Académique Documents
Professionnel Documents
Culture Documents
1.29
REMARKS
1.0 MATERIALS:Ready Mixed Spatterdash Slurry Coat for Blocks (Premix SRC-1) --> (4kg/m) Premix SP-1 (1.6kg per m per 1mm thk) Clean Cool Water Plaster accessories kg kg liters 25.80 206.40 43.344 0.39 0.35 0.038 10.00 71.21 1.63
Rate = Inv. Rate + 25%OH&P Rate = Inv. Rate + 25%OH&P Rate = Inv. Rate + 25%OH&P
Wastage (3%)
2.48
SUB-TOTAL (1.0)
85.32
2.0 EQUIPMENTS/PLANT :2.1 Motor Hose 2.2 Air Hose 2.3 Power Spray Gun 2.4 Hose Bracket 2.5 Driver Claw 2.6 Electric mixer 2.7 Rotor D5 2.8 Stator D5 SUB-TOTAL (2.0) -
5/3/F 5/3/A
7.48 7.48
21.20 15.29
158.58 114.36
3.2 Laborers
(Rate = Daywork Rates + 25%OH + 25%P)
TOTAL (1.0-3.0)
358.26
UNIT RATE
277.72
DMCC - AL MAS TOWER PROJECT JAP016 - PACKAGE NO. 3 : MAIN BUILDING WORKS JUMEIRAH LAKE TOWERS
1.29
REMARKS
1.0 MATERIALS:Ready Mixed Spatterdash Slurry Coat for Blocks (Premix SRC-1) --> (4kg/m) Premix SP-1 (1.6kg per m per 1mm thk) Clean Cool Water Plaster accessories kg kg liters 25.80 206.40 43.344 0.39 0.35 0.038 10.00 71.21 1.63
Rate = Inv. Rate + 25%OH&P Rate = Inv. Rate + 25%OH&P Rate = Inv. Rate + 25%OH&P
Wastage (3%)
2.48
SUB-TOTAL (1.0)
85.32
2.0 EQUIPMENTS/PLANT :2.1 Rotor (Spare part for premix plaster machine) 2.2 Stator (Spare part for premix plaster machine) 2.3 Mixing Spiral 2.4 Motor Hose 2.5 Air Hose 2.6 Hose Bracket 2.7 Driver Claw 2.8 Adjustable Clamps SUB-TOTAL (2.0) No. No. No. No. No. No. No. No. 650.00 550.00 850.00 1,125.00 145.00 1,200.00 700.00 575.00 -
5/3/F 5/3/A
7.48 7.48
21.20 15.29
158.58 114.36
3.2 Laborers
(Rate = Daywork Rates + 25%OH + 25%P)
TOTAL (1.0-3.0)
358.26
UNIT RATE
277.72
DMCC - AL MAS TOWER PROJECT JAP016 - PACKAGE NO. 3 : MAIN BUILDING WORKS JUMEIRAH LAKE TOWERS
1.29
REMARKS
1.0 MATERIALS:Ready Mixed Spatterdash Slurry Coat for Blocks (Premix SRC-1) --> (4kg/m) Premix SP-1 (1.6kg per m per 1mm thk) Clean Cool Water Plaster accessories kg kg liters 25.80 206.40 43.344 0.39 0.35 0.038 10.00 71.21 1.63
Rate = Inv. Rate + 25%OH&P Rate = Inv. Rate + 25%OH&P Rate = Inv. Rate + 25%OH&P
Wastage (3%)
2.48
SUB-TOTAL (1.0)
85.32
2.0 EQUIPMENTS/PLANT :2.1 Electric Mixer 2.2 Power Spray Gun 2.3 Steel Float ehr ehr ehr 0.10 6.45 1.03 5.00 5.00 0.50 0.50 32.25 0.52
SUB-TOTAL (2.0)
33.27
5/3/F 5/3/A
mhr mhr
7.48 7.48
21.20 15.29
158.58 114.36
3.2 Laborers
(Rate = Daywork Rates + 25%OH + 25%P)
TOTAL (1.0-3.0)
391.53
UNIT RATE
303.51
DMCC - AL MAS TOWER PROJECT JAP016 - PACKAGE NO. 3 : MAIN BUILDING WORKS JUMEIRAH LAKE TOWERS
1.29
REMARKS
1.0 MATERIALS:1.1 Ready Mixed Spatterdash Slurry Coat for Blocks (Premix SRC-1) --> (4kg/m) 1.2 Premix SP-1 (1.6kg per m per 1mm thk) 1.3 Clean Cool Water 1.4 Plaster accessories 1.5 Wastage (3%) 2.44 kg kg liters 25.80 206.40 43.34 0.39 0.35 0.004 10.00 71.21 0.16
