RECOMMENDED PRACTICES FOR WATER PIPELINES SITING/PLANNING, DESIGN, CONSTRUCTION AND OPERATIONS
Overview The responsible development of clean-burning natural gas from the Marcellus and Utica Shale formations is water intensive. Increasingly, though, water resources are transferred by pipeline for recycle and reuse purposes, helping to minimize overall road congestion while reducing the overall amount of water use. To ensure that these water resources are properly managed in way that protects the environment as well as on-site workers, the Marcellus Shale Coalition has development a set of Recommend Practices for Water Pipelines Siting/Planning, Design, Construction and Operations. These Recommended Practices are underpinned by the following guidelines: Minimization of land disturbances by placing water pipelines in gas pipeline corridors, or planning for future conversion of pipelines from water to gas is encouraged; All water pipeline operations shall be planned and performed in compliance with all applicable regulations. Clear roles, responsibilities and accountabilities should be established for all positions within the design, construction and operations organizations; A transition plan should be in place detailing the transfer of responsibility for the control of the water pipelines between different organizational units; Periodic audits and inspections should be conducted in order to ensure compliance with applicable Occupational Safety and Health Administration (OSHA) and federal, state, and local agency requirements; and Emergency contact information should be prominently displayed at appropriate locations.

In great detail, the Water Pipeline Recommended Practices address a series of related matters, including: Health, Safety and Environment, covering permitting, proper worker equipment and practices, contractor safety, maintenance management systems, as well as emergency response plans; Pre-Job Meeting Guidelines, to ensure employees, contractors, vendors and other personnel have proper training and understand procedures; Materials and Waste Management, to make certain plans are in place prior to construction that account factors such as containment and spill prevention measures; Routing and Installation, which require a host of engineering, environmental, construction, operations, maintenance and Right-of-Way considerations; and

2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

CONFIDENTIAL DRAFT NOT FOR DISTRIBUTION Design Considerations, to ensure that the pipelines are safe at the intended operating pressures, can be drained to prevent freezing, can be pressure-tested properly, and are compatible with the fluids being conveyed.

The Water Pipeline Recommended Practices also outline a series of guidelines and procedures for the overall permitting process, as well as testing, maintenance and monitoring methods. Taken together, the Water Pipeline Recommended Practices will help MSC members fulfill the organizations mission of providing the safest possible workplace and implementing state-of-theart environmental protection aimed at ensuring the safe and responsible development of the regions natural gas resources.

2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

RECOMMENDED PRACTICES FOR WATER PIPELINES SITING/PLANNING, DESIGN, CONSTRUCTION AND OPERATIONS Preface
This document provides general guidance on recommended practices for the subject(s) addressed. It is offered as a reference aid and is designed to assist industry professionals in improving their effectiveness. It is not intended to establish or impose binding requirements. Nothing herein constitutes, is intended to constitute, or shall be deemed to constitute the setting or determination of legal standards of care in the performance of the subject activities. The foregoing disclaimers apply to this document notwithstanding any expressions or terms in the text that may conflict or appear to conflict with the foregoing.

Section 1 Introduction
1.1 MSC Guiding Principles

We, the members of the Marcellus Shale Coalition, embrace and operate by the following guiding principles: We provide the safest possible workplace for our employees, our contractors, and in the communities in which we operate; We implement state-of-the-art environmental protection across our operations; We continuously improve our practices and seek transparency in our operations; We strive to attract and retain a talented and engaged local workforce; We are committed to being responsible members of the communities in which we work; We encourage spirited public dialogue and fact-based education about responsible shale gas development; and We conduct our business in a manner that will provide sustainable and broad-based economic and energy security benefits for all. We recognize that to succeed in business, we must not only embrace these principles, we must live by them each and every day. This will be our legacy.

2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 2

1.2

Purpose These recommended practices address relevant considerations and guidelines for Water Pipelines Siting/Planning, Design, Construction and Operations. These recommended practices support our guiding principles.

Section 2 General
2.1 All water pipeline operations shall be planned and performed in compliance with all applicable regulations. All applicable governmental permits shall be obtained prior to commencement of operations. Clear roles, responsibilities and accountabilities should be established for all positions within the design, construction and operations organizations. A transition plan should be in place detailing the transfer of responsibility for the control of the water pipelines between different organizational units. Periodic audits and inspections should be conducted in order to ensure compliance with applicable OSHA and federal, state and local agency requirements. Emergency contact information should be prominently displayed at appropriate locations.

2.2

2.3

2.4

2.5

Section 3 Health, Safety and the Environment


3.1 General Operators and contractor personnel involved in the management and supervision of water pipeline design, construction and operation need to be aware of and comply with applicable environmental requirements, including those contained in sitespecific permits and approval processes. Likewise, company policies and procedures regarding health and safety should be communicated and followed by all personnel involved in water pipeline design construction and operations. Operators and contractor personnel involved in the management and supervision of water pipeline design, construction and operation shall be aware of and comply with applicable provisions of OSHA regulations found at 29 CFR 1910 (General Industry) and 29 CFR 1926 (Construction), as well as the OSHA General Duty Clause to provide a workplace free from recognized hazards. Some of the more pertinent OSHA provisions are highlighted below as a reminder to users of this Recommended Practice (RP).

2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 3

Personnel who may be exposed to potentially hazardous conditions or materials should be made aware of the hazards and be provided with training to manage the risks of exposure, the limitations, proper use of personal protective equipment, other precautions to be taken, emergency procedures to be followed, and any required additional measures such as exposure monitoring. Water pipeline operations safety, environmental incidents and significant near misses should be investigated and recorded to determine root causes and identify actions to prevent a recurrence. Neither alcoholic beverages nor illegal drugs shall be allowed on any water pipeline right-of-way or facility. Current Material Safety Data Sheets (MSDS) for pipeline materials such as cleaning agents, bonding agents, anti-corrosion agents, adhesives, etc., should be easily accessible. Smoking shall only be allowed in designated smoking areas. Excessive working hours contribute to fatigue and impairment of mental alertness. Personnel engaged in water pipeline-related operations should work no more than 16 hours without rest during any 24-hour period. All equipment, materials and services should be fit for the intended purpose and be in compliance with both local regulations and industry standards and specifications as required. Connections should not be hammered, adjusted or tightened while under pressure. If a bolted fitting is leaking during operations, the pipeline should be taken out of service, depressurized, and the bolts should be tightened immediately to control leakage.

3.2

Personal Protective Equipment (PPE) OSHA Standard 29 CFR 1910.132 requires the following usage of PPE to reduce employee exposure to hazards when engineering and administrative controls are not feasible or effective enough to produce an acceptable level of safety: Head protection - hard hats must comply with ANSI Z889.1-1986. Foot protection - safety-toe footwear should be boot style and show labels as meeting requirements of either ANSI Z41 or ASTM F2412 and F2413. Eye and face protection - safety glasses with side shields must comply with ANSI Z87.1-1989. Face shields and/or chemical goggles must be worn during chemical handling/transfers. The MSDS should be consulted for proper eye and face protective equipment. Hand protection - hand protection should be worn when hands are exposed to hazards such as absorption, cuts, punctures, chemicals and harmful temperature extremes. Hearing protection - areas where high noise levels exist should be identified and hearing protection should be used. Respiratory protection a suitable respirator should be utilized anytime air is contaminated with harmful dusts, fogs, fumes, mists, gases, smokes, sprays or vapors.

2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 4

Flame Resistant Clothing (FRC) - Operators should provide and ensure the use of FRC necessary to protect employees from burns due to potential flash fires as specified by OSHA Standard 29 CFR 1910.132 during hot work operations.

3.3

Flammable and Combustible Liquids Operators need to store and transport flammable and combustible liquids in appropriate containers pursuant to OSHA Standard 29 CFR 1910.106 and 1200, as well as Department of Transportation (DOT), state and local regulations. All containers must be affixed with either a National Fire Protection Agency (NFPA) label or a Hazardous Materials Information System (HMIS) label or manufacturers label.

