanted to send
orbiters to all the planets in the solar system and heavy landers to Mercury, Venus, Mars,
Jupiter's moons, and Pluto, and eventually men 'to Mars (see table 4-77). Electric upper
stages offered one solution for sending these large payloads on their way. Teamed with
conventional chemical or advanced nuclear boosters, an electric propulsion system could
be used very efficiently in a zero gravity environment. Electric propulsion was also be-
ing considered for spacecraft onboard propulsion (for stationkeeping and attitude con-
ADVANCED RESEARCH AND TECHNOLOGY 471
Table 4-76.
Changing Organization of OART Advanced Propulsion and
Power Systems Divisions, 1961-1968
Nov. 1961-1962
1963-1968
Deputy Director, Nuclear Systems and Space Power (Woodward); office dropped in 1968
Assistant Director, Nuclear Power Systems (Shulman)
Assistant Director, Electric Thrusters Systems (Lazar)
Assistant Director, Vehicle Technology (Nuclear and Space Power Systems) (Novik); office dropped
in 1967
1961-1968
trol maneuver). During NASA's fh'st decade, electric systems such as these moved beyond
theoretical and laboratory studies to rudimentary hardware tests with Project SERT
(Space Electric Rocket Test). Experimental electric thrusters were carried on Applica-
tions Technology Satellites (ATS) payloads. Electric systems, researchers believed, could
be highly reliable and lightweight. A hybrid system that combined solar cells with elec-
tric propulsion hardware was also being studied in the late 1960s.
Table 4-77.
Booster Requirements for Advanced Missions
Type of Rocket
IB V IB V IB V
A. Lunar ferries
(1 800 000 kg total in
6 yr.)
Moon -- 35 - - 56 - - I00
B. 900-kg orbiters
Mercury 165 - 1 60 - 1 65
Venus R 130 - 1 30 1 - 55
Mars D 170 - 1 80 1 - 125
Jupiter, Ganymede D 590 - 1 250 1 -- 500
Jupiter i 100 No mission No mission
Saturn, Titan 850 - 1 600 1 - 1100
Saturn, outer ring 1000 - 1 900 - 1 1200
Uranus, Titania 1270 - 1 2000 - 1 2000
Uranus 1490 - l 2000 No mission
Neptune, Triton 1850 No mission No mission
Neptune 2170 No mission No mission
Pluto B 2160 No mission No mission
C. 4500-kg landers
Mercury l D 410 m 75 -- 2 90
Venus 1 280 B 30 -- 1 40
Mars 1 260 R 90 -- 1 120
Ganymede - 1 550 m 250 -- 1 300
Titan - 1 780 B 700 -- 1 850
Titania - 1 1200 B 2000 -- 1 2000
Triton - 1 1740 No mission No mission
Pluto - 1 2030 No mission No mission
D. Manned Mars
roundtrips
Earth reentry
37 000 m/sec - 3 420 -- 4 420 -- 9 420
25 000 m/sec - 5 450 -- 14 420 -- 123 420
ADVANCED RESEARCH AND TECHNOLOGY 473
Electric Propulsion
Since it takes considerably less thrust to put a mass in motion once it is in zero
gravity, advanced researchers at NASA considered developing relatively low-power
electric propulsion systems for spacecraft. As an upper stage of a launch vehicle
(prime propulsion), an electric propulsion unit could boost a payload out of earth
orbit, and an onboard electric propulsion system could "fine-tune" spacecraft during
maneuvers or lift satellites to higher orbits (auxiliary propulsion). Prime and aux-
iliary propulsion systems are based on the same operating principle: electric power
generated by a solar or nuclear device is fed to a thruster system, of which there are
three kinds-electrothermal, electrostatic, and electromagnetic.* Electrothermal
thrusters, of which resistojets were the most highly developed example in the 1960s,
could produce specific impulses of thrust lasting 150 to 850 seconds. Electrostatic
and electromagnetic thrusters produced impulses lasting 3000 to l0 000 seconds. A
small resistojet was included on A TS 1 in December 1967, but it was damaged dur-
ing the mission. Evaluation of the system was inconclusive. Resistojets were tested
successfully in 1968 on later ATS flights, and a cesium propellant contact ion
thruster was carried on ,,ITS 4. Because the gravity-gradient-stabilized ATS
spacecraft had two very long booms, stationkeeping maneuvers were accomplished
with extremely low thrust (4.448 x 10 5 newtons) to minimize torque distrubances
to the booms.
OART specialists were suggesting in 1967 that the addition of a solar-electric
stage capable of 4 to 28 kilowatts of power to an Atlas-Centaur, a Titan IIIC, or a
Saturn IB-Centaur would greatly increase the payload capacity of these configura-
tions without adding much weight to the vehicle. In this concept, lightweight solar
arrays were the power source for the electric propulsion system, teamed with either a
resistojet or an electron-bombardment thruster. As with ion thrusters, electron-
bombardment thrusters develop thrust by accelerating charged particles. Although
the resultant thrust is not enough to lift the engine's own weight on earth, it is suffi-
cient in weightless, frictionless space to propel large payloads over vast distances at
, high speeds. In the late 1960s, researchers were striving for low specific impulses t
*Electrothermal thrusters produce heat by passing the propellant over a hot metal surface and ex-
panding it through a nozzle. Electrostatic and electromagnetic thrusters produce heat by accelerating the
propellant by means of electrical forces and reactions.
I Specific impulse is defined as the velocity imparted to the propellant divided by gravitational ac-
celeration.
ADVANCED RESEARCH AND TECHNOLOGY 475
and high efficiency. But electric propulsion was also recognized for its growth
potential. For example, a launch vehicle consisting of a nuclear booster and a
megawatt-class electric upper stage would reduce both mission time and launch vehi-
cle weight on some future manned voyage to Mars. At Lewis Research Center,
30-kilowatt and 150-kilowatt thrusters were being evaluated to determine if more
powerful electric propulsion systems were feasible. At the Jet Propulsion
Laboratory in California, specialists established a program in 1968 they called Solar
Electric Propulsion Systems Technology (SEPST) to find the best propulsion system
for unmanned planetary flyby spacecraft.13
Project SERT (Space Electric Rocket Test). SERT was an integral part of the
electric propulsion team's technology development program. SERT l's basic goal
was to prove that an ion beam could be neutralized by injecting electrons, thereby
producing thrust. Because researchers could not duplicate in the laboratory the exact
conditions of spaceflight that this test demanded, NASA Headquarters approved a
flight test of an electric propulsion engine, with the first launch scheduled for late
1962. With the transfer of the project from Marshall Space Flight Center to Lewis
Research Center in November 1961, the first mission was slipped to 1964, giving
engineers at Lewis and Hughes Research Laboratories more time to build the two
kinds of ion thrusters that would be tested. Lewis specialists constructed a mercury
electron bombardment thruster, and Hughes was responsible for a cesium contact
ion thruster. The summer 1964 ballistic test, which lasted 47 minutes, proved the
Lewis electron bombardment design; the cesium thruster, however, failed to
operate.* SERT1 demonstrated that the ion thruster concept would work. Plans for
repeat tests were dropped, but Lewis set SERT2 into motion shortly thereafter, with
official approval coming in the fall of 1966. SERT2, originally scheduled for a later
1968 launch, would demonstrate the long-term operation of electric thrusters in
space (two 1-kilowatt mercury bombardment ion engines powered by a 1.5-kilowatt
solar array) and provide information on how the propulsion system interacted with
other spacecraft systems. This earth orbital mission was launched on February 3,
1970.
Nuclear Propulsion
NASA's search for a nuclear-powered launch vehicle was one of the agency's
most controversial undertakings. It met both ardent support and disapproval in
Congress and was the subject of many debates in congressional committees, at the
Bureau of the Budget, and within NASA itself. The agency's managers recognized
that they should investigate how advances in atomic research would affect space
power and propulsion systems and how new atomic hardware could be applied to
NASA missions. In August 1960, NASA joined with the Atomic Energy Commis-
sion to form the joint Space Nuclear Propulsion Office to serve as an interface be-
tween the two agencies (see fig. 4-2). Thereby, NASA could monitor, evaluate, test,
*Subsequently, the Air Force flew a cesium contact ion thruster in a hardware development test,
which functioned as predicted.
476 NASA HISTORICAL DATA BOOK
and eventually adopt new propulsion and power technology developed by AEC. Ad-
vanced planners believed that for the post-Apollo period the agency would need
powerful boosters for manned interplanetary and solar system escape missions.
Nuclear propulsion systems, they reasoned, could provide 890 000 to 1 100 000
newtons of thrust.
The Air Force and AEC had long been interested in developing a nuclear rocket.
Calling their effort Project Rover, research was well under way on various nuclear
reactors at Los Alamos Scientific Laboratory and Livermore Radiation Laboratory
when NASA was established. In 1958, the civilian agency inherited the Air Force's
role in Rover, basically assuming responsibility for every aspect of the nuclear
rocket program except reactor research and engineering, which was AEC's domain.
The grand plan (see table 4-65) called for the development and ground-testing of in-
creasingly sophisticated reactors (Kiwi and Phoebus), a flight test of a nuclear upper
stage (RIFT), and the launch of a nuclear vehicle (NERVA). For several reasons--
expense, complexity, safety questions, lack of specific applications-funds for
nuclear propulsion were cut from the agency's budget request several times, slimm-
Table 4-78.
Date Event
July 17, 1961 Marshall Space Flight Center announced the selection of RCA's Astro-
Electronics Division as contractor for developing a payload capsule for flight
testing electric propulsion engines. Four flights were planned, with the first to
be launched in late 1962. Hughes Research Laboratories and Lewis Research
Center were developing engines to be tested on the spacecraft.
Nov. 1961 The electric propulsion project was transferred from Marshall to Lewis.
Summer 1962 NASA Headquarters officials signed the project approval document for
Project SERT (Space Electric Rocket Test).
Aug. 1962 Lewis issued a request for proposals for a 12-month research program to
develop and test an ion rocket engine system of the electron bombardment
ionization type.
Dec. 1962 The Air Force attempted to test an ion engine during a ballistic flight test; the
engine failed to start (engine built by Electro-Optical Systems, Inc.).
July 20, 1964 Launch of SERT 1 was successful; the Lewis engine performed as planned,
but the Hughes engine failed to respond to commands to start.
Oct. 16, 1964 A second SERT/-class flight was cancelled because the July experiment had
accomplished the program's basic goal.
Dec. 23, 1964 The Air Force successfully tested a cesium thruster in a ballistic test.
Oct. 4, 1966 Lewis was authorized to proceed with a SERT2 project, an orbital ion engine
test to last six months (1968). Lewis was assigned the task of designing two
engines for SERT2.
July 18, 1967 Lewis awarded various SERT2 systems contracts to Fairchild-Hiller Corp.,
Hughes Aircraft Corp., Westinghouse Electric Corp.'s Aerospace Electrical
Div., and Cutler-Hammer Corp.'s Airborne Instruments Div.
Feb. 1968 Lockheed Missiles and Space was awarded a contract for adapting the Agena
stage for use in SERT2.
ADVANCED RESEARCH AND TECHNOLOGY 477
ing the venture down from a flight hardware program to a technology research and
development project.
The reactor is the key component of a nuclear rocket propulsion system. The
nucleus of an atom is composed of particles held together by tremendous bonds of
energy, and when these bonds are broken the nucleus splits apart, or fissions. Great
quantities of heat and radiation are released when elements such as uranium or
plutonium are fissioned. When this activity takes place within a confined
space- such as rods within a graphite-lined container, a reactor* - the resultant heat
energy can be controlled and used to heat a propellant. The propellant, liquid
hydrogen, for example, is pumped through the reactor. Heated, the propellant ex-
pands and exits at a high velocity through a nozzle. During the 1960s, atomic re-
searchers searched for heat-resistant materials from which to construct the reactor
and sought to design a pumping system that could handle the very cold liquid-
hydrogen propellant. Other reactor configurations were considered, such as a
gaseous-core reactor and a tungsten solid-core reactor, but it was the graphite solid-
core reactor that captured most of the AEC and NASA's attention.
The Lewis Research Center in Cleveland, a participant in nuclear research as it
related to possible applications to aeronautics since the 1940s (as part of the Na-
tional Advisory Committee for Aeronautics), had acquired the Army's Plum Brook
nuclear research reactor. In 1958 when NASA began participating in the nuclear
rocket program, the AEC was building a reactor and the complex facilities needed to
test it in the deserts of Nevada on Jackass Flats. Plum Brook, therefore, did not play
a major role in the nuclear rocket program.
*Graphite, inexpensive and easy to fabricate, has the unique quality of gaining strength as the
temperature increases. However, hydrogen can erode the carbon from the graphite, causing it to collapse.
The graphite in a reactor would have to be covered by a coating of some protective material.
Table 4-79.
SERT 1 Characteristics
_oc
zw
ill
0:
DO
_1
tz:_
O_:
at7
o
I---
i-.- I--.
o-
w
"
m-_O,
_F-
o_ci
C_ F-- _r) F
_-_<_.i
fflz
ILl
a
c -
:
_
i
C
a._
_,
gC_
C
*_ _ I
I
L''-: O.l-
(/)Z
_,w _-I
a
! I
'<0
C_
'_z
>_
tu
_u
I
I
_ I
i I
I
w I
,a I zo
/"
_( ,,_z I Z*_ I- O0
OzO_
>z • _c_ . __
8 _ _-_ =-_ os I__1
_: _ / -"=_:'__>_:> "_ '
_,_/< I
0
ILl
O0 L---. _ -"
I '
_
"_Z
__0
•-r V_
= ,_
ADVANCED RESEARCH AND TECHNOLOGY 479
Kiwi A, the first step in AEC's reactor test program, was designed to
demonstrate that a high-power reactor could heat a propellant quickly and stably to
high temperatures, to establish basic testing procedures, and to determine the basics
of graphite-hydrogen interaction. Kiwi A (100-megawatt power level) passed its first
hot test* in the summer of 1959, convincing many that a nuclear rocket was possible.
During the two years that it took to develop and test Kiwi A, work was being con-
ducted simultaneously on the larger Kiwi B (1000-megawatt power level), which
would utilize liquid hydrogen as a propellant. A Kiwi B-class reactor would be
suitable for use in the upper stage of a launch vehicle.t AEC-NASA specialists saw
the development of a structurally sound reactor core to be their most urgent task and
pursued three new core concepts in 1960: Kiwi Bl, B2, and B4.** NASA's first hard-
ware task associated with the Kiwi B reactor was providing a turbopump that could
deliver liquid hydrogen to the reactor quickly and in great quantities without in-
creasing the temperature of the propellant through friction before it entered the
reactor. Before it gave up its part in Rover, the Air Force had assigned the develop-
ment of a pumping system to the Rocketdyne Division of North American Aviation,
but NASA favored assigning the pump to personnel at Lewis Research Center. At
AEC's request, however, NASA funded Rocketdyne's effort as a backup.
At this juncture, still smarting from the Soviet Union's early successes with
Sputnik, lawmakers, policy advisers, and technical specialists were closely examin-
ing the country's launch vehicle technology. Project Rover tt with its promiseofgreat
power-but very long lead time and high price tag-was considered less critical to
the immediate success of the U.S. space program than the development of large
chemical rockets. Rover's most visible supporter was Senator Clinton P. Anderson,
who came to the defense of the nuclear rocket program many times, capturing funds
for NASA's part in it when the budget situation looked bleakest. Chemical rockets
were a priority item for the 1960s, but many experts believed that future vehicles
would be powered by nuclear means. It was agreed in 1960 that NASA and AEC
should proceed with an incremental program leading to the development of a
nuclear rocket engine.* ° ° Harold B. Finger, of Lewis' compressor and turbine division
and a leader of that center's nuclear rocket study group, went to Washington to
manage the joint venture. In August 1960, the agencies signed a memorandum of
understanding establishing the Space Nuclear Propulsion Office. The next year
*"Hot" tests were conducted with the fuel cell in the reactor; "cold" tests were run without the fuel
cell to evaluate the nonnuclear components of the reactor.
tNASA planners reasoned it would be safer to use a nuclear reactor in an upper stage; an accident
with a nuclear booster on the launch pad would contaminate the area and endanger launch operations
personnel.
**The B4 was also called Phoebus for a time, a name that was adopted for an advanced graphite-
core reactor program (AEC) in the mid-1960s.
tt This designation was not used widely by OART; instead the program was referred to by the several
stepping stones that would lead to a nuclear rocket--Kiwi, RIFT, and NERVA.
*** AEC would continue to favor a higher priority program with operational capability by the late
1960s.
480 NASA
HISTORICAL
DATABOOK
Westinghouse'sturnto incorporate
thebasicKiwiB4coredesignintothecomplex
NERVAsystem.But NERVAhadbeendowngraded in December 1963by the
budgetcuttersontheeastcoastfroma flight-ratedengine projectto a research
pro-
ject.TherewouldbenoKiwi C. RIFThadbeencancelled altogether.
TheReactor-In-Flight-Test
wasto haveincludedfour flightsof the nuclear
stagewith a Saturnbooster.LockheedMissilesandSpaceCompany,studying
nuclearrocketdesignsince1957,hadbeenawarded acontractfor RIFT'sairframe
in June1962.Convair,Lockheed, the Martin Company, and Douglas Aircraft
Company, with funds from NASA, had conducted preliminary studies of a nuclear
flight test program in 1960; Lockheed and Convair did further work in 1961 for the
Marshall Space Flight Center's new Nuclear Vehicle Project Office. Marshall would
manage the development of the RIFT stage and integrate it into a Saturn vehicle.
During the first phase of their contract, Lockheed employees produced an engineer-
ing analysis development plan and test facilities definition that they hoped would
lead to the manufacture of 10 RIFT stages.* One of Lockheed's major objectives in
its early work was to determine how radiation might affect critical electronic in-
struments and vehicle materials. As with Kiwi, these tests would require special
facilities that would add greatly to the budget. An extensive, expensive complex
designated the Nuclear Rocket Development Station (NRDS) was proposed for
RIFT and NERVA in 1962. Its operation would boost NASA's nuclear rocket
budget request even higher. RIFT did not get beyond the paper and preliminary
component test phase; the construction of the development station, however, was
approved and built. Kiwi's failure and Washington's doubts that the country needed
this expensive nuclear rocket project brought about RIFT's cancellation in late 1963.
Lockheed's contract was terminated in February 1964.
NERVA faced the same doubters and its own unique technical problems. The
nuclear engine would require massive engine test stands, which were difficult to con-
struct and required a long lead time- like everything else connected with the nuclear
propulsion program. Because the NERVA contractors' pace was dictated by the
Kiwi team's success with finding a suitable reactor, Westinghouse and Aerojet never
got beyond preliminary studies for a flight-rated NERVA. When Lyndon B.
Johnson assumed the presidency, he was faced with balancing many demands on the
nation's treasury-an escalating war in Indochina, urban strife and racial unrest, the
Apollo lunar landing. Protecting South Vietnam from the communists of the north,
salving the cities' wounds, and getting an American astronaut to the moon were all
goals to which this country was committed. It was clearly not the time for ambitious
post-Apollo projects such as lunar bases and manned Mars landings that would re-
quire nuclear rockets. If NASA wanted to continue with a nuclear propulsion pro-
gram, it would have to be a modest one.
During the next several years, the AEC and NASA continued their experiments
with nuclear reactors, albeit at a much lower funding level. The two agencies' ad-
vanced propulsion experts made slow but sure progress in defining a nuclear system
that might be used some day to launch large payloads to Mars and beyond. This
steady, if plodding, pace was more to the liking of many NASA specialists (especial-
ly at Lewis) who had been disquieted by the brief but costly flurry of Project Rover.
* The RIFT stage was to be 24.4 meters long and 11.1 meters in diameter.
482 NASA HISTORICAL DATA BOOK
*Ground testing of NERVA experimental reactors and engines was completed in August 1969.
Table 4--80.
Chronology of Nuclear Propulsion Program
(Kiwi, RIFT, NERVA) Research and Development
Date Event
1945 At the suggestion of Manhattan Project participants, the Air Force Scientific
Advisory Board studied the possible use of nuclear propulsion for rocket
systems. No action was recommended.
June 1946 The Atomic Energy Commission's (AEC) Division of Reactor Development
requested the Applied Physics Laboratory (APL) of Johns Hopkins to study
the feasibility of nuclear propulsion.
luly 1, 1946 North American Aviation Corp. prepared "A Preliminary Study on the Use
of Nuclear Power in Rocket Missiles."
Jan. 14, 1947 APL's report concluded that a nuclear rocket was feasible, but expressed con-
cern over the associated technological problems and expense.
Feb. 7, 1947 An Air Force report investigated the "Feasibility of Nuclear Powered Rockets
and Ramjets" for the USAF MX-770 missile project. In preparing the report,
the authors investigated almost every major problem that would arise in
Project Rover.
Sept. 1948 An Air Force report recommended pursuing the development of a turbojet
rather than a nuclear rocket.
July 1953 R. W. Bussard of AEC's Oak Ridge National Laboratory authored a study
on "Nuclear Energy for Rocket Propulsion," rekindling Air Force interest in
the subject.
July-Dec. 1954 A series of meetings was held by the Weapons Div. of AEC's Los Alamos
Scientific Laboratory on the feasibility of developing nuclear rockets. The
laboratory's Reactor Division was also interested in the subject. A committee
was formed in October to look at proposals for utilizing nuclear energy for
rockets. The committee came to be known as the Condor Committee.
Oct. 18, 1954 The Air Force Scientific Advisory Board Ad Hoc Committee on Nuclear
Missile Propulsion convened to study application of nuclear reactors to space
propulsion. Presentations were made by industry on the design of turbojets,
ramjets, and nuclear rockets.
ADVANCED RESEARCH AND TECHNOLOGY 483
Table 4-80.
Date Event
Fall 1954 H. F. Bunze of the USAF Wright Air Development Center and Frank Rom*
of the National Advisory Committee for Aeronautics's (NACA) Lewis
laboratory briefed the Air Force Air Research and Development Command
on the design of a nuclear-powered ICBM, after which the Air Force re-
quested the AEC to study the subject. The AEC authorized a six-month
nuclear rocket propulsion study at Los Alamos and the Livermore Radiation
Laboratory.
March 1955 The Los Alamos and Livermore studies were presented at the Air Force
Scientific Advisory Board ad hoc committee's second meeting (studies
published in April 1955 as "The Feasibility of Nuclear-Powered Long Range
Ballistic Missiles," by Los Alamos, report LAMS 1870, and as "Nuclear
Rockets," by Livermore, report UCRL 4499).
April 15, 1955 Nuclear rocket divisions were formed at Los Alamos and Livermore.
Oct. 18, 1955 In their final report, the Air Force Scientific Advisory Board ad hoc commit-
tee reaffirmed its recommendation that development work begin on a nuclear
rocket.
Nov. 2, 1955 AEC approved programs at Los Alamos and Livermore to demonstrate the
feasibility of nuclear rocket propulsion. This effort became Project Rover.
The two laboratories pursued independent preliminary research on reactor
designs. The Air Force was considered the prospective "user agency" of any
hardware that was developed as a result of this project (Air Force manage-
ment of Rover was assigned to the Propulsion Laboratory at Wright Air
Development Center).
April 1956 The Department of Defense (DoD) Armed Forces Special Weapons Project
group conducted a two-week study to set 1959 as a target date for the
development of a nuclear rocket.
Spring 1956 The Air Force assigned property it owned in Nevada to the AEC for reactor
testing; Los Alamos chose a site on Jackass Flats, Livermore at Cain Springs.
May 18, 1956 The Air Force awarded a contract to Aerojet-General Corp. to provide non-
nuclear component support to Rover at Los Alamos.
July 15, 1956 The Air Force awarded a contract to the Rocketdyne Div. of North American
Aviation to provide nonnuclear component support to Rover.
Dec. 28, 1956 At DoD's request, the Armed Forces Special Weapons Project group con-
ducted a study to determine if the military advantages of a nuclear-powered
ICBM were commensurate with the great expense involved in its develop-
ment. The group's report indicated that there was no immediate application
for a nuclear ICBM but that the project should be continued for its possible
future applications. The feasibility of a reactor for nuclear propulsion could
be demonstrated by 1960-1961, according to thi s study.
Jan. 12, 1957 DoD suggested that it reduce the level of its support of the nuclear rocket
program. The group at Los Alamos began defining their first nuclear propul-
sion reactor, Kiwi A.
March 18, 1957 The AEC assigned Project Rover to Los Alamos and the nuclear ramjet proj-
ect to Livermore.
May 1957 Construction of reactor test facilities (Test Cell A) began in Nevada.
484 NASA HISTORICAL DATA BOOK
Table 4-80.
Chronology of Nuclear Propulsion Program
(Kiwi, RIFT, NERVA) Research and Development (Continued)
Date Event
Sept. 1957 Los Alamos held the first of a series of meetings to determine goals beyond
Kiwi A.
Winter 1957-1958 A Rover Coordination Group was formed representing the Wright Air
Development Center, Los Alamos, AEC's Albuquerque Operations Office,
Aerojet-General, and Rocketdyne. This group began planning for technical
support of Kiwi B ill early 1958 at its first meeting.
Jan. 22, 1958 The Joint Committee on Atomic Energy of the Congress held hearings to
review Project Rover.
June I1, 1958 The AEC requested that the Air Force increase its support of the develop-
ment of Kiwi B's turbopump and flow control system, which were to be built
by Aerojet-General and Rocketdyne.
Oct. 1, 1958 The executive order that created NASA also transferred responsibility for the
nonnuclear aspects of Project Rover from the Air Force to the new civilian
agency. NASA managers were of the opinion that Rover should be supported
as fast as the technology would allow. The AEC would continue to provide
technical direction of the reactor program within a broad framework of
guidance from NASA.
Late 1958 Fabrication of Kiwi A was near completion at Los Alamos; it was shipped to
Nevada and assembled there for testing.
April 1959 During a checkout test of Kiwi A's flow control system, the bellows pumping
the gaseous hydrogen ruptured, causing a fire. The testing schedule was
delayed.
July 1, 1959 Kiwi A passed its first hot test successfully (5 minutes at 78 megawatts), after
which it was disassembled and inspected.
Fall 1959 Because of the expense involved in developing it, a reactor called Dumbo
with a tungsten core was dropped from the test program. In its place, Los
Alamos introduced Kiwi A Prime (sometimes written Kiwi A_), which would
test Kiwi B's core design and protected fuel elements, and Kiwi A3, which in-
corporated some further design changes in the coating and core.
April 29, 1960 NASA awarded Rocketdyne a contract for a regeneratively-cooled nozzle for
Kiwi B.
Spring 1960 Assembly and checkout of Kiwi A Prime was begun in Test Cell A.
July 8, 1960 Kiwi A Prime was hot-tested (3 minutes at 85 megawatts). The results in-
dicated that the core design was not structurally sound.
Aug. 15, 1960 Martin, Douglas, Convair, and Lockheed began work on RIFT (Reactor-In-
Flight-Test) studies for Marshall Space Flight Center.
Aug. 29, 1960 NASA and AEC signed a memorandum of understanding establishing the
joint Space Nuclear Propulsion Office (SNPO).
Oct. 10, 1960 Kiwi A3 underwent a hot test (5 minutes at 100 megawatts) with results
similar to Kiwi A Prime's.
Feb. 2, 1961 NASA and AEC issued a request for proposals for the development of a
NERVA (Nuclear Engine for Rocket Applications) engine.
Table
4--80.
Chronology of Nuclear Propulsion Program
(Kiwi, RIFT, NERVA) Research and Development (Continued)
Date Event
May 25, 1961 President John F. Kennedy in a special message to Congress recommended a
supplement for Rover to be added to the FY 1962 budget (the development of
a nuclear rocket as part of an accelerated space and Atoms for Peace pro-
gram had been a plank in the Democratic platform during Kennedy's cam-
paign).
June 9, 1961 NASA and AEC selected Aerojet-General and Westinghouse as the builders
of the NERVA engine (the contract was effective on July 10). Aerojet-
General was the prime contractor, Westinghouse the reactor subcontractor.
July 1, 1961 Follow-on RIFT studies to determine a preliminary design were begun by
Martin, Douglas, Convair, and Lockheed for Marshall.
Summer 1961 SNPO field offices in Cleveland, Albuquerque, and Nevada were staffed.
Two Kiwi BI reactors were under construction. Designs for the cores of Kiwi
B2 and B4 were being studied.
Nov. 1961 During the final checkout of Kiwi BIA, a leak of hydrogen gas caused an ex-
plosion.
Dec. 1961 Kiwi BIA underwent a hot test (30 seconds at 300 megawatts). A leak of
hydrogen caused a large fire. The NERVA phase-one contract was com-
pleted. A structural weakness was found in Kiwi B2's hot-end graphite disc.
March 1962 After Kiwi B2 failed a preassembly test, it was redesigned. AEC personnel
began assembling Kiwi B4, but they encountered problems with this con-
figuration, too.
June 28, 1962 NASA awarded a contract to Lockheed to design and develop the RIFT
stage.
Sept. 1962 A Kiwi BIB hot test was run (a few seconds at 900 megawatts), during which
the core failed. Nonnuclear components of the reactor performed satisfac-
torily. Checkout of Kiwi B4A and assembly of B4B were begun.
Nov. 30, 1962 A Kiwi B4A hot test was conducted (a few seconds at 600 megawatts), during
which extensive core damage was suffered.
Dec. 7-8, 1962 President Kennedy was briefed on the nuclear propulsion program at Los
Alamos. As a result, he agreed to continue funding a test program, albeit an
abbreviated one, pending the results of the next reactor hot test. RIFT was
not to go beyond the study stage.
Jan. 1963 Because of the reactor failures and the importance given the next reactor hot
test by the president, SNPO reoriented the reactor test program. More em-
phasis was placed on component evaluation and cold tests, postponing fur-
ther hot tests until later in the year.
March 1963 Assembly of Kiwi B4A cold flow reactor was begun.
May 15, 1963 Kiwi B4A cold test was conducted, confirming that vibration had been the
cause of earlier core failures. Corrective redesign of B4B was initiated im-
mediately.
Table
4-80.
Chronology of Nuclear Propulsion Program
(Kiwi, RIFT, NERVA) Research and Development (Continued)
Date Event
Aug. 1963 A Kiwi B4B cold test was conducted, proving out the improved hot-end seal.
SNPO approved the resumption of hot testing.
Nov. 1963 Lewis Research Center (NASA) specialists began cold tests on another reac-
tor design at the Plum Brook Nuclear Rocket Dynamics Test Facility.
Dec. 1963 As a result of budget problems and the complex problems that were
associated with developing a nuclear rocket, Project Rover was downgraded
from a flight project to a technology development project. RIFT was can-
celled (Lockheed's contract was terminated in February 1964).
Sept. 24, 1964 NRX-A2 reactor was tested at high power for 6 minutes; gaseous hydrogen
was used as the propellant.
Oct. 15, 1964 NRX-A2 was restarted successfully.
Dec. 1964 There was some discussion in Congress on reviving RIFT, but it did not lead
to any policy changes.
Jan. 12, 1965 The Kiwi Transient Nuclear Test was completed; this was a safety test de-
signed to verify the behavior of a graphite-core reactor during power excur-
sion.
April 23, 1965 NRX-A3 reactor was tested for 3V2 minutes at full power.
May 20, 1965 NRX-A3 reactor was restarted and operated at full power for 13 minutes.
May 28, 1965 NRX-A3 reactor was restarted and operated at low to medium power for 45
minutes.
June 25, 1965 A Phoebus 1A reactor built by AEC was tested for 10Y2 minutes at full
power. The test was conducted to evaluate design improvements that were to
be incorporated into the larger Phoebus 2 reactor.
Summer 1965 Lewis began an in-house study of nuclear powered aircraft concepts to deter-
mine what progress had been made in this field since 1961. The Air Force had
expressed interest in such aircraft.
