Académique Documents
Professionnel Documents
Culture Documents
F (Fig. 3).
To determine the pressure rating needed, the operator eval-
uated 29 frac stages from wells in the same section/township/
range as the damaged well. Bottomhole pressures were calculated,
and owback rates and pressures were analyzed along with sur-
face treating pressures. It was determined that the composite plug
would need a differential-pressure rating of at least 6,000 psi. The
operator requested an 8,000-psi rating. Finally, a 3 1/4-in. com-
posite frac plug was modied to 3.06 in. and tested for pressure
and temperature capacity. The test revealed that 300
F tempera-
ture was not a problem; however, even though the plug could
withstand pressures more than 6,000 psi, the vendor was not com-
fortable rating the custom plug at greater than 6,000 psi.
The nal plug test occurred in a different well to be completed
before the casing repair. A nearby offset was chosen, and comple-
tion operations were performed. The lower six zones of the offset
well were completed with the wireline-conveyed custom-compos-
ite frac plug run on the bottom of the perforation gun. The bottom
stage was fracture stimulated, the gun and plug for the next stage
were run, and the plug was set and perforations were made. Next,
the stage was completed, exposing the plug to fracturing pressure.
After this stage, the next plug and gun were run, and the process
was repeated until the bottom six stages were completed. At this
point, the well was owed back. After a couple of days, a service
unit was brought in to drill out the test plugs. The customplugs per-
formed to specication because each one was exactly where it was
placed before stimulation operations and was drilled without issue.
Now that the single-joint solid-expandable-liner and plug
designs were reviewed and tested, the nal design component had
to do with drilling out the plugs with the restricted ID of the liner
and the production tubing string to be run in the well after com-
pletion operations were nished. Coiled tubing (CT) with a 1.688-
in. OD would be used to drill out the frac plugs above and below
the repair. After all plugs were drilled out, the production-tubing
string would be landed in the well.
One production-string issue that required attention was the
need to increase the annular space between the ID of the expanded
liner and the OD of the tubing collar. The expanded-liner ID of
3.261 in. combined with the 2 3/8-in. EUE-collar OD of 3.063 in.
warranted the ush-joint tubing option through the liner to miti-
gate particles packing off in the annular space between the
expanded liner and the tubing collar. Therefore, the production
tubing string would consist of the following components:
1,990 ft. of 2 3/8-in., 4.6-lbm/ft L-80 ush-joint tubing
(open-ended)
Crossover sub
9,330 ft of 2 3/8-in., 4.6-lbm/ft N-80 EUE tubing.
Installation and Performance
To begin the installation process, a service unit was rigged up over
the well, and a 2 3/8-in., 4.6-lbm/ft, P-110 tubing was run in the
hole to 9,900 ft to circulate the wellbore. After consistent, clean
returns were coming back, the tubing was pulled. The single-joint
solid-expandable liner was run in the hole along with a crossover,
one 6-ft. P-110 pup joint, and 307 joints of 2 3/8-in., 4.6-lbm/ft, P-
110 tubing to place the center of the liner across from the part. A
pipe tally was performed, and a wireline gamma ray tool was run
to correlate tubing and patch depth. After a safety meeting, the
well was circulated at 1 bbl/min to clean the liner-setting ball seat.
At this point, the ball was dropped, and circulation began until a
pressure increase was witnessed, signaling the landing of the ball
in the liner-setting ball seat. After the ball landed, expansion was
started by pressuring up the tubing to 8,000 psi. The liner was then
expanded with a 10,000-lbf overpull on the work string and an av-
erage of 6,000 psi of hydraulic pressure as the expansion cone
3.25" 3.06"
Green composite
components were trimmed
down from 3.25 inches to
3.06 inches
Fig. 3Custom-composite frac plug.
116 June 2013 SPE Drilling & Completion
slowly expanded the liner from bottom to top. After the liner was
expanded and the launcher assembly was stung out of the
expanded single-joint liner, a casing-pressure test was performed
to 4,000 psi as an immediate test to determine whether casing in-
tegrity had improved. The 4,000-psi pressure test was a success.
Tubing was pulled; a 3 1/4-in. mill, a bit sub, and tubing were run
in the hole to drill out the pressure plate in the liner. Tubing tagged
the pressure plate at 9,775 ft (after correcting to wireline depth),
conrming the liner was set at the correct depth. After operations
were drilled and reamed, the pressure plate then circulated the well
while working through the lower portion of the expanded single-
joint liner. Condent that the pressure plate had been drilled and
all components had been circulated out of the wellbore, one could
prepare for stimulation operations to begin.