3.4

Fire Protection Fire extinguishers should be suitably located, readily available, properly maintained, and plainly labeled as to their type and method of operation per OSHA Standard 29 CFR 1910.157. Portable fire extinguishers should be tagged with a durable tag showing the date of the last inspection, maintenance or recharge. Any fire extinguishers that have been used should be taken out of service and replaced.

3.5

Contractors Safety and Maintenance Management System The contractors safety management system should include Job Safety Analysis (JSA), pre-job safety meetings, inspection and audit programs, action-tracking processes, personnel training, and competencies. All designated company representatives and contractors should participate in the primary contractors safety meetings. Documentation of safety meetings should be kept on file and available to company representatives on request. Contractors should have a maintenance management system in place for their equipment. All safety critical equipment should be included in the maintenance management system, including load-bearing, lifting, hoisting and pressure-containing equipment.

3.6

Emergency Response Plans Water pipeline construction and operations should have plans to cover emergency management, spill contingency and pipeline rupture response. Emergency Response Plans should be maintained at appropriate pipeline locations and offices. Applicable portions of the Emergency Response Plans should be communicated to the appropriate local and state emergency response agencies. Emergency response drills are encouraged where practical.

2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 5

3.7

Vehicle Safety Abide by all traffic laws and regulations. Forklifts and aerial lifts need to be operated by trained and certified operators only, never driven off location, and operated to avoid overhead power lines. Use spotters, barricades and flagging tape when appropriate. Be aware of unstable or uneven ground and overhead power lines. Back into parking space if possible to best facilitate immediate evacuation. Non-essential vehicles should be parked at least 100 feet from a well or other source of flammable material.

3.8

Excavation OSHA defines an excavation as any man-made cut, cavity, trench or depression in the earths surface as formed by earth removal. If an excavation is more than five feet in depth, there must be a protective system in place while workers are present in the excavation. Excavations more than four feet in depth must have a way to get in and out, usually a ladder, for every 25 feet of horizontal travel. OSHA requires that regardless of the depth on an excavation, a competent person must inspect conditions at the site on a daily basis and as frequently as necessary during the progress of work to assure that the hazards associated with excavations are eliminated before workers are allowed to enter. A competent person has the following qualifications: Thorough knowledge of the OSHA Standard 29 CFR 1926.650-652. Understands how to classify soil types. Knows the different types and proper use of excavation safety equipment. Has the ability to recognize unsafe conditions, the authority to stop work when unsafe conditions exist, and the knowledge of how to correct the unsafe conditions.

The estimated location of utility installations, such as sewer, telephone, fuel, electric, water lines, or any other underground installations that reasonably may be expected to be encountered during excavation work, shall be determined prior to opening an excavation. Activate the One-Call System based on state requirements. 3.9 Hoisting and Lifting Equipment Fixed or portable hoisting and lifting equipment need to be installed and maintained pursuant to manufacturers specifications. Such equipment should only be operated by properly trained personnel. Prior to lifting operations consider the following: Major lifting operations should be pre-planned. Crane inspections, certifications and daily inspection logs must be current and available on location for review as per OSHA Standard 29 CFR 1910.179 and 1910.180. Inspect and use proper rigging on loads, including but not limited to load ratings, cable condition and anti-two block sensors.

2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 6

Body position: Always leave yourself an escape route if you are the spotter or banksman. Do not stand under suspended loads. Use tag lines when appropriate and watch out for swinging or shifting loads. Review air hoist, winches and laydown bucket line hazards. Hand-spliced wires and slings should not be used for lifting. Homemade or flame cut pad eyes are not recommended. Crane operations should be under the direct control of a banksman who should not otherwise be involved in the lifting operation.

3.10

Hot Work Permits In general, any work activity that causes or can cause a source of ignition for a combustible or flammable gas, liquid or material should be conducted under a Hot Work Permit as per OSHA Standard 29 CFR 1910.252. Examples of work activities include, but are not limited to, open flames, welding, brazing and grinding. Examples of potential flammable or combustible fuel sources include, but are not limited to, wellheads, tanks and pressure relief devices. When performing water pipeline work at or in the immediate vicinity of a gas well, gas pipeline or any other potential gas source, consider the following advice when conducting work under a Hot Work Permit: When in proximity to well or gas source, use a Lower Explosive Limit (LEL) meter, ensure fire extinguishers are readily available, and conduct a fire watch. Position electrical or fired equipment away from gas pipelines or other sources if possible. Receive permission from the gas pipeline/other source supervisor before beginning hot work. Use fire protection tarps if necessary.

3.11

Confined Space Entry Operators should provide a permit-required confined space program that controls and protects employees from permit space hazards and regulates employee entry into permit spaces per OSHA Standard 29 CFR 1910.146. A "confined space" is defined as a space that: Is large enough and configured so that an employee can bodily enter and perform assigned work; Has limited or restricted means for entry or exit (for example, tanks, vessels, silos, storage bins, hoppers, vaults and pits are spaces that may have limited means of entry).; and Is not designed for continuous employee occupancy.

2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 7

3.12

Energy Isolation OSHA Standard 29 CFR 1910.147 covers the servicing and maintenance of machines and equipment in which the unexpected energization or startup of the machines or equipment, or the release of stored energy, could cause injury to employees. The following should be considered for the control of such hazardous energy: Disconnect power source and controls prior to repairing all equipment, such as hydraulic tongs, power packs, motors, engines, hydraulic power units and cylinders. Any operation which requires the isolation of energy should utilize Lockout/Tagout (make sure equipment is out of service prior to repairing). Examples of stored energy sources include load binders, pressured lines and air hoist operations. Pressure testing/pumping: Clear personnel, secure lines with clamps/cables/chains, and verify flow path. Inspect threads on swedges and nipples. Pressure Washing: A positive displacement pump should not be used without a bypass and a secondary means of overpressure protection. Bleed off pressure and keep it vented when removing a flange or cap. Keep electric cords/wiring, electrical grounding and protective guards in place at all times.

Section 4 Safety Critical Tasks for Water Pipeline and Appurtenances Operations
4.1 The intent is for the water pipeline construction and operation supervisor (or designate) to have direct involvement in the planning for these critical operations. This would include a pre-job safety and operations planning meeting to ensure full job requirements and responsibilities are understood. The supervisor or designate should audit/verify, and provide assurance/oversight that the job is executed as planned. Supervisors should consider production and facility safety critical tasks when determining if a pre-job safety assessment is necessary. These tasks include, but are not limited to, the following: Pre-move hazard assessment (including but not limited to: condition of roads, power line clearance). Permit to work assignments (including, but not limited to, hot work or confined space). Simultaneous operations with gas lines, nearby wells, access roads or other construction operations. Any critical lifting operations. Movement of equipment to, from and onto location. Spotting of equipment on location. Equipment pressure testing.

4.2

2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 8

Digging/Trenching.

Section 5 Pre-Job Safety Meeting Guidelines


5.1 Supervisors should identify hazards/risks specific to the job prior to beginning work or conducting a safety meeting. Contractors, vendors and any other personnel to be at the job site should be included the safety meeting. Always ask what if? before every job to determine the biggest hazards and risks of the job and how they can be avoided. Use the contractors JSA, procedures, checklists and other available tools. The company water pipeline supervisor should review the contractors safety policies, standard procedures, JSA, and other related documents prior to beginning operations. A walk-through audit with a contractor representative is recommended and should include topics such as equipment, pre-job planning, procedure review, site orientation, hazard discussion and other conditions.

5.2

A comprehensive pre-job safety meeting should precede safety-critical tasks (see list for examples) and should include the following topics: PPE that will be required. General safety information for prevention of slips, trips, falls and proper vehicle safety. Energy Isolation: o Electricity Lockout/Tagout and energized components o Pressure Lockout/Tagout and line of fire Job-site communication.

Section 6 Materials and Waste Management


6.1 Operators should have a materials management strategy prior to initiating construction or maintenance activities. At a minimum, the materials management strategy should include: 6.2 MSDS; Containment protocols, including spill prevention measures; Inventory/measurement tracking to identify consumption anomalies; and Vegetation removal and topsoil management plans.