Dec. 8, 1965- NRX/EST (NERVA Reactor Experiment/Engine System Test) breadboard
March 25, 1966 test was conducted. NRX-A4 was used in this combination reactor-system
test.
March 4, 1966 The NERVA breadboard engine system was ground-tested at full power.
May 26- NRX-A5 reactor was tested; it maintained full power (1100 megawatts) for 30
June 23, 1966 minutes.
Feb. 1967 The Phoebus IB reactor was tested; it maintained full power (1500
megawatts) for 30 minutes.
ADVANCED RESEARCH AND TECHNOLOGY 487
Table 4-80.
Chronology of Nuclear Propulsion Program
(Kiwi, RIVr, NERVA) Research and Devdopment (Continued)
Date Event
Spring 1967 President Lyndon B. Johnson and the congressional Joint Committee on
Atomic Energy supported increased funds for Rover, but the full Congress
did not approve them. The extra funds were not appropriated.
June 1967 DoD declared that it had no plans for using a NERVA engine in its space pro-
gram.
July 12-19, 1967 Phoebus 2 was cold-tested.
Dec. 1967 NRX-A6 reactor was tested for 60 minutes at full power (1100 megawatts).
Spring 1968 NERVA test engines XE-I and XE-2 were being assembled for testing (testing
was scheduled to begin in 1969).
June 26, 1968 Phoebus 2A was tested for 32 minutes (12 minutes at 4000 + megawatts).
*Harold B. Finger, manager of the NASA-AEC joint Space Nuclear Propulsion Office, had been
Rom's protege.
Table 4-81.
Reactors Evaluated by AEC-NASA in Their Search for a
Reactor Suitable for NERVA, 1959-1968
Table 4-81.
Reactors Evaluated by AEC-NASA in Their Search for a
Reactor Suitable for NERVA, 1959-1968 (Continued)
aActually a test of the Kiwi B core design and protected fuel elements; also written as Kiwi A'.
bActually a test of Kiwi B design improvements.
CTested without fuel cells installed.
aAfter extensive damage to the reactor during hot tests, a Kiwi B4A cold-flow reactor was built and
tested to determine why the reactor had failed during the earlier tests.
Chemical Propulsion
*The Air Force called the "260-inch" motor the S-10. It was 49.38 meters long and weighed nearly 2
million kilograms loaded with its monolithic propellant grain.
_Different roles considered for the motor included use as a strap-on to Saturn, as a booster stage for
the manned lunar project, or in a half-length configuration as the first stage of the Saturn IB. None of
these possibilities proved practical because of the extra weight the large motor would have added to the
configuration.
490 NASA HISTORICAL DATA BOOK
Table 4-82.
Date Event
June 1961 NASA and the Air Force agreed that the Air Force Space Systems Division
would develop any large solid motors that NASA might require for Apollo.
Winter 1961 The Air Force initiated a technology development program for two solid
motors (6.6 meters and 4 meters in diameter).
May 4, 1962 A joint NASA-Air Force meeting was held to review the proposed specifica-
tions for the two motors.
Summer 1962 The Marshall Space Flight Center intensified its study of using large solid
motors on future launch vehicles.
Nov. 9, 1962 NASA and the Department of Defense (DoD) formally defined the general
scope of their solid-motor program.
Nov. 19, 1962 NASA and DoD agreed that two contractors would be selected to build and
test-fire two half-length 6.6-meter motors each, followed by selection of one
of the contractors to proceed with a full-length motor program.
Jan. 15, 1963 A request for proposals was sent to industry for the development of a large
solid motor.
April 1963 Aerojet-General and Thiokol were selected for the 6.6-meter project,
Lockheed and Thiokol for the 4-meter (6.6-meter project contracts were
signed in June).
Nov. 1963 DoD requested that NASA fund the 6.6-meter project starting in FY 1965.
NASA assigned the project to OART.
May 1964 Aerojet-General and Thiokol dedicated their 6.6-meter motor facilities.
July 1964 Thiokol tested its motor igniter system for the 6.6-meter motor.
Sept. 10, 1964 Lewis Research Center was assigned project management of the 6.6-meter
motor project.
Winter 1964-1965 The Bureau of the Budget (BOB) eliminated NASA's FY 1966 budget request
for the large motor project, but Congress subsequently authorized the agency
more funds than it had requested originally.
April 1965 During a hydrotest of Thiokol's 6.6-meter motor, the motor case burst after
reaching 60 percent pressure.
June 1965 NASA decided to terminate Thiokors contract because the firm could not
meet project milestones within budget.
Aug. 1965 A hydrotest of the 6.6-meter motor by Aerojet-General was successful.
Sept. 25, 1965 The first successful firing of the 6.6-meter motor was conducted by Aerojet-
General. A maximum thrust of 15.88 million newtons was attained as the
motor burned 2 minutes.
Nov. 1965 BoB again deleted the large solid motor project from NASA's budget (FY
1967), and again Congress restored the funds.
Dec. 1965 The Air Force and NASA jointly endorsed continuing the 6.6-meter and
4-meter solid-motor projects so the technology would be available for future
missions.
Jan. 1966 NASA decided to fund a third motor firing test, using a shortened motor (test
officially approved as SL-3 on March 4).
Feb. 23, 1966 The second 6.6-meter solid motor was successfully fired by Aerojet-General.
March 10, 1966 A 90-day transition contract was initiated with Aerojet-General (the original
contract had been completed). A contract for the third test was signed on
August 29, 1966 to cover the period through June 1967.
Sept. 1966 Aerojet-General successfully hydrotested the SL-3 motor case.
Dec. 1966 OART proposed deleting the large solid motor from the FY 1968 budget so
that the office could fund other projects likely to be cut by BoB.
June 17, 1967 The SL-3 motor was fired successfully by Aerojet-Gerneral for 80 seconds.
The motor developed 25.4 million newtons thrust and burned 726 thousand
kilograms of propellant.
1968 The large solid-motor project was funded on a "sustaining" basis to keep it
alive as an option for future missions.
ADVANCED RESEARCH AND TECHNOLOGY 491
Mercury Redstone, Vanguard, and Thor) for missions that would require precise
burn times, but it took propulsion specialists many years to perfect the next step up
in liquid rockets-the high-energy Centaur stage (LH2/LOX). Centaur's super-
cooled liquid hydrogen was difficult to handle, and the components of the RL-10
engines that would come into contact with the propellants were hard to qualify. As
were all NASA launchers, the large engines included in the various Saturn stages and
in Centaur (H-l and F-1 used RP-1/LOX; RL-10 and J-2 used LHE/LOX) were
developed and procured by the launch vehicle development office, the launch vehicle
procurement office, and the user (usually the Office of Manned Space Flight or the
Office of Space Science and Applications). But improving the state of the art of
liquid propulsion systems was the task of OART's two liquid propulsion teams as-
signed to the Chemical Propulsion Office.
Specialists evaluated the efficiency of various propellants and oxidizers (e.g.,
adding fluorine to liquid oxygen-FLOX-promised to add considerably to an
engine's power; so much so that OSSA assumed management of the FLOX project
in FY 1964 for Atlas-Centaur), searched for better insulators for propellant tanks,
tested multichambered engines and improved turbopumps and nozzles, investigated
the desirability of very high-pressure engines, and sought safer handling procedures
for liquid fuels. The single project that attracted the most attention in this field was
the M-1 engine, a huge motor that was slated to produce 6.67 million newtons of
thrust (the equivalent of the Saturn F-1 engine) as an upper stage. But in addition to
the M-l, the liquid propulsion experts also contributed-to the development of aux-
iliary engines and small-motor technology.
The M-1 engine, 8 meters long and 5 meters in diameter at the nozzle exit, was
initiated in 1961 by the Launch Vehicle Programs Office and transferred to OART
in 1964. Aerojet-General was on board as contractor for the large engine by January
1962, and later that year Lewis Research Center assumed management responsibility
of the project from the Marshall Space Flight Center. Constructing a large engine test
stand and the complicated propellant pumping and storage system that would be re-
quired for test firings was a key milestone that the contractor failed to meet. A test
stand failure in June 1964, the month during which hardware for the M-1 was to
have undergone its first hot firing, prompted NASA officials to demand that
Aerojet-General make some changes in how it was managing the test program.
Because the M-1 was another advanced propulsion project without a mission
but with an escalating budget, the agency began phasing it out in August 1965.*
NASA's budget allowed Lewis and the contractor to conduct a number of small-
scale tests, leading to a full-scale thrust chamber test in August 1966, the closeout
event of the project. The M-1 was not incorporated into a launch vehicle configura-
tion, because the agency did not have any clear post-Apollo plans that called for
such increased power.
*Advanced planners had originally considered using the M-1 in an upper stage with the Nova
booster, which was not developed, or with Saturn.
492 NASA HISTORICAL DATA BOOK
Table 4-83.
Chronology of M-1 Engine Research and Development
Date Event
Fall 1961 The Office of Propulsion in the Launch Vehicle Programs Office initiated the
development of a "one million-pound [thrust]" liquid hydrogen-liquid oxygen
engine. The engine was called the M-I.
Jan. 24, 1962 NASA selected Aerojet-General as the contractor for the development and
fabrication of the M-I (a letter contract was issued in April).
Nov. 1962 Project management of the M-I was transferred from the Marshall Space
Flight Center to the Lewis Research Center.
Jan. 1964 NASA Headquarters management of the M-I was transferred from the Of-
fice of Manned Space Flight to OART.
March 25, 1964 NASA awarded contracts to Aerojet-General for the building of test facilities
and preliminary flight-rate testing of the M-I. Tests were scheduled to begin
in April 1967.
June 20, 1964 Development hardware for the M-I was ready to undergo its first hot test
when a malfunction in the liquid oxygen delivery system at the engine test
stand stopped the test midway. NASA's dismay at this failure led to manage-
ment changes at Aerojet-General.
Summer 1964 Headquarters managers started to question the need for the M-I as a flight
hardware project. It was suggested that it be downgraded to a technology
development project.
Feb. 4, 1965 Headquarters advised Lewis to suspend the construction of major facilities
that were being planned exclusively for the M-I project.
Aug. 6, 1965 NASA executed a project approval document to phase out the M-I project.
Funds were authorized in FY 1966 that would support tests.
March 24, 1966 Initial tests of the M-I turbopumps, the largest ever built for handling pro-
pellants, were conducted successfully at Lewis.
April 18, 1966 Aerojet-General successfully tested the M-I turbopumps.
Aug. 1966 A gaseous fluorine ignition system was used in the first full-scale thrust
chamber tests of the M-I. The test firings, heldat Lewis, were successful.
Electric Power
Along with propulsion, onboard spacecraft power was one of the ciritical
systems that paced the development of early space vehicles. Telemetry systems,
scientific experiments, spacecraft control apparatus could be only as sophisticated as
the power supply would allow. Spacecraft designers could look to three sources for
electricity: chemical, solar, and nuclear (see table 4-84).
Batteries alone, the chemical source, offered a short-term supply of electricity,
but their weight and short lifespan spoke against carrying a bank of batteries on an
orbiting vehicle. However, teamed with solar cells, attached directly to the
spacecraft or on extendable panels, the battery could offer a reliable energy source
for lengthy missions. When an orbiting spacecraft was in earth's shadow, it would
depend on energy that had been stored in the battery during each revolution. Alone,
the solar cells could supply only direct power intermittently, while in the sun. The
chemical-solar system, often tailor-made for each spacecraft, was used successfully
throughout the 1960s in numerous configurations. Some spacecraft resembled wind-
mills with several solar paddles; others had fixed pairs of solar panels; some were
ADVANCED RESEARCH AND TECHNOLOGY 493
studded on all sides with solar cells. Batteries were of three types: nickel-cadmium,
silver-cadmium, and silver-zinc. In 1968, this kind of system was producing 500 to
1000 watts of electrical power, enough to operate a weather satellite or a physical
properties Explorer but hardly enough to provide a crew of astronauts en route to
Mars with the power they would need to keep life support equipment running for
months or powerful enough to operate a direct broadcast satellite. To produce
megawatts of electricity, NASA would need either very improved solar-chemical
systems or nuclear power generating systems or a combination of some kind. Two
nuclear power sources were available to the agency from the Atomic Energy Com-
mission: radioisotope generators and reactors.
Solar cells, made from a semiconductor material (most often silicone) into
which impurities have been introduced that alter its crystalline structure, convert
sunlight directly into electricity. To improve this photovoltaic system, NASA re-
searchers experimented with altering the shape and construction of solar cells,
sought to protect the system from radiation to lengthen its operational life, and in-
creased the efficiency of solar cells while decreasing their mass. (In 1966, one of
OART's projects in this field was a 20-watt-per-45-kilogram solar array.) The space
agency was also working on a cell that would operate at both great distances from
the sun and very close to it (solar cells are heat sensitive). Lowering the manufactur-
ing cost of solar cells was another important goal.
To improve batteries for spacecraft use, NASA and contractor personnel
decreased their weight and increased their operating life, magnetic compatibility,
stability at high and low temperatures, and ability to dissipate heat. Late in the agen-
cy's first decade, OART was assigned the development of a rechargeable battery
with a three-to five-year cycling capability. In addition, the agency would need bat-
teries that would operate on the cold moon and very close to the sun. Besides
developing nondestructive test methods, the power specialists were concerned with
sterilization techniques, electrode corrosion, and component ruggedness.
The AEC-NASA partnership extended to cover spacecraft power systems
research as well as propulsion research. AEC had begun its SNAP (Systems for
Nuclear Auxiliary Power) program in the 1950s, and the Air Force had been quick to
incorporate a SNAP-1A-class RTG on a satellite in 1955. In 1960 and 1961, NASA
expressed its interest in SNAP-8, a reactor system, for future spacecraft applications
and in the SNAP-11 RTG for the Surveyor lunar orbiter. Rather than depend on
nuclear systems for immediate full-power systems, OART personnel emphasized
development of components and subsystems._5
Working with AEC and Aerojet-General, one group of experts at Lewis
Research Center spent most of 1958-1968 trying to produce an acceptable SNAP-8
prototype. While AEC worked on the reactor, NASA was responsible for the mer-
cury Rankine converter. In July 1968, SNAP-8DR sustained a nuclear reaction for
the first time. The only other reactor-class SNAP NASA advanced researchers in-
vestigated in any depth was SNAP-50, an advanced reactor power unit capable of
300 kilowatts to 1 megawatt. NASA's support of this ambitious project, which was
of special interest to the military, was limited to the early 1960s.
NASA found the relatively less powerful RTG system (whereby heat is created
by decaying isotopes) more suitable to its needs than reactor SNAPs. Although the
agency was forced to drop its plans for a Surveyor orbiter and the SNAP-11 that
would have powered it, OART was quick to request AEC's assistance with an RTG
for the Nimbus weather satellite. SNAP-19 would contribute supplementary power
494 NASAHISTORICAL
DATABOOK
DESCRIPTION - AERONAUTICS
Advanced aeronautics had been the major research field of the National Ad-
visory Committee for Aeronautics (NACA), its only field for decades. But for
NACA's predecessor, it was of decidedly lesser importance. The ambitious "space
goals" that NASA was expected to achieve during the 1960s were given first priority.
When the Office of Advanced Research and Technology was organized in 1961,
aeronautics was assigned to it.
Table 4-84.
Power Conversion Systems under Investigation, 1958-1968
With each of the three energy sources under investigation-chemical, solar and nuclear-there were
several different means for converting the source energy to electrical energy:
CHEMICAL SOLAR
Primary batteries* Photovoltaic*
Secondary batteries* Brayton
Fuel ceils* Thermionic
Engines
NUCLEAR
RADIOISOTOPE REACTOR
Thermoelectric* Brayton
Brayton Rankine
Thermionic Thermionic
Rankine Magnetohydrodynamic conversion (MHD)
*Operational systems.
ADVANCED RESEARCH AND TECHNOLOGY 495
The laboratories at Langley and Ames with their wind tunnels and other special
facilities had been NACA's major aeronautical research sites; personnel at Lewis in
Cleveland had worked on aircraft propulsion problems; crews at Muroc, California,
had flight-tested new rocket-powered aircraft. With the call for orbiting manned
spacecraft and lunar landings, Langley, Ames, and Lewis, along with NASA's new
centers, turned most of their energies to solving the many problems of spaceflight.
Little time and money were left for aeronautics. As the agency's first decade was
coming to a close, members of Congress began echoing the accusations of earlier,
more farsighted proponents of aeronautical research, who in the early 1960s had
predicted that if the U.S. diverted all its support to astronautics and space science
the country would start lagging behind in the competitive field of aeronautics. Some
experts believe this is exactly what happened in both military and commercial avia-
tion _6 However, NASA did contribute significantly to several areas of aeronautical
research in 1958-1968, although this work took on an increasingly applied, as op-
posed to a basic research, flavor (see fig. 4-3).
Table 4-85.
SNAP Systems Used or Investigated by NASA, 1958-1968
DEVELOPMENTAL
TECHNOLOGY
AERONAUTICS DIVISION
AMES 93 7948
FLIGHT 90 3488
APPLIED
TECHNOLOGY TOTAL 537 37629
applied technology = study of new vehicle concepts, a definition phase useful to industry to in-
dicate the feasibility of a design
developmental technology = support to a user agency in testing and analyzing new technology
Most of the OART managers that served the aeronautics research directorate at
NASA Headquarters during the first I0 years began their careers with NACA. John
Stack and Charles H. Zimmerman, the first two directors, were old Langley hands.
From Ames came Charles W. Harper, who was NASA's director of aeronautics
from October 1964 through April 1967, when he assumed the new post of deputy
associate administrator for aeronautics, reporting directly to the OART associate
administrator. Albert J. Evans, who had served as acting director in 1963-1964 and
later as deputy director, took the director's job again when Harper moved to his new
post. Membership in the headquarters aeronautics group was stable, with the same
chiefs leading the branches offices for many years. William S. Aiken, Jr. (NACA,
Langley) headed the operating problems office; John B. Parkinson (NACA,
Langley) oversaw the management of aerodynamics research; Harvey H. Brown was
the loads and structures man; Nelson F. Rekos represented propulsion; and James
A. Martin (NACA, Muroc) oversaw the various flight systems projects (a super-
sonics systems manager, Leonard Sternfield, was added in 1967). (See table 4-71 for
more information on the management structure of this directorate.) Adding a dep-
uty associate administrator for aeronautics in 1967 was recognized as a symbol of a
renewed and greater interest in this area of research by NASA.
By mandate, NASA's primary goal in aeronautics research was to provide the
aviation community-civilian and military-with data that would lead to advanced
aircraft and safer operating proceduces. To do this, the agency had to work closely
with the Department of Defense and the Federal Aviation Administration. Many
aeronautics projects, because of their great expense and their possible applications
to several parties, were joint projects. The NASA-FAA-DoD-industry team
members did not always agree among themselves as to priorities and research tech-
niques, but the nature of the enterprise required them to work together and share
their expertise. Throughout the first decade, there were numerous joint panels, in-
vestigative boards, and committees (technical and managerial) to coordinate the
projects that demanded group action.
Of the many projects the NASA aeronautics team contributed to, the best
known are probably the flight tests at the Flight Research Center of high-speed
research aircraft such as the X-15. But the bulk of the work was accomplished less
dramatically in wind tunnels, on drawing boards, and with computers. Langley
Research Center absorbed most of the aeronautics research and development budget
during the decade, and it was there that most of the general aviation studies took
place. NASA pilots were assigned to Langley, Ames, and FRC, and they flew ex-
perimental and specially instrumented aircraft of all classes. They worked closely
with aeronautical engineers who tested designs in wind tunnels under simulated
flight conditions before they trusted their ideas and the ideas of others to actual fly-
ing hardware. The work was unglamorous and tedious for the most part; it often led
nowhere; but it was undeniably important to a country that depended on aircraft for
transportation and defense. _7
498 NASA HISTORICAL DATA BOOK
Table 4-86.
Changing Organization of the OART
Aeronautics Office, 1961-1968
General Aviation
V/STOL
Aircraft capable of landing and taking off vertically or with a relatively short
ground-run showed promise as military vehicles and as short-haul commercial or
civil transports. The armed conflicts in Korea and later in Indochina alerted the
*NACA had played a leading role in the military's testing program.NACA pilots flew prototypes of
new military aircraft and worked with the services and the manufacturers in improving (or rejecting)
designs. This tradition was being revived by NASA in the late 1960s.
500 NASA HISTORICAL DATA BOOK
Department of Defense to the need for aircraft that could operate from widely
dispersed, relatively unprepared sites close to the front. Large metropolitan areas
with inadequate highway systems needed a way to transport emergency crews and
commuters and goods. Experts at Langley and Ames Research Centers studied many
V/STOL (vertical/short takeoff and landing) concepts during 1958-1968, rejecting
many of the designs but steadily contributing to the state of the art. In the search for
advanced designs, specialists also found ways to improve the conventional
helicopter (for example, by introducing nonarticulated rotors).
V/STOL concepts took many forms (see fig. 4-4). Some resembled helicopters,
some bent-winged airplanes. Others sat on their tails. One way of classifying the
possible types was by comparing their methods of converting from vertical or near
V/STOL TESTBEDS
CONVAIR XFY-1
"'POGOSTICK" _
A FAIRCHILD
VZ-SFA
S DORNIER DO-29 SHORT SC-1
VZ-2PH
c X-lO0 _ BEDSTEAD ' . " _,
vertical flight to horizontal flight-tilting the entire craft; tilting only the rotors,
propellers, or other source of thrust; deflecting the thrust; or using dual propulsion
(one set of engines for lifting-lowering, another for driving horizontally). Possible
sources of thrust were rotors, propellers, ducted fans, jet exhausts, or some com-
bination of these. The goal with an STOL was a steep climb out of a congested area;
a VTOL might be required to hover for long periods of time. With wind tunnels and
computers, NASA employees analyzed the various designs. The promising ones
were translated to flight prototypes and equipped with extra instrumentation for a
rigorous test flight program. NASA's investigations of V/STOLs covered
aerodynamic design, materials and structures, the power plant, handling, and
operating costs. 19
Supersonic/Hypersonic Research
Traveling faster than the speed of sound had been a goal of flyers and aircraft
designers since the early 1940s, and NACA and the services had jointly pursued that
goal with an instrumented research aircraft program. The Army-sponsored Bell
XS-1 was the first of these specially built air-launched X-series aircraft to be ap-
proved.* With the Army, Air Force, and Navy supporting them, Bell Aircraft,
Reaction Motors, Douglas Aircraft, and others became involved with designing
faster and higher-flying aircraft. NACA's part in this activity increased as the
builders entered the detail design phases of their projects and when flight-testing
began. One of the committee's major contributions in the search for high-speed air-
craft was the concept of variable swept wings (1946-1947). If an aircraft's wings
could be made to move, changing their angle (sweep), the aircraft could adapt itself
to different regimes of flight.
In October 1947, pilot Charles E. Yeager broke the sound barrier. In the XS-1, he
traveled at more than the speed of sound-Mach 1.06 at 13_000 meters.t By the next
year, the scope of the research aircraft program had increased greatly to include
several types of aircraft, operational or under development. To manage this growing
activity, NACA established a Research Airplane Projects Panel that would serve as
coordinator for the committee's high-speed aircraft program and as an interface be-
tween NACA and the military. The 1950s saw NACA engineers and pilots working
*It was NACA's participation in the testing of the XS-1 in 1946in Muroc, California, that prompted
a contingent of specialists from Langley to move to this land of dry lake beds so suitable for test flights.
They became the nucleus around which NASA's Ames Flight Research Center was built in the 1960s.
tAs an airplane's speed increases, it piles up a mass of air ahead of it, formed from constantly emit-
ted pressure disturbances that move outward from the plane. These disturbance waves move at the speed
of sound, approximately 1220 kilometers per hour at sea level, dropping to 1060 kilometers per hour at
about 12 000 meters. As an airplane approaches the speed of sound, it begins to catch up with its own
forward-moving pressure wave fronts. When flying well below the speed of sound, a plane is said to be
moving at subsonic speed; flight at velocities around the speed of sound is termed transonic; flight faster
than sound is supersonic. Hypersonic flight is generally defined as five times the speed of sound. The
common unit of measurement for the speed of sound is Mach number, the ratio of an object's speed to
the speed of sound (Mach 1.0 = the speed of sound).
502 NASA
HISTORICAL
DATABOOK
*For details on these aircraft, see Langley Research Center, Progress in Aircraft Design since 1903
(Hampton, VA, 1974); and Flight Research Center, "Experimental Research Aircraft," n.d.
I"Round three was to have been the Air Force Dyna-Soar (X-20) orbital lifting reentry vehicle. This
project was cancelled in 1963 because of rising costs.
** North American pilot A. Scott Crossfield flew the initial checkout flights before the aircraft were
officially turned over to NASA and the Air Force.
_t Depending on the mission, the X-15's rocket engine provided 80-120 seconds of thrust; the re-
mainder of the 10 to 11-minute flight was powerless, ending with a 300-kilometer-per-hour glide landing.
One of two flight profiles was normally used: a high-altitude plan that called for the pilot to maintain a
steep rate of climb, or a speed profile that called for the pilot to maintain a level altitude.
I ADVANCED
RESEARCH
ANDTECHNOLOGY 503
1968. For many weeks thereafter, the group at FRC tried for one more flight, the
200th, but minor mechanical problems and inclement weather thwarted their ef-
forts. On their last attempt in December, it snowed on the desert runways.z1
LENGTH: 15.24 m
WING SPAN: 6.7 m
WEIGHT, EMPTY: 22,500kg
WEIGHT, AT LAUNCH: 54,700 kg
THRUST: 267,000newtons
Table 4-87.
Date Event
Aug. 1944 A report by German scientists Eugen S_inger and Irene Bredt supported the
design of a hypersonic rocket-propelled ground-launched global aircraft also
capable of spaceflight. It would reeenter in a semi-ballistic skip trajectory.
The iron-shaped aircraft would weigh 91 000 kilograms. (This report in-
fluenced hypersonic research conducted later by the National Advisory Com-
mittee for Aeronautics [NACA]. After World War II, Walter Dornberger
[war-time director at Peenemfinde] of Bell Aircraft proposed a boost-glide
vehicle based on the S_inger-Bredt design.)
Oct. 4, 1951 Robert J. Woods of Bell suggested that NACA build a hypersonic-class
research aircraft.
Jan. 30, 1952 Woods recommended that NACA establish a group to study Mach 5_
manned winged aircraft designs.
June 24, 1952 NACA's Committee of Aerodynamics voted to expand its research aircraft
program to include flight at altitudes of 19 to 80 kilometers at Mach 4-10 and
to devote a modest effort to studying escape-velocity flights.
Aug. 1952 NACA appointed a hypersonic research aircraft study group at the Langley
Memorial Aeronautical Laboratory (Clinton Brown, W. J. O'Sullivan,
Charles Zimmerman).
June 1953 The hypersonic aircraft study group submitted a report recommending that
NACA investigate aerodynamic heating problems and undertake rocket-
propelled hypersonic aircraft model tests.
Oct. 1953 The Air Force Scientific Advisory Board's Aircraft Panel advocated a hyper-
sonic research aircraft program.
Fall 1953 Douglas Aircraft Corporation's El Segundo Division was awarded a contract
by the Office of Naval Research for a feasibility study of a hypersonic
research aircraft capable of Mach 7 at 200 000 meters.
Feb. 1954 NACA's Research Airplane Projects Panel concluded that an entirely new
research aircraft capable of hypersonic speeds was desirable.
March 9, 1954 NACA directed its laboratories to submit their views on hypersonic aircraft
to headquarters.
March 15, 1954 Langley created a hypersonic research airplane study group (John V. Baker,
Maxime Faget, Thomas Toll, N. F. D0w, J. B. Whitten). Their work led to
the design that would later be adopted for the X-15.
June 1954 NACA invited the military services to join them in forming a joint hypersonic
research aircraft program.
July 9, 1954 Becker submitted the Langley study group's design proposal at a joint
NACA-Air Force-Navy meeting.
Sept. 13, 1954 The Air Force, through Wright Air Development Center, endorsed NACA's
proposal for a hypersonic aircraft, but cautioned that selection of a power
plant should be deferred until propulsion requirements were more adequately
defined. The Air Force wanted "executive responsibility" for the project.
Oct. 18, 1954 NACA, the Air Force, and the Navy created a committee to define the
specifications for a hypersonic research aircraft (Hartley Soul6, NACA;
R. M. Wray, Air Force; Abraham Hyatt, Navy).
506 NASA HISTORICAL DATA BOOK
Table 4-87.
Chronology of X-15 Development and Operations (Continued)
Date Event
Winter 1954 NACA, Air Force, and Navy participants worked out the management
responsibilities for the project; the Air Force and the Navy would jointly
fund the design and development phases of the aircraft; NACA would have
responsibility for the technical aspects of the project. A Research Airplane
Committee would advise NACA.
Dec. 23, 1954 A memorandum of understanding was signed by NACA, Air Force, and
Navy participants.
Dec. 30, 1954 The Air Force Air Materiel Command Aircraft Division released an invita-
tion to bid to 12 firms; the deadline for reply was May 9, 1955. The aircraft
was to be capable of speeds of 2000 meters per second and an altitude of
76 000 meters.
Jan. 17, 1955 The Air Force designated the hypersonic research aircraft project the X-15.
NACA selected Arthur Vogely of Langley as project officer; the Air Force
chose Chester McCollough as project engineer.
Jan. 18, 1955 A briefing on the X-15 project was held for industry.
May 9, 1955 Bell, Douglas, North American Aviation, and Republic Aviation submitted
proposals for an X-15.
May 17, 1955 The X-15 Research Airplane Committee decided that the Air Force would
build and equip the new test-flight range that would be required for the X-15
and that NACA would operate it.
Aug. 5, 1955 North American's proposal was judged to be the best package, with
Douglas's proposal a close second.
Dec. 9, 1955 North American signed a letter contract with the Air Force that called for the
development and fabrication of three X-15 aircraft.
Feb. 15, 1956 The Air Force awarded Reaction Motors, Inc., a contract for the X-15 power
plant, a liquid oxygen-ammonia engine designated the XLR-99.
June 11, 1956 The Air Force awarded North American a definitive contract for the X-15.
Feb. 1958 Because of delays with the XLR-99 engine, the project office authorized the
use of two XLR-I 1 engines in place of the 99 for the X-15's initial flights.
NACA, the Air Force, and the Navy's Bureau of Aeronautics set up a
technical advisory group to monitor the new engine's development. The Air
Force secured the cooperation of North American's Rocketdyne Div. to assist
Reaction Motors.
Oct. 1958 The Air Force cancelled Rocketdyne's backup engine program. At NASA's
facility at the flight-test site, 80 personnel were added to the X-15 group.
Oct. 15, 1958 Rollout of the first X-15 took place at North American's Los Angeles Div.;
the aircraft was delivered to Edwards Air Force Base the next day.
March 10, 1959 Carried under the wing of a B-52, the first X-15 was flown captively to check
out onboard systems. An electrical generator malfunctioned, terminating the
test prematurely.
April 1, 1959 A second captive flight revealed problems with the pilot's pressure suit.
ADVANCED
RESEARCH
ANDTECHNOLOGY 507
Table4-87.
Chronology
of X-15Development
andOperations
(Continued)
Date Event
April10,1959 The second X-15 was delivered to Edwards.
May1959 Flight Research Center (FRC, NASA) engineer Hubert Drake suggested us-
ing the X-15 to carry scientific and engineering experiments.
June
8,1959 X-I 5 number one performed its first glide flight (no power); North American
pilot A. Scott Crossfield was at the controls. The pilot had some difficulty
with the landing, but the problems were easily solved.
July1959 The X-15 High Range was ready for operations (three radar tracking
facilities).
