Académique Documents
Professionnel Documents
Culture Documents
= 0.215 X
0.1025 X
0.065
0.00143
= 0.225 X
0.1025 X
0.075
0.00173
= 1.000 X
1.000 X
0.1025
0.10250
Nr of bricks in 1m2
59.26
= 0.103
=
0.0014324 =
59.00
0.01799
Nr of bricks in a square
0.103
0.002
-
59
59
0.108
546.30
547
1X
0.5 X
0.215
0.1075
= 0.215 X
0.1125 X
0.075
0.0018
Nr of bricks in 1m2
59.26
strecher coarse
1X
0.5 X
0.215
0.1075
= 0.215 X
0.225 X
0.075
0.00363
Nr of bricks in 1m2
59.26
Total Nr of bricks
= 59.26
118.52
Nr of bricks in a square
1097.39
0.108
0.002
0.108
X
0.004
2
+
59.25926
118.5
0.108
1097
= 0.086 X
1.33 X
1.33 X
0.222 X
0.33 =
1
6
5
6
1441
50
1.33
m3
1.33
m3
= 0.221667
m3
= 1.108333
X 0.017986
0.086
Cube
0.431968
Cube
Bricks
7.50 =
1.30
cwt cement
790.00 =
1,027.00
0.10
cube sand
6800.00 =
680.00
50
gal water
1.50 =
1.5
1000.00 =
1,500.00
600.00 =
1,200.00
add
5%
scaffolding
60.00
8,873.25
wastage
4,125.00
206.25
75.00 =
6,113.25
labour
8,873.25
3,105.64
11,978.89
FORMWORK
Column Formwork (9 " X 9 " X 5 ')
4
9
12
15.00
10.76
1.39
A.Making Mould
(i)
Material
18.15
45.00 =
816.75
17.10
20.00 =
342.00
16.12
12.00 =
193.44
1.50
95.00 =
142.50 =
(ii)
0.5
day carpenter
@ 1,000.00
0.5
500.00
600.00 =
300.00
2,294.69 =
1,494.69
2,294.69
2,294.69
4
573.67 =
573.67
B.Assembling(Per use)
(i)
Material
12
300.00 =
3,600.00
20
35
L.ft 100X50mm props
Assume 10 uses & cost per use
3,600.00
180.00 =
180.00
250.00 =
125.00 =
125.00
40.00 =
1,400.00
10
1,400.00
140.00 =
140.00
1,018.67
(ii)
Labour
0.25
day carpenter
@ 1,000.00
250.00
0.25
600.00 =
150.00
400.00 =
400.00
1,418.67
150.00 =
400.00
1,818.67
day carpenter
@ 1,000.00
0.25
600.00 =
250.00
25%
=
profit & overhead
1,818.67
=
1.39
1304.59
1,630.74
=
=
9
12
55
=
10.76
20
5.11
12
12
20
m2
A.Making Mould
(i)
Material
60.00
45.00 =
2,700.00
55
24.00
12.00 =
288.00
45.00
20.00 =
900.00
30.00
40.00 =
1,200.00
2.00
95.00 =
(ii)
1.5
day carpenter
@ 1,000.00
600.00 =
7,978.00
4
190.00 =
5,278.00
1,500.00
1,200.00 =
7,978.00
7,978.00
1,994.50 =
1,994.50
199.45 =
199.45
= 2,193.95
B.Assembling(Per use)
(i)
Material
40.00 =
4,400.00
80.00
20.00 =
1,600.00
50.00
20.00 =
1,000.00
6.00
45.00 =
270.00
22.00
nos. wedges
15.00 =
330.00 =
7,600.00
1,266.67 =
1,266.67
126.67 =
126.67
7,600.00
6
= 1,393.33
day carpenter
@ 1,000.00
1,000.00
2.00
600.00 =
1,200.00
0.50
1125.00 =
562.50
0.50
95.00 =
=
47.50
2,810.00 = 2,810.00
Labour
0.50
day carpenter
@ 1,000.00
500.00
600.00 =
1,200.00
1,700.00 = 1,700.00
25%
8,097.28
8,097.28
=
5.11
1,584.12
1,980.15
20
10
200
10.76
200
18.59
A.Making Panel
(i)
220
Material
sq.ft 25mm thk. Class II timber planks
with tung & groove jooints
45.00 =
9,900.00
40.00 =
4,840.00
4.00
95.00 =
(ii)
3.00
day carpenter
@ 1,000.00
3.00
600.00 =
=
19,920.00
4
380.00 = 15,120.00
3,000.00
1,800.00 = 19,920.00
19,920.00
4,980.00
996.00
5,976.00 = 5,976.00
B.Assembling(Per use)
(i)
Material
40.00 =
27,600.00
66.00
20.00 =
1,320.00
15.00 =
1,830.00
45.00 =
45,735.00
6
14,985.00 = 45,735.00
7,622.50 = 7,622.50
1,000.00
day carpenter
@ 1,000.00
4.00
600.00 =
2,400.00
1.00
1125.00 =
1,125.00
2.00
95.00 =
190.00
4,715.00 = 4,715.00
day carpenter
@ 1,000.00
500.00
600.00 =
1,200.00
1,700.00 = 1,700.00
= 20,013.50
per 1m2
25%
20,013.50
=
18.59
profit & overhead
1,076.73
1,345.91
Ex: Tender hs been called for construction of two storey office building Colombo.analysis the following rate
per tender purpose.
1.
10mm dia. T/S for issolated column footings not exceeding 1.5 m depth from G.L
2.
20mm dia. T/S in columns up to DPC level
3.
6mm dia. M/S for strruips in columns up to DPC level
Material
Labour
he following rate
GEOTECHNICAL ENGINEERING
GEOTECHNICAL ENGINEERING
APPLICATIONS
NS
APPLICATIONS
NS