Each operations site should have a waste management strategy prior to initiating construction or maintenance activities. The waste management strategy should include:

2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 9

Waste storage facilities and locations that provide labels and containment; MSDS; Differentiation of exempt and non-exempt construction/maintenance wastes according to the Resources Conservation and Recovery Act (RCRA); Contingency plans to contain and cleanup spills; Waste treatment, transfer and disposal procedures; Waste tracking and reporting protocols; Mechanisms to ensure personnel are properly trained in waste management; and Completion of required documentation for transportation of wastes as required by DOT and state waste management rules and regulations.

6.3

The location layout should allow for safe storage, handling, use and disposal, and take into account: Recommended safe handling practices; Chemical and physical compatibility; Ignitability and proximity to potential ignition sources; Moisture, precipitation and storm water runoff; Environmental conditions; and Distance from surface waters and allowance for spill containment and cleanup.

6.4

Unused chemicals and materials should be removed from the construction/maintenance site as soon as it is practical to do so.

Section 7 Alignment Planning, Engineering and Environmental Considerations


7.1 General Water pipelines are constructed to serve one or more purposes. At a minimum, they are installed to move fluids from a source to a destination -- be it from a freshwater or recycled water source to a hydraulic fracturing operation, or to return flowback or produced water to a collection point for recycling or proper disposal. However, with proper planning, these pipelines may have more than one function or the ability to serve multiple wells or pads. Likewise, with multiple stacked gas-bearing formations, water pipelines can be used for the stimulation of multiple formations. Many operators find that, with proper planning, these pipelines can be valuable conduits beyond the initial well-stimulation operations, including for potential future conversion to gas-gathering pipelines. Given these numerous short- and long-term considerations, pipelines will vary for each location and application. Each site and potential use will provide its own set of requirements regarding the pipeline materials and their installation. Key elements that impact planning, design and installation are: the desired service life of the pipeline; range
2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 10

of fluids or gases to be transported; routing constraints including dense population areas and areas where securing easements is difficult; soil and subsurface conditions; ledge rock; utility conflicts; wetland and other sensitive area avoidance; and road/highway crossings. 7.2 Routing and Installation Considerations Pipeline routing entails several criteria. Routing plans needs to consider a host of engineering, environmental, construction, operations and maintenance factors so that the resulting alignment and design are both cost effective and of such a character that necessary permits will be obtainable. Further, the alignment and design must ensure that the pipeline will serve all intended uses and can be readily constructed and maintained in accordance with the operational and environmental requirements, including postconstruction erosion and sediment control and stormwater management. Pump locations and capacities, although not considered within this RP document, must also be considered within the route planning program. Routing surveys should be conducted in two parts office and field. The initial officebased survey should draw on aerial photographs, topographic maps, National Wetlands Inventory maps, property ownership maps, state-maintained sensitive resource inventories, and other readily available sources to identify challenges, constraints and potential optimal routings for the alignment. Once the pipelines starting location and the delivery point are defined, a field routing survey between the two locations should be conducted. This will provide insight as to actual conditions which will be encountered during construction and that will need to be addressed in design and permit application preparation, and also allows for evaluation of alternate routings. Existing underground utilities should be marked per the states One-Call system to aid in identification during the field survey. The survey team should be a multi-disciplined party consisting of pipeline engineers, environmental scientists and permitting specialists, landmen, civil/geotechnical engineers, and the construction contractor. Several items to be considered are described below. A. The Right-of-way (ROW) width should be determined based on several factors including both temporary and long term requirements. Consider the use of temporary work space during the construction phase to accommodate access for construction equipment and laydown of materials. It may be possible to reduce the ROW after installation has occurred. The long term ROW width should be based on the width required for the pipeline itself and for ongoing activities such as inspection, repair and if needed, removal of the pipeline. For a typical water pipeline, the ROW width needs to be wide enough to allow for equipment movement on either side during installation and working space to set piping, joints, valves and other items of construction, as well as shoring materials for placement in the trench when needed. A minimum ROW width of 20 feet is typically required, although widths of 40 and 50
2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 11

feet are not uncommon. Access points to the ROW from both sides of perpendicular barriers like streams must be available and verified during the routing survey. To minimize the footprint of oil and gas operations, use of existing ROWs, or the sharing of proposed ROWs for gathering lines, access roads or transmission lines, is highly encouraged. B. In many cases, a water pipeline will be in the same ROW as gas gathering lines. In these cases, the water pipeline should have only the amount of separation from the gas pipelines necessary to allow installation and service to the water pipeline without impacting the gas pipelines (or as per individual company requirements). Access to both gas and water pipelines during construction, operation and maintenance and removal should be taken into account. Also, unless state permitting requirements specifically specify otherwise, the water pipeline will need to be permitted separately from the gas pipeline. C. A routing survey should be conducted to evaluate potential pipeline routes and to identify potential conflicts. In order to complete a routing survey, the operator should obtain landowner permission to enter their property. Routing data also provides preconstruction conditions and minimizes potential damage claims during and after construction. Items that should be evaluated during the site visit and, if field survey plans are to be prepared, included on survey plans, are: Length of pipeline to be installed; Utilities: Are existing utility lines located in the proposed route? Identify and locate both horizontal and vertical locations to avoid conflicts; Waterway crossings should include information on water levels that can be expected during installation; Existing and proposed rights-of-way for gas pipelines, highways and railroads (requires baseline stationing and right-of-way layout information); Wetland areas should be evaluated for boundary location of wetlands and buffer zones. Other potential high-value habitat or habitats of threatened or endangered species should be observed as well; Dwellings and other development features that would inhibit restrict pipeline installation, or that may require sound attenuation features for pumps installed along the pipeline; Cemeteries, schools, other buildings and cultural resources; Identification of roadway, sidewalk and driveway materials (bituminous, concrete, gravel, etc.); Utility pole locations and identification numbers; Landscaped areas; Pavement conditions; Berms and curbing locations; and Ledge and boulder outcrops;

2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 12

Fences and stonewalls, along with identification of the medium (i.e., wood fences, stone walls, etc.); Edges of water bodies, rivers, creeks, streams and water levels at time of the survey; and Boring locations. (if borings are taken after the survey, a minimum of two ties should be taken into the field and added to base drawing sheets).

D. Public roadway rights-of way can be used to install the pipelines. Buried piping can be installed either under the roadway surface or in the shoulder areas, provided sufficient space is available. Surface installations can be added along shoulders with proper protection from traffic and pedestrians. Public roadway installations require coordination with the local authorities having jurisdiction over the road. Additional costs will be incurred in order to restore paving or road surfaces to pre-construction conditions. Road installations will also require traffic control and signage to minimize potential traffic impacts. A minimum bury depth of four feet should be utilized to prevent traffic load impacts and minimize potential freezing. E. Surface installation of pipelines can be used for temporary or short-term installations. When using surface pipelines, operators should be aware of freezing conditions and properly drain the pipeline under these conditions to prevent ice damage. Surface installed pipe should be laid in areas that are not subject to traffic or pedestrian access. Driveways or road crossings require a shallow bury of the pipe across the drive or road. When surface piping is to be used, joints need to be restrained. This can be accomplished by the use of restrained joints such as fused piping, locking joints or mechanical restraint systems as described later in this document. F. Highway/waterway/railroad crossings pose additional requirements and challenges to the pipe installation. Highway and roadway crossings are under the jurisdiction of the state, county, and/or municipal highway/road agency/department. Crossings requiring open-cut trenching may not be allowed due to traffic considerations. In order to cross a highway, trenchless installation, such as directional drilling or jacking, and installation of a casing pipe may be required. If culverts can be located, it is sometimes possible to install the pipeline inside the existing culvert to cross a highway, depending upon which agency has jurisdiction of the highway (some agencies prohibit installation inside existing culverts). However, this possibility would require a hydraulic analysis to determine the impact to the flow capacity of the culvert if a pipe is installed inside. This method, if permitted, should be limited to temporary or short-term and those that have a small diameter with respect to the culvert opening size. Waterway crossings are typically installed by excavating the stream bed, by installing the pipe in a bridge structure crossing over the waterway, or by directional drilling beneath the stream bed. If a buried or directional drill approach is used, a minimum bury depth of four feet should be utilized to prevent scouring damage and freezing. In some areas with subsurface fractures or poor subsurface conditions, horizontal directional drilling may not be suitable, as drilling
2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 13

