2 Install guide rail at construction joint Pour concrete and put re-bar to
fix the guide rail in pitch @900 on
the vinyl sheet.
Install guide rail ( 40x40 square
pipe ) after checking the location
and level. After that fix by
welding.
1/9
CANON VIETNAM 06A TIEN SON FACTORY PROJECT 16,October, 2006
1 Inspection of concrete
1 st day
Slump tolerance:9±2cm
If slump is out of tolerance, the
concrete shall not be
used.(Check all trucks)
Check there is no wooden and
clay pieces.
2/9
CANON VIETNAM 06A TIEN SON FACTORY PROJECT 16,October, 2006
8 Rubbing hardener
1 st day
10
1 st day
5/9
CANON VIETNAM 06A TIEN SON FACTORY PROJECT 16,October, 2006
According to requirement,
arrange watchman and install
equipment to keep off anyone.
6/9
CANON VIETNAM 06A TIEN SON FACTORY PROJECT 16,October, 2006
7/9
CANON VIETNAM 06A TIEN SON FACTORY PROJECT 16,October, 2006
1 Cutter joint
8 th day
Turn up the vinyl sheet, then
spray water to keep wet condition
during working.
8/9
CANON VIETNAM 06A TIEN SON FACTORY PROJECT 16,October, 2006
1 Natural drying
2 weeks later or more
■ Attention
1. Protect column and wall. Mark the level on the column and wall.
2. Slump is very low. But don’t add water into concrete. OC staff should check the workers
not to add water.
3. Clean up around the working area frequently not to be dirty by sand, paper bag, vinyl,
insects, and waste concrete.
4. Need to consider how to remove bleeding water from next area. (Also consider about
water of curing from next area)
5. Waiting time between processes is depending on the conditions of the concrete and
weather. So we need to check the conditions and decide the starting time of the next
process every time.