Vous êtes sur la page 1sur 5

Client

THYNA PETROLEUM SERVICES


7 Avenue Abdelrahmen El Ghafiki BP 069 / 3069 Sfax-Hached Sfax (Tunisia) Phone: 216 74 229 999 - Fax: 216 74 299 916

TENDER REFERENCE PUR/TEN/02/2013

Constructor

HALWANI COMPANY Ltd INDUSTRIAL AND METAL CONSTRUCTION


Zone Industrielle Madagascar Prs Somatra CP 3000 Sfax (Tunisia) Phone: 216 74 497 166/010 - Fax: 216 74 497 795

DOCUMENT No. PDOC-53/2013-FI-06

Project Title:

LOADING / OFFLOADING STATIONS AND METERING SKIDS INSTALLATION AT TANK BATTERY / GUEBIBA BASE & TRAPSA

FIELD INSTALLATION Rev. 00


REVISION RECORD
Rev. No.
00

Submission Date
Oct 29 2013

Revision Details
Submitted for approval

Prepared By Checked By
A.FERCHICHI A.FERCHICHI

Approved by
I.GARGOURI

This document has been prepared for the titled project or named part thereof and should not be relied upon or used for any other project without an independent check being carried out as to its suitability and prior written authority of Halwani Company being obtained. Halwani Company accepts no responsibility or liability for the consequences of this document being used for a purpose other than the purposes for which it was commissioned. Any person using or relying on the document for such other purpose agrees, and will by such use or reliance be taken to confirm his agreement to indemnify Mott MacDonald for all loss or damage resulting therefrom. Halwani Company accepts no responsibility or liability for this document to any party other than the person by whom it was commissioned.

HALWANI COMPANY Ltd AUTHOR: AKRAM FERCHICHI DOC.: FIELD INSTALLATION PROJECT: LOADING / OFFLOADING STATIONS

Job No : 53-2013 PDOC-53/2013-MS-06 Rev. : 00 Sheet : 2 of 5

1. PURPOSE
The purpose of this document is to provide all necessary Equipment needs to maintain the best progress of work on site(s) including the work procedures for the erecting of steel structure as well as Civil Works.

2. SCOPE
The scope of this document will all necessary equipment descripted as follow: 1) Filed Cabin 2) Storage area(s) 3) Signalization & Markings

3. FIELD CABIN
The field Cabin is determined by the number of workers at site. The Maximum number of workers for this project is estimated at 34 persons. For choosing the dimension and the quantities of field Cabinet, HALWANI COMPANY will consider a population of 20 because 34 will be rarely reached. The field Cabins per Site will enclose: Bureau/Meeting/ Refectory Cabin WC/showers Cabin Equipment Storage Cabin

Rev. : 00

Sheet : 2 of 5

HALWANI COMPANY Ltd AUTHOR: AKRAM FERCHICHI DOC.: FIELD INSTALLATION PROJECT: LOADING / OFFLOADING STATIONS

Job No : 53-2013 PDOC-53/2013-MS-06 Rev. : 00 Sheet : 3 of 5

Rev. : 00

Sheet : 3 of 5

HALWANI COMPANY Ltd AUTHOR: AKRAM FERCHICHI DOC.: FIELD INSTALLATION PROJECT: LOADING / OFFLOADING STATIONS

Job No : 53-2013 PDOC-53/2013-MS-06 Rev. : 00 Sheet : 4 of 5

4. STORAGE AREA
4.1 precast steel structure arrangement
To avoid precast steel structure being moved so much on jobsite that might cause unexpected damages of paint, shapes, when material delved to job site, they must be unloaded and arranged closed to the erection point. Up to The materials shall be stacked in locations according to the building/areas, Should be near to the lifting position adjacent to the area to be erected. This is to facilitate the sorting and delivery during the erection. The conditions of each job site, the material arrangement plan may different but in generally, materials will be arranges as following principle to ease moving, combination and erection after later:

Members should be checked park mark as packing list enclosed before unloading for best unloaded positions. Columns should be arranged closed to their anchor bolt position. Rafter members should be arranged to ensure easy assembly, movement. Girts, purlins, eave struts and bracing are divided according to the requirements of each bay. Nested parts (purlins, girts etc.) should be separated and blocked to allow drainage of collected moisture to prevent rusting, prior to erection. End wall material is laid out for each end. Small components (nuts, bolts, clips, fasteners etc.) are stored in a given area convenient to all parts of the building. Wall, roof paneling and other components which will not be used in the initial stage of erecting the steel, are placed to the outside of the work area and properly stored and protected from the weather. Insulation should not be stored on the edge of the roll as this will damage the edges

4.2 Protection precast steel structure


With purpose of preventing and protecting material damages during storage out of environment factors such as storm water, etc. which cause rusty, stain, etc. Including below tasks: Choose firmed and dry area for storage. The material shall be stored above ground level with timber packing. The materials or component or member shall be stored separately, above ground on timber dun age. They shall not be stacked directly on top of each other but must be separated by 50mm thick timber, and shall not stack in contact with other steel member but must be separated by a minimum 250mm gap.

Rev. : 00

Sheet : 4 of 5

HALWANI COMPANY Ltd AUTHOR: AKRAM FERCHICHI DOC.: FIELD INSTALLATION PROJECT: LOADING / OFFLOADING STATIONS

Job No : 53-2013 PDOC-53/2013-MS-06 Rev. : 00 Sheet : 5 of 5

Particular care shall be taken to stiffen free ends at 200mm distance from ends, prevent permanent distortion. The materials should be placed in minimum 5% slope to avoid water pond. The materials shall be kept free from dirt, grease, and other foreign materials and shall be protected from road splash. Never step on the materials. All bolts, nuts, washers, screws, small plates and articles generally shall be suitably packed and identified.

5. SIGNALISATIONS & MARKINGS


It defines the intervention area of agents and provides a physical barrier for workers. It is marked by a longitudinal frontlet markup (cones, poles, dam, and tape). These materials must have characteristics of fluorescence and retro reflection at least class 1.

Rev. : 00

Sheet : 5 of 5