muds potentially forced out of fractures and entering streams may alarm residents and trigger calls to regulatory enforcement agencies. G. When installing pipe in rural areas, the disturbed soils should be prepared as a seedbed and seeded to prevent erosion. 7.3 Geotechnical Considerations Buried pipe installation requires knowledge of soil conditions. In order to determine the construction and bedding needs for buried pipe, a soil investigation program should be initiated. This can also provide a basis for proposed pipeline routing and construction cost estimate data. A geotechnical program typically consists of soil borings taken to a depth of approximately two feet below the proposed pipe invert. Typically borings are taken at 500-foot intervals along the proposed route. At least one soil sample should be collected from a depth of three to four feet below the surface. If a particular area such as a stream crossing, railroad crossing or casing jacking/directional drilling location is anticipated, borings should be taken at each side of the stream and at proposed jacking and receiving pits. Borings at proposed entrance/exit pits should be taken to a depth of 1.5 times the expected depth of the pit. If refusal is encountered, coring may be required to determine if the refusal is the result of a random boulder or an extensive rock ledge. Coring will provide information concerning the obstruction and the quality of the rock encountered. When trenchless installation of a pipeline is proposed, borings should be taken along the proposed trenchless route to a depth 1.5 times the expected installation depth. It should be noted that trenchless technology installations typically require the pipe to be installed at depths greater than the normal four-foot bury. Soil samples for trenchless installations should be taken at approximately four-foot intervals, or where the material changes occur. Laboratory sieve/gradation analysis should be performed on the trenchless soil boring samples. Soil borings should include depth of borings, blow counts, type of soils encountered and elevation of the ground water table. Boring locations should be surveyed with a minimum of two ties to permanent structures shown on the survey base plans. 7.4 Wetlands, Waterways and Ecologically Sensitive Areas

2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 14

Installing pipe in wetland and stream/river/floodplain areas and buffer zones may require review and approval by local, state and federal regulatory agencies. Likewise, sensitive habitats or potential archaeological sites as typically identified via searches of state inventory databases should be reviewed in the field and avoided if possible or mitigated if avoidance is not an option. Each wetland, waterway area and other sensitive resource sites will have specific constraints that will need to be addressed during the design, permitting and construction of the pipelines. Wetland or other regulated sensitive areas need to be defined early on during the design process, and meetings with permit officials should be held to discuss proposed work and expected impacts to the sites. Generally, work within wetland, riparian areas and buffer zones will require use of sedimentation barriers such as filter socks, hay bales, silt fence or other approved devices along the area of impact. Disposal of excess materials will be regulated, as will the restoration of the disturbed areas. Also, storage of materials such as fuels, oils and chemicals may not be allowed within the protected areas. Additional considerations are provided in the following section on permitting.

Section 8 Permitting and Clearances


8.1 General Most activities that require a land disturbance or that potentially impact any wetlands or waterways require some type of federal, state, local or joint permits. Similarly, many activities associated with natural gas development are regulated by various statutes and regulations. Natural gas water pipeline construction involves many activities, including land clearing, road construction, pipeline construction, road and railroad crossing, and subsequent operations and maintenance. Each state and municipality, the federal government, railroads, and other entities have permitting and clearances requirements that are required prior to pipeline construction. It is incumbent on all entities involved in developing and operating water pipelines to be aware of all pre-construction permitting/clearance requirements, as well as permit/clearance requirements that apply to operations, maintenance and potential decommissioning. The permit application review and approval process can be lengthy in some cases exceeding 12 months. It is essential to submit a complete application to appropriate agencies well in advance of scheduled construction. 8.2 Specific Permits

2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 15

Environmental and clearance permit requirements, which may be needed for a water pipeline project, can include the following groups of activities: Road construction; Land clearing; Pipeline construction and operation; Wetlands and waterways crossings; Work within areas having threatened or endangered species and/or important; historical and cultural resources; Road and railroad crossings; and Air or noise emissions (principally for pumping facilities)

The above list is not intended to be comprehensive or address the full range of permitting requirements for various locations and projects. The permitting requirements will ultimately depend on site-specific conditions and related local regulatory requirements. 8.3 Permit Identification Prior to determining which permits may be needed for a specific project, an analysis of the project should be performed that looks at the potential necessary permits and establishes a timeline for obtainment. If needed, a pre-application conference with involved agencies can greatly enhance this evaluation. Following this task, a permitting checklist can be developed that can serve as a guide for the project team. Generally, this task is performed in conjunction with the alignment planning tasks described in the previous section, and involves an office (desktop) review of available federal and state surveys of natural resources, critical habitats, endangered species, wetlands, soils, cultural resources and other potentially site development limiting criteria. 8.4 Permitting Strategy It is critical to develop a permitting strategy that optimizes company resources and capital while effectively navigating the permitting realm. While each company or project team may develop a unique strategy for a variety of reasons, a general theme to embrace for successful permitting involves the steps outlined below. Although this approach was initially brought to light in the area of wetland permitting, the concept has wide applicability. These specific steps include the following: Avoidance eliminating activities that impact resources deemed valuable, unique or critical to any agency greatly increases the success of obtaining a permit. Minimization once it is determined that a resource is going to be unavoidably impacted by a particular project, reducing the amount of regulated activity in an area or near a

2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 16

particular resource can be extremely beneficial. Minimization attempts should be welldocumented for reference in future projects. Compensation offsetting unavoidable impacts is extremely important and must be done in concert with the relevant regulatory bodies to establish replacement ratios or monetary compensation needed to access mitigation banks 8.5 Permit Application Documents Permit applications must include all required documentation for the entire project being permitted. This includes pipeline engineering and design documents, environmental and cultural features, impact assessments and associated mitigation. 8.6 Permit Tracking Successful obtainment of permits requires the careful monitoring of submission dates and the anticipated review periods. Careful monitoring, including staying in regular contact with relevant agency staff, can greatly reduce response time and produce more efficient permitting. 8.7 Permit Maintenance and Conformance During and Following Construction Once construction is set to begin, permit-required controls must be put in place, and those controls must be adhered to throughout the period of construction. This includes specific guidelines, as well as all elements associated with avoidance, minimization and compensation. 8.8 Permit Closeout Following the completion of construction, permits required to initiate the work typically have closeout or maintenance/monitoring requirements. To maintain up-to-date compliance with permit conditions, all closeout or monitoring activities must be completed within a given timeframe. Failure to perform these tasks can negatively impact the environmental compliance profile of your project.

2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 17

Section 9 General Installation Considerations


9.1 General Water pipelines may be used to convey freshwater, flowback water, produced water, and/or blended water. The water to be conveyed through a pipeline must be compatible with the pipe material selected. Above-ground and below-ground pipes each have factors that must be taken into account. Pipe diameter selection will be a function of delivery rate requirements and other factors. Each pipe material has varying requirements for installation, and should be installed in accordance with the pipe manufacturers criteria and instructions. Installation guidelines based on local procedures and requirements should also be considered. Other installation topics are listed below. 9.2 Installation Guidelines Installation procedures should be obtained from pipe manufacturers. Varying materials have different requirements for installation, bedding and testing techniques. Pipe delivered to the site should be handled with care to prevent damage to interior/exterior coating systems, cracking and breakage. Chains should not make direct contact with the pipe during lifting. Canvas belts should be used to prevent damage. Gaskets should be stored in enclosed areas to prevent degradation due to sunlight. Pipe should be stored in a central location and with sufficient quantities strung out along the pipeline route to allow for ease of installation. Pipe ends should be closed to prevent animals and debris from entering. After trench excavation is completed, pipe should be lowered into the trench and placed on firm bedding materials. Backfill should be placed in 12-inch lifts and compacted. Large boulders, rocks, etc., should not be dropped on the pipe during backfilling. Pipe joints should be carefully made. Joints utilizing rubber gaskets should be cleaned and lubricated. Lubricant should be provided by the pipe manufacturer to ensure compatibility with the gasket materials. Fused or welded joints should be made above ground prior to trench installation. Fused joints should be made by certified fusion technicians. Fusion equipment should be calibrated and certified for the application. Standards for welding pressures, times, cooling periods, etc., should be in compliance with the pipe manufacturers requirements. Manufacturers published tolerances should not be exceeded when bending pipe lengths to achieve a given radius of curvature in a pipe ditch. If thrust blocks are to be used, they should be placed behind each fitting and tee. Blocks should be sized to provide proper bearing area against undisturbed soils. Mechanical restraint systems should be installed on each fitting and valve. Restraints are to be installed on adjacent lengths of pipe on either side of each fitting or valve.