Sept.
17,1959 X-I 5 number two performed the first powered flight with the interim engines;
Crossfield reached Mach 2.11 and 15 954 meters.
Nov.5,1959 An engine fire on X-15 number two led to an emergency landing with a par-
tial propellant load, breaking the plane's "back." The aircraft was grounded
for repairs for three months.
Jan.23,1960 X-15 number one took its first powered flight; after the mission NASA took
official delivery of the aircraft.
May1960 The XLR-99 engine was installed in the third X-15, and the aircraft was
shipped to FRC.
June 1960 North American installed the XLR-99 in X-15 number two.
June 8, 1960 X-15 number three exploded in its test stand when a pressure regulator in the
ammonia tank malfunctioned. The aircraft's midsection and tail were
destroyed.
Feb. 1961 X-15 number one was returned to North American for its XLR-99 engine.
Feb. 8, 1961 NASA accepted X-15 number two from North American.
June 10, 1961 X-15 number one was returned to FRC with its XLR-99 engine.
Aug. 1961 NASA and the Air Force established an X-15 Joint Program Coordinating
Committee to plan X-15 follow-on experiments; their report was readied by
September.
Sept. 1961 North American delivered the repaired X-15 number three to FRC; it was
equipped with a unique stability augmentation system (Honeywell MH-96
Adaptive Flight Control System), which would enable the craft to reach
higher altitudes.
Oct. 4, 1961 The lower half of the ventral vertical fin was removed to improve pilot con-
trol of the aircraft and to allow for angles of attack greater than 20 degrees to
simulate spacecraft reentry.
Nov. 1961 NASA and the Air Force approved using the X-15 as an experiments carrier.
Nov. 9, 1961 X-15 number two reached its design speed of Mach 6 +.
Dec. 20, 1961 X-15 number three took its first powered flight.
March 23, 1962 The X-15 Research Airplane Committee approved the follow-on research
program.
Nov. 9, 1962 X-15 number two crash-landed, injuring the pilot. The plane had to be totally
rebuilt. Its design was modified by the addition of external fuel tanks and a
hypersonic ramjet engine. The damaged aircraft was delivered to North
American on December 7.
5O8 NASA
HISTORICAL
DATABOOK
Table4-87.
Chronology
ofX-15Development
andOperations
(Continued)
Date Event
March
25,1963 North American was notified to proceed with the modifications that would
transform number two into a Mach 8 aircraft.
May9,1963 North American received a letter contract for modifications to number two.
Feb.18,1964 The X-l 5 Research Airplane Committee held its last formal meeting, approv-
ing the Langley hypersonic ramjet experiment for X-15A-2.
June
25,1964 X-15A-2 took its first flight.
Jan.1966 NASA negotiated a contract with the Martin Company for the design and
testing of an ablative coating for X-15A-2 that would protect it at speeds
above Mach 6.
Oct.3,1967 X-15A-2 with the ramjet set an official world speed record of Mach 6.72. The
heating experienced at that speed caused problems with the ramjet, and the
spray-on ablative coating proved unsatisfactory. The aircraft was returned to
North American Rockwell for general maintenance and repairs, but this was
the aircraft's last flight.
Nov. 15, 1967 Due to probable distraction and misinterpretation of instrument displays and
possible vertigo, pilot Michael J. Adams in X-15 number three went into a
spin at Mach 5+ and then into a steep dive at Mach 4.7+ during at-
mospheric reentry. The plane broke up, and the pilot was killed. An accident
board was convened to investigate.
June 27, 1968 X-15A-2 was returned to FRC but not flown again.
Dec. 1968 NASA decided to cancel the X-15 program. The flight team at FRC tried to
accomplish the 200th X-15 flight with number one, but minor mechanical
problems and unfavorable weather conditions prevented them from attaining
this symbolic goal.
ADVANCED
RESEARCH AND TECHNOLOGY 509
Table 4-88.
X-15 Flight Log
1959
1960
1960
Table 4-88.
X-15 Flight Log (Continued)
1961
1962
Table 4-88.
X-15 Hight Log (Continued)
1959
1963
Table4-88.
X-15FlightLog(Continued)
No. Date Flight no.* Pilot Max. Max. alt. Remarks
Mach (meters)
1959
1964
1965
Table4-88.
X-15FlightLog(Continued)
No. Date Flight
no.* Pilot Max. Mal.alt. Remarks
Mach(meters)
138 June29 3-44-67 Engle 4.94 85527
139 July8 2-40-72 McKay 5.19 64800
140 July20 3-45-65 Rushworth 5.40 32126
141 Aug.3 2-41-73 Rushworth 5.16 63612
142 Aug.6 1-56-93 Thompson 5.15 31455
143 Aug.10 3-46-70 Engle 5.20 82601
144 Aug.25 1-57-96 Thompson 5.11 65258
145 Aug.26 3-47-71 Rushworth 4.79 73030
146 Sept.
2 2-42-74 McKay 5.16 73091
147 Sept.
9 1-58-97 Rushworth 5.25 29627
148 Sept.14 3-48-72 McKay 5.03 72847
149 Sept.
22 1-59-98 Rushworth 5.18 30571
150 Sept.
28 3-49-73 McKay 5.33 90099
151 Sept.30 1-60-99 William
J. 4.06 23348
Knight,
USAF
152 Oct.12 3-50-74 Knight 4.62 28773
153 Oct.14 1-61-101Engle 5.08 81229
154 Oct.27 3-51-75 McKay 5.06 72207
155 Nov.3 2-43-75 Rushworth 2.31 21519 Firstflightwithexternal
tanks (empty).
156 Nov.4 1-62-103William
H. 4.22 24445
Dana,
NASA
1966
Table 4-88.
X-15 Flight Log (Continued)
1968
*The three numbers stand for: X-15 number, free flight number, and B-52 number.
technical support that industry needed to design and build a reliable, economical,
safe, and publicly acceptable SST.
In their studies of supersonic and hypersonic flight, engineers and designers at
NASA's Langley, Ames, and Lewis Research Centers had amassed a wealth of data
on aircraft design and high-performance power plants. At the Flight Research
Center, specialists had had firsthand experience with operating high-speed aircraft,
as had Air Force personnel at Edwards Air Force Base. NASA's advanced research-
ers suggested investigating three configurations for the supersonic transport: a
slender delta, a variable swept-wing craft, and a canard (horizontal stabilizing and
control surfaces located in front of the main supporting surfaces). By 1963, Ames's
and Langley's wind tunnels were being used extensively to evaluate various designs
based on these three possibilities. The FAA, meanwhile, solicited industry for SST
proposals, and in January 1964 Boeing, North American, and Lockheed submitted
their ideas. Interestingly enough, each firm had followed a different design route:
Boeing submitted a variable-sweep proposal, North American a canard based on
their XB-70, and Lockheed a double delta. It took nearly three years to evaluate
these packages. Langley participants contributed reports on what they called SCAT
(Supersonic Commercial Air Transport) configuration studies.
To complement the theoretical work, pilots at FRC flew high-speed military air-
craft to get some understanding of problems that a commercial supersonic transport
might have with landings, terminal approaches, air traffic control procedures, and
handling. A General Purpose Airborne Simulator developed for NASA by Cornell
Aeronautical Laboratory also was put to use simulating flight patterns and emergen-
cy situations. One aircraft flown at FRC as part of this study program captured the
public's attention: the XB-70, a futuristic-looking strategic bomber prototype built
by North American for the Air Force (see fig. 4-6).* Designed as a replacement for
the B-52, the XB-70 proved very costly and of questionable military value. Only two
were manufactured, and they were turned over to NASA to use as research aircraft
in the late 1960s. They were flow as part of a joint Air Force-NASA research project
in support of the SST as early as June 1966.I"
Boeing's variable swept-wing SST was named the winning design in December
1966 by the FAA (General Electric would build the engine), but this decision did not
mean that the aircraft had been precisely defined. Two years later, behind schedule
and over-budget, Boeing was still making major changes to the configuration. The
FAA announced in early 1968 that the SST design required still more development
work before a prototype could be constructed. In fact, Boeing engineers had
changed their minds about the variable sweep wing; they wanted to go with a fixed-
* Other aircraft flown in SST studies at FRC were the Douglas F5D-1 Skylancer (landing studies), the
F-100C Super Sabre (handling quality studies), the North American A-SA Vigilante (approach and lan-
ding studies), and the Lockheed YF-12A Blackbird.
l'XB-70-1's first flight took place on September 21, 1964, and for two years both aircraft participated
in flight worthiness demonstrations. At Mach 3, the aircraft tended to loose their outer skin, which led to
extensive maintenance to keep them flight-ready. On June 8, 1966,XB-70-2 was involved in a mid-air col-
lision, killing the co-pilot Carl S. Cross, USAF, and destroying the aircraft. (Joseph A. Walker, NASA,
piloting an F-104 was also killed). The remaining aircraft was not as well-suited for the research role (it
never flew beyond Mach 2.57). It was this vehicle that NASA received from the Air Force on March 15,
1967.
516 NASA HISTORICAL DATA BOOK
LENGTH: 57.6 rn
WING SPAN: 32 m
WEIGHT, LOADED: 227,000 kg
THRUST: 800,000 newtons
SCAP ;CAPSU,
PITOT BOOM --_
FLIGHT VIEW
wing design instead. There were other problems, as well. Environmentalists were
concerned over the excessive noise an SST would make. NASA participated in sonic
boom studies and concluded that the SST design would have to be tailored con-
siderably to minimize the magnitude of the shock waves. NASA, the FAA, and the
Air Force had also joined together to measure the cosmic and solar radiation en-
vironment at the altitudes an SST would fly. But money was probably the supersonic
transport managers' greatest worry. The government had funded a great many ex-
pensive studies and tests, and by the end of the 1960s it was obvious that a private
concern such as Boeing would need federal assistance to build an SST assembly line,
if an SST design was ever found that proved satisfactory to all parties. By 1971,
Congress had had enough. It dropped its support of the project, and the enterprise
was too large for a nongovernment body to pick up alone.
As far as NASA was concerned, its participation in the SST program had been
worthwhile. Its aeronautics team had been funded for several years to support the
activity, and it had collected data on high-speed flight and aircraft design that were
applicable to several fields of research. NASA had been able to procure special in-
strumentation for the XB-70 and other aircraft and extend its ground- and air-
simulation studies considerably. By December 1968, the agency had moved to ter-
minate its XB-70 flight program. It had been exploited to its potential in support of
SST; the aircraft was expensive to operate; and another Mach 3 + aircraft would
soon be available for FRC's research program. Personnel at the Flight Research
Center had been participating in tests of the Lockheed YF-12A Blackbird high-speed
reconnaissance aircraft since 1967, and the center would acquire two of them in
1969.
NASA participated in one other high-speed aircraft testing project during the
1960s that deserves mention here. It was the agency's only project that followed the
old NACA tradition of the 1950s of using civilian flight-test specialists to iron out
technical problems in a new weapons system. In January 1967, the Air Force sent the
sixth production F-I 11 (made by General Dynamics/Convair Aerospace) to FRC.
The advanced fighter had been suffering engine problems. FRC's testing program
led to a major engine inlet redesign. 22
CHAPTER FIVE
TRACKING AND DATA
ACQUISITION
CHAPTER FIVE
521
522 NASA HISTORICAL DATA BOOK
make a speedy recovery possible. Under "routine" circumstances, reentry and land-
ing was not as exact an operation as some manned spaceflight personnel would have
liked; but trying to find a bobbing capsule on the high seas in an emergency situation
without an initial estimate of its location provided by tracking data was unthinkable.
In the case of communications, weather, and scientific satellites, knowing the exact
location of the spacecraft at certain times was likewise critical to mission objectives;
antennas, instruments, and camera had to be in just the right place pointing just the
right way. Tracking could be accomplished optically or by one of several radio-wave
techniques.
Data acquisition, the other half of the tracker's job, is the reception at a ground
station of scientific and engineering data generated by a spacecraft. The process of
conveying data from spacecraft to earth via radio waves is called radio telemetry.
Raw data, often stored on spacecraft recorders until it can be conveniently relayed,
are coded (a common coding method used in the 1960s was the binary number
system) and converted into usable information by data reduction equipment at mis-
sion control facilities. Information is sent to the spacecraft (uplinked) in a similar
fashion. In response to commands, the spacecraft will perform some particular task:
downlink telemetry, take a pressure reading, point an antenna. 1 The process of
sending messages to a spacecraft and receiving information from it is generally
known as command and control.
These many tracking and data acquisitions procedures required that network
tracking stations have extensive arrays of antennas, radar devices, interferometers,
computers, consoles, and a small jungle of relays, switches, and other "black
boxes." But not all stations performed every possible function. Some provided only
radar support or voice communications; others acted as complete nerve centers;
some were mobile to add extra tracking hardware for special missions. All were in
direct, real-time contact with the appropriate mission control center (Goddard Space
Flight Center for earth orbital satellites; JPL for lunar and interplanetary
spacecraft; Kennedy Space Center for Project Mercury; and the Manned Spacecraft
Center for Projects Gemini and Apollo).
NASA's tracking stations were by necessity positioned all over the globe so that
contact with a spacecraft could be maintained throughout its mission, not just when
its orbit brought it over the United States (see fig. 5-1 for the location of NASA's
tracking facilities in 1966). Several of NASA's centers helped define the networks
and locate sites for stations; Goddard and JPL operated the networks (Goddard was
responsible for STADAN and MSFN, JPL for DSN). But overall management
authority for development and operations went to the Office of Tracking and Data
Acquisition (OTDA) at NASA Headquarters, where Edmond C. Buckley was in
charge. Buckley, who joined the National Advisory Committee for Aeronautics
(NACA) in 1930 as an instrumentation specialist at the Langley Memorial
Aeronautical Laboratory helped establish tracking facilities at Wallops Island and at
the Edwards Air Force Base-NACA High-Speed Flight Station complex. In 1959, he
came to NASA Headquarters as assistant director of spaceflight operations. The
next year Buckley's office staff was shuffled and increased, but the November 1961
agencywide reorganization brought a more significant change. Buckley's new title
was director of tracking and data acquisition; Gerald M. Truszynski became his
deputy. Truszynski had also been a NACA instrumentation expert, having worked
on ground instrumentation for the X-series aircraft range at the California test-
flight station. Reporting to Buckley and his deputy were chiefs or directors for
TRACKING AND DATA ACQUISITION 523
Z
_o
I--
g
Z
0
i._
_3 if)
_o
o@
I
524 NASA HISTORICAL DATA BOOK
Table 5-1.
Four Phases of Tracking and
Data Acquisition Management, NASA Headquarters
Phase I
1959-June 1960
Phase II
July 1960-Oct. 1961
Administrator/Deputy Administator
Associate Administrator
Director, Space Flight Development (Silverstein)
Assistant Director, Space Flight Operations (Buckley)
Chief, Advanced Development (vacant)
Manager, Tracking Systems (Clarence R. Morrison)
Manager, Telemetry Systems (Wallace Ikard)
Manager, Data and Computing Systems (John Sterrett)
Chief, Operations (Gerald M. Truszynski)
Manager, Network Operations (H. R. Brockett)
Manager, Interagency Operations (Norman Pozinsky)
Manager, Flight Mission Operations (Victor W. Hammond)
Manager, Communications Operations (Paul A. Price)
Phase III
Nov. t961-mid-1965
Administrator/Deputy Administrator
Associate Administrator
Table 5-1.
Four Phases of Tracking and
Data Acquisition Management, NASA Headquarters (Continued)
Phase IV
Fall 1965-1968
Administrator/Deputy Administrator
Associate Administrator
Associate Administrator, Tracking and Data Acquisition (Buckley; Truszynski, Jan. 1968)
Deputy Associate Administrator, Tracking and Data Acquisition (Truszysnki; Brockett, March
1968)
Director, Systems Planning and Development (Morrison; Robert T. Hynes, 1967; Truszynski,
acting, 1968)
Director, Program Coordination and Resources Management (Lucas)
Director, Operations, Communications, and ADP (Brockett; Charles A. Taylor, 1968)
Chief, Network Operations (Barely)
Chief, Communications and Frequency Management (Price)
Chief, ADP Management (Kenneth Webster)
Director, DoD Coordination (Bryant)
Director, Network Support Implementation (Pozinsky)
BUDGET
OTDA's budget was divided among three basic categores: research, operations,
and equipment. This organization was intact for most of the 1958-1968 period. The
network operations and equipment-components monies were divided among the
satellite, manned, and deep space networks, the communications system that linked
the stations with the control centers, data processing, and other instrumentation
needs, such as the X-15 range in California. For the first years of Project Mercury,
part of the funding for the manned tracking network came from the manned
spaceflight budget. Starting with the FY 1963 budget request, the MSFN was being
funded only by OTDA. For a more detailed breakdown of the tracking and data ac-
quisition budget, consult the NASA yearly budget estimates. Also, review the bot-
tom notes of the following tables carefully before making conclusions about totals
for any particular aspect of the program.*
*It would also be useful to review the introduction to the budget section of chapter 1 for general in-
formation on NASA's budget and on the sources and format used for the budget tables in this book.
TRACKING AND DATA ACQUISITION 527
Table 5-2.
Total Tracking and Data Acquisition Funding History
(in thousands of dollars)
aln addition, $2 840 000 was programmed for Mercury network operational implementation and
network operations in the Mercury budget.
b In addition, $5 450 000 was requested by the manned spaceflight program for the operation of
Mercury stations.
Cln addition, $25 254 000 was programmed for tracking, data acquisition, and control network in
the Mercury budget.
aIn addition, $20 385 000 was requested for Mercury network operational implementation and net-
work operations in the Mercury budget.
eThe appropriations conference committee further reduced the total to $270 000 000 in October
1967.
528 NASA
HISTORICAL
DATABOOK
Table5-3.
Programmed
CostbyTracking
andDataAcquisition
Projects
(inthousands
ofdollars)
1959 1960 1961 1962 1963 1964 1965 1966 1967 1968
Supporting research
and technology 856 a 4266 b 11 512 c 9097 13 277 12 890 t3 500 13 800 13 800 12 800
Network operations
Satellite network 2060 d 5705 e 9620 9374 12 252 23 464 25 063 27 640 37 700 41 488
Manned flight
network ...... f 293 g 15 183 16 495 18 795 23 118 37 909 65 650 71 079
Deep space network --- 1341 4233 6743 8117 I 1 833 19 040 25 350 35 500 37 290
Communications --- 580 6915 8393 10 821 12 026 17 478 23 890 39 500 42 118
Data processing --- 3400 h 3006 1660 4240 6277 4625 6101 10 200 13 608
Other
instrumentation 180 i 1477 j 000 000 4018 k 5736 5930 6620 6506 5900
Equipment and
components
Satellite network ...... 7346 3940 9390 15 297 17 995 14 500 I 1 700 9478
Manned flight
network ......... 10 253 28 100 56 234 98 348 48 523 27 700 24 181
Deep space network ...... 1179 000 7636 12 004 15 168 13 420 7500 9354
Communications ...... 226 967 1925 4036 4755 7200 6000 3090
Data processing ......... 300 3316 11 065 3916 2612 5100 2164
Other
instrumentation ......... 8921 2555 m 4690 4300 3500 4000 3300
m Includes 51 545 000 for Wallops and other instrumentation, and 51 010 000 for an aerodynamics test range.
Table 5-4.
Tracking and Data Acquisition Supporting Research and Technology Funding History
(in thousands of dollars)
a Includes $580 200 for network communications and $3 400 440 for computation and data reduc-
tion.
b In addition, $5 450 000 was requested by the manned spaceflight program for the operation of
Mercury stations.
c Includes $9 122 900 for network communications and $2 350 000 for computation and data reduc-
tion.
dAuthorizations were not broken down further to indicate where the reductions were made.
e Neither the authorization nor the appropriation was broken down to indicate where the reductions
were made.
Table 5-6.
Network Operations-Satellite Network Funding History
(in thousands of dollars)
Table 5-7.
Network Operations-Manned Flight Network Funding History
(in thousands of dollars)
1960 ...... a
1961 ___b 293 c
1962 ___d 15 183
1963 24 047 16 495
1964 24 000 18 795
1965 25 400 23 118
1966 35 100 37 909
1967 60 000 65 650
1968 78 000 71 079
a $2 840 000 was programmed for Mercury network operational implementation and network opera-
tions from the Mercury budget.
b $5 450 000 was requested by the manned spaceflight program for the operation of Mercury sta-
tions.
c In addition, $25 254 000 was programmed for tracking, data acquisition, and control network from
the Mercury budget.
d $20 385 000 was requested for Mercury network operational implementation and network opera-
tions in the Mercury budget.
Table 5-8.
Network Operations-Deep Space Network Funding History
(in thousands of dollars)
Table 5-9.
Network Operations-Other Instrumentation Funding History
(in thousands of dollars)
Table 5-10.
Network Operations-Communications Funding History
(in thousands of dollars)
Table5-11.
Network
Operations-Data
Processing
Funding
History
(inthousands
ofdollars)
Year Request Programmed
Table 5-12.
Total Equipment and Components Funding History
(in thousands of dollars)
a Authorization was not broken down further to indicate where the reductions were made.
bNeither the authorization nor the appropriation was broken down to indicate where the reductions
were made.
Table 5-13.
Equipment and Components-Satellite Network Funding History
(in thousands of dollars)
Table 5-14.
Equipment and Components-Manned Flight Network Funding History
(in thousands of dollars)
Table 5-15.
Equipment and Components-Deep Space Network Funding History
(in thousands of dollars)
Table 5-16.
Equipment and Components-Other Instrumentation Funding History
(in thousands of dollars)
Table 5-17.
Equipment and Components-Communications Funding History
(in thousands of dollars)
Table 5-18.
Equipment and Components-Data Processing Funding History
(in thousands of dollars)
During the 1940s, the Peenemunde rocket team in Germany adapted the
astronomer's methods for optical tracking and radio Doppler techniques to suit its
needs for tracking the V-2 rocket, a less than perfect but revolutionary tool of war
used against England. After the Second World War, tracking experts in the U.S. not
only improved the conventional radar and optical tracking methods employed dur-
ing the war, but also looked to a new field: radio astronomy. Using radio astronomy
techniques, specialists could find and follow objects launched into space. The ob-
jects of interest were ballistic missiles.
In the late 1940s, the Army Air Corps and the Naval Research Laboratory
(NRL) were particularly interested in techniques whereby they could measure in-
terference: the effect produced by the combination or superposition of two systems
of waves (sound or light) in which the waves reinforced, neutralized, or in other
ways interfered with each other. The instrument used to measure the velocity and
absorption of sound waves in a gas or liquid or to compare unknown light-wave
TRACKING AND DATA ACQUISITION 535
lengths with a standard wav.e length was called an interferometer (acoustic or op-
tical). While NRL's initial studies concentrated on measuring sound waves under
water, the Army Air Corps team was interested in devising a radio wave in-
terferometer that could be used for tracking missiles. A radio interferometer, two or
more radio telescopes (antennas) separated by known distances, could pinpoint
sources of radiation, such as that transmitted by a beacon fixed on a vehicle in
space, in the radio range (see figs. 5-2 and 5-3). The Azusa interferometry system
developed by the Army Air Corps with the assistance of Consolidated Vultee Air-
craft Corporation was successfully put to use on American missile ranges. During
the early 1950s, the Navy borrowed Azusa technology for its Viking missile tracking
system, and communications experts at NRL began to consider the usefulness of the
radio interferometer in some future satellite tracking scheme.
NRL soon had an opportunity to put its advanced studies to work. A trackable
artificial satellite was the ambitious goal of the United States as part of its contribu-
tion to the International Geophysical Year (IGY, 1957-1958). The Army and the
Navy both submitted serious proposals for a launch vehicle and spacecraft that
might meet that goal ahead of the Soviet Union, which had also expressed an interest
in launching a satellite.
The Navy's Project Vanguard, suggested in 1955, included plans for a radio
tracking network; Project Orbiter, the Army's bid, originally called for optical
tracking only. John T. Mengel, a member of the Vanguard team, coined the name
Minitrack for its satellite tracking scheme. The spacecraft beacon by which
Vanguard would be followed on its orbits would be of minimum weight (0.37
kilogram), thus Minitrack. Telemetry reception and command would be ac-
complished by Yagi antennas fixed so that they could track the craft from horizon to
TO
A
c_y
1
/
SATELLITE
B
_.1
0_
Source: From Samual Glasstone, Sourcebook on the Space Sciences (New York: D. Van Nostrand Co.,
Inc., 1965), pp. 218-20.
536 NASA HISTORICAL DATA BOOK
horizon (rocking horse antennas). Mengel likened the Vanguard tracking antennas
to ears: "An individual locates the source of sound by virtue of the phase differences
in the sound waves, arriving at different times at his two ears. Similarly the listening
units of the minitrack system are pairs of receiving antennas, set a measured distance
apart, which indicates the direction of the signal by phase differences in the radio
waves .... -2 Processing the data that these pairs of antennas gathered would fall to
an IBM 704 computer based in a computing facility in Washington, D.C.
By late 1955 after authorization for Vanguard had been secured-due in part to
the maturity of the radio tracking plan- and after Mengel had been put in charge of
NRL's Radio Tracking Branch, the Navy tracking specialists were busy defining
where Vanguard ground stations should be built. The proposed number of stations
had grown from four to a network of nine stations that would create a "radar
fence"- a chain of overlapping antenna patterns through which an orbiting satellite
that had been launched from Cape Canaveral would have to intersect frequently. A
long north-south fence was not financially feasible for NRL, but nine stations,
several of which were to be strung along the 75th meridian within 45 degrees north
or south of the equator, would enable the trackers to compile sufficient orbital data
on satellites whose orbits did not incline more than 45 degrees. Early in 1956, the
laboratory was ready with a team that would travel to South America to locate sites
and negotiate agreements with foreign government officials.*
In March and April, NRL had negotiations under way for stations in Havana,
Panama, Quito, Antofagasta, and Santiago. Responsibility for construction was
assigned to a Project Vanguard Task Force of the Army Map Service. At the urging
of NRL, all participants had agreed to a radio frequency of 108 megahertz for the
IGY activities. In the United States, stations would be built at Blossom Point,
Maryland, at San Diego, and on two islands (Antigua and Grand Turk) near Cape
Canaveral, the launch site. This brought the number of station locales to 10, with an
1 lth being added at Woomera, Australia, for the collection of geodetic data, shortly
after the network became operational in October 1957, well in advance of the first
successful mission the following March.I"
After NASA assumed authority for Vanguard in October 1958, Mengel and his
tracking specialists were assigned to the new Beltsville Space Center, soon to be
renamed the Goddard Space Flight Center. Mengel was appointed assistant director
for tracking and data systems at Goddard, and Minitrack, over the next several
years, was transformed into a global satellite tracking network. The net was always
in a state of change: stations were added (Winkfield, Alaska, Johannesburg, Mo-
jave, East Grand Forks, St. John's, Ft. Myers, Rosman, Brazilia) to support
satellites with orbits that took them further away from the equator or to supplement
the existing net; others were phased out (Havana, Ft. Stewart, Antofagasta, San
*The Minitrack ground equipment required at least 0.093 square kilometer with a minimum gradient
of less than I degree in the area of the antenna arrays. For 8 kilometers in all directions from the equip-
ment, the elevation angle could not exceed 20 degrees. The site also had to be isolated from heavy electric
power installations and airways.
Diego) when they were no longer needed or when conditions at the station became
unfavorable; collateral stations established by other countries became part of the
network as they were needed (see table 5-20 for a chronology of these events and
table 5-27 for a complete list of NASA's tracking stations). New telemetry reception
and command equipment that corresponded with new hardware and scientific in-
struments carried by NASA's satellites was added to certain stations as it became
available. Telemetry antennas grew in size. Station operations became more com-
plex. Reliable communications between stations and mission control became more
critical. In 1960, the network switched to a frequency range of 136-137 megahertz, a
range set aside by the International Telecommunications Union for space research.
The Rosman, North Carolina, station, which became operational in 1963, was the
NORTH
AMBIGUITY
ARRAY
_B
WEST EAST
101.7 m
(333.7 ft)
i
125.7 m
(412.3 ft)
Q I
SOUTH
Figure 5-4. Layout of a typical Minitrack station. A set of four antennas positioned & a par-
ticular configuration (in this instance, a cross) can detect signals from a spacecraft entering a fan-
shaped volume (about 10.8 degrees in one direction and 76 degrees in a direction at right angles).
A Minitrack station had two wuch sets of antennas so that there were two fan-shaped volumes
(at an angle of 90 degrees to one another) in which a vehicle couM be detected. One set, called
equatorial (E), had the narrow dimensions of the fam beam arranged east-west; the second set,
called polor (P), was oriented north-south. Equipment at a Minitrack station included the fixed
arrays for angle tracking, one fixed antenna array for telemetry reception, a rhombic communica-
tions antenna, a ground station electronics trailor, a telemetry trailor, and associated power sources
and maintenance units.
Source: From Samuel Glasstone, Sourcebook on the Space Sciences (New York: D. Van Nostrand, Co., Inc.,
1965), pp. 220-22.
538 NASA HISTORICAL DATA BOOK
first of a second generation of satellite tracking facilities that did not require an in-
terferometer. Its 26-meter pointable antenna would support the new observatory
class of satellites (OGO, OSO, OAO).*
As NASA's satellites became more sophisticated, data acquisition rather than
tracking became the more critical of the network's tasks, and the equipment added
to the stations reflected the change. Satellite Automatic Tracking Antennas
(SATAN)-one type for telemetry reception, a second for command-replaced the
Yagi arrays to serve either as a complement to the large dish antennas or as the prime
receiver-command antenna at stations where there were no large dishes. Since the
original Minitrack system could not cope with spacecraft sent into highly eccentric
or synchronous orbits (the latter a popular orbit for communications and weather
satellites), Goddard specialists devised an alternate tracking device called Goddard
Range and Range Rate Equipment (GRARR).t The GRARR sent a signal to the
spacecraft, which replied through a transponder. By recording the time of signal
transit to and from the satellite, distance could be determined, while Doppler
measurement could provide range rate.3 With all these changes, Minitrack was hard-
ly a suitable name for the network any longer.
By 1964, NASA officials were using the name Space Tracking and Data Ac-
quisition Network (STADAN) for the satellite net. Along with the new title came a
new trend. STADAN managers would work toward maintaining a minimum
number of stations, but they would equip those stations with the most efficient in-
strumentation available. The streamlining of the net precipitated the closeout of
Blossom Point, College, East Grand Forks, and Woomera stations, the transfer of
one of Alaska's 26-meter antennas to the Environmental Sciences Services Ad-
ministration, and the transfer of Kano station to the Manned Space Flight Network.
From 22 stations in 1965, the system was reduced to 17 (plus a training facility at
Goddard and two collateral stations) in 1968, with more closings planned for the
next year (see table 5-19). Increased automation was one of the key tools the Office
of Tracking and Data Acquisition used to improve the remaining stations and to cut
costs. If done manually, most tracking tasks (e.g., prepass checkouts, station
switchovers from one satellite to another, recording operations) required a great
amount of switch-throwing and careful monitoring and timing. During the
mid-1960s, automation began to increase the stations' flexibility and reliability. The
end of the decade brought increased computerization to many of the stations' track-
ing operations. OTDA's program for implementing the first level of station com-
puterization was known as Station Technical Operations Control. During the 1970s,
the use of computers to handle tracking and data acquisition tasks would increase
greatly.
Goddard Space Flight Center served as mission control for the satellites that
STADAN supported. 4 Before communictions between the stations and Goddard
*NASA's first 26-meter pointable antenna was built at the Alaska station in 1962 to support Nimbus
operations. Minitrack's telemetry reception antennas could not handle the large amounts of data that
were produced by picture-taking weather satellites. Rosman's two 26-meter antennas were completed in
1962 and 1964. Another was erected at Orroral Valley, Australia, in 1965.
t Under contract, Space Technology Laboratories built the first GRARR in 1961. Motorola, General
Electric, and General Dynamics/Electronics also built GRARR units for NASA. GRARR equipment was
installed at Carnarvon, Santiago, Tananarive, Fairbanks, and Rosman.