Rate = Inv. Rate + 25%OH&P
SUB-TOTAL (1.0)
83.81
2.0 EQUIPMENTS/PLANT :2.1 Spare Parts for Spraying Machine (2% material cost) 2.1 Spraying Machine 2.2 Material Hoist 2.3 Water Tank ehr ehr ehr 2.00% 81.21 1.62
SUB-TOTAL (2.0)
49.69
3.2 Plasterers
(Rate = Daywork Rates + 25%OH + 25%P)
3.3 Laborers
(Rate = Daywork Rates + 25%OH + 25%P)
TOTAL (1.0-3.0)
577.95
UNIT RATE
448.02
DMCC - AL MAS TOWER PROJECT JAP016 - PACKAGE NO. 3 : MAIN BUILDING WORKS JUMEIRAH LAKE TOWERS
1.29
REMARKS
1.0 MATERIALS:1.1 Ready Mixed Spatterdash Slurry Coat for Blocks (Premix SRC-1) --> (4kg/m) 1.2 Premix SP-1 (1.6kg per m per 1mm thk) 1.3 Clean Cool Water 1.4 Wastage (3%) Sodap Sodap kg kg liters 25.80 206.40 43.34 0.39 0.35 0.004 10.00 71.21 0.16 2.44
Rate = Inv. Rate + 25%OH&P
SUB-TOTAL (1.0)
83.81
2.0 EQUIPMENTS/PLANT :2.1 Spare Parts for Spraying Machine (10% material cost = 10%(1.1 + 1.2) * 1.03) 10.00% 83.64 8.36
Sodap will provide the spraying machine but JV will pay for the spare parts
2.2 Hoist 2.3 Generator set 2.4 Water Pump 2.5 Water Tank 2.6 Scaffolding materials SUB-TOTAL (2.0)
3.2 Plasterers
(Rate = Daywork Rates + 25%OH + 25%P)
3.3 Laborers
(Rate = Daywork Rates + 25%OH + 25%P)
3.4 Scaffolders
(Rate = Daywork Rates + 25%OH + 25%P)
TOTAL (1.0-3.0)
392.07
UNIT RATE
303.93
DMCC - AL MAS TOWER PROJECT JAP016 - PACKAGE NO. 3 : MAIN BUILDING WORKS JUMEIRAH LAKE TOWERS
1.29
REMARKS
1.0 MATERIALS:1.1 Ready Mixed Spatterdash Slurry Coat for Blocks (Premix SRC-1) --> (4kg/m) 1.2 Premix SP-1 (1.6kg per m per 1mm thk) 1.3 Clean Cool Water 1.4 Wastage (3%) Sodap Sodap kg kg liters 25.80 206.40 43.34 0.35 0.31 0.003 8.96 63.80 0.15 2.19
Rate = Inv. Rate + 12%OH&P
SUB-TOTAL (1.0)
75.09
2.0 EQUIPMENTS/PLANT :2.1 Spare Parts for Spraying Machine (10% material cost = 10%(1.1 + 1.2) * 1.03) 10.00% 74.94 7.49
Sodap will provide the spraying machine but JV will pay for the spare parts
2.2 Hoist 2.3 Generator set 2.4 Water Pump 2.5 Water Tank 2.6 Scaffolding materials SUB-TOTAL (2.0)
3.2 Plasterers
(Rate = Daywork Rates + 12%OH &P)
3.3 Laborers
(Rate = Daywork Rates + 12%OH &P)
3.4 Scaffolders
(Rate = Daywork Rates + 12%OH &P)
TOTAL (1.0-3.0)
307.06
UNIT RATE
238.03
DMCC - AL MAS TOWER PROJECT JAP016 - PACKAGE NO. 3 : MAIN BUILDING WORKS JUMEIRAH LAKE TOWERS
1.30
REMARKS
1.0 MATERIALS:1.1 Ready Mixed Spatterdash Slurry Coat for Blocks (Premix SRC-1) --> (4kg/m) 1.2 Premix SP-1 (1.6kg per m per 1mm thk) Sodap Sodap kg kg 5.00 208.00 0.31 0.28 1.55 57.41
For Consumption Rate, see attached method statement (Attachment 2.2) For Consumption Rate, see attached method statement (Attachment 2.3)
liters
46.00
0.022
1.03
For Consumption Rate, see attached method statement (Attachement 2.2 & 2.3)