2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 18

Lengths to be restrained are determined based on pipe material lengths, pressures and other criteria. Manufacturers should be contacted to provide data on installation of restraints. Plastic or HDPE pipe should have metallic tracing tape installed along the route approximately two feet below the surface. If pipe is to be installed above grade, pipe joints should be either fused or mechanically restrained to eliminate the need for thrust blocking. If pipe is to be installed above grade, insulation may be required to prevent freezing. Exposed piping should be installed in locations that will minimize damage due to vehicular traffic and pedestrians.

9.3

General Pipeline Requirements Pipelines should be installed with isolation valves at regular intervals to allow for isolating the pipeline in order to provide maintenance and testing. At a minimum, valves should be located at the source and at the discharge points. Additional valves should be located based on site-specific and regulatory requirements. Valved drains should be installed at or near low points, taking into account regulatory water body and other buffer requirements to allow for decommissioning of the pipeline and/or draining during maintenance periods. For pipelines carrying fluids other than fresh water, containment should be placed under each drain valve, and air releases should be continually monitored and cleaned. High points of the pipeline should be equipped with air/vacuum valves to allow for removal of trapped air and to allow for draining of the pipeline. Valves on above ground installations should have handles removed or installed with locks to prevent unauthorized closure. Below grade valves require boxes to allow access to the operating nut. Valve operating keys will need to be supplied to allow for the opening/closing of the buried valves. Repair clamps and sections of pipe should be available to make necessary repairs. Cleanout valves should be located at appropriate locations to accommodate pipe sediment cleanout. Where necessary, above-ground installations should be covered with appropriate cover material to allow vehicular access, to a maximum width of 50 feet.

2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 19

Section 10 Hydraulics
10.1 Determining Pipeline Diameter Determination of proper pipeline diameter is required not only to minimize the cost of pipeline materials, but also to reduce construction and power costs associated with pumping water from the supply to the point of usage. Water pipelines are referred to as pressure conduits, and the resistance of flow in the pipeline occurs when water encounters frictional resistance. This resistance results in head loss, which is determined by flow velocity and roughness of the interior surface of the pipe. Use of smooth-walled pipes, such as those made from polyvinyl chloride (PVC), will result in lower head losses, while a corrugated wall pipe will have rougher walls, causing turbulence and greater head losses. Each pipeline material has a numerical value referred to as the Hazen-Williams C-factor. The C-factor can vary based on the age and material. Higher C-factors result in lower friction impacts. Over time, as pipes age or tuburculate, the C-factor will decrease. The average C-factor for various new pipe materials are: Cement lined ductile iron 140 Concrete 120 PVC 150 HDPE 150 Corrugated steel 60 Bitumastic-lined steel 140

Typically, a C-factor of 110 is used in design to account for future pipe aging and other factors likely to impact flow capability.. For pressurized flow, the Hazen-Williams formula is used to determine pipeline head losses. The Hazen-Williams formula is: Hf = 0.002083 L (100/C)1.85 (GPM1.85/D4.8655 ) Where: Hf = Head loss due to friction (feet of water) L = Length of pipe (feet) C = Hazen-Williams C-factor (unitless) GPM = flow (gallons per minute) D = Inside diameter of pipe (inches)

2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 20

Use of the Hazen-Williams formula shows the impact that pipe diameter has on a given flow rate and how it impacts the system head losses. As the pipe diameter increases, friction head loss decreases and a reduction in pumping horsepower results. However, this does not mean that over sizing a pipeline will result in a better system. As pipe diameter increases, flow velocity decreases while material and construction costs and required construction work areas increase. Velocity is determined by the formula:

V = Q/A Where: V = Pipeline velocity (feet per second) Q = Flow (cubic feet per second) A = Cross sectional area of pipeline (square feet) Generally, an accepted rule of thumb for sizing a pipeline states that the velocity should range between 2.5 to 7 feet per second. Pipe manufacturer tables typically include velocity ranges vs. head loss for varying diameters. Undersizing a pipeline results in high velocities, increased head loss and higher pumping costs due to increased horsepower requirements. It should also be remembered that doubling the flow rate will double the velocity and approximately quadruple the head loss value. 10.2 Head Loss vs. Flow Tables Pipe manufacturers provide tables showing head losses vs. varying pipe materials, diameters and flow rates. 10.3 Pressure Most typical water pipeline materials such as pipe, valves, fittings, etc., are designed for working pressures of 0 to 150 psi. Maximum pressures, such as those which may occur during a surge or water hammer, are typically in the range of 350 psi. Piping design is usually based on the expected working pressure of the system. During pipeline design, the pipe and appurtenance data sheets should be checked to ensure that the required materials can safely handle the expected working pressure value. The working pressure value is also the basis of the pressure test conducted after the pipeline is installed. Normal test pressures are 1.25 to 1.5 times the maximum working pressure value, or 150 psi maximum. Pressure testing should be performed in accordance with pipe manufactures specifications. Additional information concerning testing is provided in this RP.

2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 21

Section 11 Pipe Materials


11.1 General Several materials are available for water transmission pipelines. Each has its own benefits, and choosing which to use should be determined by the type of installation, use, expected timeframe the pipe may be in use, ease of construction, availability and cost. Each of the described pipe materials is capable of handling fresh water. Flowback and produced water, which have a high salt content, should be limited to PVC, HDPE metal pipes treated with special corrosion resistant liners, or other compatible pipe materials. When selecting pipe materials, operators must consider the potential environmental consequence of a flowback or produced water pipeline leak or rupture and apply any riskmitigation strategies they deem appropriate. An outline description of several commonly used pipe materials is included below. Other pipe materials may be used depending on potential long-term application (such as eventual usage for gas gathering applications) and the development of any new pipeline materials. 1. Ductile Iron A. Ductile iron (DI) pipe is commonly used in water pipeline distribution and transmission lines. DI is available in diameters ranging from 3 to 54 inches. DI pipe is rated for pressures up to 350 psi. B. DI pipe can be obtained in two versions; thickness class and pressure class. Thickness class (Class 50 - Class 56) results in pipe that has thicker walls based on loading parameters. Pressure class pipe (PC 150 PC 350) has thinner walls based on loading parameters. Most current installations use pressure class ratings. The use of pressure class pipe results in cost savings due to lower material weights. C. DI pipe is provided with a bituminous exterior coating. Bituminous or cement lining can also be specified. D. Interior coatings for fluids, which may be corrosive, are also available for DI pipe. Coating requirements should be confirmed with the pipe manufacturer during design. Lining information is contained in Section 9.2. E. Whether pressure or thickness class DI pipe is used, the coatings, linings and expected material life are the same. F. DI pipe is available in 18- and 20-foot lengths G. Typical C-factor values for DI pipe range from C- 120 to C150. H. Additional information on DI pipe design and installation can be obtained from pipe suppliers and the Ductile Iron Pipe Research Association (DIPRA) (www.dipra.org). 2. Polyvinyl Chloride (PVC)