TRACKING
ANDDATA
ACQUISITION 539
Figure 5-5. Minitrack stations, 1961. By this time, five of the original Minitrack stations had been
phased out and replaced (Antigua, Ft. Stewart, Grank Turk, Havana, and San Diego). A col-
lateral station was also in operation at South Point, Hawaii.
Source: From Samuel Glasstone, Sourcebook on the Space Sciences (New York." D. Van Nostrand, Co., Inc.,
1965), p. 218.
were completely reliable, the individual stations often played the role of flight con-
trollers. But by 1964-1965, the NASA communications system (NASCOM) was in
operation, and project participants could command their satellites from one control
center. The trend at Goddard's mission control facility in the mid-1960s was toward
establishing "project unique" control areas (i.e., separate centers for OGO, ATS,
Tiros, and other projects). Nine of these posts were in operation in 1967. To con-
serve funds, however, the control operations were being centralized in the late 1960s
into a Multisatellite Operations Center (the control of meteorology satellites would
remain separate from the others).
Goddard was also the site of the Network Test and Training Facility (NTTF).
Here new equipment destined for tracking stations was tested and new personnel
trained. Equipment from the Blossom Point, Maryland, prototype Minitrack sta-
tion was transferred to NTTF in 1966. Tracking and data acquisition was one of
Goddard's primary functions, and John Mengel as assistant director for tracking
and data systems orchestrated the many tasks it involved. Ozro M. Covington, who
had helped instrument DoD's White Sands Missile Range in the 1940s, was Mengel's
deputy for most of the center's first decade. A 1967 reorganization that divided
satellite and manned operations left Covington as assistant director for manned
flight support.
One other element that played a part in satellite tracking from the Vanguard
days through NASA's first decade was the Smithsonian Astrophysical Observatory
540 NASA HISTORICAL DATA BOOK
Table-5-19.
NASA Satellite Tracking Stations
Ahmedabad x 1962
Alaska X 1962-?
Antigua x 1957-61
Antofagasta x 1957-63
Blossom Point t x 1956-66
Brazilia Project SERB 1962
Carnarvon x 1964-74
College High-inclination 1960-66
College Park** 1962-64
Darwin OGO 1966-69
East Grand Forks High-inclination 1960-66
Ft. Myers X 1959-72
Ft. Stewart x 1957-59
Grand Turk x 1957-61
Havana x 1957-59
Johannesburg X 1958-75
Kano ISIS 1965-66
Kasima Machi x 1967-70
Kauai ISIS 1965-
Lima x x 1957-69
Majunga Indian O.-inclination 1963-64
Mojave X 1960-69
Network Test and Training
Facility** 1966-
Orroral Valley X 1965-
Quito x X 1957-
Rosman X 1963-81
San Diego x 1957-60
Santiago x X 1957-
Singapore x 1963-70
Solant x 1963-?
South Point x 1961-66
St. John's X 1960-70
Tananarive X 1965-75
Toowoomba X 1966-69
Wink field X 1961-?
Woomera x 1957-66
Tracking Network.* This optical tracking network could be used only at dawn and
dusk under clear conditions when the sky was fairly dark (the satellite was made visi-
ble by reflected sunlight). Though its use was restricted, optical trackers could pro-
vide highly accurate data with their Baker Nunn cameras. Although the approximate
position of the satellites had to be known beforehand, the optical system was also
called on to track vehicles that did not carry radio beacons. The Smithsonian net-
work provided support to NASA's tracking operations under contract.
*The 12 SAO stations were located at Arequipa, Peru; Comodoro Rivadavia, Argentina; Debre Zeit,
Ethiopia; Dionysos, Greece; Dodaira, Japan; Island Lagoon, Australia; Maui, Hawaii; Mt. Hopkins,
Arizona; Naini Tal, India; Natal, Brazil; Olifantsfontein, South Africa; and San Fernando, Spain. For a
history of the SAO, officially in existence since 1890, see Bessie Zaban Jones, Lighthouse of the Skies; the
Smithsonian Astrophysical Observatory: Background and History, 1846-1955 (Washington: Smithsonian
Institution, 1965). See also Constance McLaughlin Green and Milton Lomask, Vanguard: A History,
NASA SP-4202 (Washington, 1970), pp. 149-54.
Table 5-20.
Chronology of Space Tracking and Data
Acquisition Network (STADAN) Development and Operations
Date Event
1948 As part of the Army Air Corps MX-774 project (a forerunner of the Atlas
ICBM program), a radio interferometry tracking system was established
(called the Azusa system). A Naval Research Laboratory (NRL) team work-
ing on underwater sound (acoustic) interferometers was in contact with the
Azusa group; they informally exchanged ideas about the technology involved
in their respective projects.
Early 1950s The Navy borrowed the Azusa technology for its Viking missile project.
1950-1955 The Air Force, in establishing its missile range near Cape Canaveral, set up
tracking and instrumentation stations along an 8000-kilometer stretch. The
stations included Grand Bahama, Grand Turk, the Dominican Republic, and
Mayaguana. Tracking instruments also were installed on aircraft and ships to
augment the range.
1955 Of the two serious American proposals for orbiting an International
Geophysical Year (IGY) satellite, NRL's Vanguard included a radio tracking
scheme derived from the Navy's Viking experiences; the Army's Orbiter pro-
posal suggested optical tracking.
April 1955 NRL specialists generated a document entitled "Proposal for Minimum
Trackable Satellite (Minitrack)." An appendix of this document discussed the
proposed Vanguard tracking system, Minitrack (the name was coined by
John Mengel, one of the report's authors).
Sept. 9, 1955 The Department of Defense (DoD) authorized NRL to proceed with its Proj-
ect Vanguard and the Minitrack system (Mengel would lead the NRL Radio
Trackitlg Branch).
Dec. 1955 The number of proposed Minitrack stations in a network primarily along the
75th meridian grew from two to nine.
542 NASA HISTORICAL DATA BOOK
Table 5-20.
Chronology of Space Tracking and Data
Acquisition Network (STADAN) Development and Operations (Continued)
Date Event
Spring 1956 An NRL team led by Winfred Berg toured South America and negotiated
agreements for six Minitrack stations (Havana, Panama, Quito, Lima, An-
tofagasta, and Santiago). Construction would be the responsibility of a Proj-
ect Vanguard Task Force of the Army Map Service. Plans were also under
way for the operation of U.S. stations (Blossom Point, Maryland, San
Diego, and downrange stations near Cape Canaveral-Antigua and Grand
Turk). This put the number of stations at 10.
July 1956 Blossom Point station went into operation, serving as a training center for
tracking operations and as a test facility for Minitrack equipment and pro-
cedures.
Oct. 1, 1957 The Minitrack network became operational. The stations included Antigua,
Antofagasta, Blossom Point, Ft. Stewart, Grand Turk, Havana, Lima,
Quito, San Diego, Santiago, and Woomera.
Nov. 8, 1957 In response to delays with Vanguard and the success of Sputnik, the
Secretary of Defense announced that the Army with the support of the Jet
Propulsion Laboratory (JPL) would also participate in the IGY attempt to
launch a satellite. Their project was renamed Explorer. The original optical
tracking scheme had been replaced by a system developed at JPL called
Microlock, which combined Doppler tracking and interferometer receivers.
For the early Explorer satellites (1958), three Microlock tracking stations
were established in a network called Spheredrop.
March 17, 1958 Vanguard 1 was successfully launched and tracked by NRL.
Oct. 1, 1958 The newly established NASA assumed responsibility for Vanguard, including
its tracking network. Mengel became assistant director for tracking and data
systems at the Goddard Space Flight Center.
1958-1961 Minitrack was used successfully to track NASA's early scientific satellites.
Antigua and Grand Turk were phased out in July 1961; stations were added
in Alaska and East Grand Forks in 1960; Ft. Myers replaced Ft. Stewart in
1959; Cuba station was phased out in 1959; Johannesburg, Mojave, and St.
John's were added in 1960; the San Diego facility was phased out in August
1960; South Point, Hawaii, began serving as a collateral station in 1961.
Spring 1961 NASA Headquarters managers began to search for a more appropriate name
for the satellite network; suggestions included Satellite Tracking and In-
strumentation Network and Satellite Instrumentation Network.
1962
Although Minitrack continued to be suitable for NASA's early satellite pro-
gram, the agency's plans for the future called for more sophisticated payloads
and orbits that would demand more support than the Minitrack net could
give. Ahmedabad, a collateral station in India, was added; Alaska station got
a 26-meter antenna; telemetry reception equipment was erected at Brazilia to
support Project SERB (Study of the Enhanced Radiation Belt); telemetry
receiving and tape recording equipment was installed at a NASA data proc-
essing facility at College Park, Maryland; a 26-meter dish was under con-
struction at Rosman, North Carolina. The tracking stations continued to be
called Minitrack (M/T) stations, with the entire system being generally re-
ferred to as the satellite network (or less frequently as the electronics satellite
system).
TRACKING AND DATA ACQUISITION 543
Table 5-20.
Chronology of Space Tracking and Data
Acquisition Network (STADAN) Development and Operations (Continued)
Date Event
1963 The first of a new generation of satellite tracking stations was dedicated in
October. Rosman station was established specifically to receive telemetry
from the new observatory-class satellites (OGO, OSO, OAO). Rosman did
not have a Minitrack-type interferometer. Antofagasta and Brazilia were
phased out, with equipment from the latter being installed in a new station at
Majunga, Madagascar. Collateral stations on Singapore and Solant were put
into operation.
1964 The trend in satellite tracking was toward fewer stations, with a greater em-
phasis on data acquisition. Attempts were made to consolidate stations and
supply the facilities that remained in the net with improved equipment to con-
trol and handle the high data output rates of new scientific satellites. NASA's
satellite tracking system came to be known officially as the Space Tracking
and Data Acquisition Network (STADAN). A second 26-meter dish went
into operation at Rosman, and range and range-rate equipment was installed
at Carnarvon. Majunga and College Park stations were closed.
1965 Activity was under way at three new stations in Australia: at Darwin to sup-
port OGO, in the Orroral Valley where a 26-meter dish was installed, and at
Toowoomba in support of ATS. Kano station in Nigeria was opened to get
better coverage for ISIS, an ionospheric research program. Kauai, Hawaii,
was used for the same purpose. Range and range-rate equipment was being
installed at Tananarive station. At Goddard, specialists were investigating
methods of computerizing STADAN stations so that they could process the
greater amounts of data expected from new satellites (the program for im-
plementing the first level of station computerization was called Station
Technical Operations Control).
1966 Six STADAN stations were phased out during the year (Blossom Point, Col-
lege Park, East Grand Forks, Woomera, Kano, and one of the Alaska sta-
tion's 26-meter dishes). Blossom Point's equipment was transferred to the
new Network Test and Training Facility at Goddard. Additional equipment
and a 12-meter antenna were installed at Tananarive. Transportable equip-
ment, including a 12-meter antenna, was put into place at Toowoomba for
the ATS program. This was the last year of operation for the South Point sta-
tion.
1967 A new collateral station was put into operation at Kasima Machi by the
Japanese. At mission control at Goddard, nine project-unique control
centers were established for OSO, OGO, OAO, space physics, multisatellite
operations, atmospheric studies Explorers, ATS, Tiros, and geodetic
satellites.
1968 At the end of NASA's first decade, 16 STADAN stations were in operation:
Alaska, Carnarvon, Darwin (phased out in 1969), Ft. Myers, Goddards' test
and training facility, Kauai, Lima (phased out in 1969), Mojave, Orroral
Valley, Quito, Rosman, Santiago, St. John's, Tananarive, Toowoomba
(phased out in 1969), and Winkfield. In addition, three collateral stations
supported STADAN at Kasima Machi, Singapore, and Solant.
544 NASA HISTORICAL DATA BOOK
More than a decade before NASA Headquarters managers named the members
of the Space Task Group and charged them with leading the agency's manned space
program, the National Advisory Committee for Aeronautics and the military were
working on ground instrumentation that could be used for tracking high-speed air-
craft and guided missiles. NACA's Pilotless Aircraft Research Station at Wallops
Island tracked experimental aircraft and rockets with radar as they made their way
over the Atlantic. The military established ranges in the deserts of New Mexico and
across the south Atlantic from Florida to the islands of the Bahamas
(1600-kilometer range) and later on to Barbados (8000-kilometer range). The Air
Force set up radar and telemetry equipment at several locations along the Atlantic
missile range and connected the stations by undersea cable. Equipment borne by air-
craft and ships augmented the island-station system.
In the 1950s, NACA and the Department of Defense established a joint high-
speed research aircraft program that called for sophisticated tracking and com-
munications gear. In the opinion of many, the logical extension of this joint pro-
gram was earth orbital flight, and accordingly, tracking specialists began to define
the global tracking network such a mission would require. To pull together the
several teams that were working on tracking schemes and instrumentation, NACA
Director Hugh L. Dryden in the spring of 1958 suggested establishing an interagency
Working Group on Ranges, Launch, and Tracking Facilities. At about the same
time, the Advanced Research Projects Agency (ARPA), in answer to great interest
being shown by the military, formed an ad hoc Ground Based Information System
for Support of Manned Space Flight Committee (known as GBIS). In October 1958
when President Dwight D. Eisenhower assigned the exploration of space to the new
civilian space agency, it had a respectable well of tracking-data acquisition
knowledge from which to draw. But the steps from range to network, from studies
to operations would be giant ones.
The Space Task Group (STG), housed at Langley from its beginnings in 1958
until November 1961 when it became the nucleus of the new Manned Spacecraft
Center in Houston, had a huge task ahead of it, of which tracking was only one of
several critical parts. STG's mission planners established the base requirements for
manned flight tracking operations and put a team of specialists, the Tracking
Systems Study Group of Langley's Instrumentation Research Division, to work to
find the means and techniques to meet these criteria. Project Mercury, the first step
in NASA's manned program, had four broad tracking needs: (1) continuous
coverage by all systems from launch to orbital insertion and again during reentry
maneuvers; (2) periods of no contact not to exceed 10 minutes during the first one or
two orbits; (3) at least one contact of several minutes per orbit (preferably per hour)
during later orbits; and (4) reliance on state-of-the-art hardware that required little
or no further development. Manned spaceflight demanded two-way voice com-
munications, telemetry trajectory measurements, and uplinked commands, and it
made these demands around the globe.
The man responsible for Mercury tracking in the early days was Edmond C.
Buckley, an instrumentation expert from Langley who had helped set up the ranges
at Wallops and at the High-Speed Flight Station in California. In January 1959, the
Space Task Group was formally relieved of the tracking responsibility for Mercury,
TRACKING AND DATA ACQUISITION 545
and Buckley and his people were established as the Tracking and Ground Instrumen-
tation Unit (TAGIU), an organizational entity at Langley separate from the STG.
Buckley, however, was assigned a management role at NASA Headquarters soon
thereafter, and G. Barry Graves, Jr., an electronics engineer, was named TAGIU's
new leader. In addition to their own skills and knowledge, the Mercury tracking
team had two groups from whom to tap ready expertise-the satellite trackers at the
Goddard Space Flight Center, and members of the electronics industry who were
already familiar with tracking requirements and equipment through their work for
the military. Specialists from Goddard were soon applying their experiences with
communications and computers to Mercury's unique problems. Representatives
from interested companies attended a preliminary bidders' conference on tracking,
telemetry, and telecommunications needs for Mercury in early April 1959; the next
month they had in their hands official specifications for the ground instrumenta-
tion, a plan called S-45. Formal competition among potential contractors began in
June.
S-45 stressed conservative design principles and astronaut safety. Mercury
tracking stations around the globe would be equipped with proven C-band (RCA
FPS-16) and S-band (Reeves Instrument Corp. Verlort) radar units.* A new piece of
hardware, an active acquisition aid, would assist the narrow-band radars in locating
the orbiting spacecraft. Additionally, Mercury would be equipped with
transponders to ensure a strong return signal. The telemetry receivers would, of
course, be compatible with the transmitters carried on the spacecraft, all of which
would be built with off-the-shelf components. Manufacturers of the uplink com-
mand equipment were to follow the same guidelines. UHF (ultrahigh frequency)
radio was specified for the primary communications link between the spacecraft and
ground stations, with an HF (high frequency) backup and a second set of UHF
equipment available at each ground station. Communications on the ground
(telemetry, commands, radar acquisition data, tracking data, voice messages,
teletype) were to be real-time. Two IBM 7090 computers would operate at
Goddard's computing center to made the computations necessary for real-time
monitoring and spacecraft control. A backup computer would be installed at Ber-
muda station to help make the go/no go decision for orbital insertion if communica-
tions to and from the island should fail during that critical juncture. The Mercury
Control Center would be located at Cape Canaveral) Industry would not be called
*Radar (a contraction of "radio detection and ranging") was used to locate a spacecraft and deter-
mine its velocity and direction of movement by means of radio waves. Pulses of electromagnetic waves
were transmitted by a directional antenna at a ground station, rotated or scanned over a certain sector at a
constant rate. The pulses were reflected back to earth by the spacecraft. In the case of Mercury, the pulses
triggered a repeater radar set on the capsule, which transmitted a stronger return signal via a radio
transponder. Range was determined by measuring the time it took the radar signal to reach the target and
return. The spacecraft's direction in respect to the radar unit was determined from the direction in which
the pulse was transmitted. Velocity was determined by applying the Doppler princile and making the ap-
propriate calculations: if the object were approaching the unit the frequency of the returned signal was
greater than the frequency of the transmitted signal; if receding the returned frequency was less; if not
moving the returned and transmitted frequencies were the same. The S-band radar operated at frequen-
cies of 2700-3000 megacycles, the C-band at 5400-5700 megacycles. Verlort radar units were utilized for
long-range (1100 kilometers) tracking; the FPS-16s pinpointed the capsule within half a degree at 920
kilometers (as modified for NASA).
546 NASA HISTORICAL DATA BOOK
on to build the total package outlined in S-45 for a global network of 17 stations,
since some of the facilities needed to support Mercury were already in existence as
part of the military ranges. The new sites would connect the Pacific Missile Range
(California) with the Atlantic Missile Range (Florida), continue the net across
Africa, the Indian Ocean, Australia, and the Pacific. S-45 made general recommen-
dations for the locations of new stations, but following the satellite trackers' lead the
Mercury specialists would send survey teams to choose the precise sites for their
overseas facilities. Again, NASA's International Programs Office would play a key
role in negotiating agreements in the many foreign countries that would host Mer-
cury stations.
It did not take TAGIU long to choose a group of contractors for the construc-
tion of thc Mercury network. The planned completion date of the net, June 1, 1960,
did not leave time for lengthy evaluations. A team composed of Western Electric,
Bell Telephone Laboratories, Bendix Corporation, IBM, and Burns and Roe-do-
ing business as WECo-was awarded a letter contract in July 1959:* WECo was
directed to construct and equip stations at Bermuda; Canton Island in the Pacific;
Corpus Christi, Texas; Grand Canary Island; Guaymas, Mexico; Kano, Nigeria;
Kauai, Hawaii; Muchea and Woomera, Australia; and Zanzibar. NASA-owned
equipment was also needed for facilities at Cape Canaveral, Grand Bahama Island,
Grand Turk Island, Eglin Air Force Base, Point Arguello, and the White Sands
Missile Range. The contractors also supplied the Wallops Island demonstration site
station with equipment, where hardware and new procedures were tested. DoD
would contribute additional ground support, plus two tracking ships (Rose Knot
Victor and Coastal Sentry Quebec) for the Atlantic and Indian Oceans.
That summer, NASA requested the assistance of eight foreign governments in
establishing sites for its Mercury tracking stations, with the first technical visits tak-
ing place during the late summer and fall of 1959.t Although formal agreements
were not always speedily obtained, actual costruction was under way at all sites in
1960. For several reasons independent from the tracking operations, Mercury's
flight schedule slipped several times, giving the NASA-contractor team extra months
to ready all the ground stations and train personnel to operate them. The final
master plan called for an operational network by June 1, 1961. The last station,
*WECo (from Western Electric Company) was also sometimes called the Systems Engineering
Group. The five participants were assigned separate responsibilities as follows: Western Electric-overall
management, equipment procurement, installation and testing, ground communications system design,
and personnel training; Bell-systems analysis, command and control display design for Cape Canaveral
and Bermuda, and a flight controller-astronaut simulation system; Bendix-telemetry and site display
equipment, radar units, and capsule communication equipment; IBM-computer programming and
operation at Goddard and Bermuda and maintenance and operation of Cape Canaveral's launch and
display data subsystem; and Burns and Roe-construction, management, logistics, and operation of
nonelectric equipment. The radar units Bendix was to modify for the Mercury net were to come from
RCA and Reeves Instrument Corp. Since the relationship between RCA and Bendix, who were com-
petitors, was not a good working one, NASA directly acquired the seven RCA FPS-16 units it required;
Bendix then modified them according to plan, lengthening their range from 460 to 920 kilometers and
adding a display and control package (the Instrumentation Radar Acquisition Kit).
1Original plans called for a station on Guadalcanal, and contact with the appropriate authorities was
made. However, for reasons of economy, this potential site was dropped for consideration before a
technical visit was made.
TRACKING AND DATA ACQUISITION 547
Kano, was finished in March 1961; the net was operating in July (table 5-21 lists the
manned tracking stations; more complete information is provided in table 5-27).
By early 1961, it had become apparent that Langley was not the best place for
the Tracking and Ground Instrumentation Unit. The Space Task Group would be
leaving for Texas soon; it was also time for TAGIU to find a new home that was less
isolated from NASA Headquarters and tracking operations. Goddard Space Flight
Center was the logical choice. Tracking and data systems personnel under John
Mengel were already overseeing satellite tracking operations and Mercury com-
munications and were slated to assume responsibility for operating the Mercury net-
work during the third quarter of 1961. Assisting the specialists who transferred to
Goddard from Virginia was Niles R. Heller, chief of manned spaceflight support for
Mengel until 1967, when Ozro Covington took the newly created post of assistant
director for manned flight support. Only a small contingent of TAGIU personnel re-
mained at Langley.* At headquarters in late 1961, the management of tracking and
data acquisition was centralized under Edmond Buckley. Planning and construction
over, the time had come for operations.
A concentration of five tracking facilities monitored the initial phases of a Mer-
cury mission (see fig. 5-6). Through the Bermuda station, flight controllers deter-
mined if the conditions were satisfactory for inserting the spacecraft into orbit. If
they were not, the mission could be aborted, with the capsule making an emergency
splashdown in the Atlantic or on the African continent. If the spacecraft were put
into orbit successfully, it made its way over the Atlantic, looping over Africa
heading for Australia; from Australia the orbits swept north near the Hawaiian
Islands heading for Mexico and the southern U.S. On the final orbit, retrofire
maneuvers preparatory for landing took place as the spacecraft approached North
America, with splashdown occurring in the Atlantic. Eighteen stations were
prepared to track the typical three-orbit missions planned for Mercury.
Before the first manned orbital mission in 1962, the network had several tests.
Individual stations calibrated their equipment by tracking aircraft equipped with
Mercury-type electronics gear. Stations practiced procedures and simulated mis-
sions. The entire network participated in computer-controlled practice runs, during
which the specialists at Goddard analyzed response times and data flows, made sug-
gestions for improvements, and called for more simulations. Mercury-Redstone
ballistic missions gave the Atlantic area stations a workout in December 1960 and
March 1961 and again in May and July when NASA put its first two astronauts into
space. The first orbital mission came on September 13, 1961. MA-4 (unmanned) was
tracked successfully by the net during its single orbit of earth. Network and STG
personnel had hoped to conduct a more thorough test of the tracking system via a
small instrumented satellite, but Mercury-Scout 1 was destroyed seconds after liftoff
on November 1, 1961. A technical error had caused the vehicle to behave erratically,
and the range safety officer had been forced to terminate the launch (see table
5-22).t There was no opportunity for a second try. 6 When the day finally came for
the first orbital manned flight, however, all network systems proved themselves.
* TAGIU leader Graves resumed his work with Langley's Instrument Research Division.
MA-6 with John H. Glenn, Jr., aboard made three orbits on February 20, 1962,
while the network below tracked, communicated, and received data as it was de-
signed to.t
Table 5-21.
NASA Manned Spaceflight
Tracking Stations
Antigua a x x 1967-70
Antigua a x x x
Ascension a x x x 1967-
Ascension a x x
Bermuda x x x 1961-
Canton Island x x 1960-67
Cape Canaveral/ x x x x 1961-
Cape Kennedy
Carnarvon x x x 1964-74
Corpus Christi x x x 1961-74
East Island b x
Eglin x x x
Goldstone x x 1967-
Grand Bahama a x 1967-70
Grand Bahama a x x x x
Grand Canary x x x 1961-75
Grand Turk x x x x 1961-?
Guam x 1966-
Guaymas x x x 1961-70
Honeysuckle Creek x 1967-
Kano x x x 1961-67
Kauai x x x x 1961-
Kwajalein b x
Madrid x x 1967-
Merritt Island x 1973-
Muchea x 1961-64
Patrick x x
Point Arguello x x x 1961-?
Pretoria x x x 196?-?
San Nicolas b x
Tananarive x x x 1965-75
TEL-4 x x
Vandenburg x x
Wake Island b x
Wallops Island x x 1961-67
White Sands x x x x
Woomera x x 1961-66
Zanzibar x 1961-64
TRACKING AND DATA ACQUISITION 549
Table 5-21.
NASA Manned Spaceflight
Tracking Stations (Continued)
Tracking ships:
American Mariner c x
Coastal 1 Sentry Quebec d x x x
Huntsville e x
Kingsport x x
Mercury d x
Range Tracker b x x
Redstone d x
Rose Knot Victo_ x x x
Twin Fall Victory x
Vanguard d x
Watertown e x x
Tracking aircraft:
ARIA (8)
a Both NASA and DoD operated tracking facilities here that were used to support NASA missions.
The code letters used for the two stations always differed. See table 5-27 for information on how the sta-
tions were equipped.
b Used during Mercury 9 only.
CUsed during Mercury 8 only.
d All or part of the tracking and data acquisition instrumentation was owned by NASA.
eUsed during Mercury 8 and later modified for Apollo.
Table 5-22.
Mercury-Scout 1 (MS-l) Characteristics
;l
r
o
o x_
_o_
__ZZ
z__
_0_
o _<_
z_ZN
<5<53
_z_O_
--z_z_
5
m _
_ZZ
I
, @\
I
TRACKING AND DATA ACQUISITION 551
Like the satellite tracking system, the manned network changed to meet new
mission profiles. There were only two three-orbit manned Mercury flights. Since
astronauts Glenn and M. Scott Carpenter (MA-7, May 24, 1962) and their Mercury
spacecraft had experienced few problems during the first two missions, the third
flight was lengthened to 6 orbits, the fourth to 22 orbits. Since the tracks of the or-
bits for all missions would stay in a band of latitude of almost 66 degrees (roughly
33 °N by 33 °S), NASA did not have to provide a great amount of extra support for
the longer missions, but the network needed beefing up, especially in the Pacific.
For MA-8, the Rose Knot Victor, carrying new command equipment, was moved
from the Atlantic to the Pacific, south of Japan. Three other DoD instrumented
ships (American Mariner, Huntsville, and Watertown) were positioned near Midway
Island. These four ships assisted the network with both voice and telemetry opera-
tions. To support MA-9's 22 orbits, DoD provided NASA with supplementary
coverage from ships and ground stations. In the Pacific, Coastal Sentry Quebec,
Range Tracker, and Rose Knot Victor were added to the net, along with stations on
Wake Island, Kwajalein Island, and San Nicolas Island, California (voice only).
Twin Falls Victory operated in the Atlantic range, as did DoD facilities at Ascension
Island, Antigua, and East Island, Puerto Rico. In addition, DoD aircraft with voice
relay and radar equipment assisted during reentry and landing.
Before the Mercury stations were even operational, the Space Task Group was
thinking beyond earth orbital missions to lunar expeditions. They established an
Apollo Technical Liaison Group for Instrumentation and Tracking to study the new
problems they would face tracking and communicating with a manned spacecraft
near and on the moon. But NASA did not leap from Mercury to Apollo without an
intermediate step that allowed the agency to gain expertise with two-man crews in
larger and more sophisticated spacecraft, rendezvous maneuvers involving two
vehicles, and lengthier missions. The manned network had to expand its operations
as well during Project Gemini. By early summer 1962, specialists at Goddard were
ready with recommendations for how the Manned Space Flight Network (MSFN)
should be changed to support the next step in manned flight, keeping in mind that
the network should be evolving toward a configuration that could eventually meet
Project Apollo's tracking requirements. Because Gemini's long missions would
repeatedly take the spacecraft beyond the normal limits of the Mercury stations, the
network would have to expand geographically if the project managers wanted voice-
communication time comparable to that required during Mercury. Goddard
trackers proposed less frequent voice contact, and the Gemini personnel in Houston
agreed to this constraint. For Mercury, several different frequencies had been used
for the communications subsystems (voice, telemetry, command, tracking); for the
trackers, unifying all these into a single frequency was highly desirable. But for the
designers and engineers at the Manned Spacecraft Center, this was an im-
possible-albeit admirable-goal that would require too many onboard systems
changes. For now, this idea was shelved. Both parties agreed to convert the analog
telemetry system to a more efficient digital system (pulse code modulation, or
PCM). Likewise, the tracking group in Maryland wanted the uplink commands in a
digital form so that station computers could handle both telemetry and command.
Because they feared software errors with the station computers, Gemini personnel
refused to go along with the command half of this scheme. Computer-driven
alphanumeric displays, however, was another area of agreement at Goddard and
552 NASA
HISTORICAL
DATABOOK
Houston.*Thetrackingstationswouldrequiremoreequipment to trackandcom-
municatewith two vehicles(eithera Geminispacecraftandan unmanned target
vehicleor twoGeminispacecraft)duringrendezvousmaneuvers. In addition,these
two-vehicle missions
wouldneedincreasedcomputersupportatmissioncontrol.For
mostof ProjectGeminiandallof Apollo,missioncontrolandmissioncomputing
wouldbecentralized atthecenterin Houston,wherenewfacilitieswerebeingbuilt.
Goddardwouldcontinueitsroleasthetrackingoperations center.
Themovetowardincreased computerization
anddecreased voicesupportmade
possiblea morecentralized networkwith fewerprimarystationsandmorese-
condarystations.Somesitesthathadbeennecessary for Mercurycouldbedropped
duringGemini,althoughthosemajorfacilitiesthatstayedin thenetwouldhaveto
bebetterequipped.Someof thehardwarefromWoomerastationandthe entire
facilityatMucheawerecombined tomadeanewprimaryAustralianstationatCar-
narvon.OtherprimarystationsincludedCapeKennedy, Bermuda, GrandCanary,
Kauai,Guaymas, andCorpusChristi.Addingtheirsupporttothelaunchareawere
Eglin,GrandBahama,GrandTurk, Antigua,Ascension, andRose Knot Victor
(with command capabilities). In Africa, secondary stations were operated at Kano
and Pretoria. When the Zanzibar station had to be abandonded in 1964 because of a
revolution that threatened the safety of the personnel, Tananarive in the Malagasy
Republic off the east coast of Africa became that locale's secondary station.
