Académique Documents
Professionnel Documents
Culture Documents
. Assume start date as 05 Nov 2012. Identifier Activity Perform Planning and Scheduling A1 Revise overall project plan A2 Complete detailed plan for detail design A3 Revise skeleton and generic plan for rest A4 Brief new team members A5 Complete phase estimate A6 Review plan A7 Revise plan A8 Complete project schedule A9 Milestone Prepare Database Design B1 Document data models to catalog B2 Determine file structures for flat files B3 Prepare copylibs for flat file structures B4 Define each process B5 Review process access with database administration B6 Physical database design B7 Review design B8 Revise design B9 Conduct call pattern reviews B10 Milestone Prepare Physical Design Documents C1 Prepare process to program specifications C2 Determine security specifications C3 Prepare physical system flow C4 Milestone D1 Design programs and write specifications D2 Write data conversion and interface programs D3 Revise documents D4 Milestone Predecessor None A1 A1 A2, A3 A4 A5 A6 A5start + 3 A7, A8 None B1 B1 B2, B3 B4 B5 B6 B7 B6 B8, B9 B4 B9, C1 C2 C3 A8, B9 D1 D2 D3 Days 10 3 3 1 4 1 11 4 0 13 10 7 3 1 10 1 10 8 0 10 8 10 0 10 6 20 0 P B, P B, P B, P R(3) R (3) B, P B B B, P D, M, N, P B, R B, D, M, N, P B, R B Resource N, P P P M, N, P O, P M, N, O, P O, P N
E1 E2 E3 E4
C3, D3 E1 E2 E3
6 10 2 0
B, P, R B, P, R M, N, D
Work 5 days Per Week Holidays rd 3 and 4th Monday in Nov 3rd Monday in Dec, 25 Dec 1st and 3rd Wednesday in Jan 2013 Details of Resources Resources M Manager N Assistant O Cost estimator P System analysts P1, P2 Cost/Day $300(1) $150(1) $200(1) $350(2) Resources R Systems programmers R1,R2 and R3 D Database administrator B Database designers Cost/Day $200(3) $500(1) $300(1)
Answer the following:Stage-1 (a) What is the project finish date before leveling? (b) (d) (e) Which are the over scheduled resources? Carry out resource leveling and show your results Save the project as a baseline. Generate the following:(i) Gantt chart showing start and finish dates of each activity and resources assigned. (ii) Network diagram (iii) Relationship diagram (iv) Resource sheet (v) Resource Usage (vi) Task Sheet (vii) Task Usage
Stage-2 Consider that 27 days have passed. Task completion status is as follows:(a)A1,A2, A4,B1 and B2 is 100% (b)A3, B3 and B4 is 50% Carry out EV analysis find SPI,CPI and EAC
Note : 1. Assume suitable values wherever required. 2. You may use Microsoft Project or any other suitable software application -----------------------------------------------------------------------------------------------------------