2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 22

A. Polyvinyl chloride (PVC) pipe is available for use in pressurized water systems if it is manufactured in accordance with American Water Works Association/American National Standards Institute (AWWA/ANSI) standards. B. PVC pipe in diameter range of 4 to 12 inches is manufactured in accordance with AWWA/ANSI C-900 standard. Pipe having a diameter of 14 to 48 inches is manufactured in accordance with AWWA/ANSI C-905 standard. C. PVC pipe is commonly furnished with push-on, bell and spigot gasketed joints. D. Fusible joint PVC pipe is also available if leak-free joints are required. E. Use PVC pipe that has an outside diameter that matches the DI pipe diameter to allow for direct connection between the two materials. F. For pressurized water pipe applications, do not use gravity/low pressure PVC pipe that is designed for sewer or drainage applications. G. Due to possible UV degradation, PVC pipe should not be used for aboveground installations. Modified PVC pipe manufactured with UV inhibitors is discussed below. H. Typical C-factor values for PVC pipe are C-140 to C-150. I. PVC pipe is typically manufactured in 20-foot lengths. J. Fittings for use on PVC pipe are typically ductile iron and mechanical joint. If corrosion is a consideration, fittings should be furnished with interior protective coatings. K. AWWA/ANSI C-900 PVC pipe is available in pressure range of 165 to 305 psi. L. AWWA/ANSI C-905 PVC pipe is available in pressure range of 80 to 235 psi. M. Additional information on PVC pipe design and installation can be obtained from pipe suppliers and the Uni-Bell PVC Pipe Association (www.unibell.org). 3. Modified PVC Pipe A. A modified PVC pressure pipe (such as Yelomine ) should be utilized for above-grade applications. B. Modified PVC pipe is manufactured with impact modifiers and UV inhibitors. These modifiers provide higher impact resistance and allow for long term UV exposure. C. Modified PVC pipe is available in 2 to 16-inch diameters. D. Pressure range for modified PVC is 100 to 315 psi. E. For pressurized water supply applications, do not use PVC pipe that is designed for sewer or drainage applications. F. Use PVC pipe that has a diameter which matches that of DI pipe to allow for direct connection between the two materials G. Modified PVC pipe can be furnished with locking joints to eliminate additional thrust restraint systems. Pipe used in non-permanent installations should be furnished with non-permanent use joints. The use of this type joint allows for ease of disassembly and reuse of the pipe in other locations. If the
2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 23

H. I. J. K.

pipe is to be installed underground for long period, it should be furnished with permanent-use restrained joints. Fittings with locking joints can be furnished with the modified PVC pipe. Typical C-value for modified PVC pipe is C-150. Modified PVC pipe is available in 20-foot lengths. Additional information on modified PVC pipe can be obtained from pipe suppliers and the Uni-Bell PVC Pipe Association (www.uni-bell.org).

4. High Density Polyethylene Pipe A. High Density Polyethylene (HDPE) pipe is suitable for water distribution and transmission. B. HDPE is available in diameters of -inch to 54-inches. Water supply pipe is manufactured in accordance with AWWA/ANSI C-901 for pipe less than 3 inches in diameter and AWWA/ANSI C-906 for pipe 4 to 54 inches in diameter. HDPE pipe comes in up to 50-foot lengths and requires fusion welding to join each length together. Fusion welded joints result in zero leakage. C. HDPE can be obtained with an outside diameter that matches other pipe types, allowing for direct connection between the two materials. D. Fusion fittings and bends are available. Mechanical joint and flanged joint adapters can also be used to allow connecting to other pipe materials. E. Typical C-value for HDPE pipe is C-150. F. Maximum pressure of HDPE pipe is available up to 267 psi, in accordance with manufacturers specifications. G. Additional information on HDPE pipe design and installation can be obtained from pipe suppliers and the Plastics Pipe Institute (www.plasticpipe.org). 11.2 Linings Several linings are available for use with ductile iron pipe materials. The linings are based on the expected use of the pipeline and should be specified during the design phase of the work. Pipe manufacturers should be consulted to obtain specific recommendations and lining thicknesses based on expected service conditions. Linings and their applications include: A. Portland Cement Mortar with sealcoat: Used for freshwater and drinking water having maximum temperature of 150 F. B. Portland Cement Mortar without sealcoat: Used for seawater, flowback and produced water, non-septic gravity sewer, sanitary force mains and reclaimed waters, having maximum temperatures of 212 F. C. Fusion bonded Epoxy: Used on fittings only and for use in freshwater and drinking water, non-septic gravity sewer, sanitary force mains and reclaimed waters, having maximum temperatures of 120 to 150 F.

2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 24

11.3

Gasket Materials

D. Ceramic quartz filled Amine Cured Novalac Epoxy: Used for septic sewers, acids, alkali waste, pickling brine, flowback and produced water, and reclaimed water having maximum temperatures of 120 to 150 F.

Pipe joint gaskets are available in several materials to provide sealing when in contact with various fluids and temperature ranges. The gasket materials are based on the expected contents and temperature of the pipeline, and should be specified during the design phase of the work. Pipe manufacturers should be consulted to obtain specific recommendations concerning materials based on expected service conditions.

Gasket Material SBR (Styrene Butadiene)

Max. Service Temperature (F) 150

EPDM (Ethylene Propylene Diene Monomer)

212

Nitrile (NBR)

150

Neoprene (CR) (Polychloroprene) Viton, Fluorel (FKM) (Fluorocarbon)

200

212

Pipeline Contents Sea water, flowback and produced water, drinking water, reclaimed water, storm water, raw water Sea water, flowback and produced water, drinking water, reclaimed water, storm water, raw water Chemicals, oils, refined petroleum, flowback and produced water, drinking water, reclaimed water, storm water, raw water Sea water, flowback and produced water, reclaimed water, storm water, raw water Many chemicals and solvents, chlorinated hydrocarbons, drinking water, reclaimed water, raw water, storm water

Source: Ductile Iron Pipe Research Association

Section 12 Pipe Joining


12.1 General Pipeline, fittings and valves can be joined by several methods, including push-on joints, mechanical joints, welded or fused joints, Victaulic-style grooved coupling and locking
2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 25

joints. Each joint type has a particular application and use. Designers should be familiar with the project needs and the capabilities of the selected joining systems. Additional information concerning joints, their uses and installation requirements can be obtained from various pipe manufacturers and the AWWA/ANSI Standard C-111. 1. Push-on Joints. The push-on joint is commonly used in pressurized water systems. Push-on pipe joints consist of bell, plain end and rubber gaskets. The bell is equipped with an internal groove in which the gasket is seated. The plain end is beveled and the joint is assembled by pushing the plain end into the bell. This compresses the gasket and provides a watertight seal. The joint is flexible and allows for deflection of the pipe so that the number of fittings required can be reduced. Push-on joints do not provide restraint unless additional clamp devices or restraining gaskets are installed. Push-on joints are typically used in below grade installations. 2. Mechanical Joints. The mechanical joint has four parts: flange cast with the bell; a rubber gasket that fits into the socket; a gland or follower ring; and tee head bolts and nuts for tightening the joint. Joint make-up is similar to that of the push-on joint with the exception of the bolted follower ring which compresses the gasket to provide a watertight seal. Mechanical joints do not provide joint restraint. Special restraining fittings can be utilized if joint restraint is required. Typically, fittings and valves are furnished and installed with mechanical joints. Pipe segments typically do not require the use of mechanical joints for installation. 3. Fused Joints. When HDPE or fusible PVC pipe is used, joints are typically made by fuse welding. This requires placing plain end pipe into heater plates, cleaning and preparing the ends and heating the element to high temperatures to melt the material. The two ends are then brought together and pressure applied. This method provides a leak-tight joint capable of withstanding pressures equal to that of the pipe material. If necessary, flanged and mechanical joint ends can also be fused onto plain-end HDPE or PVC pipe to allow for transition to other materials, or joining to appurtenances or pumps. Fused-joint welding should be performed by a certified fusion technician with certified equipment. 4. Grooved Couplings. Grooved Victaulic Style couplings joints are typically utilized on above-ground steel piping systems. Special coupling systems are also available for use on HDPE and PVC pipe products. The pipe is prepared with a grooved end and the coupling installed at the joint. The coupling consists of three components: the housing; gasket; and nuts and bolts. The coupling provides flexible, leak-free joints that allow for pipe movement and thermal expansion. 5. Locking Joints. Locking joints are provided by various PVC pipe manufacturers to allow for the installation of piping systems above or below grade. The joints
2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 26

consist of an O-ring gasket seal, locking spline, and joint coupling. The locking spline provides joint restraint for the piping system. Some manufacturer systems are designed for permanent installations while other systems allow fast disassembly when the piping is no longer required.