Woomera offered radar and voice support in Australia. Canton Island and Coastal
Sentry Quebec (with command capabilities), positioned south of Japan, helped
bridge the Pacific. At the end of the orbital track were Point Arguello and White
Sands, now secondary stations. A large industry team had the Gemini network "on
line" by the spring of 1964, in time for practice runs during a Saturn vehicle test
(SA-6), the first Gemini-Titan flight (GT-1, unmanned), and a Centaur vehicle
development mission (AC-3). All was ready in 1965 for the first manned Gemini
flight. 1 7
Gemini's first manned mission (Gemini 3), a three-orbit check-out flight, took
place on March 23, 1965. The next two flights gave the network its first lengthy exer-
cise-62 and 120 orbits (Gemini 4 and 5, June and August 1965). In December,
Gemini 7 and 6-A conducted rendezvous maneuvers. The net was kept especially
busy in 1966 with five missions, all of which included rendezvous and docking
operations by the Gemini spacecraft with unmanned target vehicles. The centralized
network with its reduced number of primary stations proved adequate for Gemini.
Apollo, however, would force further changes on the system.
Apollo activities would include operations near earth, in cislunar space, in lunar
orbit, and on the moon's surface, most of which was beyond the manned network's
grasp as it was configured for Mercury and Gemini. But NASA had begun to consult
*During their first meeting in June 1962, Goddard tracking specialists and Project Gemini personnel
from MSC did not agree on many items on the trackers' list of proposed changes. By the time of their next
major session in June 1963, the two sides were able to work out an agreement on how the network should
be instrumented.
"lThe companies participating in the construction and equipping of the Gemini network were ITT,
Canoga Electronics Corp., Bendix Corp., Electro-Mechanical Research, Inc., RCA, IBM, AT&T, Col-
lins Radio Co., Radiation, Inc., and UNIVAC.
TRACKING AND DATA ACQUISITION 553
with deep space tracking experts regarding Apollo's unique requirements as early as
1961. The Jet Propulsion Laboratory in Pasadena, California, had been in the
tracking and data acquisition business since the early 1950s and had begun construc-
tion of its first 26-meter diameter dish antenna for tracking lunar probes before
NASA was established. In 1961 when the Apollo Technical Liaison Group for In-
strumentation began its work, the Deep Space Network was already four stations
strong with a fifth under construction. The Mercury-Gemini stations could be
adapted for Apollo's near-earth operations, and JPL's 26-meter antennas or ones
like them could reach out to Apollo spacecraft on and near the moon. However,
there was some doubt as to whether there were enough conventional MSFN stations
to enable the controllers to monitor two critical events: the transition from earth or-
bit to a lunar trajectory and the narrow-corridor, high-speed reentry into earth's at-
mosphere. And Apollo, with its requirement for television, would be sending back
more telemetry than the Mercury-Gemini stations could receive. NASA would have
to uprate the equipment at existing stations and augment the ground communica-
tions system before the network was ready for lunar missions.
In 1962, Edmond Buckley, director of the Office of Tracking and Data Acquisi-
tion at NASA Headquarters, appointed Gerald Truszynski to lead an Apollo Task
Group composed of specialists from headquarters, Goddard, and JPL. Working
with spacecraft designers at the Manned Spacecraft Center and at North American,
where spacecraft design studies were being prepared under contract, this task group
shaped the Apollo network. Their decision to introduce a unified (and higher) fre-
quency band, the S-band, for Apollo communications was especially important.*
Unified S-band (USB) might have been too great a leap for Gemini, but the experts
considered it a necessity for the manned lunar venture. One unified carrier system on
the spacecraft would take less space, weigh less, cause less heating, and require less
power than a multicarrier system. Another consideration was the better signal-to-
noise ratio the ground crews and astronauts would experience at the higher S-band
frequency.t By November 1962, the tracking people were ready with an instrumen-
tation support plan for near-earth Apollo operations, and OTDA had officially re-
quested JPL's assistance with the lunar portion of the flight plan and with the
development of a USB system. Planning over the next year called for the expansion
of Gemini stations with the installation of 9-meter USB antennas and associated
equipment and the construction of three 26-meter USB stations roughly 120 degrees
apart around the globe, located near Deep Space Network antennas at Goldstone
*S-band is that band of radio frequencies extending from 1550 to 5200 megacycles (in the upper por-
tion of the ultra-high frequency spectrum and the lower portion of the super-high frequency). The
Federal Communications Commission (FCC) wanted space communications moved out of the crowded
VHF range and into higher frequencies.
tThe original Deep Space Network stations were equipped with L-band rather than S-band equip-
ment, but in 1962 the decision was made to convert to the higher frequency. Because of ongoing missions
(primarily Ranger) that would suffer from an immediate changeover, an L/S conversion system was
devised. New facilities were provided with S-band; older stations were equipped with the L/S converter.
Complete transition to S-band was completed by 1967. This commitment to S-band by the DSN influ-
enced the MSFN planners' decision to adopt the higher frequency for Apollo.
554 NASA HISTORICAL DATA BOOK
*By locating the MSFN 26-meter antennas near existing DSN facilities, the manned network could
rely on the deep space antennas as backups in case of equipment failure and as a means for com-
municating with two lunar spacecraft simultaneously, as would be the case when Apollo's lunar module
separated from the command module and descended to the moon's surface. New MSFN support wings
were built at the three DSN stations so that Apollo ground operations would not interfere with scientific
missions they might be supporting.
TRACKING AND DATA ACQU ISITION 555
a
z
EI-
z
a
I-u
ZI
a 3
556 NASA HISTORICAL DATA BOOK
1. ANTENNA CONTROL
2. SPACECRAFT COMM
3. TLM RECORDING HF PROBE
4. SYSTEMS MONITOR ANTENNA
5. GROUND COMM
6. TIMING
7. POWER CONTROL
HF TRAILING WIRE
ANTENNA
COMBINED
S-BAND/VHF
ANTENNA
WEATHER
RADAR
lunar orbital) missions (see table 5-23). To test MSFN's new lunar operations sta-
tion, NASA exacted a double duty from Lunar Orbiter spacecraft that were
photographing the moon in search of safe and scientifically interesting landing areas
for Surveyor (unmanned) and Apollo. The new facilities at Goldstone, Madrid, and
Canberra, along with MSFN 9-meter stations, passively and actively tracked Lunar
Orbiters in 1966-1967, a valuable experience for the technicians operating the sta-
tions and extra insurance for Apollo.*
There was a hiatus of almost two years between the last Gemini and the first
manned Apollo missions. The trackers spent the time installing new equipment,
training personnel, and practicing the many new procedures Apollo would demand
of them. When Apollo 7's crew of three orbited earth in October 1968 in a successful
test of spacecraft operations, the network was also proven operational. In
December, Apollo 8 took its crew to the moon, orbiting earth's natural satellite 10
times. Scientific and engineering telemetry, photographic images, voice communica-
tions- all were received in good order by MSFN ground stations. Apollo was on its
way to meeting the ambitious goal President John F. Kennedy had established for
NASA.
&
<
l
558 NASA HISTORICAL DATA BOOK
o
TRACKING AND DATA ACQUISITION 559
Table 5-23.
Test and Training Satellite (TTS) Characteristics
TTS-1 TTS-2
Table 5-24.
Chronology of Manned Space Flight Network
(MSFN) Development and Operations
Date Event
Spring 1945 The National Advisory Committee for Aeronautics (NACA) established the
Pilotless Aircraft Research Station at Wallops Island, Virginia. PARD, the
division assigned to the new station, was charged with testing model aircraft
and aerodynamic shapes. Using the Atlantic as their test range, the specialists
tracked experimental vehicles with radar and analyzed the telemetry signals
they received. PARD launched its first rocket on July 4, 1945.
May 1946 An Army Signal Corps team led by Ozro M. Covington began instrumenting
the White Sands Missile Range.
1950 Guided missile launchings were begun at Florida's Long Range Proving
Ground (LRPG). Downrange tracking and observation stations were
established in the Bahamas and on other nearby islands (1600-kilometer
range). After the Air Force announced its plans in August for the accelera-
tion of its missile program, steps were taken to establish additional tracking
stations in Jamaica and the Dominican Republic.
1952 The Air Force Missile Test Center (AFMTC), formerly the LRPG, was plan-
ning to extend its missile range to 8000 kilometers with stations at Barbados,
off the coast of Brazil in the south Atlantic, and at Dutch Guiana and French
Guiana. These stations would be connected by an undersea cable com-
munications system. The expanded tracking-data acquisition system would
include equipment borne by aircraft and ships.
560 NASA HISTORICAL DATA BOOK
Table 5-24.
Chronology of Manned Space Flight Network
(MSFN) Development and Operations (Continued)
Date Event
1955-1957 The Naval Research Laboratory planned and put into operation its Minitrack
satellite tracking system. At White Sands and other missile ranges in the
U.S., the radar and communications equipment used for tracking operations
were becoming increasingly sophisticated. The system employed at White
Sands was called MINSTREL (Missile Instrumentation by Electronic
Means), a centralized real-time system. Both Air Force and NACA personnel
had begun to investigate a global tracking scheme for the Air Force's propos-
ed Dyna-Soar orbital lifting body.
1958 The Advanced Research Projects Agency (ARPA) approved the Department
of Defense's (DoD) Discoverer satellite project, which was originally planned
as part of an investigation of the technological problems the Air Force would
face in putting man into space. Although Discoverer did not lead to an Air
Force manned program, it did provide NASA and the services with data on a
number of topics and was instrumental in establishing a worldwide radar net-
work that would benefit the newly established civilian space agency's Project
Mercury.
Spring 1958 In March, NACA Director Hugh Dryden suggested that NACA, the military,
and others interested in the subject establish a Working Group on Ranges,
Launch, and Tracking Facilities. ARPA also established an ad hoc commit-
tee known as GBIS (Ground Based Information System for Support of
Manned Space Flight). At NACA's Langley center, Edmond C. Buckley of
the Instrument Research Division directed a group of specialists (the Track-
ing System Study Group) to study spaceflight instrumentation problems, in-
cluding ground and range instrumentation.
June 1958 The Air Force published a report entitled "Ground Based Information
Systems for the Support of Manned Space Flight."
November 1958 On the 5th, NASA established the Space Task Group (STG) to implement the
civilian manned spaceflight program. STG was to have become a part of the
new Beltsville Space Center (later Goddard Space Flight Center), but in the
interim the group was housed at Langley Research Center. NASA set up an
Atlantic Missile Range Operations Office at AFMTC.
Jan. 1959 It was recommended that STG be relieved of the responsibility for developing
the manned tracking network for Mercury. On the 26th, Buckley's tracking
group was enlarged and became known as the Tracking and Ground In-
strumentation Unit (TAGIU). Buckley was assigned to NASA Headquarters
as assistant director for spaceflight operations. G. Barry Graves, Jr., was
named the new leader of TAGIU. Also in January, NASA and DoD officials
signed an agreement regarding global tracking centers.
May 21, 1959 TAGIU issued its "Specifications for Tracking and Ground Instrumentation
for Project Mercury" (S-45).
Summer 1959 NASA contracted with four companies to accomplish tracking and data ac-
quisition tasks: Ford Aeronutronics-radar and trajectory computation
study; RCA Service Corp.-network specification writing; Space Elec-
tronics-mission control center design; and MIT Lincoln Labora-
tories-general consultation and proposal evaluation. TAGIU also sought
the assistance of Goddard computing and communications specialists (under
the management of Goddard's Niles R. Heller).
TRACKING
ANDDATA
ACQUISITION 561
Table 5-24.
Chronology of Manned Space Flight Network
(MSFN) Devdopment and Operations (Continued)
Date Event
June 22, 1959 Langley sent requests for proposals to industry based on S-45.
July 1959 The X-15 High-Range was put into operation with its three radar tracking
facilities. Edmond Buckley had been responsible for much of this work (he
had also worked on the instrumentation of the NACA Wallops Island fa-
cility).
July 29, 1959 A second edition of the network specifications was issued (S-45A).
July 30, 1959 NASA awarded a letter contract to an industry team-Western Electric, Bell
Telephone Laboratories, Bendix, Burns and Row, and IBM-for the
development of the manned spaceflight network.
July-Aug. 1959 NASA informed the following foreign governments that it required their
cooperation in establishing tracking stations: Bermuda, Nigeria, Zanzibar,
Australia, Guadalcanal, Canton Island, Mexico, and Spain (for Grand
Canary Island).
Oct. 30, 1959 A third edition of the network specifications was issued (S-45B).
Jan. 11, 1960 NASA executed a definitive contract with WECo, the industry team.
April 1960 Construction was begun on the first foreign Mercury tracking station.
July 7, 1960 The first meeting of the Mercury Network Coordination Committee was held
at Cape Canaveral. This group was assigned the task of overseeing problems,
primarily operational, that faced the network.
Sept. 14, 1960 A Space Flight Ground Environment Panel, part of the newly created
Aeronautics and Astronautics Coordinating Board (interagency), was
established to handle network coordination matters.
Jan. 6, 1961 The newly created Apollo Technical Liaison Group for Instrumentation and
Tracking (established by STG) held its first meeting. This body was in charge
of studying the problems of tracking, commanding, and communicating with
a manned lunar spacecraft.
Spring 1961 Construction of all foreign Mercury tracking stations was completed. Plans
were made to assign responsibility for the operation of the Mercury network
to Goddard during the third quarter of 1961.
Mid-1961 Ozro Covington and other personnel from White Sands were transferred to
Goddard to assist with the conversion of the Mercury network into a more
advanced system capable of supporting manned projects beyond Mercury.
Covington became deputy assistant director for tracking and data systems at
Goddard.
Sept. 13, 1961 The Mercury network functioned as planned during the first orbital flight
(MA-4, unmanned). There were 19 stations in operation (Cape Canaveral,
Grand Bahama, Grand Turk, Bermuda, Grand Canary, Kano, Zanzibar,
Muchea, Woomera, Canton Island, Kauai_ Pt. Arguello, Guaymas, White
Sands, Corpus Christi, and Eglin, plus 2 instrumented ships in the Indian and
Atlantic Oceans. The communications center was at Goddard.
Nov. 1961 STG moved to the new Manned Spacecraft Center (MSC) in Houston, Texas.
Nov. 1, 1961 An attempt to test the Mercury network with a small communications
satellite (Mercury-Scout 1) failed because of a technician's error prior to
launch. The vehicle was destroyed 43 seconds after liftoff.
562 NASA HISTORICAL DATA BOOK
Table 5-24.
Chronology of Manned Space Flight Network
(MSFN) Development and Operations (Continued)
Date Event
Feb. 20, 1962 The standard Mercury network functioned as planned during the first two
May 24, 1962 orbital missions (MA-6 and 7).
June 1962 Goddard engineers advised Project Gemini personnel of the changes that
would be required in the tracking network to support more advanced mis-
sions.
July 20, 1962 NASA announced that a new mission control center would be built at MSC
for Gemini. This center would also assume the mission computing tasks that
had been performed at Goddard.
Oct. 3, 1962 The MA-8 mission was six orbits long; three instrumented DoD ships were
added to the net. MSC requested the support of the Jet Propulsion
Laboratory (JPL) in developing a tracking and communications network for
Apollo. JPL personnel (Eberhardt Rechtin and Walter Victor) had been serv-
ing as consultants to the Apollo Technical Liaison Group for Instrumenta-
tion and Tracking since early 1961 because of their experience with deep
space tracking. Apollo's network would require the technology and services
represented by the Deep Space Network for lunar operations support.
Nov. 23, 1962 Goddard contributed its plans for an Apollo network in the form of a report,
"A Ground Instrumentation Support Plan for the Near-Earth Phases of
Apollo Missions" (X-520-62-211).
March 11, 1963 In a NASA Headquarters Apollo management plan, JPL was identified as a
major participant in the MSFN, along with Goddard.
April 23, 1963 The MA-9 mission was 22 orbits long. Various adjustments were made in the
network to support the additional orbits (DoD sites provided extra tracking
and telemetry capabilities).
June 1963 Goddard tracking and data acquisition personnel met again with Gemini
managers to discuss their proposed changes to the tracking network, which
had not been met with enthusiasm in Houston the previous year. At this
meeting, project managers agreed to the network plan with two stipulations:
station computers would be used for telemetry processing only, and the USB
proposal could not be implemented. The Gemini net would require fewer
prime stations than had Mercury's, but the primary stations that were
planned would be better equipped (secondary stations with limited facilities
would support the main stations).
Late 1963 Plans for the Apollo network called for the expansion of 7 Gemini stations to
include 9-meter USB equipment; the construction of 9-meter USB stations at
Merritt Island, Ascension, Antigua, and Guam; the construction of 3
26-meter USB stations at Goldstone, Canberra, and Madrid; the addition of
wings to existing Deep Space Network stations at Goldstone (Pioneer
station), Cebreros (Madrid), the Tidbinbilla (Canberra); the conversion of 5
ships to provide USB and C-band radar; and the conversion of 8 aircraft to
provide VHF/UHF and USB. The Apollo Network Implementation Plan
was drawn up on November 11.
TRACKING
ANDDATAACQUISITION 563
Table 5-24.
Chronology of Manned Space Flight Network
(MSFN) Development and Operations (Continued)
Date Event
April 20, 1964 In answer to plans for an accelerated flight schedule and other changes sug-
gested by MSC, the Office of Tracking and Data Acquisition at NASA Head-
quarters issued a second Apollo Network Implementation Plan.
March 23, 1965 The first manned Gemini mission (Gemini 3), only three orbits, took place
successfully. The tracking network functioned as planned.
May 1965 NASA and DoD officials signed a document outlining cooperative activities
the two organizations would be participating in during Apollo: "DOD-NASA
Agreement regarding Land-based Tracking, Data Acquisition, and Com-
munications Facilities."
June 3-7, 1965 The first lengthy manned Gemini mission (Gemini 4) was tracked successfully
by the MSFN during its 62 orbits.
Aug. 21-29, 1965 During Gemini 5, the new mission control center in Houston assumed
responsibility for the computing aspects of the mission.
Dec. 4-18, 1965 Gemini 6,4 and 7 accomplished rendezvous maneuvers on Dec. 15-16. The
tracking network successfully coped with the double load.
March-Nov. 1966 Five Gemini missions (Gemini 8, 9,4, 10, 11, and 12) took place in which the
Gemini spacecraft rendezvoused (and at times docked) with target vehicles.
The network tracked these pairs of spacecraft successfully.
Sept.-Dec. 1966 The following MSFN stations became operational for Apollo: Carnarvon,
Bermuda, Corpus Christi, Cape Kennedy, Kauai, Guaymas, Guam, and one
of five instrumented ships.
Jan.-June 1967 The following MSFN stations became operational for Apollo: Ascension,
Goldstone, Canberra, and Grand Bahama.
July 1967-Feb. 1968 The following MSFN stations became operational for Apollo: Antigua,
Madrid, Grand Canary, and the remaining four ships.
Nov. 9, 1967 The Apollo net participated in the Apollo 4 mission, an unmanned orbital
test of the launch vehicle and spacecraft (command module).
Dec. 13, 1967 The launch of TTS-I was successful. This small satellite served as a training
target for the Apollo network.
Oct. 11-22, 1968 The first manned Apollo mission (Apollo 7), earth orbital, took place suc-
cessfully, and the tracking net functioned as planned. (Parts of the MSFN
had been used in 1966-1968 to track unmanned Apollo-Saturn development
flights and Lunar Orbiter spacecraft.)
Nov. 8, 1968 The launch of TTS-2 was successful. This was a second training satellite for
the Apollo net.
Dec. 21-27, 1968 The first lunar orbital Apollo mission (Apollo 8) took place successfully with
a crew Of three. MSFN tracked the spacecraft as planned during its 10 orbits
of the moon.
564 NASA HISTORICAL DATA BOOK
Tracking a man-made object beyond the confines of earth orbit became an of-
ficial requirement in March 1958 when the Advanced Research Projects Agency
(ARPA) approved the Pioneer lunar probe series, with both the Army and the Air
Force participating independently. Communications specialists at the California In-
stitute of Technology's Jet Propulsion Laboratory (JPL) had been alerted to the
possibility of participating in such a mission in late 1957 when Cal Tech's president
and JPL's director had suggested to the Department of Defense that the country
pursue this particular goal.* Having been involved as a partner in the Army's early
missile and satellite work, JPL's experienced tracking-communications team was
able to suggest two possible schemes for tracking a spacecraft that would be
operating at such distances from earth that it would appear as a star, rising and set-
ting each day.
One of JPL's deep space radio tracking plans called for a single station in the
U.S. equipped with a large parabolic dish antenna. The station would be in contact
with the spacecraft during a single period daily when it was in view. Another scheme
included three stations. A network of three antennas located roughly 120 degrees
apart in longitude would provide continuous support for lunar and planetary space-
craft. Obviously, the three-station plan would give project personnel more oppor-
tunities for receiving data, monitoring spacecraft systems, and controlling the vehi-
cle. But implementing such a network would require facilities in foreign countries
and a reliable global ground communications system. Because the Army's first
Pioneer lunar probe was scheduled for launch in late 1958, JPL could not build an
entire network, but the tracking specialists did have time to erect a 26-meter-
diameter antenna (Pioneer station) in southern California's Mojave Desert and
deploy a mobile station near Mayaguez, Puerto Rico, for the first mission (see fig.
5-11). Unfortunately, none of the early Pioneer probes was successful. The Army's
Pioneer 3 did not achieve the velocity required for a lunar trajectory; Pioneer 4 did
not pass close enough to the moon for its experiments to record lunar data. The
tracking system, however, operated as planned, following Pioneer 4 some 651 200
kilometers.
JPL's tracking team, under the overall direction of NASA Headquarters and the
local leadership of telecommunications expert Eberhardt Rechtin, was occupied
over the next several years with building and improving the three components of
their deep space tracking system: a mission control center at JPL (the Space Flight
Operations Facility); a communications system that linked the tracking stations with
mission control and operated as part of the broader NASCOM (the Ground Com-
munications Facility); and the network of stations (the Deep Space Instrumentation
Facility). The original three-station plan had been altered somewhat. Antennas that
were to have been placed in Nigeria and the Philippines were destined for Spain and
Australia. A South African site was also added to the net. These locations would of-
fer the best support for NASA's lunar and planetary missions. But before construc-
tion of the first foreign station was begun, the Mojave Desert site (Goldstone) was
expanded. Echo station, built to track NASA's passive communications satellites,
became operational in April 1960. That fall, a 26-meter antenna near Woomera,
Australia, be_ -me the first overseas facility to begin operations. In time for the first
attempt at se_,ding Ranger probes to the moon, Johannesburg station and a mobile
compatibility test station at Cape Canaveral were added to the list. These additions
gave the network the strength to support two deep space missions simultaneously,
which it did during the fall of 1962 with Ranger 5 and Mariner 2 (Venus flyby). A se-
cond Australian station, Tidbinbilla near Canberra, and one in Spain, Robledo near
Madrid, plus a large 64-meter antenna at Goldstone (Mars station) were all under
construction in 1963. The manager of the Deep Space Network (DSN), as this ex-
panding system came to be called, received permission to erect a permanent test sta-
tion at the Cape in 1964. Goldstone saw one more DSN station put into operation;
Venus station with a 26-meter antenna would serve the net as a research and
development facility.
It was at this juncture that Project Apollo and the Office of Manned Space
Flight intruded on the deep space trackers' world of scientific missions. The Manned
Space Flight Network (MSFN) would be able to support relatively simple earth or-
bital operations, such as Mercury and Gemini flights, but Apollo planners proposed
operating two spacecraft simultaneously, one in lunar orbit and one on the moon.
Tracking lunar spacecraft was not possible with the manned network as configured
for Gemini; JPL's special expertise with deep space communications was in demand
on two fronts. Top-level managers at JPL were understandably reluctant to become
deeply involved in the Apollo enterprise, especially since the coming years promised
to be very active ones at the Pasadena center. Besides supporting JPL's Ranger lunar
probes, Surveyor lunar landers, and Mariner interplanetary craft, the Deep Space
Network would also be called on to participate in the Pioneer interplanetary probe
series being managed at Ames Research Center and the Lunar Orbiter project of the
Langley center. DSN personnel and facilities would assist with Apollo's operations,
but in a manner that did not negatively influence their primary roles.
The end result of the combined JPL-manned network effort was a hybrid.
Apollo's near-earth activities were supported by existing MSFN stations; lunar
operations were the task of three new 26-meter antennas built near DSN stations at
Goldstone, near Madrid, and in Australia. New wings that housed duplicate control
equipment were built at the three DSN stations so that the manned network could
augment its system or use the DSN antennas as backups without disturbing ongoing
ground operations. At Goldstone, a MSFN wing was added to Pioneer station in
1964. A new station being built near Madrid, Cebreros, was also equipped with a
dual wing. Tidbinbilla near Canberra was the last to get the extra ground equipment
it would need to support Apollo. A joint DSN-MSFN station with a 9-meter antenna
was also established on Ascension Island in 1965. As discussed elsewhere in this
chapter, the Apollo net proved successful in supporting the first manned spacecraft
to orbit the moon in 1968.
566 NASA HISTORICAL DATA BOOK
In addition to its traditional role as spacecraft tracker, the DSN was put to use
as a radio astronomy tool. Goldstone's Venus station was especially active in this
area. Built to serve as an advanced engineering and development facility with a high-
power radio transmitter, the antenna beamed radar signals to the moon, Venus,
Mercury, Mars, and Jupiter. By measuring the returned signals, scientists speculated
on the surface characteristics of the bodies and added to their knowledge of the
planets' positions and locations. In addition to the 26-meter reflector antenna,
Venus station was equipped with a 1/7-scale model of the large antenna built for the
Goldstone Mars station (see fig. 5-12). With the model, technicians tested the design
and operation of the 64-meter antenna's feed system. After Mars station became
operational in 1966, 5 percent of its working time was also allocated to radio science
experiments. DSN equipment could also be used for other investigations; for exam-
ple, by measuring the Doppler shift and signal attenuation characteristics of a signal
that has passed through a planetary atmosphere scientists can obtain a temperature-
pressure profile of the atmosphere.
JPL's Space Flight Operations Facility was the functional center of the network
(see fig. 5-14). As the net evolved, the operations facility changed with it. Old com-
puters were exchanged for new ones; new ones were used in series; more efficient
techniques for data storage were put to use. The transition from single-mission to
multimission support demanded a multimission telemetry system. And network
managers wanted equipment and procedures that could accommodate the Mariner
Mars 1969 goal of telemetering of 16 200 bits of data to earth during each second of
transmission. In 1968, prototype high-rate telemetry hardware was installed and
checked out at JPL and elsewhere in the net.
Eberhardt Rechtin, leader of the tracking group at JPL throughout most of the
decade, joined JPL in 1949. In a 1963 reorganization of the lab, Rechtin's title was
changed from chief of telecommunications (division 33) to assistant laboratory
director for tracking and data acquisition. In addition, he served as director of the
Deep Space Instrumentation Facility. Also vital to the management of the DSN in a
number of capacities were Walter K. Victor, Nichola A. Renzetti, and J. W. Thatch-
er. William H. Bayley was general manager of the network from 1963 until 1967,
when he took the lead position from Rechtin, who left JPL to become director of the
Advanced Research Projects Agency. One person at the laboratory was usually
assigned to manage the tracking operations for each individual project or group of
related projects (e.g., in 1965, there was a tracking and data systems manager for
Lunar Orbiter, one for Mariner, Surveyor, and Ranger, and another for Pioneer
and Apollo). The field stations all had directors; supervisors for communications,
data systems, USB systems, and facilities answered to them. The NASA Head-
quarters Office of Tracking and Data Acquisition had overall management authori-
ty for the Deep Space Network and its operations, s
TRACKING AND DATA ACQUISITION 567
568 NASA HISTORICAL DATA BOOK
\ \
\ \
\
MARS
STATION
GOLDSTONE
\
|PIONEER
DRY LAKE
GOLDSTONE \
JCOLL TOWER
\ \
ANTENNA
\
s",;v L,c.o w
I
COLL TOWERS
I
I _ "N_ TO FORT
I'COLL _O / IRWIN
Figure 5-12. Deep Space network 64-meter Antenna. The Deep Space Network extended its
range to the most distant planets of the solar system with the addition of a 64-meter-diameter
antenna at Goldstone. The Mars station parabolic antenna could maintain spacecraft com-
munications to a distance of 2½ to 3 times the range achieved by the 26-meter antennas and
had 6½ times more transmitting and receiving capability. Standing 71 meters" tall, the struc-
ture weighed 7.2 million kilograms. Its azimuth-elevadon mount and motors (1300 horsepoweO
couM move the giant dish from a horizon-pointing attitude to a straight-up position in 3 minutes.
Mars station went into operation in 1966, and NASA planned two additional 64-meter sta-
tions for ,4 ustralia and Spain.
TRACKING AND DATA ACQUISITION 569
CK-UP STRUCTURE
_PRECISlON ANGLE-DATA
TEM ASTRODOME
_ ,LEVR, 'ON
A S,M"LY
f \ ''ST"UM Nr
¢ _j/ TOWER
SUBREFLECTOR ___ "_\\\'_, /2"_/,I......ELEVATION DRIVE
_\,,_ ASSEMBLY
ALIDADE _'_
ALIDADE BUILDING
_j AZIMUTH RADIAL
IlllillrilUIIl[l_iil_ EAR'NG
PRIMARY REFLECTOR i
I_ilI_J_IJ_AZlMUTH DRIVE
_--_ ASSEMBLY
CABLE wRAP-uP' .
Figure 5-13. The Jet Propulsion Laboratory's Goldstone Space Commun&ations Station in
southern California's Mojave Desert was the site of the largestcollection of NASA tracking
equipment. In addition to the Mojave STADAN satellite station and the Apollo station with
its 26-m antenna, there were four deep space stations at this location: Mars (64-m antenna),
Pioneer (26-m), Echo (26-m), and Venus (26-m). These facilities were built on a 176-square-
kilometer plot of land leased by NASA from DoD.
570 NASA HISTORICAL DATA BOOK
TELEMETRY J
CAPE
GOLDSTONE GOLDSTONE
COMMAN
DSS 61,
ROBLEDO GOLDSTONE
_SS 42,
JOHANNES- TIDBINBILLA
Figure 5-14. Deep Space network Mission Operations. during a mission, the several deep space
stations fed data to the Space Flight Operations Facility at JPL. In turn, the flight controllers
at JPL coordinated the traacking and data acquisition needs of the mission and commended
the spacecraft through the ground stations. This figure depicts the Deep Space Network as
it was configured for the Surveyor lunar landing missions. The arrows indicate what form
or forms the interaction between mission control and the stations took. Note that the com-
munications links available at each station are also indicated.
TRACKING AND DATA ACQUISITION 571
Table 5-25.
Deep Space Network Stations
*Before the permanent facility was built, DSN had a temporary station at the Cape.
tCebreros and Robledo were both sometimes referred to as Madrid station.
Table 5-26.
Chronology of Deep Space Network (DSN)
Development and Operations
Date Event
1944-1947 As part of their work for the Army in developing the Corporal missile,
specialists at the Jet Propulsion Laboratory (JPL) in California devised
guidance and telemetry systems for the liquid propellant missile (Sperry
Gyroscope Co. assisted with the design of the guidance system). The
telemetry system used frequency modulation and phase modulation tech-
niques. Testing of the Corporal began in 1947, with operational deployment
in 1954.
March 15, 1953 In a report, F.W. Lehan and Robert J. Parks of JPL suggested using a phase-
locked loop as a narrow-band tracking filter in the recovery of Doppler data.
Eberhardt Rechtin and Richard Jaffe, also of JPL, followed up this research
and refined the concept.
Early 1954 In a proposal to the Army for the design of the Sergeant missile, JPL sug-
gested a radio system that would provide range and velocity information
(Coded Doppler and Ranging Communications).
Summer-fall 1955 The Army Ballistic Missile Agency (ABMA) submitted a proposal to the
Department of Defense (DoD) for an earth orbital International Geophysical
Year (IGY) satellite (Project Orbiter) to be launched by a Redstone booster
and a JPL-designed upper stage. JPL had also devised a telemetry system for
the proposal; tracking would be done optically. DoD chose instead the
Navy's Vanguard proposal, which included a radio tracking scheme.
