Vous êtes sur la page 1sur 8

Energy Efficiency and Potential Savings in Chinese Hospitals

KFW-Working Group Energy Efficiency in the Health Sector 8 November 2013

Energy Efficiency in Public Buildings (Schools and Hospitals) Shecan Zhang

Project Struktur

MOFCOM
Steering Committee MoHURD (Chair) MoE (member) MoH (member) GIZ (member)

BMZ

GIZ China
Joint Project Office (GIZ and Partners)

Chin. Experts
& Consulting

Local Authorities

Pilot Hospitals

PilotSchools

Intern. experts & Consulting

Energy Benchmarking in 100 Chinese Hospitals


City Ningbo Qingdao
Hospitals
Grade 3 Grade 2 General hospitals Special hospitals Privat Public

26 27

14 8

12 19

23 23

3 4

7 -

19 27

Tianjin
Urumqi Summe

22
25 100

6
14 42 Ningbo mild 2 6 9 6 3 26

16
11 58 Qingdao cold 2 11 9 2 3 27

17
18 81 Tianjin cold 3 9 8 1 1 22

5
7 19

1
1 9 Urumqi very cold 1 15 1 4 1 3 25

21
24 91

Category Climate Zone I100 - 199 beds II200 - 499 beds III500 - 799 beds IV800 -1199 beds V1200-1999 beds VI> 2000 beds <100 beds Insgesamt

Total 8 41 27 12 8 3 1 100

Energy Cost Shares of Total Costs (incl. Water) in 100 Chinese Hospitals (2011)

Energy Costs (incl. Water) of Total Costs - max. value + mid. value - min. value

All together

Energy Consumption per Bed/p.a. in 100 Chinese Hospitals (2011)

Energy consumption per bed/p.a.


Kgec/bed/a

- max. value + mid. value - min. value

All together

Main Challenges in Chinese Hospitals

User behaviour (patients and staff)


Poor qualification of the technical staff Overdesigned facilities bad maintenance high running costs

More than 54 % hospital buildings were built before 2005 no external wall insulation High energy loss in the steam supply system (20-30%) Old water pipe system Problem with hydraulic balance in the heating and cooling system (controls and regulations) Capacity shortage of hospitals Project financing
5

Approaches and Technical Options for Energy Efficiency Measures

Approaches Awareness raising through energy benchmarking Energy analysis to uncover main problems Prioritize the energy efficiency measures using a catalog Start with simple measures with short pay-pack periods Set up pilot project for demonstration Technical Options Quick steam generators Cogeneration/Trigeneration (KWK/K) Heat/Chill recovery technology External wall isolation Modernization of the heat/cooling system Set up effective energy consumption controlling system
100% Consumption In % (installed Capacity 750kW) 90% 80% 70% 60% 50% 40% 30%

Steam consumption in a German hospital Steam sterilization Steam kitchen Loss stand by

20%
10% 0% 1 2 3 4 5 6 7 8 9 101112131415161718192021222324 Source: Wolfgang Mller

Thank You!
Shecan Zhang

Project Director Energy Efficiency in Public Buildings (Schools and Hospitals)