Section 13 Appurtenances
13.1 General Water pipelines require the installation of various appurtenances to facilitate construction, testing and maintenance. While each pipeline installation is different, the following is a brief description of pipeline appurtenances that may be utilized. 13.2 Valves 1. The three types of isolation valves used in water transmission and distribution pipelines are gate valves, butterfly valves and ball valves. A. Gate valves provide the ability to shut a line down for maintenance or testing. Gate valves should be used in full open or full closed position. Throttling of flow with gate valves is not recommended because the gate can creep over time and not maintain desired flows. Gate valves for water use typically are non-rising stem, resilient wedge type. The disc is encapsulated in a rubber-like compound, which provides a tight seal and a smooth interior to improve hydraulic flow. Buried valves are furnished with two-inch operating nuts and installed with valve boxes to allow for opening and closing. Above-grade installations are furnished with hand wheel operators. B. Butterfly valves also provide the ability to shut down a pipeline for maintenance or testing. The butterfly valve has a full diameter disc which rotates up to 90 degrees. Unlike the gate valve, the butterfly valve can be used to throttle flows if required. Buried valves are furnished with two-inch operating nuts and installed with valve boxes to allow for opening and closing. Above-grade installations are furnished with hand wheel operators. C. Ball valves are available with diameter sizes ranging from one-fourth inch to 48 inches, and are available in many materials such as carbon steel, stainless steel, brass, CPVC, PVC, and cast iron. Valves are also available in two-way or threeway configurations. Three-way configurations include side outlets to allow for diverting flow. Ball valve end connections include threaded, socket weld, butt weld and flanged. Ball valves are operated with 90-degree turn handles. The ball provides a full-port opening to minimize hydraulic losses.

2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 27

D. Valved tees at low points should be installed to allow the pipeline to drain. To prevent possible environmental releases, drains should not be located in or near waterway crossings and roadways. 2. Air release, vacuum relief and combination valves: Trapped air resulting from initial pipeline filling and normal operations needs to be removed from the pipe to maintain flow capacity. Accumulated air can pose flow restrictions and possibly cause surges. Also, trapped air pockets will result in false test readings during pipeline pressure testing. Vacuums created during draining or sudden breaks can be prevented by use of a vacuum relief valve. Valves should comply with AWWA/ANSI C512 standards. If clogging or corrosion may be a problem, wastewater versions of the following valves are available. A. Air release, vacuum relief and combination valves are tapped into the top of the pipe and located along high points of the piping route. Valves are typically installed with a tapping saddle or by flanged connection to maintain pipe integrity. Valves should be equipped with isolation ball valves to allow removal if necessary. B. Air release valves vent small quantities of air from a pipe during normal operations. Due to orifice sizes, the typical air release valve cannot handle the venting of large quantities of air during start up or initial filling. Air release valves are available in half-inch to six-inch dimensions. C. Air and vacuum relief valves vent large quantities of air from the pipe during initial filling. The valves will also allow air to enter the pipe during draining operations. An air release valve will not vent small pockets of air which accumulate over time in a pressurized pipe. Air and vacuum valves are available in half-inch to 20-inch dimensions. D. Combination valves provide the ability to vent large quantities of air during filling operations and admit air during draining. This type of valve will also vent small quantities of air collected during normal operations. Combination valves are available in one-inch to eight-inch dimensions. E. A vacuum valve is designed to open so as to allow air to enter the pipe during draining. This prevents the collapse of the pipeline and also allows for faster draining to take place when the lines are decommissioned. Vacuum valves do not vent air from the pipeline. F. Additional information on air/vacuum/combination valves can be obtained from manufacturers catalogues.

2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 28

13.3

Fittings Pipeline routings typically require installation of fittings or bends to allow for changes in direction and/or elevations of the pipe. Bends are available in standard offsets of 90 degrees (1/4 bend), 45 degrees (1/8 bend) 22.5 degrees (1/16 bend) and 11.25 degree s (1/32 bend). Bends are furnished with flanged or mechanical joint ends to allow for connecting to the pipeline. Pipe offsets can also be achieved by deflecting the pipe at the joints. The radius of curvature which can be obtained by deflection varies with pipe diameter. Ductile iron pipe 12 inches in diameter or less, and having lengths of 20 feet, can be deflected to achieve a radius of approximately 230 feet. PVC pipe 12--inches in diameter or less, and having lengths of 20 feet, can be deflected to achieve a radius of approximately 380 to 460 feet. For design purposes, a maximum of 75 percent of the available deflection should be used. Each pipe material and joint type will have its own deflection capabilities. Pipe manufacturers data sheets should be referenced when deflection is planned.

Section 14 Thrust Restraints


14.1 General Pressurized piping systems require the design of restraint systems in order to prevent pipe movement at joints and adjacent pipe lengths. Restraint for belowground piping can be provided by either thrust blocks or mechanical systems installed on the pipe joints. Above-grade installations can be restrained by use of fused joints, grooved couplings, and/or restrained mechanical systems. Above-grade piping to be installed on hills, ravines or embankments should also be designed to resist slipping due to elevation changes. This can be accomplished by means of securing the pipe with pipe blocks, anchors and/or sand bags. Pipeline designers should design the restraint system based on the expected maximum pressure of the pipeline plus a factor of safety. Typically for pressurized water systems, the thrust restraints are designed for 1.5 times the maximum working pressure or 150 psi, or whichever is greater. 14.2 Thrust Blocks Thrust blocks are used in buried piping systems and consist of a concrete block designed to transfer the thrust force into the adjoining soil. Thrust block design requires knowledge of the soil bearing capacity and the thrust forces.

2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 29

When the resultant thrust force is determined, the bearing area of the thrust block, in square feet, is calculated by dividing the force (lbs) by the bearing capacity of the adjacent soil (lbs/ft). Thrust blocks require proper placement and sizing in order to be effective. Use of precast blocks is not recommended. When piping requires vertical bends, the fitting on the upper portion of the pipeline must be restrained by means of a gravity block. The block is designed to offset the upward acting (vertical) thrust force component with the weight of the block. The upward acting thrust force is calculated with the formula T=PA (SIN ) where: T = Thrust force component (y-axis) (lbs) P = Maximum sustained pressure (test or surge pressure), (psi) A = Pipe cross-sectional area (in) = Bend deflection angle (degrees)

Thrust force is calculated with the formula T=PA (SIN /2) where: T = Resultant thrust force (lbs) P = Maximum sustained pressure (test or surge pressure), (psi) A = Pipe cross-sectional area (in) = Bend deflection angle (degrees)

The gravity block volume (Vg, ft3 ) is calculated by dividing T by the density of the block material (Wm, lbs/ft3). Vg = PA (SIN ) / Wm Additional information concerning thrust block design is provided in various pipe design manuals and manufacturers literature. Slippage When above-grade piping is installed along hills, ravines or embankments, movement such as slippage can occur due to the weight of the pipe and its contents. This can be alleviated by installing concrete blocks and/or sand bags at the low point of the pipeline. The blocks or sand bags should be sized sufficiently to offset the weight of the pipeline and its contents. Anchor blocks can also be used. They should be sufficiently attached to the pipe to secure it from slipping. The blocks should be set into the ground so that the load is transferred into the soil. Tie down straps should be of a design to eliminate point loads on the pipe in order to prevent damage to the pipe.