However, ABMA and JPL continued to work on their design (the launch
vehicle was subsequently designated Jupiter C).
Sept. 1956 As part of the Reentry Test Vehicle Program, the first Jupiter C was suc-
cessfully launched down the Atlantic missile range in a test of the vehicle
design and the JPL phase-locked telemetry-tracking system (Microlock). The
Jupiter C test program was completed in August 1957.
Nov. 1957 In answer to the Soviet Union's success with Sputnik and to delays with
Vanguard at the Naval Research Laboratory, DoD authorized the Army to
572 NASA HISTORICAL DATA BOOK
Table 5-26.
Chronology of Deep Space Network (DSN)
Development and Operations (Continued)
Date Event
revive their satellite proposal. JPL's Microlock tracking and data acquisition
system was part of the revised plan, which was renamed Project Explorer.
Also in November, JPL Director William H. Pickering and California In-
stitute of Technology President Lee A. DuBridge proposed to DoD that the
U.S. send a probe to the moon by June 1958.
Jan. 31, 1958 The successful launch of the Army's Explorer 1 took place; the Microlock
system ensured the return of data from James Van Allen's radiation-
measuring experiment.
March 1958 The newly created Advanced Research Projects Agency (ARPA) announced
that the U.S. would conduct a lunar program with both the Air Force (three
launch attempts) and the Army (two launch attempts) participating. Verify-
ing a tracking and communications design was one of the program's objec-
tives. Specialists at JPL had determined that a large steerable parabolic
antenna would be necessary for ground stations to support a lunar mission. A
JPL survey team chose southern California's Mojave Desert as the site for the
first antenna.
Early 1958 In response to the government's growing interest in space exploration, JPL
specialists suggested a three-station network (each station 120 degrees apart
in longitude) for tracking deep-space probes. Suggested station sites included
Goldstone, California, Nigeria, and the Philippines. ARPA approved JPL's
plans for a network (Tracking and Communication Extraterrestrial, or
TRACE).
Summer 1958 Construction of the Goldstone 26-meter antenna station was begun, and a
mobile tracking station was located near Mayaguez, Puerto Rico, for support
of Pioneer. In addition, support was sought from the managers of the Jodrell
Bank (England) 76-meter radio astronomy antenna.
July 1958 To render their planned three-station network more useful to other future
space projects, its designers proposed that the Nigerian site be shifted to
southern Portugal or Spain and the Philippine site to Australia.
Nov. 1958 JPL's Ground Communications Facility, which had served as a combined
operations and communications center for Explorer 1, became established as
a separate entity within the laboratory. The Pioneer deep space station at
Goldstone was completed.
Dec. 3, 1958 The newly created National Aeronautics and Space Administration (NASA)
assumed responsibility from the Army for the facilities and personnel of JPL
(as per Executive Order 10793).
Dec. 6, 1958 The attempt to send Pioneer 3 to the moon was unsuccessful because the
launch vehicle failed. The tracking crews successfully followed the probe in
its try to escape earth's gravity and during its reentry into the atmosphere 38
hours later.
March 3, 1959 In its second attempt, the Army sent a probe, Pioneer 4, beyond earth's
gravitational pull hut not close enough to the moon for its experiments to
record data concerning it. Again the tracking system functioned well, work-
ing for 41 hours until the probe's battery went dead at 651 200 kilometers.
Late 1959 Tracking experts proposed that a deep space station be located near Johan-
nesburg, South Africa, so that continuous coverage could be provided mis-
sions. A site was chosen near the existing Minitrack station.
TRACKING AND DATA ACQUISITION 573
Table 5-26.
Chronology of Deep Space Network (DSN)
Development and Operations (Continued)
Date Event
Dec. 1959 Goldstone's second station, Echo, was completed in time to support NASA's
Echo communications satellite experiments (passive).
March 1960 Construction of a deep space station was begun near Woomera, Australia,
also the site of an IGY Minitrack station.
Dec. 24, 1963 The Deep Space Network was officially established as a separate directorate
at JPL under the direction of Eberhardt Rechtin.
Feb. 12, 1964 A conference was held at Cape Kennedy to establish procedures and initiate
action for the procurement of a site for the Cape Kennedy DSN station.
574 NASA HISTORICAL DATA BOOK
Table 5-26.
Chronology of Deep Space Network (DSN)
Development and Operations (Continued)
Date Event
March 1964 Construction began on the MSFN support wing at Goldstone's Pioneer sta-
tion.
April 1964 An initial investigation was made on Ascension Island to find a site for an In-
tegrated Apollo and Deep Space Station. A site was approved in July.
May 6, 1964 Final plans for the Cape Kennedy DSN station were delivered to the U.S.
Army Corps of Engineers.
July 1964 The first L/S-band conversion unit became operational at Woomera.
Sept. 1964 To support the MSFN and provide for improved deep space tracking, a se-
cond DSN station was proposed for the Madrid area. The site chosen for the
antenna was Cebreros.
Oct. 1964 Construction began at Cape Kennedy on the DSN Compatibility Test Sta-
tion.
Jan. 1965 Construction of the joint MSFN-DSN facility on Ascension Island was
begun.
April 1967 Transition of the DSN to the S-band configuration was completed
throughout the network (Johannesburg was the last station to be converted to
full S-band operation),
Nov. 1967 At JPL, construction of the DSN Compatibility Test Facility was begun.
Communications testing between the DSN and spacecraft would be con-
ducted at this facility.
o_
o_= d
.- @_-_
_ ._ ,.._
o _ < --,.o ,_
._5_ o "o " m
__, _ _ ._
o"
to
O_
.o
e.,
t"-
¢',10'
_a t_ Z
'O
!= Z
.=.
,,a
I-
c_
.<
[-
z_
o o
t,'q t'_
,..1,-.1 t'q r--
<
[-,
r_
< [..., <
O Z Z tO
oz_ < < < <
0
"O
,.c:, ,.-,
,-, O _r._
O'_
.,a
_o ,.-, O
<
576 NASA HISTORICAL DATA BOOK
_o="
_.o =o
d:: o= o=
_._ .'o'E o o ,,, ,_
.
m<'= 2 _-=o._
0 ¢_ 0
P" 0 " 0
E ¢1
m
¢1
"6.'- "_,_,
o
©
0
(J
Z
__
c_
Z
<
°_e..
[-
o o
Z r,j_
uz_ <m
0
TRACKING AND DATA ACQUISITION 577
_ _ ._
._ e, I.. O _ 0
i.., ._ _ e_ "m ..
g g.
_ "_ °_
,,..,
0
.S _ o o
rTl O i_ ¢',
_ ._
r) f_
r_
_._ Z
r_
<
I--,
o o o
,..1 ,.d
b,
Z
*_ Z
_Z
O
= t3
e
o=
ta ,_
0 _
.____ _, g ._
o
I:zl_ _ u u u_
578 NASA HISTORICAL DATA BOOK
_._
_ .-_
Z_- _ _ =_.__
e_._ - _ .rJ6
_._
._ -_
_-_e_ .g._
6
.o
: __
o"
t_
_'_o=_'_.__
0
o_
O
¢..)
,.o
t_
r_ Z
r-,
b-,
[..,
o o
Z
O
0
Z
o_.-
_ _._-
m o
r_ _, UU_
TRACKING AND DATA ACQUISITION 579
_:_ _._
o_ _ _ __,
_._ ,.
,..¢
o_._ _ __ _ __
:::1
•r. _ o= ,,
.-. _ _ "__
o_ Ox O_
O
r"- ,_, ¢q
t_
o_
ccJ Z
t_ r/3
[..
Z
r'..- ¢q
o o o o
,---,
o o'_
580 NASA HISTORICAL DATA BOOK
° ._e
__ _:_.
_:_ _
_, _'_
o.__ _'_
6
-... _ _.u
_0
_ _ _._
I1)
c-
0
o
o
o_
_._
°_
_'_
Z
,<
[...,
r._
0 0
o o
_'_ eq
o o
,-1,-1
Z ,,.d
0
_Z o_
r._
_ 0
TRACKING AND DATA ACQUISITION 581
_ _._
.<
_u8 _ ,.. _ ,-, o°
E
e...,
©
¢q O_
O_
e-_
t_
o_
Z
_°_
..q
[.-,
z_
,.d ,.d ,_o o o
.=_
r._
._.q
[...,
I=
t_
[...,
r,
<
< Z
r_
,-, o
° _
._°_
582 NASA HISTORICAL DATA BOOK
-_ o -,-n .
.o _ g , o "_ .._o
,
0 • _ _'_=_ --._,
_-_ _' ._
-_
"d
"2
_ 0 0 _
E
o_o
e_ a,.=_
U.I
E E _ E
¢-,i _._ 8 -_
0 ,.D
_._ Z
°_
_'_
Z
<
[- z_
_'_
o o
J.l
o_
UZ 0
0
0
E
I I I
I
e., .0 0 0 0
0 0 0
0 0 0 0
TRACKING AND DATA ACQUISITION 583
I::I
_ _ c_
t_ >o=C_
_'_
1-, _ °,,-, _ _
._ o--
0 0 _ 0
E
i =o "_'=
*..' Io ___ _ _o
_'_
6_
©
o_
O
r.)
,.Q
t_
o_
Z
03
Z
t_
[-..,
o o o o
(.) _...
O
584 NASA HISTORICAL DATA BOOK
©
O_
,..,
0
O
xo
o,, ox
e_
__
E-
°°o_
o o o
r.- 0
p_
0 0
TRACKING AND DATA ACQUISITION 585
z ,_z _._
'= m 0
_'=_' ._ _ s._,'=
z_
.., o.= =_,, • -_
©
e_
r_
o
°_
Z
_'_
Z
<
o
r_
z_
o o o o o o
o_
OZ
c-
o
a:°<
586 NASA HISTORICAL DATA BOOK
.9.
°
• _ _
"_ "_ =
0".9 -_
0 ,.-, 0
__ _ .__-_
_e_ _o_
m o "_
_ _ _
¢1)
©
O_ O_ O_
t,.)
O'.
_._
o_
z
-_'_
,.Q
o o
=
,<
.<
o ..,..
o _ "_ ._ _
TRACKING AND DATA ACQUISITION 587
0,_ 0
0 _ c_
O
e_
¢..,
o( .9°.= _
o
_ oM _
_A
o_ _-_ ,_
E
mo_,, _._
6_ -'_ ._ _<o.
•_ r_
la)
©
a'._
°_
Z
_'_
[-
z_
o o
_1_ _ I_
la.,
<
<
o_ ,.d
..,..,
=
t_
..,,_ 1..,
_ 0
g ,.,
_j ,,t= ._._
:_._
o _g
588 NASA HISTORICAL DATA BOOK
t_
_o _ _ _._ _ _
0
o.
0
E
0 O_
t"
r"
0
_._ m
Z
0¢2
-_'_
r,¢3
e-
[-.,
o o o o o o
r. 0
o __o
_<
TRACKING AND DATA ACQUISITION 589
_._:
,v
_ I_
0
,-.1 [.,
_-_
o" ,- _ "_.
"_,-=
_._
Z
__
Z
r_
e_
b.,
z_ z._
o o o o o o o o
,-.1
0 ,d
< <
0 t_
=._ 0
0 _
_ 0
590 NASA HISTORICAL DATA BOOK
t_ t_
o+a: o_
E
=._ - z_ _
, _ _ _'_
©
oo
o_
0
e-,
r_
_._ m
Z
r_
__
r_
e-
Z
I:m .<
<
l.--,
E.-
o o o o o
Z
m <
0
[-
0
o_
0
g: .0
0 _ "r" E_
TRACKING AND DATA ACQUISITION 591
"O
" "0
0 ,-'
.'_..
8_,_
= -_._ ,_ .=
_o
e.,
,:7
•__ _ _._--
©
e.,
..a
o
t_
[-
Z
t_
r_
Z
o.0 <
..q <
[-
[-
o
0
<
z
0
e_
°.
_o
592 NASA HISTORICAL DATA BOOK
o , _ _ _,,
_ __ _o
i_'_ _
__ _ ._ -'_ _,; 'E :_.= '* 8
_-o _ _o _
_._ .
_ °- _
_o--m 0
I::
_Zoo_ = _ -=
_-_ >o =
_._0 ._
t,'q
"O
._.9.
[-
z_
o o_
go_
¢-,I oo
<
0 ,d
0
[..
C_
0
0a',-
O
do -:_,
o.=-_ •"_ _ ='_.
o __._ _._ N._
[-., _ .<
TRACKING AND DATA ACQUISITION 593
_ _ ,.._ _ o _ _C_ o.
._-o . _ _ _ 0-_
•_, _ .
_ _o_ _"
_oZ_ _-_
•= ..- < =_-_ _ ._
E & _-_ t_
L_
_._ -__ _ _ t_
E
_._ _ _ _ _ .- ¢q
©
y_y_ ¢q
O
_J f_
O
t_ o_
--Z --
Z
t_ r/3
z
<
<
cj [-
z_
_=._
t'q
o o o o
,-1
Z 0
o 0 _
03
594 NASA HISTORICAL DATA BOOK
: _ _. e _ _ __ ._._
C:
t-
O
.o '/t
,.o
_.__
°_
_'_
E.-
._
_-_
N
N
O_
0 '_
_.o
TRACKING AND DATA ACQUISITION 595
._ ._
_ ._-_ .= . ,, _, .....,
Z_ "" z_ - "_'_'_
"" ..a "" "" _ "_
_.- .= =-_ _
- _ _= _ _ _ ._._"
, _=_,_ _.=._
o=
E
,g
e-,
o
tO
..= .¢t"
,.,,,
Iu
[...
Z
tn [.-, m [-., s.,, <
>
596 NASA HISTORICAL DATA BOOK
_.la,
_Z< _o
"_ 0
O.'_. o
_0_
,.o
gl
e.a
°_
Z
r_
Z
.<
.9
[.-,
[-
Z <
r,
OZ <
1.Propulsion
Staff,NASA, "ANational Space Vehicle Program;
AReport tothePresident," Jan.27,
1959;andAeronautics andAstronautics Coordinating Board,
"National Launch Vehicle
Program
Summary,"Feb.14,1961.
2.NASA borrowed launchersfromtheAirForce, Army,andNavy during itsfirstdecade.
In1961,
DoDassignedtheAirForce themajor responsibilityfordevelopment, production, andlaunching of
military
spaceboosters (DoD Directive 5160.32, "Development of Space Systems," March 6, 1961).
The Army Ballistic Missile Division, which also supplied the new space agency with boosters, lost its
most important element when the yon Braun team was transferred to NASA in 1960. The Navy
through NRL supplied NASA with the Vanguard vehicle. For more information on military vehicles,
see Ernest G. Schweibert, A History of the U.S. Air Force Ballistic Missiles (New York et al.:
Frederick A. Praeger, 1965); and David Baker, The Rocket: The History and Development of Rocket
& Missile Technology (New York: Crown Publishers, Inc., 1978).
3. Abraham Hyatt, "NASA Launch Vehicle Development Program," paper, Conference on Physics of
the Solar System and Reentry Dynamics, Virginia Polytechnic Institute, Aug. 1, 1961; NASA, Sec-
ond Semiannual Report of the National Aeronautics and Space Administration, 86th Cong., 2d sess.
(henceforth 86/2), House Doc. 361 (Washington, 1960), pp. 19-22; and Senate, Committee on
Aeronautical and Space Sciences, NASA Authorization Subcommittee, NASA Authorization for
Fiscal Year 1961; Hearings, pt. 2, 86/2 (Washington, 1960), pp. 777-91.
4. Arnold Levine, Managing NASA in the Apollo Era (1963-69). NASA SP-4102 (Washington, 1982),
chap. 7; and Jane Van Nimmen and Leonard C. Bruno with Robert L. Rosholt, NASA Historical
Data Book, 1958-1968, vol. 1, NASA Resources, NASA SP-4012 (Washington, 1976), pp. 113-14.
6. Subcommittee on Space Science and Applications, U.S. Civilian Space Programs, pp. 199-205; Loyd
S. Swenson, Jr., James M. Grimwood, and Charles C. Alexander, This New Ocean; A History of
Project Mercury, NASA SP-4201 (Washington, 1966), pp. 167-90; General Dynamics, "Centaur
Technical Handbook," report GD/A-BPM64-001, Feb. 15, 1964; Lockheed Missiles & Space Co.,
"Standard Agena Space Vehicle Technical Description," report LMSC-A397890, Dec. 1, 1964; and
Barton C. Hacker and James M. Grimwood, On the Shoulders of Titans: .4 History of Project
Gemini, NASA SP-4203 (Washington, 1977), pp. 297-321.
7. Subcommittee on Space Science and Applications, U.S. Civilian Space Programs, pp. 185-87.
8. Swenson, Grimwood, and Alexander, This New Ocean, pp. 208-13; and Courtney G. Brooks, Grim-
wood, and Swenson, Chariots for Apollo: .4 History of Manned Lunar Spacecraft, NASA SP-4205
(Washington, 1979), pp. 91-93, 141-42.
9. Swenson, Grimwood, and Alexander, This New Ocean, pp. 167-90; MSFC, Saturn/Apollo Systems
Off., "The Mercury-Redstone Project," TMX 53107, Dec. 1964; and Subcommittee on Space Science
and Applications, U.S. Civilian Space Programs, p. 186.
10. NASA-DoD, "Large Launch Vehicle Planning Group Summary Report," vol. 1, LLVPG 105, Sept.
597
598 NASA HISTORICAL DATA BOOK
24, 1962; Subcommittee on Space Science and Applications, U.S. Civilian Space Programs, pp.
216-17.
I I. Roger E. Bilstein, Stages to Saturn: A Technological History of the ApolloSaturn Launch Vehicles,
NASA SP-4206 (Washington, 1980); and Frederick O. Ordway III and Mitchell R. Sharpe, The
Rocket Team (New York: Thomas Y. Crowell, 1979).
12. Vought Corp., "100 Scout Launches," July 27, 1979; and Subcommittee on Space Science and Ap-
plications, U.S. Civilian Space Programs, pp. 195-99.
13. Subcommittee on Space Science and Application, U.S. Civilian Space Programs, pp. 187-95; and
GSFC, "Delta, 1960-1980; America's Busiest and Most Versatile Launch Vehicle" [n.d.].
14. Subcommittee on Space Science and Applications, U.S. Civilian Space Programs, pp. 205-10.
15. Constance McLaughlin Green and Milton Lomask, Vanguard: A History, NASA SP-4202
(Washington, 1970). Most sources agree that Vanguard was built on the technology of Viking and
Aerobee sounding rockets. Milton W. Rosen, who was NASA Headquarters's first chief of rocket
vehicle development (1958-59), believes this is a myth "generated by the NRL people who were trying
to sell the Vanguard project to the Stewart committee, in order to mitigate the impression that much
of the project was new development." See Rosen to Monte D. Wright, May 7, 1981.
Chapter 2
NOTES
1. Thomas A. Sturm, The USAF Scientific Advisory Board." Its First Twenty Years, 1944-1964
(Washington, 1967), pp. 80-88. Also see Loyd S. Swenson, Jr., James M. Grimwood, and Charles C.
Alexander, This New Ocean; A History of Project Mercury, NASA SP-4201 (Washington, 1966),
pp. 23-26, 69-74, 77-82, 91-93.
2. Wernher von Braun and Frederick I. Ordway 111, History of Rocketry & Space Travel rev. ed. (New
York: Thomas Y. Crowell Co., 1969), pp. 159-67; Erik Bergaust, Werhner von Braun (Washington:
NSI, 1976), pp. 2, 4-19, 239-47, 269-78; and von Braun, "The Redstone, Jupiter, and Juno,"
Technology and Culture 4 (fall 1963): 452-65. Also see Alice C. Cole et al., eds., The Department of
Defense; Documents on Establishment and Organization, 1944-1978 (Washington, 1979), pp.
171-75, 311.
3. Swenson, Grimwood, and Alexander, This New Ocean, pp. 20, 29, 41-42, 50, 100-01. For the story
of this country's early satellite programs, also see Constance McLaughlin Green and Milton Lomask,
Vanguard; A History, NASA SP-4202 (Washington, 1970).
4. Joseph A. Shortal, A New Dimension; Wallops Island Flight Test Range: The First Fifteen Years,
NASA Ref. Pub. 1028 (Washington, 1978), pp. 35-46, 93-97,237-41,590-99; and Robert R. Gilruth,
"From Wallops Island to Project Mercury, 1945-1958: A Memoir," in R. Cargill Hall, ed., Essays on
the History of Rocketry and Astronautics; Proceedings of the Third through the Sixth History Sym-
posia of the International Academy of Astronautics, vol. 2, NASA Conf. Pub. 2014 (Washington,
1977), pp. 445-76.
5. Alfred J. Eggers, Jr., H. Julian Allen, and Stanford E. Neice, "A Comparative Analysis of the Per-
formance of Long-Range Hypervelocity Vehicles," NACA Tech. Rep. 1382, also appearing in a
modified version as Allen, "Hypersonic Flight and the Reentry Problem," Journal of the
Aeronautical Sciences 25 (Apr. 1958): 217-30.
7. Public Papers of the Presidents of the United States; John F. Kennedy, Containing the Public
Messages, Speeches, and Statements of the Preident, Jan. 20 to Dec. 31, 1961 (Washington, 1962),
pp. 396-406. For a discussion of the Soviet and American manned programs, see Edward C. Ezell
and Linda N. EzeU, The Partnership; A History of the Apollo-Soyuz Test Project, NASA SP-4209
(Washington, 1978), pp. 61-96.
8. John M. Logsdon, The Decision to Go to the Moon; Project Apollo and the National Interest (Cam-
bridge: MIT Press, 1970); Logdson, "The Apollo Decision in Historical Prespective," in Richard P.
Hallion, ed., Apollo: Ten Years since Tranquility Base (Washington: Smithsonian Institution Press,
1979), pp. 3-9; and Walter Sullivan, America's Race for the Moon (New York: Random House,
NOTES 599
1962). Also helpful is U.S. House of Representatives, Toward the Endless Frontier; History of the
Committee on Science and Technology, 1959-79 (Washington, 1980), pp. 63-93.
9. For an outline of NASA's early management schemes, see Robert L. Rosholt, An Administrative
History of NASA, 1958-1963, NASA SP-4101 (Washington, 1966). Also useful is Arnold Levine,
Managing NASA in the Apollo Era (1963-69), NASA SP-4102 (Washington, 1982).
10. Swenson, Grimwood, and Alexander, This New Ocean, pp. 114-16; and Gilruth, "From Wallops
Island," pp. 469-71.
11. NASA, This Is NASA, NASA EP-155 (Washington, 1979), p. 20; and Thomas O. Paine to Clinton
P. Anderson, Nov. 21, 1969. Also see Swenson, Grimwood, and Alexander, This New Ocean, pp.
508, 643; Barton C. Hacker and Grimwood, On the Shoulders of Titans; A History of Project
Gemini, NASA SP-4203 (Washington, 1977), pp. 173-75,387-88,581-82; and Courtney G. Brooks,
Grimwood, and Swenson, Chariots for Apollo; A History of Manned Lunar Spacecraft, NASA
SP-4205 (Washington, 1979), pp. 25, ll0-11, 167-68.
12. The following document will give the reader a thorough look at the early planning for Mercury: U.S.
Senate, Project Mercury: Man-in-Space Program of the National Aeronautics and Space Ad-
ministration; Report of the Committee on Aeronautical and Space Sciences, U.S. Senate, 86th
Cong., 1st sess. (hereafter 86/1) (Washington, 1959).
13. Shortal, A New Dimension, pp. 633-63, describes the various support, including the Little Joe I
launches, that Wallops gave to Mercury. Other testing included ballon drops of Mercury capsule
models, flight stability investigations, high-altitude parachute drops, and aerodynamic heating
measurements.
14. Systems design for Mercury, Gemini, and Apollo is compared in John H. Boynton and Kenneth S.
Kleinknecht, "Systems Design Experience from Three Manned Space Programs," paper 69-1077,
AIAA 6th Annual Meeting, Anaheim, CA, Oct. 20--24, 1969.
15. The Mercury training equipment included the following: attitude control analog trainers (NASA),
centrifuges (Navy), an air-lubricated free-altitude attitude control trainer (NASA), a slowly revolving
room (Navy), the Multi-Axis Inertia Facility trainer (NASA) an egress trainer (McDonnell), an en-
vironmental control system trainer (McDonnell), a ground recognition trainer (NASA), a yaw
recognition trainer (NASA), a vertical image celestial display (Farrand Optical Co.), and two Mer-
cury procedures trainers (manufactured by McDonnell; one was in use at Langley, the other at the
Cape). See Robert B. Voas, Harold I. Johnson, and Raymond Zedekar, "Astronaut Training," in
NASA, Mercury Project Summary including Results of the Fourth Manned Orbital Flight, May 15
and 16, 1963, NASA SP-45 (Washington, 1963), pp. 171-98; and Swenson, Grimwood, and Alex-
ander, This New Ocean, pp. 240-48, 413-19. For biographical information on the astronauts, see
U.S. House of Representatives, Astronauts and Cosmonauts; Biographical and Statistical Data,
Report Prepared for the Committee on Science and Technolgoy, 97/1 (Washington, 1981).
16. Charles A. Berry, "Aeromedical Preparations," in NASA, Mercury Project Summary, pp. 199-209;
and Mae Mills Link, Space Medicine in Project Mercury, NASA SP-4003 (Washington, 1965), pp.
44-63, 85-111, 135-68.
17. Leighton I. Davis, "Operational Support from the Department of Defense," in NASA, Mercury
Project Summary, pp. 155-70. For further background material on NASA-DoD relations, see W.
Fred Boone, "NASA Office of Defense Affairs, the First Five Years," NASA HHR-32, Dec. 1970,
pp. 6-9, NASA Hq. History Off. files.
18. Section III of NASA, Mercury Project Summary, deals with flight operations. See also part 3 of
Swenson, Grimwood, and Alexander, This New Ocean.
19. The importance of rendezvous as it related to lunar missions is discussed in Brooks, Grimwood, and
Swenson, Chariots for Apollo, pp. 61-86; and Hacker and Grirnwood, On the Shoulders of Titans,
pp. 35-38.
20. Hacker and Grimwood, On the Shoulders of Titans, pp. 125-27, 139-44, 181-89; Alfred J. Gardner,
"Launch and Target Vehicle Support by the Department of Defense," in MSC, Gemini Summary
Conference, NASA SP-138 (Washington, 1967, pp. 167-84; MSC, Gemini Midprogram Conference,
including Experiment Results, NASA SP-121, pt. B (Washington, 1966), pp. 103-52; and Martin
Marietta Corp. "Gemini-Titan II Air Force Launch Vehicle Press Handbook," Feb. 2, 1967.
21. Hacker and Grimwood, On the Shoulders of Titans, pp. 157-62, 297-303. In response to continued
problems with the GATV main engine, Lockheed and Bell Aerosystems, supplier of the engine,
undertook an extensive series of test firings in 1965-1966 called Project Sure-fire. The 76 firings led
600 NASA HISTORICAL DATA BOOK
to modifications to the model 8247 engine. See also Gardner, "Launch and Target Vehicle Support,"
in Gemini Midprogram Conference, pp. 167-84.
22. For details on EVA equipment and operations, see Reginald M. Machell, ed., Summary of Gemini
Extravehicular Activity, NASA SP-149 (Washington, 1967); and MSC, Gemini Summary Con-
ference, pp. 67-148.
23. See Donald K. Slayton, Warren J. North, and C. H. Woodling, "Flight Crew Procedures and Train-
ing," in MSC, Gemini Midprogram Conference, pp. 201-12.
24. For details about the Gemini experiments program, see the following papers in Gemini Summary
Conference: Norman G. Foster and Olav Smistad, "Gemini Experiments Program Summary," pp.
221-30; Richard W. Underwood, "Space Photography," pp. 231-90; Jocelyn R. Gill and Willis B.
Foster, "Science Experiments Summary," pp. 291-306; and "DoD/NASA Gemini Experiments Sum-
mary," pp. 307-20.
25. Hacker and Grimwood, On the Shoulders of Titans, pp. 76-77, 117-22.
26. Brooks, Grimwood, and Swenson, Chariots for Apollo, pp. 4-16. Meeting from May to Dec. 1959,
the Research Steering Committee for Manned Space Flight headed by Harry Goett influenced the
authors of the 10-year plan. Also active at this time was the New Projects Panel of the Space Task
Group, chaired by H. Kurt Strass. For information on special committees, see Ivan D. Ertel and
Mary Louise Morse, The Apollo Spacecraft; A Chronology, Volume I through November 7, 1962,
NASA SP-4009 (Washington, 1969), pp. 207-22.
27. The mission mode decision is discussed in depth in Brooks, Grimwood, and Swenson, Chariots for
Apollo, pp. 61-86.
28. Convair/Astronautics' study depicted a three-module lunar-orbiting spacecraft based on the lifting
body concept; GE's study utilized a semi-ballistic blunt-body reentry vehicle design; Martin Com-
pany's five-part design was similar to the Apollo spacecraft that finally emerged. See Brooks, Grim-
wood, and Swenson, Chariots for Apollo, pp. 27-29.
29. Brooks, Grimwood, and Swenson, Chariots for Apollo, pp. 212-14.
30. The fire is covered in Brooks, Grimwood, and Swenson, Chariots for Apollo, pp. 213-27; and Ertel
and Roland W. Newkirk with Brooks, The Apollo Spacecraft; A Chronology, Volume IV, January
21, 1966-July 13-1974, NASA SP-4009 (Washington, 1978), pp. 63-126. Original review board
members were Floyd L. Thompson (LaRC), chairman, Frank Borman (MSC), Maxime A. Faget
(MSC), E. Barton Geer (LaRC), George Jeffs (NAA), Frank A. Long (PSAC), Charles F. Strong
(USAF), George C. White (NASA Hq.), and John Williams (KSC). The 21 task panels were in-
structed to address the following subjects: spacecraft and ground support equipment configuration,
test environments, sequence of events, disassembly activities, origin and propagation of fire,
historical data, test procedures review, materials review, design reviews, analysis of fracture areas,
medical analysis, witness statements, ground emergency provisions, security of operations, board ad-
ministrative procedures, special tests, final board report, integration analysis, safety of investigation
operations, in-flight fire emergency provisions, and service module disposition. Basic documents
relating to the investigation of the accident include "Report of Apollo 204 Review Board to the Ad-
ministrator, National Aeronautics and Space Administration," Apr. 5, 1967, with appx. A-G; U.S.
Senate, Committee on Aeronautical and Space Sciences, Apollo Accident: Hearings, 8 pts., 90/1,
90/2 (Washington, 1967-1968); U.S. House of Representatives, Committee on Science and
Astronautics, Subcommittee on NASA Oversight, Investigation into Apollo 204 Accident: Hearings,
3 vols., 90/1, 90/2 (Washington, 1967); and U.S. Senate, Committee on Aeronautical and Space
Sciences, Apollo 204 Accident: Report, 90/2 (Washington, 1968).
31. For more information on Gemini and Apollo crew assignments, see Brooks, Grimwood, and Swen-
son, Chariots for Apollo, pp. 373-80. Astronauts who joined in 1962 were Nell A. Armstrong, Frank
Borman, Charles Conrad, Jr., James A. Lovell, Jr., James A. McDivitt, Elliot M. See, Jr., Thomas
P. Stafford, Edward H. White II, and John W. Young; in 1963, Edwin E. Aldrin, Jr., William A.
Anders, Charles A. Bassett II, Alan L. Bean, Eugene A. Cernan, Roger B. Chaffee, Michael Collins,
R. Walter Cunningham, Donn F. Eisele, Richard F. Gordon, Jr., Russell L. Schweickart, David R.
Scott, and Clifton C. Willims, Jr.; in 1965, Owen K. Garriott, Edward G. Gibson, Joseph P. Kerwin,
and Harrison H. Schmitt; in 1966, Vance D. Brand, John S. Bull, Gerald P. Carr, Charles M. Duke,
Jr., Joe H. Engle, Ronald E. Evans, Fred W. Haise, Jr., James B. Irwin, Don L. Lind, Jack R.