1.4 Wastage (5%) Subtotal >>> JV's OH & P (12%) >>> TOTAL FOR MATERIALS
2.0 EQUIPMENTS/PLANT :2.1 Spare Parts for Spraying Machine (10% material cost = 10%(1.1 + 1.2) * 1.03) 10.00% 60.73 6.07 Sodap will provide the
spraying machine but JV will pay for the spare parts
2.2 Hoist
(Rate = 15375 / 26 / 8)
2.5 Scaffolding materials Subtotal >>> JV's OH & P (12%) >>> TOTAL FOR EQUIPMENTS/ PLANT
3.0 MANPOWER/LABOUR :3.1 Chargehand 3.2 Plasterers 3.3 Laborers (including roughening) 3.4 Scaffolders Subtotal >>> JV's OH & P (12%) >>> TOTAL FOR MANPOWER/ LABOUR 5/3/F 5/3/A 5/3/B mhr mhr mhr mhr 1.25 5.59 6.89 0.25 23.88 14.13 10.19 14.13 29.85 78.99 70.21 3.53 182.58 21.91 204.49
mhr = 10% (3.2 + 3.3) Parameter = 0.86mhr/m *5
TOTAL (1.0-3.0)
349.87
UNIT RATE
269.13
1200mm 900mm
Coupler Braces
Spigot Jack
200
Propping ties
1200mm
2 2
Description
Standard Open Ended 2500mm Standard Open Ended 700mm Propping Ties 1200mm Propping Ties 900mm Coupler Braces 1500mm Spigot Jack 565mm Deck Platforms
Unit
nos. nos. nos. nos. nos. nos. nos.
SCAFFOLDING WORKS
1200mm
900mm
Spigot Jack
1200mm
Propping ties
Description
Standard @ 2.5m Standard @ 0.7m Propping Ties @ 1.2m Propping Ties @ 0.9m Coupler Bracing @ 1.5m Universal Jack & Socket Scaffolding Boards
Unit
nos. nos. nos. nos. nos. nos. nos.
Unit Rate
0.1933 0.0683 0.0700 0.0600 0.0875 0.0683 0.0875
Amount
0.7732 0.2732 0.42 0.36 0.35 0.2732 0.525
2.9746
per day
1200mm
Coupler Braces
FLOOR HEIGHT
1200mm
Standards
DMCC - AL MAS TOWER PROJECT JAP016 - PACKAGE NO. 3 : MAIN BUILDING WORKS JUMEIRAH LAKE TOWERS
1.30
REMARKS
1.0 MATERIALS:1.1 Ready Mixed Spatterdash Slurry Coat for Blocks (Premix SRC-1) --> (4kg/m) 1.2 Premix SP-1 (1.6kg per m per 1mm thk) Sodap Sodap kg kg 5.00 208.00 0.31 0.28 1.55 57.41
For Consumption Rate, see attached method statement (Attachment 2.2) For Consumption Rate, see attached method statement (Attachment 2.3)
liters
46.00
0.022
1.03
For Consumption Rate, see attached method statement (Attachement 2.2 & 2.3)
1.4 Wastage (5%) Subtotal >>> JV's OH & P (12%) >>> TOTAL FOR MATERIALS
2.0 EQUIPMENTS/PLANT :2.1 Spare Parts for Spraying Machine (10% material cost = 10%(1.1 + 1.2) * 1.03) 10.00% 60.73 6.07 Sodap will provide the
spraying machine but JV will pay for the spare parts
2.2 Hoist
(Rate = 15375 / 26 / 8)
2.5 Scaffolding materials Subtotal >>> JV's OH & P (12%) >>> TOTAL FOR EQUIPMENTS/ PLANT
3.0 MANPOWER/LABOUR :3.1 Chargehand 3.2 Plasterers 3.3 Laborers (including roughening) 3.4 Scaffolders Subtotal >>> JV's OH & P (12%) >>> TOTAL FOR MANPOWER/ LABOUR 50% 5/3/F 5/3/A 5/3/B mhr mhr mhr mhr 1.25 5.59 6.89 0.25 23.88 14.13 10.19 14.13 14.93 78.99 70.21 3.53 167.65 20.12 187.77
mhr = 10% (3.2 + 3.3) Parameter = 0.86mhr/m *5
TOTAL (1.0-3.0)
310.03
UNIT RATE
238.49