SUBMITTAL FORM

BATHEAY REFERRAL HOSPITAL PROJECT


TO: Attention: KOICA Representative KIM SANG JUN RO HI YOUL Subject: Deputy Representative TOPEC CM Document Type We would like to submit you the Weekly Progress Report (WR41) for October 2013. Please find attached report. For Thank you for your good cooperation, Action Status KOICA's Comment: Received by Date: Reviewed by Position: Approved by Schedule Calculation Sample Report Proposed Review Approved 1 = No. Objection 2 = No. Objection with Comment 4 = Objection 5 = Return to Contractor (Resubmit) Drawing Quality Document Catalogue Method Statement Information Record Submission Date: Submission No.: 20-Oct-2013 HSBA-110

Weekly Progress Report (WR41)

FOR KOICA USE

Project Manager/ HWASHIN

TAI GONE, WON

Position:

WEEKLY PROGRESS REPORT (WR41)


BATHEAY REFERRAL HOSPITAL PROJECT DESCRIPTION THIS WEEK (2013.10.13-10.19)
1. Site Survey Work 2. Gutter Canopy Formwork & Rebar Work

NEXT WEEK (2013.10.20-10.26)


1. Site Survey Work 2. Gutter Canopy Concrete 3. Roof Floor of Mechanical Room Beam & Slab Concrete 4. Under Roof Floor Column Part B Concrete 5. Line Marking for Ground Floor Brick Work 6. Laying Brick Work for Ground Floor 7. Install Air-con Pipe for Ground Floor

REMARK

TEMPORARY WORK CONCRETE WORK & MASONRY WORK

3. Roof Floor of Mechanical Room Beam & Slab Rebar Work 4. Under Roof Floor Column Part B Formwork 5. Line Marking for Ground Floor Brick Work 6. Laying Brick Work for Ground Floor 7. Install Air-con Pipe for Ground Floor 8. Curing Water for Under Roof Floor

8. Curing Water for Under Roof Floor

SAFETY STATUS PERCENTAGE (DONE/PLAN)

None ( 35.80% / 40.10% )

SPECIAL ITEMS

MONTHLY SCHEDULE (OCTOBER)


Date: 30-Sep-2013 DESCRIPTION Site cleaning Line marking Concrete curing Form support External Scaffolding Earth work Footing con'c ARCHITECTURAL WORKS Level extension work Ground floor con'c First floor con'c Under roof con'c 2nd floor slab con'c Roof column con'c Steel frame work Masonry work Tiling work Carpentry work Roofing work Metal work Plaster work Door & window work MECHANICAL WORKS ELECTRICAL WORKS PERCENTAGE (Plan/Done)
27.10 28.90 30.70 32.70 34.50 37.30 40.10 42.90 24.80 25.30 26.60 29.80 31.20 32.70 35.80 45.70 49.15 52.60 56.05 59.50 Finished Finished Finished Finished Finished

SEPTEMBER
9/1-9/7

OCTOBER

NOVEMBER

9/8-9/14 9/15-9/21 9/22-9/28 9/29-10/5 10/6-10/12 10/13-10/19 10/20-10/26 10/27-11/2 11/3-11/9 11/10-11/16 11/17-11/23 11/24-11/30

REMARK

SITE PHOTOS

UNDER ROOF FLOOR COLUMN FORMWORK

UNDER ROOF FLOOR COLUMN FORMWORK

DATE:

14-Oct-2013

DATE:

15-Oct-2013

SITE PHOTOS

GUTTER CANOPY FORMWORK

BRICK WORK INSTRUCTION MEETING

DATE:

15-Oct-2013

DATE:

17-Oct-2013

SITE PHOTOS

LAYING BRICK WORK FOR GROUND FLOOR

LAYING BRICK WORK FOR GROUND FLOOR

DATE:

17-Oct-2013

DATE:

19-Oct-2013

SITE PHOTOS

ROOF FLOOR OF MECHANICAL ROOM BEAM REBAR WORK

ROOF FLOOR OF MECHANICAL ROOM BEAM & SLAB REBAR WORK

DATE:

18-Oct-2013

DATE:

19-Oct-2013