Lousma, Thomas K. Mattingly 1I, Bruce McCandless II, Edgar D. Mitchell, William R. Pogue,
Stuart A. Roosa, John L. Swigert, Paul J. Weitz, and Alfred M. Worden; and in 1967, Joseph P.
NOTES 601
AllenIV,PhilipK.Chapman,
Anthony
W.England,
KarlG.Henize,
William
B.Lenoir,
F.Story
Musgrave, and Robert A. R. Parker. For biographical data, consult House of Representatives, Com-
mittee on Science and Technology, Astronauts and Cosmonauts Biographical and Statistical Data,
97/1 (Washington, 1981). Selection and training is discussed in Brooks, Grimwood, and Swenson,
Chariots for Apollo, pp. 178-80, 260-65,320-26; a popular account of astronaut training and mission
operations is provided in Michael Collins, Carrying the Fire: An Astronaut's Journeys (New York:
Farrar, Strauss, and Giroux, 1974).
32. JSC, "Apollo Program Summary Report," JSC-09423, Apr. 1975, p. 3-1; section 3 of this report
presents a science summary.
33. For a detailed account of activities at KSC during the Apollo years, see Charles D. Benson and
William B. Faherty, Moonport: A History of Apollo Launch Facilities and Operations, NASA
SP-4204 (Washington, 1978); Launch Complex 39 is described on pp. 535-37. Roger E. Bilstein,
Stages to Saturn: A Technological History of the ApolloSaturn Launch Vehicles, NASA SP-4206
(Washington, 1980), tells the Marshall Space Flight Center story. The early contributions of the
Langley Research Center can be found in LaRC, Conference on Langley Research related to Apollo
Mission, NASA SP-101 (Washington, 1965).
Chapter 3
NOTES
1. Homer E. Newell, Beyond the Atmosphere: Early Years of Space Science, NASA SP-4211
(Washington, 1980), pp. 11-13.
2. Office of the General Counsel, NASA Hq., "National Aeronautics and Space Act of 1958, as
Amended, and Related Legislation," July 1, 1969, p. 1.
4. For more on this subject, see Newell, Beyond the Atmosphere, chap. 2. Newell discusses the working
relationship of the space scientists and the manned spaceflight specialist in Beyond the Atmosphere,
pp. 290-95.
5. For more on the organization of space science and applications, see Arnold Levine, Managing NASA
in the Apollo Era (1963-69), NASA SP-4102 (Washington, 1982), pp. 167-72; and Newell, Beyond
the Atmosphere, pp. 101-15.
6. Newell, Beyond the Atmosphere, pp. 394-95,408-10.
7. Jesse L. Mitchell, "Physics & Astronomy Programs Program Review Document," Oct. 26, 1965.
8. [NASA Hq.], "Areas of Research in the NASA Space Sciences Program," Feb. 10, 1959, p. 44; and
Off. of the Assistant Director for Space Sciences, NASA Hq., "The NASA Space Sciences
Program," April 16, 1959, pp. 25-29.
9. [Langley Memorial Aeronautical Laboratory, NACA], "Preliminary Langley Staff Study, NASA
Space Flight Program," May 15, 19581 and Off. of Space Sciences, NASA Hq., "Office of Space
Sciences Ten Year Program," Aug. 17, 1959.
14. NASA, Space Communications and Navigation, 1958-1964, NASA SP-93 (Washington, 1966) pp.
v, 1.
16. See Phillip N. Larsen, "The Management of Commercial Satellite Communications," Perspectives in
Defense Management (Nov. 1967): 29-43.
17. William J. O'Sullivan, interview by Edward Morse, Aug. 28, 1964, in O'Sullivan biog. file, NASA
History Off.
18. George R. Thompson, "NASA's Role in the Development of Communications Satellite Technology,"
NASA HHM-8, Jan. 31, i966; and Edgar W. Morse, "Preliminary History of the Origins of Project
Syncom," NASA HNN-40, Sept. 1, 1964.
19. Eugene T. Jilg, "Engineering Designs for a Commercial Communications Satellite," paper, AIAA
Unmanned Spacecraft Meeting, Los Angeles, March 1, 1965.
20. B. 1. Edelson, H. W. Wood, and C. J. Reber, "Cost Effectiveness in Global Satellite Communica-
tions," paper, International Astronautical Federation 26th Congress, Lisbon, Sept. 21-27, 1975.
21. Ronald L. Weitzel, "The Origins of ATS," NASA HHN-83, Aug. 1968; and Gilbert D. Bullock,
comp. and ed., "ATS Program Summary," rev. April 1968.
Chapter 4
NOTES
I. Alex Roland, Research by Committee: A History of the National Advisory Committee for
Aeronautics, 1915-1958, NASA SP-4103 (Washington, 1985), pp. 80-87.
2. Irwin Hersey, "Research and Technology: Aeronautics and Space (1963-1968)," in "Preliminary
History of the National Aeronautics and Space Administration of President Lyndon B. Johnson,
November 1963-January 1969," unpublished NASA administrative histories project, Jan. 15, 1969,
p. V-4; also available as Hersey, "Advancing the Technology of Flight; Research and Development in
NASA, 1963-1968," NASA Historical Note 38, Oct. 1968.
4. Arnold Levine, Managing NASA in the Apollo Era (1963-69), NASA SP-4102 (Washington, 1982),
pp. 163-67.
5. Helen T. Wells, Susan H. Whiteley, and Carrie Karegeannes, Origins of NASA Names, NASA
SP-4402 (Washington, 1976), pp. 138-41, 150-53.
6. See NASA budget estimates, research and development volumes, for FY 1965-1968.
7. Ibid.; "Statement of Dr. Hermann H. Kurzweg, Director of Research, Office of Advanced Research
& Technology, National Aeronautics and Space Administration, before the Subcommittee on Ad-
vanced Research & Tracking [sic], Committee on Science & Astronautics, House of Representatives,"
March 3, 1964; and "Statement of Dr. Hermann H. Kurzweg, Director of Research, Office of Ad-
vanced Research and Technology, National Aeronautics and Space Administration, before the Sub-
committee on Advanced Research and Technology, Committee on Science & Astronautics, House of
Representatives," March 16, 1967.
8. See NASA budget estimates, research and development volumes, FY 1965-1968; and "Statement of
Milton B. Ames, Jr., Director of Space Vehicles, Office of Advanced Research and Technology, Na-
tional Aeronautics and Space Administration, before the Subcommittee on Advanced Research and
Technology, Committee on Science and Astronautics, House of Representatives," Feb. 22, 1968.
NOTES 603
9. Francis
Ragallo,
"Flexible
Wings,"
Astronautics & Aeronautics 6 (Aug. 1968): 50-54; Aerospace
Technology 21 (June 3, 1968), is a special report on parachute technology; and Richard P. Hallion,
On the Frontier." Flight Research at Dryden, 1946-1981, NASA SP-4303 (Washington, 1984), pp.
137-40.
10. See Clarence J. Geiger, "History of the X-20A Dyna-Soar," Historical Div., Information Off.
Aeronautical Systems Div., Air Force Systems Com., 3 vols., AFSC Hist. Pubs. Series 63-50-1,
63-50-II, 63-50-1II, Oct. 1963, available on microfilm, Air University Library, Maxwell AFB; vol. I
at JSC History Off.
11. The site selection process is outlined in Thomas P. Murphy, "NASA's Electronics Research Center,"
unpublished paper, ERC file, NASA History Off.
12. For more on NASA's changing life sciences program, see John Pitts, The Human Factor:
Biomedicine in the Manned Space Program to 1980, NASA SP-4213 (Washington, 1985).
13. "Transcript of the Briefing for Industry on NASA Space Power and Electric Propulsion Programs,"
April 27, 1967; and a four-part series on electric propulsion in Aviation Week & Space Technology 80
(Jan. 27, Feb. 3, Feb. 10, Feb. 17), gives a good summary of the many projects under way in this field
sponsored by industry, DoD, and NASA.
14. For a look at the nuclear rocket program, see James A. Dewar, "Project Rover: A Study of the
Nuclear Rocket Development Program, 1953-1963," unpublished Ph.D. dissertation, Kansas State
Univ., 1974; and Keith Boyer, "Nuclear Rockets," paper, AIAA 4th Annual Meeting and
Technology Display, Anaheim, CA, Oct. 23-27, 1967. For information on reactor and engine
testing, see Robert W. Schroeder, "NERVA-Entering a New Phase," Astronautics & Aeronautics 6
(May 1968): 42-53. A useful general introduction to nuclear propulsion is William Corliss, Nuclear
Propulsion for Space, part of a series "Understanding the Atom" (Oakridge, TN: AEC, 1967).
15. For general introductory materials, see Corliss and Robert L. Mead, Power from Radioisotopes, part
of a series "Understanding the Atom" (Oakridge, TN: AEC, 1971); and Corliss, SNAP; Nuclear
Space Reactors, part of a series "Understanding the Atom" (Oakridge, TN: AEC, 1966).
16. House of Rep., Com. on Science and Astronautics, Research and Development in Aeronautics: In-
terim Report, 87th Cong., 1st sess. (henceforth 87/1) (Washington, 1961); Mac C. Adams to Direc-
tors, Ames, Lewis, Langley, and Flight Research Centers, "Aeronautics Program," Oct. 14, 1965,
and Charles W. Harper, "Prospects in Aeronautics Research and Development," paper, AIAA Air-
craft Design for 1980 Operations Meeting, Washington, Feb. 12-14, 1968.
17. For a brief overview of aeronautics, see David A. Anderton, Sixty Years of Aeronautical Research,
1917-1977 (Washington, 1978). A good introductory work on the mechanics of flight is NASA, Ex-
ploring in Aeronautics, an Introduction to Aeronautical Sciences Developed at the NASA Lewis
Research Center, Cleveland, Ohio (Washington, 1971).
18. For a look at the variety of research that falls into the operating problems category, refer to NASA,
Conference on Aircraft Operating Problems, Langley Research Center, May 10-12, 1965, NASA
SP-83 (Washington, 1965).
19. Astronautics & Aeronautics 6 (Sept. 1968) was devoted to V/STOL technology. Also see NASA,
Conference on V/STOL and STOL Aircraft, Ames Research Center, Moffett Field, California,
April 4-5, 1966, NASA SP-116 (Washington, 1966).
20. Wendell H. Stillwell, X-15 Research Results, NASA SP-60 (Washington, 1965), contains an excellent
bibliography. Another source is Myron B. Gubitz, Rocketship X-15; A Bold New Step in Aviation
(New York; Julian Messner, Inc., 1960). Ronald H. Smith, "Antecedents and Analogues--Ex-
perimental Aircraft," in Jay D. Pinson, ed., Diamond Jubilee of Powered Flight: The Evolution of
Aircraft Design (Dayton, OH: Dayton-Cincinatti Section, AIAA, 1978), pp. 80-86, gives a short
history of the early X-series, the X-15, and lifting bodies. Hallion, Supersonic Flight: The Story of
the Bell X-I and Douglas D-558 (New York: MacMillan Co., 1972), thoroughly discusses the early
research aircraft program.
21. For a very readable account of NASA's research aircraft story, see Hallion, On the Frontier, chaps.
4-6, 8.
22. For information on the F-111, the XB-70, and other aircraft, consult John W. R. Taylor, ed., Jane's
All the World's Aircraft, 1968-69 (New York: McGraw-Hill Book Co., 1968), pp. 278-80, 341-42.
604
Chapter
5
NOTES
1.Forfurtherinformation on tracking and data acquisition techniques, see Samuel Glasstone,
Sourcebook on the Space Sciences (New York et al: D. Van Nostrand Co., Inc., 1965), pp. 217-39.
2. John T. Mengel and Paul Herget, "Tracking Satellites by Radio," Scientific American 198 (Jan.
1958): 23-29, deal specifically with the Minitrack system. See also Constance McLaughlin Green and
Milton Lomask, Vanguard: .4 History, NASA SP-4202 (Washington, 1970), pp. 145-63. Green and
Lomask relate how the Smithsonian Astrophysical Observatory optical tracking system was also used
for Vanguard, pp. 149-54.
3. William R. Corliss, "Histories of the Space Tracking and Data Acquisition Network (STADAN), the
Manned Space Flight Network (MSFN), and the NASA Communications Network (NASCOM),"
NASA CR-140390, June 1974, pp. 24-57, discusses the evolution of STADAN equipment. For infor-
mation on communications and data handling operations and equipment, see Corliss, Scientific
Satellites, NASA SP-133 (Washington, 1967), pp. 133-63. For technical information regarding
equipment and facilities, see the following Goddard Space Flight Center reports: "Satellite In-
strumentation Facilities Report," GSFC report X-530-62-3, April 1962; "Satellite Tracking and Data
Acquisition Network Facilities Report (STADAN)," GSFC report X-539-64-159, June 1964; and
"Space Tracking and Data Acquisition Network Facilities Report (STADAN)," GSFC report
X-530-66-33, Dec. 1965.
4. For more on Goddard's Space Operations Control Center and other data acquisition and tracking
facilities, see Alfred Rosenthal, Venture into Space; Early Years of Goddard Space Flight Center,
NASA SP-4301 (Washington, 1968), pp. 65-78.
5. For information on Mercury tracking, communications, and data acquisition equipment, see
Howard C. Kyle, "Manned Spaceflight Communications Systems," in A. V. Dalakrishnan, ed., Ad-
vances in Communication Systems, vol. 2 (New York: Academic Press, 1966), pp. 195-204.
6. Loyd S. Swenson, Jr., James M. Grimwood, and Charles C. Alexander, This New Ocean: A History
of Project Mercury, NASA SP-4201 (Washington, 1966), pp. 392-97.
7. For more on the Gemini network, see Corliss, "Histories of the Space Tracking and Data Acquisition
Network (STADAN), the Manned Space Flight Network (MSFN), and the NASA Communications
Network (NASCOM)," pp. 140-61; and Barton C. Hacker and Grimwood, On the Shoulders of
Titans: .4 History of Project Gemini, NASA SP-4203 (Washington, 1977), pp. 584-92. Kyle,
"Manned Spaceflight Communications Systems," pp. 205-10, describes the equipment and techni-
ques used for Gemini tracking and data acquisition.
8. For information on the Deep Space Network, see Nichola A. Renzetti, ed., "A History of the Deep
Space Network, from Inception to January 1, 1969," JPL tech. report 32-1533, vol. 1, Sept. 1, 1971,
which has a 7-page bibliography; JPL, "DSIF: Goldstone," JPL tech. memo 33-205, 1965; and Cor-
liss, "A History of the Deep Space Network," NASA CR-151915, May 1, 1976. R. Cargill Hall,
Lunar Impact: A History of Project Ranger, NASA SP-4210 (Washington, 1977), pp. 81-91, relates
how the DSN supported Ranger.
NOTES ON SOURCES
The authors of the NASA Historical Data Book series have necessarily relied on
hundreds of sources to compile the many tables and charts presented. In Volume II,
no attempt was made to list the sources used for each table because the notes would
have overwhelmed the content in many cases. The number of source notes sup-
porting the narrative has also been kept to a minimum. This note on sources will
serve as a guide for the researcher interested in pursuing the material from which this
volume was compiled.
The author relied heavily on the subject and biographical files of the NASA
Headquarters History Office, Washington, D.C., for primary documents from
which to glean the facts and figures. For most topics, the following kinds of
documents can be found in these files: NASA press releases, speeches, congressional
testimony, contractor reports, related articles from periodicals and newspapers, cor-
respondence, and photographs. Mission operations reports and midterm and
prelaunch reviews are an important part of the many "mission" files. When the
author was confronted with conflicting data-not uncommon when working with
material that dates from NASA's first years-mission operations reports (or their
equivalents) and contractor reports were considered the most authoritative sources.
Also very useful was the document collection of the Johnson Space Center History
Office, Houston, Texas.*
In addition to primary sources and project chronologies and histories published
by NASA, the author frequently used a number of general reference works. Most
helpful was the series Astronautics and Aeronautics, Chronology on Science,
Technology, and Policy. Compiled by staff members of the NASA Headquarters
History Office, a volume is available for each year, starting with 1963.t A handy
guide to NASA projects and installations is Helen Wells, Susan H. Whitely, and
*Many of the records formerly held at JSC that pertain to the Mercury and Gemini projects have
been loaned to the Fondern Library, Rice University, Houston, Texas, where they will be catalogued and
made available to scholars.
tThe following chronologies were also useful: Eugene M. Emme, Aeronautics and Astronautics; An
American Chronology of Science and Technology in the Exploration of Space, 1915-1960 (Washington,
1961); NASA, Aeronautical and Astronautical Events of 1961; Report to the Committee on Science and
Astronautics, U.S House of Representatives, 87th Cong., 2d sess. (henceforth 87/2) (Washington, 1962);
and NASA, Astronautical and Aeronautical Events of 1962; Report to the Committee on Science and
Astronautics, U.S. _Iouse of Representatives, 88/1 (Washington, 1963).
605
606 NASA
HISTORICAL
DATABOOK
CarrieE. Karegeannes,
Origins of NASA Names, NASA SP-4402 (Washington,
1976). For a quick look at NASA and its predecessor organization, the National Ad-
visory Committee for Aeronautics, the author relied on Frank W. Anderson, Jr.,
Orders of Magnitude; A History of NA CA and ?CA SA, 1915-1980, NASA SP-4403
(Washington, 1981). Also useful was a reference work that covers the first 20 years
of U.S. involvement in aerospace activities: House of Representatives, Committee
on Science and Technology, Subcommittee on Space Science and Applications,
United States Civilian Space Programs, 1958-1978; Report (Washington, 1981). A
standard reference on NASA's early organization is Robert L. Rosholt, An Ad-
ministrative History of NASA, 1958-1963, NASA SP-4101 (Washington, 1966). A
report that proved especially helpful was Kennedy Space Center, "A Summary of
Major NASA Launchings," KSC Historical Report 1, revised in 1970. NASA's
semiannual reports to Congress, the last of which was submitted in 1969, were useful
guides. "Pocket Statistics," compiled monthly by NASA (from 1960), provided
selected technical, financial, and manpower data. Another research tool that was
brought out again and again was the History Office's collection of NASA Head-
quarters and center telephone directories.
The budget tables for all five chapters of Volume II were compiled from two
sources: NASA Chronological History Fiscal Year Budget Submissions, prepared
annually by the Budget Operations Division of the Office of Administration, NASA
Headquarters; and the Budget Estimates (research and development volumes only)
prepared for Congress by NASA each fiscal year. As noted in the introduction to the
budget section of Chapter 1, this volume is only concerned with research and
development monies. This approach reflects advice given the author by the NASA
Headquarters Office of the Comptroller.
The author used the following publications as source material for five chapters
of Volume II. For additional sources, see the source notes. Refer also to the descrip-
tive sections of each chapter.
Chapter 1:
Baker, David. The Rocket: The History and Development of Rocket & Missile
Technology. New York: Crown Publishers, 1978.
Bilstein, Roger E. Stages to Saturn: A Technological History of the Apollo/
Saturn Launch Vehicles. NASA SP-4206, Washington, 1980.
Brooks, Courtney G., Grimwood, James M., and Swenson, Loyd S. Chariots for
Apollo: A History of Manned Lunar Spacecraft. NASA SP-4205, Washington,
1979.
Green, Constance McLaughlin and Lomask, Milton. Vanguard." A History.
NASA SP-4202, Washington, 1970.
Hacker, Barton C. and Grimwood. On the Shoulders of Titans: A History of
Project Gemini. NASA SP-4203, Washington, 1977.
Levine, Arnold. Managing NASA in the Apollo Era (1963-69), NASA SP-4102,
Washington, 1982.
Marshall Space Flight Center. Saturn Illustrated Chronology; Saturn's First
Eleven Years, April 1957 through April 1968. MHR-5, Huntsville, 1971.
Swenson, Grimwood, and Alexander, Charles C. This New Ocean: A History of
Project Mercury. NASA SP-4201, Washington, 1966.
NOTES 607
Chapter 2:
Chapter 3:
Rosenthal, Alfred. Venture into Space: Early Years of Goddard Space Flight
Center. NASA SP-4301, Washington, 1968.
Rosenthal and Corliss. Encyclopedia of Satellites and Sounding Rockets, August
1959 to December 1969. Beltsville, MD: Goddard Space Flight Center, 1970.
Shortal, Joseph A. A New Dimension; Wallops Island Flight Test Range: The
First Fifteen Years. NASA Ref. Pub. 1028, Washington, 1978.
Chapter 4:
Chapter 5:
Corliss, William R. "Histories of the Space Tracking and Data Acquisition Net-
work (STADAN), the Manned Space Flight Network (MSFN), and the NASA
Communications Network (NASCOM)." NASA CR-140390, June 1974.
Thomas, Shirley. Satellite Tracking Facilities: Their History and Operation. New
York: Holt, Rinehart and Winston, 1963.
Since 1973, NASA has used the metric system in its publications. Although
many metric weights and measurements are now commonly used in the United
States, some may still sound foreign to the reader. Probably the most frequently
questioned measurement is newtons of thrust (pounds thrust x 4.448 = newtons).
A useful publication for the reader not familiar with the metric system is E. A.
Mechtly, The International System of Units, Physical Constants and Conversion
Factors, NASA SP-7012, 2d rev. (Washington, 1973). Also note that weights of
launch vehicles and spacecraft are "wet weights"; that is, vehicle and fuel. Dates and
times of mission events are local; ground elapsed time is the amount of time
(hours:minutes:seconds) that has elapsed since launch.
The following individuals assisted the author by commenting on the manuscript
or assisting with the research. By so doing, they became valuable "sources."
ORGANIZATION CHARTS
APPENDIX A 61 1
o_oO_oz
_o9_o_
o_o_i= _
uOz_ o_
7
z
_o oz
_o5 _o_
oo _
_o_ _._1 _° _ _ o_
_u
__
W
=_
z
o
° _°1
___>
±o
__
>_
- :iu
,_o
1
z
z a
m_z _om
_zO_ ozz o
_ _ o
_=o
,_ -_ o
o_____ o_ __
z
w
_z
m
0 z >_
_°
uT_
_o_ _o
-r
L__
un_n
-- _I_o
612 NASA HISTORICAL DATA BOOK
I ;:-_;
INN
_m
m
-1-
_ _^
m
m
__._l_
_cc Z
I-_ >_
o_
_5
-V-
_ r5
ul
z_
•: a.
E
APPENDIX A 613
614
!i_!i
I!_il
II
m
I
I
---7
8
i,
APPENDIX A 615
P "t ,_o
_om
z
I-______J _z
_-- o_
)__tJ
g
o
i.-i wm
i--
m xO
J
f- _A
wZ
wc
OC
I
E
o__
" gl
-} tJ
o
616 NASA HISTORICAL DATA BOOK
-r--- I-I _i
I_ i I I
m aa_
____.
"T""
.L..-
°_1
_1
m
--T-_
f_|_._i__ _1
T--
_a
---T iiii_
z I I
, .. ,
APPENDIX A 617
r .... I
I_z,_O
I__z_
I
I
.i!
i_,_
l<<v_< Ii
I
o___l
z
o___ I
0 _-
i .._a:
-m_-
[_z
;a<
_'_>-
mi
5 --
z> I
_ I
O0
<
<
oecw-
z,_m
I_ _
INDEX
Page references to illustrations or photographs are in italics.
619
620 NASA
HISTORICAL
DATA
BOOK
Orbiting
Laboratory
(MOL),177n; Simulator, 499; Solar Probe Team,
Missile
TestCenter
(AFMTC),559, 304
560;Nuclear
Missile
Propulsion,
Ad Ampex, 264
HocCommitteeon,482;PatrickAFB, Anders, William A., 167, 168, 177, 185,
548, 554, 589; Randolph AFB, 96; 189
School of Aviation Medicine, 467 n; Anderson, Clinton P., 479
Scientific Advisory Board, 97, 482, Anderson, George M., 111
483, 505; Space Medicine, Department Anderson, Melvin S., 102 n
of, 96; Space Systems Division, 155, Andover, Maine, 376
489, 490; Systems Command, 101, Andrus, A. Marion, 366
102; Trailblazer, 463 n, 464; USAF Antarctica, 400
MX-770, 482; Vandenburg AFB, 548, Antares, 10, 13, 24, 29, 41,448-50; An-
554, 592; Wright Air Development tares II, 62, 63; X-254-A1, 465 n
Center, 137 n, 483,484, 505; Wright- Antigua, B. W. I., 523, 536, 539 n, 540,
Patterson AFB, 96, 467 n 542, 548, 552, 554, 557, 558, 562, 563,
Air Force-NASA Joint Conference on 575
Lifting Manned Hypervelocity and Antofagasta, Chile, 536, 539, 540, 542,
Reentry Vehicles, 454 543, 575
Alabama, 171, 172 Apache, 272, 273, 281
Alaska, 538, 540, 542, 543, 575, 581; Apollo, 4, 6, 12, 13, 16-18, 22-24, 48, 50,
Alaska Station, 579 53, 56-59, 101-03, 112, 116, 121-23,
Albuquerque, New Mexico, 137 n, 480, 128 n, 151, 152, 156, 171-94, 197, 203,
485 248, 272, 301, 302, 308-10, 319,
Alcor, 279, 465 n 321-23, 325-27, 329, 338, 339, 390,
Aldrin, Edwin A., Jr., 153, 158, 161, 438, 441,444, 445, 448-50, 461,473,
165, 166, 168, 169 474, 481, 490, 524, 548, 549, 552-57,
Algol I and IIB, 62, 63, 66 559, 562, 563, 565, 566, 568, 569 n,
Algranti, Joseph S., 115, 120 573-75, 583, 585, 587, 589, 591, 593,
Alleghany Ballistics Laboratory, 34, 41, 595, 596; Apollo 204 Review Board,
62, 72, 80, 86, 87 176, 184; Apollo 4, 61, 101, 174, 176,
Allen, Harry B., 107 184, 563; Apollo 5, 59, 176, 184, 554;
Allen, H. Julian, 94, 96, 97 Apollo 6, 61, 176, 185; Apollo 7, 55,
Allenby, R. J., 109, 302 59, 176, 177, 179 n, 185, 188, 556,
Almy, Donald C., 107 557, 563; Apollo 8, 2, 61, 101, 177,
Alouette, 38, 296; Alouette 1, 69, 74, 178, 179 n, 185, 189, 554-57,
288-90; Alouette 2, 74, 249, 288, 290 563; Apollo 9, 555 n; Apollo 12, 494;
Alphonsus (crater), 318 Apollo Experiments, Ad Hoc Working
Altair, 62, 63, 72, 77 Group on, 177; Apollo Instrumented
American Mariner (tracking ship), 549, Tracking Ship, 555; Apollo Lunar
551 Surface Experiments Package
American Rocket Society, 97, 454 (ALSEP), 494, 495; Apollo Mission Plan-
American Science and Engineering, Inc., ning Panel, 183; Apollo Network Im-
254 plementation Plan, 562, 563; Apollo
American Standard: Advanced Project Office, 179; Apollo Range In-
Technology Division, 264 strumentation Aircraft (ARIA), 549,
American Telephone & Telegraph Com- 556; Apollo-Saturn, 182, 563; Apollo-
pany (AT&T), 364, 373-75, 552 n Soyuz Test Project, 121; Apollo
Ames, Milton B., 406, 407, 435, 436, Spacecraft Project Office (ASPO),
439, 453 172, 179, 182, 185; Apollo Task
Ames Research Center (ARC) (formerly, Group, 553; Apollo Technical Liaison
Ames Aeronautical Laboratory and Group for Instrumentation and Track-
Moffett Field Laboratory), 94, 96-98, ing, 551, 552. 561. 562; astronauts,
100 n, 103 n, 135, 155-57, 180, 240, 176-78, 183-85, 188, 189, 494;
241,243, 250, 251, 254, 256-58, 260, characteristics and chronology, 171-94,
302-04, 307-09, 341,342, 344-46, 407 203; funding, 129_, 123. 128-32; Project
n, 431, 433-35, 437, 439, 450-52, Apollo, 17, 18, 22-24, 100, 384, 522,
454-57, 469, 495-97, 499-501, 515, 551, 565; Skylab, 55,461
565; Movingbase Landing-Approach Applications Technology Satellite (ATS),
INDEX 621
13,29,37,38,40,43,44,206,221n, Range
224-26,368,384,408,461,474,
539, Atlantic Research Corporation, 72, 192,
543,590,592 278-80
Appropriations
Conference Committee, Atlas, 1-3, 9-12, 14-16, 24, 27-45, 51, 74,
128 83, 84, 92, 94, 96, 98-100, 121, 134,
APT(automatic picture
transmission) 136-39, 145-48, 153, 155, 171,446,
system,349,356-59,363 449, 453,489, 541; Atlas-Able, 3, 10, 11,
Arabian;DonaldD., 116,119 27, 214 n, 217 n, 301, 303, 304; Atlas-
Archives,
U.S.National:National Agena, 9-11, 19-21, 27, 29, 121, 156,
Weather RecordsCenter,
350 158, 206, 223 n, 334; Atlas-Agena B,
Arctic Ocean, 557, 558 13, 20, 156, 209, 223 n, 270, 309, 311,
Arequipa, Peru, 523, 541 313-18, 332, 335, 336, 443, 448, 450;
Argentina, 272 Atlas-Agena D, 13, 20, 22, 158,262,
Ariel, 437; Ariel 1, 2, and 3, 64, 65, 68, 270, 321-25, 332, 337-39, 397, 398;
288, 291-93 Atlas-Antares, 10, 174, 186, 438, 448,
Arizona, University of, 316-18 451; Atlas-Centaur, 2, 3, 10, 27-29,
Armstrong, George G., Jr., 120 262, 263, 326-31, 334, 387, 398, 474,
Armstrong, Harry G., 96, 110 491; Atlas D, 29, 450; Atlas-Hustler,
Armstrong, Neil A., 153, 158, 161, 164, 3, 36; Atlas SLV-3, 29; Atlas-Vega, 29;
165, 167, 189, 510, 511 Atlas-X259, 27; "FLOX Arias" pro-
Army, U.S. Department of the, 1, 46, ject, 30
47, 52, 54, 91-93, 96, 140, 180, 235, Atomic Energy Commission (AEC), 64,
276, 286, 303,306, 501, 524, 542, 564, 405, 438,470, 473-81,483,485,486,
571-73, 575, 593; Army Ordnance 488, 494, 495; Albuquerque Opera-
Missile Command (AOMC), 52, 56, tions Office, 478, 484; Argonne Na-
99, 180; Corps of Engineers, 574; tional Laboratory, 478; Chicago
Guided Missile Center, 52; Map Ser- Operations Office, 478; Division of
vice, 536, 542; Ordnance Department, Reactor Development, 478, 482; Oak
275; Plum Brook Nuclear Rocket Ridge National Laboratory, 438, 482.