A nal pressure test to 8,500 psi was performed, and the casing
passed. It was decided to run a 3.25-in. gauge ring through the
expanded single-joint liner before every perforating run to ensure
plugs and guns would not get hung up in the liner. The rst gauge
ring that was run before perforating the bottom interval would not
pass through the expanded single-joint liner. After sizing down to
3.15 in., the gauge ring still would not pass through the expanded
single-joint liner ID of 3.261 in. A 3.20-in. watermelon mill was
run in the hole and milled the top of the expanded liner briey
before falling through the rest of the expanded single-joint liner
with no issue. After the frac head was reinstalled and tested, the
bottom frac interval was perforated; the 2.50-in. guns went through
the expanded liner without incident. The bottom stage was com-
pleted, a 3.20-in. gauge ring was run through the expanded single-
joint liner, and the custom plug with perforation gun for the next
stage was run without issue. The plug was set, and perforations
were shot. The stage was completed, and the process was repeated
up the wellbore for the remaining stages below the repair without
incident. The four stages above the expanded liner were then com-
pleted with conventional composite frac plugs. With no sand or
hang-up issues through the expanded single-joint liner during
completions, attention was turned to the drill-out process.
The 1.688-in. CT was used to drill out all plugs. After drilling
the frac plugs above the liner, the 3.875-in. underreamer could not
get past 9,700 ft. It was pulled out of the hole (POOH), and a
3.15-in. mill, motor, and CT were run to 9,700 ft to work through
the tight spot. The mill was used to clean through the liner, tag the
rst custom frac plug below the liner, and was POOH. In prepara-
tion to drill out the remaining frac plugs below the liner, the CT
bottomhole assembly consisted of a 3.15-in. mill, a 3.875-in.
underreamer, a mud motor, and jars. With minimal sand on plugs,
the plug location was correct for every plug run below the liner
(Fig. 4). At this point, the CT was POOH, and the well was put on
owback/sales. After owback pressures and water rates dropped,
a snubbing unit was moved in and rigged up to snub in production
tubing. The production-tubing string consisted of 60 joints of 2 3/
8-in. ush-joint tubing to be run through the liner and below, fol-
lowed by 286 joints of 2 3/8-in., 4.6-lbm/ft L-80 tubing landed in
the production tree.
The nal wellbore schematic is shown in Fig. 5.
Summary Discussion
The operator was faced with the issue of casing-integrity failure
in one of their Piceance basin wells. It is a problem that the opera-
tor has faced several times over the course of drilling and com-
pleting more than 4,000 wells in the basin. The economics of
running a frac liner with slimhole perforating guns and possibly
shing the liner out of the hole, combined with a less effective
stimulation, did not appeal to the operator. Writing off two-thirds
of the well reserves by completing only the upper four zones was
also uneconomical. Furthermore, after unsuccessful attempts to
repair the well with a corrugated liner and cement squeezes, the
well sat dormant for a year as the team re-evaluated how best to
move forward. A different expandable liner was chosen because
of its solid, single-joint design; high internal yield strength; and
large post-expansion ID. Custom frac plugs were designed, tested,
and used along with CT to put the well on full production.
With minimal operational problems throughout the installation
of the single-joint solid-expandable liner, the running of the plugs,
and drillout/owback of the well, opportunities for improvement
are largely focused on cost. CT worked for this project; however,
moving forward, the use of a service unit with slim tubing would
be more cost-effective to drill out plugs below the expanded sin-
gle-joint liner.
Ultimately, the operator was able to address a familiar issue in
a way that enabled full recovery of the wells reserves. This was a
rst for the operator, considering the high treating pressure and
location of the split. The plug-and-perforate method had not been
an option in the past; however, in the future moving forward, the
operator has a cost-effective solution that enables the use of plugs
and ensures the operator that effective stimulation of the pay
interval is still possible.
Solid-expandable-tubular technology, engineering advance-
ments in frac-plug design, and CT advancements have given the
oil and gas industry tools that were not available in the past.
Fig. 4Single-joint solid-expandable liner installed, indicating
frac-plug type and location post-stimulation.
