Académique Documents
Professionnel Documents
Culture Documents
Date : 10/11/2003
Page : 1
Description
1 - PRIMARY ELEMENTS
1-1
100 - FOUNDATIONS
1-2
Cost
R
Quantity
Unit
Cost per
Unit
R
Cost per
M2
R
Cost
%
818 756
205.64
M2
3 981.50
3 981.50
86.47%
58 756
53.09
M2
1 106.73
285.72
6.21%
26 424
53.09
M2
497.71
128.49
2.79%
214 955
174.59
M2
1 231.20
1 045.30
22.70%
45 000
252.17
M2
178.45
218.83
4.75%
214 761
252.17
M2
851.65
1 044.35
22.68%
1-3
1-4
1-5
1-6
105 - ROOFS
51 805
62.55
M2
828.22
251.92
5.47%
1-7
15 740
45.44
M2
346.39
76.54
1.66%
1-8
107 - PARTITIONS
11 892
40.59
M2
292.98
57.83
1.26%
1-9
19 843
98.09
M2
202.29
96.49
2.10%
1-10
24 590
312.45
M2
78.70
119.58
2.60%
1-11
24 034
152.55
M2
157.55
116.88
2.54%
1-12
111 - FITTINGS
82 268
11.41
M2
7 210.17
400.06
8.69%
1-14
12 893
NO
4 297.81
62.70
1.36%
1-15
7 544
NO
2 514.71
36.69
0.80%
8 250
14.5
568.97
40.12
0.87%
2 - SPECIAL INSTALLATIONS
58 154
282.80
6.14%
2-3
32 025
104.55
M2
306.31
155.73
3.38%
2-23
26 129
205.64
M2
127.06
127.06
2.76%
4 - EXTERNAL WORKS
69 978
340.29
7.39%
1-16
2
4-1
5 746
50
114.92
27.94
0.61%
4-4
4 550
50
91.00
22.13
0.48%
4-5
3 940
10
394.00
19.16
0.42%
409 - EARTHWORKS
55 742
119
M3
468.42
271.07
5.89%
4-10
TOTAL
946 888
4 604.59
100.00%
VAT
132 564
644.64
14.00%
1 079 452
5 249.23
114.00%
GRAND TOTAL