Dynamics Test Facility, 477, 486; See also Space Nuclear Propulsion
Signal Corps, 275, 559; Signal R&D Office
Laboratory, 287 Atoms for Peace program, 485
Army Air Corps, U.S., 534, 535, 541; Atwood, J. L., 184
MX-774 project, 541 Aucremanne, Marcel T., 233,249, 264,
Army Ballistic Missile Agency (ABMA), 303
1, 46-48, 54, 56, 87, 91-93, 96, 134, Augerson, William S., 137 n
138, 139, 171, 180, 232, 235, 238, 286, Augmented Target Docking Adapter (AT-
302, 306, 347, 348, 351, 571; Develop- DA), 165
ment Operations Division, 1, 180. See Aurora 7, 146
also Marshall Space Flight Center A urorae. See European Space Research
Ascension Island, 347, 449, 523, 548, Organization
551, 552, 554, 557, 558, 562, 563, 565, Australia, 244, 272, 283, 343, 546, 547,
570, 571, 574, 576 552, 554, 561, 565,568, 572, 573, 582,
Ashley, William T., 104, 106 585, 589, 595
Ashworth, C. Dixon, 254, 260, 264 Authorization Conference Committee, 204
Asia, 380, 382 Avco Corporation, 192, 340; Space
Asmara, Ethiopia, 381 Systems Division, 192
Astronautics Avco Corporation, 182 AVCS (advanced vidicon camera system),
Astronomy Missions Board, 198 349, 358, 359, 361-63, 395
Atlantic 2. See International Telecom- Aviation Medical Acceleration
munications Satellite Consortium Laboratory, 467
Atlantic (coast and ocean), 91, 136, 138, Azusa, 535, 541
157, 158, 381, 385, 390, 391, 393, 398,
444, 449, 544, 546, 547, 550-52, 554,
555 n, 557-59, 561, 576, 582, 595
Atlantic Missile Range (AMR), 102, 138,
140, 531, 544, 546, 571; Operations
Office, 560. See also Eastern Test
622 NASAHISTORICAL
DATABOOK
Budget,U.S.Bureau of the(BOB),
6,7, Center
203,362,392,475,485, 490 Caporale, A. J., 299, 300
Buglia,James J., 98,100n Capsule Coordination Committee, 139,
Bunze,
H. F.,483 141 n
Burcham, Donald P.,340 Camarvon, Australia, 523, 538 n, 540,
Burke,J. D., 310-16 543,548, 552, 554, 557, 563, 577, 588,
Burke,JohnR.,107 593
Burke,Joseph R.,366,370,373,376, Carnegie Institute, 567 n
380,393 Carpenter, M. Scott, 116, 137 n, 138,
Burlage,Henry,471 141, 145-48, 551
BurnsandRoe,546,561.See also WECo Carr, Gerald P., 189
Bussard, R. W., 482 Case Institute of Technology, 433
Butler, H. I. 352 Castor I and II, 62, 63, 75
Butler, Paul, 240, 243, 245, 248, 251 Catterson, A. D., 120
Causse, Jean-Pierre, 296
Cebreros, 554, 562, 565, 571, 574, 579,
587, 590
C Centaur, 1-3, 5, 9, 24, 29-31, 33, 41-45,
171 n, 223 n, 262, 326, 327, 331,379,
Cain, Dwight C., 109 399, 470, 473,491, 552
Cain Springs, 483 Central Radio Propagation Laboratory,
Cajun, 272, 276, 282 244
California, 145-47, 154, 156, 341, 369, Cernan, Eugene A., 153, 158, 162, 165,
451,475,522, 526, 544, 546, 553, 168, 188
571-73, 589, 592 Chaffee, Roger B., 159, 176, 184
California, University of, 243,259; at Chamberlin, James A., 102, 113-15, 117,
Berkeley, 395; at La Jolla, 379; at Los 119, 139, 141 n, 154, 157
Angeles (UCLA), 250, 251, 337, 395; Chance Vought Aircraft Corporation, 61,
at San Diego (UCSD), 242, 243,247, 62, 181, 182, 449-51. See also Ling-
254, 256, 257, 314, 316-18, 395 Temco-Vought Aerospace Corporation
California Institute of Technology (Cal Cherrick, Irwin, 254
Tech), 313, 314, 329, 330, 335, 337, Chicago, University of, 237, 243, 307,
564, 572; Guggenheim Aeronautical 309, 313, 328, 330, 337, 433
Laboratory (GALCIT), 564 n. See Chickering, John B., 105, 107
also Jet Propulsion Laboratory Chilton, Robert G., 102 n
Calio, Anthony J., 119 China Lake, California, 444
Cambridge, Massachusetts, 405,460 Christiansen, Everett E., 107, 110
Cambridge, University of (U.K.), 292 Chrysler Corporation, 46, 47, 51, 52,
Camp Roberts, California, 381 55-59
Canada, 233, 236, 249, 272, 277, 288, Chukchi Sea, 557
550, 591; Defence Research Telecon Civilian-Military Liaison Committee, 2,
Establishment, 289, 290; Defense 45. See also Aeronautics and
Research Board, 289, 290; Transporta- Astronautics Coordinating Board
tion, Department of, 354 Clark, John F., 200, 201,232, 301
Canary Islands, 550, 557, 558, 577 Clarke, Arthur C., 364
Canberra, Australia, 523, 554, 556, 557, Clements, Henry E., 116, 118
562, 563, 565, 573, 577, 592 Cleveland, Ohio, 40, 44, 405, 477, 480,
Cannetti, Anthony, 108 485, 495
Canoga Electronics Corporations, 552 n Clummons, D. L., Jr., 298
Canright, Richard B., 6, 104 Coastal Sentry Quebec (tracking ship),
Canton Island, 523, 546, 548, 550, 552, 147, 148, 546, 549, 551, 552
561, 577 Cobby Creek, Australia, 592
Cape Canaveral/Kennedy, Florida, 1, 33, Coffee, Claude W., Jr., 244, 246, 253
44, 52, 57, 138, 143, 153, 154, 157, Cohen, Aaron, 119
159-62, 164-68, 179, 523, 536, 541, Cohen, Haggai, 111
542, 545, 546, 548, 550, 552, 554, 557, Cohen, William, 471
561, 562, 565,570, 571, 573, 574, 577, Cole, 106
588, 592. See also Kennedy Space College, Alaska, 538-40, 575, 577
624 NASAHISTORICAL
DATA
BOOK
College Park, Maryland, 540, 542, 543, Critzos, Chris C., 112
577 Cross, Carl S., 515 n
Collins, Michael, 153, 158, 162, 166, 189 Crossfield, A. Scott, 502 n, 507, 509, 510
Collins Radio Company, 192, 372, 552 n Crowley, John W., 404, 406
Coil Towers, 568 Cuckoo-Raven II, 283
Colorado, University of, 339 Culbertson, Philip E., 110, 111
Columbia University, 314, 355, 433 Cummings, C. I., 311
command and service module (CSM), 172 Cunningham, Newton W., 310, 332
n, 174-76, 178, 183, 185-94 Cunningham, R. Walter, 164, 176, 185,
command module (CM), 173, 188, 189 188
Commerce, U.S. Department of, 248, Curfman, Howard J., Jr., 464
348, 349, 351, 368, 399 Cutler-Hammer Corporation, 244, 476;
Communication by Moon Relay, 364 Airborne Instruments Division, 476
communications projects, 199, 222, 224,
244, 246, 364-91
Communications Satellite Corporation
(COMSAT), 364, 366, 368, 371, 382, D
384, 385, 388-92, 396
Comodoro Rivadavia, Argentina, 523, D'Aiutolo, Charles T., 241, 445
541 Dallow, Thomas P., 344
Condor Committee, 483 Dana, William H., 456, 457, 513, 514
Congress, U.S., 2, 7, 93, 95, 99, 128 n, Danberg, James E., 431
172, 181, 198, 203, 225, 301, 310, 338, Darcey, Robert J., 380, 384, 393, 397,
339, 343, 360, 364, 369, 384, 387, 392, 398
396, 403,460, 467, 470, 475,482, Darwin, Australia, 540, 543, 580
484-90, 495, 517; Joint Committee on David Clark Company, 157, 192
Atomic Energy, 484, 486 Davis, Leo R., 247
Conlon, Emerson W., 406 Davis, William P., 108
Connor, Joseph, 105, 106 Day, LeRoy E., 6, 108, 109
Conrad, Charles, Jr., 153, 157, 158, 161, Dayton, Ohio 137 n
164, 167, 168 D. B. Milliken Company, 193
Consolidated Vultee Aircraft Corporation Deacon, 276
(Convair), 29, 30, 33, 34, 36, 37, 41, Debre Zeit, Ethiopia, 523, 541
42, 44, 45, 48, 50, 57, 92, 94, 96, 481, Debus, Kurt H., 179
484, 485, 535. See also General Decker, James L., 114
Dynamics Decker, Ralph S., 471
Control Data Corporation, 393, 396 Deep Space Network (DSN), 332, 521-23,
Coogan, John, 240 548, 549, 553, 554, 562, 564-96; Com-
Cooley, J. E., 243 patibility Test Station, 574; Deep
Cooley, William, 5 Space Instrumentation Facility, 565,
Cooney, Thomas V., 437 566; Deep Space Stations, 574
Coons, D. Owen, 116, 118, 120 Defense, U.S. Department of (DoD), 1,
Cooper, L. Gordon, 137 n, 138, 141, 4, 17, 29, 86, 87, 93 n, 98, 138, 140,
145-48, 153, 157, 159, 161, 166, 168, 153, 154, 156, 235,248, 286, 302, 303,
364 348, 360, 362, 366, 368, 370, 376, 378,
Cooper Development Corporation, 282 379, 382-84, 392, 393, 399, 465, 487,
Cornell Aeronautical Laboratory, 515 488, 490, 497, 500, 514, 524, 539, 541,
Cornell University, 337 544, 546, 548, 549, 551, 554, 560,
Corporal. See Baby Wac 562-64, 569, 571, 572, 575, 576, 578,
Corpus Christi, Texas, 523, 546, 548, 580, 583, 585, 589, 592, 593, 595, 596;
550, 552, 554, 561, 563, 580 Armed Forces Special Weapons Pro-
Cortright, Edgar M., 107, 109, 200, 201, ject, 483; Communications Agency,
301 366; Discoverer, 39, 560; Research and
Cotton, Paul E., 104-08, 407 Development Board, 403 n; Scientific
Coulter, John M., 107 Satellite Project, 1; Secretary of
Cover, Joseph W., 110 Defense, 95, 98, 138, 303, 542; Special
Covington, Ozro M., 539, 547, 559, 561 Capabilities, Committee on (Steward
Coyne, C. C., 108 Committee), 87, 235
INDEX 625
FordMotorCompany: Aeronautics
Divi- Gemini 6, 163, 552, 563; Gemini 7,
sion,310,311,549;Aeronutronic 162, 552, 563; Gemini 8, 164, 563;
Division,314-16,
560 Gemini 9, 165, 563; Gemini 10, 166,
Fordyce,
DonV., 393,399 563; Gemini 11, 167, 563; Gemini 12,
FormosaBay,300 168, 563; Gemini-Agena D, 157;
Forsythe,
DixonL., 5,254 Gemini Agena Target Vehicle, 38, 151,
FortChurchill,Canada,
272,277,282, 163-68; Gemini Experiments Office,
284,285,531n 153; Gemini Launch Vehicle (GLV),
FortIrwin,568 84, 158-61,163-68; Gemini Mission
Fort Myers, Florida, 523, 536, 539, 540, Evaluation Team, 159-68; Gemini
542, 543, 581, 585 Operational and Management Plan,
Fort Stewart, Georgia, 536, 539 n, 540, 156; Gemini Project Office, 153-55,
542, 581 157, 158, 174; Gemini-Titan (GT),
Foster, Norman G., 118 152-54, 157-63, 166, 552; Project
Foster, Willis B., 201 Gemini, 30, 37, 40, 85, 100, 101,439,
France, 272, 288, 295, 296, 373, 375-77; 522, 551,552, 562
Centre d'Etudes Nucleaires de Saclay, General Dynamics, 29, 30, 34, 36, 37, 41,
295, 297; Centre d'Etudes des 42, 44, 45, 48, 50, 53, 54, 57, 182,
Telecommunications, 296; Centre Na- 331,555 n; Astronautics, 261,262,
tional d'Etudes Spatiales (CNES), 296; 449, 450; Convair/Astronautics Divi-
satellites, 64, 221,288, 296 sion, 172, 180, 181. See also Con-
Freden, S., 119 solidated Vultee Aircraft Corporation
Freedman, Carl, 201 General Dynamics/Astronautics, 261,
Freedom 7, 143 262, 449-51,469, 485
Freitag, Robert F., 5, 106-08 General Dynamics/Convair Aerospace,
French Guiana, 559 517
Frick, Charles W., 113, 179, 182 General Dynamics/Electronics, 538 n
Friebaum, Jerome, 366, 385 General Electric Corporation (GE), 45,
Friendship 7, 100 86, 87, 150, 172, 180, 181, 192,
Fry, W. J., 107 260-62, 340, 343-46, 361, 362, 378,
Fucino, Italy, 376 393, 396, 397, 445,446, 462, 494, 515,
538 n; Missile and Space Vehicle
Department, 182, 446, 448; Spacecraft
Department, 360, 363
G General Motors Corporation, 193; AC
Electronics Division, 193
Gagarin, Yuri A., 100, 102, 141 General Purpose Airborne simulator, 505
Galileo, 259 General Services Administration, 366
Gamble, Allen O., 137 n Gentry, Jerauld R., 457-59
Gangler, James J., 434 Geodynamics Experimental Ocean
Garbacz, Michael L., 348, 349 Satellite (GEOS), 248, 252, 288, 400.
Garbarini, Robert F., 201 See also Explorer
Gardiner, Robert A., 117, 119 Geophysics Corporation of America:
Garland, Benjamin J., 98, 100 n Viron Division, 372
Garrett Corporation, 192 George C. Marshall Space Flight Center.
Gartrell, Harold E., 117, 119 See Marshall Space Flight Center
Gassiot High Altitude Vehicle, 283 Germany, Federal Republic of, 272, 288
Gautraud, John A., 104, 106 n, 534; Army, 275; Junkers Flugzeug-
Gay, Clarence C., Jr., 109 and Motorenwerke GmbH, 297;
Gemini, 2, 11, 13, 22, 24, 28, 29, 32, 38, Peenemiinde, 505; 534; rockets, 91,
83, 102, 103, 174, 176, 177, 182, 93, 275, 534; scientists, 505; West Ger-
190-94, 355, 441, 450, 548, 549, 552, man Post Office, 374, 377
554, 556, 562, 563, 565, 575, 580, 589, Gessow, Alfred, 432
591-93, 595; astronauts, 152-70, 174, Gibberson, Walker E., 326
442; characteristics and chronology, Gillam, I. T., 6
149-70; funding, 122, 126, 127, 133 n; Gilmore, Alaska, 575, 581
Gemini 3, 464, 552, 563; Gemini 4, Gilruth, Robert R., 95, 96, 99, 102, 103,
552, 563; Gemini 5, 161, 552, 563; 112, 113, 115, 116, 118, 120, 137 n,
628 NASAHISTORICAL DATA BOOK
Lindell,KeithG.,112 M
Lindsay,JohnC.,237,256,257,307
Ling-Temco-Vought AerospaceCorpora- McClintock, J. G., 116, 119
tion,62,449,466;Range Systems McCollough, Chester, 506
Division,555n; Vought Astronautics, McDivitt, James A., 152, 157, 160, 161
61,66 McDonald, F. B., 240, 241,243,246,
LinkGroupofGeneral Precision,
184 248, 251
Little,AlbertP., 108 McDonnell Aircraft Corporation, 102,
LittleJoe(LJ), 10,27,49,134,139;Lit- 137, 138, 140-43, 149, 150, 153-58,
tleJoeI, ll, 12,15,16,24,48-50, 182, 193,455. See also Douglas Air-
121,134,140;LittleJoeII, 16,24, craft Company
27,48,50,121,140,182,186 MacDougall, George F., Jr., 102 n
Livermore RadioationLaboratory,476, McElmurry, Thomas U., 110
483 McGolrick, Joseph E., 6
Lockheed MissilesandSpace Company, McGuire, Charles W., 109
29,36,37,39,57,67,74-76,151,154, Mach speeds, 92, 96, 501-03, 506-08
155,182,193,260,262,320,334,343, Machell, Reginald M., 119
344,389,397,476,481,484, 485,490, McKay, John B., 509-13
515 McKee, Daniel D., 104, 106
Loftus,Joseph P.,Jr. 119 Mackey, Robert J., Jr., 118, 119
London, Universityof (U.K.),295,297 McMullen, Thomas H., 109
Longanecker, GeraldW.,247 McMurdo Sound, Antarctica, 347
Long_Range Proving Ground (LRPG), 559 McTigue, John, 453, 457
Looney, C.H.,248 Madagascar, 543, 587, 588
Lord,Douglas R., 105,106,109,110 Madrid, Spain, 523, 548, 554, 556-58,
LosAlamos Scientific
Laboratory,476, 562, 563, 565, 571, 573, 579, 587, 590
478, 480, 483-85; Reactor Division, Magin, Betsy F., 102 n
482; Weapons Division, 482 Magnetometer-Plasma Probe, 239
Los Angeles, California, 98 Mahon, Joseph B., 4-6, 202
Love, Eugene S., 453 Maine, 376
Lovejoy, W. L., 6 Majunga, Malagasy Republic, 540, 543,
Lovelace, W. Randolph, 108 577, 588
Lovelace Foundation for Medical Educa- Manhattan Project, 482
tion and Research, 137 n Manke, John A., 457-59
Lovell, James A., Jr., 153, 157, 158, 160, Manchester, University of (U.K.), 292,
162, 164, 165, 168, 177, 185, 189 293
Lovell, Powell M., 407 "Manned Earth Reconnaissance" mission,
Low, George M., 102, 104-06, 108, 115, 94
116, 118, 176, 179-81, 185, 200 Manned Lunar Landing, Ad Hoc Task
Lucas, Thomas V., 525, 526 Group for Study of, 181
Ludwig, George H., 266, 268, 286 Manned Spacecraft Center (MSC),
Lunar and Planetary Missions Board, 198 Houston, 100, 103, 134, 139, 141,
Lunar Mission Planning Board, 184 154-57, 170, 172, 174, 176, 179,
lunar module (LM), 173-76, 179, 184, 182-84, 188, 189, 285,439, 466, 468,
187-94 469, 494, 522, 544, 551-53, 561, 563;
Lunar Orbiter, 29, 32, 37, 39, 40, 176, Experiments Program Office, 153;
205, 214 n, 215, 310, 319-25, 327, 556, Florida Operations Office, 179; Lunar
563, 565, 566; Lunar Orbiter 1 Surface Experiments Panel, 183;
through 5, 319-25; Project Office, 320 organization, 112-20. See also Space
Lunar Science Institute, 301 Task Group
Luskin, Harold T., 107, 110 Manned Spacecraft Criteria Board, 183
Lutman, C. C., 106 Manned Space Flight, Office of (OMSF),
Lyle, John, 108 4-6, ll, 13, 23, 24, 101, 102, Ill n,
121, 130 n, 179, 182, 301, 319, 320,
340, 341, 405, 466-68, 491,492, 554,
565; Division of Aerospace Medicine,
468; launch vehicle and propulsion
systems, 17, 18, 22-25
INDEX 633
Ness,
Norman F.,250,251 Olympic games, 369, 376
Netherlands,
the,288n,295 OMEGA Position Location Experiment
Nevada,474,483-85 (OPLE), 395
Newell,HomerE., Jr.,5,6, 199-201 O'Neill, James E., 105, 106
NewHampshire, University
of, 240-42, Operation Lost Ball, 343
247 Oppenheim, A. G., 285
NewJersey,369 Optical Tracking Network (OTN), 523
NewMexico, 544 orbital attitude and maneuvering system
NewMexico, Universityof, 254,257 (OAMS), 152
NewOrleans,Louisiana, 179n Orbiter, 235, 301, 541; Project Orbiter,
Newton,R.,247 535, 571
NewZealand, 272 Orbiting Astronomical Observatory
Nicks,OranW.,20i,301,340 (OAO), 13, 29, 32, 37, 39, 43, 44,
Nicolaides,
JohnD.,201 205, 209, 211, 232, 254, 288, 362, 538,
Nigeria,
561,565,572 543; characteristics and chronology,
Nimbus,20,38,69,70,75,77,205,220, 259-63
226n, 347,348,360-63, 473,493,494, Orbiting Geophysical Observatory
538,579;Nimbus 1 (Nimbus-A) and (OGO), ll, 13, 20, 29, 31, 32, 36,
Nimbus 2 (Nimbus-C), 360, 362, 363; 38-40, 69, 70, 75, 205, 209, 211, 232,
Nimbus 3, 494; Nimbus B, 360, 362, 288, 362, 437, 538-40, 543, 580;
494; Nimbus Operational System characteristics and chronology, 264-70
(NOS), 360, 361; Project Nimbus, 360 Orbiting Solar Observatory (OSO), 11,
Nolan, James P., Jr., 105, 106, 110 13, 21, 67-70, 80-82, 205, 209, 211,
Norris, Theodore B., 5, 6 232, 288, 538, 543; characteristics and
North, Warren J., 104, 113-15, 120, 137 n chronology, 254-59
North America, 389, 547 Organ Pass, Arizona, 523
North American Aviation Corporation, Orroral Valley, Australia, 538 n, 540,
48, 49, 52, 56, 58, 60, 134, 140, 152, 543, 589, 593
155-57, 176, 179, 180, 182, 183, 311, Ostrander, Ron R., 4, 5
327, 482, 502, 506-10, 515, 553, 562; O'Sullivan, William J., 239, 244, 368-70,
Los Angeles Division, 506; Rocket- 505
dyne Division, 29, 30, 34, 36, 37, 41,
42, 45-47, 51, 53-56, 59, 61, 68, 70,
72, 74-76, 80, 193; Rocketdyne P
engines, 30, 41, 45, 46, 55, 72, 74-79
North American Rockwell, 508 Pacific 2. See International Telecom-
Northrop Corporation, 193, 312, 343, munications Satellite Consortium
344, 452, 455, 457; Norair Division, Pacific Missile Range, 281, 531, 591. See
452, 455; Ventura Division, 193,439 also Wallops Island
North Sea, 557 Pacific (coast and ocean), 177, 178, 185,
Norway, 272, 294; Norwegian Institute of 343, 379, 381, 385, 390, 391, 397, 546,
Cosmic Physics, 294; Norwegian Space 550-52, 554, 555 n, 557, 558, 577, 584,
Committee, 294 587, 589, 594-96
Nova, 3, 10, 16, 24, 171, 172, 180, 182, Pad Abort-1 and 2, 178, 183, 186
491 n PAEGOS 1, 38, 40, 70, 75, 298,400
Nuclear Engine for Rocket Vehicle Ap- Pakistan, 272
plications (NERVA), 473,479-88 Panama, 536, 542
Nutley, New Jersey, 376 Panel on Operation Meteorological
Satellites, 361
paraglider landing system, 152, 155-57,
435,439
O Parkinson, John B., 497, 498
Parks, Robert J., 326, 328
O'Bryant, William T., 109 Parsons, John F., 103 n
Ocean of Storms area, 328 Pasadena, California, 1, 197, 340, 553,
Ohio State University Research Founda- 565
tion, 463 n Patterson, Herbert G., 102 n
Olifantsfontein, South Africa, 541, 586 Paul VI, Pope, 364
INDEX 637
Sergeant,
1, 47, 64, 235, 571; Sergeant- 272-74, 276-78, 284; Aerobee-Hi, 35,
Delta, 370 73, 275, 276; Arcas, 272-74, 276, 278,
SERT (Space Electric Rocket Test), 1, 64, 284, 444, 445; Arcon, 274, 279; Argo,
475; Project SERT, 472, 475,476; 272, 280, 281; Asp, 272, 281;
SERT 1, 64, 476, 477; SERT 2, 475, Astrobee, 272-74, 279, 285; Black
476 Bryant, 272-74, 276, 279, 280, 285;
service module (SM), 193 Iris, 274, 280; Javelin, 272-74, 280,
Shea, John T., 253 284; Journeyman, 272, 274, 281,340;
Shea, Joseph F., 104-06, 113-16 Nike, 272, 276, 280-82, 438, 439;
Sheffield, University of (U.K.), 293 Nike-Apache, 274, 281,284; Nike-
Shelton, Harvey W. C., 105, 107 Asp, 274, 282; Nike-Cajun, 273, 274,
Shepard, Alan B., Jr., 15, 120, 137 n, 276, 282, 285, 370; Nike-Deacon, 276;
138, 141, 143-48 Nikc-Tomahawk, 273, 274, 283,285;
Sherburne, R. K., 6 Skylark, 272, 274, 283; Tomahawk,
Shows, James C., 119 272, 273; vs. earth-orbiting satellites,
Shulman, Fred, 471 271
Sigma 7, 147 South Africa, 565
Silverstein, Abe, 2, 5, 35, 101, 104, 137 South America, 136, 542
n, 180, 200, 525 South China Sea, 557, 558
Sims, Theo E., 465,466 Southeast Asia, 591
Singapore, 540, 543, 591 South Point, Hawaii, 539 n, 540, 542,
Sinus Medii (area), 330 543, 591
Sjoberg, Sigurd A., 116, 118, 120 Southwest Center for Advanced Studies,
Skaggs, James B., 6, 109 251, 284
Skylab. See Apollo Soviet Union. See Union of Soviet
Slayton, Donald K., 103, 114-16, 120, Socialist Republics
137 n, 141, 143, 146, 147 Spacecraft Integration and Sounding
Slidell, Louisiana, 179 n Rocket Division, 271
Slidell Computer Facility, 179 n Space Electronics, 560
Slivka, William R., 471 Space-General (Aerojet-General), 278
Sloan, James E., 105 space science and applications, 197-400;
Sloop, John L., 5,406, 471 ATS program, 392-99; budget, 203-31;
Small, John W., 118, 119 communications program, 364-91; life
Smith, Arvin H., 471 sciences program, 340-46, 466-69;
Smith, Charles P., 373, 375, 385, 389-91 lunar and planetary program, 300-40;
Smith, Earl K., 117 meteorology program, 346-63; physics
Smith, Francis B., 525 and astronomy program, 232-300
Smith, G. Dale, 104, 200 Space Task Group (STG), 102, 103, 134,
Smith, Henry J., 201, 205 137-41, 144, 149, 155, 171 n, 172, 181,
Smith, Norman F., 112 466, 467, 545, 547, 549, 551, 560, 561;
Smith, W. S., 285 Advanced Vehicle Team, 180;
Smithsonian Astrophysical Observatory Aeromedical Consultants Staff, 466;
(SAO), 260, 261, 399, 524, 539-41, Engineering and Contract Administra-
585; Celescope, 263; Tracking Net- tion Division, 112 n; Flight Systems
work, 541 Division, 112 n, 155; New Projects
Smolensky, Stanley M., 6, 104, 106, 108 Panel, 155, 180; Operations Division,
Smull, Thomas L. K., 200, 201 112 n, 113 n; organization, 112-20;
Smylie, Robert E., 119 Technical Liaison Groups, 181. See
Snyder, Samuel, 5,471 also Manned Spacecraft Center
SOCS (spacecraft orientation control Space Technology Laboratories, Inc.
system) project, 419 (STL), 34, 35, 72, 182, 194, 237, 255,
Solant, 540, 543, 591 265, 266, 302, 303, 305, 307, 320, 327,
Solar Electric Propulsion Systems 376, 377, 485, 538. See also TRW
Technology (SEPST), 475 Space Tracking and Data Acquisition
Sorlie, Donald, 457, 458 Network (STADAN), 395, 521-23,
Soule, Hartley, 505 534-43, 569 n, 575-96
sounding rocket program, 205, 206, 209, Spain, 288 n, 561, 565, 568, 572, 573,
220, 228-31, 270-85, 288; Aerobee, 87, 582
INDEX 641
Sparrow, 276 Surveyor, 14, 29, 31, 32, 42-44, 176, 205,
Special Committee on Life Sciences, 341 214 n, 215, 301, 310, 319-23, 325-31,
Spencer, N. W., 243, 250, 267, 269 338, 493, 565, 566, 570; Surveyor 1
Sperry Gyroscope Company, 571 through 7, 326-31
Spin Scan Cloud Cover Experiment Swanson, Andrew G., 445,447
(SSCCE), 395 Sweden, 272, 294; Kiruna Geophysical
Spreen, William C., 271, 348 Observatory, 43
Stack, John P., 406, 497, 498 Sweeney, William R., 108
Stafford, Henry N., 380 Swigert, John L., 188
Stafford, Thomas P., 153, 157-59, 163, Switzerland, 288 n
165, 188 Sylvania, 393
Stampfl, Rudolf A., 349 Syncom, 13, 21, 67, 69, 81,205, 206,
Stanford Research Institute, 378, 382 224, 364, 367, 368, 380, 393, 396; Ad-
Stanford University, 237, 307-09, 337, vanced Syncom, 392, 393, 396; Project
339 Syncom, 377, 379, 385; Syncom 1,
Starfish (high altitude nuclear test), 242, 380, 382, 383, 396; Syncom 2, 380-82,
375 384, 396; Syncom 3, 364, 381, 382,
State, U.S. Department of, 364, 366, 368, 384, 396
524 Systems Engineering Group. See WECo
Station Technical Operations Control, Systems for Nuclear Auxiliary Power
543 (SNAP), 360-62, 473,494, 495
Stephens, Robert R., 525 Syverston, Clarence A., 453
Sternfield, Leonard, 497, 498
Sterrett, John, 525
Stevens, Samuel R., 296
Stevenson, John D., 110 T
Stever, H. Guyford, 98
Steward Committee. See Defense, U.S. Talbot, John M., 105
Department of Talentino, J., 294, 295
Stoddard, David H., 105, 106 Tananarive, Malagasy Republic, 523, 538
STOL (short takeoff and landing), 501 n, 540, 543, 548, 552, 554, 557, 587,
Stoller, Morton J., 200, 271 588, 591
Stone, David G., 395,449, 451 Tasman Sea, 343,557
Stone, Robert G., 253 Taylor, B., 297
Stoner, George, 109 Taylor, Charles A., 526
Stoney, William E., 109, 114, 115, 117 Taylor, Eldon D., 201, 202
Strass, H. Kurt, 180, 436 Taylor, Paul D., 102 n, 111
Stroud, William G., 348, 349, 352, 361 Taylor, William B., 105, 106, 109, 111
Strughold, Hubertus, 96 TEL-4 (tracking station), Florida, 548,
Studebaker-Packard Corporation: Cincin- 592
nati Testing and Research Laboratory, Telstar, 68, 69, 81,202, 364, 367, 373-75,
194 377; Telstar I and 2, 373-75
Stuhlinger, Ernst, 238, 440 Temco, 361
Sullivan, Francis J., 407,460 Temple University, 251, 337
Summerfelt, William A., 108 Tepper, Morris, 201, 346, 347, 349
Sunblazer, 212 n Test and Training Satellites (TTSs), 554;
Sunderlin, Wendell S., 377, 379 TTS-1 (TETR-1), 308, 554, 559, 563;
supersonic/hypersonic transport, 501-17; TTS-2 (TETR-2), 309, 554, 559, 563
Douglas FSD-1 skylancer, 515 n; Test Cell A, 483
F-100C Super Sabre, 515 n; F-104, 515 Texas A&M University, 355
n; F-Ill, 517; Lockheed YF-12A Textron, 36, 37, 74-76
Blackbird, 515 n, 517; North Thatcher, J. W., 566
American A-5A Vigilante, 515 n; Thibodaux, Joseph G., Jr., 115, 117, 119
SCAT (Supersonic Commercial Air Thiokol Chemical Corporation, 49, 50,
Transport), 515; SST, 514-17; SST 62, 63, 67, 75, 76, 78-80, 194, 279-83,
Advisory Board, 514; X-15, 502-14; 489, 490, 502, 506
XB-70, 515-17. See also SCANNER Thome, Pitt, 202
Sures, Allan H., 260 Thompson, Floyd L., 176, 184
642 NASA
HISTORICAL
DATABOOK