June 2013 SPE Drilling & Completion 117
Supplemental to the case outlined in this paper, the application of
these technologies could involve, but certainly are not limited to,
multiple parts in a casing string, sliding-sleeve bypass, or isolation
of perforations that are no longer necessary.
This paper strives to convey the benet of stepping back from a
familiar issue and thinking through all possible solutions, particu-
larly those solutions that have not been tried in the past. Finally, this
case study should be viewed as yet another example of how a team
can accurately diagnose a problem, think through a solution that
clearly meets the dened criteria, and show how eld testing the so-
lution before application is the way to ensure safe and reliable wells.
Acknowledgments
The authors wish to thank management at WPX Energy, Enven-
ture Global Technology, and Magnum Oil Tools for approval to
publish and present this paper. In addition, the authors wish to
thank the WPX EnergyPiceance Field completions staff and
ofce, including Jay Foreman, Kent Hejl, and Brian ODell;
members of the Enventure Global Technology engineering and
operations teams, including Chris Cornelius, Kris Mitrushi, and
Robert Goss; and the design staff at Magnum Oil Tools, including
Lynn Frazier, Mark Chaudoir, Ken Yong, and Derrick Frazier.
References
Waddell, K. and Schuurmans, R. 2004. Installation of Solid Expandable
Tubular Systems Through Milled Casing Windows. Paper SPE 87208
presented at the IADC/SPE Drilling Conference, Dallas, texas, 24
March. http://dx.doi.org/10.2118/87208-MS.
Chris Caplis is Completions Team Lead for the Piceance basin
for WPX Energy Rocky Mountain, LLCin Denver. He has 15 years
of oil and gas experience in drilling and completion engineer-
ing, with most of his time spent in the Rocky Mountains. Caplis
currently oversees completions in the Niobrara formation for
WPX Energy in the Piceance basin. He earned a BS degree in
petroleumengineeringfromLouisianaTech University.
John Cameron is currently the Well Services Solutions Manager
at Enventure Global Technology in Houston, where he has
been working for nearly 2 years. At Enventure, Cameron pro-
motes and develops solutions with solid-steel expandable cas-
ing and liners for well-production and completion challenges.
Before coming to Enventure, he worked as a consultant for 1
1/2 years with Eclipse Petroleum Technology in Houston, and
as a consultant for 9 years for PCM Technical in Tulsa. At these
companies, Cameron consulted in the areas of drilling, well
completions, unconventional reservoirs, and geomechanics.
Before his role as a consultant, he worked as a staff engineer
for 18 years at Amoco Production Technology Center in Tulsa
in completions and drilling-technology development, with a
focus on hydraulic-fracturing materials evaluation and specifi-
cation, drilling-fluid hydraulics, formation-damage evaluation
and remediation, and completions optimization. Cameron
has authored a number of SPE publications and has published
in the Oil & Gas Journal, Journal of Rheology, and Colloids
and Surfaces. He earned PhD and MS degrees in chemical en-
gineering at the University of Michigan and The Ohio State Uni-
versity, respectively, and a BS degree in mathematics at The
Ohio State University. He is a registered petroleum engineer in
Oklahoma.
Garrett Frazier is the Director of Sales and Marketing for Mag-
num Oil Tools International. He graduated with a Bachelors of
Business Administration degree majoring in marketing from
Texas A&M University, Corpus Christi. While pursuing his market-
ing degree, Frazier began his career in the oil and gas industry
as an assembly manager and ran jobs for Magnum Oil Tools in
Corpus Christi, Texas. Since that time, he has worked closely
with his father and CEO of Magnum Oil Tools International,
Lynn Frazier, helping him develop and market Magnums cur-
rent line of patented well-completion products. Today, Frazier
oversees all marketing and US sales efforts with offices in Cor-
pus Christi, Texas; Midland, Texas; Oklahoma City, Oklahoma;
and Calgary.
Darwin Holte has 40 years of oil-and-gas-industry experience,
most of it in the electric wireline business. He has spent the last
10 years as part owner and General Manager/Vice of Mesa
Wireline in Grand Junction, Colorado. Holte recently took a
position as Technical Sales Manager/Rocky Mountains for
Magnum Oil Tools based in Grand Junction, Colorado.
Fig. 5Final completedwellbore with production tubing landed.
118 June 2013 SPE Drilling & Completion