14.3

14.4

Mechanical Restraints It may be appropriate to use mechanical restraint systems in situations where there are difficulties in installing properly sized thrust blocks. An example is a situation where there is insufficient room for the thrust block due to proximity to nearby utility lines. Mechanical restraint systems consist of restraining devices that are placed on each fitting and valve. These systems provide full thrust restraint, provided they are properly

2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 30

designed and installed. Because mechanical systems provide their restraint capability by utilizing friction between the soil-pipe interfaces, the joints of adjacent pipe lengths must also be restrained. Because of the soil-pipe interface, each pipe material will have different required restrained length. Other factors impacting the design of mechanical restraint systems are type of pipe material, depth of bury, test pressure, diameter, trench type, soil classification, and selected factor of safety. Mechanical restraint manufacturers can provide detailed information on the use of their systems. Some manufacturers have online computer programs that can provide restraintlength data based on the above criteria.

Section 15 Testing
15.1 General After a pipeline is installed and the thrust restraint system is in place, hydrostatic pressure testing should be conducted to verify the pipe can maintain leak-free operation and that the thrust restraint system is adequate. Pressure testing should be performed between blind flanges installed for testing purposes, as testing between two closed valves can provide false leakage results. Buried pipe should be backfilled prior to testing. Air testing of PVC pipelines or other pipelines with manufacturer warnings against air testing should not be utilized due to the potential for catastrophic failure of the pipe. 15.2 Procedures The following procedures are applicable to all pipelines regardless of materials: A. Verify that all thrust restraints are in place. B. Slowly fill the line with water and vent all air from high points. Air pockets will give false leakage readings to the test results. Air pockets can be vented through air release valves or through corporation stops installed on the top of the pipe. After the air has been vented, close the corporation stops. The stops can be removed upon completion of the test or left in place. C. Pressure should be brought up slowly in the segment being tested. Typical test pressures should not be less than 1.25 times the working pressure at the highest elevation along the test segment and 1.5 times the working pressure at the lowest elevation along the test segment. The test pressure should not exceed the thrust restraint design pressure or be greater than 1.5 times the pipes pressure rating. D. A calibrated barrel filled with water should be used to provide the supply to the pipeline during the hydrostatic test. Test pressure shall be applied using a suitably
2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 31

sized metering pump connected to the barrel and the pipeline. Allow the pipeline to stabilize at the test pressure before conducting the test. E. Tests should be performed for a minimum of four hours. During this period, the test pressure should not vary by more than +/- five psi. Test pressure shall be maintained by adding makeup water from the barrel to the pipeline. F. The amount of makeup water added to maintain the test pressure should be accurately measured in gallons per hour and should not exceed the calculated allowable testing allowance. G. Exposed pipe joints, valves and fittings should be examined for leakage. H. If excessive leakage is noted, the pressure should be relieved and the pipe should be repaired or replaced. The hydrostatic test should be repeated until satisfactory results are obtained. I. Upon completion of the hydrostatic test, the pipeline can be placed directly into service. Draining of the pipeline is not required. J. Allowable leakage for freshwater pipelines is determined by the following formula: Q = (L D P)/148,000, where Q = Quantity of makeup water, (gallons per hour) L = length of pipe tested, (feet) D = nominal diameter of the pipe, (inches) P = average test pressure during the hydrostatic test, (pounds per square inch, gauge) K. In order to minimize potential environmental releases, pipelines carrying flowback or produced water, or any water that is not fresh water, should have zero leakage. In order to insure against leakage, these pipes should be constructed using fuse-welded joints.

Section 16 Operations and Maintenance


16.1 General Properly installed pipe should be relatively maintenance free. However, breaks in the pipeline can result in the loss of water and washout of the area around the pipeline failure. In order to minimize the volume of water released due to breaks, isolation valves

2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 32

should be installed during the construction and regularly operated to ensure they close properly. As-built drawings of buried pipelines, showing the pipeline location, and valve and fitting locations with ties to permanent structures should be prepared during construction and maintained. These should also provide details on pipe materials, diameter, depth of bury, detailed joint/coupling information with fusion information, if applicable, and other useful information to be used in case of a break or to facilitate maintenance. Repair materials should be readily available and should include repair clamps, sections of pipe of various diameters and materials installed. A list of approved local utility contractors should be maintained in order to facilitate a quick response in the event of breaks or other emergencies. Also, a contact list of local regulatory agencies and permit officials should be maintained. Most jurisdictions will allow for emergency excavation to allow for repairs to broken pipelines. However, certain pre-approved permit conditions may apply. If above ground pipelines are to be inactive for a prolonged period of time, they should be drained or pigged to prevent freezing. 16.2 Monitoring of Pipeline Temporary lines carrying non-fresh water should be continually monitored during operation. Pipeline should be inspected at intervals decided by the operators based on their riskmanagement strategies. Valves, air releases and joints should be thoroughly inspected for leaks or signs of failure. Pipeline condition should be continually recorded to document inspection. o Pressure should be recorded to ensure that pipeline is running to engineered specifications o Time of inspection should be recorded for individual accountability, as well as documentation in the event of a failure. o Condition of drain valves, fittings and air releases should be noted. o Where necessary, torque specifications should be recorded for any bolted connections. o Documentation should be signed by inspector and inspectors supervisor.

Temporary lines carrying fresh water should be continually monitored during operation. Pipelines should be inspected at intervals decided by the operators based on their riskmanagement strategies. Valves, air releases and joints should be inspected for leaks or signs of failure. Signs of failure should be conveyed to supervisors as soon as they are noticed.

2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 33

Section 17 Deactivation of Pipeline


17.1 Deactivation When it is determined that the pipeline is no longer needed for current or potential future uses, it should be deactivated and, if possible, removed in its entirety. In order to ensure that proper procedures are incorporated, meetings with relevant federal, state and local officials should be held to discuss the deactivation program, and to gain insight into any special procedures that these agencies may require. Permits issued for the original installation should be reviewed to ensure compliance with any special requirements. Many permits require a close-out submittal be prepared and forwarded to the appropriate agency. Prior to deactivating a pipeline, all water remaining in the pipeline should be removed. The two most common methods for removing water from the pipeline are described below: A. Draining Prior to draining, samples of the water should be taken and analyzed to determine water quality. If the water does not meet regulatory parameters for "fresh," the water should be either drained to a lined impoundment or tank for further treatment, or pumped to a truck for transport and treatment or disposal. Water that meets regulatory requirements for fresh water can be slowly discharged to areas where it can percolate into the ground. If drainage catchbasins or sanitary sewers are located in the area, they can also be utilized for draining water. Prior to utilizing basins or sewers, discussions with local authorities should be held to verify that they will allow use of the drains or sewers for release of water from the pipeline. If pipelines are to be discharged to the soils, sedimentation barriers consisting of stone rip-rap, other energy dissipaters, or other agency permitted measures should be installed to minimize possible erosion due to high flows. Flows should be regulated by throttling a valve. B. Pig Launching or "Pigging" Pigging involves inserting a device called a pig into a pipeline to push the water in the pipeline to an impoundment or storage tank. When pigging a pipeline, an adequately-sized air compressor capable of supplying the necessary flow rate should be used. The operating pressure cannot exceed the manufactures pressure rating of the pipe. The pig should be adequately sized for the inside diameter of the pipe. The proper launcher and receiver devices need to be installed prior to pigging.
2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.

Page 34

All drains and vents should be closed prior to pigging. Proper safety precautions should be followed when operating a pressurized pipe. The operator should adequately secure the end of the pipe, typically at an impoundment or tank that is receiving the pig.

During deactivation of above-ground HDPE pipeline, precautions should include placing plastic underneath the pipeline during the cutting of the joints to avoid shavings being left on the ground. Materials should be transported to a safe location for possible reuse in future projects. All disturbed areas from pipeline deactivation should be restored to pre-construction conditions. If pipelines were buried under roads, shoulders or streams, removal may require excavation and restoration of surface areas. If possible, the pipelines should be drained at low points and abandoned in place. Abandoned pipelines should be capped and plugged to prevent migration of surrounding soils into the pipeline. Depending upon the local regulations, abandoned pipelines may need to be filled with flowable fill material. Filling the pipelines prevents the possible collapse of the abandoned pipe and also eliminates future reuse of the piping system. Records of the pipeline deactivation should be maintained. The records should include information about the location of removed pipe, removal methodology, water quality data, and pre- and post- site photographs.

2012 The Marcellus Shale Coalition. Unauthorized reproduction prohibited.